CN111663457A - Assembled module, modular construction platform and method, bridge pier construction method - Google Patents
Assembled module, modular construction platform and method, bridge pier construction method Download PDFInfo
- Publication number
- CN111663457A CN111663457A CN202010662928.1A CN202010662928A CN111663457A CN 111663457 A CN111663457 A CN 111663457A CN 202010662928 A CN202010662928 A CN 202010662928A CN 111663457 A CN111663457 A CN 111663457A
- Authority
- CN
- China
- Prior art keywords
- construction
- module
- abutment
- modules
- construction platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/20—Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
- E04G11/28—Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/002—Workplatforms, railings; Arrangements for pouring concrete, attached to the form
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明属于土木工程技术领域,具体涉及一种拼装模块、模块化施工平台及方法、桥梁墩台施工方法。The invention belongs to the technical field of civil engineering, and particularly relates to an assembled module, a modular construction platform and method, and a bridge abutment construction method.
背景技术Background technique
目前公路、铁路、建筑等诸多领域在进行混凝土浇筑爬模施工时,各种施工平台普遍采用。随着桥梁墩台等建筑高度的不断增加,施工平台应具备的轻便稳定、安全实用、安拆方便、组合灵活等性质尤为重要。At present, various construction platforms are widely used in the construction of concrete pouring and climbing formwork in many fields such as highways, railways, and buildings. With the continuous increase in the height of buildings such as bridge piers and abutments, it is particularly important that the construction platform should have the characteristics of lightness and stability, safety and practicality, convenient installation and disassembly, and flexible combination.
纵观常见的桥梁墩台施工平台,种类繁多,但均存在一些不足之处。如结构单薄、过于笨重、安拆不便、通用性差等。Throughout the common bridge pier and abutment construction platform, there are many kinds, but there are some shortcomings. Such as thin structure, too bulky, inconvenient installation and disassembly, poor versatility and so on.
发明内容SUMMARY OF THE INVENTION
本发明目的是针对上述存在的问题和不足,提供一种拼装模块、模块化施工平台及方法、桥梁墩台施工方法,其结构设计合理,稳定性好,能够大大提高产品的使用性,施工方便且效率高,可广泛用于公路、铁路、建筑、电力等行业,可以重复利用,便于定型和批量生产,具有较好的效益。The purpose of the present invention is to address the above-mentioned existing problems and deficiencies, and provide an assembled module, a modular construction platform and method, and a bridge abutment construction method, which have reasonable structural design, good stability, can greatly improve the usability of the product, and are convenient for construction. And high efficiency, can be widely used in highway, railway, construction, electric power and other industries, can be reused, easy to shape and mass production, and has good benefits.
为实现上述目的,所采取的技术方案是:In order to achieve the above purpose, the technical solutions adopted are:
一种拼装模块,包括:An assembled module, comprising:
模块框架;module framework;
连接部,所述连接部用于与相邻的结构件连接装配,在所述模块框架的至少一侧设置有连接部;以及a connecting part, the connecting part is used for connecting and assembling with an adjacent structural member, and a connecting part is provided on at least one side of the module frame; and
围挡,其设置在所述模块框架的顶部外侧。The enclosure is arranged on the outside of the top of the module frame.
根据本发明拼装模块,优选地,所述模块框架包括:According to the present invention to assemble a module, preferably, the module frame includes:
上支撑架;upper support frame;
下支撑架;以及the lower support frame; and
连接杆,其布设在所述上支撑架和所述下支撑架之间,在所述上支撑架上铺设有踏板。A connecting rod is arranged between the upper support frame and the lower support frame, and pedals are laid on the upper support frame.
根据本发明拼装模块,优选地,所述下支撑架呈倾斜设置,所述上支撑架呈水平布置;或所述下支撑架与所述上支撑架平行设置;According to the assembling module of the present invention, preferably, the lower support frame is arranged obliquely, and the upper support frame is arranged horizontally; or the lower support frame and the upper support frame are arranged in parallel;
所述下支撑架与所述上支撑架的各侧边竖向对齐布置;或所述下支撑架与所述上支撑架之间的至少一侧面为倾斜的斜面。Each side edge of the lower support frame and the upper support frame is vertically aligned; or at least one side surface between the lower support frame and the upper support frame is an inclined slope.
根据本发明拼装模块,优选地,所述模块框架的横截面呈扇形、矩形或L型结构。According to the assembling module of the present invention, preferably, the cross section of the module frame is a fan-shaped, rectangular or L-shaped structure.
根据本发明拼装模块,优选地,所述连接部为连接螺杆或连接销;或所述连接部包括连接块,所述连接块设置在所述模块框架的侧部,所述模块框架上的连接块与对应的结构件上的连接块通过连接件连接;According to the assembling module of the present invention, preferably, the connecting part is a connecting screw or a connecting pin; or the connecting part includes a connecting block, and the connecting block is arranged on the side of the module frame, and the connection on the module frame The block is connected with the connecting block on the corresponding structural member through the connecting member;
所述模块框架与所述围挡通过螺栓连接固定;或所述模块框架上设置有承口,所述围挡下部设置有与所述承口对应的插头,所述插头与所述承口之间设置有连接螺栓。The module frame and the enclosure are connected and fixed by bolts; or the module frame is provided with a socket, the lower part of the enclosure is provided with a plug corresponding to the socket, and the plug is connected to the socket. There are connecting bolts between them.
一种模块化施工平台,布设在墩台模板外侧,包括如上所述的拼装模块,多个所述拼装模块呈环状贴合布设所述墩台模板外侧;相邻两拼装模块之间、拼装模块与墩台模板之间通过连接部连接固定,在多个所述拼装模块形成的施工平台周向布设有围挡。A modular construction platform is arranged on the outside of a pier formwork, and includes the assembled modules as described above, a plurality of the assembled modules are arranged in a ring shape and arranged on the outside of the abutment formwork; The modules and the abutment formwork are connected and fixed by connecting parts, and a surrounding block is arranged on the circumference of the construction platform formed by the plurality of assembled modules.
根据本发明模块化施工平台,优选地,所述施工平台呈圆环形或矩形环;在相邻两桥梁墩台之间设置有连接通道,所述连接通道包括多个拼装模块,且所述连接通道的拼装模块与桥梁墩台上施工平台的拼装模块为一体拼装连接,所述连接通道的两侧均设置有围挡。According to the modular construction platform of the present invention, preferably, the construction platform is in the shape of a circular ring or a rectangular ring; a connection channel is provided between two adjacent bridge abutments, the connection channel includes a plurality of assembled modules, and the The assembling module of the connecting channel is assembled and connected with the assembling module of the construction platform on the bridge abutment, and both sides of the connecting channel are provided with enclosures.
一种模块化施工平台施工方法,用于上述的模块化施工平台的施工,具体包括以下步骤:A construction method for a modular construction platform, which is used for the construction of the above-mentioned modular construction platform, specifically includes the following steps:
拼装墩台模板,并根据桥梁墩台的墩台模板的结构尺寸选择相应的拼装模块;Assemble the pier and abutment formwork, and select the corresponding assembling module according to the structural size of the pier and abutment formwork of the bridge pier;
对各个拼装模块进行拼装,并整体起吊,在墩台模板上布设加强肋,完成施工平台与墩台模板的固定;或先在墩台模板上布设加强肋,再依次起吊各拼装模块,将各拼装模块依次与对应的加强肋连接固定,同时对相邻的两拼装模块进行连接固定;Assemble each assembly module, lift it as a whole, and arrange reinforcing ribs on the pier formwork to complete the fixing of the construction platform and the pier formwork; The assembled modules are sequentially connected and fixed with the corresponding reinforcing ribs, and at the same time, the two adjacent assembled modules are connected and fixed;
在墩台模板的侧壁与拼装模块的底部之间布设斜顶撑;A sloping top brace is arranged between the side wall of the pier formwork and the bottom of the assembled module;
对拼装后的施工平台进行稳定性检测。Check the stability of the assembled construction platform.
根据本发明模块化施工平台施工方法,优选地,在施工平台拼装前,对拼装模块进行预拼装,并对拼装模块的稳定性进行检测;According to the construction method of the modular construction platform of the present invention, preferably, before the construction platform is assembled, the assembled modules are pre-assembled, and the stability of the assembled modules is detected;
当两桥梁墩台同步施工,并在两桥梁墩台之间布置有连接通道时,对所述连接通道的拼装模块拼装完成后,通过起吊设备整体吊装所述连接通道,并与墩台模板外侧的拼装模块进行整体连接,在所述连接通道的底部与墩台模板之间也设置有斜顶撑。When the piers and abutments of the two bridges are constructed synchronously, and a connecting channel is arranged between the piers and abutments of the two bridges, after the assembling modules of the connecting channel are assembled, the connecting channel is hoisted as a whole by the lifting equipment, and is connected with the outside of the pier template. The assembled modules are integrally connected, and a sloping top brace is also provided between the bottom of the connection channel and the abutment formwork.
一种桥梁墩台施工方法,具体包括以下步骤;A method for constructing a bridge pier and abutment, specifically comprising the following steps;
a、根据桥梁墩台结构,确定模板爬升高度,并确定模板的结构尺寸和拼装模块的结构尺寸;a. According to the bridge pier structure, determine the climbing height of the formwork, and determine the structural size of the formwork and the structural size of the assembled module;
b、进行第一区段的钢筋和墩台模板的安装,并通过如上述的模块化施工平台施工方法进行第一区段墩台模板顶部的施工平台的施工;b. Carry out the installation of the reinforcing bars and the pier formwork in the first section, and carry out the construction of the construction platform on the top of the pier formwork in the first section by the above-mentioned modular construction platform construction method;
c、进行第一区段的混凝土浇筑;c. Concrete pouring in the first section;
d、重复步骤b和c,完成第二区段的混凝土浇筑;d. Repeat steps b and c to complete the concrete pouring of the second section;
e、拆除第一区段的墩台模板和施工平台的拼装模块,进行第三区段的钢筋和墩台模板的安装,并通过如上述的模块化施工平台施工方法进行第三区段墩台模板顶部的施工平台的施工;e. Remove the pier formwork and the assembly module of the construction platform in the first section, install the steel bars and the pier formwork in the third section, and carry out the third section pier through the modular construction platform construction method as described above. Construction of the construction platform on top of the formwork;
f、进行第三区段的混凝土浇筑;f. Concrete pouring in the third section;
g、重复步骤e和f,直至完成整个桥梁墩台的施工;g. Repeat steps e and f until the construction of the entire bridge abutment is completed;
当需要进行系梁或盖梁施工时,在接近系梁或盖梁底部的调节区段,通过步骤b和c进行该调节区段的钢筋、墩台模板和施工平台的施工;当调节区段的混凝土强度满足施工要求后,拆除调节区段的施工平台和墩台模板,并在浇筑完成的桥梁墩台上安装支撑抱箍,通过步骤b和c进行系梁或盖梁的钢筋、墩台模板和施工平台的施工。When the tie beam or cover beam construction needs to be carried out, in the adjustment section close to the bottom of the tie beam or cover beam, the steel bars, pier formwork and construction platform of the adjustment section are constructed through steps b and c; After the concrete strength meets the construction requirements, remove the construction platform and pier formwork in the adjustment section, install the support hoop on the bridge pier after pouring, and perform steps b and c to tie the beams or cover the beams. Construction of formwork and construction platforms.
采用上述技术方案,所取得的有益效果是:By adopting the above technical scheme, the beneficial effects obtained are:
1、本发明设计合理、结构轻巧,拼接灵活,操作安全,适用公路、铁路、建筑、电力等行业,可以重复利用,产生较好的效益。1. The present invention has reasonable design, lightweight structure, flexible splicing, safe operation, and is suitable for industries such as highway, railway, construction, electric power, etc., and can be reused to generate better benefits.
2、本申请的所用的材料可以采用常见的定型材料,容易购得,且便于定型和批量生产,更便于整个施工工程的系统化、标准化作业,能够保障施工的效率和结构的稳定性。2. The materials used in this application can adopt common shaping materials, which are easy to purchase, and are convenient for shaping and mass production, which is more convenient for the systematic and standardized operation of the entire construction project, and can ensure the efficiency of construction and the stability of the structure.
3、本发明的施工平台和拼装模块,系根据常见的圆柱式墩台、方柱式、矩形薄壁墩台、圆端形薄壁墩台、系梁、墩台帽施工搭设平台的需求,将平台合理划分成段落即模块,分类制作、逐块安拆或分段组装、整体安拆,随模板一起向上爬升,与物料提升机配合作业,施工效率较高,更便于进行系统化作业。3. The construction platform and assembling module of the present invention are based on the requirements of common cylindrical piers, square column piers, rectangular thin-walled piers, round-end thin-walled piers, tie beams, and pier caps. The platform is reasonably divided into sections, that is, modules, which are classified and produced, assembled piece by piece or assembled in sections, assembled and disassembled as a whole, climbed up together with the formwork, and cooperated with the material hoist. The construction efficiency is high, and it is more convenient for systematic operation.
4、本申请中拼装模块的连接部,通过在贴近墩台的两根连接杆上、下端各焊接一对凹形连接块,在墩台模板适宜位置焊接纵向加强肋,肋上与模块对应位置设置凸形连接块,凸、凹形连接块位置对准后以销钉插入固定,方便快捷,且能够通过调整加强肋的位置和高度,控制装配间隙,更便于进行拼装模块的装配,通用性强。4. In the connection part of the assembled module in this application, a pair of concave connecting blocks are welded to the upper and lower ends of the two connecting rods close to the pier, and longitudinal reinforcing ribs are welded at the appropriate positions of the pier template, and the ribs correspond to the modules. Set the convex connection block, the position of the convex and concave connection blocks are aligned and fixed with pins, which is convenient and quick, and can control the assembly gap by adjusting the position and height of the reinforcing rib, which is more convenient for the assembly of the assembly module, and has strong versatility .
5、本申请可以进行同一墩台中的两根、三根墩柱同时施工时,既可分别搭设环形平台,分别施工,也可以通过搭设连接通道,形成整体平台,增加稳定性。5. When two or three piers in the same pier can be constructed at the same time in this application, annular platforms can be set up for separate construction, or a connecting channel can be set up to form an integral platform to increase stability.
6、本申请还可以进行侧面积较大的柱式墩台的系梁、盖梁、薄壁墩台身、墩台帽的施工,可通过原地进行拼接模块的拼装,整体安装,提高工效,降低施工的难度和风险。6. The application can also carry out the construction of the tie beam, cover beam, thin-walled pier body and pier cap of the column pier with a large side area, and the splicing module can be assembled on the spot, and the overall installation can improve the work efficiency. , reduce the difficulty and risk of construction.
7、本申请的墩台之间间隙较大时,为避免通道刚度不足而产生较大挠度,可在墩柱模板与通道底部适当位置对称加设斜顶撑,即可增加通道稳定性,也可避免为保持稳定加大模块断面而增加自重。7. When the gap between the piers and abutments of the present application is large, in order to avoid the large deflection caused by the insufficient stiffness of the channel, inclined top braces can be added symmetrically at the appropriate positions of the pier column formwork and the bottom of the channel, which can increase the stability of the channel and also improve the stability of the channel. It can avoid increasing the dead weight for maintaining stability and increasing the module section.
8、本申请的围挡与拼装模块的连接,通过围挡连接杆的下端外轮廓尺寸与拼装模块连接杆上端内轮廓尺寸相宜,设置成插口+承口模式,并在承口顶端向下一定深度部位焊接隔板,插口、承口适当位置钻取螺栓孔,围挡的连接杆下端插入模块连接杆上端后,用螺栓固定即可,简便牢固。8. The connection between the enclosure and the assembled module of the present application is set up in a socket + socket mode through the outer contour size of the lower end of the enclosure connecting rod and the inner contour size of the upper end of the connecting rod of the assembled module, and the top of the socket is fixed downward. Weld the partition at the depth, drill the bolt hole at the appropriate position of the socket and socket, insert the lower end of the connecting rod of the enclosure into the upper end of the connecting rod of the module, and fix it with bolts, which is simple and firm.
9、本申请还可以用于变截面墩台的施工,通过调整上支撑架和下支撑架内侧竖杆的坡度,在墩台模板上设置简易轨道,用于搭设浇筑坡面混凝土施工平台。9. The application can also be used for the construction of variable-section piers. By adjusting the slope of the vertical rods on the inner sides of the upper and lower support frames, a simple track is set on the pier formwork for setting up a concrete construction platform for pouring slope.
10、本申请还可用于搭设临时施工便桥,进行桥梁基础施工。10. The present application can also be used to set up temporary construction bridges and carry out bridge foundation construction.
11、本申请的施工平台能够根据墩台模板的形状进行结构设计,在拼装连接结构上保持多点拼装固定,从而分散受力点,避免墩台模板和各拼装模块局部受力过大,保障结构稳定性,从而提高整体结构的稳定性和安全性;在施工方法上,能够实现高效的施工,避免施工平台整体重量过大,降低施工风险,提高整体的稳定性和效率。11. The construction platform of the present application can be structurally designed according to the shape of the pier formwork, and maintain multi-point assembling and fixing on the assembling connection structure, so as to disperse the stress points, avoid the pier formwork and the local parts of the assembled modules being too large. Structural stability, thereby improving the stability and safety of the overall structure; in terms of construction methods, it can achieve efficient construction, avoid the overall weight of the construction platform being too large, reduce construction risks, and improve overall stability and efficiency.
附图说明Description of drawings
为了更清楚地说明本发明实施例的技术方案,下文中将对本发明实施例的附图进行简单介绍。其中,附图仅仅用于展示本发明的一些实施例,而非将本发明的全部实施例限制于此。In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the accompanying drawings of the embodiments of the present invention will be briefly introduced hereinafter. The accompanying drawings are only used to illustrate some embodiments of the present invention, but not to limit all the embodiments of the present invention thereto.
图1为根据本发明实施例的拼装模块的结构示意图之一。FIG. 1 is a schematic structural diagram of an assembled module according to an embodiment of the present invention.
图2为根据本发明实施例的拼装模块的结构示意图之二。FIG. 2 is a second schematic structural diagram of an assembled module according to an embodiment of the present invention.
图3为根据本发明实施例的拼装模块的结构示意图之三。FIG. 3 is a third schematic structural diagram of an assembled module according to an embodiment of the present invention.
图4为根据本发明实施例的拼装模块的结构示意图之四。FIG. 4 is a fourth schematic structural diagram of an assembled module according to an embodiment of the present invention.
图5为根据本发明实施例的拼装模块的结构示意图之五。FIG. 5 is a fifth schematic structural diagram of an assembled module according to an embodiment of the present invention.
图6为根据本发明实施例的模块框架、连接部和围挡的连接结构示意图。FIG. 6 is a schematic diagram of a connection structure of a module frame, a connection part and a enclosure according to an embodiment of the present invention.
图7为根据本发明实施例的模块化施工平台的结构示意图之一。FIG. 7 is one of the schematic structural diagrams of the modular construction platform according to the embodiment of the present invention.
图8为根据本发明实施例的模块化施工平台的结构示意图之二。FIG. 8 is a second schematic structural diagram of a modular construction platform according to an embodiment of the present invention.
图9为根据本发明实施例的模块化施工平台的结构示意图之三。FIG. 9 is a third schematic structural diagram of a modular construction platform according to an embodiment of the present invention.
图10为根据本发明实施例的模块化施工平台的结构示意图之四。FIG. 10 is a fourth schematic structural diagram of a modular construction platform according to an embodiment of the present invention.
图11为根据本发明实施例的桥梁墩台施工爬模的工艺步骤图。Fig. 11 is a process step diagram of a climbing form for the construction of a bridge abutment according to an embodiment of the present invention.
图中序号:Serial number in the picture:
100为拼装模块、110为上支撑架、111为踏板、120为下支撑架、130为连接杆、140为连接块、150为围挡、160为插头、170为承口、180为销钉、190为加强肋;100 is the assembly module, 110 is the upper support frame, 111 is the pedal, 120 is the lower support frame, 130 is the connecting rod, 140 is the connecting block, 150 is the enclosure, 160 is the plug, 170 is the socket, 180 is the pin, 190 for reinforcing ribs;
200为安全爬梯;200 is a safe ladder;
300为墩台模板、310为系梁或盖梁模板;300 is the pier formwork, 310 is the tie beam or cover beam formwork;
400为施工平台。400 is the construction platform.
具体实施方式Detailed ways
下文中将结合本发明具体实施例的附图,对本发明实施例的示例方案进行清楚、完整地描述。除非另作定义,本发明使用的技术术语或者科学术语应当为所属领域内具有一般技能的人士所理解的通常意义。Hereinafter, the exemplary solutions of the embodiments of the present invention will be clearly and completely described with reference to the accompanying drawings of the specific embodiments of the present invention. Unless otherwise defined, technical or scientific terms used in the present invention should have the ordinary meaning as understood by those of ordinary skill in the art.
应注意到,当一个元件与另一元件存在“连接”、“耦合”或者“相连”的表述时,可以意味着其直接连接、耦合或相连,但应当理解的是,二者之间可能存在中间元件;即涵盖了直接连接和间接连接的位置关系。It should be noted that when an element is expressed as "connected", "coupled" or "connected" to another element, it may mean that it is directly connected, coupled or connected, but it should be understood that there may be Intermediate elements; that is, the positional relationship covering both direct and indirect connections.
应当注意到,使用“一个”或者“一”等类似词语也不必然表示数量限制。“包括”或者“包含”等类似的词语意指出现该词前面的元件或物件涵盖出现在该词后面列举的元件或者物件及其等同,而不排除其他元件或者物件。It should be noted that the use of "a" or "an" and similar words also does not necessarily imply a limitation of quantity. "Comprising" or "comprising" and similar words mean that the elements or things appearing before the word encompass the elements or things recited after the word and their equivalents, but do not exclude other elements or things.
应注意到,“上”、“下”、“左”、“右”等指示方位或位置关系的术语,仅用于表示相对位置关系,其是为了便于描述本发明,而不是所指装置或元件必须具有特定的方位、以特定的方位构造和操作;当被描述对象的绝对位置改变后,则该相对位置关系也可能相应的改变。It should be noted that terms such as "upper", "lower", "left", and "right" indicating an orientation or positional relationship are only used to indicate a relative positional relationship, which is for the convenience of describing the present invention, rather than referring to a device or a device. Elements must have a specific orientation, be constructed and operated in a specific orientation; when the absolute position of the described object changes, the relative positional relationship may also change accordingly.
参见图1-图6,本申请公开了一种拼装模块,包括模块框架、连接部和围挡150,连接部用于与相邻的结构件连接装配,在模块框架的至少一侧设置有连接部;围挡设置在模块框架的顶部外侧。Referring to FIGS. 1-6 , the present application discloses an assembled module, including a module frame, a connecting part and a
进一步地,本实施例中的模块框架包括上支撑架110、下支撑架120和连接杆130,连接杆130布设在上支撑架和下支撑架之间,在上支撑架上铺设有踏板111,其踏板111为薄钢板支撑的防滑板,在防滑板和模块框架上设置有对应的螺孔,并通过螺栓连接固定。根据不同的墩台形状、应用位置的不同,拼装模块的形状有不同的结构。Further, the module frame in this embodiment includes an
本实施例中的下支撑架120可以呈倾斜设置,上支撑架110呈水平布置,此时,能够保障内侧连接杆长度较长,便于与墩台模板300有更大的接触面积,并且能够使得拼装模块自身的下支撑架形成斜支撑,保障结构的稳定性,避免上支撑架的外端负重过多时,导致连接部受力过大;在大部分情况下,可以将下支撑架与上支撑架平行设置,纵截面形成矩形箱体结构,如图1-5所示的拼装模块均采用了上、下支撑架平行的布置形式。In this embodiment, the
进一步地,本实施例中的下支撑架与上支撑架的各侧面竖向对齐布置,从而便于进行相邻的结构件的连接,如相邻两拼装模块的连接,或者拼装模块与墩台模板的连接;如图5所示,由于墩台可能为变径结构,即下端横截面较大,上端横截面逐渐减小,此时为了保障装配结构的稳定性,可以将下支撑架与上支撑架之间的至少一侧面为倾斜的斜面,此时方便进行固定,且便于受力稳定,该变截面的拼装模块用于变截面墩台身施工搭设的平台,内侧的连接杆倾斜设置,坡度与墩台模板相同,形成的施工平台可呈矩形或圆环形,在外侧设置围挡。Further, the lower support frame in this embodiment is vertically aligned with the sides of the upper support frame, so as to facilitate the connection of adjacent structural members, such as the connection of two adjacent assembled modules, or the assembled module and the abutment formwork. As shown in Figure 5, since the pier may be a variable-diameter structure, that is, the cross-section of the lower end is large, and the cross-section of the upper end is gradually reduced, in order to ensure the stability of the assembly structure, the lower support frame and the upper support At least one side between the frames is an inclined slope, which is convenient for fixing and stable under force. The variable-section assembly module is used for the platform for the construction of the variable-section pier body. The inner connecting rod is inclined and the slope is Similar to the pier formwork, the formed construction platform can be rectangular or circular, with enclosures on the outside.
如图1所示,模块框架的横截面呈扇形,即模块框架的内侧和外侧均为圆弧结构,模块框架的两侧呈锥台型;如图2、图3和图5所示,模块框架的横截面还可以设置成矩形结构,图3中还可以对模块框架的端角进行倒角处理,使得其装配过程中避免干涉,用在如图8所示的连接通道与施工平台的连接位置;如图4所示,模块框架的横截面为L型结构。上述结构根据应用位置的不同、墩台结构的不同,对模块框架的形状进行一定的改变。As shown in Figure 1, the cross section of the module frame is fan-shaped, that is, the inner and outer sides of the module frame are arc structures, and the two sides of the module frame are truncated cones; as shown in Figures 2, 3 and 5, the module The cross-section of the frame can also be set to a rectangular structure. In Figure 3, the end corners of the module frame can also be chamfered to avoid interference during the assembly process. It is used in the connection between the connection channel and the construction platform as shown in Figure 8. Position; as shown in Figure 4, the cross-section of the module frame is an L-shaped structure. The above structure changes the shape of the module frame to a certain extent according to different application positions and different pier structures.
本实施例中的连接部可以直接通过连接螺杆或连接销进行连接固定;为了便于调节,避免结构之间装配位置错位导致无法装配,还可以将连接部设置为多对连接块,连接块设置在模块框架的侧部,如连接杆的侧边上,模块框架上的连接块与对应的结构件上的连接块通过连接件连接。如图6所示,可以在墩台模板上设置凸连接块,在连接杆上设置凹连接块,凸凹连接块匹配对位后通过销轴连接;因为墩台模板上固定位置可能发生一定的变动,因此,凸连接块可以通过加强肋固定在墩台模板上,在确定固定位置后,将加强肋焊接在墩台模板上,然后在墩台模板上固定凸连接块。The connecting part in this embodiment can be directly connected and fixed by connecting screws or connecting pins; in order to facilitate the adjustment and avoid the dislocation of the assembly positions between the structures, which may lead to inability to assemble, the connecting parts can also be set as multiple pairs of connecting blocks, and the connecting blocks are set in On the side part of the module frame, such as the side edge of the connecting rod, the connecting block on the module frame is connected with the connecting block on the corresponding structural member through the connecting member. As shown in Figure 6, a convex connecting block can be set on the pier formwork, and a concave connecting block can be set on the connecting rod. After the convex and concave connecting blocks are matched and aligned, they are connected by pins; because the fixed position on the pier formwork may change to a certain extent Therefore, the convex connecting block can be fixed on the pier formwork through the reinforcing rib. After the fixing position is determined, the reinforcing rib is welded on the pier formwork, and then the convex connecting block is fixed on the pier formwork.
进一步地,本实施例中的模块框架与围挡通过螺栓连接固定;当考虑到围挡的受力支撑,为了保障结构的稳定性,本实施例中的模块框架上设置有承口,围挡下部设置有与承口对应的插头,插头与承口之间设置有连接螺栓,如图6所示。Further, the module frame and the enclosure in this embodiment are connected and fixed by bolts; when considering the force support of the enclosure, in order to ensure the stability of the structure, the module frame in this embodiment is provided with a socket, and the enclosure is The lower part is provided with a plug corresponding to the socket, and a connecting bolt is provided between the plug and the socket, as shown in FIG. 6 .
如图7-图10所示,本申请还公开了一种模块化施工平台,其布设在墩台模板外侧,包括上述的拼装模块,多个拼装模块呈环状贴合布设墩台模板外侧;相邻两拼装模块之间、拼装模块与墩台模板之间通过连接部连接固定,在多个拼装模块形成的施工平台周向布设有围挡。As shown in Fig. 7-Fig. 10, the present application also discloses a modular construction platform, which is arranged on the outside of the abutment formwork, including the above-mentioned assembled modules, and a plurality of assembled modules are arranged in a ring shape and are attached to the outside of the abutment formwork; Between two adjacent assembled modules, between the assembled modules and the pier formwork are connected and fixed by connecting parts, and enclosures are arranged circumferentially on the construction platform formed by the plurality of assembled modules.
本实施例中的施工平台可以呈圆环形;当在相邻两桥梁墩台之间设置连接通道时,连接通道可以在施工平台之间布置;具体地,连接通道包括多个拼装模块,且连接通道的拼装模块与桥梁墩台上施工平台的拼装模块为一体拼装连接,连接通道的两侧均设置有围挡,如图7和8所示,图8为图7的俯视结构视图;施工平台还可以为矩形环状,如图9和图10所示,图10为图9的俯视结构示意图。The construction platform in this embodiment can be in the shape of a circular ring; when a connecting channel is set between two adjacent bridge piers, the connecting channel can be arranged between the construction platforms; specifically, the connecting channel includes a plurality of assembled modules, and The assembly module of the connecting channel and the assembly module of the construction platform on the bridge pier are assembled and connected as a whole, and enclosures are provided on both sides of the connecting channel, as shown in Figures 7 and 8, and Figure 8 is the top view of Figure 7; construction; The platform may also be a rectangular ring, as shown in FIG. 9 and FIG. 10 , and FIG. 10 is a schematic top view of FIG. 9 .
本申请还公开了一种模块化施工平台施工方法,用于上述的模块化施工平台的施工,具体包括以下步骤:The present application also discloses a method for constructing a modular construction platform, which is used for the construction of the above-mentioned modular construction platform, and specifically includes the following steps:
拼装墩台模板,并根据桥梁墩台的墩台模板的结构尺寸选择相应的拼装模块;Assemble the pier and abutment formwork, and select the corresponding assembling module according to the structural size of the pier and abutment formwork of the bridge pier;
对各个拼装模块进行拼装,并整体起吊,在墩台模板上布设加强肋,完成施工平台与墩台模板的固定;或先在墩台模板上布设加强肋,再依次起吊各拼装模块,将各拼装模块依次与对应的加强肋连接固定,同时对相邻的两拼装模块进行连接固定;Assemble each assembly module, lift it as a whole, and arrange reinforcing ribs on the pier formwork to complete the fixing of the construction platform and the pier formwork; The assembled modules are sequentially connected and fixed with the corresponding reinforcing ribs, and at the same time, the two adjacent assembled modules are connected and fixed;
在墩台模板的侧壁与拼装模块的底部之间布设斜顶撑;A sloping top brace is arranged between the side wall of the pier formwork and the bottom of the assembled module;
对拼装后的施工平台进行稳定性检测。Check the stability of the assembled construction platform.
在施工平台拼装前,对拼装模块进行预拼装,并对拼装模块的稳定性进行检测;Before assembling the construction platform, pre-assemble the assembled modules, and test the stability of the assembled modules;
当两桥梁墩台同步施工,并在两桥梁墩台之间布置有连接通道时,对连接通道的拼装模块拼装完成后,通过起吊设备整体吊装连接通道,并与墩台模板外侧的拼装模块进行整体连接,在连接通道的底部与墩台模板之间也设置有斜顶撑。When the piers and abutments of the two bridges are constructed simultaneously and a connecting channel is arranged between the piers and abutments of the two bridges, after the assembly module of the connecting channel is assembled, the connecting channel is hoisted as a whole by the hoisting equipment, and the assembly module on the outside of the pier template is carried out. It is integrally connected, and there is also a sloping roof support between the bottom of the connecting channel and the pier formwork.
参见图11,本申请还公开了一种桥梁墩台施工方法,具体包括以下步骤;Referring to FIG. 11 , the present application also discloses a method for constructing a bridge pier and abutment, which specifically includes the following steps;
a、根据桥梁墩台结构,确定模板爬升高度,并确定模板的结构尺寸和拼装模块的结构尺寸;a. According to the bridge pier structure, determine the climbing height of the formwork, and determine the structural size of the formwork and the structural size of the assembled module;
b、进行第一区段的钢筋和墩台模板的安装,并通过如权利要求8或9的模块化施工平台施工方法进行第一区段墩台模板顶部的施工平台的施工;B, carry out the installation of the reinforcing bars and the pier formwork of the first section, and carry out the construction of the construction platform on the top of the pier formwork of the first section by the modular construction platform construction method as claimed in claim 8 or 9;
c、进行第一区段的混凝土浇筑;c. Concrete pouring in the first section;
d、重复步骤b和c,完成第二区段的混凝土浇筑;d. Repeat steps b and c to complete the concrete pouring of the second section;
e、拆除第一区段的墩台模板和施工平台的拼装模块,进行第三区段的钢筋和墩台模板的安装,并通过如权利要求8或9的模块化施工平台施工方法进行第三区段墩台模板顶部的施工平台的施工;e. Remove the pier formwork in the first section and the assembly module of the construction platform, install the steel bars and the pier formwork in the third section, and carry out the third section through the modular construction platform construction method as claimed in claim 8 or 9. Construction of the construction platform on top of the section pier formwork;
f、进行第三区段的混凝土浇筑;f. Concrete pouring in the third section;
g、重复步骤e和f,直至完成整个桥梁墩台的施工;g. Repeat steps e and f until the construction of the entire bridge abutment is completed;
当需要进行系梁或盖梁施工时,在接近系梁或盖梁底部的调节区段,通过步骤b和c进行该调节区段的钢筋、墩台模板和施工平台的施工;当调节区段的混凝土强度满足施工要求后,拆除调节区段的施工平台和墩台模板,并在浇筑完成的桥梁墩台上安装支撑抱箍,通过步骤b和c进行系梁或盖梁的钢筋、墩台模板和施工平台的施工。When the tie beam or cover beam construction needs to be carried out, in the adjustment section close to the bottom of the tie beam or cover beam, the steel bars, pier formwork and construction platform of the adjustment section are constructed through steps b and c; After the concrete strength meets the construction requirements, remove the construction platform and pier formwork in the adjustment section, install the support hoop on the bridge pier after pouring, and perform steps b and c to tie the beams or cover the beams. Construction of formwork and construction platforms.
以下针对各部件的具体结构各工序的施工方法,进行进一步的详细说明:The following is a further detailed description of the construction methods of the specific structures and processes of each component:
本申请中的拼装模块可以通过平杆、竖杆、斜杆、连接杆、连接点、围挡、斜撑及其他定型材料组成。根据桥梁墩台形式,组成施工平台的模块分如图1-图5所示的多种形式。The assembled module in this application can be composed of flat rods, vertical rods, inclined rods, connecting rods, connecting points, enclosures, diagonal braces and other shaping materials. According to the form of bridge piers and abutments, the modules that make up the construction platform are divided into various forms as shown in Figures 1-5.
如图1,其拼装模块呈扇环形,用于圆形柱式墩及圆端形墩身施工。贴近墩身的圆弧段两根连接杆上、下端各焊接一对凹连接块,在墩身模板适宜位置焊接纵向加强肋,肋上与凹连接块对应设置凸连接块。在外侧设置围挡。As shown in Figure 1, the assembly module is fan-shaped, which is used for the construction of circular column piers and round-end pier bodies. A pair of concave connection blocks are welded to the upper and lower ends of the two connecting rods in the arc section close to the pier body, and longitudinal reinforcing ribs are welded at the appropriate positions of the pier body formwork, and convex connection blocks are arranged on the ribs corresponding to the concave connection blocks. Set up a fence on the outside.
如图2所示,其拼装模块呈矩形,用于同一墩台相邻墩台柱同时施工时搭设连接通道。相邻模块两端连接杆的外侧(长度方向)分别设置凸、凹连接块,并设置双侧围挡。As shown in Figure 2, the assembled module is rectangular, which is used to set up connecting passages when adjacent piers and abutments on the same pier are constructed at the same time. The outer sides (length direction) of the connecting rods at both ends of the adjacent modules are respectively provided with convex and concave connecting blocks and double-sided enclosures.
如图3所示,其拼装模块为过渡段使用,呈六边形。如图8所示,其用在环形施工平台和直线的连接通道之间,在与相邻拼装模块相连的四根连接杆上设有连接块,并设置双侧围挡。As shown in Figure 3, the assembling module is used for the transition section and is hexagonal. As shown in Figure 8, it is used between the annular construction platform and the straight connecting channel, and the four connecting rods connected to the adjacent assembled modules are provided with connecting blocks and double-sided enclosures.
如图2所示,其拼装模块还可以用于柱式墩的系梁、盖梁、薄壁墩台身、墩台帽的施工,呈矩形,连接在模板外侧。固定连接方式也是在两端连接杆上设置连接块,并在外侧设围挡。As shown in Figure 2, its assembly module can also be used for the construction of the tie beam, cover beam, thin-walled pier body and pier cap of the column pier. It is rectangular and connected to the outside of the formwork. The fixed connection method is also to set connecting blocks on the connecting rods at both ends, and set up enclosures on the outside.
如图4所示,其拼装模块用于矩形断面墩台身转角处搭设的平台。转角两端的连接杆上设连接块,与墩台模板的加强肋上的连接块相连,沿转角两边外侧设置围挡。As shown in Figure 4, the assembly module is used for the platform erected at the corner of the rectangular section pier body. The connecting rods at both ends of the corner are provided with connecting blocks, which are connected with the connecting blocks on the reinforcing ribs of the pier formwork, and enclosures are arranged along the outer sides of both sides of the corner.
如图5所示,其拼装模块用于变截面墩台身施工搭设的平台。两端的连接杆斜向设置,坡度与模板相同,平面可呈矩形或圆环形,外侧设置围挡。As shown in Figure 5, the assembly module is used for the platform for the construction of the variable-section pier body. The connecting rods at both ends are arranged obliquely, the slope is the same as that of the template, the plane can be rectangular or circular, and the outer side is provided with enclosures.
由两根相互平行的竖杆(图5内侧的竖杆随模板坡度)、两根相互平行的平杆和一根斜杆组成一个模块框架(图5中的模块框架为梯形框架),作为模块的基本组成单位。两个模块框架(模块分段较长时可增加)间用平杆(分为直线型和曲线型)连接,组成模块的骨架结构。模块框架可以是多根杆焊接为一体结构,也可以通过上、中、下结构进行拆分,进行可拆卸的拼装,即通过上部的矩形上支撑架和下部的下矩形支撑架形成主体结构,通过连接杆进行连接,并可以调整结构的大小。A module frame (the module frame in Figure 5 is a trapezoid frame) is composed of two parallel vertical rods (the vertical rod on the inside of Figure 5 follows the slope of the formwork), two parallel flat rods and an inclined rod, as a module basic unit. The two module frames (which can be added when the module segment is longer) are connected by flat rods (divided into linear and curved) to form the skeleton structure of the module. The module frame can be a multi-rod welded integral structure, or it can be split by the upper, middle and lower structures for detachable assembly, that is, the main structure is formed by the upper rectangular upper support frame and the lower lower rectangular support frame. The connection is made by connecting rods and the size of the structure can be adjusted.
在每种模块骨架的顶部铺设薄钢板制成的防滑板,防滑板与框架顶部钻孔,以螺栓连接。A skid plate made of thin steel plate is laid on the top of each module frame, and the skid plate is drilled with the top of the frame and connected with bolts.
本申请中的模块之间的连接方式,对于不需要搭设通道(柱式墩台的立柱分别施工)的方案,每个模块的连接杆两侧分别钻取螺栓孔。拼装模块与墩台模板固定后,用长杆螺栓穿过相邻两连接杆的螺栓孔固定即可。围挡上的连接杆也以此方式连接。For the connection method between modules in the present application, for the solution that does not require a channel (the columns of the column pier are constructed separately), bolt holes are drilled on both sides of the connecting rod of each module. After the assembly module is fixed with the pier formwork, it can be fixed with long rod bolts through the bolt holes of the adjacent two connecting rods. The connecting rods on the enclosure are also connected in this way.
当柱式墩台的立柱施工需要搭设空中连接通道时,每个模块的连接杆上、下端分别焊接连接块,安装模块时首先将模块连接杆内侧的连接块与模板上相应的连接块用销钉连接,再将相邻模块间的连接块用销钉连接即可。When the column construction of the column pier needs to set up an aerial connection channel, the upper and lower ends of the connecting rod of each module are welded with connecting blocks respectively. When installing the module, first connect the connecting block inside the connecting rod of the module and the corresponding connecting block on the formwork with pins. Connect, and then connect the connecting blocks between adjacent modules with pins.
围挡与模块的连接,围挡连接杆的下端外轮廓尺寸与模块连接杆上端内轮廓尺寸相宜,设置成插口+承口模式,并在承口顶端向下一定深度部位焊接隔板,插口、承口适当位置钻取螺栓孔,围挡连接杆下端插入模块连接杆上端后,用螺栓固定即可。在围挡适当部位设置一处开启式围挡,与安全爬梯200出口连接,便于施工人员出入。For the connection between the enclosure and the module, the outer contour size of the lower end of the enclosure connecting rod is suitable for the inner contour size of the upper end of the module connecting rod. Drill bolt holes at the appropriate position of the socket, insert the lower end of the enclosure connecting rod into the upper end of the module connecting rod, and fix it with bolts. An open enclosure is set up at the appropriate part of the enclosure, which is connected to the exit of the
搭设空中连接通道时,可在墩台柱模板适当部位增设加强肋,焊接连接块,同时在通道适当部位的模块连接杆底部设置相应的连接块,用适宜尺寸的型钢(共4根)连接两点,增加通道的稳定性。When erecting an aerial connection channel, reinforcing ribs can be added to the appropriate parts of the pier and column formwork, and connecting blocks can be welded. At the same time, corresponding connecting blocks can be set at the bottom of the module connecting rods in the appropriate parts of the channel, and the two points are connected with appropriate size steel (4 in total). , to increase the stability of the channel.
利用上述的一种模块化桥梁通用施工平台的应用方法,其特征在于,包括以下步骤:Utilize above-mentioned a kind of application method of modular bridge universal construction platform, is characterized in that, comprises the following steps:
用于常见的桥梁墩台柱(身)施工时搭设施工平台:It is used to build a construction platform during the construction of common bridge piers and columns (body):
一、模块制作:1. Module production:
1、如图1所示拼装模块的制作:1. The production of the assembled module as shown in Figure 1:
(1)、按设计尺寸下料,其中竖杆选择适宜规格的型钢,以方钢为佳。原则上一个模块设6根竖杆、4根直线型平杆、5根圆弧形平杆、2根直线型斜杆、一块扇环形防滑板(薄钢板)。(1) Cut the material according to the design size, among which the vertical rod selects the appropriate specification of the steel, preferably the square steel. In principle, a module is equipped with 6 vertical rods, 4 linear flat rods, 5 arc-shaped flat rods, 2 linear inclined rods, and a fan-shaped anti-skid plate (thin steel plate).
(2)、首先用2根直线型竖杆、2根直线型平杆、1根直线型斜杆焊接成一个框架。每个模块原则上设2个框架,用4根圆弧形平杆连接成骨架。(2) First,
(3)、在内侧竖杆(连接杆)正面(迎向模板的一面)上、下端各焊接一对凹形连接块,在连接杆的两个侧面上,根据模块间的连接方式各设置一对凹形连接块(与之相邻的连接杆上则设置凸形连接块),或在两侧壁上钻取一对螺栓孔,用以连接相邻模块及固定围挡。(3) Weld a pair of concave connecting blocks on the upper and lower ends of the front (the side facing the template) of the inner vertical rod (connecting rod), respectively. On the two sides of the connecting rod, set a For the concave connecting block (the convex connecting block is set on the connecting rod adjacent to it), or drill a pair of bolt holes on the two side walls to connect the adjacent modules and fix the enclosure.
(4)、围挡由2根竖杆、1根平杆连接而成,两根竖杆下端外轮廓尺寸较骨架外侧两根竖杆内轮廓尺寸稍小,在对应位置上钻取同直径的螺栓孔。(4) The enclosure is connected by two vertical rods and one flat rod. The outer contour size of the lower end of the two vertical rods is slightly smaller than the inner contour size of the two vertical rods outside the skeleton. Drill bolts of the same diameter at the corresponding positions. hole.
(5)、在骨架外侧两竖杆顶端向下适当深度,焊接一块钢质隔板,与围挡竖杆下部形成承插口结构,围挡就位后用长杆螺栓穿过4个螺栓孔,固定围挡。(5) Weld a steel partition plate to a suitable depth from the top of the two vertical rods on the outside of the skeleton to form a socket-socket structure with the lower part of the vertical rod of the enclosure. After the enclosure is in place, use long rod bolts to pass through the 4 bolt holes. Fixed fence.
(6)、在扇环形防滑板与骨架平杆对应位置上钻取小孔,与平杆点焊连接或用螺丝连接,螺丝钉面与板顶平齐。(6) Drill small holes at the corresponding positions of the fan annular anti-skid plate and the skeleton flat rod, and connect them with the flat rod by spot welding or with screws. The screw surface is flush with the top of the board.
2、如图2所示的拼装模块的制作:2. The production of the assembled module as shown in Figure 2:
该拼装模块呈矩形构造,其用于搭设连接墩柱施工平台的空中通道,或者用作搭设薄壁墩台身及墩台帽施工平台、柱式墩系梁、盖梁施工平台。The assembled module has a rectangular structure, and is used for erecting an aerial passage connecting a pier-column construction platform, or as a construction platform for erecting a thin-walled pier body and a pier cap, a column-type pier tie beam, and a cover-beam construction platform.
该拼装模块的制作方式与图1所示的拼装模块相同,在不同的应用位置可能需要设置双侧围挡。搭设空中连接通道时,在连接杆的两个侧面上,上、下端各设置一对凹形连接块(与之相邻的连接杆上则设置凸形连接块),在适当位置的模块底部,设置一对凹形斜撑连接块,用以连接斜撑,提高通道整体稳定性。The manufacturing method of the assembled module is the same as that of the assembled module shown in FIG. 1 , and double-sided enclosures may need to be provided in different application positions. When setting up the air connection channel, a pair of concave connection blocks are set on the upper and lower ends of the two sides of the connection rod (the convex connection block is set on the adjacent connection rod), and at the bottom of the module at the appropriate position, A pair of concave diagonal brace connecting blocks are arranged to connect the diagonal braces and improve the overall stability of the passage.
在通道或平台的适当位置设置一处开启式围挡,在该处围挡竖杆上设置锁扣。与安全爬梯连接固定,方便操作人员出入。An open enclosure is arranged at an appropriate position of the passage or platform, and a lock is arranged on the vertical rod of the enclosure. It is connected and fixed with the safety ladder, which is convenient for operators to enter and exit.
3、图3-5所示的拼装模块的制作:3. Production of the assembled module shown in Figure 3-5:
图3-5所示的拼装模块根据不同的应用场合进行应用,在此不再重述,其基本构造及制作方法同前述1,根据需要可以设置双侧围挡。The assembled modules shown in Figures 3-5 are applied according to different application occasions, and will not be repeated here.
二、施工平台作业:2. Construction platform operation:
1、原地试拼:1. Try on the spot:
将加工成型的模块分类存放,选择平整坚实的场地,按照设计的平台样式进行拼接,以检验模块的制作精度,直观地分析、改进模块的结构,评价连接件设置的合理性。Store the processed modules in categories, choose a flat and solid site, and splicing them according to the designed platform style to test the production accuracy of the modules, intuitively analyze and improve the structure of the modules, and evaluate the rationality of the connection settings.
2、墩柱、墩身试拼:2. Trial of pier column and pier body:
以柱式墩身为例。Take the column pier as an example.
选择平整、坚实场地,按需要定制适当长度的墩台柱、墩台身模板,在模板上部适当范围内焊接加强肋(型钢),数量及位置根据模块连接杆上的连接块位置确定,在加强肋对应位置上焊接凸形连接块。连接块大小以能够使模块内侧与模板之间保持适当空隙,方便插、拔销钉为准。Choose a flat and solid site, customize the pier column and pier body formwork of appropriate length as required, and weld reinforcing ribs (section steel) within an appropriate range on the upper part of the formwork. Solder the convex connection block on the corresponding position. The size of the connection block should be able to maintain a proper gap between the inner side of the module and the template, so that the pins can be easily inserted and pulled out.
在每根墩柱模板适当位置另设2根加强肋(双柱墩共4根),在每个肋上沿墩身横向位置焊接一个斜撑连接块。Two additional reinforcing ribs (4 in total for double-column piers) are installed at the appropriate position of each pier column formwork, and a diagonal bracing connection block is welded on each rib along the lateral position of the pier body.
将模板竖起,按照设计的方案固定(如缆绳拉紧,花篮螺栓调整松紧)。Erect the formwork and fix it according to the designed scheme (such as tightening the cable and adjusting the tension of the flower basket bolt).
(1)、将如图1所示的拼装模块逐块吊起,将拼装模块连接杆上的连接块与模板加强肋上的连接块对准,插入销钉固定。(1) Lift up the assembled modules as shown in Figure 1 one by one, align the connecting blocks on the connecting rods of the assembled modules with the connecting blocks on the reinforcing ribs of the formwork, and insert pins to fix them.
(2)、拼装模块间的连接视需要采取相邻模块用销钉连接固定,或用长杆螺栓穿过模块间相邻竖杆上的螺栓孔,拧紧固定,将外侧围挡竖杆下端(插头)插入模块竖杆承口内,与相邻竖杆通过长杆螺栓固定。相邻围挡上端固定方式相同。(2) The connection between the assembled modules can be fixed by connecting the adjacent modules with pins as needed, or using long-rod bolts to pass through the bolt holes on the adjacent vertical rods between the modules, tighten and fix, and connect the lower end of the outer wall of the vertical rod (plug. ) into the socket of the vertical rod of the module, and fixed with the adjacent vertical rod by long rod bolts. The upper ends of adjacent enclosures are fixed in the same way.
(3)、墩柱平台圆弧段拼装完成后,在地面上将如图2所示的拼装模块拼接成通道整体,两端与如图3所示的拼装拼接,两种连接均通过相邻的连接块插入销钉,再整体吊起,与已经安装在模板上的圆弧形平台连接。视设计需要安装4根斜顶撑,斜顶撑用型钢制作,两端各焊接一对斜撑连接块,与拼装模块底部及模板侧面的斜撑连接块对应连接。(3) After the arc segment of the pier and column platform is assembled, the assembled modules shown in Figure 2 are spliced into the whole channel on the ground, and the two ends are assembled and spliced as shown in Figure 3, and the two connections are connected by adjacent The connecting block is inserted into the pin, and then lifted as a whole to connect with the arc-shaped platform that has been installed on the formwork. Depending on the design, 4 diagonal braces should be installed. The diagonal braces are made of section steel, and a pair of diagonal bracing connection blocks are welded at both ends, corresponding to the diagonal bracing connection blocks at the bottom of the assembled module and the side of the formwork.
(4)对拼装完的平台进行配重、摆动、振动试验,检验其整体刚度和稳定性,及时修正、优化设计,便于定型。(4) Carry out counterweight, swing and vibration tests on the assembled platform to check its overall stiffness and stability, and correct and optimize the design in time to facilitate finalization.
可以对模块分别进行逐块安拆、分段安拆、整体安拆对比试验,找出效率最高的安拆方式。The modules can be installed and disassembled block by block, sectioned and disassembled, and the overall installation and disassembly comparison test can be carried out to find out the most efficient way of installation and disassembly.
三、桥梁墩台施工方法:3. Construction methods of bridge piers and abutments:
以双柱式墩台,爬模施工方法为例。Take the double-column pier and climbing formwork construction method as an example.
1、根据施工组织设计确定的爬模施工方案,确定模板每次爬升高度,设计模板长度、构造,由此设计施工平台的形式、尺寸。以双柱墩为例,需立柱模板4段,施工平台2座。1. According to the construction plan of the climbing formwork determined by the construction organization design, determine the climbing height of the formwork each time, design the length and structure of the formwork, and design the form and size of the construction platform. Taking the double-column pier as an example, 4 sections of column formwork and 2 construction platforms are required.
墩台柱施工顺序为:安装第1区段钢筋、模板→在第1区段模板顶部安装第1座平台→浇筑第1区段混凝土→安装第2区段钢筋、模板→在第2区段模板顶部安装第2座平台→浇筑第2区段混凝土→安装第3区段钢筋→拆除第1区段模板、第1座平台→将第1区段模板、第1座平台转至第三段工作面,依此向上推进。The construction sequence of the pier and abutment column is: install the steel bars and formwork in the first section → install the first platform on the top of the formwork in the first section → pour the concrete in the first section → install the steel reinforcement and formwork in the second section → formwork in the second section Install the second platform on the top → pour the second section concrete → install the third section steel reinforcement → remove the first section formwork and the first platform → transfer the first section formwork and the first platform to the third section for work face, and proceed upwards accordingly.
在安装模板、搭设平台的过程中,在适当位置搭设安全爬梯,在平台位置设置出口,与平台的活动围挡相连,安全爬梯与两座平台中至少一座保持连接状态。In the process of installing the formwork and setting up the platform, set up a safety ladder at an appropriate position, set an exit at the platform position, connect with the movable enclosure of the platform, and keep the safety ladder connected to at least one of the two platforms.
系梁、盖梁施工平台的搭设:The erection of the construction platform of the tie beam and the cover beam:
在两个立柱系梁高度搭设由如图1所示的拼装模块组成的圆弧形平台→搭设系梁施工支架→整体安装系梁钢筋→将系梁模板与如图2所示的拼装模块分段或整体连接→吊装系梁模板,与立柱模板、圆弧形平台对接→浇筑混凝土→拆除系梁模板、支架。Set up a circular arc-shaped platform composed of the assembled modules as shown in Figure 1 at the height of the two column tie beams → set up the tie beam construction brackets → install the tie beam steel bars as a whole → separate the tie beam template from the assembled modules as shown in Figure 2 Section or overall connection → hoist the tie beam formwork, butt with the column formwork and arc-shaped platform → pour concrete → remove the tie beam formwork and support.
盖梁施工平台搭设:Cover beam construction platform erection:
在两个立柱盖梁高度搭设由如图1所示的拼装模块组成的圆弧形平台→搭设盖梁施工支架→整体安装盖梁钢筋→将盖梁模板与如图2所示的拼装模块分段或整体连接→吊装盖梁模板→浇筑混凝土→拆除该梁模板、支架→拆除平台。Set up an arc-shaped platform composed of the assembled modules as shown in Figure 1 at the height of the two columns and cover beams → set up the cover beam construction brackets → install the cover beam steel bars as a whole → separate the cover beam formwork from the assembly modules shown in Figure 2 Section or overall connection → lifting cover beam formwork → pouring concrete → removing the beam formwork and support → removing the platform.
2、场地准备2. Site preparation
将施工场地整平、压实,如有特殊要求(如现场制作钢筋、墩柱过高需要锚固安全爬梯和物料提升机),在适当范围内浇筑混凝土地面或基础。The construction site shall be leveled and compacted. If there are special requirements (such as on-site production of steel bars, piers that are too high, safety ladders and material hoists need to be anchored), concrete floors or foundations shall be poured within an appropriate range.
3、模板、平台准备3. Template and platform preparation
立柱、系梁、盖梁模板首先在原地试拼,检验其整体刚度、接缝严密性、纵横向顺直度,不足之处加以改进。立柱模板合理分段,便于接近系梁或盖梁的一段安装,使其顶部恰为系梁或盖梁的底部。Columns, tie beams, and cover beam formwork are first tested on the spot to check their overall stiffness, joint tightness, vertical and horizontal straightness, and improve the deficiencies. The column formwork is reasonably segmented to facilitate the installation of a section close to the tie beam or cover beam, so that the top is just the bottom of the tie beam or cover beam.
组成平台的模块在原地组合、试拼,检查拼装后的整体刚度,掌握模块间连接的操作,合理设置吊点,保证安、拆过程的安全。The modules that make up the platform are assembled and tried together in situ, the overall stiffness after assembly is checked, the operation of the connection between the modules is mastered, and the lifting points are reasonably set to ensure the safety of the installation and disassembly process.
进行模板与平台的连接、试拼,检验连接块的设置是否合理,安拆是否方便,及时改进。Carry out the connection and trial assembly between the template and the platform, check whether the setting of the connecting block is reasonable, whether the installation and disassembly are convenient, and improve it in time.
4、墩柱第1区段施工:4. Construction of the first section of the pier column:
放出墩柱中心位置。Release the center of the pier.
第1区段钢筋安装后,安装第1区段模板。模板底部对中,用缆绳(3根或4根)拉紧固定,调整垂直度。After the 1st section reinforcement is installed, install the 1st section formwork. The bottom of the formwork is centered and fixed with cables (3 or 4) to adjust the verticality.
逐块吊起模块A,使其连接块与模板顶端加强肋上的连接块对准,插入销钉固定,相邻模块间用螺栓连接,加装围挡,拼接成平台圆弧段。也可Lift module A block by block, so that its connecting block is aligned with the connecting block on the reinforcing rib at the top of the formwork, insert pins to fix it, connect adjacent modules with bolts, install enclosures, and spliced into a platform arc segment. also may
在原地拼接平台圆弧段,整体起吊安装。The arc segment of the platform is spliced in situ, and the whole is lifted and installed.
逐块拼接模块B、C,在原地拼成空中通道,整体吊装,与已经安装的平台圆弧段对接,如通道整体刚度不足,则安装斜撑固定。同时拼装安全爬梯,与通道连接固定。The modules B and C are spliced block by block to form an air channel on the spot, hoisted as a whole, and docked with the installed platform arc segment. If the overall stiffness of the channel is insufficient, install diagonal braces to fix it. At the same time, the safety ladder is assembled and fixed with the passage.
平台固定后,再次校正、调整模板的垂直度,封堵模板底部与地面之间的缝隙,浇筑第1区段混凝土。After the platform is fixed, correct and adjust the verticality of the formwork again, seal the gap between the bottom of the formwork and the ground, and pour the concrete in the first section.
5、墩柱第2区段施工:5. Construction of the second section of the pier column:
在已经浇筑的第1区段墩柱顶部放出墩柱中心位置,焊接第2区段钢筋,安装第2区段模板,牵拉固定后,安装第2座平台,浇筑第2区段混凝土,方式同前述4。Release the center of the pier column at the top of the pier column of the first section that has been poured, weld the steel bar of the second section, install the template of the second section, pull and fix it, install the second platform, and pour the concrete of the second section. Same as above 4.
混凝土达到规定强度后,焊接第3区段钢筋。After the concrete reaches the specified strength, the reinforcement of the third section is welded.
6、模板爬升、平台安拆:6. Template climbing, platform installation and dismantling:
墩柱第2区段混凝土与模板间的粘结力达到足以支承第3区段施工荷载后,拆除第1区段平台及模板,在原地将模板打磨整理,安装到第3区段位置,再将平台安装到模板顶部,其余操作同前树5。After the bonding force between the concrete and the formwork in the second section of the pier column is sufficient to support the construction load of the third section, remove the platform and formwork in the first section, grind and arrange the formwork in situ, install it in the third section, and then re-install it. Install the platform on top of the template, and the rest of the operations are the same as in tree 5 above.
依此操作,向上爬升施工。According to this operation, climb up the construction.
7、系梁、盖梁施工:7. Construction of tie beam and cover beam:
接近系梁或盖梁底部时,该段模板顶部换成适当长度的调节段,仔细调整该段顶部标高,使其等于系梁或盖梁底部标高。平台安装在调节段上,When approaching the bottom of the tie beam or cover beam, the top of this section of the formwork is replaced with an adjustment section of appropriate length, and the top elevation of this section is carefully adjusted to make it equal to the bottom elevation of the tie beam or cover beam. The platform is installed on the adjustment section,
浇筑该段混凝土。Pour this section of concrete.
首先拆除平台及调节段模板,在调节段上安装系梁或盖梁施工的支撑抱箍,再安装横向支撑和底板。First, remove the platform and the formwork of the adjustment section, install the support hoop for the construction of the tie beam or the cover beam on the adjustment section, and then install the lateral support and the bottom plate.
在地面上将系梁与墩柱的组合模板、系梁侧板与组成平台的模块连接固定,或将盖梁侧板、端板与组成平台的模块连接固定。On the ground, the combined formwork of the tie beam and the pier column, the side plate of the tie beam and the module forming the platform are connected and fixed, or the side plate and end plate of the cover beam and the module forming the platform are connected and fixed.
同时安装调节段以上一段墩柱钢筋和系梁钢筋。At the same time, install a section of pier column reinforcement and tie beam reinforcement above the adjustment section.
将模板与模块的组合体吊装就位,连接固定,浇筑混凝土。拆除平台和模板,向上段爬升。The combination of the formwork and the module is hoisted into place, connected and fixed, and concrete is poured. Remove the platform and formwork and climb the upper section.
盖梁施工方法与此相同。The construction method of the cover beam is the same.
上文已详细描述了用于实现本发明的较佳实施例,但应理解,这些实施例的作用仅在于举例,而不在于以任何方式限制本发明的范围、适用或构造。本发明的保护范围由所附权利要求及其等同方式限定。所属领域的普通技术人员可以在本发明的教导下对前述各实施例作出诸多改变,这些改变均落入本发明的保护范围。The preferred embodiments for carrying out the present invention have been described in detail above, but it should be understood that these embodiments are intended to be illustrative only and not intended to limit the scope, applicability, or configuration of the invention in any way. The scope of protection of the present invention is defined by the appended claims and their equivalents. Those skilled in the art can make many changes to the foregoing embodiments under the teaching of the present invention, and these changes all fall within the protection scope of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010662928.1A CN111663457A (en) | 2020-07-10 | 2020-07-10 | Assembled module, modular construction platform and method, bridge pier construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010662928.1A CN111663457A (en) | 2020-07-10 | 2020-07-10 | Assembled module, modular construction platform and method, bridge pier construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN111663457A true CN111663457A (en) | 2020-09-15 |
Family
ID=72392277
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010662928.1A Pending CN111663457A (en) | 2020-07-10 | 2020-07-10 | Assembled module, modular construction platform and method, bridge pier construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111663457A (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113756565A (en) * | 2021-09-28 | 2021-12-07 | 北京怡泰盛达技术发展有限责任公司 | Special template mounting and dismounting system for building |
| CN114395988A (en) * | 2022-02-15 | 2022-04-26 | 中国建筑第六工程局有限公司 | Design template construction platform |
| CN115110766A (en) * | 2022-07-11 | 2022-09-27 | 中铁十一局集团有限公司 | Pit internal vibration table suspended formwork structure and construction method |
| CN117513714A (en) * | 2024-01-04 | 2024-02-06 | 河北盛卓建筑设备制造有限公司 | Lifting platform for building construction |
| CN119221691A (en) * | 2024-09-11 | 2024-12-31 | 中建八局发展建设有限公司 | A frame for arc-shaped concrete structure construction and construction method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104727223A (en) * | 2015-01-22 | 2015-06-24 | 中交路桥建设有限公司 | Annular platform for bridge pier stud construction and construction method |
| CN106592438A (en) * | 2016-12-27 | 2017-04-26 | 中铁六局集团有限公司 | Two-column pier and middle tie beam construction method employing integral movement of trusses |
| CN209114333U (en) * | 2018-10-29 | 2019-07-16 | 河南省公路工程局集团有限公司 | A kind of combined steel structural unit block |
| CN110205918A (en) * | 2019-05-23 | 2019-09-06 | 山东省交通规划设计院 | A kind of packaged type bridges pile splicing structure and attaching method thereof |
| CN212452315U (en) * | 2020-07-10 | 2021-02-02 | 河南省公路工程局集团有限公司 | Assembly module and modular construction platform |
-
2020
- 2020-07-10 CN CN202010662928.1A patent/CN111663457A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104727223A (en) * | 2015-01-22 | 2015-06-24 | 中交路桥建设有限公司 | Annular platform for bridge pier stud construction and construction method |
| CN106592438A (en) * | 2016-12-27 | 2017-04-26 | 中铁六局集团有限公司 | Two-column pier and middle tie beam construction method employing integral movement of trusses |
| CN209114333U (en) * | 2018-10-29 | 2019-07-16 | 河南省公路工程局集团有限公司 | A kind of combined steel structural unit block |
| CN110205918A (en) * | 2019-05-23 | 2019-09-06 | 山东省交通规划设计院 | A kind of packaged type bridges pile splicing structure and attaching method thereof |
| CN212452315U (en) * | 2020-07-10 | 2021-02-02 | 河南省公路工程局集团有限公司 | Assembly module and modular construction platform |
Non-Patent Citations (1)
| Title |
|---|
| 焦胜军: "《高速铁路桥梁施工与维护(上册)》", 28 February 2011, 西南交通大学出版社, pages: 208 - 216 * |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113756565A (en) * | 2021-09-28 | 2021-12-07 | 北京怡泰盛达技术发展有限责任公司 | Special template mounting and dismounting system for building |
| CN114395988A (en) * | 2022-02-15 | 2022-04-26 | 中国建筑第六工程局有限公司 | Design template construction platform |
| CN115110766A (en) * | 2022-07-11 | 2022-09-27 | 中铁十一局集团有限公司 | Pit internal vibration table suspended formwork structure and construction method |
| CN117513714A (en) * | 2024-01-04 | 2024-02-06 | 河北盛卓建筑设备制造有限公司 | Lifting platform for building construction |
| CN117513714B (en) * | 2024-01-04 | 2024-03-15 | 河北盛卓建筑设备制造有限公司 | Lifting platform for building construction |
| CN119221691A (en) * | 2024-09-11 | 2024-12-31 | 中建八局发展建设有限公司 | A frame for arc-shaped concrete structure construction and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111663457A (en) | Assembled module, modular construction platform and method, bridge pier construction method | |
| CN107090975B (en) | Formwork erecting construction method for ultrahigh large-span concrete cast-in-place beam bailey truss | |
| CN103328820B (en) | Method for assembling shell segments for forming tower segments of a hybrid wind turbine tower | |
| CN113756592B (en) | Lifting system of truss roof when height of upper lifting point is limited and construction method thereof | |
| CN105926448A (en) | Construction method for cable-stayed bridge main tower with curve single tower double cable planes | |
| CN102733545A (en) | Section steel column for high-rise building section steel concrete combination structure, and construction method thereof | |
| CN115467421A (en) | A hoisting construction method for complex long-span steel roof | |
| CN108360380A (en) | A kind of bridge pier column construction operation platform and its construction method | |
| JP2000045231A (en) | Arch bridge erection method | |
| CN118166637A (en) | Pile plate type bridge prefabricated assembly type bent cap and construction method thereof | |
| CN212452315U (en) | Assembly module and modular construction platform | |
| CN117005739A (en) | A bottom support system for shallow round silo roof construction and its construction method | |
| CN115787996A (en) | Overhung construction method and overhung frame for super-high building | |
| CN111910766B (en) | A giant long-span rigid concrete steel structure and construction method | |
| CN112554577B (en) | Construction method of large-diameter thick-wall continuous Y-shaped steel pipe column | |
| CN211815605U (en) | Construction device for pile column type pier tie beam and capping beam | |
| CN109989590B (en) | Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam | |
| CN108797350B (en) | Tower column inner and outer stiff skeleton device and construction method thereof | |
| JP7339477B2 (en) | Concrete column formwork construction device and concrete column formwork construction method using the same | |
| CN219604164U (en) | Variable cross-section special-shaped steel tower crown mounting device | |
| CN116104018B (en) | Construction method of variable-section special-shaped steel tower crown installation device | |
| CN108661301B (en) | Modular assembly platform for vertical frames of well frames and use method | |
| CN211201305U (en) | Protection rack of submarine cable terminal preparation | |
| CN116927495B (en) | Sectional beam column pouring construction method | |
| CN209855253U (en) | Auxiliary fixing device for mounting roof super-long steel beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200915 |
|
| RJ01 | Rejection of invention patent application after publication |