CN111768123A - Visual management system for power distribution network construction site - Google Patents

Visual management system for power distribution network construction site Download PDF

Info

Publication number
CN111768123A
CN111768123A CN202010653016.8A CN202010653016A CN111768123A CN 111768123 A CN111768123 A CN 111768123A CN 202010653016 A CN202010653016 A CN 202010653016A CN 111768123 A CN111768123 A CN 111768123A
Authority
CN
China
Prior art keywords
unit
data
construction site
management
distribution network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010653016.8A
Other languages
Chinese (zh)
Inventor
何平
刘建忠
万飞
石浩玮
李明
汪丰阳
杨帅
余悦
张玉东
李煜峰
任旭
张继林
王翔峰
樊立伟
宋冬
项宝平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ordos Electric Power Bureau Of Inner Mongolia Power Group Co ltd
Original Assignee
Ordos Electric Power Bureau Of Inner Mongolia Power Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ordos Electric Power Bureau Of Inner Mongolia Power Group Co ltd filed Critical Ordos Electric Power Bureau Of Inner Mongolia Power Group Co ltd
Priority to CN202010653016.8A priority Critical patent/CN111768123A/en
Publication of CN111768123A publication Critical patent/CN111768123A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B25/00Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems
    • G08B25/01Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems characterised by the transmission medium
    • G08B25/08Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems characterised by the transmission medium using communication transmission lines
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B25/00Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems
    • G08B25/01Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems characterised by the transmission medium
    • G08B25/10Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems characterised by the transmission medium using wireless transmission systems
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N5/00Details of television systems
    • H04N5/76Television signal recording
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
    • H04N7/181Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast for receiving images from a plurality of remote sources

Abstract

The invention discloses a power distribution network construction site visual management system which comprises a video monitoring unit, an approach management unit, an abnormality reminding unit, a tower positioning unit, a data wireless transmission unit, a comparison database, a report generating unit, a data importing unit, an operation terminal, a real-time display unit and a central processing unit, wherein the approach management unit is used for monitoring the approach of a power distribution network; the video monitoring unit, the entrance management unit, the abnormity reminding unit and the tower positioning unit are connected with the data wireless transmission unit; the data wireless transmission unit, the comparison database, the report generation unit, the data import unit, the operation terminal and the real-time display unit are connected with the central processing unit. Has the advantages that: a mode of hierarchical management and multistage application is established, so that managers at each level can remotely master the operation progress and risk condition of a construction site in real time, the major risk of the power grid project is supervised and controlled in the whole process, and the safety control capability and the management efficiency of the project site are improved; the green, energy-saving and high-efficiency construction of the power grid is realized.

Description

Visual management system for power distribution network construction site
The technical field is as follows:
the invention relates to the technical field of engineering monitoring, in particular to a visual management system for a power distribution network construction site.
Background art:
with the rapid development of national economy in China, the power consumption demand is higher and higher, and the construction projects of the power engineering are increased day by day. The electric power engineering project relates to a plurality of factors such as personnel, machines, materials and environment, has high management difficulty and frequently generates electric power construction operation accidents.
At present, the power distribution network construction project has the difficult problems of large volume, short construction period, many process interlude, large personnel flow amplitude and the like, and the difficulty of safety supervision is higher. Meanwhile, in the supervision process, due to the fact that the related materials are various, data information of tower equipment is not complete and inaccurate, and the like, the requirements for energy conservation, emission reduction and green construction cannot be met due to the existence of one or more problems. And the mode that uses the manual work to solve in traditional management is with high costs, inefficiency, and information acquisition is untimely, and project management personnel can not realize the considerable, measurable, controllable lean management and control demand to overall process such as project safety, quality, progress, and project management personnel are difficult to realize the control to the whole condition of engineering. Resulting in undesirable final management effects. Therefore, the quality improvement, consumption reduction and efficiency improvement are urgently needed by applying an informatization means, so that the project is informationized, automatically and intelligently progresses, and an intelligent construction site is realized.
The invention content is as follows:
the invention aims to provide a power distribution network construction site visual management system which carries out overall process supervision and control on major risks of power grid engineering and improves the engineering site safety control capability and management efficiency.
The invention is implemented by the following technical scheme: the visual management system for the power distribution network construction site comprises a video monitoring unit, an entrance management unit, an abnormality reminding unit, a tower positioning unit, a data wireless transmission unit, a comparison database, a report generation unit, a data import unit, an operation terminal, a real-time display unit and a central processing unit; the video monitoring unit, the entrance management unit, the abnormity reminding unit and the tower positioning unit are connected with the data wireless transmission unit; the data wireless transmission unit, the comparison database, the report generation unit, the data import unit and the real-time display unit are connected with the central processing unit;
preferably, the video monitoring unit is used for collecting video information of a construction site, and comprises a fixed high-definition monitoring camera and a movable monitoring camera arranged on a safety helmet; the video monitoring unit is connected with the data wireless transmission unit through a 5G wireless communication module.
Preferably, the entrance management unit is used for identifying the identity information of personnel entering and exiting the construction site, and comprises a fingerprint authentication module, a face authentication module, an iris authentication module and an RFID authentication module; the entrance management unit is connected with the data wireless transmission unit through a 5G wireless communication module.
Preferably, the abnormality reminding unit is configured to remind and alarm for abnormal data, and the abnormality reminding unit includes an optical alarm device and an acoustic alarm device, and the optical alarm device and the acoustic alarm device are configured to provide an optical alarm and an acoustic alarm; the abnormity prompting unit is connected with the data wireless transmission unit through a 5G wireless communication module.
Preferably, the tower positioning unit is used for transmitting tower position information in real time; the tower positioning unit comprises an RFID module, a Beidou/GPS positioning module, a narrow-band Internet of things protocol communication module and an encryption transmission module; the abnormity prompting unit is connected with the data wireless transmission unit through the narrow-band Internet of things protocol communication module.
Preferably, the comparison database comprises a data storage module, a data updating module and a data transmission module, the data storage module is used for storing all data sent by the central processing unit, the data updating module is used for updating relevant indexes of a power distribution network construction site, and the data transmission module is used for realizing bidirectional transmission between the central processing unit and the comparison database.
Preferably, the report generation unit is connected to a report printing unit, the report generation unit is configured to generate the collected data, the analyzed data, and the predicted data, and the report printing unit is configured to print out all data generated in the report generation unit.
Preferably, the data import unit is used for importing construction progress, operation tasks, operation time periods, building personnel, and the number and types of operation equipment.
Preferably, the real-time display unit is used for displaying the monitored data and the analyzed data in real time.
The invention has the advantages that: a mode of hierarchical management and multistage application is established, so that managers at each level can remotely master the operation progress and risk condition of a construction site in real time, and particularly, overall process supervision and control are carried out on major risks of power grid engineering, and the safety management and control capability and management efficiency of the engineering site are greatly improved; the system realizes real-time remote monitoring of the construction site, improves the engineering management efficiency, supervises the safe and civilized construction of the engineering site, and realizes green, energy-saving and high-efficiency power grid construction.
The intelligent video high-definition monitoring, face recognition, RFID, narrowband Internet of things protocol (NB-IOT), 5G/4G and other technologies are applied to construction site management, the intelligent video high-definition monitoring, operation site personnel positioning and violation operation instant early warning are included, the access control, safety monitoring, site positioning and violation early warning of production area workers are realized, and the number of the site personnel and the site time are managed in real time. The construction site management strength is enhanced, the construction site management process is perfected, the real-time monitoring of the construction site is realized, and an intelligent construction site management scheme is formed.
According to the construction site conditions, a fixed focus or integrated network camera is installed at the position of an important area, an important entrance, an important room and the like in a selected position, the construction site is monitored and covered in a full-range dead angle-free mode to the maximum extent, the site information is captured in real time, the site conditions are transmitted in real time, monitoring management personnel can know the site environment, personnel dynamics and operation conditions at the first time, the occurring site conditions can be replayed and inquired according to the conditions for verification or analysis, and the real-time safety management and precaution of people, objects and sites are achieved.
According to the monitoring requirements of the operation site, a high-definition suitcase type emergency monitoring terminal and a high-definition distribution control ball can be configured, the whole process video recording function of the engineering site is mainly provided, evidence obtaining exposure is carried out on violation operation, and the classical standard flow is stored so as to promote and study.
The construction site real-time monitoring mainly depends on a wireless video acquisition terminal (mobile equipment such as a high-definition camera and a mobile phone terminal), a narrow-band Internet of things protocol (NB-IOT), a Beidou/GPS satellite positioning system, a multimedia information retransmission system and a 5G/4G wireless broadband technology, and can effectively conduct remote command, data uploading, video and picture uploading and other work.
The construction site real-time condition is that video and photo data shot by the camera are stored in the hard disk video recorder through the high-definition camera or the camera on the intelligent helmet worn by constructors on site, the hard disk video recorder can also be connected with the wireless router, and then the data are transmitted to the construction site management platform in real time by using 5G, so that project managers can monitor the construction site in real time through the platform, and meanwhile, the operation of the constructors on the construction site is remotely commanded.
The method comprises the steps of obtaining position information of a built line part in a construction process by using an RFID, a narrow-band Internet of things protocol (NB-IOT) and a Beidou satellite positioning technology, forming a position trend of the built line part on a map, and applying the result to safety, progress and quality management of a construction site.
Description of the drawings:
FIG. 1 is a schematic diagram of the system of the present invention.
Fig. 2 is a schematic structural diagram of a video monitoring unit according to the present invention.
Fig. 3 is a schematic structural diagram of an approach management unit according to the present invention.
Fig. 4 is a schematic structural diagram of the tower positioning unit of the present invention.
FIG. 5 is a diagram illustrating a structure of a comparison database according to the present invention.
The specific implementation mode is as follows:
the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b):
as shown in fig. 1 to 5, the power distribution network construction site visual management system includes a video monitoring unit, an approach management unit, an abnormality reminding unit, a tower positioning unit, a data wireless transmission unit, a comparison database, a report generation unit, a data import unit, an operation terminal, a real-time display unit, and a central processing unit; the video monitoring unit, the entrance management unit, the abnormity reminding unit and the tower positioning unit are connected with the data wireless transmission unit in a wireless communication mode; the data wireless transmission unit, the comparison database, the report generation unit, the data import unit and the real-time display unit are connected with the central processing unit, and the data wireless transmission unit is connected with the central processing unit in an Internet/private network mode.
The video monitoring unit is used for acquiring video information of a construction site and comprises a fixed high-definition monitoring camera and a movable monitoring camera arranged on a safety helmet; the video monitoring unit is connected with the data wireless transmission unit through a 5G wireless communication module.
The entrance management unit is used for identifying the identity information of personnel entering and exiting a construction site, and comprises a fingerprint authentication module, a face authentication module, an iris authentication module and an RFID authentication module; the entrance management unit is connected with the data wireless transmission unit through a 5G wireless communication module.
The abnormity reminding unit is used for reminding and alarming abnormal data, and comprises an optical alarm device and an acoustic alarm device, wherein the optical alarm device and the acoustic alarm device are used for providing an optical alarm and an acoustic alarm; the abnormity prompting unit is connected with the data wireless transmission unit through a 5G wireless communication module.
The tower positioning unit is used for transmitting tower position information in real time; the tower positioning unit comprises an RFID module, a Beidou/GPS positioning module, a narrow-band Internet of things protocol communication module and an encryption transmission module; the abnormity prompting unit is connected with the data wireless transmission unit through the narrow-band Internet of things protocol communication module.
The comparison database comprises a data storage module, a data updating module and a data transmission module, wherein the data storage module is used for storing all data sent by the central processing unit, the data updating module is used for updating relevant indexes of a power distribution network construction site, and the data transmission module is used for realizing bidirectional transmission between the central processing unit and the comparison database.
The report generation unit is connected with a report printing unit, the report generation unit is used for generating collected data, analyzed data and predicted data, and the report printing unit is used for printing out all the data generated in the report generation unit.
The data import unit is used for importing construction progress, operation tasks, operation time periods, participating personnel, the number and the types of operation equipment, and is a PC (personal computer) end or a mobile terminal.
The real-time display unit is used for displaying monitored data and analyzed data in real time, and the real-time display unit displays the monitored data and the analyzed data through a television wall, a PC (personal computer) end or a mobile terminal.
The invention comprises the following monitoring management contents:
first, basic information management
1. Master data management
The contrast database provides a project main data management function, project basic information management is achieved, project construction task allocation is conducted in the contrast database, a participating unit and a project task are hooked, specific participating personnel are determined, the participating personnel are matched with the project, longitudinal chain management of the project to be built, the participating unit and the participating personnel is achieved, the allocation condition of each project personnel is clearly shown through a platform and serves as the basis of visual monitoring of a construction site.
2. Qualification management
Qualification management of participating units
The database is compared with information of each participating unit such as a construction unit, a supervision unit, a construction unit and the like, and the information comprises information such as a unit name, a business license, a qualification certificate, a contact, a main business direction and the like.
3. Personnel qualification management
The method comprises the steps of comparing the names, identification numbers, affiliated units, titles, work categories, personal certificates, personal work histories, safety training, examination conditions and the like of the participating units such as the construction units, the supervision units, the construction units and the like, acquiring face information of project personnel by adopting a face recognition technology and storing the face information into a power distribution network project construction site management system, wherein relevant leaders and project management departments can use mobile terminals to call and read detailed information of the project personnel at any time according to dimensions of the participating units, the work categories, the project projects and the like.
Second, monitoring and managing construction site
1. Personnel monitoring management
After the face information of the project personnel is input, the video monitoring unit is used for dynamically monitoring personnel in the construction site in real time, authorized project personnel can work in the corresponding construction site, otherwise, the abnormal reminding unit gives an alarm, the key area can be planned in advance, if the key area invades in an illegal way, the alarm can be given immediately, the alarm information is automatically sent to designated personnel, and the manager is reminded to timely process the early warning condition.
2. Patrol monitoring management
The system can be used for carrying out inspection monitoring on the construction task at the same day, capturing violation pictures and recording videos through the system and uploading the violation pictures and the videos to the data storage module for storage, and carrying out statistical management on the problems found in the task.
The position and the action track of the personnel on the construction site can be acquired at any time and any place, the condition that the personnel on the site arrive at the post can be conveniently mastered, and when the site personnel deviate from the track, the relevant managers can be actively reminded to handle the situation.
3. Real-time monitoring management
The construction site is provided with the fixed high-definition monitoring cameras, managers can check the conditions of the construction site in real time through the fixed high-definition monitoring cameras, carry out real-time recording and snapshot on violation behaviors of regulations in the construction site and store the violation behaviors in the data storage module, can remind and urge related responsible personnel to deal with hidden trouble conditions in time on line, and then check the rectification and modification conditions through the fixed high-definition monitoring cameras to form first-time problem finding, first-time rectification and modification problems and first-time rectification and modification condition closed-loop management, so that the visual supervision of the hidden trouble problems in the construction site is realized.
Third, construction map management
1. Construction process line path management
Before a project is not built, after line design is completed, line trend information can be automatically identified through a map, the line trend is marked on the map, in the line building stage, automatic positioning of a tower is achieved through an RFID technology, tower position information is uploaded and automatically marked on the map through a narrow-band Internet of things protocol (NB-IOT) during tower construction, and a rear-end manager can see the line design trend and the actual line trend in the building process in a real-time display unit or a data importing unit.
The tower positioning unit arranged on the tower has the advantages of ultra-low power consumption performance, accurate positioning, periodic reporting of position information and ultra-high power consumption control performance, and can completely meet the requirement of accurate positioning of the tower on a construction site.
2. Job site project display management
The position coordinates of construction sites of each project are automatically displayed on the map, and by clicking the site positions, the project construction progress condition, the number of people on site construction, the attendance condition of constructors, the log reporting condition and various field inspection rectification conditions can be checked for the main line of the venation.
Fourthly, construction progress management
1. Progress management
1.1, the data import unit adopts a PC (personal computer) terminal or a mobile terminal to complete project progress reporting, project management personnel can use the data import unit to report construction plan progress and actual construction progress at any time, the reporting content comprises progress data and construction site work result videos and pictures, and the progress report is summarized and reported after being approved by relevant leaders. Leaders and project personnel can check detailed information of each project progress in real time in the authority range, meanwhile, construction photos, videos, detailed information of related personnel, project basic data and the like of the project can be inquired, and the real situation of a construction site is tightly combined with the project progress.
For line engineering, the real-time display unit can check the length of an actual construction line in real time, judge the actual progress of the engineering, transversely compare the actual progress of the engineering with an engineering progress plan, monitor whether the actual progress of the construction meets the requirements of the progress plan, monitor whether a construction unit performs construction privately under the condition that a project management department is not informed, solve the problem that the project management department is difficult to accurately master the pain point of the actual construction progress of the engineering for a long time, and strictly monitor the construction unit to perform construction work according to the progress requirements.
According to standard milestone nodes and network plans, the functions of intelligent flow management, intelligent supervision, delayed early warning and reminding and the like of the whole process management of a construction site are realized, and the supervision burden of managers is reduced while the smooth implementation of a progress plan is ensured.
1.2 Log management
The log is the most original recording evidence in the project construction process, the actual situation of a construction site can be reflected most truly, the project log management requirement is formulated to meet the fine management and control requirement of the construction site management, the log classification management is realized, and the reporting situations of various logs are identified intelligently, such as meeting before (after) recording, construction log, supervision log and the like, so that a log analysis report is formed, and the supplement situation after the log is strictly controlled is realized; and generating a log through a report generating unit.
Fifth, construction safety management
The fixed high-definition monitoring camera is used for monitoring the construction site in real time, risk identification such as wearing of the safety helmet, rail setting, foundation pit risk and cavity covering is achieved through the fixed high-definition monitoring camera, risks are found through recording, designated personnel are informed to handle related risks in time, meanwhile, regulation and modification notices are generated for violation behaviors, related responsible persons are sent, and project personnel can inquire safety inspection problems and safety regulation and modification conditions at any time. Various safety problems of intelligence multidimension degree analysis and rectification condition if: safety management overall statistics, project safety problem rectification rate, rectification cycle and the like.
For line engineering, the real-time display unit can check the length of an actual construction line in real time, the actual progress of the engineering is judged, whether the construction is carried out is monitored, whether project construction work is carried out on the premise that various safety regulations are met or not is monitored, whether construction units carry out construction privately or not under the conditions that various safety checks are not carried out and safety approval procedures are lacked or not is carried out, and construction potential safety hazards are effectively prevented.
Sixthly, construction quality management
The construction is carried out according to the construction standard process requirement, the construction site picture is uploaded to the management platform through the mobile terminal, the construction standard process and the actual construction picture are compared through the platform, the site construction condition is mastered in real time, the management work of the hidden project is particularly facilitated, the actual condition of the hidden project is remotely monitored before the hidden project is completed, and meanwhile, a constructor is required to upload a video or a photo of the hidden project.
For line engineering, whether the line trend is consistent with the actual construction line trend or not and whether the line trend is changed or not can be checked in real time through the real-time display unit, and whether the line trend is changed or not is monitored, so that the quality risk caused by that a construction unit arbitrarily changes the line trend is greatly reduced, and the pain point that a project management department cannot accurately master the construction change condition for a long time is solved.
Seventh, management of construction materials
The high-definition monitoring camera is fixed on the construction site to realize real-time dynamic monitoring of materials on the construction site, store the materials monitoring video data on the construction site and facilitate the manager to review the materials video monitoring data on the construction site.
Eighthly, project personnel management
1. Project personnel attendance management
The attendance of personnel is automatically recorded by the entrance management unit, an attendance report is automatically generated according to time periods, personal attendance records can be inquired and exported according to names, card numbers and job numbers, the attendance records of groups can also be inquired and exported through dimensions such as job types, units, departments and the like, and the attendance rate and the attendance number can be visually checked in a chart mode.
2. Project personnel health management
The method comprises the steps of establishing a project personnel health file, uploading a constructor physical examination report data participating in project construction to a system in an electronic version, monitoring environmental sanitation of a life site of constructors, construction labor protection measures, prevention and publicity of occupational diseases, training conditions of occupational health and the like through construction site high-definition camera equipment, remotely shooting illegal operations through a camera, remotely monitoring the constructors through the camera after rectification, or uploading videos, pictures and the like after rectification by the constructors, really forming real-time monitoring, timely rectification and effective feedback closed-loop management of the health of the constructors in the construction site, and effectively guaranteeing the health of the constructors in the construction site.
Ninthly, construction site management decision
Through the report generation unit, classified statistics of violation events and comprehensive analysis weak links of various statistical charts such as report support column diagrams, pie diagrams and broken line diagrams is achieved, risk assessment is given, monitoring reports are generated, management efficiency is improved in an auxiliary mode, construction task completion conditions, violation operation warning/correcting conditions, system operation conditions and the like are brought into assessment indexes, and comprehensive management capacity of the management and control platform is improved.

Claims (9)

1. The visual management system for the power distribution network construction site is characterized by comprising a video monitoring unit, an entrance management unit, an abnormality reminding unit, a tower positioning unit, a data wireless transmission unit, a comparison database, a report generation unit, a data import unit, a real-time display unit and a central processing unit; the video monitoring unit, the entrance management unit, the abnormity reminding unit and the tower positioning unit are connected with the data wireless transmission unit; the data wireless transmission unit, the comparison database, the report generation unit, the data import unit, the operation terminal and the real-time display unit are connected with the central processing unit.
2. The visual management system for the power distribution network construction site as claimed in claim 1, wherein the video monitoring unit is used for video information acquisition of a construction site, and comprises a fixed high-definition monitoring camera and a mobile monitoring camera mounted on a safety helmet; the video monitoring unit is connected with the data wireless transmission unit through a 5G wireless communication module.
3. The visual management system for the power distribution network construction site as claimed in claim 1, wherein the approach management unit is used for identifying identity information of personnel entering and exiting the construction site, and comprises a fingerprint authentication module, a face authentication module, an iris authentication module and an RFID authentication module; the entrance management unit is connected with the data wireless transmission unit through a 5G wireless communication module.
4. The visual management system for the power distribution network construction site as claimed in claim 1, wherein the abnormality reminding unit is configured to remind and alarm abnormal data, and the abnormality reminding unit includes an optical alarm device and an acoustic alarm device, and the optical alarm device and the acoustic alarm device are configured to provide an optical alarm and an acoustic alarm; the abnormity prompting unit is connected with the data wireless transmission unit through a 5G wireless communication module.
5. The visual management system for the power distribution network construction site according to claim 1, wherein the tower positioning unit is used for transmitting tower position information in real time; the tower positioning unit comprises an RFID module, a Beidou/GPS positioning module, a narrow-band Internet of things protocol communication module and an encryption transmission module; the abnormity prompting unit is connected with the data wireless transmission unit through the narrow-band Internet of things protocol communication module.
6. The power distribution network construction site visualization management system according to claim 1, wherein the comparison database comprises a data storage module, a data updating module and a data transmission module, the data storage module is used for storing all data sent by the central processing unit, the data updating module is used for updating relevant indexes of the power distribution network construction site, and the data transmission module is used for realizing bidirectional transmission between the central processing unit and the comparison database.
7. The power distribution network construction site visualization management system according to claim 1, wherein the report generation unit is connected to a report printing unit, the report generation unit is configured to generate the collected data, the analyzed data, and the predicted data, and the report printing unit is configured to print out all the data generated in the report generation unit.
8. The visual management system for the power distribution network construction site as claimed in claim 1, wherein the data import unit is used for importing construction progress, operation tasks, operation time periods, personnel involved in construction, and the number and types of operation equipment.
9. The visual management system for power distribution network construction sites according to claim 1, wherein the real-time display unit is used for displaying monitored data and analyzed data in real time.
CN202010653016.8A 2020-07-08 2020-07-08 Visual management system for power distribution network construction site Pending CN111768123A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010653016.8A CN111768123A (en) 2020-07-08 2020-07-08 Visual management system for power distribution network construction site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010653016.8A CN111768123A (en) 2020-07-08 2020-07-08 Visual management system for power distribution network construction site

Publications (1)

Publication Number Publication Date
CN111768123A true CN111768123A (en) 2020-10-13

Family

ID=72726079

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010653016.8A Pending CN111768123A (en) 2020-07-08 2020-07-08 Visual management system for power distribution network construction site

Country Status (1)

Country Link
CN (1) CN111768123A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112433537A (en) * 2020-11-11 2021-03-02 广西电网有限责任公司电力科学研究院 Visual monitoring method and system for power transmission line iron tower erection construction
CN112446690A (en) * 2020-12-15 2021-03-05 湖北省水利水电规划勘测设计院 Hydraulic engineering building-up modularized management system and method
CN112990784A (en) * 2021-05-07 2021-06-18 中铁一局集团有限公司 Engineering management system based on Internet of things
CN113570233A (en) * 2021-07-22 2021-10-29 吕福瑞 Construction organization management system based on 5G technology
CN113591577A (en) * 2021-06-30 2021-11-02 安徽省国维通信工程有限责任公司 Artificial intelligence video image detecting system in communication engineering
CN113625673A (en) * 2021-08-17 2021-11-09 国网宁夏电力有限公司 Dynamic scheduling method, device and system for power safety inspection personnel and storage device
CN113762926A (en) * 2021-09-07 2021-12-07 广东电网有限责任公司 Intelligent monitoring system and intelligent monitoring method
CN116432937A (en) * 2023-01-12 2023-07-14 汉唐融科(北京)科技有限公司 Flexible recruitment settlement management system
CN116681409A (en) * 2023-08-03 2023-09-01 吉林建筑大学 Urban space layout information management system based on big data

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112433537A (en) * 2020-11-11 2021-03-02 广西电网有限责任公司电力科学研究院 Visual monitoring method and system for power transmission line iron tower erection construction
CN112433537B (en) * 2020-11-11 2022-09-16 广西电网有限责任公司电力科学研究院 Visual monitoring method and system for power transmission line iron tower erection construction
CN112446690A (en) * 2020-12-15 2021-03-05 湖北省水利水电规划勘测设计院 Hydraulic engineering building-up modularized management system and method
CN112990784A (en) * 2021-05-07 2021-06-18 中铁一局集团有限公司 Engineering management system based on Internet of things
CN113591577A (en) * 2021-06-30 2021-11-02 安徽省国维通信工程有限责任公司 Artificial intelligence video image detecting system in communication engineering
CN113570233A (en) * 2021-07-22 2021-10-29 吕福瑞 Construction organization management system based on 5G technology
CN113625673A (en) * 2021-08-17 2021-11-09 国网宁夏电力有限公司 Dynamic scheduling method, device and system for power safety inspection personnel and storage device
CN113762926A (en) * 2021-09-07 2021-12-07 广东电网有限责任公司 Intelligent monitoring system and intelligent monitoring method
CN113762926B (en) * 2021-09-07 2023-10-31 广东电网有限责任公司 Intelligent supervision system and intelligent supervision method
CN116432937A (en) * 2023-01-12 2023-07-14 汉唐融科(北京)科技有限公司 Flexible recruitment settlement management system
CN116681409A (en) * 2023-08-03 2023-09-01 吉林建筑大学 Urban space layout information management system based on big data

Similar Documents

Publication Publication Date Title
CN111768123A (en) Visual management system for power distribution network construction site
CN110971878B (en) Engineering field management system
CN107665419B (en) Labor service real-name management system of intelligent building site management and control platform of national power grid
CN111598734A (en) Intelligent building site integrated management system of BIM and Internet of things
CN110287859A (en) A kind of personnel's material dispatching system based on artificial intelligence technology
CN110888402A (en) Intelligent building site environment comprehensive monitoring system based on SAAS platform
CN209543518U (en) The device that a kind of pair of river illegal sand mining behavior is monitored automatically
CN113177768A (en) Intelligent engineering platform based on comprehensive digital management of capital construction whole process
CN113902237A (en) On-site operation risk management and control system
CN107180312A (en) A kind of capital construction operation intelligent safety monitoring method and system
CN209402635U (en) A kind of monitoring of transformer substation video and intelligent analysis system
CN111770315A (en) Intelligent building site video online monitoring system
CN114548656B (en) Safe emergency management commanding and dispatching system
CN111126217A (en) Intelligent operation and maintenance management system for power transmission line based on intelligent identification
CN111861799A (en) Intelligent construction site management system and method
CN110430246A (en) Capital construction security management and control system
CN112819374A (en) System and method for risk management of railway bridge constructors
CN107693997B (en) Fire fighting equipment detection and maintenance management system and management method
CN114399265A (en) Electric power engineering construction project overall process management and control system
CN107730212A (en) A kind of project under construction personnel long-distance real-time management system
CN114648307A (en) Project progress real-time feedback system based on wisdom building site platform
CN207070219U (en) Projects supervision system based on video monitoring
CN116882670A (en) Intelligent building site management system for water transport engineering based on BIM
CN207571805U (en) A kind of Campus Security ensures intelligent supervision early warning system
CN116168337A (en) System for intelligent image recognition of unworn violations of safety helmet on electric power construction site

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination