CN111705793A - A kind of artificial digging pile prefabricated retaining wall construction method - Google Patents
A kind of artificial digging pile prefabricated retaining wall construction method Download PDFInfo
- Publication number
- CN111705793A CN111705793A CN202010467659.3A CN202010467659A CN111705793A CN 111705793 A CN111705793 A CN 111705793A CN 202010467659 A CN202010467659 A CN 202010467659A CN 111705793 A CN111705793 A CN 111705793A
- Authority
- CN
- China
- Prior art keywords
- section
- pile
- retaining wall
- wall
- prefabricated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 24
- 239000004568 cement Substances 0.000 claims abstract description 13
- 239000002002 slurry Substances 0.000 claims abstract description 12
- 230000002787 reinforcement Effects 0.000 claims abstract description 4
- 239000002689 soil Substances 0.000 claims description 17
- 238000000034 method Methods 0.000 claims description 13
- HEMHJVSKTPXQMS-UHFFFAOYSA-M Sodium hydroxide Chemical compound [OH-].[Na+] HEMHJVSKTPXQMS-UHFFFAOYSA-M 0.000 claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 7
- 239000010959 steel Substances 0.000 claims description 7
- 239000002893 slag Substances 0.000 claims description 6
- 238000004806 packaging method and process Methods 0.000 claims description 5
- 239000000203 mixture Substances 0.000 claims description 4
- 239000010881 fly ash Substances 0.000 claims description 3
- 235000019353 potassium silicate Nutrition 0.000 claims description 3
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 3
- 238000005538 encapsulation Methods 0.000 abstract description 5
- 230000001681 protective effect Effects 0.000 description 32
- 238000009412 basement excavation Methods 0.000 description 6
- 239000011435 rock Substances 0.000 description 6
- 238000009417 prefabrication Methods 0.000 description 5
- 229920003041 geopolymer cement Polymers 0.000 description 4
- 239000011413 geopolymer cement Substances 0.000 description 4
- 239000007799 cork Substances 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 230000006872 improvement Effects 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 230000009471 action Effects 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 2
- 239000002440 industrial waste Substances 0.000 description 2
- 239000002910 solid waste Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
- E02D5/68—Mould-pipes or other moulds for making bulkheads or elements thereof
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本发明适用孔桩护壁施工技术领域,提供了一种人工挖孔桩预制护壁施工方法,依次在预制工厂预制护壁段的各预制件,预制件包括有标准块、邻接块和封装块,2~4个所述标准块、2个邻接块和1个封装块合围形成一个护壁圈,多个护壁圈的沿轴向堆叠形成一个护壁段,每一个所述护壁段内相邻的所述护壁圈通过螺栓固定连接,沿预设计桩孔的高度方向向下开挖桩孔,每挖到深度为预设深度的一个桩孔段时,在该桩孔段内支设一个护壁段,并在第一个护壁段支设完成后注入水泥浆,直到完成预设计桩孔深度的护壁支设,最后吊装钢筋笼,浇筑桩身混凝土,本发明采用预制管片,能实现护壁快速支设,地层适应性广,管片厚度和灵活调节,安全性更高。
The invention is applicable to the technical field of hole pile protection wall construction, and provides a construction method for artificially digging a hole pile prefabricated protection wall. 4 of the standard blocks, 2 adjacent blocks and 1 encapsulation block are enclosed to form a retaining wall, a plurality of retaining rings are stacked in the axial direction to form a retaining wall segment, and the adjacent retaining walls in each said retaining wall segment Through the bolted connection, the pile holes are excavated downward along the height direction of the pre-designed pile holes. When a pile hole section with a preset depth is dug, a retaining wall section is supported in the pile hole section, and a retaining wall section is set up in the pile hole section. After the support of a retaining wall section is completed, the cement slurry is injected until the retaining wall supporting of the pre-designed pile hole depth is completed, and finally the reinforcement cage is hoisted, and the pile body concrete is poured. Wide range of properties, segment thickness and flexible adjustment, higher safety.
Description
技术领域technical field
本发明属于孔桩护壁施工技术领域,尤其涉及一种人工挖孔桩预制护壁施工方法。The invention belongs to the technical field of hole pile protection wall construction, and in particular relates to a construction method of artificial hole pile prefabricated protection wall.
背景技术Background technique
目前,大直径桩普遍采用人工挖孔方法施工,该法施工一般流程是每往下挖1-1.5m,支设模板浇筑护壁混凝土,待护壁混凝土达到一定强度后,再进行下一步开挖,如此循环,只到设计桩长位置,然后吊装钢筋笼和浇筑混凝土。At present, large-diameter piles are generally constructed by manual digging. The general construction process of this method is to dig down 1-1.5m, and set up formwork to pour the retaining wall concrete. After the retaining wall concrete reaches a certain strength, the next step is excavated. In this cycle, only to the design pile length position, and then hoist the steel cage and pour concrete.
上述方法存在如下问题:(1)每往下挖一段,都要浇筑护壁混凝土,待护壁混凝土达到一定强度后才能继续下挖,无法连续开挖,影响工效;(2)受浇筑护壁影响,这种方法施工的桩身直径一般上大下小,浪费桩身混凝土,无法充分发挥桩底好土层的承载力;(3)在软土地层或遇水地层,无法快速护壁,容易塌孔,造成施工事故,轻则影响工期,提高造价,重则导致人员伤亡。The above method has the following problems: (1) Every time a section is dug down, the retaining wall concrete must be poured. After the retaining wall concrete reaches a certain strength, the digging can continue, and the continuous excavation cannot be carried out, which affects the work efficiency; (2) Affected by the pouring of the retaining wall, this The diameter of the pile body constructed by this method is generally large in the upper part and small in the lower part, which wastes the concrete of the pile body and cannot give full play to the bearing capacity of the good soil layer at the bottom of the pile; (3) In the soft soil layer or the stratum in contact with water, the wall cannot be quickly protected, and the hole is easy to collapse. Cause construction accidents, ranging from affecting the construction period, increasing the cost, and causing casualties.
发明内容SUMMARY OF THE INVENTION
本发明提供一种人工挖孔桩预制护壁施工方法,旨在解决现有技术存在的问题。The invention provides a construction method for artificially digging a hole pile prefabricated protective wall, aiming at solving the problems existing in the prior art.
本发明是这样实现的,一种人工挖孔桩预制护壁施工方法,包括以下步骤:The present invention is achieved in this way, a construction method for artificially digging a hole pile prefabricated retaining wall, comprising the following steps:
S1、在预制工厂预制护壁段的各预制件,预制件包括有标准块、邻接块和封装块,2~4个所述标准块、2个邻接块和1个封装块合围形成一个护壁圈,多个护壁圈的沿轴向堆叠形成一个护壁段,每一个所述护壁段内相邻的所述护壁圈通过螺栓连接,每一个护壁圈内的周向相邻的预制件之间通过螺栓连接并且设置有橡胶止水条;S1. The prefabricated parts of the retaining wall section are prefabricated in the prefabrication factory. The prefabricated parts include standard blocks, adjacent blocks and packaging blocks. 2 to 4 of the standard blocks, 2 adjacent blocks and 1 packaging block are enclosed to form a retaining wall. A plurality of retaining wall rings are stacked in the axial direction to form a retaining wall segment, the adjacent retaining wall rings in each retaining wall segment are connected by bolts, and the circumferentially adjacent prefabricated parts in each retaining wall ring are connected and arranged by bolts There is a rubber water stop;
S2、沿预设计桩孔的高度方向向下开挖桩孔,每挖到深度为预设深度的一个桩孔段时,在该桩孔段内支设一个护壁段,并在第一个护壁段支设完成后注入水泥浆以增加护壁段外壁与周边岩土体的摩擦力,直到完成预设计桩孔深度的护壁支设;S2. Excavate the pile hole downward along the height direction of the pre-designed pile hole. When a pile hole section with a preset depth is dug, a retaining wall section is supported in the pile hole section, and a retaining wall section is installed in the first retaining wall section. After the section support is completed, inject cement slurry to increase the friction between the outer wall of the retaining wall section and the surrounding rock and soil mass, until the retaining wall supporting of the pre-designed pile hole depth is completed;
S3、吊装钢筋笼,浇筑桩身混凝土。S3. Hoist the steel cage and pour concrete for the pile body.
优选的,步骤S2中,在支设位于一个护壁段下方的相邻的一个护壁段时,采用千斤顶将位于下方的护壁段顶升,并利用螺栓连接相邻的两个护壁段。Preferably, in step S2, when supporting an adjacent protective wall section below a protective wall section, a jack is used to lift the protective wall section below, and two adjacent protective wall sections are connected by bolts.
优选的,所述预制件的表面采用拉毛处理。Preferably, the surface of the preform is brushed.
优选的,所述水泥浆为粉煤灰、矿渣、钢渣或尾矿、NaOH溶液、水玻璃的混合物。Preferably, the cement slurry is a mixture of fly ash, slag, steel slag or tailings, NaOH solution and water glass.
与现有技术相比,本发明的有益效果是:本发明的一种人工挖孔桩预制护壁施工方法,依次在预制工厂预制护壁段的各预制件,沿预设计桩孔的高度方向向下开挖桩孔,每挖到深度为预设深度的一个桩孔段时,在该桩孔段内支设一个护壁段,并在第一个护壁段支设完成后注入水泥浆以增加护壁段外壁与周边岩土体的摩擦力,直到完成预设计桩孔深度的护壁支设,最后吊装钢筋笼,浇筑桩身混凝土,本发明采用预制管片方法,能实现护壁快速支设,节省工期。Compared with the prior art, the beneficial effects of the present invention are as follows: in the present invention, a method for constructing a prefabricated retaining wall of an artificial hole-digging pile of the present invention sequentially prefabricates the prefabricated parts of the retaining wall section in a prefabrication factory, and then downwards along the height direction of the pre-designed pile holes. Excavation of pile holes, every time a pile hole section with a preset depth is dug, a retaining wall section is supported in the pile hole section, and after the first retaining wall section is supported, cement slurry is injected to increase the retaining wall section The friction force between the outer wall and the surrounding rock and soil mass, until the supporting wall of the pre-designed pile hole depth is completed, and finally the reinforcement cage is hoisted, and the pile body concrete is poured.
附图说明Description of drawings
图1为本发明的护壁的整体结构示意图。FIG. 1 is a schematic diagram of the overall structure of the protective wall of the present invention.
图2为本发明的护壁的俯视图。Fig. 2 is a top view of the retaining wall of the present invention.
图3为本发明的标准块的剖视图。3 is a cross-sectional view of the standard block of the present invention.
图4为图3中的A处细节放大示意图FIG. 4 is an enlarged schematic view of the details of the A part in FIG. 3
图中:1-标准块、11-注浆孔、12-橡胶止水条、13-软木衬垫、2-邻接块、3-封装块。In the picture: 1-standard block, 11-grouting hole, 12-rubber waterstop, 13-cork liner, 2-adjacent block, 3-packaging block.
具体实施方式Detailed ways
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, but not to limit the present invention.
实施例一Example 1
请参阅图1-4,本实施例提供一种技术方案:一种人工挖孔桩预制护壁施工方法,包括以下步骤:Referring to Figures 1-4, this embodiment provides a technical solution: a method for constructing a prefabricated retaining wall for artificially digging piles, comprising the following steps:
S1、在预制工厂预制护壁段的各预制件。请参阅图1-2,预制件包括有标准块1、邻接块2和封装块3,2~4个标准块1、2个邻接2块和1个封装块3合围形成一个护壁圈,多个护壁圈的沿轴向堆叠形成一个护壁段,每一个护壁段内相邻的护壁圈通过螺栓固定连接,即上下两个相邻的护壁圈抵接的一面通过螺栓连接固定。每一个护壁圈内的周向相邻的预制件之间通过螺栓连接并且设置有橡胶止水条12。所有标准块1、邻接块2、封装块3均为作为管片,相邻的管片的环向和纵向均采用弯曲螺栓连接,并且可以根据需要设置防水结构,防水结构为设置在相邻管片间隙处的橡胶止水条12和软木衬垫13。护壁的直径为1.5m。管片的厚度为30cm。S1. Prefabricate each prefabricated part of the retaining wall section in a prefabrication factory. Please refer to Figure 1-2, the prefab includes a
预制管片可采用普通混凝土、防水混凝土或再生混凝土制作。管片内外面拉毛处理,以增加外壁和周边岩土体的摩擦力和内壁与后浇桩身混凝土的粘结。管片预留注浆孔11,通过注浆增加外壁与周边岩土体的摩擦力,既实现施工过程中支设好的每段预制护壁的自稳能力,又能提升施工完成后的桩侧摩阻力,可以增加单桩承载力。Prefabricated segments can be made of ordinary concrete, waterproof concrete or recycled concrete. The inner and outer surfaces of the segment are roughened to increase the friction between the outer wall and the surrounding rock and soil mass and the bonding between the inner wall and the post-cast pile concrete. Grouting
S2、沿预设计桩孔的高度方向向下开挖桩孔,每挖到深度为预设深度的一个桩孔段时,在该桩孔段内支设一个护壁段,并在第一个护壁段支设完成后注入水泥浆,直到完成预设计桩孔深度的护壁支设。在支设位于一个护壁段下方的相邻的一个护壁段时,采用千斤顶将位于下方的护壁段顶升,并利用螺栓连接相邻的两个护壁段。S2. Excavate the pile hole downward along the height direction of the pre-designed pile hole. When a pile hole section with a preset depth is dug, a retaining wall section is supported in the pile hole section, and a retaining wall section is installed in the first retaining wall section. After the section support is completed, the cement slurry is injected until the retaining wall support of the pre-designed pile hole depth is completed. When supporting an adjacent protective wall section below a protective wall section, a jack is used to lift the protective wall section located below, and bolts are used to connect two adjacent protective wall sections.
具体为:首先开挖第一段桩孔段,然后完成第一段预制护壁段的支设,固定护壁段的底端,然后进行壁后注浆,接着进行下一代开挖,同时提升注浆强度,护壁与周边土体的摩擦力能后支撑其自重。拆除第一段护壁底端固定,进行第二段预制护壁支设,并通过第二段底端设置千斤顶顶升第二段护壁上升,将第二段护壁顶端与第一段护壁底端通过预留螺栓孔螺栓连接,然后保留第二段千斤顶顶升的状态,先开挖第三段核心土体,第三段核心开挖完成,第二段壁后注浆强度上升,在第二段护壁与周边土体摩擦力作用以及第一段护壁吊设作用下,此时第一段护壁周边注浆强度进一步提升,护壁与周边土体摩擦力进一步提升,撤出第二段底端千斤顶,完成第三段桩体开挖,进行第三段护壁支设,如此持续,直至护壁施工到设计的桩底深度。Specifically: first excavate the first section of the pile hole section, then complete the support of the first section of the prefabricated retaining wall section, fix the bottom end of the retaining wall section, then carry out post-wall grouting, and then carry out the next generation of excavation, and at the same time lift the grouting Strength, the friction between the retaining wall and the surrounding soil can support its own weight. The bottom end of the first section of the protective wall is removed, and the second section of the prefabricated protective wall is supported, and the second section of protective wall is lifted by the jack at the bottom of the second section, and the top of the second section of protective wall and the bottom of the first section of protective wall are passed through the Leave the bolt holes for bolt connection, and then retain the state of the second section of the jack, first excavate the third section of the core soil, the third section of the core excavation is completed, the grouting strength increases after the second section of the wall, in the second section of the protective wall Under the action of friction with the surrounding soil and the hoisting of the first section of the protective wall, the grouting strength around the first section of protective wall is further improved, and the friction between the protective wall and the surrounding soil is further improved, and the bottom jack of the second section is withdrawn to complete. The third section of pile body is excavated, and the third section of retaining wall is supported, and this continues until the retaining wall is constructed to the designed depth of the pile bottom.
S3、最后吊装钢筋笼,浇筑桩身混凝土,完成人挖桩施工。S3. Finally, the steel cage is hoisted, the concrete of the pile body is poured, and the construction of the man-made pile is completed.
其中,注浆用的水泥浆可采用具有速凝性能的地聚物水泥,在本实施方式中,水泥浆为粉煤灰、矿渣、钢渣的混合物,实现固废资源化利用。地聚物水泥具有速凝效果,有利于早日形成强度,提升施工速度;二是工业废弃物资源化利用,节能环保且经济。Among them, the cement slurry used for grouting can use geopolymer cement with quick-setting properties. In this embodiment, the cement slurry is a mixture of fly ash, slag, and steel slag, so as to realize the resource utilization of solid waste. Geopolymer cement has a quick-setting effect, which is conducive to early formation of strength and improvement of construction speed; the second is the resource utilization of industrial waste, which is energy-saving, environmentally friendly and economical.
本发明的一种人工挖孔桩预制护壁施工方法,依次在预制工厂预制护壁段的各预制件,沿预设计桩孔的高度方向向下开挖桩孔,每挖到深度为预设深度的一个桩孔段时,在该桩孔段内支设一个护壁段,并在第一个护壁段支设完成后注入水泥浆,直到完成预设计桩孔深度的护壁支设,最后吊装钢筋笼,浇筑桩身混凝土,本发明采用预制管片方法,能实现护壁快速支设,节省工期,地层适应性广,橡胶止水条的防水效果好,管片厚度在预制时可以根据施工要求灵活调节,安全性更高。The present invention provides a method for constructing a prefabricated retaining wall of an artificial hole-digging pile. The prefabricated parts of the retaining wall section are sequentially prefabricated in a prefabricated factory, and the pile holes are excavated downward along the height direction of the pre-designed pile holes. When a pile hole section is used, a retaining wall section is supported in the pile hole section, and cement slurry is injected after the first retaining wall section is supported until the retaining wall supporting of the pre-designed pile hole depth is completed, and finally the reinforcement cage is hoisted. When pouring the concrete of the pile body, the present invention adopts the prefabricated segment method, which can realize the rapid support of the retaining wall, save the construction period, wide adaptability of the stratum, good waterproof effect of the rubber waterstop, and the thickness of the segment can be flexibly adjusted according to the construction requirements during prefabrication. Higher security.
实施例二
本实施例提供一种技术方案:一种人工挖孔桩预制护壁施工方法,包括以下步骤:The present embodiment provides a technical solution: a method for constructing a prefabricated retaining wall of artificial digging piles, comprising the following steps:
S1、在预制工厂预制护壁段的各预制件。预制件包括有标准块1、邻接块2和封装块3,2~4个标准块1、2个邻接2块和1个封装块3合围形成一个护壁圈,多个护壁圈的沿轴向堆叠形成一个护壁段,每一个护壁段内相邻的护壁圈通过螺栓固定连接,即上下两个相邻的护壁圈抵接的一面通过螺栓连接固定。每一个护壁圈内的周向相邻的预制件之间通过螺栓连接并且设置有橡胶止水条12。所有标准块1、邻接块2、封装块3均为作为管片,相邻的管片的环向和纵向均采用弯曲螺栓连接,并且可以根据需要设置防水结构,防水结构为设置在相邻管片间隙处的橡胶止水条12和软木衬垫13。护壁的直径为1m。管片的厚度为40cm。S1. Prefabricate each prefabricated part of the retaining wall section in a prefabrication factory. The prefab includes a
预制管片可采用普通混凝土、防水混凝土或再生混凝土制作。管片内外面拉毛处理,以增加外壁和周边岩土体的摩擦力和内壁与后浇桩身混凝土的粘结。管片预留注浆孔11,通过注浆增加外壁与周边岩土体的摩擦力,既实现施工过程中支设好的每段预制护壁的自稳能力,又能提升施工完成后的桩侧摩阻力,可以增加单桩承载力。Prefabricated segments can be made of ordinary concrete, waterproof concrete or recycled concrete. The inner and outer surfaces of the segment are roughened to increase the friction between the outer wall and the surrounding rock and soil mass and the bonding between the inner wall and the post-cast pile concrete. Grouting holes 11 are reserved for the segment, and the friction between the outer wall and the surrounding rock and soil mass can be increased by grouting, which not only realizes the self-stabilizing ability of each prefabricated retaining wall supported during the construction process, but also improves the pile side after the construction is completed. The friction resistance can increase the bearing capacity of the single pile.
S2、沿预设计桩孔的高度方向向下开挖桩孔,每挖到深度为预设深度的一个桩孔段时,在该桩孔段内支设一个护壁段,并在第一个护壁段支设完成后注入水泥浆,直到完成预设计桩孔深度的护壁支设。在支设位于一个护壁段下方的相邻的一个护壁段时,采用千斤顶将位于下方的护壁段顶升,并利用螺栓连接相邻的两个护壁段。S2. Excavate the pile hole downward along the height direction of the pre-designed pile hole. When a pile hole section with a preset depth is dug, a retaining wall section is supported in the pile hole section, and a retaining wall section is installed in the first retaining wall section. After the section support is completed, the cement slurry is injected until the retaining wall support of the pre-designed pile hole depth is completed. When supporting an adjacent protective wall section below a protective wall section, a jack is used to lift the protective wall section located below, and bolts are used to connect two adjacent protective wall sections.
具体为:首先开挖第一段桩孔段,然后完成第一段预制护壁段的支设,固定护壁段的底端,然后进行壁后注浆,接着进行下一代开挖,同时提升注浆强度,护壁与周边土体的摩擦力能后支撑其自重。拆除第一段护壁底端固定,进行第二段预制护壁支设,并通过第二段底端设置千斤顶顶升第二段护壁上升,将第二段护壁顶端与第一段护壁底端通过预留螺栓孔螺栓连接,然后保留第二段千斤顶顶升的状态,先开挖第三段核心土体,第三段核心开挖完成,第二段壁后注浆强度上升,在第二段护壁与周边土体摩擦力作用以及第一段护壁吊设作用下,此时第一段护壁周边注浆强度进一步提升,护壁与周边土体摩擦力进一步提升,撤出第二段底端千斤顶,完成第三段桩体开挖,进行第三段护壁支设,如此持续,直至护壁施工到设计的桩底深度。Specifically: first excavate the first section of the pile hole section, then complete the support of the first section of the prefabricated retaining wall section, fix the bottom end of the retaining wall section, then carry out post-wall grouting, and then carry out the next generation of excavation, and at the same time lift the grouting Strength, the friction between the retaining wall and the surrounding soil can support its own weight. The bottom end of the first section of the protective wall is removed, and the second section of the prefabricated protective wall is supported, and the second section of protective wall is lifted by the jack at the bottom of the second section, and the top of the second section of protective wall and the bottom of the first section of protective wall are passed through the Leave the bolt holes for bolt connection, and then retain the state of the second section of the jack, first excavate the third section of the core soil, the third section of the core excavation is completed, the grouting strength increases after the second section of the wall, in the second section of the protective wall Under the action of friction with the surrounding soil and the hoisting of the first section of the protective wall, the grouting strength around the first section of protective wall is further improved, and the friction between the protective wall and the surrounding soil is further improved, and the bottom jack of the second section is withdrawn to complete. The third section of pile body is excavated, and the third section of retaining wall is supported, and this continues until the retaining wall is constructed to the designed depth of the pile bottom.
S3、最后吊装钢筋笼,浇筑桩身混凝土,完成人挖桩施工。S3. Finally, the steel cage is hoisted, the concrete of the pile body is poured, and the construction of the man-made pile is completed.
其中,注浆用的水泥浆可采用具有速凝性能的地聚物水泥,在本实施方式中,水泥浆为尾矿、NaOH溶液、水玻璃的混合物,实现固废资源化利用。地聚物水泥具有速凝效果,有利于早日形成强度,提升施工速度;二是工业废弃物资源化利用,节能环保且经济。Among them, the cement slurry used for grouting can use geopolymer cement with quick-setting properties. In this embodiment, the cement slurry is a mixture of tailings, NaOH solution, and water glass, so as to realize the resource utilization of solid waste. Geopolymer cement has a quick-setting effect, which is conducive to early formation of strength and improvement of construction speed; the second is the resource utilization of industrial waste, which is energy-saving, environmentally friendly and economical.
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included in the protection of the present invention. within the range.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010467659.3A CN111705793A (en) | 2020-05-28 | 2020-05-28 | A kind of artificial digging pile prefabricated retaining wall construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010467659.3A CN111705793A (en) | 2020-05-28 | 2020-05-28 | A kind of artificial digging pile prefabricated retaining wall construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111705793A true CN111705793A (en) | 2020-09-25 |
Family
ID=72538510
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010467659.3A Pending CN111705793A (en) | 2020-05-28 | 2020-05-28 | A kind of artificial digging pile prefabricated retaining wall construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111705793A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2387145Y (en) * | 1999-09-02 | 2000-07-12 | 阎慧奎 | Mounting concrete precast dado for hole digging pile |
CN2469046Y (en) * | 2001-04-04 | 2002-01-02 | 陈扬德 | Prefabricated steel bar reinforced concrete bulk head for piles |
JP2017082513A (en) * | 2015-10-29 | 2017-05-18 | 大亜ソイル株式会社 | Cast-in-place concrete pile and construction method thereof |
CN106703028A (en) * | 2016-11-22 | 2017-05-24 | 重庆建工第九建设有限公司 | Large-diameter manual hole digging pile prefabricated assembly type steel guard wall and construction technology thereof |
CN209053021U (en) * | 2018-11-12 | 2019-07-02 | 马鞍山钢铁建设集团有限公司 | A kind of groove and tognue type precast concrete culvert pipe retaining wall and its artificial digging pile |
CN110258550A (en) * | 2019-06-25 | 2019-09-20 | 湘潭大学 | A kind of concrete prefabricated retaining wall of artificial digging pile and construction method |
-
2020
- 2020-05-28 CN CN202010467659.3A patent/CN111705793A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2387145Y (en) * | 1999-09-02 | 2000-07-12 | 阎慧奎 | Mounting concrete precast dado for hole digging pile |
CN2469046Y (en) * | 2001-04-04 | 2002-01-02 | 陈扬德 | Prefabricated steel bar reinforced concrete bulk head for piles |
JP2017082513A (en) * | 2015-10-29 | 2017-05-18 | 大亜ソイル株式会社 | Cast-in-place concrete pile and construction method thereof |
CN106703028A (en) * | 2016-11-22 | 2017-05-24 | 重庆建工第九建设有限公司 | Large-diameter manual hole digging pile prefabricated assembly type steel guard wall and construction technology thereof |
CN209053021U (en) * | 2018-11-12 | 2019-07-02 | 马鞍山钢铁建设集团有限公司 | A kind of groove and tognue type precast concrete culvert pipe retaining wall and its artificial digging pile |
CN110258550A (en) * | 2019-06-25 | 2019-09-20 | 湘潭大学 | A kind of concrete prefabricated retaining wall of artificial digging pile and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104264688B (en) | Manually digging hole non-uniform pile support construction process | |
CN104818728A (en) | Permanent supporting system with basement floor and supporting piles capable of working together | |
CN107642041A (en) | Super large diameter hollow pile group anchorage | |
CN108149696B (en) | Construction method of composite support structure combining temporary support soil nail wall and permanent anti-floating anchor rod | |
CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration | |
CN107642040A (en) | Construction method of super large diameter hollow pile group anchorage | |
CN207484290U (en) | The hollow clump of piles anchorage of super-large diameter | |
CN110485431A (en) | A kind of interlocking pile combines foundation pit supporting construction with ground-connecting-wall | |
CN210562162U (en) | Prefabricated tubular pile crackle prosthetic devices | |
CN209958408U (en) | Underground structure using row piles to resist groundwater buoyancy | |
CN209339156U (en) | The embedding rock foot pilework of anchor tube formula in a kind of Extra-Deep Foundation Pit | |
CN111705793A (en) | A kind of artificial digging pile prefabricated retaining wall construction method | |
CN114108694B (en) | Micro-disturbance anti-floating underground cylindrical structure and construction method thereof | |
CN111305220A (en) | Concrete support and structural top plate combined building system based on permanent and temporary combination and construction method thereof | |
CN114482070B (en) | Construction tool and construction method for temporary high-speed railway line deep foundation pit occluding pile | |
CN217325391U (en) | Construction tool for high-speed rail line deep foundation pit secant pile | |
CN115198759A (en) | Supporting pile and vibration isolation barrier structure, design and construction method | |
CN108547286A (en) | A kind of prefabricated guide groove structure of concrete cut and guide groove installation method | |
CN211285658U (en) | Structure capable of carrying out deep water area hollowing repair in rapid stream state | |
CN110735434B (en) | Method for replacing traditional inner support construction by underground force transmission belt in long and narrow deep foundation pit | |
CN113152446A (en) | Multi-section type prestressed hollow pile and construction method thereof | |
CN111945742A (en) | A unilateral prestressed supporting pile | |
CN106337421A (en) | Lattice concrete composite retaining pile wall and construction method based on BIM | |
CN206173972U (en) | Compound retaining pile wall of lattice formula concrete | |
CN106193744B (en) | The round prefabricated assembled underground granary of equal steel plated inside and outside one kind |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200925 |
|
RJ01 | Rejection of invention patent application after publication |