CN115467421A - A hoisting construction method for complex long-span steel roof - Google Patents

A hoisting construction method for complex long-span steel roof Download PDF

Info

Publication number
CN115467421A
CN115467421A CN202211195657.9A CN202211195657A CN115467421A CN 115467421 A CN115467421 A CN 115467421A CN 202211195657 A CN202211195657 A CN 202211195657A CN 115467421 A CN115467421 A CN 115467421A
Authority
CN
China
Prior art keywords
truss
main
herringbone
chord
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211195657.9A
Other languages
Chinese (zh)
Other versions
CN115467421B (en
Inventor
杨斌
管磊
朱张豪
王清华
沙伟楠
王文晋
吴德宝
金锋
包晗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN202211195657.9A priority Critical patent/CN115467421B/en
Publication of CN115467421A publication Critical patent/CN115467421A/en
Application granted granted Critical
Publication of CN115467421B publication Critical patent/CN115467421B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/342Structures covering a large free area, whether open-sided or not, e.g. hangars, halls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/36Bearings or like supports allowing movement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/08Vaulted roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3577Extraordinary methods of construction, e.g. lift-slab, jack-block prefabricating a building and moving it as a whole to the erection site
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3588Extraordinary methods of construction, e.g. lift-slab, jack-block using special lifting or handling devices, e.g. gantries, overhead conveying rails

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a hoisting construction method of a complex large-span steel roof, which adopts a method combining software simulation and field construction, builds a BIM model of a structure before construction to simulate the whole construction process, divides a main truss into 11 modules to be prefabricated and assembled on site, then adopts a crawler crane to hoist the steel truss, realizes three-point support of the main truss based on a herringbone column, a jig frame and a main body structure, and simultaneously monitors key parts of the structure, ensures the safety and the installation accuracy of the whole construction process, and solves the problems of construction difficulty and potential safety hazard caused by complex stress form and large construction process difficulty of the large-span space steel truss roof.

Description

一种复杂大跨钢屋盖吊装施工方法A hoisting construction method of complex long-span steel roof

技术领域technical field

本发明属于建筑施工技术领域,尤其涉及一种复杂大跨钢屋盖吊装施工方法。The invention belongs to the technical field of building construction, and in particular relates to a hoisting and construction method of a complicated large-span steel roof.

背景技术Background technique

随着综合国力的不断增强,我国建筑行业迅猛发展,大型体育场馆朝着大跨、轻便的方向发展,结构形式不断创新。钢桁架屋盖因其结构轻盈、外形美观、跨度大、用钢量省等优点越来越多地被应用于现代建筑结构中。但是,针对大跨空间钢桁架屋盖进行施工时,由于大跨空间钢桁架屋盖结构受力情况较为复杂,导致施工工艺难度较大,存在吊装困难、变形难以控制、节点安装准确度难以控制等方面的技术难题;为此,本发明设计了一种针对大跨钢屋盖的新型吊装施工方法,综合考虑了吊装施工过程中的构件分段、吊装顺序等的影响,同时利用测量仪器对钢桁架拼装及吊装过程进行实时监测,以解决大跨空间钢桁架屋盖因为受力形式复杂、施工工艺难度大而导致的施工困难及安全隐患问题。With the continuous enhancement of comprehensive national strength, my country's construction industry is developing rapidly, and large-scale sports venues are developing in the direction of large spans and light weights, and their structural forms are constantly innovating. Steel truss roofs are more and more used in modern building structures due to their light structure, beautiful appearance, large span, and low steel consumption. However, when constructing a long-span space steel truss roof, due to the complex force of the long-span space steel truss roof structure, the construction process is difficult, and there are difficulties in hoisting, deformation control, and joint installation accuracy. etc.; for this reason, the present invention designs a kind of novel hoisting construction method aiming at the large-span steel roof, comprehensively considers the impact of component segmentation, hoisting order, etc. in the hoisting construction process, and utilizes measuring instruments to measure The steel truss assembly and hoisting process is monitored in real time to solve the construction difficulties and potential safety hazards of the large-span space steel truss roof due to the complex force form and difficult construction process.

发明内容Contents of the invention

针对现有技术中存在的不足,本发明提供了一种复杂大跨钢屋盖吊装施工方法,提高了复杂大跨钢桁架屋面吊装施工的准确性和施工质量,保证了施工期间的安全性。Aiming at the deficiencies in the prior art, the present invention provides a complex long-span steel truss roof hoisting construction method, which improves the accuracy and construction quality of complex long-span steel truss roof hoisting construction, and ensures safety during construction.

本发明通过以下技术手段实现上述技术目的。The present invention achieves the above-mentioned technical purpose through the following technical means.

一种复杂大跨钢屋盖吊装施工方法,包括如下步骤:A construction method for hoisting a complex long-span steel roof, comprising the following steps:

步骤1:建立钢桁架屋盖及支撑胎架的BIM模型,全过程模拟,确定吊装方案;Step 1: Establish a BIM model of the steel truss roof and supporting frame, simulate the whole process, and determine the hoisting plan;

步骤2:吊装支撑胎架;Step 2: Hoist the supporting tire frame;

步骤3:主桁架分段拼装;Step 3: Assembling the main truss in sections;

步骤4:将排水柱以及人字柱吊装至建筑主体结构上;Step 4: Hoist the drainage column and herringbone column to the main structure of the building;

步骤5:将步骤3拼装完成的多榀主桁架结构依次吊装至建筑主体结构上,且支撑在支撑胎架以及人字柱上;Step 5: Hoist the multiple main truss structures assembled in step 3 to the main structure of the building in sequence, and support them on the supporting tire frames and herringbone columns;

步骤6:将压环梁吊装并焊接在相邻主桁架前端之间,然后在主桁架及压环梁上焊接安装环向结构;Step 6: Hoist and weld the pressure ring beam between the front ends of adjacent main trusses, and then weld and install the ring structure on the main truss and pressure ring beam;

步骤7:进行主桁架卸载;Step 7: Unload the main truss;

步骤8:拆除支撑胎架;Step 8: Remove the supporting tire frame;

步骤9:待支撑胎架全部拆除完成后,在屋盖转角处安装其余的局部位置杆件。Step 9: After all the supporting tire frames are removed, install the remaining local position rods at the corners of the roof.

进一步地,所述步骤2的具体过程为:Further, the specific process of the step 2 is:

首先在支撑胎架安装位置处的地面上浇筑混凝土基础,在混凝土基础顶部设置预埋件,待混凝土基础强度达到要求后,利用履带吊吊装第一节格构柱至混凝土基础上并与预埋件焊接固定,然后继续在第一节格构柱顶部吊装2~3节格构柱标准节和顶部非标准节,然后拉设缆风绳,揽风绳呈90度布置,揽风绳锚固点设置于建筑主体结构看台梁与立柱节点上,用钢丝绳绑扎形成锚固点。Firstly, pour the concrete foundation on the ground at the installation position of the support tire frame, and set the embedded parts on the top of the concrete foundation. Then continue to hoist 2 to 3 standard sections and non-standard sections on the top of the lattice column on the top of the first section of the lattice column, and then pull the cable wind rope, the wind rope is arranged at 90 degrees, and the anchor point of the wind rope is It is installed on the node of the stand beam and column of the main structure of the building, and is bound with a steel wire rope to form an anchor point.

进一步地,所述顶部非标准节上均设置有转换平台,转换平台上均安装有沙箱,沙箱两侧各设置一根副撑;每榀支撑胎架设置4根揽风绳;每榀主桁架端头压环梁节点处均设置一榀临时支撑胎架。Further, the non-standard section on the top is provided with a conversion platform, and a sandbox is installed on the conversion platform, and an auxiliary support is arranged on both sides of the sandbox; each support tire frame is provided with 4 wind ropes; each A temporary support tire frame is set at the joints of the pressure ring beam at the end of the main truss.

进一步地,所述步骤3中,主桁架由11种类型构件组成,由工厂加工完成后运送至现场进行拼装,包括人字柱、铸钢节点、上端人字柱、桁架尾部弦杆及其腹杆、人字柱间上弦杆、人字柱间上弦杆腹杆、桁架主上弦杆及其腹杆、桁架端部上弦杆及其腹杆、端头弦杆、桁架下弦圆杆、桁架下弦圆管腹杆,拼装过程中,利用钢尺、经纬仪、水准仪以及全站仪对跨距、中心线、位移、标高、起拱度进行精确测量,及时发现并纠正拼装时可能出现的位置偏差,确保整体拼装精度。Further, in the step 3, the main truss is composed of 11 types of components, which are processed by the factory and then transported to the site for assembly, including herringbone columns, cast steel nodes, upper-end herringbone columns, truss tail chords and their webs. Rods, top chords between herringbone columns, top chord webs between herringbone columns, main top chords and their webs of trusses, top chords at truss ends and their webs, end chords, bottom chord round bars of trusses, bottom chord circles of trusses During the assembly process of the pipe web rod, the steel ruler, theodolite, level and total station are used to accurately measure the span, center line, displacement, elevation, and camber, and to detect and correct possible position deviations during assembly in time to ensure Overall assembly accuracy.

进一步地,所述人字柱单独吊装,主桁架其余构件的具体拼装过程为:Further, the herringbone column is hoisted separately, and the specific assembly process of the remaining components of the main truss is as follows:

步骤3.1:在施工现场空地上,完成桁架主上弦杆及其腹杆、桁架端部上弦杆及其腹杆的焊接;Step 3.1: In the open space of the construction site, complete the welding of the main top chord of the truss and its web, the top chord of the truss end and its web;

步骤3.2:在施工现场空地上,焊接用于放置支撑主桁架的拼装胎架,然后将铸钢节点、桁架下弦圆杆、端头弦杆焊接成整体,并放置在拼装胎架上;Step 3.2: On the open space of the construction site, weld the assembled tire frame for placing the main truss, and then weld the cast steel nodes, truss bottom chord round rods, and end chords into a whole, and place them on the assembled tire frame;

步骤3.3:在铸钢节点上靠近首部的一端焊接一组上端人字柱,然后将桁架主上弦杆与上端人字柱焊接固定,接着将桁架端部上弦杆与桁架主上弦杆焊接固定,最后将桁架端部上弦杆与端头弦杆焊接固定;Step 3.3: Weld a set of upper gable columns at the end near the head of the cast steel node, then weld and fix the main top chord of the truss with the upper gable column, then weld and fix the top chord at the end of the truss with the main top chord of the truss, and finally Weld and fix the upper chord at the end of the truss with the end chord;

步骤3.4:在桁架主上弦杆与桁架下弦圆杆之间、桁架端部上弦杆与桁架下弦圆杆之间均焊接桁架下弦圆管腹杆;Step 3.4: Weld the truss lower chord round tube webs between the truss main upper chord and the truss lower chord round rod, and between the truss end upper chord and the truss lower chord round rod;

步骤3.5:在铸钢节点上靠近尾部的一端焊接另一组上端人字柱;Step 3.5: Weld another set of upper chevron columns at the end near the tail on the cast steel node;

步骤3.6:在上端人字柱之间焊接人字柱间上弦杆,在人字柱间上弦杆内焊接人字柱间上弦杆腹杆;Step 3.6: Weld the upper chord between the herringbone columns between the upper herringbone columns, and weld the upper chord web between the herringbone columns in the upper chord between the herringbone columns;

步骤3.7:在靠近主桁架尾部的一组上端人字柱外侧焊接桁架尾部弦杆及其腹杆;Step 3.7: Weld the truss tail chord and its web on the outside of a group of upper gable columns near the tail of the main truss;

步骤3.8:在拼装完成的主桁架内安装人行通道,然后采用三维扫描机器人及时采集现场拼装数据并反馈到BIM模型中,进行数据对比分析,从而及时进行构件纠偏。Step 3.8: Install the walkway in the assembled main truss, and then use the 3D scanning robot to collect the on-site assembly data in time and feed it back to the BIM model for data comparison and analysis, so as to correct the deviation of the components in time.

进一步地,所述步骤4的具体过程为:Further, the specific process of step 4 is:

在建筑主体结构上的人字柱安装位置处设置盆式橡胶支座,然后采用钢板将盆式橡胶支座的上支座板与下支座板进行临时焊接,然后利用履带吊将人字柱吊装至盆式橡胶支座的上支座板上,并通过焊接方式固定,然后采用角钢对人字柱进行临时支撑,接着,利用履带吊将排水柱吊装至建筑主体结构上的设计位置处并安装固定住。Set the basin-type rubber bearing at the installation position of the herringbone column on the main structure of the building, and then use the steel plate to temporarily weld the upper bearing plate and the lower bearing plate of the basin-type rubber bearing, and then use the crawler crane to lift the herringbone column It is hoisted to the upper support plate of the basin-type rubber bearing and fixed by welding, then the angle steel is used to temporarily support the herringbone column, and then the drainage column is hoisted to the designed position on the main structure of the building by a crawler crane The installation is fixed.

进一步地,所述排水柱底部焊接有排水柱耳板,排水柱耳板与建筑主体结构上的预埋耳板先进行临时焊接固定,然后在排水柱耳板两侧采用热轧型钢进行临时焊接固定。Further, the bottom of the drainage column is welded with a drainage column ear plate, and the drainage column ear plate and the pre-embedded ear plate on the main structure of the building are first temporarily welded and fixed, and then hot-rolled steel is used for temporary welding on both sides of the drainage column ear plate fixed.

进一步地,所述步骤5的具体过程为:Further, the specific process of step 5 is:

利用履带吊将步骤3中拼装完成的多榀主桁架结构按照顺时针方向依次吊装至设计位置处,保证主桁架前部搭设在支撑胎架上,主桁架下端凸起放置于人字柱顶部,再在主桁架与人字柱连接节点处进行焊接施工,两者之间的焊缝填充完成三分之一后吊车松钩,然后将主桁架尾部与建筑主体结构的销轴连接点耳板进行连接;其中,吊装过程中,主桁架的端头、压环梁与主桁架连接节点处、主桁架与人字柱连接节点处作为安装控制点,布设相应的传感器实时监测。Use the crawler crane to hoist the multiple main truss structures assembled in step 3 to the design position in a clockwise direction to ensure that the front of the main truss is erected on the supporting tire frame, and the lower end of the main truss is placed on the top of the herringbone column. Then weld the joints between the main truss and the herringbone column. After one-third of the weld between the two is filled, the crane unhooks, and then the tail of the main truss is connected to the ear plate of the pin connection point of the main structure of the building. Connection; Among them, during the hoisting process, the end of the main truss, the connection node between the compression ring beam and the main truss, and the connection node between the main truss and the herringbone column are used as installation control points, and corresponding sensors are deployed for real-time monitoring.

进一步地,所述步骤6的具体过程为:Further, the specific process of the step 6 is:

钢屋盖平面为中心对称结构,有相互垂直的两条对称轴,以长度较长的对称轴称为长轴,长度较短的对称轴称为短轴,将压环梁按从长轴、短轴中间位置向相邻屋盖角部的顺序分区进行吊装,并将其焊接在相邻主桁架前端之间;The plane of the steel roof is a centrally symmetrical structure with two mutually perpendicular symmetrical axes. The longer symmetrical axis is called the major axis, and the shorter symmetrical axis is called the minor axis. The middle position of the short axis is hoisted to the sequential partitions of the adjacent roof corners, and welded between the front ends of the adjacent main trusses;

待压环梁安装就位并焊接完成后,在地面上将径向次梁和环向次梁拼装成整体,然后将径向次梁和环向次梁整体吊装至主桁架与压环梁上方,焊接连接在主桁架及压环梁上;After the pressure ring beam is installed in place and the welding is completed, the radial secondary beam and the circumferential secondary beam are assembled into a whole on the ground, and then the radial secondary beam and the circumferential secondary beam are hoisted as a whole above the main truss and the pressure ring beam, and welded on the On the main truss and pressure ring beam;

最后将屋盖四个角部的环向结构(环向次梁与径向次梁组合)与主桁架及压环梁进行合拢焊接,形成四道合拢缝。Finally, the hoop structure at the four corners of the roof (combination of hoop and radial sub-beams) is closed and welded with the main truss and compression ring beams to form four closing seams.

进一步地,所述步骤7中,主桁架卸载时,首先拆除支撑胎架顶部的副撑,然后基于分区分级循环卸载原则,采用沙箱排沙卸载法进行主桁架的卸载,保证主桁架卸载后的变形均匀,每级卸载按预定下降释放量进行,且整个过程采用全站仪配合健康监测单位进行全程监控。Further, in the step 7, when the main truss is unloaded, the auxiliary support supporting the top of the tire frame is first removed, and then based on the principle of zonal and graded cycle unloading, the sandbox unloading method is used to unload the main truss to ensure that the main truss is unloaded. The deformation of each level is uniform, and the unloading of each level is carried out according to the predetermined drop release amount, and the whole process is monitored by a total station and a health monitoring unit.

本发明具有如下有益效果:The present invention has following beneficial effect:

本发明采用软件模拟及现场施工相结合的方法,在施工前建立结构的BIM模型进行施工全过程模拟,将主桁架分成11个模块预制完成后现场拼装,然后采用履带吊进行钢桁架的吊装,基于人字柱、胎架、主体结构实现对主桁架的三点支撑,同时对结构关键部位进行监测,保证了施工全过程的安全性和安装的准确性。本发明基于软件模拟结果及现场情况确定钢桁架吊装施工方案,综合考虑了吊装施工过程中的构件分段、吊装顺序等的影响,同时利用测量仪器对钢桁架拼装及吊装过程进行监测,从而最终有效提高复杂大跨空间钢桁架屋盖的施工效率及施工质量,保证施工安全,解决大跨空间钢桁架屋盖因为受力形式复杂、施工工艺难度大而导致的施工困难及安全隐患问题。The present invention adopts the method of combining software simulation and on-site construction, establishes the BIM model of the structure before construction to simulate the whole construction process, divides the main truss into 11 modules and assembles them on site after prefabrication, and then uses crawler cranes to hoist the steel truss. The three-point support for the main truss is realized based on the herringbone column, tire frame and main structure, and the key parts of the structure are monitored at the same time to ensure the safety of the whole construction process and the accuracy of installation. The invention determines the steel truss hoisting construction scheme based on software simulation results and site conditions, comprehensively considers the influence of component segmentation and hoisting sequence in the hoisting construction process, and uses measuring instruments to monitor the steel truss assembly and hoisting process, so that the final Effectively improve the construction efficiency and construction quality of complex long-span space steel truss roofs, ensure construction safety, and solve the construction difficulties and safety hazards of large-span space steel truss roofs due to complex force forms and difficult construction techniques.

附图说明Description of drawings

图1为大跨钢屋盖平面示意图;Figure 1 is a schematic plan view of a large-span steel roof;

图2为单榀主桁架安装示意图;Figure 2 is a schematic diagram of the installation of a single main truss;

图3为主桁架与压环梁安装节点示意图;Figure 3 is a schematic diagram of the installation nodes of the main truss and the compression ring beam;

图4为单榀主桁架结构示意图;Fig. 4 is a schematic diagram of a single main truss structure;

图5为混凝土基础内预埋件布置示意图;Figure 5 is a schematic diagram of the layout of embedded parts in the concrete foundation;

图6为支撑胎架吊装示意图;Fig. 6 is a schematic diagram of supporting the hoisting of the tire frame;

图7为主撑和副撑布置示意图;Figure 7 is a schematic diagram of the layout of the main support and auxiliary support;

图8为步骤3.2中的拼装示意图;Figure 8 is a schematic diagram of assembly in step 3.2;

图9为步骤3.3中的拼装示意图;Figure 9 is a schematic diagram of assembly in step 3.3;

图10为步骤3.4中的拼装示意图;Figure 10 is a schematic diagram of assembly in step 3.4;

图11为步骤3.5中的拼装示意图;Figure 11 is a schematic diagram of assembly in step 3.5;

图12为步骤3.6中的拼装示意图;Figure 12 is a schematic diagram of assembly in step 3.6;

图13为步骤3.7中的拼装示意图;Figure 13 is a schematic diagram of assembly in step 3.7;

图14为人行通道拼装示意图;Figure 14 is a schematic diagram of assembling pedestrian walkways;

图15为人字柱临时支撑示意图;Figure 15 is a schematic diagram of the temporary support of the herringbone column;

图16为排水柱固定节点示意图;Figure 16 is a schematic diagram of the fixed node of the drainage column;

图17为压环梁吊装分区以及合拢缝示意图;Figure 17 is a schematic diagram of the hoisting partition and closing joint of the pressure ring beam;

图18为主桁架卸载分区示意图;Figure 18 is a schematic diagram of the unloading partition of the main truss;

图19为本发明所述施工流程图。Fig. 19 is a construction flow chart of the present invention.

图中:1-主桁架;101-人字柱;102-铸钢节点;103-上端人字柱;104-桁架尾部弦杆;105-人字柱间上弦杆;106-人字柱间上弦杆腹杆;107-桁架主上弦杆;108-桁架端部上弦杆;109-端头弦杆;110-桁架下弦圆杆;111-桁架下弦圆管腹杆;2-支撑胎架;201-混凝土基础;202-预埋件;203-揽风绳;204-沙箱;205-副撑;3-拼装胎架;4-人行通道;5-角钢;6-排水柱;601-排水柱耳板;602-热轧型钢;7-压环梁;8-径向次梁;9-环向次梁。In the figure: 1-main truss; 101-herringbone column; 102-cast steel node; 103-upper herringbone column; 104-truss tail chord; 105-top chord between herringbone columns; Rod web; 107-truss main upper chord; 108-truss end upper chord; 109-end chord; 110-truss lower chord round rod; 111-truss lower chord round tube web; Concrete foundation; 202-embedded parts; 203-wind rope; 204-sandbox; 205-auxiliary support; 3-assembled tire frame; 4-walkway; plate; 602-hot-rolled section steel; 7-pressure ring beam; 8-radial secondary beam; 9-circular secondary beam.

具体实施方式detailed description

下面结合附图以及具体实施例对本发明作进一步的说明,但本发明的保护范围并不限于此。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments, but the protection scope of the present invention is not limited thereto.

本实施例优选以昆山足球场项目主体育场大跨空间钢桁架屋盖的施工为例进行方案说明,其中,屋盖主要由36榀悬挑三角主桁架1、场内环向结构、索膜排水柱等组成,钢屋盖场中心对称,几何平面尺寸为长轴方向长 254.6 米,短轴方向宽 217.5 米,36 榀主桁架1沿环向布置,长轴中部相邻桁架端点之间的距离最大,为 19 米,在角部间距最小,为4.5 米;主桁架1几何尺寸均相同,长度61米,悬挑长度46.5米,主桁架1最高点距地面44.5米;在36榀主桁架1单元前端,通过梯形截面环向压环梁7及环向次桁架、主次梁等进行连接,形成封闭环向结构;每榀主桁架1均对应设有一根排水柱6,排水柱6外形尺寸为:长4.75m×宽2.58m×高0.664m。This embodiment preferably takes the construction of the large-span space steel truss roof of the main stadium of the Kunshan Football Stadium Project as an example to illustrate the scheme, in which the roof mainly consists of 36 cantilevered triangular main trusses 1, the ring structure in the field, and cable-membrane drainage The center of the steel roof field is symmetrical. The geometric plane size is 254.6 meters long in the direction of the long axis and 217.5 meters wide in the direction of the short axis. The 36 main trusses 1 are arranged along the ring direction. The largest is 19 meters, and the smallest distance at the corner is 4.5 meters; the main truss 1 has the same geometric dimensions, the length is 61 meters, the cantilever length is 46.5 meters, and the highest point of the main truss 1 is 44.5 meters from the ground; the 36 main trusses 1 The front end of the unit is connected by the trapezoidal cross-section hoop pressure ring beam 7 and the hoop secondary truss, primary and secondary beams, etc. to form a closed hoop structure; each main truss 1 is correspondingly provided with a drainage column 6, and the external dimensions of the drainage column 6 It is: length 4.75m × width 2.58m × height 0.664m.

本发明所述的复杂大跨钢屋盖吊装施工方法,包括如下步骤:The complex large-span steel roof hoisting construction method described in the present invention comprises the following steps:

步骤1:建立钢桁架屋盖BIM模型;Step 1: Build a BIM model of the steel truss roof;

采用BIM软件建立钢桁架屋盖及支撑胎架2的整体模型,并进行吊装施工全过程模拟,基于模拟结果以及现场实际情况确定吊装施工方案;Use BIM software to establish the overall model of the steel truss roof and supporting frame 2, and simulate the whole process of hoisting construction, and determine the hoisting construction plan based on the simulation results and the actual situation on site;

步骤2:吊装支撑胎架2;Step 2: hoisting support tire frame 2;

每榀主桁架1端头压环梁7节点处均需设置一榀临时支撑胎架2,共计36榀,支撑胎架2由多节格构柱拼装组成;吊装支撑胎架2时,首先在支撑胎架2安装位置处的地面上浇筑C30混凝土基础201,混凝土基础201高度为500mm,在混凝土基础201顶部设置预埋件,待混凝土基础201强度达到要求后,利用200t履带吊吊装第一节12m高的格构柱至混凝土基础201上并与预埋件202焊接固定;然后继续在第一节格构柱顶部吊装2~3节格构柱标准节和顶部非标准节,然后拉设缆风绳203,每榀支撑胎架2设置4根揽风绳203,呈90度布置,揽风绳203锚固点设置于主体结构看台梁与立柱节点上,用钢丝绳绑扎形成锚固点;每榀支撑胎架2顶部非标准节上均设置有转换平台,转换平台上均安装有沙箱204,沙箱204两侧各设置一根副撑205。A temporary supporting tire frame 2 needs to be installed at the node 7 of the compression ring beam at the end of each main truss 1, a total of 36 towers. The supporting tire frame 2 is composed of multi-section lattice columns; Pour C30 concrete foundation 201 on the ground at the installation position of support tire frame 2. The height of concrete foundation 201 is 500mm. Embedded parts are installed on the top of concrete foundation 201. After the strength of concrete foundation 201 meets the requirements, use a 200t crawler crane to lift the first section The 12m-high lattice column is placed on the concrete foundation 201 and fixed by welding with the embedded parts 202; then continue to hoist 2 to 3 lattice column standard sections and the top non-standard section on the top of the first lattice column, and then pull the cable Wind rope 203, every supporting tire frame 2 is provided with 4 wind ropes 203, arranged at 90 degrees, the anchor point of wind rope 203 is arranged on the node of the stand beam and column of the main structure, and is bound with steel wire rope to form anchor point; A conversion platform is arranged on the non-standard section at the top of the tire frame 2, and a sandbox 204 is installed on the conversion platform, and an auxiliary support 205 is respectively arranged on both sides of the sandbox 204.

步骤3:钢桁架分段拼装;Step 3: Assemble the steel truss in sections;

参考步骤1中的模型模拟分析结果得出主桁架1变形理论尺寸,重构主桁架1三维模型,根据起拱后构件不同形式,将每榀主桁架1拆分为11种类型构件(人字柱101、铸钢节点102、上端人字柱103、桁架尾部弦杆104及其腹杆、人字柱间上弦杆105、人字柱间上弦杆腹杆106、桁架主上弦杆107及其腹杆、桁架端部上弦杆108及其腹杆、端头弦杆109、桁架下弦圆杆110、桁架下弦圆管腹杆111),由工厂加工完成后运送至现场进行拼装;拼装过程中,利用钢尺、经纬仪、水准仪以及全站仪对跨距、中心线、位移、标高、起拱度进行精确测量,及时发现并纠正拼装时可能出现的位置偏差,确保整体拼装精度,具体的拼装方法如下:Refer to the model simulation analysis results in step 1 to obtain the theoretical deformation size of the main truss 1, reconstruct the three-dimensional model of the main truss 1, and split each main truss 1 into 11 types of components (herringbone Column 101, cast steel node 102, upper herringbone column 103, truss tail chord 104 and its web, herringbone column top chord 105, herringbone column top chord web 106, truss main top chord 107 and its web Rods, truss end upper chords 108 and their webs, end chords 109, truss lower chord round rods 110, truss lower chord round tube webs 111), are processed by the factory and transported to the site for assembly; during the assembly process, use The steel ruler, theodolite, level and total station can accurately measure the span, center line, displacement, elevation and camber, and detect and correct the possible position deviation during assembly in time to ensure the overall assembly accuracy. The specific assembly method is as follows :

步骤3.1:在施工现场空地上,完成桁架主上弦杆107及其腹杆、桁架端部上弦杆108及其腹杆的焊接;Step 3.1: Complete the welding of the truss main top chord 107 and its webs, the truss end top chord 108 and its webs on the open space of the construction site;

步骤3.2:在施工现场空地上,焊接用于放置支撑主桁架1的拼装胎架3,然后将铸钢节点102、桁架下弦圆杆110、端头弦杆109焊接成整体,并放置在拼装胎架3上;Step 3.2: On the open space of the construction site, weld the assembled tire frame 3 for placing the main truss 1, then weld the cast steel node 102, the truss lower chord round bar 110, and the end chord 109 into a whole, and place them on the assembled tire frame rack 3;

步骤3.3:在铸钢节点102上靠近首部的一端焊接一组上端人字柱103,然后将步骤3.1中焊接完成的桁架主上弦杆107及其腹杆吊装至指定安装位置处,将桁架主上弦杆107与上端人字柱103焊接固定,接着将步骤3.1中焊接完成的桁架端部上弦杆108及其腹杆吊装至指定安装位置处,将桁架端部上弦杆108与桁架主上弦杆107焊接固定,最后将桁架端部上弦杆108与端头弦杆109焊接固定;Step 3.3: Weld a set of upper gable columns 103 at the end of the cast steel node 102 close to the head, and then hoist the truss main top chord 107 and its web member welded in step 3.1 to the designated installation position, and the truss main top chord The rod 107 is welded and fixed to the upper herringbone column 103, and then the upper chord 108 at the end of the truss and its web member welded in step 3.1 are hoisted to the designated installation position, and the upper chord 108 at the end of the truss is welded to the main upper chord 107 of the truss Fixing, and finally the upper chord 108 at the end of the truss and the end chord 109 are welded and fixed;

步骤3.4:在桁架主上弦杆107与桁架下弦圆杆110之间、桁架端部上弦杆108与桁架下弦圆杆110之间均焊接桁架下弦圆管腹杆111;Step 3.4: Weld the truss lower chord round tube webs 111 between the truss main upper chord 107 and the truss lower chord round rod 110, and between the truss end upper chord 108 and the truss lower chord round rod 110;

步骤3.5:在铸钢节点102上靠近尾部的一端焊接另一组上端人字柱103;Step 3.5: Weld another set of upper-end chevron columns 103 on the cast steel node 102 near the end;

步骤3.6:在上端人字柱103之间焊接人字柱间上弦杆105,在人字柱间上弦杆105内焊接人字柱间上弦杆腹杆106;Step 3.6: Weld the upper chords 105 between the upper herringbone columns 103, and weld the upper chord webs 106 between the upper chords between the herringbone columns 105;

步骤3.7:在靠近主桁架1尾部的一组上端人字柱103外侧焊接桁架尾部弦杆104及其腹杆;Step 3.7: welding the tail chord 104 of the truss and its web on the outside of a group of upper gable columns 103 near the tail of the main truss 1;

步骤3.8:在拼装完成的主桁架1内安装相关辅助结构,即人行通道4(后续主桁架1吊装完成后拆除);然后采用三维扫描机器人及时采集现场拼装数据并反馈到模型中,进行数据对比分析,从而及时进行构件纠偏;Step 3.8: Install relevant auxiliary structures in the assembled main truss 1, that is, the walkway 4 (removed after the subsequent main truss 1 is hoisted); then use a 3D scanning robot to collect on-site assembly data in time and feed them back to the model for data comparison Analysis, so as to timely rectify components;

步骤4:人字柱101及排水柱6吊装;Step 4: hoisting the herringbone column 101 and the drainage column 6;

人字柱101吊装采用场内吊装,首先在建筑主体结构上的人字柱101安装位置处设置盆式橡胶支座,其中,盆式橡胶支座的下支座板与建筑主体结构预埋板焊接,然后采用12mm以上的钢板将盆式橡胶支座的上支座板与下支座板进行临时焊接(待后续主桁架1全部吊装完成后再拆除该临时固定的钢板);The hoisting of the herringbone column 101 adopts on-site hoisting. Firstly, a basin-type rubber bearing is installed at the installation position of the herringbone column 101 on the main structure of the building. Welding, and then temporarily weld the upper bearing plate and the lower bearing plate of the basin rubber bearing with a steel plate of 12mm or more (the temporary fixed steel plate will be removed after the subsequent main truss 1 is completely hoisted);

然后利用200t履带吊将人字柱101吊装至盆式橡胶支座的上支座板上,并通过焊接方式固定,然后采用角钢5对人字柱101进行临时支撑,保证人字柱101的稳定性;Then use a 200t crawler crane to hoist the herringbone column 101 to the upper bearing plate of the basin-type rubber bearing, and fix it by welding, and then use angle steel 5 to temporarily support the herringbone column 101 to ensure the stability of the herringbone column 101 ;

接着,利用200t履带吊将排水柱6吊装至建筑主体结构上的设计位置处并安装固定,其中,排水柱6底部焊接有排水柱耳板601,排水柱耳板601与建筑主体结构上的预埋耳板先进行临时焊接固定,且排水柱耳板601与预埋耳板接触的两侧,每侧焊缝长度均为100mm,焊角均为25mm,然后在排水柱耳板601两侧采用热轧型钢602进行临时焊接固定;Then, use a 200t crawler crane to hoist the drainage column 6 to the designed position on the main structure of the building and install and fix it. The bottom of the drainage column 6 is welded with a drainage column ear plate 601, and the drainage column ear plate 601 is connected to the pre-installed part on the main structure of the building. The ear plate is temporarily welded and fixed, and the two sides of the ear plate 601 of the drainage column are in contact with the pre-embedded ear plate. The length of the weld on each side is 100mm, and the welding angle is 25mm. Temporary welding and fixing of hot-rolled section steel 602;

步骤5:主桁架1吊装;Step 5: hoisting of the main truss 1;

屋面单榀主桁架1采用场外吊装,利用600t履带吊将步骤3中拼装完成的36榀主桁架1按照顺时针方向依次吊装至设计位置处,保证主桁架1前部搭设在支撑胎架2上,主桁架1下端的两个凸起放置于步骤4布置的人字柱101顶部,再在主桁架1与人字柱101连接节点处进行焊接施工,两者之间的焊缝填充完成三分之一后吊车松钩;然后将主桁架1尾部与建筑主体结构的销轴连接点耳板进行连接;吊装过程中,主桁架1的端头、压环梁7与主桁架1连接节点、主桁架1与人字柱101连接节点作为安装控制点,布设相应的传感器实时监测;Roof single main truss 1 is hoisted off-site, and the 36 main trusses 1 assembled in step 3 are hoisted clockwise to the design position using a 600t crawler crane to ensure that the front of main truss 1 is erected on supporting tire frame 2 Above, the two protrusions at the lower end of the main truss 1 are placed on the top of the herringbone column 101 arranged in step 4, and then the welding construction is carried out at the connection node between the main truss 1 and the herringbone column 101, and the weld between the two is filled three times. After one-third, the crane loosens the hook; then connects the tail of the main truss 1 with the ear plate of the pin connection point of the main structure of the building; The connection node between the main truss 1 and the herringbone column 101 is used as the installation control point, and corresponding sensors are deployed for real-time monitoring;

吊装时,每榀主桁架1上设置4个吊点,每个吊点位置处均焊接有吊装耳板,其中两个吊点设计在靠近首部的上端人字柱10与桁架主上弦杆107连接节点处,另外两个吊点设计在桁架主上弦杆107与桁架端部上弦杆108连接节点处;During hoisting, 4 lifting points are set on each main truss 1, each lifting point is welded with hoisting lugs, and two of the lifting points are designed to connect with the truss main upper chord 107 at the upper end of the truss 10 near the bow At the node, the other two lifting points are designed at the node connecting the main top chord 107 of the truss and the top chord 108 at the end of the truss;

步骤6:压环梁7吊装;Step 6: hoisting the pressure ring beam 7;

由于足球场钢屋盖为中心对称结构,有相互垂直的两条对称轴,本实施例将长度较长的对称轴称为长轴,长度较短的对称轴称为短轴;将压环梁7按从长轴、短轴中间位置向相邻屋盖角部的顺序分区(A区、B区、C区、D区)进行吊装,并将其焊接在相邻主桁架1前端之间;待压环梁7安装就位并焊接完成后,在地面上将径向次梁8和环向次梁9拼装成整体,然后将径向次梁8和环向次梁9整体吊装至主桁架1与压环梁7上方,焊接连接在主桁架1及压环梁7上;Since the steel roof of the football field is a centrally symmetrical structure with two mutually perpendicular symmetrical axes, in this embodiment the longer symmetrical axis is called the major axis, and the shorter symmetrical axis is called the minor axis; the compression ring beam 7 Carry out hoisting according to the sequence from the middle position of the major axis and the minor axis to the corner of the adjacent roof (area A, area B, area C, area D), and weld it between the front ends of the adjacent main truss 1; After the pressure ring beam 7 is installed in place and the welding is completed, the radial secondary beam 8 and the circumferential secondary beam 9 are assembled into a whole on the ground, and then the radial secondary beam 8 and the circumferential secondary beam 9 are integrally hoisted to the main truss 1 and the top of the pressure ring beam 7, welded to the main truss 1 and the pressure ring beam 7;

最后将屋盖四个角部的环向结构(环向次梁与径向次梁组合)与主桁架1及压环梁7进行合拢焊接,屋盖的合拢缝设在如图17所示对称位置,共设置四道合拢缝;图17中的箭头表示压环梁7吊装方向。Finally, the hoop structure at the four corners of the roof (combination of hoop beam and radial beam) is welded together with the main truss 1 and ring beam 7, and the seams of the roof are set symmetrically as shown in Figure 17. position, a total of four closing joints are set; the arrows in Figure 17 indicate the hoisting direction of the pressure ring beam 7.

步骤7:主桁架1卸载;Step 7: Main truss 1 is unloaded;

首先拆除支撑胎架2顶部的副撑205,然后采用分区分级循环卸载方式进行主桁架1的卸载:将每榀主桁架1看做一个轴,以图18(图18中的数字编号代表的是各各卸载区内的支撑胎架2,图18中的箭头表示卸载方向)中的A-2/36轴延长线(或A-2/18轴延长线)为分界线,划分两个卸载区(1区和2区),采用沙箱204排沙卸载法,两区分别从A-2/9轴、A-2/27轴中间段开始向两端同步对称分级循环卸载,保证主桁架1卸载后的变形均匀,每级卸载按预定下降释放量进行,且整个过程采用全站仪配合健康监测单位进行全程监控;First remove the auxiliary support 205 supporting the top of the tire frame 2, and then unload the main truss 1 by adopting a partitioned and graded cycle unloading method: each main truss 1 is regarded as an axis, and the numbers in Figure 18 represent The supporting tire frame 2 in each unloading area, the arrow in Figure 18 indicates the unloading direction), the A-2/36 axis extension line (or A-2/18 axis extension line) is the dividing line, dividing two unloading areas (Zone 1 and Zone 2), the sand box 204 sand discharge and unloading method is adopted, and the two zones start from the middle section of the A-2/9 axis and the A-2/27 axis to unload synchronously and symmetrically in stages at both ends, ensuring that the main truss 1 The deformation after unloading is uniform, and each level of unloading is carried out according to the predetermined drop release amount, and the whole process is monitored by a total station and a health monitoring unit;

步骤8:支撑胎架2拆除;Step 8: Remove the supporting tire frame 2;

待所有主桁架1均卸载完成后,自上而下依次拆除支撑胎架2,首先利用汽车吊拆除顶部转换平台和非标准节,拆除缆风绳203,然后利用汽车吊拆除2~3节标准,然后吊住第一节格构柱,切割第一节格构柱与混凝土基础201之间的连接后吊走第一节格构柱,最后破除混凝土基础201。After all the main trusses 1 are unloaded, remove the supporting frame 2 sequentially from top to bottom. Firstly, use a truck crane to remove the top conversion platform and non-standard joints, remove the cable wind rope 203, and then use a truck crane to remove 2 to 3 standard joints. , then hang the first section of the lattice column, cut the connection between the first section of the lattice column and the concrete foundation 201, lift the first section of the lattice column, and finally break the concrete foundation 201.

步骤9:局部杆件安装;Step 9: Partial member installation;

待支撑胎架2全部卸载完成后,再在屋盖四个转角处安装相应的环向次结构局部位置杆件,避免卸载过程中结构变形对环向次结构受力造成不利影响。After all the unloading of the support tire frame 2 is completed, the corresponding local position rods of the circumferential substructure are installed at the four corners of the roof to avoid adverse effects of structural deformation on the force of the circumferential substructure during the unloading process.

所述实施例为本发明的优选的实施方式,但本发明并不限于上述实施方式,在不背离本发明的实质内容的情况下,本领域技术人员能够做出的任何显而易见的改进、替换或变型均属于本发明的保护范围。The described embodiment is a preferred implementation of the present invention, but the present invention is not limited to the above-mentioned implementation, without departing from the essence of the present invention, any obvious improvement, replacement or modification that those skilled in the art can make Modifications all belong to the protection scope of the present invention.

Claims (10)

1. A hoisting construction method for a complex large-span steel roof is characterized by comprising the following steps:
step 1: building a BIM model of the steel truss roof and the supporting jig frame (2), simulating the whole process, and determining a hoisting scheme;
step 2: hoisting a supporting jig frame (2);
and step 3: assembling the main truss (1) in sections;
and 4, step 4: hoisting the drainage column (6) and the herringbone column (101) to the building main body structure;
and 5: sequentially hoisting the multi-truss structure assembled in the step (3) to a building main body structure, and supporting the multi-truss structure on a supporting jig frame (2) and a herringbone column (101);
step 6: hoisting and welding the compression ring beam (7) between the front ends of the adjacent main trusses (1), and then welding and installing a ring-shaped structure on the main trusses (1) and the compression ring beam (7);
and 7: unloading the main truss (1);
and 8: dismantling the support jig frame (2);
and step 9: and after the supporting jig frame (2) is completely dismantled, installing other local position rod pieces at the corner of the roof.
2. The hoisting construction method for the complex long-span steel roof as claimed in claim 1, wherein the specific process of the step 2 is as follows:
firstly, a concrete foundation (201) is poured on the ground at the installation position of a supporting jig frame (2), an embedded part is arranged at the top of the concrete foundation (201), after the strength of the concrete foundation (201) meets the requirement, a first section of lattice column is hoisted to the concrete foundation (201) by using a crawler crane and is welded and fixed with the embedded part (202), then 2-3 sections of lattice column standard sections and top non-standard sections are continuously hoisted at the top of the first section of lattice column, then a cable rope (203) is pulled, the cable rope (203) is arranged at 90 degrees, the anchoring point of the cable rope (203) is arranged on the node of a stand beam and a stand column of a building main body structure, and the anchoring point is formed by binding of steel wire ropes.
3. The hoisting construction method for the complex large-span steel roof as claimed in claim 2, wherein the top nonstandard sections are provided with conversion platforms, the conversion platforms are provided with sandboxes (204), and two sides of the sandboxes (204) are respectively provided with an auxiliary support (205); 4 wind-pulling ropes (203) are arranged on each supporting jig frame (2); and a temporary supporting jig frame (2) is arranged at the node of the end pressure ring beam (7) of each main truss (1).
4. The hoisting construction method for the complex large-span steel roof as claimed in claim 1, wherein in step 3, the main truss (1) is composed of 11 types of members, and is transported to the site for assembly after being processed by the factory, and comprises a herringbone post (101), a cast steel node (102), an upper end herringbone post (103), a truss tail chord (104) and a web member thereof, an upper chord (105) between the herringbone posts, an upper chord web member (106) between the herringbone posts, a main truss upper chord (107) and a web member thereof, an upper chord (108) and a web member thereof at the truss end, an end chord (109), a lower chord (110) and a lower chord (111), and during the assembly, span, theodolite, a leveling instrument and a total station are used for accurately measuring displacement, elevation and camber of the central line, and position deviation which may occur during the assembly is found and corrected in time, so as to ensure the overall accuracy.
5. The hoisting construction method of the complex large-span steel roof as claimed in claim 4, wherein the herringbone columns (101) are hoisted independently, and the specific assembling process of the other components of the main truss (1) is as follows:
step 3.1: welding a main upper chord (107) and a web member thereof, and an upper chord (108) at the end part of the truss and the web member thereof on the air ground of a construction site;
step 3.2: welding an assembling jig frame (3) on the air and ground of a construction site, then welding a cast steel node (102), a truss lower chord round rod (110) and an end head chord member (109) into a whole, and placing the whole on the assembling jig frame (3);
step 3.3: welding a group of upper herringbone columns (103) at one end of a cast steel node (102) close to the head part, welding and fixing a main upper chord (107) of the truss and the upper herringbone columns (103), welding and fixing an upper chord (108) at the end part of the truss and the main upper chord (107) of the truss, and finally welding and fixing the upper chord (108) at the end part of the truss and an end chord (109);
step 3.4: welding truss lower chord circular tube web members (111) between a truss main upper chord member (107) and a truss lower chord circular rod (110) and between a truss end upper chord member (108) and the truss lower chord circular rod (110);
step 3.5: welding another group of upper herringbone columns (103) at one end of the cast steel node (102) close to the tail part;
step 3.6: welding herringbone column upper chords (105) between the herringbone columns between the upper end herringbone columns (103), and welding herringbone column upper chord member web members (106) in the herringbone column upper chords (105);
step 3.7: welding truss tail chord members (104) and web members thereof at the outer sides of a group of upper end herringbone columns (103) close to the tail part of the main truss (1);
step 3.8: and (3) installing a pedestrian passageway (4) in the assembled main truss (1), then adopting a three-dimensional scanning robot to collect field assembly data in time and feed the field assembly data back to the BIM model for data comparison and analysis, and thus correcting the deviation of the component in time.
6. The hoisting construction method for the complex long-span steel roof as claimed in claim 1, wherein the specific process of the step 4 is as follows:
herringbone post (101) mounted position department on building subject structure sets up basin formula rubber support, then adopt the steel sheet to carry out interim welding with basin formula rubber support's upper bracket board and lower bolster board, then utilize crawler crane to hoist herringbone post (101) to basin formula rubber support's upper bracket board on, and fixed through welding mode, then adopt angle steel (5) to carry out interim support to herringbone post (101), then, utilize crawler crane to hoist drainage post (6) to the structural design position department of building subject and install fixedly.
7. The hoisting construction method for the complex large-span steel roof as claimed in claim 6, wherein the bottom of the drainage column (6) is welded with a drainage column ear plate (601), the drainage column ear plate (601) and the embedded ear plate on the main structure of the building are temporarily welded and fixed, and then the hot rolled section steel (602) is adopted to temporarily weld and fix the two sides of the drainage column ear plate (601).
8. The hoisting construction method for the complex long-span steel roof as claimed in claim 1, wherein the concrete process of the step 5 is as follows:
sequentially hoisting a plurality of main truss (1) structures assembled in the step (3) to a design position in a clockwise direction by using a crawler crane, ensuring that the front parts of the main trusses (1) are erected on a supporting jig frame (2), arranging the lower ends of the main trusses (1) at the tops of the herringbone columns (101) in a protruding mode, performing welding construction at the connecting nodes of the main trusses (1) and the herringbone columns (101), loosening hooks of the crane after one third of welding seams between the main trusses and the herringbone columns are filled, and then connecting the tail parts of the main trusses (1) with pin shaft connecting point ear plates of a building main structure; in the hoisting process, the end of the main truss (1), the connecting node of the pressure ring beam (7) and the main truss (1), and the connecting node of the main truss (1) and the herringbone column (101) are used as installation control points, and corresponding sensors are arranged for real-time monitoring.
9. The hoisting construction method for the complex long-span steel roof as claimed in claim 1, wherein the concrete process of the step 6 is as follows:
the steel roof plane is a central symmetrical structure, two symmetrical axes which are vertical to each other are arranged, the symmetrical axis with longer length is used as a long axis, the symmetrical axis with shorter length is used as a short axis, the press ring beam (7) is hoisted in a partitioning mode from the middle position of the long axis and the short axis to the corner of the adjacent roof, and the press ring beam is welded between the front ends of the adjacent main trusses (1);
after the pressure ring beam (7) is installed in place and welded, the radial secondary beam (8) and the annular secondary beam (9) are assembled into a whole on the ground, then the radial secondary beam (8) and the annular secondary beam (9) are integrally hoisted to the positions above the main truss (1) and the pressure ring beam (7), and the radial secondary beam and the annular secondary beam are welded and connected to the main truss (1) and the pressure ring beam (7);
and finally, the annular structures (the annular secondary beams and the radial secondary beams are combined) at the four corners of the roof are welded with the main truss (1) and the compression ring beams (7) in a folding mode to form four folding seams.
10. The hoisting construction method of the complex long-span steel roof according to claim 3, characterized in that in the step 7, when the main truss (1) is unloaded, the auxiliary support (205) at the top of the supporting jig frame (2) is firstly removed, then the unloading of the main truss (1) is carried out by adopting a sand discharging unloading method of a sandbox (204) based on a subarea grading circulation unloading principle, so as to ensure uniform deformation of the unloaded main truss (1), each stage of unloading is carried out according to a preset descending release amount, and the whole process is monitored by adopting a total station to cooperate with a health monitoring unit.
CN202211195657.9A 2022-09-29 2022-09-29 A kind of complex long-span steel roof hoisting construction method Active CN115467421B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211195657.9A CN115467421B (en) 2022-09-29 2022-09-29 A kind of complex long-span steel roof hoisting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211195657.9A CN115467421B (en) 2022-09-29 2022-09-29 A kind of complex long-span steel roof hoisting construction method

Publications (2)

Publication Number Publication Date
CN115467421A true CN115467421A (en) 2022-12-13
CN115467421B CN115467421B (en) 2023-09-22

Family

ID=84335457

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211195657.9A Active CN115467421B (en) 2022-09-29 2022-09-29 A kind of complex long-span steel roof hoisting construction method

Country Status (1)

Country Link
CN (1) CN115467421B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116163521A (en) * 2023-03-06 2023-05-26 陕西建工第六建设集团有限公司 Construction method of hundred-meter arc stone-like aluminum plate ribbon of truss lattice system
CN116623964A (en) * 2023-07-25 2023-08-22 北京城建集团有限责任公司 Reverse construction method of large-span variable-curvature roof
CN116695868A (en) * 2023-06-29 2023-09-05 山西建筑工程集团有限公司 Vertical face dislocation spiral building adopting pipe truss structure and construction method
CN116856544A (en) * 2023-07-24 2023-10-10 浙江中南绿建科技集团有限公司 A circumferential inclined truss structure and its installation method
CN116927419A (en) * 2023-06-11 2023-10-24 上海宝冶集团有限公司 A large-span giant ring truss and tension grid steel structure system and its construction method
CN117403904A (en) * 2023-11-15 2024-01-16 中建八局发展建设有限公司 A diagonal sliding construction method for ultra-tall and long-span roof steel trusses
CN117868514A (en) * 2024-02-22 2024-04-12 中建八局发展建设有限公司 A method for constructing a large-span steel structure for a factory building
CN118774390A (en) * 2024-05-22 2024-10-15 中建八局第三建设有限公司 A funnel-shaped roof adjustable drainage construction method
CN119062119A (en) * 2024-09-23 2024-12-03 北京城建集团有限责任公司 A method for constructing an assembled dome
CN120026766A (en) * 2025-04-23 2025-05-23 中建四局芜湖建设投资有限公司 A method for constructing a single-side tireless frame on the outer side of a ring truss

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120034187A (en) * 2012-03-21 2012-04-10 원대연 Constrution methoed for prestressed composite truss girder using steel truss member
CN106836498A (en) * 2016-12-28 2017-06-13 郑州工业应用技术学院 A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN110409837A (en) * 2019-07-11 2019-11-05 中建八局第三建设有限公司 A kind of large-span double-layer steel screen roof system sub-unit construction method for hanging
CN111501997A (en) * 2020-04-23 2020-08-07 贵州建工集团第四建筑工程有限责任公司 Steel truss structure construction method applied to stadium
CN112814248A (en) * 2021-02-06 2021-05-18 青岛腾远设计事务所有限公司 Spoke type wave cable membrane structure roof with three-dimensional outer ring truss
CN113463768A (en) * 2021-07-09 2021-10-01 南通华荣建设集团有限公司 120 m-span prestressed triangular steel pipe truss girder construction method
CN114439249A (en) * 2022-04-07 2022-05-06 中铁建工集团有限公司 Construction method for lifting large-span triangular truss through air swivel
CN216587766U (en) * 2021-09-26 2022-05-24 上海建科工程咨询有限公司 Hoisting facility and hoisting structure of large-span overhanging steel structural member

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120034187A (en) * 2012-03-21 2012-04-10 원대연 Constrution methoed for prestressed composite truss girder using steel truss member
CN106836498A (en) * 2016-12-28 2017-06-13 郑州工业应用技术学院 A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN110409837A (en) * 2019-07-11 2019-11-05 中建八局第三建设有限公司 A kind of large-span double-layer steel screen roof system sub-unit construction method for hanging
CN111501997A (en) * 2020-04-23 2020-08-07 贵州建工集团第四建筑工程有限责任公司 Steel truss structure construction method applied to stadium
CN112814248A (en) * 2021-02-06 2021-05-18 青岛腾远设计事务所有限公司 Spoke type wave cable membrane structure roof with three-dimensional outer ring truss
CN113463768A (en) * 2021-07-09 2021-10-01 南通华荣建设集团有限公司 120 m-span prestressed triangular steel pipe truss girder construction method
CN216587766U (en) * 2021-09-26 2022-05-24 上海建科工程咨询有限公司 Hoisting facility and hoisting structure of large-span overhanging steel structural member
CN114439249A (en) * 2022-04-07 2022-05-06 中铁建工集团有限公司 Construction method for lifting large-span triangular truss through air swivel

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116163521A (en) * 2023-03-06 2023-05-26 陕西建工第六建设集团有限公司 Construction method of hundred-meter arc stone-like aluminum plate ribbon of truss lattice system
CN116927419A (en) * 2023-06-11 2023-10-24 上海宝冶集团有限公司 A large-span giant ring truss and tension grid steel structure system and its construction method
CN116695868A (en) * 2023-06-29 2023-09-05 山西建筑工程集团有限公司 Vertical face dislocation spiral building adopting pipe truss structure and construction method
CN116695868B (en) * 2023-06-29 2023-11-17 山西建筑工程集团有限公司 Vertical face dislocation spiral building adopting pipe truss structure and construction method
CN116856544A (en) * 2023-07-24 2023-10-10 浙江中南绿建科技集团有限公司 A circumferential inclined truss structure and its installation method
CN116623964A (en) * 2023-07-25 2023-08-22 北京城建集团有限责任公司 Reverse construction method of large-span variable-curvature roof
CN116623964B (en) * 2023-07-25 2023-11-28 北京城建集团有限责任公司 Reverse construction method of large-span variable-curvature roof
CN117403904A (en) * 2023-11-15 2024-01-16 中建八局发展建设有限公司 A diagonal sliding construction method for ultra-tall and long-span roof steel trusses
CN117868514A (en) * 2024-02-22 2024-04-12 中建八局发展建设有限公司 A method for constructing a large-span steel structure for a factory building
CN118774390A (en) * 2024-05-22 2024-10-15 中建八局第三建设有限公司 A funnel-shaped roof adjustable drainage construction method
CN119062119A (en) * 2024-09-23 2024-12-03 北京城建集团有限责任公司 A method for constructing an assembled dome
CN120026766A (en) * 2025-04-23 2025-05-23 中建四局芜湖建设投资有限公司 A method for constructing a single-side tireless frame on the outer side of a ring truss

Also Published As

Publication number Publication date
CN115467421B (en) 2023-09-22

Similar Documents

Publication Publication Date Title
CN115467421A (en) A hoisting construction method for complex long-span steel roof
CN100503977C (en) Tower column of cable-stayed bridge and its construction method
CN111501997A (en) Steel truss structure construction method applied to stadium
CN110004832B (en) Large-span cantilever truss type bent cap bracket system and construction method
CN102154988B (en) Arch-after-girder construction method of large-span steel box tacked arch bridge
CN114214920B (en) Large-span double-layer steel truss arch bridge and its construction method
CN105568854B (en) Shaped form fish-bellied type cast-in-situ steel reinforced concrete box girder construction method waterborne
CN216891927U (en) Large-span double-layer combined construction steel truss arch bridge
CN114482280B (en) Hexagonal section assembled annular supporting system and installation method thereof
CN110373988A (en) The big segment steel truss girder and manufacturing technology of a kind of band pair purlin
CN114718325A (en) Stadium hyperboloid cantilever space pipe truss construction method
CN209941511U (en) Supporting device for high-altitude folding of bridge steel box girder by section hoisting
CN111254836A (en) Site assembling and bridge girder erection machine erecting construction method for large-span steel-concrete composite beam in mountainous area
CN107882328A (en) The construction method of large span steel truss overhung construction
CN111663457A (en) Assembled module, modular construction platform and method, bridge pier construction method
CN116837967A (en) Construction method of large-span cable-stayed truss structure
CN210066504U (en) Large-span cantilever truss type bent cap support system
CN102767282B (en) Prefabricated high formwork construction method for cantilever beam of oversized special-shaped conversion layer
CN114908968A (en) Construction method of large-span fish belly type pipe truss in gymnasium
CN115787996A (en) Overhung construction method and overhung frame for super-high building
CN113931054B (en) Manufacturing method of super large eccentric half-width steel-concrete composite box girder
CN102877657A (en) Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method
CN114351584A (en) Special-shaped steel ladle concrete upper tower column and construction method thereof
CN116122579B (en) Hoisting method for bidirectional bending dome bracket
CN109267439B (en) Efficient and stable three-layer viaduct and construction process thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant