CN111749272A - Method for treating permeable water leakage back water surface system of underground pipe gallery - Google Patents

Method for treating permeable water leakage back water surface system of underground pipe gallery Download PDF

Info

Publication number
CN111749272A
CN111749272A CN202010500037.6A CN202010500037A CN111749272A CN 111749272 A CN111749272 A CN 111749272A CN 202010500037 A CN202010500037 A CN 202010500037A CN 111749272 A CN111749272 A CN 111749272A
Authority
CN
China
Prior art keywords
pipe gallery
underground pipe
stratum
water leakage
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010500037.6A
Other languages
Chinese (zh)
Inventor
吴挺鹏
刘向东
阳作亮
成军
黄兴
苟仕川
钟久安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Hetuo Civil Engineering Co ltd
Original Assignee
Chengdu Hetuo Civil Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Hetuo Civil Engineering Co ltd filed Critical Chengdu Hetuo Civil Engineering Co ltd
Priority to CN202010500037.6A priority Critical patent/CN111749272A/en
Publication of CN111749272A publication Critical patent/CN111749272A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The invention relates to a method for treating a system on the back surface of an underground pipe gallery after water leakage; underground pipe gallery (2) are because stratum (1) differential settlement leads to misplacing between multisection underground pipe gallery (2) to form the crack, get slip casting hole (3) through boring on the wall of underground pipe gallery (2), pour into the thick liquid in slip casting hole (3), after the thick liquid solidifies connect underground pipe gallery (2) and stratum (1) of the peripheral certain limit of pipe gallery as a whole, reach and improve stratum (1) of the peripheral certain limit of pipe gallery and be the homogeneous stratum, and then weaken the differential settlement. And meanwhile, the permeable channels in the stratum (1) and the pipe gallery (2) can be sealed, and the channel for water in the stratum (1) to permeate into the pipe gallery (2) is cut off. The invention blocks the water seepage channel in the stratum (1) by the slurry, thus solving the water seepage problem from the source; and the underground pipe gallery (2) can not be cracked again in a short time.

Description

Method for treating permeable water leakage back water surface system of underground pipe gallery
Technical Field
The invention relates to the technical field of underground pipe gallery water seepage construction, in particular to a treatment method for a backwater surface system for underground pipe gallery water seepage.
Background
The underground pipe gallery is also called as an underground city pipeline comprehensive corridor, namely a tunnel space is built underground in a city, various functional pipelines such as electric power, communication, gas, heat supply, water supply and drainage and the like are integrated, a special overhaul port, a special hoisting port and a special detection system are arranged, unified planning, unified construction and management are implemented, and the underground pipe gallery is an important infrastructure and a life line for city operation. The underground pipe gallery contains various pipelines and needs to provide a passing road for maintenance personnel. Because the underground pipe gallery is built in sections, after the underground pipe gallery is built, the settlement speeds of the underground pipe galleries are different due to different materials of foundations, different compositions below the foundations or different stresses above the pipe galleries, so that the joints of the underground pipe galleries are staggered to generate cracks; because the piping lane is located the underground, during the water infiltration that exists in the stratum reached crack department and flowed into the underground pipe gallery from the crack, the damage of piping lane interior conduit was caused easily in the piping lane infiltration to hinder maintenance personal's the current, the infiltration caused the incident more easily at the power line pipeline part. The existing maintenance method aiming at the water seepage of the underground pipe gallery is to expand the crack at the crack, cut the crack flat by a cutting tool and fill the crack by concrete so as to achieve the purpose of preventing the water seepage. However, the method cannot solve the problem of inconsistent settlement speed of the underground pipe gallery, and the newly repaired crack is a weak part and can be stretched and cracked again under the continuous settlement of the underground pipe gallery. The prior art is therefore not able to serve the purpose of preventing water penetration for a long time.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a treatment method for underground pipe gallery water seepage.
The purpose of the invention is realized by the following technical scheme: a method for treating a backwater surface system of an underground pipe gallery after water leakage seepage comprises the following steps:
s1, measuring the length of the sinking section of the underground pipe gallery, and determining a sinking area; the regional process that sinks that detects promptly underground pipe gallery is whole sinks for the region, sinks one section that the speed is faster for the rest of underground pipe gallery, sinks fastly and geology is more loose, exists rivers in the stratum more easily.
S2, drilling holes, namely drilling a plurality of grouting holes on the water leakage surface of the underground pipe gallery; the depth of the plurality of grouting holes requires drilling into the stratum connected with the back water surface of the underground pipe gallery.
S3, grouting, namely grouting slurry into the grouting holes to fill the gap on the back surface side of the underground pipe gallery with the slurry; the surface of a back of the body of underground pipe gallery is for being close to one side of stratum, after the thick liquid is injected, the thick liquid fills up the space of injected hole and surface of a back of the body one side, after the thick liquid solidifies, then will be with the sunken stratum connection of different speeds as a whole, make to have the effort between the stratum, through the mutual containment between the stratum, slow down the sunken relative velocity difference between the stratum, even the underground pipe gallery sinks under this condition, also sink as a whole, make the underground pipe gallery can not appear the dislocation in the short time, lead to the crack to enlarge or the crack of having repaired splits once more. And the injected slurry will simultaneously block the passage of the water flow, fundamentally preventing the infiltration of water into the formation.
S4, expanding the seam, and cutting and flattening the seam at the water leakage position by a cutting tool; the cut and leveled cracks are convenient for filling concrete, and the weak points of the cracks can be cut off by cutting the cracks, so that the newly filled concrete is stably supported.
S5, filling the crack, grouting in the cut and leveled crack, filling the space and the water seepage channel in the crack with the poured grout, completely blocking the water seepage channel at the crack after the grout is solidified, preventing the water seepage even if the crack cracks again, and then plugging the crack with concrete.
Preferably, the plurality of grouting holes are drilled in the direction of the trend of the underground pipe gallery.
Preferably, grouting holes are drilled in the underground pipe gallery wall surface of the sinking area. The wider the slurry is diffused after the whole grouting, the larger the connection range between the stratums is, the larger the interaction force between the stratums is after the slurry is solidified, and the more stable the whole stratum is.
Preferably, the underground pipe gallery wall surface comprises the wall surfaces of the left side, the right side and the upper side of the underground pipe gallery. Fill and repair the underground pipe gallery that sinks the region all-roundly, it is that all stratum around the underground pipe gallery link as an organic whole through the thick liquid, reduce the stratum and sink the speed difference, avoid underground pipe gallery's dislocation.
The invention has the following advantages:
1. the problem of water seepage is solved from the source by plugging a water seepage channel in the stratum by slurry;
2. after the poured slurry is solidified, the whole stratum is connected into a whole, so that the sinking speed of the whole stratum around the underground pipe gallery is consistent, and the repaired crack can not be cracked again in a short period even if the sinking speeds are inconsistent.
Drawings
FIG. 1 is a schematic view of an underground pipe gallery;
FIG. 2 is a schematic view of a grouting hole drilled in the present invention;
in the figure: 1-stratum, 2-underground pipe gallery and 3-grouting hole.
Detailed Description
The invention will be further described with reference to the accompanying drawings, but the scope of the invention is not limited to the following.
As shown in fig. 1, a method for treating a seepage and water leakage backing surface system of an underground pipe gallery comprises the following steps:
s1, measuring the length of the sinking section of the underground pipe gallery 2, and determining a sinking area; the regional process that sinks that detects is underground pipe gallery 2 whole sinks for the region promptly, sinks one section that speed is faster for 2 rest parts of underground pipe gallery, sinks fastly and geology is more loose promptly, has rivers in the stratum 1 more easily.
S2, drilling holes, namely drilling a plurality of grouting holes 3 on the water leakage surface of the underground pipe gallery 2; the depth of the plurality of grouting holes 3 requires drilling into the ground layer 1 connected with the back surface of the underground pipe gallery 2.
S3, grouting, namely grouting slurry into the grouting holes 3 to fill the gap on the back side of the underground pipe gallery 2; the surface of a poor water of underground pipe gallery 2 is for being close to one side of stratum 1, after the thick liquid is injected, the thick liquid is filled up the space of injected hole 3 and surface of a poor water one side, after the thick liquid solidifies, then will be connected as a whole with the sunken stratum 1 of different speeds, make to have the effort between the stratum 1, through the mutual containment between the stratum 1, slow down the sunken relative velocity difference between the stratum 1, even underground pipe gallery 2 sinks under this condition, also sink as a whole, make underground pipe gallery 2 can not appear the dislocation in the short time, lead to the crack to enlarge or the crack of having repaired splits once more. And the injected slurry will simultaneously block the passage of water, fundamentally preventing the infiltration of water into the formation 1.
S4, expanding the seam, and cutting and flattening the seam at the water leakage position by a cutting tool; the cut and leveled cracks are convenient for filling concrete, and the weak points of the cracks can be cut off by cutting the cracks, so that the newly filled concrete is stably supported.
S5, filling the crack, grouting in the cut and leveled crack, filling the space and the water seepage channel in the crack with the poured grout, completely blocking the water seepage channel at the crack after the grout is solidified, preventing the water seepage even if the crack cracks again, and then plugging the crack with concrete.
Preferably, the plurality of grouting holes 3 are drilled in the direction in which the underground pipe gallery 2 runs. Multiple rows of grouting holes 3 may be drilled, each row of grouting holes 3 being arranged equidistantly.
Preferably, grouting holes 3 are drilled in the wall surface of the underground pipe gallery 2 in the sinking area. The wider the slurry is spread after the whole grouting, the larger the connection range between the stratums 1 is, the larger the interaction force between the stratums 1 is after the slurry is solidified, and the more stable the whole stratum 1 is.
Preferably, 2 wall surfaces of underground pipe gallery include the wall surfaces of both sides and top about 2 underground pipe gallery. Fill and repair in all-round to the underground pipe gallery 2 of the region that sinks, be that all stratum 1 around underground pipe gallery 2 link as an organic whole through the thick liquid, reduce stratum 1 and sink the speed difference, avoid underground pipe gallery 2's dislocation.

Claims (5)

1. A treatment method for a backwater surface system for underground pipe gallery water leakage is characterized by comprising the following steps: the method comprises the following steps:
s1, measuring the length of the sinking section of the underground pipe gallery (2) and determining a sinking area;
s2, drilling holes, namely drilling a plurality of grouting holes (3) on the water leakage surface of the underground pipe gallery (2);
s3, grouting, namely grouting slurry into the grouting holes (3) to fill the gap on the back water surface side of the underground pipe gallery (2) with the slurry;
s4, expanding the seam, and cutting and flattening the seam at the water leakage position;
and S5, repairing the gap, grouting in the cut and leveled gap, and then plugging the gap by using concrete.
2. The method for treating the seepage water leakage backwater surface system of the underground pipe gallery according to claim 1, wherein the method comprises the following steps: the depth of the plurality of grouting holes (3) requires drilling into the stratum (1) connected with the back water surface of the underground pipe gallery (2).
3. The method for treating the seepage water leakage backwater surface system of the underground pipe gallery according to claim 1, wherein the method comprises the following steps: and drilling the plurality of grouting holes (3) along the direction of the trend of the underground pipe gallery (2).
4. The method for treating the seepage water leakage backwater surface system of the underground pipe gallery according to claim 1, wherein the method comprises the following steps: grouting holes (3) are drilled on the wall surface of the underground pipe gallery (2) in the sinking area.
5. The method for treating the seepage water leakage backwater surface system of the underground pipe gallery according to claim 4, wherein the method comprises the following steps: underground pipe gallery (2) wall includes the wall of underground pipe gallery (2) left and right sides and top.
CN202010500037.6A 2020-06-04 2020-06-04 Method for treating permeable water leakage back water surface system of underground pipe gallery Withdrawn CN111749272A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010500037.6A CN111749272A (en) 2020-06-04 2020-06-04 Method for treating permeable water leakage back water surface system of underground pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010500037.6A CN111749272A (en) 2020-06-04 2020-06-04 Method for treating permeable water leakage back water surface system of underground pipe gallery

Publications (1)

Publication Number Publication Date
CN111749272A true CN111749272A (en) 2020-10-09

Family

ID=72674593

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010500037.6A Withdrawn CN111749272A (en) 2020-06-04 2020-06-04 Method for treating permeable water leakage back water surface system of underground pipe gallery

Country Status (1)

Country Link
CN (1) CN111749272A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112411632A (en) * 2020-11-16 2021-02-26 吉士达建设集团有限公司 Pipe gallery seepage repairing process
CN112705533A (en) * 2021-01-25 2021-04-27 成都和拓土木工程有限公司 Blind pipe dredging and detecting integrated equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112411632A (en) * 2020-11-16 2021-02-26 吉士达建设集团有限公司 Pipe gallery seepage repairing process
CN112705533A (en) * 2021-01-25 2021-04-27 成都和拓土木工程有限公司 Blind pipe dredging and detecting integrated equipment

Similar Documents

Publication Publication Date Title
CN108060908B (en) Long-distance horizontal directional drilling and grouting reinforcement process for water-rich sand layer under building group
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN107217691A (en) For city underground leak stopping and the method for strengthening construction
CN109653777B (en) High-speed railway open cut tunnel water leakage and crack regional integral treatment method
CN105804758A (en) Shallow-earthing, large-section and small-distance construction method for rectangular pipe jacking overpass subway tunnel
LU501539B1 (en) Pumping and drainage method for foundation pit bottom plate construction of deep foundation pit and pumping and drainage structure
CN102425421B (en) Novel water control method suitable for mine shafts
CN104963334A (en) Construction method for utilizing grouting freezing pipe to reinforce and freeze contact passage to restrain frost heaving and thaw collapsing
CN106640154A (en) Treatment method and structure for water seepage of tunnel lining circular construction joint crack
CN111749272A (en) Method for treating permeable water leakage back water surface system of underground pipe gallery
CN106351312A (en) Pipeline and construction method thereof
CN110130936A (en) It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN109184754A (en) A kind of tunnel water handling Disease Processing method and system
CN111395263B (en) Leakage treatment method for roller compacted concrete dam body
CN107191188B (en) Bedrock section bad aquifer positioning and targeting grouting vertical shaft wall structure, construction device and construction method
CN104594379B (en) Between rail yard interior lines, be incubated culvert pipe system and burial and construction method
CN114109442B (en) Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method
WO2022188436A1 (en) Earth surface deep grouting process
CN103437779B (en) The construction method of regulation tunnel lining pore gas flow
CN104033165A (en) Repairing method and grout for tunnel defects
CN206157860U (en) Drainage pipeline
CN103669347B (en) Underwater anchor rod construction method
CN112482415B (en) Consolidation grouting method for underground cavern under high external water pressure and flowing water condition
CN107975376A (en) Tunneling shield push pipe and vertical duct connection structure and construction method
CN103866787A (en) Process for constructing impervious concrete wall by using open excavation and inverted construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20201009