CN114790693B - Construction method of large-span river-crossing steel truss bridge structure - Google Patents
Construction method of large-span river-crossing steel truss bridge structure Download PDFInfo
- Publication number
- CN114790693B CN114790693B CN202210429944.5A CN202210429944A CN114790693B CN 114790693 B CN114790693 B CN 114790693B CN 202210429944 A CN202210429944 A CN 202210429944A CN 114790693 B CN114790693 B CN 114790693B
- Authority
- CN
- China
- Prior art keywords
- truss
- section
- box girder
- river
- span
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D6/00—Truss-type bridges
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/28—Prefabricated piles made of steel or other metals
- E02D5/285—Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Bridges Or Land Bridges (AREA)
Description
技术领域Technical Field
本发明涉及建筑施工技术领域,具体涉及一种大跨度跨河钢桁架桥结构的施工方法。The invention relates to the technical field of building construction, and in particular to a construction method of a large-span river-spanning steel truss bridge structure.
背景技术Background technique
对于大跨度的跨河钢桁架桥结构施工,通常采用大型吊装机械整体吊装或使用专业的架桥机设备施工。采取大型吊装机械吊装,一般是在各桁架段现场拼装后,使用大型起重机械站在河岸边或已完结构上吊装,此方法需有较大的构件拼装场地,对起重机械站位点的结构承载力要求高,若是站在已完结构上,结构需受力验算及回顶加固。采用架桥机设备施工,需选用专用的架桥机设备,架桥机安装和拆卸周期长,技术难度大,对操作人员要求高,在一定程度延长了工期,增加了施工成本。如上所述的常规施工方法,对施工工况要求较高,不利于缩短施工工期,成本偏高,适用范围受限。For the construction of large-span steel truss bridge structures across rivers, large hoisting machinery is usually used for overall hoisting or professional bridge-building equipment is used for construction. When large hoisting machinery is used for hoisting, generally after the truss sections are assembled on site, large hoisting machinery is used to stand on the river bank or on the completed structure for hoisting. This method requires a large component assembly site and has high requirements for the structural bearing capacity of the hoisting machinery station. If it stands on a completed structure, the structure needs to be force-checked and top-back reinforced. When using bridge-building equipment for construction, special bridge-building equipment must be selected. The installation and disassembly cycle of the bridge-building machine is long, the technical difficulty is high, and the requirements for operators are high. To a certain extent, the construction period is extended and the construction cost is increased. The conventional construction method mentioned above has high requirements for construction conditions, is not conducive to shortening the construction period, has high costs, and has a limited scope of application.
公开于该背景技术部分的信息仅仅旨在增加对本发明的总体背景的理解,而不应当被视为承认或以任何形式暗示该信息构成已为本领域一般技术人员所公知的现有技术。The information disclosed in this background technology section is only intended to enhance the understanding of the overall background of the invention and should not be regarded as an acknowledgment or any form of suggestion that the information constitutes the prior art already known to a person skilled in the art.
发明内容Summary of the invention
为克服现有技术所存在的缺陷,现提供一种大跨度跨河钢桁架桥结构的施工方法,以解决大跨度的跨河钢桁架桥施工采用常规施工方法施工存在工期长,成本高的问题。In order to overcome the defects of the prior art, a construction method of a large-span river-crossing steel truss bridge structure is provided to solve the problems of long construction period and high cost in the construction of large-span river-crossing steel truss bridges using conventional construction methods.
