CN106592406A - Through tied arch bridge and construction method thereof - Google Patents
Through tied arch bridge and construction method thereof Download PDFInfo
- Publication number
- CN106592406A CN106592406A CN201611257261.7A CN201611257261A CN106592406A CN 106592406 A CN106592406 A CN 106592406A CN 201611257261 A CN201611257261 A CN 201611257261A CN 106592406 A CN106592406 A CN 106592406A
- Authority
- CN
- China
- Prior art keywords
- arch rib
- sections
- rib
- binder
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D4/00—Arch-type bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a through tied arch bridge and a construction method thereof. The through tied arch bridge is composed of two single-piece arch rib units. Each single-piece arch rib unit comprises an arch rib and a tie beam, wherein a hanger rod is arranged between the arch rib and the tie beam. The two arch ribs are connected as a whole through transverse supports. The two tie beams are connected as a whole through transverse beams. A bridge deck slab is erected on the transverse beams. Each arch rib is formed by connecting arch rib sections, each tie beam is formed by connecting tie beam sections, and the arch-shaped arch rib sections and the tie beam sections are arranged correspondingly. Each transverse support is formed by connecting two transverse support sections, wherein the two transverse support sections are fixedly connected on the arch ribs of the two single-piece arch rib units correspondingly. Each transverse beam is formed by connecting two transverse beam sections, wherein the two transverse beam sections are fixedly connected on the tie beams of the two single-piece arch rib units correspondingly. By connecting each group of transverse beam sections and each group of transverse support sections on bridge location construction site, the erection work of a bridge main body can be completed, so that the construction period is shortened effectively, capital investment is reduced, and the construction method is especially suitable for bridge construction of crossing important riverways or important lines.
Description
Technical field
The present invention relates to highway and municipal bridge technology, more particularly, to a kind of crossing river channel or the base-supporting tie-rod of cross-line
Arch bridge, the invention further relates to the construction method of the bowstring arch bridge.
Background technology
Through tied arch bridge will encircle with two kinds of structural groupings of beam together with, common bearing load, give full play to beam receive it is curved,
The pressurized compound action of arch, thus lower bearing arch bridge is that one of bridge type is commonly used in cross a river or cross-line newly building bridge.
The construction method of existing through tied arch bridge mainly includes rack construction method, construction by swing and cantilever-construction
Three kinds of methods, the key problem of above-mentioned three kinds of construction methods is the construction problem for solving arch rib.Rack construction method is in river course
Erection bracket is constructed, and the advantage of the method is simple to operate, there is the operation platform for being available for operating in work progress;But,
The long construction period of the method, has a strong impact on the navigation in river course;According to limited bracket, support collides with passing ships, deposits
In potential safety hazard.Construction by swing is the construction party that a kind of utilization landform and support are carried out cast-in-place or prefabricated arch rib by design altitude
Method, in work progress vertically or level to around skewback bottom vertical pivot rotate, make arch rib close up arching.The construction method is not
Need to set up support, work high above the ground is converted into into land operation, not only ensure construction safety and construction quality, and be easy to control
Construct really, reduce construction to river course or the interference of intersecting roads, but the method needs large-scale tumbler, increases
Fund input, and the control of tumbler is relatively complicated.Cantilever-construction is to carry out horizontal transport work by cable crane,
Arch ring sections is vertically sling and installed, using cantilever truss segmentation installation is carried out, arch ring is closed up, finally carry out suspension rod
Install, tensioning and floorings are constructed;The method needs to arrange tower crane(That is cable hoisting device), increase fund input.Above-mentioned three
Plant construction method all to there is long construction period, need to arrange temporary facility(Such as support, tumbler or cable device), to existing
Field execution conditions have high demands, it is impossible to the shortcomings of making full use of existing bridge, high cost.
The content of the invention
Present invention aims to the defect that above-mentioned prior art is present, there is provided a kind of through tied arch bridge, this
Invention also provides the construction method of the bowstring arch bridge.The bowstring arch bridge constructing operation of the present invention is simple, and short construction period, engineering is whole
Body low cost, the engineering time is short at bridge location, is particularly well-suited to the bridge construction across important river course or important line.
For achieving the above object, the present invention takes following technical proposals:
Through tied arch bridge of the present invention, including spaced bridge pier, are placed with pontic on the bridge pier, described
Pontic is made up of the identical two monolithic arch rib units being arranged side by side of structure, and the monolithic arch rib unit includes domed structure
Arch rib and the binder being connected horizontally between the arch rib two-end-point, longitudinally spaced being provided with is propped up between the arch rib and binder
Support suspension rod;The arch rib of two monolithic arch rib units is connected as a single entity by the stull that is horizontally spaced about, and two monolithic arch rib units are
Beam is connected as a single entity by the crossbeam being horizontally spaced about, and in the crossbeam restocking floorings are provided with, and the arch rib is by multiple arcs
Rib-lifting section is connected forms successively, and the binder is connected successively by multiple horizontally disposed binder sections and forms, the arc
Rib sections corresponds up and down setting with the binder sections, and the two arc rib-lifting sections positioned at arch rib end are respectively with being located at
The binder sections of beam end is connected as a single entity;
The stull is formed by two length identical stull sections linkings, and two stull sections correspond to be connected in two respectively
On the arch rib of the individual monolithic arch rib unit, the crossbeam is formed by two length identical crossbeam sections linkings, described in two
Crossbeam sections corresponds to be connected on the binder of two monolithic arch rib units respectively.
The construction method of through tied arch bridge of the present invention specifically includes following steps:
At the bridge location yet to be built of river course two sides or both sides of the road there is existing bridge in side, cast in situs two at bridge location yet to be built
Bridge pier, by the rib-lifting section of prefabrication, binder sections, stull sections and crossbeam sections job site is transported to;
Step(2):Multiple assembled moulding beds and multiple assembled pedestals, assembled moulding bed and spelling are spaced apart on vacant lot at the construction field (site)
Dress pedestal is corresponded to be placed, and a binder sections is placed with each assembled moulding bed, to multiple binder sections on assembled moulding bed
Duan Yici carries out assembly;
A rib-lifting section is placed with each assembled pedestal, assembly is carried out successively to multiple rib-lifting sections on assembled pedestal,
When rib-lifting section is steel box structure or concrete filled steel tube, the faying face per two neighboring rib-lifting section is linked as by welding
Integrally, when rib-lifting section adopts reinforced concrete structure, the faying face per two neighboring rib-lifting section is linked as by wet seam
Integrally, then the both ends of arch rib are integrated respectively with the assembly of corresponding binder end;
After the completion for the treatment of arch rib and binder assembly, assembled stull sections is spaced on arch rib, assembled crossbeam sections is spaced on binder,
After the completion for the treatment of stull sections and binder section assembling, the interval anchoring propping steeve between binder and arch rib, and will support
Suspension rod initial tensioning is to designing Suo Li, you can complete the prefabricated of monolithic arch rib unit;
Step(3):After the completion for the treatment of that monolithic arch rib unit is prefabricated, above-mentioned steps(2)In be often correspondingly arranged one assembled moulding bed and
One assembled pedestal constitutes an assembling support, is arranging on the monolithic arch rib unit of two neighboring assembling support gap location
Protective stent;
Step(4):Using loop wheel machine by above-mentioned steps(3)In monolithic arch rib unit from the sleeping state of lying be lifted to after vertical state turn
It is transported on self-traveling module transportation vehicle;It is assembled one at the crossbeam sections position at binder two ends to increase transportation stability
Outside horizontal-extending interim crossbeam, at the stull sections position at arch rib two ends assembled one it is outwards horizontal-extending interim
Stull, the interim crossbeam being correspondingly arranged and false stull are fixedly connected with by the first interim drag-line, the stull section of monolithic arch rib unit
Section and crossbeam sections are fixedly connected with by the second interim drag-line, and the second interim drag-line is symmetrical arranged with the first interim drag-line;
Step(5):After first, second interim drag-line installation, start self-traveling module transportation vehicle after existing bridge, certainly
Line module transportation vehicle is moved to monolithic arch rib unit at bridge location yet to be built along the direction parallel to river course or road;
Step(6):Repeat the above steps(2)~step(5)Another monolithic arch rib unit is turned with self-traveling module transportation vehicle
Deliver at bridge location yet to be built, two monolithic arch rib units are symmetrically placed;
Step(7):Move the self-traveling module transportation vehicle below two monolithic arch rib units respectively to transfer two monolithic arch rib units
To bridge pier, the position of two monolithic arch rib units is adjusted by self-traveling module transportation vehicle, after two monolithic arch rib units are in place,
The arch springing built-in fitting on two monolithic arch rib unit arch ribs is fixedly connected with the erection support on bridge pier respectively, finally by self-propelled mould
Block transport vehicle is removed, and realizes the erection operation of two monolithic arch rib units;
Step(8):After the completion for the treatment of that two monolithic arch rib units set up, the stull sections that setting is corresponded on two arch ribs is held in the mouth respectively
One is connected in, the assembly of stull is completed, is respectively integrated one-to-one two crossbeams sections linking on two binders, complete crossbeam
Assembly;
After crossbeam and stull assembly are finished, according to the internal force for requiring to adjust the propping steeve into bridge, then will using loop wheel machine
The floorings are erected on crossbeam, finally remove first, second interim drag-line, protective stent, false stull and interim crossbeam,
Cheng Qiao is open to traffic.
The step(2)In assembled moulding bed and assembled pedestal be welded by upper strata steel plate and lower floor's shaped steel.
The step(3)In protective stent be by the frame structure of four channel-section steels linking.
Compared with existing through tied arch bridge and its construction method, through tied arch bridge of the present invention and its construction method
With advantages below:
(1)The bowstring arch bridge of the present invention adopts factory-made component, and it is single that the job site by bank or road directly carries out two
The integral assembling of piece arch rib unit, the bridge pier for then passing through existing bridge transportation to bridge location yet to be built using self-traveling module transportation vehicle
On, only need to be attached every group of crossbeam sections and every group of stull sections in bridge location job site, just can complete bridge main body
The construction of structure, it is to avoid high-altitude is constructed, effectively shortens construction period, reduces fund input, good in economic efficiency;Two monolithic arch rib lists
The assembly of unit adopts horizontal assembly, reduces work high above the ground.
(2)Bridge pier at bridge location yet to be built is cast in situs molding, it is not necessary to occupied ground in addition, reduces engineering and integrally makes
Valency.
(3), in processing transit zone precast assembly, mechanization degree is high, and then it is strong to reduce the work of workman for monolithic arch rib unit
Degree, it is ensured that construction quality, while reducing impact of the environmental factorss to construction operation;The two monolithic arch rib units that precast assembly is completed
Can complete to set up operation in one day, greatly shorten the engineering time at bridge location yet to be built, on opening the navigation or air flight or being open to traffic almost without impact,
Guarantee ship or vehicle pass-through safety, be particularly suited for the bridge construction across important river course or important line.
(4)In work progress, protective stent is used to support monolithic arch rib unit, it is ensured that transportation stability.
(5)First, second interim drag-line on two monolithic arch rib units is used to guarantee first, second arch rib unit in transport
And the lateral stability in erection operation.
Description of the drawings
Fig. 1 is the structural representation of the present invention.
Fig. 2 is the overlooking the structure diagram of Fig. 1.
Fig. 3~15 are the structural representations of through tied arch bridge construction method of the present invention.
Specific embodiment
As shown in Figure 1 and Figure 2, through tied arch bridge of the present invention, including spaced bridge pier 1, in the bridge
Pontic is placed with pier 1, the pontic is made up of the identical two monolithic arch rib units being arranged side by side of structure, the monolithic arch rib
The arch rib 2 of unit including domed structure and the binder 3 being connected horizontally between the two-end-point of the arch rib 2, in the He of the arch rib 2
It is longitudinally spaced between binder 3 to be provided with propping steeve 4;The arch rib 2 of two monolithic arch rib units passes through the stull 5 being horizontally spaced about
It is connected as a single entity, the binder 3 of two monolithic arch rib units is connected as a single entity by the crossbeam 6 being horizontally spaced about, in the restocking of the crossbeam 6
It is provided with floorings, the arch rib 2 is connected successively by five arc rib-lifting sections and forms, and the binder 3 is horizontally disposed by five
Binder sections is connected forms successively, and the arc rib-lifting section corresponds up and down setting with the binder sections(Certainly, according to
It is actually needed, the sections number of arc rib-lifting section and binder sections can also be other numerical value), positioned at two arcs of the end of arch rib 2
Shape rib-lifting section is connected as a single entity respectively with the binder sections positioned at the end of binder 3;
As shown in figure 15, stull 5 is formed by the linking of two length identical stull sections 5.1, and two stull sections 5.1 correspond to respectively solid
It is connected on the arch rib 2 of two monolithic arch rib units, crossbeam 6 is formed by two linkings of length identical crossbeam sections 6.1, two crossbeam sections
Section 6.1 corresponds to be connected on the binder 3 of two monolithic arch rib units respectively.
The construction method of through tied arch bridge of the present invention specifically includes following steps:
Step(1):At the bridge location yet to be built in river course 7 there is existing bridge 8 in upstream or downstream position, in treating for the two sides of river course 7
Cast in situs bridge pier 1 at bridge construction position, arranges processing, transit zone 9, specifically on the vacant lot between existing bridge 8 and bridge location yet to be built
As shown in figure 3, the rib-lifting section of prefabrication, binder sections, stull sections 5.1 and crossbeam sections 6.1 are transported to into described adding
Work, transit zone 9;
Step(2):The assembled moulding bed 10 of interval setting five and five assembled pedestals 11 on the vacant lot in the processing, transit zone 9,
Assembled moulding bed 10 and assembled pedestal 11 are welded by upper strata steel plate and lower floor's shaped steel, and the upper plane of assembled pedestal 11 is arc
Structure, the upper plane of assembled moulding bed 10 is square structure, and assembled moulding bed 10 and assembled pedestal 11 are corresponded and arranged, concrete as schemed
Shown in 4;
A binder sections is placed with each assembled moulding bed 10, five binder sections are spelled successively on assembled moulding bed 10
Dress;A rib-lifting section is placed with each assembled pedestal 11, five rib-lifting sections are spelled successively on assembled pedestal 11
Dress, during practice of construction, rib-lifting section can be using steel box structure or concrete filled steel tube, now per two neighboring rib-lifting section
Faying face weldering be connected as a single entity, the ferrum in the range of 30mm~50mm by rib-lifting section faying face and joint edge is needed before welding
Rust, oxide skin, oily water are distinguished except totally, groove face polishes suitable using abrasive machine, are to ensure quality of weld seam molding, using entirely
Automatic welding carriage is welded;Certainly, rib-lifting section can also adopt reinforced concrete structure, now two neighboring arch rib section
The faying face of section is connected as a single entity by wet seam;
The both ends of arch rib 2 are integrated respectively with the one end assembly of binder 3 of corresponding placement, then interval is spelled on arch rib 2
Dress stull sections 5.1, is spaced assembled crossbeam sections 6.1 on binder 3, after the completion for the treatment of stull sections 5.1 and binder section assembling,
It is spaced anchorage support suspension rod 4 between binder 3 and arch rib 2, and by the initial tensioning of propping steeve 4 to designing Suo Li, you can complete list
Piece arch rib unit it is prefabricated, specifically as shown in Figure 5, Figure 6, wherein Fig. 6 is the lateral cross section structural representation of Fig. 5;
Step(3):After the completion for the treatment of that monolithic arch rib unit is prefabricated, above-mentioned steps(2)In be often correspondingly arranged one assembled moulding bed 10
An assembling support is constituted with an assembled pedestal 11, is being set on the monolithic arch rib unit of adjacent two assembling supports gap location
Protective stent 12 is equipped with, protective stent 12 is by four channel-section steels frame structure connected successively, for guaranteeing monolithic arch rib
Unit is transporting and is setting up the stability in operation, and the arch rib 2 of unit arch rib unit is provided with hanger, is easy to lifting, specifically
As shown in Figure 7, Figure 8, wherein Fig. 8 is the lateral cross section structural representation of Fig. 7;
Step(4):Using loop wheel machine 13 by above-mentioned steps(3)In monolithic arch rib unit be lifted to after vertical state from the sleeping state of lying
It is transported on self-traveling module transportation vehicle 14, it is concrete as shown in Figure 9;To increase transportation stability, in the crossbeam section at the two ends of binder 3
Section is respectively mounted outwards horizontal-extending interim crossbeam 15 at 6.1 positions, punishes in the position of stull sections 5.1 at the two ends of arch rib 2
False stull 16 that An Zhuan be outwards not horizontal-extending, the interim crossbeam 15 being correspondingly arranged and false stull 16 interim draw by first
Rope 17.1 is fixedly connected with, and the crossbeam sections 6.1 and stull sections 5.1 of monolithic arch rib unit inside pass through the phase of the second interim drag-line 17.2
Be connected, first, second interim drag-line 17.1,17.2 is symmetrical arranged, the two ends of the first interim drag-line 17.1 respectively with interim crossbeam
15th, the anchor connection of false stull 16, the two ends of the second interim drag-line 17.2 crossbeam sections 6.1 respectively with monolithic arch rib unit,
The anchor connection of stull sections 5.1, specifically as shown in Figure 10, Figure 11, wherein Figure 11 is the overlooking the structure diagram of Figure 10;
Step(5):After the first, second interim drag-line 17.1,17.2 installations, start the self-traveling module transportation vehicle
14 by the way that after the existing bridge 8, self-traveling module transportation vehicle 14 is moved to bridge location yet to be built along the direction parallel to river course 7
Place, it is concrete as shown in figure 12;
Step(6):Repeat the above steps(2)~step(5)With self-traveling module transportation vehicle 14 by another monolithic arch rib unit
Transfer at bridge location yet to be built, and two monolithic arch rib units are symmetrically placed, it is concrete as shown in figure 13;
Step(7):Move the self-traveling module transportation vehicle 14 below two monolithic arch rib units respectively to turn two monolithic arch rib units
Deliver on bridge pier 1, the position of two monolithic arch rib units is adjusted by self-traveling module transportation vehicle 14, treat two monolithic arch rib units just
Behind position, the arch springing built-in fitting on two monolithic arch rib unit arch ribs 2 is fixedly connected with the erection support on bridge pier 1 respectively, finally will
Self-traveling module transportation vehicle 14 is removed, you can realize the erection operation of two monolithic arch rib units, concrete as shown in Figure 14, Figure 15,
Figure 14 is mounting structure schematic diagram of the monolithic arch rib unit at bridge pier 1, and Figure 15 is that monolithic arch rib unit is set up after the completion of operation
Structural representation;
Step(8):After the completion for the treatment of that two monolithic arch rib units set up, the stull sections of setting will be corresponded on two arch ribs 2 respectively
5.1 linkings are integrated, and complete the assembly of the stull 5;One-to-one two crossbeams sections 6.1 on two binders 3 is connected respectively
It is integrated, completes the assembly of the crossbeam 6, when being connected as a single entity using solder technology weldering between rib-lifting section, is often correspondingly arranged
Two stull sections 5.1 be connected as a single entity using solder technology, two for being often correspondingly arranged crossbeam sections 6.1 using solder technology connect
It is integrated;When rib-lifting section is connected as a single entity by wet seam, two for being often correspondingly arranged stull sections 5.1 is connected by wet seam
It is integrated, two for being often correspondingly arranged crossbeam sections 6.1 is connected as a single entity by wet seam;Treat that crossbeam 6 and the assembly of stull 5 are finished
Afterwards, according to the internal force for requiring to adjust the propping steeve 4 into bridge, then floorings are erected on crossbeam using loop wheel machine 13, most
First, second interim drag-line 17.1,17.2, protective stent 12, false stull 16 and interim crossbeam 15 are removed afterwards, and Cheng Qiao is open to traffic,
The structural representation of Cheng Qiao is concrete as shown in Figure 1 and Figure 2.
Claims (4)
1. a kind of through tied arch bridge, including spaced bridge pier, is placed with pontic on the bridge pier, the pontic by
Two monolithic arch rib units that structure is identical to be arranged side by side are constituted, the monolithic arch rib unit include the arch rib of domed structure and
The binder being connected horizontally between the arch rib two-end-point, it is longitudinally spaced between the arch rib and binder to be provided with support and hang
Bar;The arch rib of two monolithic arch rib units is connected as a single entity by the stull being horizontally spaced about, and the binder of two monolithic arch rib units leads to
Cross the crossbeam being horizontally spaced about to be connected as a single entity, in the crossbeam restocking floorings be provided with, it is characterised in that:The arch rib is by more
Individual arc rib-lifting section is connected forms successively, and the binder is connected successively by multiple horizontally disposed binder sections and forms, described
Arc rib-lifting section corresponds up and down setting with the binder sections, positioned at arch rib end two arc rib-lifting sections respectively with
Binder sections positioned at binder end is connected as a single entity;
The stull is formed by two length identical stull sections linkings, and two stull sections correspond to be connected in two respectively
On the arch rib of the individual monolithic arch rib unit, the crossbeam is formed by two length identical crossbeam sections linkings, described in two
Crossbeam sections corresponds to be connected on the binder of two monolithic arch rib units respectively.
2. the construction method of through tied arch bridge as claimed in claim 1, it is characterised in that:The construction method includes following step
Suddenly:
Step(1):There is existing bridge in the bridge location side yet to be built of river course two sides or both sides of the road, scene is poured at bridge location yet to be built
Two bridge piers are built, the rib-lifting section of prefabrication, binder sections, stull sections and crossbeam sections are transported to into job site;
Step(2):Multiple assembled moulding beds and multiple assembled pedestals, assembled moulding bed and spelling are spaced apart on vacant lot at the construction field (site)
Dress pedestal is corresponded to be placed, and a binder sections is placed with each assembled moulding bed, to multiple binder sections on assembled moulding bed
Duan Yici carries out assembly;
A rib-lifting section is placed with each assembled pedestal, assembly is carried out successively to multiple rib-lifting sections on assembled pedestal,
When rib-lifting section is steel box structure or concrete filled steel tube, the faying face per two neighboring rib-lifting section is linked as by welding
Integrally, when rib-lifting section adopts reinforced concrete structure, the faying face per two neighboring rib-lifting section is linked as by wet seam
Integrally, then the both ends of arch rib are integrated respectively with the assembly of corresponding binder end;
After the completion for the treatment of arch rib and binder assembly, assembled stull sections is spaced on arch rib, assembled crossbeam sections is spaced on binder,
After the completion for the treatment of stull sections and binder section assembling, the interval anchoring propping steeve between binder and arch rib, and will support
Suspension rod initial tensioning is to designing Suo Li, you can complete the prefabricated of monolithic arch rib unit;
Step(3):After the completion for the treatment of that monolithic arch rib unit is prefabricated, above-mentioned steps(2)In be often correspondingly arranged one assembled moulding bed and
One assembled pedestal constitutes an assembling support, is arranging on the monolithic arch rib unit of two neighboring assembling support gap location
Protective stent;
Step(4):Using loop wheel machine by above-mentioned steps(3)In monolithic arch rib unit from the sleeping state of lying be lifted to after vertical state turn
It is transported on self-traveling module transportation vehicle;It is assembled one at the crossbeam sections position at binder two ends to increase transportation stability
Outside horizontal-extending interim crossbeam, at the stull sections position at arch rib two ends assembled one it is outwards horizontal-extending interim
Stull, the interim crossbeam being correspondingly arranged and false stull are fixedly connected with by the first interim drag-line, the horizontal stroke of monolithic arch rib unit inside
Support sections and crossbeam sections are fixedly connected with by the second interim drag-line, and the second interim drag-line is symmetrical arranged with the first interim drag-line;
Step(5):After first, second interim drag-line installation, start self-traveling module transportation vehicle after existing bridge, certainly
Line module transportation vehicle is moved to monolithic arch rib unit at bridge location yet to be built along the direction parallel to river course or road;
Step(6):Repeat the above steps(2)~step(5)Another monolithic arch rib unit is turned with self-traveling module transportation vehicle
Deliver at bridge location yet to be built, two monolithic arch rib units are symmetrically placed;
Step(7):Move the self-traveling module transportation vehicle below two monolithic arch rib units respectively to transfer two monolithic arch rib units
To bridge pier, the position of two monolithic arch rib units is adjusted by self-traveling module transportation vehicle, after two monolithic arch rib units are in place,
The arch springing built-in fitting on two monolithic arch rib unit arch ribs is fixedly connected with the erection support on bridge pier respectively, finally by self-propelled mould
Block transport vehicle is removed, and realizes the erection operation of two monolithic arch rib units;
Step(8):After the completion for the treatment of that two monolithic arch rib units set up, the stull sections that setting is corresponded on two arch ribs is held in the mouth respectively
One is connected in, the assembly of stull is completed, is respectively integrated one-to-one two crossbeams sections linking on two binders, complete crossbeam
Assembly;
After crossbeam and stull assembly are finished, according to the internal force for requiring to adjust propping steeve into bridge, then will be described using loop wheel machine
Floorings are erected on crossbeam, finally remove first, second interim drag-line, protective stent, false stull and interim crossbeam, Cheng Qiao
It is open to traffic.
3. construction method according to claim 2, it is characterised in that:The step(2)In assembled moulding bed and assembled base
Seat is welded by upper strata steel plate and lower floor's shaped steel.
4. construction method according to claim 2, it is characterised in that:The step(3)In protective stent be by four
The frame structure of channel-section steel linking.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611257261.7A CN106592406B (en) | 2016-12-30 | 2016-12-30 | Through tied arch bridge and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611257261.7A CN106592406B (en) | 2016-12-30 | 2016-12-30 | Through tied arch bridge and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106592406A true CN106592406A (en) | 2017-04-26 |
CN106592406B CN106592406B (en) | 2018-03-06 |
Family
ID=58583008
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611257261.7A Active CN106592406B (en) | 2016-12-30 | 2016-12-30 | Through tied arch bridge and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106592406B (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107237262A (en) * | 2017-06-09 | 2017-10-10 | 中交第二航务工程局有限公司 | A kind of concrete arch rib construction method |
CN108374319A (en) * | 2018-04-08 | 2018-08-07 | 北京城建道桥建设集团有限公司 | A kind of through tied arch bridge structural unit and arch bridge structure and its construction method |
CN108442230A (en) * | 2018-06-01 | 2018-08-24 | 深圳市市政设计研究院有限公司 | A kind of arch bridge suspender structure |
CN108532465A (en) * | 2018-04-20 | 2018-09-14 | 中交第三航务工程局有限公司 | A kind of construction method of Through Steel case arch bridge |
CN110670637A (en) * | 2019-09-18 | 2020-01-10 | 深圳市综合交通设计研究院有限公司 | Arch temporary suspension protection system for underground existing channel and construction method thereof |
CN110820519A (en) * | 2019-11-26 | 2020-02-21 | 四川省公路规划勘察设计研究院有限公司 | Tunnel arch bridge convenient for rapid construction and construction method thereof |
CN111535182A (en) * | 2020-03-31 | 2020-08-14 | 中国建筑第六工程局有限公司 | Tubular bridge girder erection method |
CN111764305A (en) * | 2020-07-20 | 2020-10-13 | 四川省公路规划勘察设计研究院有限公司 | Main arch arching process for main arch single-rib staggered cantilever casting synchronous transverse connection |
CN113944095A (en) * | 2021-11-05 | 2022-01-18 | 上海市政工程设计研究总院(集团)有限公司 | Through tied arch bridge and construction method thereof |
CN114855620A (en) * | 2022-05-09 | 2022-08-05 | 广西路建工程集团有限公司 | Bridge steel pipe arch rib integral lifting anchoring device and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104404887A (en) * | 2014-12-01 | 2015-03-11 | 中铁二十局集团第一工程有限公司 | Large span steel tube arch bridge stents-free hoisting process |
CN204282188U (en) * | 2014-12-01 | 2015-04-22 | 中铁二十局集团第一工程有限公司 | A kind of long-span steel pipe arch bridge is without support lifting construction structure |
RU2567253C1 (en) * | 2014-06-05 | 2015-11-10 | Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Уральский государственный университет путей сообщения" (УрГУПС) | Arched bridge |
CN105586826A (en) * | 2015-11-30 | 2016-05-18 | 湖州交通规划设计院 | Connecting structure of anchorage ends of booms of concrete tied arch bridge and construction method of connecting structure |
CN206408510U (en) * | 2016-12-30 | 2017-08-15 | 河南省交通规划设计研究院股份有限公司 | Through tied arch bridge |
-
2016
- 2016-12-30 CN CN201611257261.7A patent/CN106592406B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2567253C1 (en) * | 2014-06-05 | 2015-11-10 | Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Уральский государственный университет путей сообщения" (УрГУПС) | Arched bridge |
CN104404887A (en) * | 2014-12-01 | 2015-03-11 | 中铁二十局集团第一工程有限公司 | Large span steel tube arch bridge stents-free hoisting process |
CN204282188U (en) * | 2014-12-01 | 2015-04-22 | 中铁二十局集团第一工程有限公司 | A kind of long-span steel pipe arch bridge is without support lifting construction structure |
CN105586826A (en) * | 2015-11-30 | 2016-05-18 | 湖州交通规划设计院 | Connecting structure of anchorage ends of booms of concrete tied arch bridge and construction method of connecting structure |
CN206408510U (en) * | 2016-12-30 | 2017-08-15 | 河南省交通规划设计研究院股份有限公司 | Through tied arch bridge |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107237262A (en) * | 2017-06-09 | 2017-10-10 | 中交第二航务工程局有限公司 | A kind of concrete arch rib construction method |
CN108374319B (en) * | 2018-04-08 | 2024-03-26 | 北京城建道桥建设集团有限公司 | Lower-bearing type tied-arch bridge structural unit, arch bridge structure and construction method thereof |
CN108374319A (en) * | 2018-04-08 | 2018-08-07 | 北京城建道桥建设集团有限公司 | A kind of through tied arch bridge structural unit and arch bridge structure and its construction method |
CN108532465A (en) * | 2018-04-20 | 2018-09-14 | 中交第三航务工程局有限公司 | A kind of construction method of Through Steel case arch bridge |
CN108442230A (en) * | 2018-06-01 | 2018-08-24 | 深圳市市政设计研究院有限公司 | A kind of arch bridge suspender structure |
CN110670637A (en) * | 2019-09-18 | 2020-01-10 | 深圳市综合交通设计研究院有限公司 | Arch temporary suspension protection system for underground existing channel and construction method thereof |
CN110820519A (en) * | 2019-11-26 | 2020-02-21 | 四川省公路规划勘察设计研究院有限公司 | Tunnel arch bridge convenient for rapid construction and construction method thereof |
CN111535182A (en) * | 2020-03-31 | 2020-08-14 | 中国建筑第六工程局有限公司 | Tubular bridge girder erection method |
CN111764305B (en) * | 2020-07-20 | 2022-02-11 | 四川省公路规划勘察设计研究院有限公司 | Main arch arching process for main arch single-rib staggered cantilever casting synchronous transverse connection |
CN111764305A (en) * | 2020-07-20 | 2020-10-13 | 四川省公路规划勘察设计研究院有限公司 | Main arch arching process for main arch single-rib staggered cantilever casting synchronous transverse connection |
CN113944095A (en) * | 2021-11-05 | 2022-01-18 | 上海市政工程设计研究总院(集团)有限公司 | Through tied arch bridge and construction method thereof |
CN114855620A (en) * | 2022-05-09 | 2022-08-05 | 广西路建工程集团有限公司 | Bridge steel pipe arch rib integral lifting anchoring device and construction method thereof |
CN114855620B (en) * | 2022-05-09 | 2023-08-01 | 广西路建工程集团有限公司 | Integral lifting and anchoring device for bridge steel pipe arch rib and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN106592406B (en) | 2018-03-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106592406B (en) | Through tied arch bridge and its construction method | |
JP5047680B2 (en) | Construction method of continuous viaduct | |
CN105236275B (en) | Soil lifting system and method for construction of deep foundation pit in narrow area building | |
CN106223360A (en) | Use the open cut cast in place and precast construction subway station construction method of stake supporting system | |
CN111119059B (en) | Ultrahigh composite support system for high-pier cast-in-place box girder and construction method | |
CN104594204B (en) | Urban light rail viaduct mountain type U beam Construction Supporting System and construction method | |
CN101781878A (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
JP3240244U (en) | Split-type horizontal beam construction structure erected on the gate-type bridge pier of the existing railway line | |
CN110387822A (en) | Cast-in-place Bent Cap assembled steel pipe holder and its construction method | |
CN103850171B (en) | A kind of all steel assembled overpass on an empty stomach | |
CN106012851A (en) | Synchronous construction method of steel box girder and concrete pier studs | |
JP5184248B2 (en) | Construction method of level crossing | |
CN109653515A (en) | Across the steel worm-gearing truss hanging method of 120m | |
CN109594581B (en) | River-crossing pipeline structure and installation method thereof | |
CN107881924A (en) | A kind of bent cap support | |
CN206408510U (en) | Through tied arch bridge | |
CN204475184U (en) | Urban light rail viaduct mountain type U beam Construction Supporting System | |
CN214005379U (en) | Prefabricated part for expanding existing elevated operation subway station platform | |
CN117488647A (en) | Combined beam suitable for upper and lower two-layer steel truss web rods of overhead in urban area and construction method | |
CN208328660U (en) | The U-shaped girder construction of the Two bors d's oeuveres of combined bridge | |
CN103061568A (en) | Tapered hanging bracket high-position in-situ casting construction method of water tank of reverse taper shell heat-preservation water tower | |
JP4685341B2 (en) | Viaduct construction method | |
CN114319159B (en) | Ascending ramp dismantling system and construction method | |
CN112610244B (en) | Prefabricated part for expanding existing elevated operation subway station platform and installation method thereof | |
CN209276999U (en) | A kind of urban viaduct cantilever is set a roof beam in place support system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |