CN111535182A - Tubular bridge girder erection method - Google Patents

Tubular bridge girder erection method Download PDF

Info

Publication number
CN111535182A
CN111535182A CN202010242721.9A CN202010242721A CN111535182A CN 111535182 A CN111535182 A CN 111535182A CN 202010242721 A CN202010242721 A CN 202010242721A CN 111535182 A CN111535182 A CN 111535182A
Authority
CN
China
Prior art keywords
construction
pipe section
section
gantry crane
bridge girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010242721.9A
Other languages
Chinese (zh)
Inventor
周俊龙
李飞
高璞
谢朋林
马慧杰
强伟亮
宋子文
张强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN202010242721.9A priority Critical patent/CN111535182A/en
Publication of CN111535182A publication Critical patent/CN111535182A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a tubular bridge girder erection method, which comprises the following specific steps: prefabricating pipe sections, namely dividing each section into a plurality of construction units, dividing each construction unit into a lower pipe section, an upper pipe section and a folded pipe section, prefabricating in a factory and transporting to a construction site; constructing a foundation; constructing a construction unit, and sequentially hoisting a lower pipe section, an upper pipe section and a folded pipe section; and (5) constructing the whole section, repeating the step three until all construction units of the section are constructed, dismantling the temporary support columns and the support frames on the beams, and finishing construction of the section. The construction method has the advantages that each pipe section is convenient to process and transport, compared with field assembly, an assembly process is not needed, the construction requirement of the tubular bridge girder can be met, the method makes full use of the upper space of the constructed part for construction, the construction floor area is small, the construction speed is high, the method is suitable for the construction of the bridge girder with a closed structure with similar characteristics, and the popularization value is high.

Description

Tubular bridge girder erection method
Technical Field
The invention relates to the technical field of bridge construction methods, in particular to a tubular bridge girder erection method.
Background
At present, bridge structures exist more as urban landmarks, so that the requirements on the appearance of bridge designs are higher and higher in consideration of the novelty and originality of the structures. The design of various special-shaped bridges enables the bridge construction process to be adaptively changed according to different bridge configurations.
For a bridge with a tubular structure, the whole bearing main beam structure of the bridge is designed into a tubular shape, and due to the large diameter of the bearing main beam structure, the bearing main beam structure is difficult to process and transport by adopting a prefabrication method, but the field assembly method is lack of the existing process for reference construction, so that the existing process method is difficult to meet the construction requirement of the tubular bridge main beam.
Disclosure of Invention
The invention aims to solve the defects of the prior art and provides a tubular bridge girder erection method.
In order to achieve the purpose, the invention adopts the following technical scheme:
a tubular bridge girder erection method comprises the following specific steps:
step one, prefabricating a pipe section,
dividing the tubular bridge girder of each section into a plurality of construction units along the axial direction, then dividing each construction unit into a lower pipe section, an upper pipe section and a folded pipe section from bottom to top in sequence, prefabricating the three pipe sections in a factory and transporting the three pipe sections to a construction site;
step two, constructing a foundation,
constructing bridge substructure, constructing concrete upright column foundations between two adjacent bridge substructure, building temporary support upright columns on the concrete upright column foundations, constructing gantry crane foundations along the full length of the bridge extension, and installing a gantry crane on the gantry crane foundations;
step three, constructing a construction unit,
hoisting a lower pipe section to a pier column and/or a temporary support column of a bridge lower part structure by using a gantry crane, arranging cranes on the lower pipe section after hoisting is finished, erecting upper beam support frames for supporting upper pipe sections on two sides of the lower pipe section by using the cranes, matching the upper parts of the upper beam support frames with the inner side lines of the upper pipe sections, hoisting the upper pipe sections by using the upper beam support frames, and hoisting the folded pipe sections by using the gantry crane after installation;
step four, constructing the whole section,
and repeating the third step from one end of the section until all the construction units of the section are completely constructed, dismantling the temporary support columns and the support frames on the beams, and finishing the construction of the section.
Furthermore, the upper pipe sections on two sides of the construction unit are four equal-length ones.
Furthermore, the gantry crane comprises a first gantry crane and a second gantry crane, the first gantry crane is used for hoisting the lower pipe section, and the second gantry crane is used for hoisting the upper pipe section and the closed pipe section.
Furthermore, when the upper support frame of the beam is erected in the third step, the gantry crane can hoist the lower pipe section of the next construction unit.
Further, the temporary support columns are arranged at intervals or continuously according to the length of the construction unit.
Furthermore, the supporting points at the top of the support frame on the beam are matched with the number and the shape of the upper pipe sections.
Furthermore, the temporary support columns and the support frames on the beams are of truss structures.
The invention has the beneficial effects that: the construction method has the advantages that each pipe section is convenient to process and transport, compared with field assembly, an assembly process is not needed, the construction requirement of the tubular bridge girder can be met, the method makes full use of the upper space of the constructed part for construction, the construction floor area is small, the construction speed is high, the method is suitable for the construction of the bridge girder with a closed structure with similar characteristics, and the popularization value is high.
Drawings
FIG. 1 is a schematic view of a tubular bridge segment division;
FIG. 2 is a schematic view of the construction of a lower pipe section;
FIG. 3 is a schematic view of the construction of the support frame on the beam;
FIG. 4 is a schematic representation of upper pipe section construction;
FIG. 5 is a schematic view of a closed pipe section construction;
FIG. 6 is a schematic view showing the distribution of the cranes and the gantry cranes;
in the figure: 1-lower structure; 2-concrete column foundation; 3-temporary support columns; 4-gantry crane foundation; 5, a first gantry crane; 6-gantry crane II; 7-lower pipe section; 8-upper pipe section; 9-folding the pipe section; 10-a crane; 11-beam upper support frame;
the following detailed description will be made in conjunction with embodiments of the present invention with reference to the accompanying drawings.
Detailed Description
The invention is further illustrated by the following examples:
as shown in the figure, the tubular bridge girder erection method comprises the following specific steps:
step one, prefabricating a pipe section,
dividing the tubular bridge girder of each section into a plurality of construction units along the axial direction, then dividing each construction unit into a lower pipe section 7, an upper pipe section 8 and a folding pipe section 9 from bottom to top in sequence, prefabricating the three pipe sections in a factory and transporting the three pipe sections to a construction site;
step two, constructing a foundation,
constructing bridge substructure 1, constructing concrete upright column foundations 2 between two adjacent bridge substructure 1, erecting temporary support upright columns 3 on the concrete upright column foundations 2, constructing a gantry crane foundation 4 along the full length of the bridge in the extending direction, and installing a gantry crane on the gantry crane foundation 4;
step three, constructing a construction unit,
hoisting a lower pipe section 7 to a pier stud and/or a temporary support column 3 of a bridge substructure 1 by using a gantry crane, arranging cranes 10 on the lower pipe section 7 after hoisting is finished, erecting upper beam support frames 11 for supporting an upper pipe section 8 on two sides of the lower pipe section 7 by using the cranes 10, matching the upper parts of the upper beam support frames 11 with the inner side line shape of the upper pipe section 8, hoisting the upper pipe section 8 by using the upper beam support frames 11, and hoisting a folded pipe section 9 by using the gantry crane after installation;
step four, constructing the whole section,
and (5) repeating the third step from one end of the section until all construction units of the section are constructed, dismantling the temporary support upright posts 3 and the support frames 11 on the beams, and finishing construction of the section.
Furthermore, the upper pipe sections 8 on both sides of the construction unit are four equal-length ones.
Further, the gantry crane comprises a first gantry crane 5 and a second gantry crane 6, wherein the first gantry crane 5 is used for hoisting a lower pipe section 7, and the second gantry crane 6 is used for hoisting an upper pipe section 8 and a folded pipe section 9.
Further, when the upper support frame 11 of the beam is erected in the third step, the first gantry crane 5 can hoist the lower pipe section 7 of the next construction unit.
Further, the temporary support columns 3 are arranged at intervals or continuously according to the length of the construction unit.
Furthermore, the pivot of the top of the beam upper support frame 11 is matched with the number and shape of the upper pipe section 8.
Further, the temporary support columns 3 and the beam upper support frames 11 are all truss structures.
The construction method has the advantages that each pipe section is convenient to process and transport, compared with field assembly, an assembly process is not needed, the construction requirement of the tubular bridge girder can be met, the method makes full use of the upper space of the constructed part for construction, the construction floor area is small, the construction speed is high, the method is suitable for the construction of the bridge girder with a closed structure with similar characteristics, and certain popularization value is realized.
The present invention has been described in connection with the specific embodiments, and it is obvious that the specific implementation of the present invention is not limited by the above-mentioned manner, and it is within the protection scope of the present invention as long as various modifications are made by using the method concept and technical solution of the present invention, or the present invention is directly applied to other occasions without modification.

Claims (7)

1. A tubular bridge girder erection method is characterized by comprising the following specific steps:
step one, prefabricating a pipe section,
dividing the tubular bridge girder of each section into a plurality of construction units along the axial direction, then dividing each construction unit into a lower pipe section (7), an upper pipe section (8) and a folding pipe section (9) from bottom to top in sequence, prefabricating the three pipe sections in a factory and transporting the three pipe sections to a construction site;
step two, constructing a foundation,
constructing bridge lower structures (1), constructing concrete upright post foundations (2) between two adjacent bridge lower structures (1), erecting temporary support upright posts (3) on the concrete upright post foundations (2), constructing a gantry crane foundation (4) along the whole length of the bridge in the extending direction, and installing a gantry crane on the gantry crane foundation (4);
step three, constructing a construction unit,
hoisting a lower pipe section (7) to a pier column and/or a temporary support column (3) of a bridge lower part structure (1) by using a gantry crane, arranging cranes (10) on the lower pipe section (7) after hoisting is finished, erecting upper beam support frames (11) for supporting upper pipe sections (8) on two sides of the lower pipe section (7) by using the cranes (10), matching the upper parts of the upper beam support frames (11) with the inner side lines of the upper pipe sections (8), hoisting the upper pipe sections (8) by using the upper beam support frames (11), and hoisting closed pipe sections (9) by using the gantry crane after installation;
step four, constructing the whole section,
and (5) repeating the third step from one end of the section until all construction units of the section are completely constructed, dismantling the temporary support columns (3) and the support frames (11) on the beams, and completing construction of the section.
2. Method for erecting a tubular bridge girder according to claim 1, wherein the upper pipe sections (8) on both sides of the construction unit are four equal-length ones.
3. The tubular bridge girder erection method according to claim 1, wherein the gantry crane comprises a first gantry crane (5) and a second gantry crane (6), the first gantry crane (5) is used for hoisting the lower pipe section (7), and the second gantry crane (6) is used for hoisting the upper pipe section (8) and the folded pipe section (9).
4. The tubular bridge girder erection method according to claim 3, wherein the hoisting of the lower pipe section (7) of the next construction unit is performed by one gantry crane (5) when the upper support frame (11) of the girder is erected in the third step.
5. The tubular bridge girder erection method according to claim 1, wherein the temporary support columns (3) are arranged at intervals or continuously according to the length of the construction unit.
6. Method for tubular bridge girder erection according to claim 1, characterized in that the fulcrums at the top of the upper support frame (11) of the girder are arranged in a number and shape fit with the upper pipe sections (8).
7. The tubular bridge girder erection method according to claim 1, wherein the temporary support columns (3) and the beam upper support frames (11) are of a truss structure.
CN202010242721.9A 2020-03-31 2020-03-31 Tubular bridge girder erection method Pending CN111535182A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010242721.9A CN111535182A (en) 2020-03-31 2020-03-31 Tubular bridge girder erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010242721.9A CN111535182A (en) 2020-03-31 2020-03-31 Tubular bridge girder erection method

Publications (1)

Publication Number Publication Date
CN111535182A true CN111535182A (en) 2020-08-14

Family

ID=71978710

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010242721.9A Pending CN111535182A (en) 2020-03-31 2020-03-31 Tubular bridge girder erection method

Country Status (1)

Country Link
CN (1) CN111535182A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113481856A (en) * 2021-07-08 2021-10-08 中国建筑第六工程局有限公司 Annular bridge tower jacking construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101001063B1 (en) * 2010-05-06 2010-12-14 주식회사 유신 The gurder to use steel pipe for bridge
CN102146660A (en) * 2011-02-25 2011-08-10 中交四航局第一工程有限公司 Installation methods of cross-arch-rib gantry crane and butterfly arch bridge space structure system
CN104404862A (en) * 2014-11-28 2015-03-11 林同棪国际工程咨询(中国)有限公司 Steel pipe net frame pedestrian pipeline bridge
CN106592406A (en) * 2016-12-30 2017-04-26 河南省交通规划设计研究院股份有限公司 Through tied arch bridge and construction method thereof
CN107130509A (en) * 2017-06-26 2017-09-05 厦门中平公路勘察设计院有限公司 A kind of different formed steel construction overpass
CN108867391A (en) * 2018-07-20 2018-11-23 中国水利水电第七工程局有限公司 A kind of construction of tubular arch and paving frame parallel operations construction method
CN110820517A (en) * 2019-11-25 2020-02-21 西南交通大学 Assembled railway tubular beam
CN110847053A (en) * 2019-11-29 2020-02-28 中铁二院工程集团有限责任公司 Construction method of vacuum magnetic suspension prefabricated assembly type pipeline beam

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101001063B1 (en) * 2010-05-06 2010-12-14 주식회사 유신 The gurder to use steel pipe for bridge
CN102146660A (en) * 2011-02-25 2011-08-10 中交四航局第一工程有限公司 Installation methods of cross-arch-rib gantry crane and butterfly arch bridge space structure system
CN104404862A (en) * 2014-11-28 2015-03-11 林同棪国际工程咨询(中国)有限公司 Steel pipe net frame pedestrian pipeline bridge
CN106592406A (en) * 2016-12-30 2017-04-26 河南省交通规划设计研究院股份有限公司 Through tied arch bridge and construction method thereof
CN107130509A (en) * 2017-06-26 2017-09-05 厦门中平公路勘察设计院有限公司 A kind of different formed steel construction overpass
CN108867391A (en) * 2018-07-20 2018-11-23 中国水利水电第七工程局有限公司 A kind of construction of tubular arch and paving frame parallel operations construction method
CN110820517A (en) * 2019-11-25 2020-02-21 西南交通大学 Assembled railway tubular beam
CN110847053A (en) * 2019-11-29 2020-02-28 中铁二院工程集团有限责任公司 Construction method of vacuum magnetic suspension prefabricated assembly type pipeline beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113481856A (en) * 2021-07-08 2021-10-08 中国建筑第六工程局有限公司 Annular bridge tower jacking construction method

Similar Documents

Publication Publication Date Title
CN112482577B (en) Large-span space chord supporting wheel spoke type truss structure system and construction method
CN208430687U (en) Self-anchored type suspended-cable structure support construction and system
CN110670722A (en) Implementation method of beam-column connecting node of fabricated building
CN113047440A (en) Double-layer radiation beam string structure with wind-resistant cable and construction method thereof
CN114214920B (en) Large-span double-layer built-up steel truss arch bridge and construction method thereof
CN111535182A (en) Tubular bridge girder erection method
US20240200321A1 (en) Long-Span Corridor Comprising Two Sets Of Floor Cantilevered Inclined Trusses Combined With Suspension Cable Bearing And Assembly Method Thereof
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
CN216920677U (en) First-layer supporting structure of large rockery outer package
CN112609586B (en) Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder
CN109469257B (en) Large-span gradual-change polygonal cross section parallel truss roof and construction method
CN111827678A (en) Method for hoisting truss steel structure at top of silo
CN114482381B (en) Method for installing parts for dome steel structure
CN220978747U (en) High-altitude cantilever structure formwork construction platform easy to assemble and disassemble and capable of being turned
CN220845151U (en) Lifting device for be used for large-span steel construction roofing
CN114673074B (en) Multipurpose standard H-shaped steel tower of cable lifting system
CN115199051B (en) Construction method of football field large-span awning
CN214089440U (en) Large-span stiff skeleton concrete arch bridge accurate assembling construction structure
CN212896821U (en) Arch coupon steel structure
CN212317148U (en) Assembled frame concrete building connected node structure
CN116556570B (en) Construction method of combined high-clearance large-span variable-section roof structure
CN216239254U (en) Steel pipe truss superimposed sheet construction braced system
CN114790693B (en) Construction method of large-span river-crossing steel truss bridge structure
CN113668688B (en) Three-layer overhanging steel structure with quick construction and land saving and construction method thereof
CN116427545B (en) Large-span overhanging roof with compact structure and difficult overturning and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200814