为实现上述目的,提供一种大跨度跨河钢桁架桥结构的施工方法,包括以下步骤:To achieve the above object, a construction method of a large-span river-crossing steel truss bridge structure is provided, comprising the following steps:
将大跨度跨河钢桁架桥结构划分为两临岸段和两跨中段;Divide the long-span river-crossing steel truss bridge structure into two bank-facing sections and two span middle sections;
于所述河道的中间打设四钢管桩,使得四所述钢管桩呈矩阵式排布;Driving four steel pipe piles in the middle of the river channel so that the four steel pipe piles are arranged in a matrix;
于相邻的两所述钢管桩的上部之间连接拉结架;Connecting a tie frame between the upper parts of two adjacent steel pipe piles;
分别于所述大跨度跨河钢桁架桥结构的架设方向的相对两侧的两所述钢管桩铺设顶梁;Laying top beams on two of the steel pipe piles on opposite sides of the erection direction of the large-span river-crossing steel truss bridge structure;
于所述架设方向的相对两侧的所述顶梁铺设贝雷支撑架;Laying Bailey support frames on the top beams on opposite sides of the erection direction;
于所述贝雷支撑架的相对两侧铺设支承型钢以形成水上支撑平台;Laying supporting steel sections on opposite sides of the Bailey support frame to form an above-water support platform;
于河道的两岸分别浇筑墩柱;Cast piers on both sides of the river;
于所述墩柱拼装形成临岸段,使得所述两岸的墩柱上的临岸段朝向所述水上支撑平台延伸设置;Assembling the piers to form shore sections, so that the shore sections on the piers on both sides extend toward the above-water support platform;
于所述临岸段上铺设基板,使得所述基板沿所述临岸段的长度方向设置;Laying a base plate on the bank section so that the base plate is arranged along the length direction of the bank section;
将吊装机械行驶于所述基板上以吊装所述跨中段的构件;Driving a lifting machine on the base plate to lift the components of the mid-span section;
于所述水上支撑平台的相对两侧与所述两岸的临岸段之间分别拼装形成所述跨中段;The mid-span section is respectively assembled between the opposite sides of the above-water support platform and the shore sections of the two banks;
合拢两所述跨中段以形成所述大跨度跨河钢桁架桥结构并拆除所述水上支撑平台。The two mid-span sections are closed to form the long-span river-crossing steel truss bridge structure and the above-water support platform is removed.
进一步的,所述临岸段包括桁架下弦箱梁、桁架上弦箱梁、腹杆、剪刀撑和桁架外悬挑梁,所述拼装所述临岸段的步骤包括:Furthermore, the bank section includes a truss lower chord box girder, a truss upper chord box girder, a web member, a scissors brace and a truss outer cantilever beam, and the steps of assembling the bank section include:
将所述桁架下弦箱梁吊装并安装至所述墩柱;Hoisting and installing the truss lower chord box girder to the pier;
于所述桁架下弦箱梁的相对两侧分别竖向安装多根所述腹杆,多根所述腹杆沿所述桁架下弦箱梁的长度方向设置;A plurality of web members are respectively vertically installed on opposite sides of the truss lower chord box girder, and the plurality of web members are arranged along the length direction of the truss lower chord box girder;
将所述桁架上弦箱梁安装于多根所述腹杆;Installing the truss upper chord box girder on the plurality of web members;
将所述剪刀撑安装于所述桁架上弦箱梁和所述桁架下弦箱梁之间;Installing the scissors brace between the truss upper chord box girder and the truss lower chord box girder;
将所述桁架外悬挑梁安装于所述桁架上弦箱梁和所述桁架下弦箱梁的外侧以形成所述临岸段。The truss outer cantilever beam is installed on the outer sides of the truss upper chord box beam and the truss lower chord box beam to form the bank section.
进一步的,所述于河道的两岸分别浇筑墩柱的步骤包括:Furthermore, the steps of respectively casting piers on both sides of the river channel include:
于所述两岸绑扎墩柱钢筋笼;Tie the pier column reinforcement cages on both banks;
于所述墩柱钢筋笼的外部安装墩柱模板;Installing a pier column formwork outside the pier column reinforcement cage;
于所述墩柱钢筋笼的顶部安装预埋件;Installing embedded parts on the top of the pier column reinforcement cage;
于所述墩柱模板内浇筑混凝土以形成所述墩柱;pouring concrete in the pier column formwork to form the pier column;
在所述墩柱的强度符合设计要求后,于所述墩柱的顶部的预埋件安放转换支座。After the strength of the pier column meets the design requirements, a conversion bearing is placed on the embedded part on the top of the pier column.
进一步的,所述贝雷支撑架的长度大于所述跨中段的宽度。Furthermore, the length of the Bailey support frame is greater than the width of the mid-span section.
进一步的,四所述钢管桩分别设置于所述跨中段的外侧。Furthermore, the four steel pipe piles are respectively arranged on the outer sides of the mid-span section.
本发明的有益效果在于,本发明的大跨度跨河钢桁架桥结构的施工方法,解决了受工况限制无法使用大型吊装机械吊装的难题,相较于复杂程度高的架桥机施工,节省了成本,缩短了工期。而且,借助于钢管桩构成水上支撑平台作为临时支撑,所需建造设备简单,适用性强,支撑平台可以提前建造,有利于工期保证,钢管桩可重复使用,经济性好。The beneficial effect of the present invention is that the construction method of the large-span river-crossing steel truss bridge structure of the present invention solves the problem that large-scale lifting machinery cannot be used for lifting due to working conditions. Compared with the construction of a highly complex bridge erection machine, it saves costs and shortens the construction period. Moreover, by using steel pipe piles to form an above-water support platform as a temporary support, the required construction equipment is simple and has strong applicability. The support platform can be built in advance, which is conducive to ensuring the construction period. The steel pipe piles can be reused and have good economic efficiency.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
通过阅读参照以下附图所作的对非限制性实施例所作的详细描述,本申请的其它特征、目的和优点将会变得更明显:Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:
图1为本发明实施例的大跨度跨河钢桁架桥结构的结构示意图。FIG1 is a schematic structural diagram of a long-span river-crossing steel truss bridge structure according to an embodiment of the present invention.
图2为本发明实施例的大跨度跨河钢桁架桥结构的跨中段的合拢部位的结构示意图。FIG2 is a schematic structural diagram of a closure portion of a mid-span section of a long-span river-crossing steel truss bridge structure according to an embodiment of the present invention.
图3为本发明实施例的水上支撑平台的结构示意图。FIG. 3 is a schematic structural diagram of an above-water support platform according to an embodiment of the present invention.
图4为本发明实施例的贝雷支撑架的结构示意图。FIG. 4 is a schematic structural diagram of a Bailey support frame according to an embodiment of the present invention.
具体实施方式Detailed ways
下面结合附图和实施例对本申请作进一步的详细说明。可以理解的是,此处所描述的具体实施例仅仅用于解释相关发明,而非对该发明的限定。另外还需要说明的是,为了便于描述,附图中仅示出了与发明相关的部分。The present application will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant inventions, rather than to limit the inventions. It should also be noted that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.
需要说明的是,在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。下面将参考附图并结合实施例来详细说明本申请。It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
参照图1至图4所示,本发明提供了一种大跨度跨河钢桁架桥结构的施工方法,其中,大跨度跨河钢桁架桥结构包括桁架下弦箱梁11、桁架上弦箱梁12、腹杆13、剪刀撑14和桁架外悬挑梁15。1 to 4 , the present invention provides a construction method for a large-span river-span steel truss bridge structure, wherein the large-span river-span steel truss bridge structure includes a truss lower chord box girder 11, a truss upper chord box girder 12, a web member 13, a scissors brace 14 and a truss outer cantilever beam 15.
具体的,参阅图1和图2,桁架上弦箱梁12与桁架下弦箱梁11同向设置,且桁架上弦箱梁12设置于桁架下弦箱梁11的上方。桁架上弦箱梁12与桁架下弦箱梁11之间连接有多根腹杆13。此外,桁架上弦箱梁12与桁架下弦箱梁11之间还连接有剪刀撑14。在桁架上弦箱梁12与桁架下弦箱梁11的外侧连接有桁架外悬挑梁15。桁架外悬挑梁15的上部连接于桁架上弦箱梁12,桁架外悬挑梁15的下部连接于桁架下弦箱梁11。参阅图2,大跨度跨河钢桁架桥结构的横截面整体呈倒梯形。Specifically, referring to Figures 1 and 2, the truss upper chord box girder 12 is arranged in the same direction as the truss lower chord box girder 11, and the truss upper chord box girder 12 is arranged above the truss lower chord box girder 11. A plurality of web members 13 are connected between the truss upper chord box girder 12 and the truss lower chord box girder 11. In addition, a scissor brace 14 is also connected between the truss upper chord box girder 12 and the truss lower chord box girder 11. A truss outer cantilever beam 15 is connected to the outer side of the truss upper chord box girder 12 and the truss lower chord box girder 11. The upper part of the truss outer cantilever beam 15 is connected to the truss upper chord box girder 12, and the lower part of the truss outer cantilever beam 15 is connected to the truss lower chord box girder 11. Referring to Figure 2, the cross-section of the large-span steel truss bridge structure across the river is generally in an inverted trapezoidal shape.
本发明的大跨度跨河钢桁架桥结构的施工方法,包括以下步骤:The construction method of the long-span river-spanning steel truss bridge structure of the present invention comprises the following steps:
S1:将大跨度跨河钢桁架桥结构划分为两临岸段和两跨中段1。S1: Divide the long-span river-crossing steel truss bridge structure into two bank-side sections and two span middle sections1.
在本实施例中,大跨度跨河钢桁架桥结构在其长度方向上划分为四段,包括两临岸段和两跨中段1。临岸段与跨中段1的结构相同。两段跨中段的一端同轴连接,临岸段连接于跨中段的另一端。其中,跨中段设置于河道的水面上,临岸段设置于河道的岸边。In this embodiment, the long-span steel truss bridge structure across the river is divided into four sections in the length direction, including two bank sections and two mid-span sections 1. The bank section has the same structure as the mid-span section 1. One end of the two mid-span sections is coaxially connected, and the bank section is connected to the other end of the mid-span section. The mid-span section is set on the water surface of the river channel, and the bank section is set on the bank of the river channel.
S2:于河道的中间打设四钢管桩,使得四钢管桩呈矩阵式排布。S2: Four steel pipe piles are driven in the middle of the river channel so that the four steel pipe piles are arranged in a matrix.
在本实施例中,先于河道中间,即两跨中段合拢位置,打设四根钢管桩。四钢管桩呈矩阵式排布。四根钢管桩两两一组,两组钢管桩分别设置于大跨度跨河钢桁架桥的架设路线的相对两侧,且两组钢管桩之间的距离大于大跨度跨河钢桁架桥的宽度。后续在拆除时,能避免别桥梁遮挡。In this embodiment, four steel pipe piles are first driven in the middle of the river channel, that is, at the position where the two spans are closed. The four steel pipe piles are arranged in a matrix. The four steel pipe piles are arranged in groups of two, and the two groups of steel pipe piles are respectively arranged on opposite sides of the erection route of the long-span steel truss bridge across the river, and the distance between the two groups of steel pipe piles is greater than the width of the long-span steel truss bridge across the river. When dismantling later, it can avoid being blocked by other bridges.
S3:于相邻的两钢管桩的上部之间连接拉结架。S3: Connect a tie frame between the upper parts of two adjacent steel pipe piles.
拉结架包括两根横杆和斜撑杆。其中,两根横杆连接于相邻的两根钢管桩的上部之间。斜撑杆斜向连接于相邻的两根钢管桩之间,且,斜撑杆设置于两根横杆之间。The tie frame includes two cross bars and an oblique brace, wherein the two cross bars are connected between the upper parts of two adjacent steel pipe piles, the oblique brace is obliquely connected between the two adjacent steel pipe piles, and the oblique brace is arranged between the two cross bars.
在本实施例中,斜撑杆的端部连接于横杆与钢管桩的交汇处。In this embodiment, the ends of the diagonal braces are connected to the intersection of the crossbar and the steel pipe pile.
S4:分别于大跨度跨河钢桁架桥结构的架设方向的相对两侧的两钢管桩铺设顶梁。S4: Lay the top beam on two steel pipe piles on opposite sides of the erection direction of the long-span river-crossing steel truss bridge structure.
S5:于架设方向的相对两侧的顶梁铺设贝雷支撑架。S5: Bailey support frames are laid on the top beams on opposite sides of the erection direction.
S6:于贝雷支撑架的相对两侧铺设支承型钢以形成水上支撑平台2。S6: Lay supporting steel sections on opposite sides of the Bailey support frame to form an above-water support platform 2.
顶梁上布置的贝雷支撑架(即贝雷架),其中的贝雷片间紧扣牢靠,使水上支撑平台形成稳固整体。The Bailey support frame (i.e. Bailey frame) arranged on the top beam has Bailey pieces that are tightly fastened to form a stable whole for the water support platform.
在贝雷架上沿大跨度跨河钢桁架桥的架设方向(即大跨度跨河钢桁架桥的长度方向)铺设支撑型钢,在支撑型钢的两端安装卸载型钢。Supporting steel sections are laid on the Bailey frame along the erection direction of the long-span river-span steel truss bridge (i.e. the length direction of the long-span river-span steel truss bridge), and unloading steel sections are installed at both ends of the supporting steel sections.
S7:于河道的两岸分别浇筑墩柱。S7: Cast piers on both sides of the river channel.
具体的,步骤S7包括:Specifically, step S7 includes:
S71、于两岸绑扎墩柱钢筋笼;S71, tie the pier column reinforcement cage on both sides;
S72、于墩柱钢筋笼的外部安装墩柱模板;S72, installing the pier column formwork outside the pier column reinforcement cage;
S73、于墩柱钢筋笼的顶部安装预埋件;S73. Install embedded parts on the top of the pier column reinforcement cage;
S74、于墩柱模板内浇筑混凝土以形成墩柱;S74, pouring concrete in the pier column formwork to form the pier column;
S75、在墩柱的强度符合设计要求后,于墩柱的顶部的预埋件安放转换支座。S75. After the strength of the pier column meets the design requirements, place the conversion bearing on the embedded parts at the top of the pier column.
转换制作的标高与大跨度跨河钢桁架桥的底面标高齐平。The elevation of the conversion is flush with the bottom elevation of the long-span steel truss bridge across the river.
S8:于墩柱拼装形成临岸段,使得两岸的墩柱上的临岸段朝向水上支撑平台2延伸设置。S8: Assembling the piers to form shore sections, so that the shore sections on the piers on both sides extend toward the above-water support platform 2 .
具体的,拼装临岸段的步骤包括:Specifically, the steps of assembling the shore section include:
S81、将桁架下弦箱梁吊装并安装至墩柱;S81. Hoist and install the truss lower chord box girder to the pier column;
S82、于桁架下弦箱梁的相对两侧分别竖向安装多根腹杆,多根腹杆沿桁架下弦箱梁的长度方向设置;S82, vertically installing a plurality of web members on opposite sides of the lower chord box girder of the truss, respectively, and the plurality of web members are arranged along the length direction of the lower chord box girder of the truss;
S83、将桁架上弦箱梁安装于多根腹杆;S83, installing the truss upper chord box girder on the plurality of web members;
S84、将剪刀撑安装于桁架上弦箱梁和桁架下弦箱梁之间;S84, installing the scissor brace between the truss upper chord box girder and the truss lower chord box girder;
S85、将桁架外悬挑梁安装于桁架上弦箱梁和桁架下弦箱梁的外侧以形成临岸段。S85. Install the truss outer cantilever beam on the outer sides of the truss upper chord box beam and the truss lower chord box beam to form a bank section.
S9:于临岸段上铺设基板,使得基板沿临岸段的长度方向设置。S9: Laying a base plate on the bank section so that the base plate is arranged along the length direction of the bank section.
S10:将吊装机械行驶于基板上以吊装跨中段1的构件。S10: Move the lifting machinery onto the base plate to lift the components of the mid-span section 1.
S11:于水上支撑平台2的相对两侧与两岸的临岸段之间分别拼装形成跨中段1。S11: Assemble the mid-span section 1 between the opposite sides of the water support platform 2 and the shore sections on both banks.
S12:合拢两跨中段1以形成大跨度跨河钢桁架桥结构并拆除水上支撑平台2。S12: Close the middle sections 1 of the two spans to form a large-span river-crossing steel truss bridge structure and dismantle the water support platform 2.
在已安装两临岸段上铺设基板,基板用于供吊车等吊装机械的行走。吊车在已完成的两临岸段上对两跨中段同步对称吊装。The base plate is laid on the two installed shore sections, and the base plate is used for the movement of cranes and other lifting machinery. The crane synchronously and symmetrically lifts the middle sections of the two spans on the two completed shore sections.
其中,跨中段的拼装与临岸段的拼装步骤相同。跨中段的桁架下弦箱梁的一端与已装的临岸段的桁架下弦箱梁对接,跨中段的桁架下弦箱梁的另一端搭设在水上支撑平台的支撑型钢的卸载型钢上,然后安装其它构件,完成大跨度跨河钢桁架桥结构的桁架下弦箱梁的贯通。同上所述,依次安装跨中段腹杆、桁架上弦箱梁、剪刀撑、桁架外挑钢梁,最终完成大跨度跨河钢桁架桥结构合拢。Among them, the assembly steps of the mid-span section are the same as those of the shore section. One end of the truss lower chord box girder of the mid-span section is butted with the installed truss lower chord box girder of the shore section, and the other end of the truss lower chord box girder of the mid-span section is erected on the unloading steel of the supporting steel of the water support platform, and then other components are installed to complete the penetration of the truss lower chord box girder of the large-span steel truss bridge structure across the river. As mentioned above, the mid-span web bar, truss upper chord box girder, scissor brace, and truss cantilever steel beam are installed in sequence to finally complete the closure of the large-span steel truss bridge structure across the river.
本发明的大跨度跨河钢桁架桥结构的施工方法,解决了受工况限制无法使用大型吊装机械吊装的难题,相较于复杂程度高的架桥机施工,节省了成本,缩短了工期。而且,借助于钢管桩构成水上支撑平台作为临时支撑,所需建造设备简单,适用性强,支撑平台可以提前建造,有利于工期保证,钢管桩可重复使用,经济性好。The construction method of the large-span river-crossing steel truss bridge structure of the present invention solves the problem that large-scale lifting machinery cannot be used for lifting due to working conditions. Compared with the construction of the highly complex bridge erection machine, it saves costs and shortens the construction period. Moreover, by using steel pipe piles to form an above-water support platform as a temporary support, the required construction equipment is simple and has strong applicability. The support platform can be built in advance, which is conducive to ensuring the construction period. The steel pipe piles can be reused and have good economic efficiency.
以上描述仅为本申请的较佳实施例以及对所运用技术原理的说明。本领域技术人员应当理解,本申请中所涉及的发明范围,并不限于上述技术特征的特定组合而成的技术方案,同时也应涵盖在不脱离所述发明构思的情况下,由上述技术特征或其等同特征进行任意组合而形成的其它技术方案。例如上述特征与本申请中公开的(但不限于)具有类似功能的技术特征进行互相替换而形成的技术方案。The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with the technical features with similar functions disclosed in this application (but not limited to) by each other.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210429944.5A CN114790693B (en) | 2022-04-22 | 2022-04-22 | Construction method of large-span river-crossing steel truss bridge structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210429944.5A CN114790693B (en) | 2022-04-22 | 2022-04-22 | Construction method of large-span river-crossing steel truss bridge structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN114790693A CN114790693A (en) | 2022-07-26 |
| CN114790693B true CN114790693B (en) | 2024-04-12 |
Family
ID=82462496
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210429944.5A Active CN114790693B (en) | 2022-04-22 | 2022-04-22 | Construction method of large-span river-crossing steel truss bridge structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN114790693B (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115030010B (en) * | 2022-07-28 | 2025-06-20 | 山东华亿钢机股份有限公司 | Combined steel bridge structure system and installation and construction method thereof |
| CN116005541A (en) * | 2023-01-13 | 2023-04-25 | 山东高速工程建设集团有限公司 | Cantilever assembled steel truss bridge with track and construction method thereof |
| CN116623546B (en) * | 2023-05-23 | 2025-09-30 | 山东高速工程建设集团有限公司 | Installation method of steel truss bridge across river |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102146660A (en) * | 2011-02-25 | 2011-08-10 | 中交四航局第一工程有限公司 | Installation methods of cross-arch-rib gantry crane and butterfly arch bridge space structure system |
| JP2015190122A (en) * | 2014-03-27 | 2015-11-02 | 株式会社竹中工務店 | Beam-shaped member construction method |
| CN111764282A (en) * | 2020-05-19 | 2020-10-13 | 中交二航局第二工程有限公司 | Rigid suspension cable stiffening steel truss bridge construction method based on inclined pull buckling hanging method |
| CN112681135A (en) * | 2020-12-14 | 2021-04-20 | 中铁二十局集团第三工程有限公司 | Construction method of n-shaped sea-crossing temporary steel trestle |
| CN113136803A (en) * | 2021-04-19 | 2021-07-20 | 中交第三公路工程局有限公司 | River-crossing steel truss bridge closure method |
| CN113652977A (en) * | 2021-09-24 | 2021-11-16 | 中国十九冶集团有限公司 | Main beam mounting method of river-crossing steel box girder bridge |
-
2022
- 2022-04-22 CN CN202210429944.5A patent/CN114790693B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102146660A (en) * | 2011-02-25 | 2011-08-10 | 中交四航局第一工程有限公司 | Installation methods of cross-arch-rib gantry crane and butterfly arch bridge space structure system |
| JP2015190122A (en) * | 2014-03-27 | 2015-11-02 | 株式会社竹中工務店 | Beam-shaped member construction method |
| CN111764282A (en) * | 2020-05-19 | 2020-10-13 | 中交二航局第二工程有限公司 | Rigid suspension cable stiffening steel truss bridge construction method based on inclined pull buckling hanging method |
| CN112681135A (en) * | 2020-12-14 | 2021-04-20 | 中铁二十局集团第三工程有限公司 | Construction method of n-shaped sea-crossing temporary steel trestle |
| CN113136803A (en) * | 2021-04-19 | 2021-07-20 | 中交第三公路工程局有限公司 | River-crossing steel truss bridge closure method |
| CN113652977A (en) * | 2021-09-24 | 2021-11-16 | 中国十九冶集团有限公司 | Main beam mounting method of river-crossing steel box girder bridge |
Also Published As
| Publication number | Publication date |
|---|---|
| CN114790693A (en) | 2022-07-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106758856B (en) | The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block | |
| CN114790693B (en) | Construction method of large-span river-crossing steel truss bridge structure | |
| CN102154988B (en) | Arch-after-girder construction method of large-span steel box tacked arch bridge | |
| CN109024225A (en) | Ultra-high performance concrete truss arch blade unit, truss arch piece bridge and construction method | |
| CN112554077B (en) | Construction system and method of steel tube concrete assembled truss composite beam | |
| CN114592436A (en) | Pier capping beam lower support system and construction method thereof | |
| CN114263114A (en) | Construction system and construction method of large-section steel box girder | |
| CN106223183A (en) | Assembled concrete-filled rectangular steel tube combination truss bridge and construction method | |
| CN110863417A (en) | A fast-installed steel-concrete composite girder bridge and its construction method | |
| CN110184903B (en) | A truss-type prefabricated pipe column assembled bridge pier | |
| CN111962372A (en) | Road-rail combined construction steel web member double-combination continuous truss girder and construction method thereof | |
| CN111979891A (en) | A kind of semi-penetrating rectangular steel tube concrete composite truss bridge and construction method | |
| CN204570446U (en) | The T-shaped simply supported beam of a kind of precast assembly | |
| CN205874944U (en) | Double T type wave form steel web profiled steel sheet combination beam | |
| CN111851307A (en) | Construction method of large-span prefabricated corrugated web composite box girder transport frame | |
| CN114717944B (en) | Erection method of inverted trapezoid-section steel truss bridge | |
| CN116122325A (en) | Construction method for assembled high pile wharf | |
| CN110820519A (en) | Tunnel arch bridge convenient for rapid construction and construction method thereof | |
| CN214737317U (en) | Steel-concrete combined rigid frame bridge connected through slots | |
| CN214168790U (en) | Concrete-filled steel tube assembled truss composite beam construction system | |
| CN115287992A (en) | Combined box girder structure and construction method | |
| CN209816632U (en) | Arch foot structure for special-shaped space arch bridge | |
| CN112458879A (en) | Bolt-welding mixed-connection segmented prefabricated assembled combination beam and construction method thereof | |
| CN117604883B (en) | Steel-concrete composite Y-shaped inclined leg structure and construction method | |
| CN115821713B (en) | A prestressed UHPC composite structure continuous box girder bridge with corrugated steel web and its construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |