CN111827084A - A frame pier connected by a steel beam and a concrete column and a construction method - Google Patents

A frame pier connected by a steel beam and a concrete column and a construction method Download PDF

Info

Publication number
CN111827084A
CN111827084A CN202010606634.7A CN202010606634A CN111827084A CN 111827084 A CN111827084 A CN 111827084A CN 202010606634 A CN202010606634 A CN 202010606634A CN 111827084 A CN111827084 A CN 111827084A
Authority
CN
China
Prior art keywords
steel
pier
concrete
column
steel beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010606634.7A
Other languages
Chinese (zh)
Inventor
孙树礼
苏伟
张帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
China State Railway Group Co Ltd
Original Assignee
China Railway Design Corp
China State Railway Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp, China State Railway Group Co Ltd filed Critical China Railway Design Corp
Priority to CN202010606634.7A priority Critical patent/CN111827084A/en
Publication of CN111827084A publication Critical patent/CN111827084A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a frame pier connected with a concrete column through a steel cross beam and a construction method, and relates to the technical field of bridge construction. The frame pier comprises a steel cross beam and a pier stud, a steel-concrete combination section is arranged at the joint of the steel cross beam and the pier stud, the steel-concrete combination section comprises a top steel plate, a bottom steel plate and a vertical plate, shear nails, stiffening ribs and rib plates are arranged on the steel-concrete structure section, a pier stud transition section is arranged above the pier stud, main ribs and the reinforcing ribs extend out of the top of the pier stud by preset lengths, during assembly, the main ribs and the reinforcing ribs on the pier stud penetrate through reserved holes in the bottom steel plate of the steel cross beam, post-cast concrete is poured into pouring holes in the top steel plate, post-cast concrete is cured, and after post-cast concrete curing is completed, connection between the steel cross beam and the pier stud is realized; the construction method corresponds to the structure of a frame pier. The structure and the construction method have small influence on the railway and the road below, the construction safety risk is small, the assembling speed of the beam and the pier stud is high, the stress is reliable, the cost is low, and the foundation stress can be reduced.

Description

一种通过钢横梁与混凝土柱连接的框架桥墩及施工方法A frame pier connected by a steel beam and a concrete column and a construction method

技术领域technical field

本发明涉及桥梁建造技术领域,尤其涉及一种通过钢横梁与混凝土柱连接的框架桥墩及施工方法。The invention relates to the technical field of bridge construction, in particular to a frame bridge pier connected by a steel beam and a concrete column and a construction method.

背景技术Background technique

铁路、市政、公路等工程与既有铁路、道路等小角度交叉时,常采用框架型桥墩,利用框架墩跨越障碍物,再在框架墩上方设置简支梁等小跨度梁体,具有较好的经济性。When railways, municipalities, highways and other projects intersect with existing railways, roads, etc. at small angles, frame piers are often used, and frame piers are used to span obstacles, and then small-span beams such as simply supported beams are set above the frame piers, which has better performance. economy.

以往,框架桥墩常采用现浇施工,墩柱和横梁采用支架法施工,支架搭设高度高、施工风险大、施工干扰大,而横梁若采用预制拼装法施工,能显著提高施工速度、减小施工干扰;横梁常采用钢结构,钢结构具有自重轻、便于运输吊装,特别适用于大跨度横梁等优点,但存在钢横梁与墩柱间的接头处受力复杂,钢混连接构造处理难度大,以及如何保证钢横梁与墩柱间快速拼装等问题;同时,框架墩若钢横梁与墩柱间采用一次拼装完成,两者间形成固结,则框架墩上方上部梁体的一期自重、桥面附属等二期自重均造成墩底受弯,从而增大了基础的受力,往往造成基础设计困难。因此,研发一种通过钢横梁与混凝土柱连接的框架桥墩及施工方法是个亟待解决的问题。In the past, the frame piers were often constructed by cast-in-place construction, and the piers and beams were constructed by the bracket method. The height of the brackets is high, the construction risk is large, and the construction interference is large. If the beams are constructed by the prefabricated assembly method, the construction speed can be significantly improved. Interference; beams are often made of steel structures. Steel structures have the advantages of light weight, easy transportation and hoisting, and are especially suitable for large-span beams. However, there are complex forces at the joints between steel beams and pier columns. And how to ensure the rapid assembly between the steel beam and the pier column; at the same time, if the steel beam and the pier column of the frame pier are assembled at one time, and the two are consolidated, the first-phase self-weight of the upper beam body above the frame pier, the bridge The self-weight of the second phase, such as the surface attachment, will cause the pier bottom to be bent, which will increase the stress of the foundation and often cause foundation design difficulties. Therefore, it is an urgent problem to develop a frame pier connected by a steel beam and a concrete column and a construction method.

公开于该背景技术部分的信息仅仅旨在加深对本发明的总体背景技术的理解,而不应当被视为承认或以任何形式暗示该信息构成已为本领域技术人员所公知的现有技术。The information disclosed in this Background section is only for enhancement of understanding of the general background of the invention and should not be taken as an acknowledgement or any form of suggestion that this information forms the prior art already known to a person skilled in the art.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种通过钢横梁与混凝土柱连接的框架桥墩及施工方法,以实现对下方铁路、道路影响小,施工安全风险小,横梁与墩柱拼装速度快、受力可靠、成本低,并可减小了基础受力。The purpose of the present invention is to provide a frame bridge pier connected with a concrete column through a steel beam and a construction method, so as to realize little impact on the railway and road below, little construction safety risk, fast assembly speed of the beam and the pier column, reliable force and low cost low, and can reduce the foundation force.

为了实现上述目的,本发明采用以下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:

本发明提供的一种通过钢横梁与混凝土柱连接的框架桥墩,包括钢横梁和墩柱,所述钢横梁与所述墩柱相接处设钢混结合段,所述钢混结合段包括顶钢板、底钢板和竖板,所述钢混结构段上设置剪力钉、加劲肋及肋板,所述墩柱上方设置墩柱过渡段,主筋和加强筋伸出墩柱顶部预设长度,拼装时,所述墩柱上的主筋和加强筋穿入所述钢横梁的所述底钢板上的预留孔,再在所述顶钢板上的灌注孔中灌注后浇混凝土,对所述后浇混凝土进行养护,待所述后浇混凝土养护完成后实现所述钢横梁与所述墩柱间的连接。The present invention provides a frame bridge pier connected by a steel beam and a concrete column, comprising a steel beam and a pier column, a steel-concrete joint section is arranged at the connection between the steel beam and the pier column, and the steel-concrete joint section includes a roof Steel plates, bottom steel plates and vertical plates, shear nails, stiffeners and rib plates are set on the steel-concrete structure section, pier-column transition sections are set above the pier columns, and the main bars and stiffeners protrude from the top of the pier columns by a preset length, When assembling, the main bars and reinforcing bars on the pier column penetrate into the reserved holes on the bottom steel plate of the steel beam, and then pour concrete into the pouring holes on the top steel plate. Concrete is poured for curing, and the connection between the steel beam and the pier is realized after the post-casting concrete curing is completed.

进一步的,所述顶钢板位于钢混结合段的顶面,所述顶钢板上设置灌注孔和排气孔。Further, the top steel plate is located on the top surface of the steel-concrete combined section, and the top steel plate is provided with a pouring hole and an exhaust hole.

进一步的,所述底钢板位于钢混结合段的底面,所述底钢板上设置多个预留孔,多个所述预留孔将所述底钢板分割成多个条形钢板区域,每个所述预留孔的尺寸大于所述主筋的外轮廓,每个所述条形钢板区域上均设有肋板进行加强。Further, the bottom steel plate is located on the bottom surface of the steel-concrete combination section, and a plurality of reserved holes are arranged on the bottom steel plate, and the plurality of reserved holes divide the bottom steel plate into a plurality of strip-shaped steel plate areas, each of which is The size of the reserved hole is larger than the outer contour of the main rib, and each strip-shaped steel plate area is provided with a rib for reinforcement.

进一步的,所述竖板位于所述钢混结合段与所述墩柱相接的四周,同时在所述墩柱中心处设置竖板,该处竖板与所述墩柱内的临时支座对应,所述临时支座与临时支撑柱对应。Further, the vertical plate is located around the connection between the steel-concrete joint section and the pier column, and at the same time, a vertical plate is arranged at the center of the pier column, where the vertical plate is connected to the temporary support in the pier column. Correspondingly, the temporary support corresponds to the temporary support column.

进一步的,所述墩柱过渡段设置有过渡板,所述过渡板包括四块竖向钢板围成的柱状结构,其高度与临时支撑柱和临时支座的叠加高度相同,所述过渡板的上部与所述钢横梁相连,所述过渡板的下部与所述墩柱的顶部相接,所述过渡板上设置剪力钉和加劲肋。Further, the transition section of the pier column is provided with a transition plate, and the transition plate includes a columnar structure surrounded by four vertical steel plates, the height of which is the same as the superimposed height of the temporary support column and the temporary support. The upper part is connected with the steel beam, the lower part of the transition plate is connected with the top of the pier, and the transition plate is provided with shear nails and stiffeners.

进一步的,所述剪力钉分散设置在顶钢板和所述竖板上;所述加劲肋分散设置在所述钢横梁的顶钢板和所述竖板上;在所述钢横梁与所述墩柱相接处,所述剪力钉、所述加劲肋均与后浇混凝土连接。Further, the shear nails are distributed on the top steel plate and the vertical plate; the stiffeners are distributed on the top steel plate and the vertical plate of the steel beam; on the steel beam and the pier Where the columns meet, the shear nails and the stiffening ribs are both connected to the post-cast concrete.

进一步的,所述肋板设置在所述钢横梁的顶钢板、竖板和底钢板上,沿所述钢横梁的内轮廓布置有多个所述肋板,所述肋板上设置有多个钢筋孔,穿孔钢筋穿过所述钢筋孔,并与两侧竖板焊接固定。Further, the rib plates are arranged on the top steel plate, the vertical plate and the bottom steel plate of the steel beam, a plurality of the rib plates are arranged along the inner contour of the steel beam, and a plurality of the rib plates are arranged on the rib plate Reinforcing steel holes, through which perforated steel bars pass, and are welded and fixed with the vertical plates on both sides.

进一步的,所述墩柱采用预制或现浇,所述墩柱的顶部设置墩柱过渡段,所述墩柱过渡段的外轮廓形状与所述钢横梁的过渡板形状相同,所述墩柱过渡段的外轮廓尺寸较所述墩柱其他位置大;Further, the pier column is prefabricated or cast-in-place, and the top of the pier column is provided with a pier column transition section, and the outer contour shape of the pier column transition section is the same as the shape of the transition plate of the steel beam. The outer contour size of the transition section is larger than that of the other positions of the pier;

所述主筋采用所述墩柱自身配置的钢筋,所述加强筋锚固在所述墩柱内部。The main reinforcement adopts the reinforcement provided by the pier column itself, and the reinforcement reinforcement is anchored inside the pier column.

进一步的,所述钢横梁和所述墩柱之间采用一次固结的形式,不设置过渡板、临时支撑柱和临时支座,施工时在所述墩柱的顶部铺设拼接缝,拼接缝采用高强砂浆。Further, the steel beam and the pier column are in the form of one-time consolidation, and no transition plates, temporary support columns and temporary supports are provided. During construction, splicing joints are laid on the top of the pier columns to splicing. The seams are made of high-strength mortar.

本发明提供的一种通过钢横梁与混凝土柱连接的框架桥墩的施工方法,包括以下步骤:A construction method of a frame pier connected by a steel beam and a concrete column provided by the present invention comprises the following steps:

步骤一、墩柱施工,钢横梁预制拼装;Step 1, pier and column construction, steel beam prefabricated assembly;

步骤二、施工墩柱顶部的临时支撑柱,在临时支撑柱上安装临时支座;Step 2, construct the temporary support column at the top of the pier column, and install the temporary support on the temporary support column;

或者,在墩柱顶面铺设拼接缝,不设置临时支撑柱和临时支座;Alternatively, lay joints on the top surface of the pier column, without setting up temporary support columns and temporary supports;

步骤三、吊装钢横梁,将钢横梁与墩柱进行对位,将墩柱上的主筋和加强筋穿入底钢板上的预留孔;Step 3: Hoist the steel beams, align the steel beams with the pier columns, and insert the main bars and reinforcing bars on the pier columns into the reserved holes on the bottom steel plate;

步骤四、通过临时支座支撑钢横梁,架设钢横梁上方梁体;Step 4. Support the steel beam through the temporary support, and erect the beam body above the steel beam;

或者,通过拼接缝支撑钢横梁,架设钢横梁上方梁体;Or, support the steel beam through the splicing seam, and erect the beam body above the steel beam;

步骤五、从顶钢板上的灌注孔灌注后浇混凝土,完成钢混结合段施工;Step 5. Concrete is poured from the pouring hole on the top steel plate to complete the construction of the steel-concrete joint section;

步骤六、养护后浇混凝土,施工完成。Step 6: Concrete is poured after curing, and the construction is completed.

本发明的有益效果为:The beneficial effects of the present invention are:

本发明提供的一种通过钢横梁与混凝土柱连接的框架桥墩及施工方法,能够获得如下效果:The invention provides a frame pier and a construction method connected by a steel beam and a concrete column, and the following effects can be obtained:

1.通过设置钢横梁,减轻了横梁重量,便于运输和吊装,施工速度快、施工干扰小。1. By setting the steel beam, the weight of the beam is reduced, which is convenient for transportation and hoisting, and the construction speed is fast and the construction interference is small.

2.通过钢横梁内部设置剪力钉、穿孔钢筋剪力键等构造,显著增加了连接部位的强度,确保钢横梁与后浇混凝土间相互传力,荷载传力路径明确,质量易于保证。2. By setting shear nails, perforated steel shear keys and other structures inside the steel beam, the strength of the connection part is significantly increased, ensuring the mutual force transmission between the steel beam and the post-cast concrete, the load force transmission path is clear, and the quality is easy to ensure.

3.钢横梁与墩柱间拼装施工容差大、拼装简单快速,墩柱主筋与钢横梁间易于穿入,两者间通过后浇筑混凝土形成刚性连接,受力安全,解决钢横梁与墩柱间协同受力的问题。3. The assembly construction tolerance between the steel beam and the pier column is large, the assembly is simple and fast, the main reinforcement of the pier column and the steel beam are easy to penetrate, and the two are rigidly connected by post-casting concrete, and the force is safe, solving the problem of steel beam and pier column the problem of inter-coordination.

4.钢横梁与墩柱间采用分阶段连接,即两者间先铰接再固结,先通过临时支座进行连接,架设上部梁体,再对钢横梁与墩柱间进行固结。从而避免一次固结使得基础受力较大,解决基础设计困难的问题。4. The steel beam and the pier column are connected in stages, that is, the two are first hinged and then consolidated, first connected through a temporary support, the upper beam body is erected, and then the steel beam and the pier column are consolidated. Thereby, it is avoided that the foundation is subjected to large force due to one-time consolidation, and the problem of difficult foundation design is solved.

附图说明Description of drawings

为了更清楚地说明本发明具体实施方式或现有技术中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施方式,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to illustrate the specific embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that need to be used in the description of the specific embodiments or the prior art. Obviously, the accompanying drawings in the following description The drawings are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained based on these drawings without creative efforts.

图1为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的主视结构示意图;1 is a schematic front view structure of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图2为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的俯视结构示意图;FIG. 2 is a schematic top-view structural diagram of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图3为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的桥墩结构示意图;3 is a schematic diagram of a pier structure of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图4为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的钢横梁结构示意图;4 is a schematic structural diagram of a steel beam of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图5为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的钢混结合段结构示意图;5 is a schematic structural diagram of a steel-concrete combined section of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图6为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的图5的Ⅰ-Ⅰ断面结构示意图;FIG. 6 is a schematic cross-sectional structural diagram of I-I of FIG. 5 of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图7为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的图5的Ⅱ-Ⅱ断面结构示意图;FIG. 7 is a schematic view of the cross-sectional structure of FIG. 5 of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图8为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的图5的Ⅲ-Ⅲ断面结构示意图;FIG. 8 is a schematic diagram of the cross-sectional structure of FIG. 5 III-III of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图9为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的图5的Ⅳ-Ⅳ断面结构示意图;FIG. 9 is a schematic view of the IV-IV cross-sectional structure of FIG. 5 of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图10为本发明实施例一提供的一种通过钢横梁与混凝土柱连接的框架桥墩的临时支撑结构示意图;10 is a schematic diagram of a temporary support structure of a frame pier connected by a steel beam and a concrete column according to Embodiment 1 of the present invention;

图11为本发明实施例二提供的一种通过钢横梁与混凝土柱连接的框架桥墩的结构示意图。11 is a schematic structural diagram of a frame pier connected by a steel beam and a concrete column according to the second embodiment of the present invention.

图标:icon:

1-钢横梁;1- Steel beam;

2-墩柱;2 - pier column;

21-墩柱过渡段;21 - pier-column transition section;

3-主筋;3 - main tendons;

31-加强筋;31- stiffener;

4-钢混结合段;4- Steel-concrete combination section;

5-后浇混凝土;5- post-cast concrete;

6-顶钢板;6- Top steel plate;

61-灌注孔;61-perfusion hole;

62-排气孔;62 - exhaust hole;

7-底钢板;7- Bottom steel plate;

71-预留孔;71- reserved hole;

8-竖板;8- riser;

9-过渡板;9- transition plate;

10-剪力钉;10 - shear nails;

11-肋板;11- Rib;

12-钢筋孔;12- Rebar hole;

13-穿孔钢筋;13 - perforated steel bars;

14-加劲肋;14 - stiffener;

15-临时支撑柱;15- Temporary support columns;

16-临时支座;16 - Temporary support;

17-拼接缝。17 - Patchwork seam.

具体实施方式Detailed ways

下面将结合附图对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

在本发明的描述中,需要说明的是,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性。In the description of the present invention, it should be noted that the terms "first" and "second" are only used for description purposes, and cannot be understood as indicating or implying relative importance.

在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that the terms "installed", "connected" and "connected" should be understood in a broad sense, unless otherwise expressly specified and limited, for example, it may be a fixed connection or a detachable connection Connection, or integral connection; can be mechanical connection, can also be electrical connection; can be directly connected, can also be indirectly connected through an intermediate medium, can be internal communication between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood in specific situations.

实施例一Example 1

如图1-10所示,为本发明实施例一提供的一种通过钢横梁1与混凝土柱连接的框架桥墩的结构示意图,结合附图1-10对发明的框架桥墩及框架桥墩的施工方法进行说明,具体结构及步骤如下。As shown in FIG. 1-10, it is a schematic structural diagram of a frame pier connected by a steel beam 1 and a concrete column provided in the first embodiment of the present invention. Combined with the accompanying drawings 1-10, the frame pier and the construction method of the frame pier of the invention are described. For description, the specific structure and steps are as follows.

本发明实施例提供的提供一种通过钢横梁1与混凝土柱连接的框架桥墩,如图1-9所示,一种通过钢横梁1与混凝土柱连接的框架桥墩,包括钢横梁1和墩柱2,钢横梁1与墩柱2相接处设钢混结合段4,钢混结合段4包括顶钢板6、底钢板7和竖板8,钢混结构段上设置剪力钉10、加劲肋14及肋板11,墩柱2上方设置墩柱过渡段21,主筋3和加强筋31伸出墩柱2顶部预设长度,拼装时,墩柱2上的主筋3和加强筋31穿入钢横梁1的底钢板7上的预留孔71,再在顶钢板6上的灌注孔61中灌注后浇混凝土5,对后浇混凝土5进行养护,待后浇混凝土5养护完成后实现钢横梁1与墩柱2间的连接。The embodiment of the present invention provides a frame pier connected with a concrete column through a steel beam 1. As shown in Figures 1-9, a frame pier connected with a concrete column through a steel beam 1 includes a steel beam 1 and a pier column. 2. A steel-concrete joint section 4 is set at the connection between the steel beam 1 and the pier column 2. The steel-concrete joint section 4 includes a top steel plate 6, a bottom steel plate 7 and a vertical plate 8. The steel-concrete structure section is provided with shear nails 10 and stiffeners. 14 and the rib plate 11, the pier column transition section 21 is set above the pier column 2, the main bar 3 and the reinforcing bar 31 extend out of the top of the pier column 2 by a preset length, when assembled, the main bar 3 and the reinforcing bar 31 on the pier column 2 penetrate into the steel The reserved hole 71 on the bottom steel plate 7 of the beam 1 is poured into the pouring hole 61 on the top steel plate 6, and the concrete 5 is poured after pouring. Connection with pier 2.

具体的,顶钢板6位于钢混结合段4的顶面,顶钢板6上设置灌注孔61和排气孔62;其中,灌注孔61用于灌注后浇混凝土5,排气孔62保证后浇混凝土5施工过程中的排气,以保证浇筑密实度。Specifically, the top steel plate 6 is located on the top surface of the steel-concrete combination section 4, and the top steel plate 6 is provided with a pouring hole 61 and an exhaust hole 62; wherein, the pouring hole 61 is used for pouring concrete 5 after pouring, and the exhaust hole 62 ensures the after pouring Exhaust during the construction of concrete 5 to ensure the compactness of the pouring.

具体的,底钢板7位于钢混结合段4的底面,底钢板7上设置多个预留孔71,多个预留孔71将底钢板7分割成多个条形钢板区域,每个预留孔71的尺寸大于主筋3的外轮廓,每个条形钢板区域上均设有肋板11进行加强;能够保证横梁底钢板7提供抗拉能力,以承担钢混结合段4的弯矩。Specifically, the bottom steel plate 7 is located on the bottom surface of the steel-concrete combination section 4, and a plurality of reserved holes 71 are provided on the bottom steel plate 7. The plurality of reserved holes 71 divide the bottom steel plate 7 into a plurality of strip-shaped steel plate areas, each reserved for The size of the hole 71 is larger than the outer contour of the main reinforcement 3, and each strip-shaped steel plate area is provided with a rib 11 for reinforcement;

具体的,竖板8位于钢混结合段4与墩柱2相接的四周,同时在墩柱2中心处设置竖板8,该处竖板8与墩柱2内的临时支座16对应,保证钢横梁1在自重作用下支撑在临时支座16上,临时支座16与临时支撑柱15对应。Specifically, the vertical plate 8 is located around the connection between the steel-concrete combination section 4 and the pier column 2, and at the same time, a vertical plate 8 is arranged at the center of the pier column 2, where the vertical plate 8 corresponds to the temporary support 16 in the pier column 2, It is ensured that the steel beam 1 is supported on the temporary support 16 under the action of its own weight, and the temporary support 16 corresponds to the temporary support column 15 .

具体的,墩柱过渡段21设置有过渡板9,过渡板9包括四块竖向钢板围成的柱状结构,其高度与临时支撑柱15和临时支座16的叠加高度相同,过渡板9的上部与钢横梁1相连,过渡板9的下部与墩柱2的顶部相接,作为后浇混凝土5的施工模板,后浇混凝土5浇筑时无需再设置临时模板;过渡板9上设置剪力钉10和加劲肋14,保证与后浇混凝土5间传力,当框架墩受力时,起到加强受力的作用。Specifically, the transition section 21 of the pier column is provided with a transition plate 9. The transition plate 9 includes a columnar structure surrounded by four vertical steel plates, and its height is the same as the superimposed height of the temporary support column 15 and the temporary support 16. The upper part is connected with the steel beam 1, and the lower part of the transition plate 9 is connected with the top of the pier column 2, which is used as the construction template of the post-cast concrete 5, and there is no need to set a temporary formwork when the post-cast concrete 5 is poured; the transition plate 9 is provided with shear nails 10 and the stiffening rib 14, to ensure the force transmission with the post-cast concrete 5, when the frame pier is stressed, it plays the role of strengthening the force.

具体的,(如图10所示)临时支撑柱15设置在墩柱2顶部,临时支撑柱15上方设置临时支座16,临时支撑柱15和临时支座16起到支撑钢横梁1的作用,当钢横梁1支撑在临时支座16上时,钢横梁1与墩柱2间为铰接,不传递弯矩,在钢横梁1上架设上部梁体时,上部梁体一期自重荷载不对基础产生弯矩作用,仅当施工完后浇混凝土5后,钢横梁1与墩柱2间形成刚结后才传递二期自重、活载等产生的弯矩,因此,大大减低了基础的受力,有利于基础的设计。Specifically, (as shown in FIG. 10) a temporary support column 15 is arranged on the top of the pier 2, a temporary support 16 is arranged above the temporary support column 15, and the temporary support column 15 and the temporary support 16 play the role of supporting the steel beam 1, When the steel beam 1 is supported on the temporary support 16, the steel beam 1 and the pier column 2 are hinged, and no bending moment is transmitted. Only when the concrete 5 is poured after the construction, the steel beam 1 and the pier column 2 form a rigid junction before the second-stage self-weight, live load and other bending moments are transmitted. Therefore, the force of the foundation is greatly reduced, which is beneficial to Basic design.

具体的,剪力钉10分散设置在顶钢板6和竖板8上,起到钢横梁1与后浇混凝土5的连接作用;在钢横梁1与墩柱2相接处,剪力钉10与后浇筑混凝土连接,当钢横梁1承受竖向力时,通过剪力钉10将竖向力传递给后浇混凝土5,当钢横梁1承受弯矩时,通过一侧剪力钉10的抗拉和另一侧剪力钉10的抗压,将荷载传递给后浇混凝土5;加劲肋14分散设置在钢横梁1的顶钢板6和竖板8上,保证钢板具有足够的稳定性,在钢横梁1与墩柱2相接处,加劲肋14与后浇混凝土5连接;能够加强钢板与后浇混凝土5间的连接。Specifically, the shear nails 10 are dispersedly arranged on the top steel plate 6 and the vertical plate 8, and play the role of connecting the steel beam 1 and the post-cast concrete 5; Post-cast concrete connection, when the steel beam 1 is subjected to vertical force, the vertical force is transmitted to the post-cast concrete 5 through the shear nails 10. When the steel beam 1 is subjected to a bending moment, the tensile force of the shear nail 10 on one side is used. And the compression resistance of the shear nail 10 on the other side transmits the load to the post-cast concrete 5; the stiffeners 14 are scattered on the top steel plate 6 and the vertical plate 8 of the steel beam 1 to ensure that the steel plate has sufficient stability. Where the beam 1 and the pier column 2 are connected, the stiffening rib 14 is connected with the post-cast concrete 5 ; the connection between the steel plate and the post-cast concrete 5 can be strengthened.

具体的,肋板11设置在钢横梁1顶钢板6、竖板8和底钢板7上,沿钢横梁1的内轮廓布置有多个肋板11,保证了钢板间的整体性和稳定性,肋板11上设有多个钢筋孔12,穿孔钢筋13穿过钢筋孔12,并与两侧竖板8焊接固定;肋板11、穿孔钢筋13和钢筋孔12内的后浇混凝土5形成剪力键,当钢横梁1上的顶钢板6、竖板8和底钢板7受力时,通过穿孔钢筋13及浇筑在穿孔钢筋13、钢筋孔12内的后浇混凝土5的抗剪作用,共同提供抗拉力,当竖板8承受弯矩或者顶钢板6和底钢板7承受弯矩时,通过剪力钉10、肋板11及穿孔钢筋13共同受力,显著提高了钢横梁1与后浇混凝土5间的连接强度。Specifically, the ribs 11 are arranged on the top steel plate 6, the vertical plate 8 and the bottom steel plate 7 of the steel beam 1, and a plurality of ribs 11 are arranged along the inner contour of the steel beam 1 to ensure the integrity and stability of the steel plates. The rib plate 11 is provided with a plurality of reinforcement holes 12, and the perforated reinforcement bars 13 pass through the reinforcement holes 12 and are welded and fixed with the vertical plates 8 on both sides; Force key, when the top steel plate 6, the vertical plate 8 and the bottom steel plate 7 on the steel beam 1 are stressed, through the shearing action of the perforated steel bar 13 and the post-cast concrete 5 poured in the perforated steel bar 13 and the steel bar hole 12, together Provide tensile force, when the vertical plate 8 bears the bending moment or the top steel plate 6 and the bottom steel plate 7 bear the bending moment, the shear nail 10, the rib plate 11 and the perforated steel bar 13 are jointly stressed, which significantly improves the steel beam 1 and the rear. The connection strength between poured concrete 5.

具体的,墩柱2采用预制或现浇,墩柱2的顶部设置墩柱过渡段21,墩柱过渡段21的外轮廓形状与钢横梁1的过渡板9形状相同,墩柱过渡段21的外轮廓尺寸较墩柱2其他位置大,保证与过渡板9间的衔接,同时其端面可作为后浇混凝土5的底模板,浇筑时无需搭设临时模板。Specifically, the pier column 2 is prefabricated or cast-in-place, and the top of the pier column 2 is provided with a pier column transition section 21. The shape of the outer contour of the pier column transition section 21 is the same as that of the transition plate 9 of the steel beam 1. The outer contour is larger than other positions of the pier column 2 to ensure the connection with the transition plate 9. At the same time, its end face can be used as the bottom formwork of the post-cast concrete 5, and there is no need to erect a temporary formwork during pouring.

具体的,主筋3采用墩柱2自身配置的钢筋,加强筋31锚固在墩柱2内部,保证主筋3和加强筋31伸入钢混结合段4具有足够的锚固长度,当钢横梁1受力时,通过后浇混凝土5对穿入其中的主筋3和加强筋31的握裹进行锚固和传力,从而保证与墩柱2间的荷载传递,加强筋31起到增加抗弯和抗剪能力的作用,同时,预留孔71设置足够的开孔空间,主筋3和加强筋31穿入方便,大大降低施工难度。Specifically, the main reinforcement 3 adopts the reinforcement provided by the pier column 2 itself, and the reinforcement reinforcement 31 is anchored inside the pier column 2 to ensure that the main reinforcement 3 and reinforcement reinforcement 31 extend into the steel-concrete joint section 4 with sufficient anchorage length. When the steel beam 1 is stressed When pierced, the main rib 3 and the reinforcing rib 31 are anchored and force-transmitted through the post-cast concrete 5, so as to ensure the load transfer with the pier 2, and the reinforcing rib 31 can increase the bending resistance and shear resistance capacity. At the same time, the reserved hole 71 is provided with enough opening space, and the main rib 3 and the reinforcing rib 31 can be easily penetrated, which greatly reduces the construction difficulty.

具体的,后浇混凝土5采用高强混凝土、超高性能混凝土(UHPC)或自密实补偿收缩混凝土中的一种。Specifically, the post-cast concrete 5 adopts one of high-strength concrete, ultra-high performance concrete (UHPC) or self-compacting compensating shrinkage concrete.

与本发明实施例一的一种通过钢横梁1与混凝土柱连接的框架桥墩对应的施工方法,包括以下步骤:A construction method corresponding to a frame pier connected by a steel beam 1 and a concrete column according to the first embodiment of the present invention includes the following steps:

一种通过钢横梁1与混凝土柱连接的框架桥墩的施工方法,包括以下步骤:A construction method of a frame pier connected with a concrete column through a steel beam 1, comprising the following steps:

步骤一、墩柱22施工,钢横梁11预制完成。Step 1: The pier column 22 is constructed, and the steel beam 11 is prefabricated.

步骤二、施工墩柱22顶部的临时支撑柱1515,在临时支撑柱1515上安装临时支座1616。The second step is to construct the temporary support column 1515 on the top of the pier column 22 , and install the temporary support 1616 on the temporary support column 1515 .

步骤三、吊装钢横梁11,将钢横梁11与墩柱22进行对位,将墩柱22上的主筋33和加强筋3131穿入底钢板77上的预留孔7171内部。Step 3, hoist the steel beam 11, align the steel beam 11 with the pier column 22, and insert the main rib 33 and the reinforcing rib 3131 on the pier column 22 into the reserved hole 7171 on the bottom steel plate 77.

步骤四、通过临时支座1616支撑钢横梁11,架设钢横梁11上方梁体。Step 4: Support the steel beam 11 through the temporary support 1616, and erect the upper beam body of the steel beam 11.

步骤五、从顶钢板66上的灌注孔6161灌注后浇混凝土55,完成钢混结合段44施工。Step 5, pour concrete 55 from the pouring hole 6161 on the top steel plate 66, and complete the construction of the steel-concrete joint section 44.

步骤六、养护后浇混凝土55,施工完成。Step 6: Concrete 55 is poured after curing, and the construction is completed.

本实施例的一种通过钢横梁1与混凝土柱连接的框架桥墩及施工方法具有如下优势:通过设置钢横梁1,减轻了横梁重量,便于运输和吊装,施工速度快、施工干扰小;通过钢横梁1内部设置剪力钉10、穿孔钢筋13剪力键等构造,显著增加了连接部位的强度,确保钢横梁1与后浇混凝土5间相互传力,荷载传力路径明确,质量易于保证;钢横梁1与墩柱2间拼装施工容差大、拼装简单快速,墩柱2主筋3与钢横梁1间易于穿入,两者间通过后浇筑混凝土形成刚性连接,受力安全,解决钢横梁1与墩柱2间协同受力的问题;钢横梁1与墩柱2间采用分阶段连接,即两者间先铰接再固结,先通过临时支座16进行连接,架设上部梁体,再对钢横梁1与墩柱2间进行固结;从而避免一次固结使得基础受力较大,解决基础设计困难的问题。The frame pier and the construction method connected with the concrete column through the steel beam 1 of the present embodiment have the following advantages: by setting the steel beam 1, the weight of the beam is reduced, the transportation and hoisting are convenient, the construction speed is fast, and the construction interference is small; The beam 1 is equipped with shear nails 10, perforated steel bars 13 shear keys and other structures, which significantly increases the strength of the connection part, ensuring mutual force transmission between the steel beam 1 and the post-cast concrete 5, the load force transmission path is clear, and the quality is easy to ensure; The assembly between steel beam 1 and pier column 2 has a large construction tolerance, and the assembly is simple and fast. It is easy to penetrate between the main bar 3 of pier column 2 and steel beam 1, and the rigid connection between the two is formed by post-casting concrete, which is safe under force and solves the problem of steel beam. The problem of coordinated stress between 1 and pier column 2; the steel beam 1 and the pier column 2 are connected in stages, that is, the two are hinged and then consolidated, first connected through the temporary support 16, and the upper beam body is erected. Consolidate between the steel beam 1 and the pier column 2; thus avoiding the one-time consolidation, which makes the foundation larger, and solves the problem of difficult foundation design.

实施例二Embodiment 2

如图11所示,为本发明实施例二的一种通过钢横梁1与混凝土柱连接的框架桥墩,当基础受力不控制时,钢横梁1和墩柱2间可采用一次固结的形式,包括实施例一的除了过渡板9、临时支撑柱15和临时支座16及与过渡板9、临时支撑柱15和临时支座16相关联的连接特征,在此不做赘述;施工时,在墩柱2顶部铺设拼接缝17,拼接缝17采用高强砂浆,施工时吊装钢横梁1放置在拼接缝17上,将主筋3和加强筋31穿入钢混结合段4内部,再浇筑后浇混凝土5,完成钢横梁1与墩柱2之间的拼装。As shown in FIG. 11 , it is a frame pier connected with a concrete column through a steel beam 1 according to the second embodiment of the present invention. When the foundation force is not controlled, the steel beam 1 and the pier column 2 can adopt the form of one-time consolidation. , including the connection feature associated with the transition plate 9, the temporary support column 15 and the temporary support 16 and the transition plate 9, the temporary support column 15 and the temporary support 16 of the first embodiment, which will not be repeated here; during construction, A splicing joint 17 is laid on the top of the pier column 2. The splicing joint 17 is made of high-strength mortar. During construction, the steel beam 1 is placed on the splicing joint 17. After pouring, pour concrete 5 to complete the assembly between the steel beam 1 and the pier column 2 .

与本发明实施例二的一种通过钢横梁1与混凝土柱连接的框架桥墩对应的施工方法,包括以下步骤:A construction method corresponding to a frame pier connected by a steel beam 1 and a concrete column according to the second embodiment of the present invention includes the following steps:

步骤一、墩柱2施工,钢横梁1预制拼装;Step 1. The pier column 2 is constructed, and the steel beam 1 is prefabricated and assembled;

步骤二、在墩柱2顶面铺设拼接缝17,不设置临时支撑柱15和临时支座16;Step 2: Lay splicing joints 17 on the top surface of the pier column 2, without setting the temporary support column 15 and the temporary support 16;

步骤三、吊装钢横梁1,将钢横梁1与墩柱2进行对位,将墩柱2上的主筋3和加强筋31穿入底钢板7上的预留孔71;Step 3, hoist the steel beam 1, align the steel beam 1 with the pier column 2, and insert the main rib 3 and the reinforcing rib 31 on the pier column 2 into the reserved hole 71 on the bottom steel plate 7;

步骤四、通过拼接缝17支撑钢横梁1,架设钢横梁1上方梁体;Step 4, supporting the steel beam 1 through the splicing seam 17, and erecting the beam body above the steel beam 1;

步骤五、从顶钢板6上的灌注孔61灌注后浇混凝土5,完成钢混结合段4施工;Step 5, pour concrete 5 after pouring from the pouring hole 61 on the top steel plate 6, and complete the construction of the steel-concrete joint section 4;

步骤六、养护后浇混凝土5,施工完成。Step 6. After curing, pour concrete 5, and the construction is completed.

本实施例的一种通过钢横梁1与混凝土柱连接的框架桥墩及施工方法具有如下优势:通过设置钢横梁1,减轻了横梁重量,便于运输和吊装,施工速度快、施工干扰小;通过钢横梁1内部设置剪力钉10、穿孔钢筋13剪力键等构造,显著增加了连接部位的强度,确保钢横梁1与后浇混凝土5间相互传力,荷载传力路径明确,质量易于保证;钢横梁1与墩柱2间拼装施工容差大、拼装简单快速,墩柱2主筋3与钢横梁1间易于穿入,两者间通过后浇筑混凝土形成刚性连接,受力安全,解决钢横梁1与墩柱2间协同受力的问题;当基础受力不控制时,钢横梁1与墩柱2间采用一次固结的形式,不设置过渡板9、临时支撑柱15和临时支座16,施工时在墩柱2顶部铺设拼接缝17,拼接缝17采用高强砂浆,施工时吊装钢横梁1放置在拼接缝17上,将主筋3和加强筋31穿入钢混结合段4内部,再浇筑后浇混凝土5,完成钢横梁1与墩柱2之间的拼装,拼装速度快、受力可靠、成本低,并可减小了基础受力。The frame pier and the construction method connected with the concrete column through the steel beam 1 of the present embodiment have the following advantages: by setting the steel beam 1, the weight of the beam is reduced, the transportation and hoisting are convenient, the construction speed is fast, and the construction interference is small; The beam 1 is equipped with shear nails 10, perforated steel bars 13 shear keys and other structures, which significantly increases the strength of the connection part, ensuring mutual force transmission between the steel beam 1 and the post-cast concrete 5, the load force transmission path is clear, and the quality is easy to ensure; The assembly between steel beam 1 and pier column 2 has a large construction tolerance, and the assembly is simple and fast. It is easy to penetrate between the main bar 3 of pier column 2 and steel beam 1, and the rigid connection between the two is formed by post-casting concrete, which is safe under force and solves the problem of steel beam. The problem of co-stressing between 1 and pier column 2; when the force of the foundation is not controlled, the steel beam 1 and the pier column 2 are in the form of one-time consolidation, and no transition plate 9, temporary support column 15 and temporary support 16 are provided. During construction, a splicing joint 17 is laid on the top of the pier column 2, and the splicing joint 17 is made of high-strength mortar. During construction, the hoisting steel beam 1 is placed on the splicing joint 17, and the main bar 3 and the reinforcing bar 31 are penetrated into the steel-concrete joint section 4. Inside, pour concrete 5 after pouring to complete the assembly between the steel beam 1 and the pier column 2. The assembly speed is fast, the force is reliable, the cost is low, and the foundation force can be reduced.

最后应说明的是:以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明实施例技术方案的范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that it can still be The technical solutions described in the foregoing embodiments are modified, or some or all of the technical features thereof are equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention.

Claims (10)

1. The utility model provides a frame pier through steel crossbeam and concrete column connection which characterized in that: including steel beam and pier stud, the steel beam with the pier stud department of meeting establishes the steel-concrete section that combines, the steel-concrete section that combines includes top steel sheet, end steel sheet and riser, set up shear force nail, stiffening rib and floor in the steel-concrete structure section, the pier stud top sets up the pier stud changeover portion, and main muscle and strengthening rib stretch out the pier stud top and predetermine length, and during the assembly, main muscle and strengthening rib on the pier stud penetrate the steel beam the preformed hole on the end steel sheet, again pour the post-cast concrete in the pouring hole on the top steel sheet, right post-cast concrete carries out the maintenance, treats realize after the post-cast concrete maintenance the steel beam with be connected between the pier stud.
2. A frame pier connected with a concrete column through a steel beam according to claim 1, wherein: the top steel plate is positioned on the top surface of the reinforced concrete combining section, and the top steel plate is provided with a filling hole and an exhaust hole.
3. A frame pier connected with a concrete column through a steel beam according to claim 1, wherein: the end steel sheet is located the bottom surface of reinforced concrete joint section, set up a plurality of preformed holes on the end steel sheet, it is a plurality of the preformed hole will a plurality of bar steel sheet regions are cut apart into to the end steel sheet, every the size in preformed hole is greater than the outline of main muscle, every all be equipped with the floor in the bar steel sheet region and strengthen.
4. A frame pier connected with a concrete column through a steel beam according to claim 1, wherein: the riser is located the reinforced concrete joint section with all around the pier stud meets, simultaneously pier stud center department sets up the riser, this department riser with temporary support in the pier stud corresponds, temporary support corresponds with temporary support post.
5. A framed pier connected to a concrete column through a steel beam according to claim 4, wherein: the pier stud transition section is provided with a transition plate, the transition plate comprises a columnar structure formed by four vertical steel plates in a surrounding mode, the height of the columnar structure is equal to the stacking height of the temporary support column and the temporary support, the upper portion of the transition plate is connected with the steel cross beam, the lower portion of the transition plate is connected with the top of the pier stud, and the transition plate is provided with shear nails and stiffening ribs.
6. A frame pier connected with a concrete column through a steel beam according to claim 1, wherein: the shear nails are dispersedly arranged on the top steel plate and the vertical plate of the steel beam; the stiffening ribs are dispersedly arranged on the top steel plate and the vertical plate of the steel beam;
and at the joint of the steel beam and the pier stud, the shear nails and the stiffening ribs are connected with post-cast concrete.
7. A frame pier connected with a concrete column through a steel beam according to claim 1, wherein: the rib plates are arranged on the top steel plate, the vertical plates and the bottom steel plate of the steel beam, a plurality of rib plates are arranged along the inner contour of the steel beam, a plurality of reinforcing steel bar holes are formed in the rib plates, and the perforated reinforcing steel bars penetrate through the reinforcing steel bar holes and are welded and fixed with the vertical plates on two sides.
8. A frame pier connected with a concrete column through a steel beam according to claim 1, wherein: the pier column is prefabricated or cast in place, a pier column transition section is arranged at the top of the pier column, the outer contour shape of the pier column transition section is the same as that of a transition plate of the steel cross beam, and the outer contour size of the pier column transition section is larger than that of other positions of the pier column;
the main reinforcement adopts the reinforcing bar of pier stud self configuration, the strengthening rib anchor is in inside the pier stud.
9. The frame pier connected with the concrete column through the steel cross beam as claimed in claim 1, wherein a form of one-time consolidation is adopted between the steel cross beam and the pier column, a transition plate, a temporary support column and a temporary support are not arranged, a splicing seam is laid at the top of the pier column during construction, and high-strength mortar is adopted as the splicing seam.
10. A construction method of a frame pier connected with a concrete column through a steel cross beam is characterized by comprising the following steps:
firstly, pier stud construction, namely prefabricating and assembling a steel cross beam;
step two, constructing a temporary support column at the top of the pier column, and mounting a temporary support on the temporary support column;
or paving splicing seams on the top surfaces of the piers without arranging temporary support columns and temporary supports;
step three, hoisting the steel beam, aligning the steel beam with the pier stud, and penetrating the main ribs and the reinforcing ribs on the pier stud into the reserved holes in the bottom steel plate;
fourthly, supporting the steel beam through a temporary support, and erecting a beam body above the steel beam;
or, supporting the steel beam through the splicing seam, and erecting a beam body above the steel beam;
pouring post-cast concrete from the pouring holes in the top steel plate to complete the construction of the steel-concrete combined section;
and step six, pouring concrete after maintenance, and finishing construction.
CN202010606634.7A 2020-06-29 2020-06-29 A frame pier connected by a steel beam and a concrete column and a construction method Pending CN111827084A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010606634.7A CN111827084A (en) 2020-06-29 2020-06-29 A frame pier connected by a steel beam and a concrete column and a construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010606634.7A CN111827084A (en) 2020-06-29 2020-06-29 A frame pier connected by a steel beam and a concrete column and a construction method

Publications (1)

Publication Number Publication Date
CN111827084A true CN111827084A (en) 2020-10-27

Family

ID=72899471

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010606634.7A Pending CN111827084A (en) 2020-06-29 2020-06-29 A frame pier connected by a steel beam and a concrete column and a construction method

Country Status (1)

Country Link
CN (1) CN111827084A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114016420A (en) * 2021-11-23 2022-02-08 兴泰建设集团有限公司 Assembly type construction method for single pier column steel bridge
CN114232501A (en) * 2022-01-18 2022-03-25 宁波市高等级公路建设管理中心 Bent cap pier stud integration template structure
CN116771037A (en) * 2023-06-16 2023-09-19 中铁广州工程局集团有限公司 Assembled steel structure door building integrated rapid installation construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102021889A (en) * 2010-12-16 2011-04-20 上海市城市建设设计研究院 Bridge erection method
JP2017172143A (en) * 2016-03-22 2017-09-28 株式会社高速道路総合技術研究所 Junction structure of precast concrete floor slab for rapid construction work, and construction method of the same
CN209891048U (en) * 2019-04-12 2020-01-03 北京市市政专业设计院股份公司 Connecting structure of precast concrete pier stud and capping beam
CN210458914U (en) * 2019-06-13 2020-05-05 华新新型建材(武汉)有限公司 Connecting structure of prefabricated bridge pier stud and capping beam
CN111172864A (en) * 2020-02-20 2020-05-19 浙江省交通规划设计研究院有限公司 Assembly type integrated pier column and capping beam combined structure and construction method thereof
CN212801178U (en) * 2020-06-29 2021-03-26 中国国家铁路集团有限公司 Frame pier connected with concrete column through steel cross beam

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102021889A (en) * 2010-12-16 2011-04-20 上海市城市建设设计研究院 Bridge erection method
JP2017172143A (en) * 2016-03-22 2017-09-28 株式会社高速道路総合技術研究所 Junction structure of precast concrete floor slab for rapid construction work, and construction method of the same
CN209891048U (en) * 2019-04-12 2020-01-03 北京市市政专业设计院股份公司 Connecting structure of precast concrete pier stud and capping beam
CN210458914U (en) * 2019-06-13 2020-05-05 华新新型建材(武汉)有限公司 Connecting structure of prefabricated bridge pier stud and capping beam
CN111172864A (en) * 2020-02-20 2020-05-19 浙江省交通规划设计研究院有限公司 Assembly type integrated pier column and capping beam combined structure and construction method thereof
CN212801178U (en) * 2020-06-29 2021-03-26 中国国家铁路集团有限公司 Frame pier connected with concrete column through steel cross beam

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114016420A (en) * 2021-11-23 2022-02-08 兴泰建设集团有限公司 Assembly type construction method for single pier column steel bridge
CN114016420B (en) * 2021-11-23 2024-02-13 兴泰建设集团有限公司 Single pier column steel bridge assembly type construction method
CN114232501A (en) * 2022-01-18 2022-03-25 宁波市高等级公路建设管理中心 Bent cap pier stud integration template structure
CN114232501B (en) * 2022-01-18 2023-12-12 宁波市高等级公路建设管理中心 Integrated template structure of capping beam pier column
CN116771037A (en) * 2023-06-16 2023-09-19 中铁广州工程局集团有限公司 Assembled steel structure door building integrated rapid installation construction method

Similar Documents

Publication Publication Date Title
CN106869316B (en) Combined frame system and construction method of beam-column flange made of concrete-filled steel tubes
CN106013432B (en) A kind of high ductility prefabricated integral frame interior joint connection structure and construction method
CN111827084A (en) A frame pier connected by a steel beam and a concrete column and a construction method
CN109057004A (en) A kind of assembled steel-Combined concrete frame and its connection installation method
CN110056092A (en) Bolt plug-in type precast shear wall and superimposed sheet connecting structure and construction method up and down
CN212801178U (en) Frame pier connected with concrete column through steel cross beam
CN114592436B (en) Pier capping beam lower support system and construction method thereof
CN108571070A (en) A kind of Prefabricated concrete-filled steel tube ring beam connection structure and construction method
CN207686092U (en) A kind of assembled overlapped hollow floor system
CN211522899U (en) Long-span steel-concrete composite beam convenient to erect by bridge girder erection machine
CN205874944U (en) Double T type wave form steel web profiled steel sheet combination beam
CN216475803U (en) A Novel Prefabricated Floor Structure Applied to Shear Wall System
CN110184903B (en) A truss-type prefabricated pipe column assembled bridge pier
CN107989247A (en) A kind of assembled overlapped hollow floor system and its construction method
CN208328647U (en) A kind of durable lower flange hollow slab bridge of the quick prefabricated assembled light in city
CN206554385U (en) Combining structure for assembled architecture
CN206503063U (en) Prefabricated assembled Wavelike steel webplate T beam bridges
CN212000589U (en) Concrete cantilever plate
CN214831817U (en) A continuous rigid frame bridge with short piers
CN212426706U (en) Fully prefabricated light large cantilever pre-bent composite cover beam structure
CN215482231U (en) Assembled waffle bridge panel combination case roof beam structure
CN109113171A (en) A Novel Bolted Precast Concrete Frame Structure
CN111561060B (en) Rigid hinged joint node of superposed beam and thin-wall steel pipe concrete column
CN212452334U (en) Arch structure for culvert and reinforced concrete arch plate thereof
CN212506737U (en) Assembled beam column node

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination