CN111305220A - Concrete support and structural top plate combined building system based on permanent and temporary combination and construction method thereof - Google Patents

Concrete support and structural top plate combined building system based on permanent and temporary combination and construction method thereof Download PDF

Info

Publication number
CN111305220A
CN111305220A CN202010250536.4A CN202010250536A CN111305220A CN 111305220 A CN111305220 A CN 111305220A CN 202010250536 A CN202010250536 A CN 202010250536A CN 111305220 A CN111305220 A CN 111305220A
Authority
CN
China
Prior art keywords
concrete support
structural
concrete
pile
top plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010250536.4A
Other languages
Chinese (zh)
Other versions
CN111305220B (en
Inventor
戴志仁
廖晖
张庆闯
李谈
喻忠
吕海军
赵亚军
段建锋
许红春
刘彤
张毓斌
查家宏
王维
马琳琳
王文彬
王耀辉
陈新平
孟宪全
黄彦彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN202010250536.4A priority Critical patent/CN111305220B/en
Publication of CN111305220A publication Critical patent/CN111305220A/en
Application granted granted Critical
Publication of CN111305220B publication Critical patent/CN111305220B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Foundations (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to a concrete support and structural roof combined building system based on permanent and temporary combination and a construction method thereof, wherein the system comprises an underground structure, fender piles, waist beams and concrete supports; the fender pile is positioned at the outer side of the periphery of the underground structure, the pile top is positioned above a top plate of the underground structure for a certain distance, and the pile bottom is positioned below a bottom plate of the underground structure for a certain distance; the inner side of the fender post is provided with a waist beam, the concrete support is rigidly connected with the waist beams at two sides, and the concrete support is positioned above the top of the underground structure. The invention relates to a concrete support and structure top plate combined system based on 'permanent temporary combination', wherein a temporary concrete support in a foundation pit is taken as a part of a structure top plate, and the temporary concrete support and the structure top plate jointly bear external loads according to the permanent structure, so that the concrete support is prevented from being chiseled out at the later stage of being taken as a temporary component, the process is simplified, the progress is accelerated, the size of the structure top plate is reduced, the integral stress requirement of the structure is met, a new thought of overall consideration of the temporary concrete support and the permanent structure top plate is provided for the first time, and the long-term durability of the foundation pit safe excavation and the underground structure is met.

Description

基于永临结合的砼支撑与结构顶板合建体系及其构建方法Concrete support and structural roof joint construction system and construction method based on the combination of permanent and permanent

技术领域technical field

本发明属于地下工程技术领域,具体涉及一种基于永临结合的砼支撑与结构顶板合建体系及其构建方法。The invention belongs to the technical field of underground engineering, and in particular relates to a combined construction system of a concrete support and a structural roof based on a permanent combination and a construction method thereof.

背景技术Background technique

对于目前广泛建设的地下工程,基坑工程是各类大埋深、大空间、异型结构等地下建筑首选的空间构筑方式,为了有效应对基坑工程施工对周边环境的不利影响,确保周边构筑物安全,内支撑被广泛采用,主要是考虑到内支撑具有刚度大、抗变形能力强、工艺成熟等特点。当深大或异型基坑紧邻重要构筑物时,砼内支撑通常为首选方案。For underground projects that are widely constructed at present, foundation pit engineering is the preferred space construction method for all kinds of underground buildings with large buried depths, large spaces, and special-shaped structures. , The inner support is widely used, mainly considering that the inner support has the characteristics of high rigidity, strong deformation resistance, and mature technology. When deep or special-shaped foundation pits are close to important structures, concrete inner support is usually the first choice.

常规基坑支护结构设计方案,无论是砼支撑还是钢支撑,都作为临时结构考虑,待基坑开挖至坑底,主体结构回筑阶段,被陆续拆除,但砼支撑由于体量大,被切割的砼块质量大,在切割与吊运过程中存在重大安全隐患,现场施工费时费力。The conventional foundation pit support structure design scheme, whether it is concrete support or steel support, is considered as a temporary structure. After the foundation pit is excavated to the bottom of the pit and the main structure is rebuilt, it will be demolished one after another. However, due to the large volume of the concrete support, The quality of the cut concrete blocks is large, and there are major safety hazards in the process of cutting and lifting, and the on-site construction is time-consuming and labor-intensive.

在深大基坑施工过程中,砼支撑的拆除与吊运已经成为制约工期、影响投资的重要因素之一,砼支撑破除、切割与外运一般发生在主体结构浇筑完成并达到养护龄期后进行,一般是基坑工程即将完工阶段,此时基坑内工序转换与步序衔接要求高,工期压力大,常规砼支撑仅作为临时构件考虑,已经严重制约了绿色、环保理念下地下工程的健康发展。During the construction of deep and large foundation pits, the dismantling and hoisting of concrete supports have become one of the important factors that restrict the construction period and affect the investment. The breaking, cutting and outbound transportation of concrete supports generally occur after the main structure is poured and the maintenance age is reached. Generally, the foundation pit project is about to be completed. At this time, the requirements for process conversion and step connection in the foundation pit are high, and the construction period pressure is large. The conventional concrete support is only considered as a temporary component, which has seriously restricted the health of the underground project under the concept of green and environmental protection. develop.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提供一种基于永临结合的砼支撑与结构顶板合建体系及其构建方法,将砼支撑标高调整至永久结构顶板标高处,砼支撑与结构顶板按叠合结构考虑,在先期浇筑的砼支撑内预埋钢筋接驳器,并在两结构接合部位进行界面处理,通过受力钢筋的机械连接、结构接合部位环氧树脂的黏合,实现砼支撑与后浇结构顶板之间的有效叠合,将砼支撑与地下结构连成一个有机整体,形成整体受力体系,避免砼支撑的拆除与外运,同时有效减少结构顶板构件尺寸,不但节约了工期与投资,更为重要的是避免了大块砼支撑切割与外运期间存在的安全隐患,更好地满足了深大基坑工程安全、绿色、环保的建设理念,同时也更有利于实现周边环境安全目标。The purpose of the present invention is to provide a combined construction system of concrete support and structural roof based on the permanent combination and construction method thereof. The elevation of the concrete support is adjusted to the elevation of the permanent structure roof. Pre-embedded steel bar connectors in the pre-cast concrete support, and interface treatment at the joint of the two structures, through the mechanical connection of the stressed steel bars and the bonding of epoxy resin at the structural joint, the connection between the concrete support and the roof of the post-cast structure is realized. The effective superposition of the concrete support and the underground structure forms an organic whole, forming an overall stress system, avoiding the dismantling and external transportation of the concrete support, and effectively reducing the size of the structural roof components, which not only saves the construction period and investment, but is more important. The main thing is to avoid the hidden safety hazards during the cutting and outbound transportation of large concrete supports, better meet the construction concept of safety, green and environmental protection for deep and large foundation pit projects, and at the same time, it is also more conducive to achieving the safety goals of the surrounding environment.

本发明所采用的技术方案为:The technical scheme adopted in the present invention is:

基于永临结合的砼支撑与结构顶板合建体系,其特征在于:The combined construction system of concrete support and structural roof based on the combination of permanent approach is characterized by:

所述体系包括地下结构、围护桩、腰梁和砼支撑;The system includes underground structures, enclosure piles, waist beams and concrete supports;

围护桩位于地下结构外侧,桩顶高于地下结构顶板,桩底在地下结构底板以下;The enclosure pile is located outside the underground structure, the top of the pile is higher than the roof of the underground structure, and the bottom of the pile is below the bottom plate of the underground structure;

围护桩内侧设置有腰梁,桩顶设置冠梁,砼支撑与腰梁刚性连接、有效传力,砼支撑位于地下结构顶部位置。The inner side of the enclosure pile is provided with a waist beam, and the top of the pile is provided with a crown beam. The concrete support is rigidly connected to the waist beam to effectively transmit force, and the concrete support is located at the top of the underground structure.

地下结构包括结构顶板、结构中板、结构底板、结构侧墙和结构中立柱,围护桩位于地下结构外侧四周,腰梁和砼支撑位于结构顶板上方。The underground structure includes the structural top plate, the structural middle plate, the structural bottom plate, the structural side wall and the structural central column. The enclosure piles are located around the outside of the underground structure, and the waist beam and the concrete support are located above the structural top plate.

围护桩顶部设置有桩顶冠梁,围护桩与冠梁之间通过植筋或预留筋有效连接。The top of the retaining pile is provided with a crown beam at the top of the pile, and the retaining pile and the crown beam are effectively connected by planting reinforcement or reserved reinforcement.

腰梁位于围护桩内侧,通过植筋连接;腰梁内侧预留受力钢筋或预埋钢筋接驳器。The waist beam is located on the inner side of the enclosure pile and is connected by planting bars; the inner side of the waist beam is reserved for stressed steel bars or pre-embedded steel bar connectors.

砼支撑内设置有砼支撑受力筋,砼支撑两端通过砼支撑受力筋与腰梁内侧的预留受力钢筋或预埋钢筋接驳器连接。Concrete support reinforcement bars are arranged in the concrete support, and both ends of the concrete support are connected with the reserved stress reinforcement bars or pre-embedded reinforcement bar connectors on the inner side of the waist beam through the concrete support reinforcement bars.

结构顶板上表面呈规律的齿轮型凹凸构造,砼支撑位于结构顶板上表面,与结构顶板呈凹凸状机械咬合连接;The upper surface of the structural roof is in a regular gear-shaped concave-convex structure, and the concrete support is located on the upper surface of the structural roof, and is mechanically engaged with the structural roof in a concave-convex shape;

砼支撑内设置有横向加强筋,加强筋两端预留钢筋接驳器,砼支撑内加强筋通过钢筋接驳器与结构顶板内对应的钢筋连接。A transverse reinforcing rib is arranged in the concrete support, and steel bar connectors are reserved at both ends of the reinforcing bar.

砼支撑与结构顶板之间接触面凿毛处理,并涂覆有界面剂。The contact surface between the concrete support and the structural roof is chiseled and coated with an interface agent.

地下结构的结构顶板、结构底板和结构侧墙外均设置有防水材料,进行全包防水。The structural top plate, the structural bottom plate and the outside of the structural side walls of the underground structure are all provided with waterproof materials for all-inclusive waterproofing.

结构顶板上方设置回填土,回填土采用分层回填。Backfill is set above the structural roof, and the backfill is backfilled in layers.

基于永临结合的砼支撑与结构顶板合建体系构建方法,其特征在于:The construction method of the joint construction system of the concrete support and the structural roof based on the combination of forever and ever, is characterized by:

包括以下步骤:Include the following steps:

步骤一:基于地下结构轮廓,在基坑轮廓外设置降水井,在基坑开挖前1个月时间进行降水施工;Step 1: Based on the outline of the underground structure, set up a dewatering well outside the outline of the foundation pit, and carry out dewatering construction 1 month before the excavation of the foundation pit;

步骤二:根据围护桩坐标与施工误差进行放样,随后进行围护桩施工,按照钻机就位、成孔、清孔、下钢筋笼、灌注砼、桩顶浮浆清理的顺序开展围护桩施工;Step 2: Stake out according to the coordinates of the enclosure piles and the construction error, and then carry out the construction of the enclosure piles, and carry out the enclosure piles in the order of drilling rig in place, forming holes, clearing holes, lowering the reinforcement cage, pouring concrete, and cleaning the floating slurry on the top of the pile. construction;

步骤三:在围护桩顶部拉槽开挖,施做桩顶冠梁,随后根据随挖随撑的原则进行基坑开挖施工;Step 3: excavate the trench at the top of the enclosure pile, construct the crown beam on the top of the pile, and then carry out the excavation of the foundation pit according to the principle of digging and supporting;

步骤四:在基坑开挖到砼支撑以下0.5m时,及时施做砼腰梁,砼腰梁与围护桩之间通过植筋连接,同时腰梁另一侧预留受力钢筋或预埋钢筋接驳器;Step 4: When the foundation pit is excavated to 0.5m below the concrete support, the concrete waist beam shall be constructed in time, and the concrete waist beam and the enclosure pile shall be connected by planting reinforcement. Buried rebar connector;

步骤五:根据砼支撑布置与截面尺寸,对基坑内土体进行拉槽开挖,随后进行整平,敷设垫层,原位绑扎砼支撑钢筋骨架,布置砼支撑受力筋,设置加强筋,加强筋位置与顶板钢筋对应,并在砼支撑两侧面预留钢筋接驳器;腰梁与砼支撑之间的连接,通过在腰梁上事先预留受力钢筋或预埋钢筋接驳器进行连接;Step 5: According to the arrangement of the concrete support and the size of the section, the soil in the foundation pit is excavated by grooving, then leveling, laying the cushion, tying the steel skeleton of the concrete support in situ, arranging the reinforcing bars of the concrete support, and setting the reinforcing bars. The position of the reinforcing bars corresponds to the reinforcing bars of the roof, and steel bar connectors are reserved on both sides of the concrete support; the connection between the waist beam and the concrete support is carried out by pre-reserving stressed bars or pre-embedded bar connectors on the waist beam. connect;

按要求浇筑砼支撑,并按规定要求进行养护;Concrete supports are poured as required and maintained as required;

步骤六:待砼支撑达到规定养护龄期与设计强度后,基于随挖随撑的原则继续开挖基坑,直至基坑底部,坑底以上0.5m采用人工开挖,随后对坑底及时进行整平、敷设防水层、素砼垫层,绑扎钢筋并浇筑结构底板、结构侧墙与结构中板,主体结构浇筑过程中及时拆除相应位置的内支撑;Step 6: After the concrete support reaches the specified curing age and design strength, continue to excavate the foundation pit based on the principle of digging and supporting until the bottom of the foundation pit. Manual excavation is used for 0.5m above the pit bottom, and then the pit bottom is dug in time. Leveling, laying waterproof layer, plain concrete cushion, binding steel bars and pouring structural bottom plate, structural side wall and structural middle plate, during the pouring process of the main structure, remove the internal support at the corresponding position in time;

步骤七:将结构顶板与砼支撑接触部位的砼支撑表面凿毛处理,随后涂刷2-3遍界面剂,基于砼支撑两侧预留钢筋接驳器,将砼支撑中部设置的加强筋与顶板钢筋进行机械连接,随后按要求浇筑结构顶板;Step 7: Chisel the surface of the concrete support at the contact part between the structural roof and the concrete support, and then apply the interface agent 2-3 times. Based on the steel bar connector reserved on both sides of the concrete support, the reinforcing ribs set in the middle of the concrete support are connected with the concrete support. Roof reinforcement is mechanically connected, and then the structural roof is poured as required;

砼支撑底部与结构底板底面之间的距离不小于300mm;The distance between the bottom of the concrete support and the bottom surface of the structural bottom plate shall not be less than 300mm;

步骤八:在结构顶板上方分层回填土体,回填土密实度不小于93%;Step 8: Backfill the soil in layers above the structural roof, and the density of the backfill is not less than 93%;

步骤九:凿除地表以下3m范围内所有结构,给后期市政管线等地下构筑物预留敷设路径。Step 9: Remove all structures within 3m below the surface, and reserve a laying path for the later underground structures such as municipal pipelines.

本发明具有以下优点:The present invention has the following advantages:

本发明将基坑内砼支撑由临时结构转化为永久结构,与结构顶板叠合处理,形成了永临结合的砼支撑与结构顶板合建工艺。砼支撑、腰梁、围护桩以及地下结构涉及的砼为常规防水砼,各类钢筋与钢筋接驳器为普通Q235钢材,地下结构外侧敷设的防水材料为常规防水卷材与防水涂料,砼支撑与结构顶板之间的界面剂为常规环氧树脂,其相应尺寸为常规类型,便于加工制造;砼支撑内预埋接驳器的直径与长度,可根据结构顶板受力主筋位置与整体受力要求综合确定,受力主筋采用螺纹钢筋,与接驳器之间采用丝扣连接。砼支撑底部至结构顶板底部之间的距离一般不小300mm,满足结构顶板受力与耐久性要求的前提下,可灵活调整。工艺简单、概念清晰、施工简便,具有较高的经济效益和社会效益,在城市轨道交通、铁路、公路等矿山法隧道工程中有广泛的应用前景。The invention transforms the concrete support in the foundation pit from a temporary structure into a permanent structure, and superimposes it with the structural roof to form a permanent combined construction process of the concrete support and the structural roof. The concrete involved in the concrete support, waist beam, enclosure pile and the underground structure is conventional waterproof concrete, all kinds of steel bars and steel bar connectors are ordinary Q235 steel, and the waterproof materials laid on the outside of the underground structure are conventional waterproof membranes and waterproof coatings. The interface agent between the support and the structural roof is a conventional epoxy resin, and its corresponding size is a conventional type, which is convenient for processing and manufacturing; the diameter and length of the pre-embedded connector in the concrete support can be determined according to the position of the main reinforcement of the structural roof and the overall load. The force requirements are comprehensively determined. The main force-bearing reinforcement is made of threaded steel bars, and the connection with the connector is made of thread. The distance between the bottom of the concrete support and the bottom of the structural roof is generally not less than 300mm, which can be flexibly adjusted under the premise of meeting the requirements of the structural roof’s stress and durability. The technology is simple, the concept is clear, the construction is simple, and it has high economic and social benefits.

附图说明Description of drawings

图1为砼支撑与结构顶板叠合布置平面图。Figure 1 is a plan view of the superimposed arrangement of the concrete support and the structural roof.

图2为地下结构横断面图。Figure 2 is a cross-sectional view of the underground structure.

图3为地下结构纵断面图。Figure 3 is a longitudinal sectional view of the underground structure.

图4为砼支撑与结构顶板连接大样图。Figure 4 is a large sample view of the connection between the concrete support and the structural roof.

图中,1-围护桩,2-桩顶冠梁,3-砼支撑,4-地下结构,5-结构顶板,6-回填土,7-砼支撑受力筋,8-加强筋,9-钢筋接驳器,10-界面剂,11-顶板钢筋,12-腰梁。In the figure, 1-enclosure pile, 2-pillar crown beam, 3-concrete support, 4-underground structure, 5-structure roof, 6-backfill, 7-concrete support reinforcement, 8-reinforcing bar, 9 - Rebar connector, 10- Interface agent, 11- Roof reinforcement, 12- Waist beam.

具体实施方式Detailed ways

下面结合具体实施方式对本发明进行详细的说明。The present invention will be described in detail below with reference to specific embodiments.

本发明涉及基于永临结合的砼支撑与结构顶板合建体系,提出了现有深基坑工程内支撑作为永久结构的设计思路,丰富了深基坑支护体系功能。The present invention relates to a combined construction system of concrete support and structural roof based on the combination of permanent and imposing conditions, proposes a design idea of internal support as a permanent structure in the existing deep foundation pit engineering, and enriches the functions of the deep foundation pit support system.

所述体系包括地下结构4、围护桩1、腰梁12和砼支撑3。围护桩1位于地下结构4四周外侧,桩顶位于地下结构4顶板以上一定距离,桩底为于地下结构4底板以下一定距离;围护桩1内侧设有腰梁12,砼支撑3与两侧腰梁12刚性连接、有效传力,砼支撑3位于地下结构4顶板位置。The system includes an underground structure 4 , an enclosure pile 1 , a waist beam 12 and a concrete support 3 . The enclosure pile 1 is located on the outer side of the underground structure 4, the top of the pile is located at a certain distance above the top plate of the underground structure 4, and the pile bottom is a certain distance below the bottom plate of the underground structure 4; The side waist beams 12 are rigidly connected and effectively transmit force, and the concrete support 3 is located at the position of the top plate of the underground structure 4 .

地下结构4包括结构顶板5、结构中板、结构底板、结构侧墙和结构中立柱,围护桩1位于结构侧墙外侧,腰梁12和砼支撑3位于结构顶板5上方。The underground structure 4 includes a structural top plate 5, a structural middle plate, a structural bottom plate, a structural side wall and a structural center column.

围护桩1顶部设置有桩顶冠梁2,围护桩1与桩顶冠梁2通过植筋连接。The top of the enclosure pile 1 is provided with a pile top crown beam 2, and the enclosure pile 1 and the pile top crown beam 2 are connected by planting bars.

腰梁12位于围护桩1内侧,通过植筋或围护桩1内预留受力钢筋连接;腰梁12内侧预留受力钢筋或预埋钢筋接驳器,用于与砼支撑3的连接。砼支撑3内设置有纵向的砼支撑受力筋7,砼支撑3两端通过砼支撑受力筋7与腰梁12内侧的预留受力钢筋或预埋钢筋接驳器连接。砼支撑受力筋7根据结构受力需要可设置一排或多排。The waist beam 12 is located on the inner side of the enclosure pile 1, and is connected by planting bars or reserved stress steel bars in the enclosure pile 1; connect. The concrete support 3 is provided with longitudinal concrete support reinforcement bars 7, and both ends of the concrete support 3 are connected with the reserved stress reinforcement bars or embedded reinforcement connectors on the inner side of the waist beam 12 through the concrete support reinforcement reinforcement bars 7. One or more rows of concrete supporting tendons 7 can be arranged according to the structural stress requirements.

砼支撑3嵌入地下结构4的结构顶板5顶面。砼支撑3内设置有横向的加强筋8,加强筋8两端设置有钢筋接驳器9,砼支撑3内的加强筋8通过钢筋接驳器9与结构顶板5内对应的顶板钢筋11连接。砼支撑3底部与结构底板5之间的距离不小于300mm,满足顶板钢筋11穿越与传力要求。砼支撑3与结构顶板5之间的结构接触面提前进行凿毛处理,并涂覆界面剂10两至三遍。砼支撑3在基坑开挖到相应标高时施做,后期与结构顶板5按叠合构件考虑、共同承载,并作为永久地下结构4的一部分。The concrete support 3 is embedded in the top surface of the structural roof 5 of the underground structure 4 . A transverse reinforcing rib 8 is arranged in the concrete support 3, and steel bar connectors 9 are arranged at both ends of the reinforcing bar 8. The reinforcing bar 8 in the concrete support 3 is connected with the corresponding roof steel bar 11 in the structural roof 5 through the steel bar connector 9. . The distance between the bottom of the concrete support 3 and the structural bottom plate 5 is not less than 300mm, which meets the requirements for the penetration and force transmission of the reinforcement bars 11 of the roof. The structural contact surface between the concrete support 3 and the structural roof 5 is chiseled in advance, and the interface agent 10 is coated two to three times. The concrete support 3 is constructed when the foundation pit is excavated to the corresponding elevation, and is considered as a superimposed member with the structural roof 5 in the later stage, and is jointly carried as a part of the permanent underground structure 4 .

结构顶板5上表面呈规律的齿轮型凹凸构造,砼支撑3位于结构顶板5上表面,与结构顶板5呈凹凸状机械咬合连接The upper surface of the structural top plate 5 has a regular gear-shaped concave-convex structure, and the concrete support 3 is located on the upper surface of the structural top plate 5, and is mechanically engaged with the structural top plate 5 in a concave-convex shape.

砼支撑3数量需要根据整体构件的受力与耐久性要求,以及基坑开挖期间的稳定性与周边环境保护要求综合确定,一般情况下砼支撑3沿地下结构4纵向间距≥6m。The number of concrete supports 3 needs to be comprehensively determined according to the force and durability requirements of the overall member, as well as the stability during foundation pit excavation and the requirements for surrounding environmental protection. Generally, the longitudinal spacing of concrete supports 3 along the underground structure 4 is ≥6m.

地下结构4的结构顶板5、结构底板和结构侧墙外均设置有防水材料,实现全包防水。结构侧墙与底板外侧防水材料可用预铺反粘防水卷材,结构顶板5外侧防水材料可用防水涂料。The structural top plate 5 , the structural bottom plate and the outside of the structural side walls of the underground structure 4 are all provided with waterproof materials, so as to realize all-inclusive waterproofing. The waterproof material on the outside of the structural side walls and the bottom plate can be pre-laid with anti-stick waterproofing membrane, and the waterproof material on the outside of the structural top plate 5 can be made of waterproof paint.

结构顶板5上方设置回填土6,分层压实,密实度需满足地面交通需求,一般情况下压实度不小于93%。The backfill 6 is set above the structural roof 5, and the compaction is layered.

围护桩1、砼支撑3、地下结构4、桩顶冠梁2与腰梁12涉及的砼为普通防水砼,涉及的钢筋均可采用Q235钢材。The concrete involved in the enclosure pile 1, the concrete support 3, the underground structure 4, the pile top crown beam 2 and the waist beam 12 is ordinary waterproof concrete, and the steel bars involved can be made of Q235 steel.

如图1-4所示,地下结构4一般由包含结构顶板5、砼支撑3在内的现浇钢筋砼结构组成,结构顶板5与砼支撑3的构件尺寸、砼支撑3底部与结构顶板5之间的竖向距离、砼支撑3内部加强筋8的数量与钢筋型号,均可根据构件连接与永久结构受力要求综合确定,砼支撑3沿地下结构4纵向的数量与分布间距,除了要根据永久结构顶板5合建构件的受力与耐久性进行综合考虑,还需要根据基坑开挖期间的稳定性与周边环境保护要求综合确定,一般情况下砼支撑3的纵向间间距≥6m。As shown in Figures 1-4, the underground structure 4 is generally composed of a cast-in-place reinforced concrete structure including the structural roof 5 and the concrete support 3. The dimensions of the structural roof 5 and the concrete support 3, the bottom of the concrete support 3 and the structural roof 5 The vertical distance between them, the number of reinforcing bars 8 inside the concrete supports 3 and the type of reinforcing bars can be comprehensively determined according to the connection of components and the stress requirements of the permanent structure. According to the comprehensive consideration of the force and durability of the composite members of the permanent structure roof 5, it also needs to be comprehensively determined according to the stability during the excavation of the foundation pit and the surrounding environmental protection requirements. Generally, the longitudinal spacing between the concrete supports 3 is ≥6m.

所有钢筋砼构件涉及的砼均为普通防水砼,钢筋与接驳器均为Q235钢材,砼支撑与结构顶板之间的界面剂可采用环氧树脂。The concrete involved in all reinforced concrete components is ordinary waterproof concrete, the steel bars and connectors are Q235 steel, and the interface agent between the concrete support and the structural roof can be epoxy resin.

本发明将基坑内临时砼支撑作为结构顶板的一部分,按永久结构考虑共同承担外部荷载,一方面避免了砼支撑作为临时构件需要凿除,简化了工艺、加快了进度、节省了投资,一方面减少了结构顶板尺寸,满足结构整体受力要求,首次提出了将临时砼支撑与永久结构统筹考虑的新思路,实现“永临结合”的砼支撑设计初衷。“基于永临结合的砼支撑与结构顶板合建工艺”的设计理念,对现有深大基坑内支撑体系设计是一个极大的提升,为践行绿色、环保、安全的地下工程提供了全新的思路,同时施工工艺简单、概念清晰、施工简便,为实现地下节能工程提供了全新思路。The invention takes the temporary concrete support in the foundation pit as a part of the structural roof, and considers the permanent structure to jointly bear the external load. On the one hand, the concrete support needs to be removed as a temporary member, which simplifies the process, speeds up the progress, and saves the investment. The size of the roof of the structure is reduced to meet the overall stress requirements of the structure. For the first time, a new idea of considering the temporary concrete support and the permanent structure is put forward, and the original intention of the concrete support design of "permanent combination" is realized. The design concept of "concrete support and structural roof co-construction technology based on the combination of forever and ever" is a great improvement to the design of the support system in the existing deep and large foundation pit, and provides a brand-new foundation for the practice of green, environmentally friendly and safe underground engineering. At the same time, the construction process is simple, the concept is clear, and the construction is simple, which provides a new idea for the realization of underground energy-saving projects.

永临结合的砼支撑与结构顶板合建工艺方法,包括以下步骤:The co-construction process method of the concrete support and the structural roof combined with Yonglin includes the following steps:

步骤一:基于地下结构4轮廓,在基坑轮廓外设置降水井,在基坑开挖前1个月时间进行降水施工;Step 1: Based on the outline of the underground structure 4, set up a dewatering well outside the outline of the foundation pit, and carry out dewatering construction 1 month before the excavation of the foundation pit;

步骤二:根据围护桩1坐标与施工误差进行放样,随后进行围护桩1施工,按照钻机就位、成孔、清孔、下钢筋笼、灌注砼、桩顶浮浆清理等主要顺序开展围护桩1施工;Step 2: Stake out according to the coordinates of the enclosure pile 1 and the construction error, and then carry out the construction of the enclosure pile 1, in accordance with the main sequence of drilling rig in place, hole formation, hole cleaning, lower reinforcement cage, cast-in-place concrete, pile top laitance cleaning, etc. Construction of enclosure pile 1;

步骤三:在围护桩1顶部拉槽开挖,施做桩顶冠梁2,随后根据随挖随撑的原则进行基坑开挖施工;Step 3: excavate the trench at the top of the enclosure pile 1, construct the crown beam 2 on the top of the pile, and then carry out the excavation of the foundation pit according to the principle of excavation and support;

步骤四:在基坑开挖到砼支撑3以下0.5m时,及时施做砼腰梁12,砼腰梁12与围护桩1之间通过植筋连接,同时腰梁12另一侧预留受力钢筋或预埋钢筋接驳器;Step 4: When the foundation pit is excavated to 0.5m below the concrete support 3, construct the concrete waist beam 12 in time. Stressed steel bar or pre-embedded steel bar connector;

步骤五:根据砼支撑3布置与截面尺寸,对基坑内土体进行拉槽开挖,随后进行整平,敷设垫层,原位绑扎砼支撑3钢筋骨架,布置砼支撑受力筋7,设置加强筋8,加强筋8位置与顶板钢筋11对应,并在砼支撑3两侧面预留钢筋接驳器9;腰梁12与砼支撑3之间的连接,通过在腰梁12上事先预留受力钢筋或预埋钢筋接驳器进行连接;Step 5: According to the arrangement and cross-sectional size of the concrete support 3, the soil in the foundation pit is excavated by grooving, then leveling, laying the cushion, tying the steel skeleton of the concrete support 3 in situ, arranging the reinforcing bars 7 of the concrete support, setting Reinforcing rib 8, the position of reinforcing rib 8 corresponds to roof steel bar 11, and steel bar connector 9 is reserved on both sides of concrete support 3; the connection between waist beam 12 and concrete support 3 is reserved in advance on waist beam 12 Stressed steel bars or embedded steel bar connectors are used for connection;

按要求浇筑砼支撑3,并按规定要求进行养护;Concrete support 3 is poured as required, and maintenance is performed as required;

步骤六:待砼支撑3达到规定养护龄期与设计强度后,基于随挖随撑的原则继续开挖基坑,直至基坑底部,坑底以上0.5m采用人工开挖,随后对坑底及时进行整平、敷设防水层、素砼垫层,绑扎钢筋并浇筑结构底板、结构侧墙与结构中板,主体结构浇筑过程中及时拆除相应位置的内支撑;Step 6: After the concrete support 3 reaches the specified curing age and design strength, continue to excavate the foundation pit based on the principle of follow-up and follow-up support until the bottom of the foundation pit. Manual excavation is used for 0.5m above the pit bottom, and then the bottom of the pit is dug in time. Carry out leveling, laying waterproof layer, plain concrete cushion, binding steel bars and pouring structural bottom plate, structural side wall and structural middle plate, and dismantle the internal support in corresponding positions in time during the pouring process of the main structure;

步骤七:将结构顶板5与砼支撑3接触部位的砼支撑3表面凿毛处理,随后涂刷2-3遍界面剂10,基于砼支撑3两侧预留钢筋接驳器9,将砼支撑3中部设置的加强筋8与顶板钢筋11进行机械连接,随后按要求浇筑结构顶板5;Step 7: The surface of the concrete support 3 at the contact position between the structural roof 5 and the concrete support 3 is chiseled, and then the interface agent 10 is brushed 2-3 times. Rebar connectors 9 are reserved on both sides of the concrete support 3, and the concrete support is 3. The reinforcing ribs 8 arranged in the middle are mechanically connected with the roof reinforcement bars 11, and then the structural roof 5 is poured as required;

砼支撑3底部与结构底板5底面之间的距离不小于300mm;The distance between the bottom of the concrete support 3 and the bottom surface of the structural bottom plate 5 is not less than 300mm;

步骤八:在结构顶板5上方分层回填土体,回填土6密实度不小于93%;Step 8: Backfill the soil in layers above the structural roof 5, and the density of the backfill 6 is not less than 93%;

步骤九:凿除地表以下3m范围内所有结构,给后期市政管线等地下构筑物预留敷设路径。Step 9: Remove all structures within 3m below the surface, and reserve a laying path for the later underground structures such as municipal pipelines.

要从理论上找出能适应任意条件下兼做地下主体结构的基坑临时内支撑,在现有的理论水平与施工技术条件下,仍有相当大的难度,因为各类基坑工程形状不一样,基坑深度与内支撑架设位置不一样,同时主体结构受力与耐久性要求也不完全一致,现有的地下工程建设,仍应遵从“永临结合”的基本理念,将结构顶板与内支撑进行叠合处理、整体受力,同时满足结构承载力与耐久性要求,确保结构上方空间满足市政工程需要。将结构顶板处砼支撑按永久受力构件设计,最大程度确保基坑安全、地下结构受力可靠与长期稳定性。目前的永临结合砼支撑与结构顶板合建工艺,仍需本着功能第一、因地制宜、对症下药、灵活应用的基本原则。It is still quite difficult to theoretically find out the temporary inner support of the foundation pit that can also be used as the main underground structure under any conditions. In the same way, the depth of the foundation pit and the erection position of the inner support are not the same, and the stress and durability requirements of the main structure are not completely consistent. The existing underground engineering construction should still follow the basic concept of "permanent combination". The inner support is superimposed and subjected to overall force, and at the same time, it meets the requirements of structural bearing capacity and durability, and ensures that the space above the structure meets the needs of municipal engineering. The concrete support at the roof of the structure is designed as a permanent stress member to ensure the safety of the foundation pit, the reliable stress of the underground structure and the long-term stability to the greatest extent. The current Yonglin combined concrete support and structural roof co-construction process still needs to adhere to the basic principles of function first, adapting measures to local conditions, prescribing the right medicine, and flexible application.

本发明将基坑内临时砼支撑作为结构顶板的一部分,与永久结构共同承担外部荷载,一方面避免了砼支撑作为临时构件需要凿除,简化了工艺、加快了进度,一方面减少了结构顶板尺寸,满足地下结构整体受力要求,首次提出了将临时砼支撑与永久顶板统筹考虑的新思路,提升了地下工程的安全、绿色与环保设计理念,具有较高的经济效益和社会效益,在城市轨道交通、铁路、公路等工程中有广泛的应用前景。The invention uses the temporary concrete support in the foundation pit as a part of the structural roof, and shares the external load with the permanent structure. On the one hand, the concrete support needs to be removed as a temporary member, which simplifies the process and speeds up the progress. On the one hand, the size of the structural roof is reduced. , to meet the overall stress requirements of the underground structure, and for the first time put forward a new idea of considering the temporary concrete support and the permanent roof as a whole, which improves the safety, green and environmental protection design concept of underground engineering, and has high economic and social benefits. Rail transit, railway, highway and other projects have a wide range of application prospects.

本发明的内容不限于实施例所列举,本领域普通技术人员通过阅读本发明说明书而对本发明技术方案采取的任何等效的变换,均为本发明的权利要求所涵盖。The content of the present invention is not limited to those listed in the embodiments, and any equivalent transformations taken by those of ordinary skill in the art to the technical solutions of the present invention by reading the description of the present invention are covered by the claims of the present invention.

Claims (10)

1.基于永临结合的砼支撑与结构顶板合建体系,其特征在于:1. The combined construction system of concrete support and structural roof based on the combination of Yonglin is characterized in that: 所述体系包括地下结构(4)、围护桩(1)、腰梁(12)和砼支撑(3);The system includes an underground structure (4), an enclosure pile (1), a waist beam (12) and a concrete support (3); 围护桩(1)位于地下结构(4)外侧,桩顶高于地下结构(4)顶板,桩底在地下结构(4)底板以下;The enclosure pile (1) is located outside the underground structure (4), the top of the pile is higher than the top plate of the underground structure (4), and the bottom of the pile is below the bottom plate of the underground structure (4); 围护桩(1)内侧设置有腰梁(12),桩顶设置冠梁(2),砼支撑(3)与腰梁(12)刚性连接、有效传力,砼支撑(3)位于地下结构(4)顶部位置。The inner side of the enclosure pile (1) is provided with a waist beam (12), the top of the pile is provided with a crown beam (2), the concrete support (3) is rigidly connected with the waist beam (12) and effectively transmits force, and the concrete support (3) is located in the underground structure (4) Top position. 2.根据权利要求1所述的基于永临结合的砼支撑与结构顶板合建体系,其特征在于:2. The combined construction system of concrete support and structural roof based on the combination of permanent proximity according to claim 1, is characterized in that: 地下结构(4)包括结构顶板(5)、结构中板、结构底板、结构侧墙和结构中立柱,围护桩(1)位于地下结构(4)外侧四周,腰梁(12)和砼支撑(3)位于结构顶板(5)上方。The underground structure (4) includes a structural top plate (5), a structural middle plate, a structural bottom plate, a structural side wall and a structural central column, the enclosure piles (1) are located around the outside of the underground structure (4), and the waist beams (12) and concrete support (3) Above the structural roof (5). 3.根据权利要求2所述的基于永临结合的砼支撑与结构顶板合建体系,其特征在于:3. The concrete support and structural roof joint construction system based on the permanent combination according to claim 2, is characterized in that: 围护桩(1)顶部设置有桩顶冠梁(2),围护桩(1)与冠梁(2)之间通过植筋或预留筋有效连接。The top of the enclosure pile (1) is provided with a pile top crown beam (2), and the enclosure pile (1) and the crown beam (2) are effectively connected by planting reinforcement or reserved reinforcement. 4.根据权利要求3所述的基于永临结合的砼支撑与结构顶板合建体系,其特征在于:4. The combined construction system of concrete support and structural roof based on the combination of permanent proximity according to claim 3, is characterized in that: 腰梁(12)位于围护桩(1)内侧,通过植筋连接;腰梁(12)内侧预留受力钢筋或预埋钢筋接驳器。The waist beam (12) is located on the inner side of the enclosure pile (1) and is connected by planting reinforcing bars; the inner side of the waist beam (12) is reserved for stressed steel bars or pre-embedded steel bar connectors. 5.根据权利要求4所述的基于永临结合的砼支撑与结构顶板合建体系,其特征在于:5. The combined construction system of concrete support and structural roof based on the permanent combination according to claim 4, is characterized in that: 砼支撑(3)内设置有砼支撑受力筋(7),砼支撑(3)两端通过砼支撑受力筋(7)与腰梁(12)内侧的预留受力钢筋或预埋钢筋接驳器连接。Concrete support stress bars (7) are arranged in the concrete support (3), and the two ends of the concrete support (3) pass through the concrete support stress bars (7) and the reserved stress bars or pre-embedded steel bars on the inner side of the waist beam (12). Connector connection. 6.根据权利要求5所述的基于永临结合的砼支撑与结构顶板合建体系,其特征在于:6. The combined construction system of concrete support and structural roof based on the permanent combination according to claim 5, is characterized in that: 结构顶板(5)上表面呈规律的齿轮型凹凸构造,砼支撑(3)位于结构顶板(5)上表面,与结构顶板(5)呈凹凸状机械咬合连接;The upper surface of the structural top plate (5) has a regular gear-shaped concave-convex structure, and the concrete support (3) is located on the upper surface of the structural top plate (5), and is mechanically engaged with the structural top plate (5) in a concave-convex shape; 砼支撑(3)内设置有横向加强筋(8),加强筋(8)两端预留钢筋接驳器(9),砼支撑(3)内加强筋(8)通过钢筋接驳器(9)与结构顶板(5)内对应的钢筋(11)连接。A transverse reinforcing rib (8) is arranged in the concrete support (3), and steel bar connectors (9) are reserved at both ends of the reinforcing bar (8), and the reinforcing bars (8) in the concrete support (3) pass through the steel bar connector (9). ) are connected to the corresponding reinforcement bars (11) in the structural roof (5). 7.根据权利要求6所述的基于永临结合的砼支撑与结构顶板合建体系,其特征在于:7. The combined construction system of concrete support and structural roof based on permanent combination according to claim 6, is characterized in that: 砼支撑(3)与结构顶板(5)之间接触面凿毛处理,并涂覆有界面剂(10)。The contact surface between the concrete support (3) and the structural top plate (5) is chiseled and coated with an interface agent (10). 8.根据权利要求7所述的基于永临结合的砼支撑与结构顶板合建体系,其特征在于:8. The combined construction system of concrete support and structural roof based on permanent combination according to claim 7, is characterized in that: 地下结构(4)的结构顶板(5)、结构底板和结构侧墙外均设置有防水材料,进行全包防水。The structural top plate (5), the structural bottom plate and the outside of the structural side walls of the underground structure (4) are all provided with waterproof materials for full waterproofing. 9.根据权利要求8所述的基于永临结合的砼支撑与结构顶板合建体系,其特征在于:9. The combined construction system of concrete support and structural roof based on permanent combination according to claim 8, is characterized in that: 结构顶板(5)上方设置回填土(6),回填土(6)采用分层回填。The backfill (6) is arranged above the structural roof (5), and the backfill (6) is backfilled in layers. 10.基于永临结合的砼支撑与结构顶板合建体系构建方法,其特征在于:10. A method for constructing a joint-construction system of concrete support and structural roof based on the combination of forever and ever, which is characterized in that: 包括以下步骤:Include the following steps: 步骤一:基于地下结构(4)轮廓,在基坑轮廓外设置降水井,在基坑开挖前1个月时间进行降水施工;Step 1: Based on the outline of the underground structure (4), set up a dewatering well outside the outline of the foundation pit, and carry out dewatering construction 1 month before the excavation of the foundation pit; 步骤二:根据围护桩(1)坐标与施工误差进行放样,随后进行围护桩(1)施工,按照钻机就位、成孔、清孔、下钢筋笼、灌注砼、桩顶浮浆清理的顺序开展围护桩(1)施工;Step 2: Stake out according to the coordinates of the enclosure pile (1) and the construction error, and then carry out the construction of the enclosure pile (1), according to the drilling rig in place, hole formation, hole clearing, lower reinforcement cage, cast-in-place concrete, pile top floating slurry cleaning Carry out the construction of the enclosure piles (1) in the sequence; 步骤三:在围护桩(1)顶部拉槽开挖,施做桩顶冠梁(2),随后根据随挖随撑的原则进行基坑开挖施工;Step 3: Excavate trenches at the top of the retaining piles (1), construct the crown beams (2) on the top of the piles, and then carry out the excavation of the foundation pit according to the principle of excavation and support; 步骤四:在基坑开挖到砼支撑(3)以下0.5m时,及时施做砼腰梁(12),砼腰梁(12)与围护桩(1)之间通过植筋连接,同时腰梁(12)另一侧预留受力钢筋或预埋钢筋接驳器;Step 4: When the foundation pit is excavated to 0.5m below the concrete support (3), construct the concrete waist beam (12) in time. The other side of the waist beam (12) is reserved for stressed steel bars or pre-embedded steel bar connectors; 步骤五:根据砼支撑(3)布置与截面尺寸,对基坑内土体进行拉槽开挖,随后进行整平,敷设垫层,原位绑扎砼支撑(3)钢筋骨架,布置砼支撑受力筋(7),设置加强筋(8),加强筋(8)位置与顶板钢筋(11)对应,并在砼支撑(3)两侧面预留钢筋接驳器(9);腰梁(12)与砼支撑(3)之间的连接,通过在腰梁(12)上事先预留受力钢筋或预埋钢筋接驳器进行连接;Step 5: According to the arrangement and cross-sectional size of the concrete support (3), the soil in the foundation pit is excavated by grooving, then leveling, laying the cushion, binding the concrete support in situ (3) Rebar skeleton, arranging the concrete support to bear the force Ribs (7) are provided with reinforcing ribs (8), the positions of the reinforcing ribs (8) are corresponding to the roof reinforcement bars (11), and steel bar connectors (9) are reserved on both sides of the concrete support (3); waist beams (12) The connection with the concrete support (3) is performed by pre-reserving stress-bearing steel bars or pre-embedded steel bar connectors on the waist beam (12); 按要求浇筑砼支撑(3),并按规定要求进行养护;Concrete support (3) is poured as required, and maintained as required; 步骤六:待砼支撑(3)达到规定养护龄期与设计强度后,基于随挖随撑的原则继续开挖基坑,直至基坑底部,坑底以上0.5m采用人工开挖,随后对坑底及时进行整平、敷设防水层、素砼垫层,绑扎钢筋并浇筑结构底板、结构侧墙与结构中板,主体结构浇筑过程中及时拆除相应位置的内支撑;Step 6: After the concrete support (3) reaches the specified curing age and design strength, continue to excavate the foundation pit based on the principle of digging and supporting until the bottom of the foundation pit. Manual excavation is used for 0.5m above the pit bottom, and then the pit is excavated. The bottom shall be leveled in time, the waterproof layer and the plain concrete cushion shall be laid, the reinforcement shall be bound, and the structural bottom plate, structural side wall and structural middle plate shall be poured, and the internal support at the corresponding position shall be removed in time during the pouring of the main structure; 步骤七:将结构顶板(5)与砼支撑(3)接触部位的砼支撑(3)表面凿毛处理,随后涂刷2-3遍界面剂(10),基于砼支撑(3)两侧预留钢筋接驳器(9),将砼支撑(3)中部设置的加强筋(8)与顶板钢筋(11)进行机械连接,随后按要求浇筑结构顶板(5);Step 7: Chisel the surface of the concrete support (3) at the contact position between the structural roof (5) and the concrete support (3), and then apply the interface agent (10) 2-3 times. Retain the steel bar connector (9) to mechanically connect the reinforcing bar (8) set in the middle of the concrete support (3) with the roof steel bar (11), and then pour the structural roof (5) as required; 砼支撑(3)底部与结构底板(5)底面之间的距离不小于300mm;The distance between the bottom of the concrete support (3) and the bottom surface of the structural bottom plate (5) shall not be less than 300mm; 步骤八:在结构顶板(5)上方分层回填土体,回填土(6)密实度不小于93%;Step 8: Backfill the soil in layers above the structural roof (5), and the density of the backfill (6) is not less than 93%; 步骤九:凿除地表以下3m范围内所有结构,给后期市政管线等地下构筑物预留敷设路径。Step 9: Remove all structures within 3m below the surface, and reserve the laying path for the later underground structures such as municipal pipelines.
CN202010250536.4A 2020-04-01 2020-04-01 Concrete support and structural top slab combined construction system based on permanent and temporary combination and its construction method Active CN111305220B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010250536.4A CN111305220B (en) 2020-04-01 2020-04-01 Concrete support and structural top slab combined construction system based on permanent and temporary combination and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010250536.4A CN111305220B (en) 2020-04-01 2020-04-01 Concrete support and structural top slab combined construction system based on permanent and temporary combination and its construction method

Publications (2)

Publication Number Publication Date
CN111305220A true CN111305220A (en) 2020-06-19
CN111305220B CN111305220B (en) 2024-08-30

Family

ID=71151820

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010250536.4A Active CN111305220B (en) 2020-04-01 2020-04-01 Concrete support and structural top slab combined construction system based on permanent and temporary combination and its construction method

Country Status (1)

Country Link
CN (1) CN111305220B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113266017A (en) * 2021-06-15 2021-08-17 中铁四局集团第一工程有限公司 Regulation and storage tank construction method based on 'permanent-face integrated' inner support structure of deep foundation pit
CN114457810A (en) * 2022-01-26 2022-05-10 中铁第一勘察设计院集团有限公司 Foundation pit inner support system based on permanent-temporary combination and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017206412A1 (en) * 2016-06-03 2017-12-07 长沙远大住宅工业集团股份有限公司 Superimposed assembly-type underground pipe gallery system and construction and manufacturing process
CN107975038A (en) * 2017-10-18 2018-05-01 广州地铁设计研究院有限公司 A kind of cap excavation method temporary support makees the support of permanent structure concrete and its construction method
CN207567780U (en) * 2017-10-18 2018-07-03 广州地铁设计研究院有限公司 A kind of cap excavation method temporary support is made permanent structure and is supported with concrete
CN212001126U (en) * 2020-04-01 2020-11-24 中铁第一勘察设计院集团有限公司 Concrete support and structure top plate combined building system based on permanent-temporary combination

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017206412A1 (en) * 2016-06-03 2017-12-07 长沙远大住宅工业集团股份有限公司 Superimposed assembly-type underground pipe gallery system and construction and manufacturing process
CN107975038A (en) * 2017-10-18 2018-05-01 广州地铁设计研究院有限公司 A kind of cap excavation method temporary support makees the support of permanent structure concrete and its construction method
CN207567780U (en) * 2017-10-18 2018-07-03 广州地铁设计研究院有限公司 A kind of cap excavation method temporary support is made permanent structure and is supported with concrete
CN212001126U (en) * 2020-04-01 2020-11-24 中铁第一勘察设计院集团有限公司 Concrete support and structure top plate combined building system based on permanent-temporary combination

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113266017A (en) * 2021-06-15 2021-08-17 中铁四局集团第一工程有限公司 Regulation and storage tank construction method based on 'permanent-face integrated' inner support structure of deep foundation pit
CN113266017B (en) * 2021-06-15 2022-05-17 中铁四局集团第一工程有限公司 Construction method of adjustment and storage tank based on the inner support structure of deep foundation pit "Yonglin integration"
CN114457810A (en) * 2022-01-26 2022-05-10 中铁第一勘察设计院集团有限公司 Foundation pit inner support system based on permanent-temporary combination and construction method thereof

Also Published As

Publication number Publication date
CN111305220B (en) 2024-08-30

Similar Documents

Publication Publication Date Title
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN101440708B (en) PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN106013241B (en) Guan Liang foundation trench uprightly performs and cap excavation method station integrated structure system and construction method
CN105464134B (en) Multi-layer underground space is along inverse combining construction method and supporting construction under existing facility
CN101509263A (en) Digging method foundation pit structure of steel cover and plate cover, and construction method
CN104895089A (en) Construction method of permanent retaining system characterized by joint work of basement floor slabs and retaining piles
CN105756091B (en) A Construction Method of Subway Station Foundation Pit Controlling the Deformation of Adjacent Buildings
CN104818728A (en) Permanent supporting system with basement floor and supporting piles capable of working together
CN110106919A (en) Enclosure structure and construction method of a cover-excavation station
CN110158630A (en) A kind of deep covering layer area large-span arch bridge annular ground continuous wall base
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN102691302A (en) Concrete structure for supporting deep foundation pit
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN108385693B (en) Equal-generation anchor bolt supporting method and system for staged basement supporting
CN111305220A (en) Concrete support and structural top plate combined building system based on permanent and temporary combination and construction method thereof
CN204311456U (en) Foundation ditch strengthening structure
CN212001126U (en) Concrete support and structure top plate combined building system based on permanent-temporary combination
CN111877358B (en) A support structure, building and construction method for a foundation pit with upper soil layer and lower soft rock
CN212427155U (en) Tongue-and-groove type prefabricated underground continuous wall structure
CN210195766U (en) A kind of underground structure with arch cover buried and built along with it
CN110939139B (en) Pile-sheet wall structure and construction method based on rigid contact of special-shaped retaining wall behind piles
CN211172070U (en) Assembled type suspended wall retaining wall structure of reinforced concrete member
CN102330430A (en) Construction method for prefabricated building enclosure of deep foundation pit in low-temperature environment construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Dai Zhiren

Inventor after: Lv Haijun

Inventor after: Zhao Yajun

Inventor after: Duan Jianfeng

Inventor after: Xu Hongchun

Inventor after: Liu Tong

Inventor after: Zhang Yubin

Inventor after: Zha Jiahong

Inventor after: Wang Wei

Inventor after: Ma Linlin

Inventor after: Wang Yaohui

Inventor after: Li Tan

Inventor after: Chen Xinping

Inventor after: Meng Xianquan

Inventor after: Huang Yanbin

Inventor after: Liao Hui

Inventor after: Li Runxuan

Inventor after: Jia Shaochun

Inventor after: Wang Wenbin

Inventor after: Weng Musheng

Inventor after: Zhang Qingchuang

Inventor after: Yu Zhong

Inventor before: Dai Zhiren

Inventor before: Liu Tong

Inventor before: Zhang Yubin

Inventor before: Zha Jiahong

Inventor before: Wang Wei

Inventor before: Ma Linlin

Inventor before: Wang Wenbin

Inventor before: Wang Yaohui

Inventor before: Chen Xinping

Inventor before: Meng Xianquan

Inventor before: Huang Yanbin

Inventor before: Liao Hui

Inventor before: Zhang Qingchuang

Inventor before: Li Tan

Inventor before: Yu Zhong

Inventor before: Lv Haijun

Inventor before: Zhao Yajun

Inventor before: Duan Jianfeng

Inventor before: Xu Hongchun

CB03 Change of inventor or designer information