CN111778876A - Construction method of wide hanging basket - Google Patents

Construction method of wide hanging basket Download PDF

Info

Publication number
CN111778876A
CN111778876A CN202010742114.9A CN202010742114A CN111778876A CN 111778876 A CN111778876 A CN 111778876A CN 202010742114 A CN202010742114 A CN 202010742114A CN 111778876 A CN111778876 A CN 111778876A
Authority
CN
China
Prior art keywords
hanging basket
tracks
loading
basket
walking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010742114.9A
Other languages
Chinese (zh)
Inventor
张承实
毋存粮
吴靖江
郭永富
王洪涛
杨孝孝
宋胜欢
张扬
李�瑞
秦亚丽
胡连超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Transportation Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Transportation Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd, Transportation Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202010742114.9A priority Critical patent/CN111778876A/en
Publication of CN111778876A publication Critical patent/CN111778876A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F3/00Devices, e.g. jacks, adapted for uninterrupted lifting of loads
    • B66F3/24Devices, e.g. jacks, adapted for uninterrupted lifting of loads fluid-pressure operated
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels

Abstract

The invention relates to a construction method of a wide hanging basket; the technical scheme for solving the problem comprises the following steps: the stress and the elongation of each suspender are calculated through the Midas checking, and the bottom templates at different suspender positions are pre-lifted according to the calculation result; step two: the bottom basket is provided with a sliding beam and a rolling box, and the sliding beam supports the bottom basket to move on the rolling box when the hanging basket moves; step three: a reserved hole is formed in the No. 0 block, the upper structure of the single-side hanging basket is integrally assembled, stress of each reaction rod is calculated according to the concrete distribution condition of the beam body, and grading loading is carried out according to the prepressing requirement; step four: the six walking tracks are accurately adjusted by a level gauge, the heights of the tops of the six walking tracks are ensured to be on the same horizontal plane, the top surfaces of the tracks are polished to be flat, polytetrafluoroethylene plates are paved, the friction coefficients of the six tracks are basically the same, synchronous hydraulic jacks are adopted, the pressure and the extension of each jack are basically the same, a specially assigned person is sent to supervise the walking synchronism of the six main trusses, and the adjustment is carried out in time when the deviation exceeds 2 cm.

Description

Construction method of wide hanging basket
Technical Field
The invention relates to the field of hanging basket construction methods, in particular to a wide hanging basket construction method.
Background
A plurality of problems of the wide hanging basket during construction, for example, the main bridge of the sinking hill sand river bridge is a double-tower double-cable-surface short-tower cable-stayed bridge, and the span is arranged as follows: 75+130+75m =280m, the bridge floor width is 40m, the beam bottom width is 31m, the structure is arranged in a whole frame, cantilever cast-in-place construction is adopted, the cantilever cast-in-place construction belongs to an ultra-wide hanging basket, an upper beam and a lower beam in front of the hanging basket are connected through 15 hanging straps, the extension amount of the hanging straps is 3-21mm, a method different from a conventional hanging basket is needed to be adopted to ensure the transverse flatness of the beam bottom plate 31m width, according to a simulation calculation result, the bottom basket is hung by only depending on the hanging straps on the outer side of the bottom plate, the strength and the rigidity of the lower beam cannot meet requirements, the ultra-wide hanging basket is specially designed to ensure the stability and the safety of the bottom basket when the hanging basket walks, the maximum segment of the beam is 235.5m in profile, the conventional preloading method is adopted, 15 days is consumed, manpower and material resources are extremely high, the occupation time of a key line is long, an unconventional preloading, The walking method of the system ensures the walking synchronization and the walking safety of the 6 main trusses.
Disclosure of Invention
Aiming at the situation, in order to overcome the defects of the prior art, the invention provides a construction method of a wide hanging basket, which effectively solves the problems of great consumption of manpower and material resources and long occupied time of a line in the design and construction process of the conventional wide hanging basket.
The technical scheme for solving the problems is that the construction method of the wide hanging basket comprises the following construction steps:
the method comprises the following steps: the stress and the elongation of each suspender are calculated through the Midas checking, and the bottom templates at different suspender positions are pre-lifted according to the calculation result;
step two: the bottom basket is provided with a sliding beam and a rolling box, and the sliding beam supports the bottom basket to move on the rolling box when the hanging basket moves;
step three: a reserved hole is formed in the No. 0 block, the upper structure of the single-side hanging basket is integrally assembled, stress of each reaction rod is calculated according to the concrete distribution condition of the beam body, and grading loading is carried out according to the prepressing requirement;
step four: the six walking tracks are accurately adjusted by a level gauge, the heights of the tops of the six walking tracks are ensured to be on the same horizontal plane, the top surfaces of the tracks are polished to be flat, polytetrafluoroethylene plates are paved, the friction coefficients of the six tracks are basically the same, synchronous hydraulic jacks are adopted, the pressure and the extension of each jack are basically the same, a specially assigned person is sent to supervise the walking synchronism of the six main trusses, and the adjustment is carried out in time when the deviation exceeds 2 cm.
The hanging basket is novel in concept, ingenious in structure and high in practicability, and effectively solves the problems that manpower and material resources are greatly consumed and the occupied time of a line is long in the design and construction process of the conventional wide hanging basket.
Drawings
Fig. 1 is a picture puzzle of a hanging basket set of the present invention.
Fig. 2 is a front cross-sectional view of a bridge according to the present invention.
FIG. 3 is a schematic view of the diamond frame assembly structure of the present invention.
FIG. 4 is a schematic view of the walking system of the present invention.
FIG. 5 is a schematic view of the construction of the rear anchor system of the present invention.
Detailed Description
The following describes embodiments of the present invention in further detail with reference to the accompanying drawings.
The construction method comprises the following steps:
the method comprises the following steps: the stress and the elongation of each suspender are calculated through the Midas checking, and the bottom templates at different suspender positions are pre-lifted according to the calculation result;
step two: the bottom basket is provided with a sliding beam and a rolling box, and the sliding beam supports the bottom basket to move on the rolling box when the hanging basket moves;
step three: a reserved hole is formed in the No. 0 block, the upper structure of the single-side hanging basket is integrally assembled, stress of each reaction rod is calculated according to the concrete distribution condition of the beam body, and grading loading is carried out according to the prepressing requirement;
step four: the six walking tracks are accurately adjusted by a level gauge, the heights of the tops of the six walking tracks are ensured to be on the same horizontal plane, the top surfaces of the tracks are polished to be flat, polytetrafluoroethylene plates are paved, the friction coefficients of the six tracks are basically the same, synchronous hydraulic jacks are adopted, the pressure and the extension of each jack are basically the same, a specially assigned person is sent to supervise the walking synchronism of the six main trusses, and the adjustment is carried out in time when the deviation exceeds 2 cm.
In the third step, phi 32 finish-rolled deformed steel bars and preformed holes are pre-embedded in the top plate of the No. 0 block, the upper structure of the hanging basket is assembled as required, the counter-force beam is placed at the designed position after the completion, the finish-rolled deformed steel bars are lengthened to serve as pull rods, and anchor plates and anchor nuts are assembled.
In step three, the experimental loading procedure: the loading adopts a mode of symmetrical loading according to working conditions, the load is a box girder load, and a jack loading path is as follows: r2 (R2 ') → R3 (R3') → R4 (R4 ')) → R5 (R5') → R6 (R6 ') → R7 (R7')) → R8 (R8 ') → R9 → R1 (R1');
the test procedure was as follows:
the first step is as follows: laying elevation monitoring points, measuring and recording original elevation values;
the second step is that: respectively placing the two jacks to R2 and R2', starting the oil pump to load to a designed value, screwing down the anchoring nut, and removing the jacks; respectively moving the jack to the positions R3 and R3', loading, and screwing down the anchoring nut; sequentially moving to R2 (R2') to finish loading;
the third step: measuring and recording elevation values of elevation layout points;
the fourth step: and repeating the second step and the third step according to a monitoring program to complete the prepressing monitoring.
Compared with the traditional equipment, the device has the following advantages:
the construction method improves the wide hanging basket memory ultra-wide hanging basket construction and erection, and the flatness of the hanging basket is difficult to ensure in the traditional wide hanging basket construction; the bottom basket is suspended by only the hanging strip on the outer side of the bottom plate, the strength and the rigidity of the rear lower cross beam cannot meet the requirements, the ultra-wide hanging basket needs to be specially designed, so that the stability and the safety of the bottom basket when the hanging basket is in walking are guaranteed, and a targeted solution is made to the problems that manpower and material resources are greatly consumed and the occupied time of a line is long in the construction process.

Claims (3)

1. The construction method of the wide hanging basket is characterized by comprising the following construction steps:
the method comprises the following steps: the stress and the elongation of each suspender are calculated through the Midas checking, and the bottom templates at different suspender positions are pre-lifted according to the calculation result;
step two: the bottom basket is provided with a sliding beam and a rolling box, and the sliding beam supports the bottom basket to move on the rolling box when the hanging basket moves;
step three: a reserved hole is formed in the No. 0 block, the upper structure of the single-side hanging basket is integrally assembled, stress of each reaction rod is calculated according to the concrete distribution condition of the beam body, and grading loading is carried out according to the prepressing requirement;
step four: the six walking tracks are accurately adjusted by a level gauge, the heights of the tops of the six walking tracks are ensured to be on the same horizontal plane, the top surfaces of the tracks are polished to be flat, polytetrafluoroethylene plates are paved, the friction coefficients of the six tracks are basically the same, synchronous hydraulic jacks are adopted, the pressure and the extension of each jack are basically the same, a specially assigned person is sent to supervise the walking synchronism of the six main trusses, and the adjustment is carried out in time when the deviation exceeds 2 cm.
2. The construction method of the wide hanging basket according to claim 1, characterized in that phi 32 finish-rolled deformed steel bars and reserved holes are pre-embedded in a top plate of a No. 0 block, the upper structure of the hanging basket is assembled as required, a counter-force beam is placed at a design position after the completion, the finish-rolled deformed steel bars are lengthened to serve as pull rods, and anchor plates and anchor nuts are installed.
3. The wide hanging basket construction method according to claim 1, characterized in that a test loading process: the loading adopts a mode of symmetrical loading according to working conditions, the load is a box girder load, and a jack loading path is as follows: r2 (R2 ') → R3 (R3') → R4 (R4 ')) → R5 (R5') → R6 (R6 ') → R7 (R7')) → R8 (R8 ') → R9 → R1 (R1');
the test procedure was as follows:
the first step is as follows: laying elevation monitoring points, measuring and recording original elevation values;
the second step is that: respectively placing the two jacks to R2 and R2', starting the oil pump to load to a designed value, screwing down the anchoring nut, and removing the jacks; respectively moving the jack to the positions R3 and R3', loading, and screwing down the anchoring nut; sequentially moving to R2 (R2') to finish loading;
the third step: measuring and recording elevation values of elevation layout points;
the fourth step: and repeating the second step and the third step according to a monitoring program to complete the prepressing monitoring.
CN202010742114.9A 2020-07-29 2020-07-29 Construction method of wide hanging basket Pending CN111778876A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010742114.9A CN111778876A (en) 2020-07-29 2020-07-29 Construction method of wide hanging basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010742114.9A CN111778876A (en) 2020-07-29 2020-07-29 Construction method of wide hanging basket

Publications (1)

Publication Number Publication Date
CN111778876A true CN111778876A (en) 2020-10-16

Family

ID=72766489

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010742114.9A Pending CN111778876A (en) 2020-07-29 2020-07-29 Construction method of wide hanging basket

Country Status (1)

Country Link
CN (1) CN111778876A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007205090A (en) * 2006-02-03 2007-08-16 Okkusu Jack Kk Transfer method of heavy load and its apparatus
CN102912738A (en) * 2012-11-07 2013-02-06 北京市公路桥梁建设集团有限公司 Overall prepressing device for hanging basket
CN103911957A (en) * 2014-04-09 2014-07-09 中交隧道工程局有限公司 Prestressed continuous box-girder cantilever construction basket
CN107034791A (en) * 2017-06-27 2017-08-11 中交第三航务工程局有限公司 A kind of assembling method of Cantilever Casting Construction Hanging Basket
CN107366234A (en) * 2017-07-26 2017-11-21 中交公局第二工程有限公司 A kind of constructing device that Hanging Basket is aided in using electric block

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007205090A (en) * 2006-02-03 2007-08-16 Okkusu Jack Kk Transfer method of heavy load and its apparatus
CN102912738A (en) * 2012-11-07 2013-02-06 北京市公路桥梁建设集团有限公司 Overall prepressing device for hanging basket
CN103911957A (en) * 2014-04-09 2014-07-09 中交隧道工程局有限公司 Prestressed continuous box-girder cantilever construction basket
CN107034791A (en) * 2017-06-27 2017-08-11 中交第三航务工程局有限公司 A kind of assembling method of Cantilever Casting Construction Hanging Basket
CN107366234A (en) * 2017-07-26 2017-11-21 中交公局第二工程有限公司 A kind of constructing device that Hanging Basket is aided in using electric block

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
屈振学: "超宽PC箱梁大节段悬浇施工技术研究", 《桥梁工程》 *
毋存粮等: "下导式无主桁斜拉挂篮在宽幅桥梁悬臂施工中的应用", 《施工技术》 *
郭万辉: "高墩大跨连续刚构桥挂篮反力架预压施工技术", 《交通世界》 *

Similar Documents

Publication Publication Date Title
CN107338963B (en) A kind of over-the-counter construction method for hanging of super-span truss string structure
CN102080357B (en) Integrated beam-falling device and method for steel pipe pier bailey beam cast-in-place bracket
CN106812328B (en) The whole two step lifting construction methods of string prestressed steel structure rack with hanging layer
CN102477717B (en) A kind of bridge pushing construction method
CN105297635B (en) Assembled lifting type construction platform for pier column construction and construction method thereof
CN105970811B (en) Long span space three-dimensional curved surface fish-bellied type box shape steel structure elevated bridge construction technology
CN208815424U (en) A kind of bridge descending hanging basket
CN105740560B (en) A kind of continuous assembling construction simulation assembling method of steel tube arch rib segment jig frame
CN203923924U (en) No. 0 section bracket prepressing device
CN102704705A (en) Building long-stroke redescending-free multi-point synchronous jacking method
CN107476581B (en) Hoisting and mounting method for steel structure double-layer overhanging structure
CN109208915B (en) Construction method for integrally lifting cooling tower system and steel gallery
CN110206366A (en) A kind of arch large-span prestressed steel structure and its construction method
CN112160255A (en) Counter-force prepressing method and tool for zero-number block bracket of double-limb thin-wall pier
CN109577212A (en) A kind of pretensioned prestressing Precasting Pedestal Construction method
CN111778876A (en) Construction method of wide hanging basket
CN105155418A (en) Construction method for bridge horizontal movement
CN205839594U (en) Over-and-under type construction system that bridge superstructure construction used
CN106836851A (en) Deep basal pit hanging-type construction stair and its construction method
CN205242238U (en) Be applied to self anchored suspension bridge's main girder structure
CN112627068B (en) Bridge support replacing auxiliary device and replacing method thereof
CN206034460U (en) Subway foundation pit liftable support system
CN110387824B (en) Cable tower creeping formwork aerial rail transfer construction method
CN210239677U (en) Structural system for controlling deformation of subway shield tunnel
CN109057363B (en) Tower type sliding support frame and construction method of large-span semicircular pipe truss structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201016

RJ01 Rejection of invention patent application after publication