CN111827095A - Prefabricated and assembled hollow pier with built-in ribs and construction method - Google Patents

Prefabricated and assembled hollow pier with built-in ribs and construction method Download PDF

Info

Publication number
CN111827095A
CN111827095A CN202010606957.6A CN202010606957A CN111827095A CN 111827095 A CN111827095 A CN 111827095A CN 202010606957 A CN202010606957 A CN 202010606957A CN 111827095 A CN111827095 A CN 111827095A
Authority
CN
China
Prior art keywords
section
segment
steel bar
connecting steel
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010606957.6A
Other languages
Chinese (zh)
Other versions
CN111827095B (en
Inventor
孙树礼
苏伟
张帅
张雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
China State Railway Group Co Ltd
Original Assignee
China Railway Design Corp
China State Railway Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp, China State Railway Group Co Ltd filed Critical China Railway Design Corp
Priority to CN202010606957.6A priority Critical patent/CN111827095B/en
Publication of CN111827095A publication Critical patent/CN111827095A/en
Application granted granted Critical
Publication of CN111827095B publication Critical patent/CN111827095B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明提供带内置肋板的预制拼装空心桥墩及施工方法,涉及桥梁建造技术领域。由下及上依次包括基础、底节段、中间节段、顶帽节段,基础顶部设置预埋钢筋,预埋钢筋上设置箍筋;底节段下方设置实体段,底节段与实体段一起预制,实体段上预留连接钢筋孔道,连接钢筋孔道的直径尺寸较基础顶部的预埋钢筋每侧大5cm;在预埋钢筋的孔道中填充有后浇混凝土;底节段、中间节段、顶帽节段上均设置肋板,每个肋板上均设置连接钢筋,每个连接钢筋均伸出相应肋板,各节段间连接钢筋相互搭接10倍钢筋直径以上;基础、底节段、中间节段、顶帽节段均预埋预应力管道,通过穿入通长预应力束进行连接,采用本案,能够解决预应力拼装墩耗能不足、延性低的缺点。

Figure 202010606957

The invention provides a prefabricated assembled hollow bridge pier with built-in ribs and a construction method, and relates to the technical field of bridge construction. From bottom to top, it includes foundation, bottom segment, middle segment, and top hat segment. The top of the foundation is provided with pre-embedded steel bars, and the stirrups are provided on the pre-embedded steel bars; the bottom segment is provided with solid segments, bottom segments and solid segments. Prefabricated at the same time, the connecting reinforcement channel is reserved on the solid section, and the diameter of the connecting reinforcement channel is 5cm larger than that of the embedded steel bar at the top of the foundation; the channel of the embedded steel bar is filled with post-cast concrete; the bottom section and the middle section are . Rib plates are arranged on the top hat segments, and connecting bars are arranged on each rib plate, and each connecting bar extends out of the corresponding rib plate, and the connecting bars between each segment overlap each other by more than 10 times the diameter of the bars; Sections, middle sections, and top hat sections are all pre-embedded with pre-stressed pipes, which are connected by penetrating through-length pre-stressed bundles. This case can solve the shortcomings of insufficient energy consumption and low ductility of pre-stressed assembled piers.

Figure 202010606957

Description

带内置肋板的预制拼装空心桥墩及施工方法Prefabricated and assembled hollow pier with built-in ribs and construction method

技术领域technical field

本发明涉及桥梁建造技术领域,尤其涉及一种带内置肋板的预制拼装空心桥墩及施工方法。The invention relates to the technical field of bridge construction, in particular to a prefabricated assembled hollow bridge pier with built-in ribs and a construction method.

背景技术Background technique

目前,当桥墩跨越大型河流或海洋时,建设条件恶劣,风浪大、现场有效作业时间短、混凝土浇筑养护困难,不适宜于现浇法施工,采用工厂化、拼装化建造具有较大优势,大大缩短了现场工作时间,提高了工程质量;且水上运输、吊装能力强,可将桥墩划分为大型节段,采用大型机械设备进行拼装,适用于高度较高的空心桥墩;在国内外一些水域或海域桥梁工程中得到应用。At present, when the bridge pier spans a large river or ocean, the construction conditions are harsh, the wind and waves are large, the effective working time on site is short, and the concrete pouring and maintenance are difficult, so it is not suitable for the cast-in-place construction. The on-site work time is shortened and the project quality is improved; and the water transportation and hoisting capabilities are strong, the piers can be divided into large segments, and large mechanical equipment is used for assembly, which is suitable for hollow piers with higher height; in some waters at home and abroad or It has been applied in sea area bridge engineering.

空心桥墩往往高度较高、截面尺寸大,墩壁内外侧均布置有普通钢筋,当采用预制拼装施工时,对密集的钢筋之间进行连接难度大,因此常采用预应力进行连接,即各节段间涂抹环氧树脂胶,再通过预应力束实现节段间的连接。该连接方式节段间仅通过预应力束连接,存在耗能能力不足、延性低等缺点,不适宜与高震区;海上多存在侵蚀性,耐久性要求高,预应力束存在腐蚀风险,若腐蚀严重时会导致连接失效,影响结构安全性,且预应力束位于孔道内,往往不易检查、修复和更换;同时,空心墩高度较高、节段长度较长时,存在墩柱整体稳定和墩壁局部稳定弱等问题。Hollow bridge piers are often high in height and large in section size, and ordinary steel bars are arranged on the inside and outside of the pier wall. When prefabricated and assembled, it is difficult to connect dense steel bars, so prestressing is often used for connection, that is, each section is connected Epoxy resin glue is applied between the segments, and then the connection between segments is realized by prestressed beams. This connection method is only connected by prestressed beams, which has shortcomings such as insufficient energy dissipation capacity and low ductility, and is not suitable for high seismic areas; the sea is mostly corrosive, and the durability requirements are high, and the prestressed beams have the risk of corrosion. Serious corrosion will lead to connection failure and affect the safety of the structure, and the prestressed bundles are located in the tunnel, which is often difficult to inspect, repair and replace. Problems such as weak local stability of the pier wall.

公开于该背景技术部分的信息仅仅旨在加深对本发明的总体背景技术的理解,而不应当被视为承认或以任何形式暗示该信息构成已为本领域技术人员所公知的现有技术。The information disclosed in this Background section is only for enhancement of understanding of the general background of the invention and should not be taken as an acknowledgement or any form of suggestion that this information forms the prior art already known to a person skilled in the art.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供带内置肋板的预制拼装空心桥墩及施工方法,以缓解上述提到的现有技术中存在的问题。The purpose of the present invention is to provide a prefabricated assembled hollow bridge pier with built-in ribs and a construction method, so as to alleviate the above-mentioned problems in the prior art.

为了实现上述目的,本发明采用以下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:

本发明提供的带内置肋板的预制拼装空心桥墩,由下及上依次包括基础、底节段、中间节段、顶帽节段,所述基础顶部设置预埋钢筋,预埋钢筋上设置箍筋,使预埋钢筋具有一定刚度,保证其竖直;预埋钢筋与箍筋形成多个钢筋笼,分散布置在基础上。The prefabricated and assembled hollow bridge pier with built-in ribs provided by the present invention includes a foundation, a bottom segment, a middle segment, and a top hat segment in sequence from bottom to top. The top of the foundation is provided with pre-embedded steel bars, and the pre-embedded steel bars are provided with hoops The pre-embedded steel bar has a certain rigidity to ensure its verticality; the pre-embedded steel bar and the stirrup form a plurality of steel cages, which are scattered on the foundation.

所述底节段下方设置实体段,底节段与实体段一起预制,保证底节段与实体段整体性,实体段上预留连接钢筋孔道,连接钢筋孔道的直径尺寸较基础预埋钢筋每侧大5cm,便于其穿入。A solid section is arranged below the bottom section, and the bottom section and the solid section are prefabricated together to ensure the integrity of the bottom section and the solid section. The connecting steel channel is reserved on the solid section, and the diameter of the connecting steel channel is larger than that of the basic embedded steel bar. The side is 5cm larger to facilitate its penetration.

后浇混凝土,采用微膨胀混凝土或高性能混凝土,填充在预埋钢筋孔道中,锚固预埋钢筋,实现实体段与基础之间的连接。Post-cast concrete, using micro-expansion concrete or high-performance concrete, fills in the pre-embedded steel duct, anchors the embedded steel, and realizes the connection between the solid segment and the foundation.

所述底节段、中间节段、顶帽节段上均设置肋板,每个所述肋板上均设置连接钢筋,每个所述连接钢筋均伸出相应所述肋板一定长度,各节段间的连接钢筋相互搭接10倍钢筋直径以上,浇筑UHPC,实现各节段相互之间的各连接钢筋之间的连接和传力。The bottom segment, the middle segment, and the top hat segment are all provided with rib plates, each of the rib plates is provided with connecting bars, and each of the connecting bars extends out of the corresponding rib by a certain length. The connecting steel bars between the segments are overlapped with each other by more than 10 times the diameter of the steel bars, and UHPC is poured to realize the connection and force transmission between the connecting steel bars of each segment.

所述基础、底节段、中间节段、顶帽节段均预埋预应力管道,通过穿入通长预应力束进行连接,保证各节段间的连接性能;预应力束固定端设置在基础内,通过自锁定式锚具连接,自顶端穿入通长预应力束后在基础内进行锁定,自顶帽节段顶端的张拉端进行张拉,封锚。The foundation, bottom segment, middle segment, and top hat segment are all pre-embedded with prestressed pipes, which are connected by penetrating a full-length prestressed bundle to ensure the connection performance between the segments; the fixed end of the prestressed bundle is set at the In the foundation, connected by self-locking anchors, the top end penetrates the full-length prestressed bundle and then locks in the foundation, and the tensioning end at the top of the top hat segment is tensioned to seal the anchor.

进一步的,多个所述肋板设置在所述底节段、中间节段、顶帽节段的墩壁内侧,沿四周分散布置,多个所述肋板与各节段一起预制。Further, a plurality of the rib plates are arranged on the inner side of the pier wall of the bottom segment, the middle segment, and the top hat segment, and are distributed along the circumference, and the plurality of the rib plates are prefabricated together with each segment.

进一步的,每个所述肋板与被连接节段的上方齐平,每个所述肋板的上部一定位置采用扩大头,扩大头外轮廓较被连接节段的肋板下方尺寸大。Further, each rib is flush with the upper part of the connected segment, and an enlarged head is used at a certain position on the upper part of each rib, and the outer contour of the enlarged head is larger than the size of the lower part of the rib of the connected segment.

进一步的,所述肋板下方较被连接节段的截面尺寸短,肋板下方设置为斜坡形式。Further, the cross-sectional dimension of the lower part of the rib is shorter than that of the connected segment, and the lower part of the rib is arranged in a slope form.

进一步的,每个所述连接钢筋伸出被连接节段的肋板,各连接钢筋之间采用交错布置,位于上方节段的连接钢筋布置在位于下方节段的连接钢筋的中间,穿入后绑扎箍筋,箍筋布置在位于上、下方节段的连接钢筋的四周。Further, each of the connecting reinforcing bars protrudes from the rib of the connected segment, and the connecting reinforcing bars are arranged in a staggered manner, and the connecting reinforcing bars located in the upper segment are arranged in the middle of the connecting reinforcing bars located in the lower segment. The stirrups are bound, and the stirrups are arranged around the connecting bars of the upper and lower segments.

进一步的,每个所述连接钢筋伸出被连接节段的肋板,各连接钢筋之间采用内外布置,当一侧连接钢筋布置外侧时,相应节段预制时在连接钢筋四周绑扎箍筋;当一侧连接钢筋布置在内侧时,相应节段预制时在连接钢筋四周绑扎箍筋,拼装时将内侧连接钢筋穿入外侧连接钢筋中,实现连接。Further, each of the connecting steel bars extends out of the rib of the connected segment, and the connecting steel bars are arranged inside and outside. When one side connecting steel bars are arranged outside, the corresponding segments are prefabricated around the connecting steel bars to bind stirrups; When one side of the connecting steel bar is arranged on the inner side, the stirrups are bound around the connecting steel bar during the prefabrication of the corresponding segment, and the inner connecting steel bar is inserted into the outer connecting steel bar during assembly to realize the connection.

进一步的,所述连接钢筋可从相邻节段的肋板伸出,也可从相邻节段内部伸出。Further, the connecting reinforcing bars may protrude from the ribs of adjacent segments, or may protrude from the interior of adjacent segments.

进一步的,各所述肋板间的浇筑材料采用UHPC;UHPC浇筑在肋板及上下节段间的间隙中。Further, UHPC is used as the casting material between the ribs; UHPC is cast in the gap between the ribs and the upper and lower segments.

本发明提供的一种带内置肋板的预制拼装空心桥墩的施工方法,包括以下步骤:A construction method of a prefabricated assembled hollow bridge pier with a built-in rib plate provided by the present invention comprises the following steps:

步骤一、基础施工,绑扎预埋钢筋的箍筋,底节段、中间节段、顶帽节段预制待拼装;Step 1, foundation construction, tie the stirrups of the pre-embedded steel bars, and prefabricate the bottom section, middle section and top hat section to be assembled;

步骤二、在基础顶面铺设底接缝高强砂浆,吊装底节段进行坐浆法安装,并将预埋钢筋穿入实体段的连接钢筋孔道,并浇筑后浇混凝土;Step 2: Lay high-strength mortar for the bottom joint on the top surface of the foundation, hoist the bottom segment for installation by the grouting method, and insert the pre-embedded steel bar into the connecting steel bar channel of the solid segment, and pour concrete after pouring;

步骤三、在底节段顶面铺设中间接缝环氧树脂胶,吊装中间节段进行安装,将中间节段下连接钢筋与底节段连接钢筋对位,相互穿入或绑扎中间节段接缝箍筋,搭设临时模板,浇筑中间节段UHPC;Step 3: Lay the middle joint epoxy glue on the top surface of the bottom section, hoist the middle section for installation, align the lower connecting steel bar of the middle section and the connecting steel bar of the bottom section, penetrate each other or bind the middle section to connect. Sew stirrups, set up temporary formwork, and pour UHPC in the middle section;

步骤四、在下方中间节段顶面铺设中间接缝环氧树脂胶,吊装上方中间节段,将上方中间节段下连接钢筋与下方中间节段上连接钢筋对位,相互穿入或绑扎中间节段接缝箍筋,搭设临时模板,浇筑中间节段UHPC;Step 4: Lay the middle joint epoxy glue on the top surface of the lower middle section, hoist the upper middle section, align the lower connecting steel bars of the upper middle section with the connecting steel bars of the lower middle section, and penetrate or bind each other in the middle Sectional joint stirrups, temporary formwork erection, intermediate section UHPC pouring;

步骤五、在中间节段顶面铺设中间接缝环氧树脂胶,吊装顶帽节段,将顶帽节段连接钢筋与中间节段上连接钢筋对位,相互穿入或绑扎顶帽节段接缝箍筋,搭设临时模板,浇筑顶帽节段UHPC;Step 5: Lay the middle joint epoxy glue on the top surface of the middle section, hoist the top hat section, align the top hat section connecting steel bars with the connecting steel bars on the middle section, and penetrate or bind the top hat sections. Joint stirrups, temporary formwork erection, UHPC pouring of the top hat segment;

步骤六、自顶帽节段顶端,依次向顶帽节段、中间节段、底节段、基础中预埋预应力管道内穿入通长预应力束,自顶帽节段顶端的张拉端进行张拉,封锚;Step 6: From the top of the top hat segment, penetrate the full-length prestressed bundles into the top hat segment, the middle segment, the bottom segment, and the pre-embedded prestressed pipeline in the foundation in turn, and stretch from the top of the top hat segment. The end is tensioned and the anchor is sealed;

步骤七、对通长预应力束的管道进行压浆。Step 7: grouting the pipeline with the long prestressed beam.

本发明的有益效果为:The beneficial effects of the present invention are:

本发明提供的带内置肋板的预制拼装空心桥墩及施工方法,具有如下效果:The prefabricated assembled hollow bridge pier with built-in rib and the construction method provided by the present invention have the following effects:

1.通过增设连接钢筋,解决预应力拼装墩耗能不足、延性低的缺点,可适宜于高震区;连接钢筋不占用墩壁空间,墩壁上预应力布置灵活、制造简便;连接钢筋施工不受外部环境恶劣条件影响,有利于施工,不影响结构外观;连接钢筋位于结构内部,耐久性好,适应于侵蚀环境;1. By adding connecting steel bars, the shortcomings of insufficient energy consumption and low ductility of prestressed assembled piers can be solved, which can be suitable for high earthquake areas; connecting steel bars do not occupy space on the pier wall, and the prestressing arrangement on the pier wall is flexible and easy to manufacture; the connecting steel bars are constructed It is not affected by the harsh conditions of the external environment, which is conducive to construction and does not affect the appearance of the structure; the connecting steel bars are located inside the structure, which has good durability and is suitable for erosive environments;

2.通过预应力钢束和连接钢筋组合,明显提高了接缝处的连接性能,弥补纯预应力连接存在的预应力束腐蚀、失效等风险,同时减少了所需预应力个数,简化了预应力穿束、张拉等工序;2. Through the combination of prestressed steel bundles and connecting steel bars, the connection performance at the joints is significantly improved, and the risks of corrosion and failure of prestressed bundles existing in pure prestressed connections are compensated. Prestress threading, tensioning and other processes;

3.通过设置肋板提高了节段的稳定性,增大墩柱节段的分节长度,减小接缝个数,提高桥墩整体和墩壁局部稳定性,特别适宜于水域或海域上的高墩;桥墩现浇施工时,受内模板爬模等影响,设置肋板大大增大施工难度,本方案节段采用预制施工,制作简单,有效解决施工不便问题。3. By setting the rib plate, the stability of the segment is improved, the length of the segment of the pier column segment is increased, the number of joints is reduced, and the overall stability of the pier and the local stability of the pier wall is improved, which is especially suitable for water or sea areas. High pier; During the cast-in-place construction of the bridge pier, due to the influence of the climbing formwork of the inner formwork, the setting of the rib plate greatly increases the construction difficulty.

4.通过节段间UHPC兼做结构剪力键,墩壁上不设剪力键,简化了节段制造时特殊模板设置,节省成本和加快节段制造进度;拼装时无需墩壁剪力键的精确对位,加快拼装速度。4. The inter-segment UHPC is also used as a structural shear key, and there is no shear key on the pier wall, which simplifies the setting of special formwork during segment manufacturing, saves costs and speeds up segment manufacturing progress; pier wall shear key is not required during assembly Accurate alignment to speed up assembly.

5.连接钢筋通过UHPC搭接,钢筋连接不用一一对位,方便施工,UHPC接缝浇筑量小,高度小,自密实、免振捣,施工方便。5. The connecting steel bars are lapped by UHPC, and the steel bars do not need to be connected one by one, which is convenient for construction. UHPC joints have small pouring volume, small height, self-compacting, vibration-free, and convenient construction.

6.节段拼装过程可通过绑扎连接钢筋的箍筋对节段进行临时锁定,保证拼装过程中节段的稳定性。6. During the segment assembly process, the segment can be temporarily locked by tying the stirrups connecting the steel bars to ensure the stability of the segment during the assembly process.

7.当墩柱有通航或防撞要求时,墩底设置实体段,实体墩与墩柱一同预制,并与基础间可靠连接。7. When the pier column is required to be navigable or anti-collision, a solid section is set at the bottom of the pier, and the solid pier is prefabricated together with the pier column and is reliably connected to the foundation.

附图说明Description of drawings

为了更清楚地说明本发明具体实施方式或现有技术中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施方式,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to illustrate the specific embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that need to be used in the description of the specific embodiments or the prior art. Obviously, the accompanying drawings in the following description The drawings are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained based on these drawings without creative efforts.

图1是本发明提供的带内置肋板的预制拼装空心桥墩的立面结构示意图;Fig. 1 is the elevational structure schematic diagram of the prefabricated assembled hollow pier with built-in rib provided by the present invention;

图2是本发明提供的带内置肋板的预制拼装空心桥墩的基础结构示意图;2 is a schematic diagram of the basic structure of a prefabricated assembled hollow pier with a built-in rib provided by the present invention;

图3是本发明提供的带内置肋板的预制拼装空心桥墩的底节段结构示意图;3 is a schematic diagram of the bottom segment structure of the prefabricated assembled hollow pier with built-in ribs provided by the present invention;

图4是本发明提供的带内置肋板的预制拼装空心桥墩的中间节段结构示意图;4 is a schematic structural diagram of a middle section of a prefabricated assembled hollow pier with a built-in rib provided by the present invention;

图5是本发明提供的带内置肋板的预制拼装空心桥墩的顶帽节段结构示意图;5 is a schematic structural diagram of a top hat segment of a prefabricated assembled hollow pier with a built-in rib provided by the present invention;

图6是本发明提供的带内置肋板的预制拼装空心桥墩的中间接缝实施例一拼装示意图;6 is a schematic view of the first embodiment of the assembly of the intermediate joints of the prefabricated and assembled hollow piers with built-in ribs provided by the present invention;

图7是本发明提供的带内置肋板的预制拼装空心桥墩的中间接缝实施例二拼装示意图;7 is a schematic diagram of the second embodiment of the assembly of the intermediate joints of the prefabricated and assembled hollow piers with built-in ribs provided by the present invention;

图8是本发明提供的带内置肋板的预制拼装空心桥墩的中间接缝实施例三拼装示意图;8 is a schematic view of the third embodiment of the assembly of the intermediate joints of the prefabricated and assembled hollow piers with built-in ribs provided by the present invention;

图9是本发明提供的带内置肋板的预制拼装空心桥墩的底接缝拼装示意图。FIG. 9 is a schematic view of the bottom seam assembling of the prefabricated assembled hollow pier with built-in ribs provided by the present invention.

图标:icon:

1-基础;1-basic;

101-预埋钢筋;101-Embedded steel bars;

102-箍筋;102 - stirrups;

2-底节段;2 - bottom segment;

201-实体段;201 - entity segment;

202-连接钢筋孔道;202-connecting steel ducts;

203-后浇混凝土;203 - post-cast concrete;

204-底节段肋板;204- bottom segment rib;

205-底节段连接钢筋;205 - Bottom segment connecting reinforcement;

3-中间节段;3 - the middle segment;

301-中间节段肋板;301- Middle segment rib;

302-中间节段下连接钢筋;302 - Connecting steel bars under the middle segment;

303-中间节段接缝箍筋;303 - mid-segment joint stirrup;

304-中间节段UHPC;304 - Intermediate segment UHPC;

305-中间节段上连接钢筋;305 - Connecting steel bars on the middle segment;

4-顶帽节段;4 - top hat segment;

401-顶帽节段肋板;401 - Top hat segment rib;

402-顶帽节段连接钢筋;402 - Top hat segment connecting reinforcement;

403-顶帽节段接缝箍筋;403 - Top hat segment seam stirrups;

404-顶帽节段UHPC;404 - Top Hat Segment UHPC;

5-底接缝;5- Bottom seam;

6-中间接缝;6-Intermediate seam;

7-预应力管道;7- Prestressed pipes;

8-通长预应力束;8- full length prestressed beam;

801-预应力束锚固端;801 - Anchoring end of prestressed beam;

802-预应力束张拉端;802 - Tensioning end of prestressed beam;

803-预应力束封锚;803 - prestressed bundle anchor;

9-压浆;9- grouting;

10-临时模板;10- Temporary template;

11-连接钢筋内侧箍筋。11- Connect the inner stirrups of the rebar.

具体实施方式Detailed ways

下面将结合附图对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

在本发明的描述中,需要说明的是,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性。In the description of the present invention, it should be noted that the terms "first" and "second" are only used for description purposes, and cannot be understood as indicating or implying relative importance.

在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that the terms "installed", "connected" and "connected" should be understood in a broad sense, unless otherwise expressly specified and limited, for example, it may be a fixed connection or a detachable connection Connection, or integral connection; can be mechanical connection, can also be electrical connection; can be directly connected, can also be indirectly connected through an intermediate medium, can be internal communication between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood in specific situations.

实施例Example

如图1-9所示,一种带内置肋板的预制拼装空心桥墩,由下及上依次包括基础1、底节段2、中间节段3、顶帽节段4,基础1顶部设置预埋钢筋101,预埋钢筋101上设置箍筋102,使预埋钢筋101具有一定刚度,保证其竖直;预埋钢筋101与箍筋102形成多个钢筋笼,分散布置在基础1上。As shown in Figure 1-9, a prefabricated assembled hollow pier with built-in ribs includes foundation 1, bottom segment 2, middle segment 3, and top hat segment 4 in order from bottom to top. The embedded steel bar 101 is provided with stirrups 102 on the embedded steel bar 101, so that the embedded steel bar 101 has a certain rigidity and ensures that it is vertical;

底节段2下方设置实体段201,底节段2与实体段201一起预制,保证底节段2与实体段201整体性,实体段201上预留连接钢筋孔道202,连接钢筋孔道202的直径尺寸较基础1预埋钢筋101每侧大5cm,便于其穿入。A solid section 201 is arranged below the bottom section 2, and the bottom section 2 is prefabricated together with the solid section 201 to ensure the integrity of the bottom section 2 and the solid section 201. The solid section 201 is reserved for connecting steel bar holes 202, and the diameter of the connecting steel bar holes 202 The size is 5cm larger than that of the embedded steel bar 101 of the foundation 1 on each side, which is convenient for its penetration.

后浇混凝土203,采用微膨胀混凝土或高性能混凝土,填充在预埋钢筋101孔道中,锚固预埋钢筋101,实现实体段201与基础1之间的连接。The post-cast concrete 203 is made of micro-expanded concrete or high-performance concrete, filled in the holes of the pre-embedded steel bars 101 , and anchored to the pre-embedded steel bars 101 to realize the connection between the solid section 201 and the foundation 1 .

底节段2、中间节段3、顶帽节段4上均设置肋板,每个肋板上均设置连接钢筋,每个连接钢筋均伸出相应肋板一定长度,各节段间的连接钢筋相互搭接10倍钢筋直径以上,浇筑UHPC,实现各节段相互之间的各连接钢筋之间的连接和传力。The bottom segment 2, the middle segment 3, and the top hat segment 4 are all provided with ribs, and each rib is provided with connecting steel bars, and each connecting steel bar extends out of the corresponding rib for a certain length. The steel bars are overlapped with each other by more than 10 times the diameter of the steel bars, and UHPC is poured to realize the connection and force transmission between the connecting steel bars of each segment.

基础1、底节段2、中间节段3、顶帽节段4均预埋预应力管道7,通过穿入通长预应力束8进行连接,保证各节段间的连接性能;预应力束锚固端801设置在基础1内,通过自锁定式锚具连接,自顶端穿入通长预应力束8后在基础1内进行锁定,自顶帽节段4顶端的预应力束张拉端802进行张拉,进行预应力束封锚803。Foundation 1, bottom section 2, middle section 3, and top hat section 4 are all pre-embedded with pre-stressed pipes 7, which are connected by penetrating through-length pre-stressed bundles 8 to ensure the connection performance between segments; pre-stressed bundles The anchoring end 801 is set in the foundation 1, connected by a self-locking anchor, penetrates the full-length prestressed bundle 8 from the top and locks in the foundation 1, and stretches the end 802 from the prestressed bundle at the top of the top hat segment 4 Tension is performed, and prestressed bundle anchors 803 are performed.

进一步的,多个肋板设置在底节段2、中间节段3、顶帽节段4的墩壁内侧,沿四周分散布置,多个肋板与各节段一起预制。Further, a plurality of ribs are arranged on the inner side of the pier wall of the bottom section 2, the middle section 3, and the top hat section 4, and are distributed along the circumference, and the plurality of ribs are prefabricated together with each section.

进一步的,每个肋板与被连接节段的上方齐平,每个肋板的上部一定位置采用扩大头,扩大头外轮廓较被连接节段的肋板下方尺寸大。Further, each rib is flush with the upper part of the connected segment, and an enlarged head is used at a certain position on the upper part of each rib, and the outer contour of the enlarged head is larger than the size of the lower part of the rib of the connected segment.

具体的,每个底节段肋板204上方与底节段2顶面齐平,每个底节段肋板204上部一定位置采用扩大头,扩大头外轮廓较被连接节段的肋板下方尺寸大。Specifically, the top of each bottom segment rib 204 is flush with the top surface of the bottom segment 2, an enlarged head is used at a certain position on the upper part of each bottom segment rib 204, and the outer contour of the enlarged head is lower than the lower part of the rib of the connected segment. Large size.

具体的,每个中间节段肋板301上方与中间节段3齐平,每个中间节段肋板301上部一定位置采用扩大头,扩大头外轮廓较被连接的肋板下方尺寸大,下部较中间节段3底部短,肋板下方设置为斜坡形式,便于UHPC浇筑及密实度。Specifically, the top of each intermediate segment rib 301 is flush with the intermediate segment 3, and the upper part of each intermediate segment rib 301 adopts an enlarged head at a certain position. It is shorter than the bottom of the middle section 3, and the bottom of the rib is set as a slope, which is convenient for UHPC pouring and compactness.

进一步的,肋板较下方被连接节段的截面尺寸短,肋板下方设置为斜坡形式。Further, the cross-sectional dimension of the rib is shorter than that of the connected segment below, and the lower part of the rib is set in the form of a slope.

具体的,顶帽节段肋板401下方较顶帽节段4底部短,下方设置为斜坡形式,便于UHPC浇筑及密实度。Specifically, the bottom of the top hat segment rib 401 is shorter than the bottom of the top hat segment 4, and the bottom is set in a slope form, which is convenient for UHPC pouring and compactness.

如图6所示,每个连接钢筋伸出被连接节段的肋板,各连接钢筋之间采用交错布置,位于上方节段的连接钢筋布置在位于下方节段的连接钢筋的中间,穿入后绑扎箍筋102,箍筋102布置在位于上、下方节段的连接钢筋的四周。As shown in Figure 6, each connecting steel bar protrudes from the rib of the connected segment, and the connecting steel bars are arranged in a staggered manner. The stirrups 102 are then bound, and the stirrups 102 are arranged around the connecting bars of the upper and lower segments.

具体的,连接钢筋利用肋板内部布置的普通钢筋,伸出底节段2、中间节段3、顶帽节段4的肋板。Specifically, the connecting reinforcing bars use ordinary reinforcing bars arranged inside the rib to extend out of the rib of the bottom segment 2, the middle segment 3, and the top hat segment 4.

需要指出的是,底节段连接钢筋205伸出底节段肋板204上方,中间节段下连接钢筋302伸出中间节段肋板301下方,底节段连接钢筋205和中间节段下连接钢筋302平面位置相互错开,便于穿入,保证搭接长度不小于10倍的钢筋直径,四周布置中间节段接缝箍筋303,加强连接。It should be pointed out that the bottom segment connecting bars 205 protrude above the bottom segment rib 204, the middle segment lower connecting bars 302 protrude below the middle segment rib 301, and the bottom segment connecting bars 205 are connected to the lower middle segment. The plane positions of the steel bars 302 are staggered to each other, which is easy to penetrate, to ensure that the overlapping length is not less than 10 times the diameter of the steel bars, and the middle section joint stirrups 303 are arranged around to strengthen the connection.

还需要指出的是,中间节段上连接钢筋305伸出中间节段肋板301上方,顶帽节段连接钢筋402伸出顶帽节段肋板401下方,中间节段上连接钢筋305和顶帽节段连接钢筋402平面位置相互错开,便于穿入,保证搭接长度不小于10倍的钢筋直径,四周布置顶帽节段4箍筋102,加强连接。It should also be pointed out that the connecting steel bars 305 on the middle section protrude above the middle section rib 301, the top hat section connecting steel bars 402 protrude below the top hat section rib 401, and the middle section connecting steel bars 305 and the top hat section. The plane positions of the connecting bars 402 of the hat segment are staggered to each other, which is easy to penetrate, ensuring that the overlap length is not less than 10 times the diameter of the bar, and the top hat segment 4 stirrups 102 are arranged around to strengthen the connection.

如图7所示,每个连接钢筋伸出被连接节段的肋板,各连接钢筋之间采用内外布置,当一侧连接钢筋布置外侧时,相应节段预制时在连接钢筋四周绑扎箍筋102;当一侧连接钢筋布置在内侧时,即形成连接钢筋内侧箍筋11,相应节段预制时在连接钢筋四周绑扎箍筋102,拼装时将内侧连接钢筋穿入外侧连接钢筋中,实现连接。As shown in Figure 7, each connecting steel bar protrudes from the rib of the connected segment, and the connecting steel bars are arranged inside and outside. When one side connecting steel bar is arranged on the outside, the corresponding segment is prefabricated and the stirrups are bound around the connecting steel bar. 102; when one side of the connecting steel bar is arranged on the inside, the inner stirrup 11 of the connecting steel bar is formed. When the corresponding segment is prefabricated, the stirrups 102 are bound around the connecting steel bar, and the inner connecting steel bar is inserted into the outer connecting steel bar during assembly to realize the connection. .

如图8所示,连接钢筋可从相邻节段的肋板伸出,也可从相邻节段内部伸出。As shown in FIG. 8 , the connecting bars can protrude from the ribs of adjacent segments, and can also protrude from the interior of adjacent segments.

另外,各肋板间的浇筑材料采用UHPC,即UHPC浇筑在肋板及上下节段间的间隙中。In addition, the pouring material between each rib is UHPC, that is, UHPC is poured in the gap between the rib and the upper and lower segments.

UHPC浇筑与各肋板之间,连接肋板间伸出的连接钢筋,尺寸与被连接的下方肋板扩大同头相同,浇筑时从临时模板10与被连接的上方节段肋板间的间隙浇筑;高度不小于10倍的连接钢筋直径,保证连接钢筋连接牢靠;现浇UHPC与预制的上下肋板、墩壁间连接牢靠,兼做预制结构间的剪力键;UHPC浇筑量小,高度小,自密实、免振捣,施工方便。Between UHPC pouring and each rib, the connecting steel bars extending from the connecting rib have the same size as the expansion of the lower rib to be connected, and the gap between the temporary formwork 10 and the connected upper segment rib during pouring Pouring; the height is not less than 10 times the diameter of the connecting steel bar to ensure the reliable connection of the connecting steel bar; the connection between the cast-in-place UHPC and the prefabricated upper and lower ribs and pier walls is firm, and it also serves as the shear key between the prefabricated structures; the UHPC pouring volume is small and the height Small, self-compacting, vibration-free, and easy to construct.

本发明实施例提供的一种带内置肋板的预制拼装空心桥墩的施工方法,包括以下步骤:A construction method of a prefabricated assembled hollow bridge pier with a built-in rib provided by an embodiment of the present invention includes the following steps:

步骤一、基础1施工,绑扎预埋钢筋101的箍筋102,底节段2、中间节段3、顶帽节段4预制待拼装;Step 1, the foundation 1 is constructed, the stirrups 102 of the pre-embedded steel bars 101 are bound, the bottom segment 2, the middle segment 3, and the top hat segment 4 are prefabricated and assembled;

步骤二、在基础1顶面铺设底接缝5高强砂浆,吊装底节段2进行坐浆法安装,并将预埋钢筋101穿入实体段201的连接钢筋孔道202,并浇筑后浇混凝土203;Step 2: Lay the bottom joint 5 high-strength mortar on the top surface of the foundation 1, hoist the bottom section 2 for grouting installation, and insert the embedded steel bar 101 into the connecting steel bar channel 202 of the solid section 201, and pour concrete 203 after pouring ;

步骤三、在底节段2顶面铺设中间接缝6环氧树脂胶,吊装中间节段3进行安装,将中间节段下连接钢筋302与底节段连接钢筋205对位,相互穿入或绑扎中间节段接缝箍筋303102,搭设临时模板10,浇筑中间节段UHPC304;Step 3: Lay the middle joint 6 epoxy glue on the top surface of the bottom section 2, hoist the middle section 3 for installation, align the lower connecting steel bar 302 of the middle section and the connecting steel bar 205 of the bottom section, penetrate each other or Bind the joint stirrups 303102 of the middle section, set up the temporary formwork 10, and pour the middle section UHPC304;

步骤四、在下方中间节段3顶面铺设中间接缝6环氧树脂胶,吊装上方中间节段3,将上方中间节段下连接钢筋302与下方中间节段上连接钢筋305对位,相互穿入或绑扎中间节段接缝箍筋303102,搭设临时模板10,浇筑中间节段UHPC304;Step 4: Lay the middle joint 6 epoxy glue on the top surface of the lower middle section 3, hoist the upper middle section 3, and align the lower connecting steel bar 302 of the upper middle section with the connecting steel bar 305 of the lower middle section, so that they are mutually Pierce or bind the joint stirrups 303102 in the middle section, set up the temporary formwork 10, and pour the middle section UHPC304;

步骤五、在中间节段3顶面铺设中间接缝6环氧树脂胶,吊装顶帽节段4,将顶帽节段连接钢筋402与中间节段上连接钢筋305对位,相互穿入或绑扎顶帽节段接缝箍筋403102,搭设临时模板10,浇筑顶帽节段UHPC404;Step 5: Lay the middle joint 6 epoxy glue on the top surface of the middle section 3, hoist the top hat section 4, align the top hat section connecting steel bar 402 with the connecting steel bar 305 on the middle section, penetrate each other or Binding the joint stirrups 403102 of the top hat segment, erecting the temporary formwork 10, and pouring the top hat segment UHPC404;

步骤六、自顶帽节段4顶端,依次向顶帽节段4、中间节段3、底节段2、基础1中预埋预应力管道7内穿入通长预应力束8,自顶帽节段4顶端的张拉端进行张拉,封锚;Step 6: From the top of the top hat segment 4, penetrate the long prestressed bundle 8 into the top hat segment 4, the middle segment 3, the bottom segment 2, and the pre-embedded prestressed pipe 7 in the foundation 1 in turn, and from the top The tension end at the top of the cap segment 4 is tensioned to seal the anchor;

步骤七、对通长预应力束8的管道进行压浆9。Step 7, grouting 9 the pipes of the long prestressed bundles 8 .

本发明实施例提供的带内置肋板的预制拼装空心桥墩及施工方法,具有如下效果:The prefabricated assembled hollow bridge pier with built-in rib and the construction method provided by the embodiment of the present invention have the following effects:

1.通过增设连接钢筋,解决预应力拼装墩耗能不足、延性低的缺点,可适宜于高震区;连接钢筋不占用墩壁空间,墩壁上预应力布置灵活、制造简便;连接钢筋施工不受外部环境恶劣条件影响,有利于施工,不影响结构外观;连接钢筋位于结构内部,耐久性好,适应于侵蚀环境;1. By adding connecting steel bars, the shortcomings of insufficient energy consumption and low ductility of prestressed assembled piers can be solved, which can be suitable for high earthquake areas; connecting steel bars do not occupy space on the pier wall, and the prestressing arrangement on the pier wall is flexible and easy to manufacture; the connecting steel bars are constructed It is not affected by the harsh conditions of the external environment, which is conducive to construction and does not affect the appearance of the structure; the connecting steel bars are located inside the structure, which has good durability and is suitable for erosive environments;

2.通过预应力钢束和连接钢筋组合,明显提高了接缝处的连接性能,弥补纯预应力连接存在的预应力束腐蚀、失效等风险,同时减少了所需预应力个数,简化了预应力穿束、张拉等工序;2. Through the combination of prestressed steel bundles and connecting steel bars, the connection performance at the joints is significantly improved, and the risks of corrosion and failure of prestressed bundles existing in pure prestressed connections are compensated. Prestress threading, tensioning and other processes;

3.通过设置肋板提高了节段的稳定性,增大墩柱节段的分节长度,减小接缝个数,提高桥墩整体和墩壁局部稳定性,特别适宜于水域或海域上的高墩;桥墩现浇施工时,受内模板爬模等影响,设置肋板大大增大施工难度,本方案节段采用预制施工,制作简单,有效解决施工不便问题。3. By setting the rib plate, the stability of the segment is improved, the length of the segment of the pier column segment is increased, the number of joints is reduced, and the overall stability of the pier and the local stability of the pier wall is improved, which is especially suitable for water or sea areas. High pier; During the cast-in-place construction of the bridge pier, due to the influence of the climbing formwork of the inner formwork, the setting of the rib plate greatly increases the construction difficulty.

4.通过节段间UHPC兼做结构剪力键,墩壁上不设剪力键,简化了节段制造时特殊模板设置,节省成本和加快节段制造进度;拼装时无需墩壁剪力键的精确对位,加快拼装速度。4. The inter-segment UHPC is also used as a structural shear key, and there is no shear key on the pier wall, which simplifies the setting of special formwork during segment manufacturing, saves costs and speeds up segment manufacturing progress; pier wall shear key is not required during assembly Accurate alignment to speed up assembly.

5.连接钢筋通过UHPC搭接,钢筋连接不用一一对位,方便施工,UHPC接缝浇筑量小,高度小,自密实、免振捣,施工方便。5. The connecting steel bars are lapped by UHPC, and the steel bars do not need to be connected one by one, which is convenient for construction. UHPC joints have small pouring volume, small height, self-compacting, vibration-free, and convenient construction.

6.节段拼装过程可通过绑扎连接钢筋的箍筋102对节段进行临时锁定,保证拼装过程中节段的稳定性。6. During the segment assembling process, the segment can be temporarily locked by binding the stirrups 102 connecting the reinforcing bars to ensure the stability of the segment during the assembling process.

7.当墩柱有通航或防撞要求时,墩底设置实体段201,实体墩与墩柱一同预制,并与基础1间可靠连接。7. When the pier column has requirements for navigation or anti-collision, a solid section 201 is set at the bottom of the pier, and the solid pier and the pier column are prefabricated together and connected with the foundation 1 reliably.

最后应说明的是:以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明实施例技术方案的范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that it can still be The technical solutions described in the foregoing embodiments are modified, or some or all of the technical features thereof are equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention.

Claims (10)

1. The utility model provides a hollow pier is assembled in prefabrication of built-in floor in area, by down and on include basis (1), end festival section (2), middle festival section (3), top cap festival section (4) in proper order, its characterized in that:
the top of the foundation (1) is provided with embedded steel bars (101), and the embedded steel bars (101) are provided with stirrups (102);
a solid section (201) is arranged below the bottom section (2), the bottom section (2) and the solid section (201) are prefabricated together, a connecting steel bar hole (202) is reserved in the solid section (201), and the diameter of the connecting steel bar hole (202) is 5cm larger than that of each side of an embedded steel bar (101) at the top of the foundation (1);
post-cast concrete (203) is filled in the pore channel of the embedded steel bar (101);
ribbed plates are arranged on the bottom section (2), the middle section (3) and the top cap section (4), each ribbed plate is provided with a connecting steel bar, each connecting steel bar extends out of the corresponding ribbed plate, and the connecting steel bars among the sections are mutually lapped by more than 10 times of the diameter of the steel bar;
the foundation (1), the bottom section (2), the middle section (3) and the top cap section (4) are all pre-embedded with prestressed pipelines (7) and are connected by penetrating through long prestressed tendons (8).
2. The precast assembled hollow pier with the built-in rib plate as claimed in claim 1, wherein the embedded steel bars (101) and the stirrups (102) form a plurality of reinforcement cages which are dispersedly arranged on the foundation (1).
3. The precast assembled hollow pier with built-in ribs according to claim 1, wherein a plurality of ribs are provided inside the pier walls of the bottom segment (2), the middle segment (3) and the top cap segment (4) and are distributed around, and the plurality of ribs are precast together with the segments.
4. The prefabricated assembled hollow pier with the built-in rib plates as claimed in claim 1, wherein each rib plate is flush with the upper part of the connected segment, an enlarged head is adopted at a certain position of the upper part of each rib plate, and the outer contour of the enlarged head is larger than the size of the lower part of the rib plate of the connected segment.
5. The precast assembled hollow pier with the built-in rib plate as claimed in claim 4, wherein the rib plate has a shorter sectional dimension than the lower connected segment, and the lower part of the rib plate is provided in a slope form.
6. The prefabricated assembled hollow pier with the built-in ribbed plates according to claim 1, wherein each connecting steel bar extends out of the ribbed plates of the connected sections, the connecting steel bars are arranged in a staggered mode, the connecting steel bar positioned on the upper section is arranged in the middle of the connecting steel bar positioned on the lower section, a binding stirrup (102) is penetrated, and the binding stirrups (102) are arranged on the periphery of the connecting steel bars positioned on the upper section and the lower section.
7. The prefabricated assembled hollow pier with the built-in ribbed plates according to claim 1, wherein each connecting steel bar extends out of the ribbed plates of the connected segments, the connecting steel bars are arranged inside and outside, and when the connecting steel bar on one side is arranged on the outer side, stirrups (102) are bound around the connecting steel bar when the corresponding segment is prefabricated; when one side connecting reinforcement is arranged in the inner side, stirrups are bound around the connecting reinforcement when corresponding sections are prefabricated, and the inner side connecting reinforcement penetrates into the outer side connecting reinforcement during assembling.
8. The precast assembled hollow pier with the built-in rib plate according to claim 1, wherein the connecting reinforcement includes rib plate reinforcements and pier column reinforcements.
9. The prefabricated assembled hollow pier with the built-in ribbed plates according to claim 1, wherein UHPC is adopted as a casting material between the ribbed plates.
10. A construction method of a prefabricated assembled hollow pier with built-in ribbed slabs is characterized by comprising the following steps:
firstly, constructing a foundation (1), binding stirrups (102) of embedded steel bars (101), and prefabricating a bottom section (2), a middle section (3) and a top cap section (4) to be assembled;
secondly, paving high-strength mortar at a bottom joint (5) on the top surface of the foundation (1), hoisting the bottom section (2) for installation by a mortar sitting method, penetrating the embedded steel bars (101) into a connecting steel bar hole channel (202) of the solid section (201), and pouring post-cast concrete (203);
laying an epoxy resin adhesive of a middle joint (6) on the top surface of the bottom section (2), hoisting the middle section (3) for installation, aligning a lower connecting steel bar (302) of the middle section with a connecting steel bar (205) of the bottom section, mutually penetrating or binding a joint stirrup (303) of the middle section, erecting a temporary template, and pouring a UHPC of the middle section;
fourthly, laying epoxy resin glue of a middle joint (6) on the top surface of the lower middle section (3), hoisting the upper middle section (3), aligning a lower connecting steel bar (302) of the upper middle section with an upper connecting steel bar (305) of the lower middle section, mutually penetrating or binding a joint stirrup (303) of the middle section, erecting a temporary template, and pouring a UHPC of the middle section;
laying epoxy resin glue of a middle joint (6) on the top surface of the middle section (3), hoisting the top cap section (4), aligning a top cap section connecting steel bar (402) with a middle section upper connecting steel bar (305), mutually penetrating or binding a top cap section joint stirrup (403), erecting a temporary template, and pouring a top cap section UHPC;
penetrating full-length prestressed bundles (8) into pre-buried prestressed pipelines (7) of the foundation (1), the bottom section (2), the middle section (3) and the top cap section (4) from the top end of the top cap section (4), and tensioning and sealing the anchor from a tensioning end at the top end of the top cap section (4);
and seventhly, grouting (9) is carried out on the pipeline with the full length of the prestressed tendons (8).
CN202010606957.6A 2020-06-29 2020-06-29 Prefabricated assembled hollow pier with built-in rib plates and construction method Active CN111827095B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010606957.6A CN111827095B (en) 2020-06-29 2020-06-29 Prefabricated assembled hollow pier with built-in rib plates and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010606957.6A CN111827095B (en) 2020-06-29 2020-06-29 Prefabricated assembled hollow pier with built-in rib plates and construction method

Publications (2)

Publication Number Publication Date
CN111827095A true CN111827095A (en) 2020-10-27
CN111827095B CN111827095B (en) 2024-06-25

Family

ID=72900747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010606957.6A Active CN111827095B (en) 2020-06-29 2020-06-29 Prefabricated assembled hollow pier with built-in rib plates and construction method

Country Status (1)

Country Link
CN (1) CN111827095B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112853947A (en) * 2021-03-22 2021-05-28 新疆铁道勘察设计院有限公司 Prestress connecting device of railway prefabricated pier
CN113106852A (en) * 2021-05-14 2021-07-13 上海市政工程设计研究总院(集团)有限公司 Light modularized prefabricated assembled pier structure
CN113481870A (en) * 2021-08-11 2021-10-08 柳州欧维姆机械股份有限公司 Prestressed anchoring structure system for assembling multi-segment bridge pier and assembling construction method of multi-segment bridge pier

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08246416A (en) * 1995-03-13 1996-09-24 Hazama Gumi Ltd Pier structure
DE19955553A1 (en) * 1999-11-18 2001-06-07 Maurer Friedrich Soehne Vibration damping assembly with fluid bath containing pair of plates which with two components produces gearing to reduce speed of movement with viscous friction
KR20040046673A (en) * 2002-11-28 2004-06-05 동양종합건업 주식회사 Precast Tall Pier for Bridge and Constructing Method therefor
KR20110008752A (en) * 2009-07-21 2011-01-27 한국건설기술연구원 Precast Segment with Reinforced Concrete Hole and Its Application
CN107794837A (en) * 2016-08-31 2018-03-13 南京理工大学 Suitable for the prefabricated assembled bridge pier and its construction method of middle meizoseismal area
CN107806010A (en) * 2017-10-23 2018-03-16 南京林业大学 A kind of assembled multiple tube seawater marine sand concrete bridge pier and preparation method
CN108678225A (en) * 2018-06-29 2018-10-19 北京工业大学 The built-in steel plate combined shear wall of built-in presstressed reinforcing steel steel pipe concrete frame and the practice
CN109162199A (en) * 2018-10-24 2019-01-08 湖南大学 Assembling-type precast pier connection structure and its construction method
CN109183607A (en) * 2018-10-23 2019-01-11 湖南大学 Precast spliced UHPC pipe-concrete super-high pier and construction method
CN109457599A (en) * 2018-11-29 2019-03-12 福州大学 Hollow pier and cushion cap splicing construction and construction method
CA3050661A1 (en) * 2018-07-25 2020-01-25 Terracon Consultants, Inc. Concrete pier foundation with lateral shear reinforcing loops and methods of constructing the same
CN111270601A (en) * 2020-03-25 2020-06-12 深圳市市政工程总公司 Connection structure of prefabricated hollow bridge pier column and sunken bearing platform with external notch

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08246416A (en) * 1995-03-13 1996-09-24 Hazama Gumi Ltd Pier structure
DE19955553A1 (en) * 1999-11-18 2001-06-07 Maurer Friedrich Soehne Vibration damping assembly with fluid bath containing pair of plates which with two components produces gearing to reduce speed of movement with viscous friction
KR20040046673A (en) * 2002-11-28 2004-06-05 동양종합건업 주식회사 Precast Tall Pier for Bridge and Constructing Method therefor
KR20110008752A (en) * 2009-07-21 2011-01-27 한국건설기술연구원 Precast Segment with Reinforced Concrete Hole and Its Application
CN107794837A (en) * 2016-08-31 2018-03-13 南京理工大学 Suitable for the prefabricated assembled bridge pier and its construction method of middle meizoseismal area
CN107806010A (en) * 2017-10-23 2018-03-16 南京林业大学 A kind of assembled multiple tube seawater marine sand concrete bridge pier and preparation method
CN108678225A (en) * 2018-06-29 2018-10-19 北京工业大学 The built-in steel plate combined shear wall of built-in presstressed reinforcing steel steel pipe concrete frame and the practice
CA3050661A1 (en) * 2018-07-25 2020-01-25 Terracon Consultants, Inc. Concrete pier foundation with lateral shear reinforcing loops and methods of constructing the same
CN109183607A (en) * 2018-10-23 2019-01-11 湖南大学 Precast spliced UHPC pipe-concrete super-high pier and construction method
CN109162199A (en) * 2018-10-24 2019-01-08 湖南大学 Assembling-type precast pier connection structure and its construction method
CN109457599A (en) * 2018-11-29 2019-03-12 福州大学 Hollow pier and cushion cap splicing construction and construction method
CN111270601A (en) * 2020-03-25 2020-06-12 深圳市市政工程总公司 Connection structure of prefabricated hollow bridge pier column and sunken bearing platform with external notch

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112853947A (en) * 2021-03-22 2021-05-28 新疆铁道勘察设计院有限公司 Prestress connecting device of railway prefabricated pier
CN113106852A (en) * 2021-05-14 2021-07-13 上海市政工程设计研究总院(集团)有限公司 Light modularized prefabricated assembled pier structure
CN113481870A (en) * 2021-08-11 2021-10-08 柳州欧维姆机械股份有限公司 Prestressed anchoring structure system for assembling multi-segment bridge pier and assembling construction method of multi-segment bridge pier

Also Published As

Publication number Publication date
CN111827095B (en) 2024-06-25

Similar Documents

Publication Publication Date Title
CN104831617B (en) Steel-Ultra High Performance Concrete Composite Beam Based on Ribbed Deck and Its Construction Method
CN111827092A (en) Applicable to prefabricated and assembled hollow piers with diaphragms and construction methods
CN108086994A (en) One kind passes through unfavourable geological tunnel set bridge underground structure and construction method
CN105735112A (en) Bolt connection-based rapid assembling precast rectangular concrete filled steel tube bridge pier
CN115045181A (en) A kind of connection method and structure of prefabricated pier column-cap socket type joint in medium and high intensity area
CN108442239A (en) A kind of full assembled light abutment and its construction method
CN110042741A (en) A kind of casing constraint Precast Concrete Segmental Bridges pier stud and its construction method
CN107675610A (en) A kind of construction and the practice of the connection of precast assembly bridge pier section
CN108560544A (en) A kind of sleeve connection assembled pile foundation and its construction method
CN110578287A (en) A prefabricated soil-covered corrugated steel plate-prestressed concrete composite arch bridge and its construction method
CN111827095A (en) Prefabricated and assembled hollow pier with built-in ribs and construction method
CN110847020A (en) Steel pipe pile steel trestle end and construction method
CN202000251U (en) Cylindrical hollow prefabricated prestressed concrete pier structure
CN115182235A (en) A kind of prefabricated cover beam pier-column composite structure and its construction method
CN111979894A (en) A steel column and concrete bearing platform connection structure and construction method thereof
CN116517191B (en) Mixed reinforcement precast concrete column with spiral stirrup core column and assembly method thereof
CN212103636U (en) A prefabricated assembled hollow pier based on UHPC joints
CN209114299U (en) A single box multi-chamber box girder bridge
CN114232892B (en) Fabricated concrete connection structure connected through segmented reinforcing steel bars and construction method thereof
CN111827091A (en) Prefabricated and assembled hollow piers connected by prestress and construction method
CN111851564A (en) An assembled type cap plate structure and construction method connected with pile foundation
CN212103631U (en) A large beam and high column prefabricated assembled frame pier
CN212561132U (en) Prefabricated and assembled hollow piers with built-in ribs
CN219604138U (en) A bridge pier protection cover
CN110863424A (en) Vertical tenon and horizontal anchor splicing structure of pier and capping beam and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant