CN111791923A - Energy-saving-oriented single-track railway train scheduling method and system - Google Patents
Energy-saving-oriented single-track railway train scheduling method and system Download PDFInfo
- Publication number
- CN111791923A CN111791923A CN202010912686.7A CN202010912686A CN111791923A CN 111791923 A CN111791923 A CN 111791923A CN 202010912686 A CN202010912686 A CN 202010912686A CN 111791923 A CN111791923 A CN 111791923A
- Authority
- CN
- China
- Prior art keywords
- train
- operation diagram
- station
- time
- optimized
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61L—GUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
- B61L27/00—Central railway traffic control systems; Trackside control; Communication systems specially adapted therefor
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61L—GUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
- B61L27/00—Central railway traffic control systems; Trackside control; Communication systems specially adapted therefor
- B61L27/04—Automatic systems, e.g. controlled by train; Change-over to manual control
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61L—GUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
- B61L27/00—Central railway traffic control systems; Trackside control; Communication systems specially adapted therefor
- B61L27/10—Operations, e.g. scheduling or time tables
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Train Traffic Observation, Control, And Security (AREA)
Abstract
An energy-saving single-track railway train scheduling method and system belong to the technical field of rail transit train operation control. Includes step S1: reading a planned train operation diagram from a train dispatching system, extracting train-to-transmission information from the planned operation diagram, and regenerating a feasible operation diagram according to the train-to-transmission information and a 'first-to-first' principle; step S2: optimizing all trains in the feasible operation diagram according to the time sequence and based on the rules to obtain an optimized train operation diagram; step S3: and returning to the step S1 to re-optimize the train operation diagram when the train late event occurs according to the current real-time train operation information. The invention considers the actual running condition of the train, optimizes the train process, reduces the train stop time at the station, dynamically optimizes the running chart in real time, generates a train speed optimization curve according to the time constraint of the running chart, improves the energy-saving efficiency of the train, and can expand the application range by setting the priority of the train.
Description
Technical Field
The invention relates to an energy-saving single-track railway train scheduling method and system, and belongs to the technical field of rail transit train operation control.
Background
Along with the improvement of environmental awareness and the increase of railway operation pressure of people, the energy consumption of trains is reduced by researching and applying related technical means, and more attention is paid. At present, both domestic and foreign countries have technical researches for train energy conservation, the foreign countries relate to the research on train energy conservation, the direction of the research mainly aims at optimizing train operation, namely, the optimal train operation speed is selected according to the type of a locomotive, the load of a train, the line condition, the transportation plan requirement and the like, so that the aim of energy conservation is fulfilled, and the research on a DAS (driver advisory System) system is wide and the technology is mature. A mature train driving auxiliary system is not provided in China. The study at home and abroad for the train dispatching of the single-track railway mainly aims at solving the train conflict and improving the transportation efficiency. The DAS capable of communicating with the control center provides a basic condition for scheduling optimization, but research for realizing energy saving by optimizing scheduling is still less.
Train scheduling is the core of railway transportation production organization, and the optimal scheduling of trains is an important means for realizing energy conservation and environmental protection of trains and improving the running efficiency of the trains. Therefore, an optimal driving scheduling plan can be formed according to the traffic flow direction, train marshalling and empty and heavy, train giving and transportation time requirements and the like, so that the purposes of saving power and reducing energy consumption are achieved. Due to the characteristics of the single-track railway, the process of enabling the train to stay at the station can be optimized by setting the priority of the train, the time for enabling the heavy train to stay at the station and the light train to stay at the station is shortened, time constraint is provided for optimizing the running speed curve of a train section, and energy-saving running of the train is realized. Because the train operation is influenced by many factors, uncertain factors exist in the departure and operation processes, the train can not be guaranteed to run completely according to the operation diagram, and the energy-saving effect is directly influenced.
Therefore, it is desirable to provide a single-track railway train dispatching method and system for energy conservation.
Disclosure of Invention
The invention aims to solve the technical problem of providing an energy-saving single-track railway train scheduling method, which considers the actual running condition of a train and dynamically optimizes a running chart in real time so as to improve the energy-saving efficiency. The invention aims to solve the other technical problem of providing an energy-saving single-track railway train dispatching system.
In order to solve the technical problems, the invention adopts the following technical scheme:
an energy-saving single-track railway train scheduling method comprises the following steps:
step S1: reading a planned train operation diagram from a train dispatching system, extracting train-to-transmission information from the planned operation diagram, and regenerating a feasible operation diagram according to the train-to-transmission information and a 'first-to-first' principle;
step S2: optimizing all trains in the feasible operation diagram according to the time sequence and based on the rules to obtain an optimized train operation diagram;
step S3: and returning to the step S1 to re-optimize the train operation diagram when the train late event occurs according to the current real-time train operation information.
Preferably, the planned operation diagram comprises train number, starting station, passing station, ending station, starting time and ending time, and train operation conflicts can exist in the planned operation diagram;
the feasible operation diagram is the operation diagram which meets the interval operation time requirement and solves the meeting conflict.
Preferably, the principle of 'first arrival first sending' is that the trains which arrive at the stations at the two ends of the target interval first enter the interval, and the trains which arrive later wait until the interval is free;
preferably, step S2 includes:
step S21: and searching for a meeting and giving event according to time, and for a light vehicle, giving a heavy vehicle event, under the condition of meeting speed limit and preparation for route switching and departure of a station, prolonging the running time of the light vehicle in a section before the meeting and giving the station, shortening the stay time of the light vehicle in the meeting and giving the station, and correspondingly adjusting the running time of the next section after giving the station according to the influence condition.
Step S22: the method comprises the steps of searching for a meeting and giving event according to time, and giving a light vehicle event to a heavy vehicle, adjusting the running time of the heavy vehicle in the section before the meeting and giving the heavy vehicle to the light vehicle by prolonging the running time of the heavy vehicle in the section before the meeting and giving the heavy vehicle and/or reducing the running time of the light vehicle in the section before the meeting and giving the heavy vehicle to the light vehicle under the condition of meeting, and adjusting the running time of the next section after giving the heavy vehicle according to the influence condition.
Step S23: searching for a yield event according to time, searching for a light vehicle event for a heavy vehicle, and adjusting the heavy vehicle event not to the light vehicle event according to the step S22, under the condition of meeting speed limit and preparation for route switching and departure of a station, prolonging the running time of the heavy vehicle in the previous section of the yield station, shortening the stay time of the heavy vehicle in the yield station, and correspondingly adjusting the running time of the next section according to the influence condition.
Step S24: the single-track railway for mixed passenger and freight running is optimized on the basis of the established running chart of the passenger car.
Preferably, the current real-time running information of the train is information such as train number, total weight, length, locomotive type, running direction, located section or station, next section or station, speed limit in front of running and the like of the current running train.
Preferably, the generated optimized train operation diagram is transmitted to the vehicle-mounted terminal module as a constraint condition for optimizing the locomotive speed curve.
The invention provides an energy-saving single-track railway train dispatching system which comprises a dispatching information acquisition module, an optimized dispatching scheme calculation module, a vehicle-mounted terminal module, an LKJ data interface module, a station terminal module and a communication module.
The scheduling information acquisition module is used for reading the planned operation chart data in the train scheduling system, the module utilizes the display unit to display the scheduling information in the train scheduling system in real time, and the scheduling information comprises: the system comprises a planning schedule, a train priority, a train temporary speed limit, a section blocking, a station track occupation and the like, wherein the display information displayed by a display unit is obtained by a camera, the display information acquired by the camera is identified by a special image identification algorithm, and the display information is transmitted to an optimized scheduling scheme calculation module.
The LKJ data interface module is used for acquiring information such as current train number, position, total weight, length, locomotive type, running direction, train running historical data and the like from an LKJ system and transmitting the information to the optimal scheduling scheme calculating module.
And the optimized scheduling scheme calculation module optimizes the planned operation diagram based on the scheduling information provided by the scheduling information acquisition module and the information provided by the LKJ data interface module, prompts a dispatcher to confirm after the operation diagram is optimized, and sends the optimized operation diagram to the vehicle-mounted terminal module and the station terminal module after the confirmation.
The vehicle-mounted terminal module is used for receiving the optimized operation diagram output by the optimized scheduling scheme calculation module, generating an energy-saving optimized speed curve and a locomotive operation sequence, calculating train energy consumption corresponding to the optimized operation diagram according to the outgoing energy consumption characteristic information of the locomotive and by combining with the historical measured energy consumption data, and displaying the train energy consumption to a driver.
And the station terminal module is used for receiving the optimized operation diagram information output by the optimized scheduling scheme calculation module and presenting the optimized operation diagram information to an operator on duty in a graphic mode through a display unit.
The communication module is used for communication among the modules such as the optimized scheduling scheme calculation module, the vehicle-mounted terminal module, the LKJ data interface module, the station terminal module and the like.
The invention has the following beneficial effects:
the invention discloses an energy-saving single-track railway train scheduling method and system, which consider the actual running condition of a train, optimize the train process, reduce the train stop time at a station, dynamically optimize a running chart in real time, generate a train speed optimization curve according to the time constraint of the running chart and improve the train energy-saving efficiency. Meanwhile, the invention can also expand the application range by setting the priority of the train.
Drawings
The following describes embodiments of the present invention in further detail with reference to the accompanying drawings.
Fig. 1 is a flow chart of an energy-saving single-track railway train scheduling method according to the present invention.
Fig. 2 is a schematic diagram of optimization and adjustment of a heavy train scenario by a light train in an embodiment of the energy-saving single-track railway train scheduling method and system.
Fig. 3 is a schematic diagram illustrating that a heavy train and a light train can be optimally adjusted in a scene in an embodiment of the energy-saving single-track railway train scheduling method and system.
Fig. 4 is a schematic diagram of a power-saving single-track railway train dispatching system of the present invention.
Fig. 5 is a feasible operation diagram of the energy-saving single-track railway train scheduling method and system.
Fig. 6 is an optimized operation diagram of the energy-saving single-track railway train scheduling method and system.
FIG. 7 is a comparison of the run charts before and after the scheduling scheme optimization in the embodiment of the present invention.
Detailed Description
In order to more clearly illustrate the invention, the invention is further described below with reference to preferred embodiments and the accompanying drawings. Similar parts in the figures are denoted by the same reference numerals. It is to be understood by persons skilled in the art that the following detailed description is illustrative and not restrictive, and is not to be taken as limiting the scope of the invention.
Example 1: as shown in fig. 1,2, 3, 4, 5, 6 and 7, an energy-saving single-track railway train dispatching method includes:
step S1: and reading the planned train operation diagram from the train dispatching system, extracting train-to-transmission information from the planned operation diagram, and regenerating a feasible operation diagram according to the train-to-transmission information and a 'first-to-first' principle. The planned operation diagram comprises train number, starting station, passing station, ending station, starting time and ending time, and train operation conflicts can exist in the planned operation diagram. According to the planned operation diagram, departure events are searched according to the time sequence, and meeting conflicts are solved according to the principle that trains which arrive at stations at two ends of a target interval first enter the interval, and then the arriving trains wait until the interval is free. Considering that a certain time is required for switching the route of the train during the period that the train can give way at the station, the time constraint of route switching needs to be considered when generating a feasible solution. Assuming that there are M stations, the first station in the ascending is defined as station 1.
Assuming that train j stops at station m and train i passes, departure time of train i at station mThe following constraints must be satisfied:
wherein: t issThe time for switching the route of the station is,
Tppreparation time for departure (when the stop time is longer due to meeting at the intermediate station, a certain program is required before departure, and when the stop time is shorter, TpTake 0).
The feasible operation diagram is the operation diagram which meets the interval operation time requirement and solves the meeting conflict.
Step S2: optimizing all trains in the feasible operation diagram according to the time sequence and based on the rules to obtain an optimized train operation diagram;
step S21: and searching for a meeting and giving event according to time, and for a light vehicle, giving a heavy vehicle event, under the condition of meeting speed limit and preparation for route switching and departure of a station, prolonging the running time of the light vehicle in a section before the meeting and giving the station, shortening the stay time of the light vehicle in the meeting and giving the station, and correspondingly adjusting the running time of the next section after giving the station according to the influence condition.
The possible scheduling scheme would have a scenario as shown in fig. 2, where:
for the running time of the descending train i (light train) from the last letting station (for example: m +1) to the mth station,
for the operation time between the m-th stop and the next letting stop of the ascending train j (heavy train),for the time of travel between the last lead station to the m-th station for the ascending train j.
aiming at the condition that the light vehicle can let the heavy vehicle in the feasible scheduling scheme, if the parking time of the light vehicle i exceeds 2Ts+TpIn this case, the train can be transported in a section of the train iLine timeAnd the train i stops for a time Δ T:
wherein the content of the first and second substances,the stop time of the train i at the m stations.
Step S22: the method comprises the steps of searching for a meeting and giving event according to time, and giving a light vehicle event to a heavy vehicle, adjusting the running time of the heavy vehicle in the section before the meeting and giving the heavy vehicle to the light vehicle by prolonging the running time of the heavy vehicle in the section before the meeting and giving the heavy vehicle and/or reducing the running time of the light vehicle in the section before the meeting and giving the heavy vehicle to the light vehicle under the condition of meeting, and adjusting the running time of the next section after giving the heavy vehicle according to the influence condition.
Aiming at the condition that the 'heavy vehicle can lead to light vehicle' in the feasible scheduling scheme, the method can be divided into two optimization conditions according to the judgment condition whether the condition can be adjusted to 'light vehicle can lead to heavy vehicle', when the following conditions are met,
wherein the content of the first and second substances,for the stopping time of the train j at the m station, the condition that the heavy train lets the light train "can be adjusted to" the light train lets the heavy train ", and then the specific optimization and adjustment steps are as follows:
ΔΤ6=-(ΔT4+2Ts+Tp)
step S23: searching for a yield event according to time, searching for a light vehicle event for a heavy vehicle, and adjusting the heavy vehicle event not to the light vehicle event according to the step S22, under the condition of meeting speed limit and preparation for route switching and departure of a station, prolonging the running time of the heavy vehicle in the previous section of the yield station, shortening the stay time of the heavy vehicle in the yield station, and correspondingly adjusting the running time of the next section according to the influence condition.
When the following condition is not satisfied,
the scene that the heavy vehicle can lead the light vehicle cannot be adjusted to the scene that the light vehicle can lead the heavy vehicle, the stop time of the heavy vehicle can be only optimized, and the interval running time of the heavy vehicleCan increase Delta T2At the same timeStop time of train jCan reduce Delta T2,ΔT2The following equation should be satisfied:
step S24: the single-track railway for mixed passenger and freight running is optimized on the basis of the established running chart of the passenger car. The train with special operation requirements can obtain the priority right of passage by setting the priority of the train, and when the train can be optimized in the process, the train with high priority has the priority right of passage; other trains can be optimized on the basis of the train operation diagram with high priority.
Step S3: and returning to the step S1 to re-optimize the train operation diagram when the train late event occurs according to the current real-time train operation information. The current real-time running information of the train is information such as train number, total weight, length, locomotive type, running direction, located area or station, next area or station, running front speed limit and the like of the current running train. The invention can detect the actual departure event in real time, can predict the arrival time of the train at the next station according to the optimized train running speed curve when the departure event is detected, and returns to S1 when other departure events which are inconsistent with the optimized running chart are detected, optimizes the running chart again according to the current information, and transmits the optimized running chart to the vehicle-mounted terminal module and the station terminal module.
Example 2: as shown in fig. 1, fig. 2, fig. 3, fig. 4, fig. 5, fig. 6, and fig. 7, the system for energy-saving single-track railway train dispatching comprises a dispatching information acquisition module, an optimal dispatching scheme calculation module, a vehicle-mounted terminal module, an LKJ data interface module, a station terminal module, and a communication module, wherein the optimal dispatching scheme calculation module is connected with the dispatching information acquisition module, the LKJ data interface module, and the communication module is connected with the station terminal module and the vehicle-mounted terminal module.
The scheduling information acquisition module is used for reading planned operation diagram data in the train scheduling system, the module utilizes the display unit to display scheduling information in the train scheduling system in real time, utilizes the camera to acquire display information displayed by the display unit, utilizes a special image recognition algorithm to recognize the display information acquired by the camera, and transmits the display information to the optimized scheduling scheme calculation module, and the scheduling information comprises: schedule, train priority, temporary train speed limit, block, station track occupation, etc.
The LKJ data interface module is used for acquiring information such as current train number, position, total weight, length, locomotive type, running direction, train running historical data and the like from an LKJ system and transmitting the information to the optimal scheduling scheme calculating module.
And the optimized scheduling scheme calculation module optimizes the planned operation diagram based on the scheduling information provided by the scheduling information acquisition module and the current train information provided by the LKJ data interface module. The optimization process comprises the following steps: reading a planned train operation diagram from a train dispatching system, extracting train-to-transmission information from the planned operation diagram, and regenerating a feasible operation diagram according to the train-to-transmission information and a 'first-to-first' principle; optimizing all trains in the feasible operation diagram according to the time sequence and based on the rules to obtain an optimized train operation diagram; and returning to the first step when a train late event occurs according to the current real-time running information of the train, and re-optimizing the train running chart. And prompting a dispatcher to confirm after the optimization of the running chart is completed, and sending the optimized running chart to the vehicle-mounted terminal module and the station terminal module after the confirmation.
The vehicle-mounted terminal module is used for receiving the optimized operation diagram output by the optimized scheduling scheme calculation module, generating an energy-saving optimized speed curve and a locomotive operation sequence, calculating train energy consumption corresponding to the optimized operation diagram according to the outgoing energy consumption characteristic information of the locomotive and by combining with the historical measured energy consumption data, and displaying the train energy consumption to a driver.
Because the stop or passing scheme of the train at the station changes after the train dispatching scheme is adjusted, only considering the running energy consumption of the train interval is not enough when the train energy consumption is calculated, and the train slave unit needs to be calculated independentlySpeed 0 accelerates to the inter-station running average speedThe required traction energy consumption. Therefore, a train dynamics model needs to be established, and the train dynamics model can be expressed as:
wherein v is the speed of the train (unit: M/s), t is the time (unit: s), u is the traction or braking force of the train (unit: newtons), r (v) is the basic resistance of the train (unit: newtons), w is the additional resistance of the train (unit: newtons), and M is the total weight of the train (unit: Kg). Since the additional resistance during the train outbound start phase is primarily ramp resistance, the additional resistance is defined as ramp resistance:
w=g(x)
where g (x) is the ramp resistance (in newtons) of the train and x is the slope. The train traction energy consumption calculation formula is as follows:
whereinI is train number, K (K is 1,2, …, K) is station number in ascending direction (station number from Longkong to Longkoxi is 1), T is running time (unit: second), and the calculated function is obtainedFor train tractive mechanical energy (in joules), then the corresponding fuel consumption can be expressed as:
wherein eta is the thermal efficiency of the diesel engine and q is the calorific value of the diesel (unit: Joule/kg). If the stopping process of the train is increased at a certain station in the process, the train starting energy consumption needs to be calculated, and the train starting energy consumption is considered in the total energy consumption.
And the station terminal module is used for receiving the optimized operation diagram information output by the optimized scheduling scheme calculation module and presenting the optimized operation diagram information to an operator on duty in a graphic mode through a display unit.
The communication module is used for communication among the modules such as the optimized scheduling scheme calculation module, the vehicle-mounted terminal module, the LKJ data interface module, the station terminal module and the like.
In the following, the present invention is further explained by taking a single-track railway with a total length of 175 km and a total of 10 stations as a specific embodiment, where 20 trains in the up-down and down-down movement within 24 hours are taken as backgrounds at a given train departure interval, the up movement is a heavy vehicle, and the down movement is a light vehicle, and the simulation data set and obtained by the relevant parameters are shown in the following tables 1,2, 3 and 4:
TABLE 1 simulation parameters Table
Parameter name | Parameter value | Parameter name | Parameter value |
Train dead weight | 1190t | Calorific value of diesel oil | 42.6MJ/kg |
Train load | 3000t | Thermal efficiency of locomotive | 30% |
Basic resistance parameter a | 0.2474 | Train departure interval | 1h |
Basic resistance parameter b | 0.0364 | Route switching time | 1min |
Basic resistance parameter c | 0.0008 |
TABLE 2 train section running information
TABLE 3 stop information of train station
TABLE 4 comparison of energy consumption before and after optimization
Index name | Index value |
Optimized front ascending train oil consumption (liter) | 992.1 |
Optimized fuel consumption (liter) of ascending train | 862.7 |
Energy saving rate of ascending train | 13.05% |
Optimized front down train oil consumption (liter) | 455.1 |
Optimized fuel consumption (liter) of downstream train | 479.5 |
Energy saving rate of down train | -5.36% |
Total energy saving rate | 7.26% |
Under the condition of a given train departure interval, a feasible scheduling scheme is generated according to the principle of 'first-come first-serve' of the train, as shown in fig. 5, in the figure, a heavy train can be called, and a light train can be called. Each giving-up process is further optimized on the basis of a feasible scheduling scheme to generate an energy-saving giving-up scheme, as shown in fig. 6, table 2 compares the running time between trains before and after optimization, table 3 compares the train stop time before and after optimization, as can be seen from table 3, the optimized running scheme totally realizes that 'heavy vehicles are given by light vehicles', and fig. 7 shows the comparison of the running schemes before and after optimization. It can be seen from table 4 that, by adopting the technical scheme of the invention, the energy consumption of light trains is increased by 5.36%, the energy consumption of heavy trains is reduced by 13.05%, and the total energy consumption of all trains is reduced by 7.26%.
In conclusion, uncertainty in train operation is considered, single-track railway train scheduling energy-saving optimization is carried out based on real-time operation information of trains, the energy-saving efficiency is effectively improved by optimizing the train condition process and using time constraints in the optimized operation diagram as constraint conditions for train operation speed curve optimization, and meanwhile, the invention provides various parameter setting functions for users, and the users can adjust according to actual requirements and can meet energy-saving requirements under the mixed running condition of trains in various levels by setting train priorities.
It should be understood that the above-mentioned embodiments of the present invention are only examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention, and it will be obvious to those skilled in the art that other variations or modifications may be made on the basis of the above description, and all embodiments may not be exhaustive, and all obvious variations or modifications may be included within the scope of the present invention.
Claims (7)
1. An energy-saving single-track railway train scheduling method is characterized by comprising the following steps:
step S1: reading a planned train operation diagram from a train dispatching system, extracting train-to-transmission information from the planned operation diagram, and regenerating a feasible operation diagram according to the train-to-transmission information and a 'first-to-first' principle;
step S2: optimizing all trains in the feasible operation diagram according to the time sequence and based on the rules to obtain an optimized train operation diagram;
step S3: and returning to the step S1 to re-optimize the train operation diagram when the train late event occurs according to the current real-time train operation information.
2. The train dispatching method according to claim 1, wherein the planned operation diagram comprises train number, starting station, passing station, ending station, starting time and ending time, and train operation conflicts can exist in the planned operation diagram;
the feasible operation diagram is the operation diagram which meets the interval operation time requirement and solves the meeting conflict.
3. The energy-saving single-track railway train dispatching method as claimed in claim 1, wherein the principle of first arrival and first transmission is that the trains arriving first at the stations at the two ends of the target section enter the section first, and then the arriving trains wait until the section is free.
4. The energy-saving-oriented single-track railway train dispatching method as claimed in claim 1, wherein the step S2 comprises:
step S21: searching for a yield event according to time, searching for a heavy vehicle yield event for a light vehicle, prolonging the running time of the light vehicle in a section before a yield station under the condition of meeting speed limit and preparation for route switching and departure of the station, shortening the stay time of the light vehicle in the yield station, and correspondingly adjusting the running time of the next section after yield according to the influence condition;
step S22: searching for a meeting and giving event according to time, and searching for a heavy vehicle and a light vehicle, under the condition of meeting the speed limit and the preparation of station route switching and departure, adjusting the running time of the heavy vehicle in the section before the meeting and giving the heavy vehicle to the running time of the light vehicle in the section before the meeting and giving the heavy vehicle by prolonging the running time of the heavy vehicle in the section before the meeting and giving the heavy vehicle, and adjusting the running time of the next section after giving the heavy vehicle according to the influence condition;
step S23: searching for a yield event according to time, searching for a light vehicle event for a heavy vehicle, and adjusting the light vehicle event not to the heavy vehicle event according to the step S22, under the condition of meeting speed limit and preparation for route switching and departure of a station, prolonging the running time of the heavy vehicle in the previous section of the yield station, shortening the stay time of the heavy vehicle in the yield station, and correspondingly adjusting the running time of the next section after yield according to the influence condition;
step S24: the single-track railway for mixed passenger and freight running is optimized on the basis of the established running chart of the passenger car.
5. The energy-saving single-track railway train dispatching method as claimed in claim 1, wherein the current train real-time running information is train number, total weight, length, locomotive type, running direction, located section or station, next section or station, and speed limit information ahead of running of the current train.
6. The energy-saving oriented single-track railway train dispatching method as claimed in claim 1, wherein the optimized train operation diagram is generated and then transmitted to a vehicle-mounted terminal module as a constraint condition for locomotive speed curve optimization.
7. An energy-saving single-track railway train dispatching system is characterized by comprising a dispatching information acquisition module, an optimized dispatching scheme calculation module, a vehicle-mounted terminal module, an LKJ data interface module, a station terminal module and a communication module;
the scheduling information acquisition module is used for reading the planned operation chart data in the train scheduling system, the module utilizes the display unit to display the scheduling information in the train scheduling system in real time, and the scheduling information comprises: the method comprises the steps that a planning schedule, a train priority, a train temporary speed limit, a zone block and station track occupation are adopted, a camera is used for obtaining display information displayed by a display unit, a special image recognition algorithm is used for recognizing the display information collected by the camera, and the display information is transmitted to an optimized scheduling scheme calculation module;
the LKJ data interface module is used for acquiring current train number, position, total weight, length, locomotive type, running direction and train running historical data information from the LKJ system and transmitting the information to the optimal scheduling scheme calculation module;
the optimized scheduling scheme calculation module optimizes the planned operation diagram based on the scheduling information provided by the scheduling information acquisition module and the information provided by the LKJ data interface module, prompts a dispatcher to confirm after the operation diagram is optimized, and sends the optimized operation diagram to the vehicle-mounted terminal module and the station terminal module after the confirmation;
the vehicle-mounted terminal module is used for receiving the optimized operation diagram output by the optimized scheduling scheme calculation module, generating an energy-saving optimized speed curve and a locomotive operation sequence, calculating train energy consumption corresponding to the optimized operation diagram according to the outgoing energy consumption characteristic information of the locomotive and by combining with historical measured energy consumption data, and displaying the train energy consumption to a driver;
the station terminal module is used for receiving the optimized operation diagram information output by the optimized scheduling scheme calculation module and presenting the optimized operation diagram information to an operator on duty in a graphic mode through a display unit;
the communication module is used for communication among the modules of the optimized scheduling scheme calculation module, the vehicle-mounted terminal module, the LKJ data interface module and the station terminal module.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2020104357117 | 2020-05-21 | ||
CN202010435711 | 2020-05-21 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111791923A true CN111791923A (en) | 2020-10-20 |
CN111791923B CN111791923B (en) | 2021-06-29 |
Family
ID=72834175
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010912686.7A Active CN111791923B (en) | 2020-05-21 | 2020-09-01 | Energy-saving-oriented single-track railway train scheduling method and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111791923B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113415324A (en) * | 2021-08-03 | 2021-09-21 | 东北大学 | Dynamic scheduling and operation control collaborative optimization method and system for high-speed train |
CN113830143A (en) * | 2021-11-29 | 2021-12-24 | 中国铁道科学研究院集团有限公司通信信号研究所 | Day shift plan application method and device based on CTC system |
CN114044031A (en) * | 2021-12-21 | 2022-02-15 | 卡斯柯信号有限公司 | Automatic train diagram adjusting method, storage medium and electronic device |
CN115366957A (en) * | 2022-05-07 | 2022-11-22 | 深圳市永达电子信息股份有限公司 | Method and system for quickly acquiring information island information data based on locomotive running |
Citations (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0357767A (en) * | 1989-07-24 | 1991-03-13 | Omron Corp | Automatic set type fuzzy controller for operation diagram |
JP4170520B2 (en) * | 1999-06-10 | 2008-10-22 | 東武鉄道株式会社 | Train operation management system operation management system |
CN102285364A (en) * | 2011-05-05 | 2011-12-21 | 西安理工大学 | Distributed train concurrent dispatching method based on train priorities |
CN103390196A (en) * | 2013-06-14 | 2013-11-13 | 北京交通大学 | High speed train operation planning optimization method and system under complex constraint condition |
CN103738367A (en) * | 2013-12-27 | 2014-04-23 | 北京交控科技有限公司 | Rail transit planed running chart optimization method |
JP5528147B2 (en) * | 2010-02-15 | 2014-06-25 | 三菱電機株式会社 | Driving arrangement support system and driving arrangement support method |
CN104192176A (en) * | 2014-05-19 | 2014-12-10 | 广州市地下铁道总公司 | Method for reducing metro traction energy consumption |
CN104875774A (en) * | 2015-06-16 | 2015-09-02 | 北京交通大学 | Train delay adjusting method and system based on urban rail transit working diagram |
JP2016159746A (en) * | 2015-02-27 | 2016-09-05 | 株式会社東芝 | Operation plan preparation device and program |
CN105930937A (en) * | 2016-05-07 | 2016-09-07 | 浙江大学 | Subway operation and scheduling integrated optimization method taking into consideration of subway fast and slow lines |
CN106335524A (en) * | 2016-09-08 | 2017-01-18 | 北京交通大学 | Urban rail transit part route operation regulating method in emergency scene |
CN106476854A (en) * | 2016-10-13 | 2017-03-08 | 交控科技股份有限公司 | A kind of train diagram establishment method and device |
US10023071B2 (en) * | 2015-08-25 | 2018-07-17 | Beijing Jioatong University | Train control method for maximizing utilization of regenerative energy |
CN108564209A (en) * | 2018-03-30 | 2018-09-21 | 广州地铁设计研究院有限公司 | A kind of urban track traffic speed car service chart optimization method and system |
CN109649417A (en) * | 2019-01-10 | 2019-04-19 | 北京交通大学 | A kind of municipal rail train traction energy consumption integrative simulation optimization system |
CN109784684A (en) * | 2018-12-27 | 2019-05-21 | 中国铁道科学研究院集团有限公司通信信号研究所 | A kind of adjusted train diagram policy decision method of case-based reasioning |
CN110287564A (en) * | 2019-06-17 | 2019-09-27 | 北京交通大学 | A kind of floating energy-saving run chart optimization method of the middling speed magnetic based on genetic algorithm |
CN110341763A (en) * | 2019-07-19 | 2019-10-18 | 东北大学 | A kind of intelligent dispatching system that fast quick-recovery high-speed rail train is run on schedule and method |
CN110533242A (en) * | 2019-08-26 | 2019-12-03 | 北京交通大学 | The energy conservation optimizing method that train interconnects under movement across lines |
CN110775112A (en) * | 2019-11-15 | 2020-02-11 | 通号城市轨道交通技术有限公司 | Real-time train operation diagram adjusting method and system |
CN110782079A (en) * | 2019-10-18 | 2020-02-11 | 西南交通大学 | Method for adjusting energy-saving high-speed railway train running chart based on stop scheme |
CN110843866A (en) * | 2018-08-21 | 2020-02-28 | 比亚迪股份有限公司 | Single-wire line driving organization method, device and storage medium |
CN111055891A (en) * | 2019-12-26 | 2020-04-24 | 交控科技股份有限公司 | Train operation diagram adjusting method |
-
2020
- 2020-09-01 CN CN202010912686.7A patent/CN111791923B/en active Active
Patent Citations (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0357767A (en) * | 1989-07-24 | 1991-03-13 | Omron Corp | Automatic set type fuzzy controller for operation diagram |
JP4170520B2 (en) * | 1999-06-10 | 2008-10-22 | 東武鉄道株式会社 | Train operation management system operation management system |
JP5528147B2 (en) * | 2010-02-15 | 2014-06-25 | 三菱電機株式会社 | Driving arrangement support system and driving arrangement support method |
CN102285364A (en) * | 2011-05-05 | 2011-12-21 | 西安理工大学 | Distributed train concurrent dispatching method based on train priorities |
CN103390196A (en) * | 2013-06-14 | 2013-11-13 | 北京交通大学 | High speed train operation planning optimization method and system under complex constraint condition |
CN103738367A (en) * | 2013-12-27 | 2014-04-23 | 北京交控科技有限公司 | Rail transit planed running chart optimization method |
CN104192176A (en) * | 2014-05-19 | 2014-12-10 | 广州市地下铁道总公司 | Method for reducing metro traction energy consumption |
JP2016159746A (en) * | 2015-02-27 | 2016-09-05 | 株式会社東芝 | Operation plan preparation device and program |
CN104875774A (en) * | 2015-06-16 | 2015-09-02 | 北京交通大学 | Train delay adjusting method and system based on urban rail transit working diagram |
US10023071B2 (en) * | 2015-08-25 | 2018-07-17 | Beijing Jioatong University | Train control method for maximizing utilization of regenerative energy |
CN105930937A (en) * | 2016-05-07 | 2016-09-07 | 浙江大学 | Subway operation and scheduling integrated optimization method taking into consideration of subway fast and slow lines |
CN106335524A (en) * | 2016-09-08 | 2017-01-18 | 北京交通大学 | Urban rail transit part route operation regulating method in emergency scene |
CN106476854A (en) * | 2016-10-13 | 2017-03-08 | 交控科技股份有限公司 | A kind of train diagram establishment method and device |
CN108564209A (en) * | 2018-03-30 | 2018-09-21 | 广州地铁设计研究院有限公司 | A kind of urban track traffic speed car service chart optimization method and system |
CN110843866A (en) * | 2018-08-21 | 2020-02-28 | 比亚迪股份有限公司 | Single-wire line driving organization method, device and storage medium |
CN109784684A (en) * | 2018-12-27 | 2019-05-21 | 中国铁道科学研究院集团有限公司通信信号研究所 | A kind of adjusted train diagram policy decision method of case-based reasioning |
CN109649417A (en) * | 2019-01-10 | 2019-04-19 | 北京交通大学 | A kind of municipal rail train traction energy consumption integrative simulation optimization system |
CN110287564A (en) * | 2019-06-17 | 2019-09-27 | 北京交通大学 | A kind of floating energy-saving run chart optimization method of the middling speed magnetic based on genetic algorithm |
CN110341763A (en) * | 2019-07-19 | 2019-10-18 | 东北大学 | A kind of intelligent dispatching system that fast quick-recovery high-speed rail train is run on schedule and method |
CN110533242A (en) * | 2019-08-26 | 2019-12-03 | 北京交通大学 | The energy conservation optimizing method that train interconnects under movement across lines |
CN110782079A (en) * | 2019-10-18 | 2020-02-11 | 西南交通大学 | Method for adjusting energy-saving high-speed railway train running chart based on stop scheme |
CN110775112A (en) * | 2019-11-15 | 2020-02-11 | 通号城市轨道交通技术有限公司 | Real-time train operation diagram adjusting method and system |
CN111055891A (en) * | 2019-12-26 | 2020-04-24 | 交控科技股份有限公司 | Train operation diagram adjusting method |
Non-Patent Citations (12)
Title |
---|
BWO-REN KE: "Improvement of Freight Train Timetable for Single-Track Railway System", 《2012 INTERNATIONAL SYMPOSIUM ON COMPUTER, CONSUMER AND CONTROL》 * |
HAINAN ZHU: "Analysis and design of Driver Advisory System (DAS) for energy-efficient train operation with real-time information", 《2016 IEEE INTERNATIONAL CONFERENCE ON INTELLIGENT RAIL TRANSPORTATION (ICIRT)》 * |
史峰: "考虑动车组周转和到发线运用的高速铁路列车运行图优化方法", 《中国铁道科学》 * |
孙焰: "单线区段货物列车运行图的一种优化方法", 《铁道学报》 * |
张晓倩: "城市轨道交通共线交路运行图的优化与编制", 《计算机应用与软件》 * |
朱子轩: "单线铁路网络列车运行智能调度仿真研究", 《计算机仿真》 * |
王军: "单线重载线路能力计算利用与加强关键技术研究", 《中国博士学位论文全文数据库 工程科技Ⅱ辑》 * |
王涛: "高速铁路行车调度节能运行图编制方法研究", 《铁路计算机应用》 * |
谈绍强: "面向节能的单线铁路调度方法研究", 《铁路计算机应用》 * |
赵强: "单线铁路列车运行调整计算机辅助决策系统研究", 《铁道学报》 * |
陈钉均: "《路网条件下铁路列车运行方案图与优化理论与方法》", 31 December 2017 * |
高天: "高速铁路列车运行方案图编制优化方法及系统规划研究", 《中国硕士学位论文全文数据库 工程科技Ⅱ辑》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113415324A (en) * | 2021-08-03 | 2021-09-21 | 东北大学 | Dynamic scheduling and operation control collaborative optimization method and system for high-speed train |
CN113830143A (en) * | 2021-11-29 | 2021-12-24 | 中国铁道科学研究院集团有限公司通信信号研究所 | Day shift plan application method and device based on CTC system |
CN114044031A (en) * | 2021-12-21 | 2022-02-15 | 卡斯柯信号有限公司 | Automatic train diagram adjusting method, storage medium and electronic device |
CN114044031B (en) * | 2021-12-21 | 2024-01-30 | 卡斯柯信号有限公司 | Automatic adjustment method for train running chart, storage medium and electronic equipment |
CN115366957A (en) * | 2022-05-07 | 2022-11-22 | 深圳市永达电子信息股份有限公司 | Method and system for quickly acquiring information island information data based on locomotive running |
Also Published As
Publication number | Publication date |
---|---|
CN111791923B (en) | 2021-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111791923B (en) | Energy-saving-oriented single-track railway train scheduling method and system | |
CN110782079B (en) | Method for adjusting energy-saving high-speed railway train running chart based on stop scheme | |
CN104299433B (en) | Bus signal priority control method based on RFID vehicle carried electronic label | |
CN108831143A (en) | Signalized intersections fleet speed guiding method based on bus or train route coordination technique | |
CN107914740B (en) | Train self-organizing dispatching system and method based on real-time passenger flow | |
CN110194201A (en) | A kind of column control grade converting system and its method | |
CN113353122B (en) | Control method of virtual coupling high-speed train under brake force failure of tracking train | |
CN108447282A (en) | A kind of public transport Real-Time Scheduling and method for controlling priority based on bus or train route collaboration | |
CN101428619A (en) | Railbus traffic system | |
CN111859718B (en) | Method and system for calculating congestion coefficient of regional multi-standard rail transit station | |
CN108501960A (en) | A kind of sky iron rail system and empty iron operation method | |
CN114132363A (en) | Train operation diagram compiling method based on passenger flow space-time state fine analysis | |
CN109559499A (en) | Vehicle platoon traveling management platform, control method and car-mounted terminal | |
CN102063791B (en) | Public transport travelling control method by combining signal control with positioning monitoring | |
CN113077162A (en) | Multi-vehicle type customized bus area scheduling method facing real-time requirements | |
CN108922211A (en) | Consider that the BRT bus rider speed of website, signal lamp and front truck constraint optimizes recommended method | |
CN113361917B (en) | High-speed train rescheduling method based on dynamic passenger flow under strong wind condition | |
Liu et al. | Modelling and simulation of cooperative control for bus rapid transit vehicle platoon in a connected vehicle environment | |
CN111524372B (en) | Bus signal priority implementation method and system based on artificial intelligence bus-road cooperation | |
CN117401001A (en) | Urban rail multi-train driving scheduling comprehensive energy-saving control method and device under complex working conditions | |
CN115432037B (en) | Method and system for calculating maximum passing capacity of high-speed rail section | |
CN111859717B (en) | Method and system for minimizing regional multi-standard rail transit passenger congestion coefficient | |
CN115545336A (en) | Track traffic stroke fine adjustment system and method | |
CN111369065B (en) | Method for determining minimum marshalling number of goods train based on time window constraint | |
CN111931386B (en) | Method and system for calculating congestion coefficient of regional multi-standard rail traffic interval |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |