CN111677000B - Method for simultaneously removing multiple connection parts of side wall of new and old subway station - Google Patents

Method for simultaneously removing multiple connection parts of side wall of new and old subway station Download PDF

Info

Publication number
CN111677000B
CN111677000B CN202010378246.8A CN202010378246A CN111677000B CN 111677000 B CN111677000 B CN 111677000B CN 202010378246 A CN202010378246 A CN 202010378246A CN 111677000 B CN111677000 B CN 111677000B
Authority
CN
China
Prior art keywords
column
breaking
broken
concrete
new
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010378246.8A
Other languages
Chinese (zh)
Other versions
CN111677000A (en
Inventor
雷升祥
代敬辉
黄欣
张京京
赵静波
冀国栋
陈一夫
岳长城
陈霞飞
彭澍
陈自龙
高飞鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN202010378246.8A priority Critical patent/CN111677000B/en
Publication of CN111677000A publication Critical patent/CN111677000A/en
Application granted granted Critical
Publication of CN111677000B publication Critical patent/CN111677000B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Sustainable Development (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a method for simultaneously removing a plurality of connection parts of a side wall of a new subway station and an old subway station. The beam column is firstly constructed as a supporting structure, and then the reinforced concrete structure in the broken hole range is removed at one time under the supporting condition of a beam column system after the concrete strength reaches the design value, so that the simultaneous breaking of a plurality of connection parts can be met. The support is arranged between the column body and the beam body, namely the column body is regarded as hinged, the column body is prevented from being bent, and particularly the buckling of the column body can be effectively avoided under the condition of large high span ratio. This technical scheme has not only changed beam column connection structure and has been applicable to the great condition of high span ratio, can also reduce to abolish the influence of construction to existing structure to can be on the basis of fully guaranteeing construction safety, abolish a plurality of positions of plugging into simultaneously, shorten construction period, practice thrift construction cost.

Description

Method for simultaneously removing multiple connection parts of side wall of new and old subway station
Technical Field
The invention relates to the related technical field of subway station building, in particular to a method for simultaneously removing a plurality of connection parts of a side wall of a new subway station and an old subway station.
Background
With the advance of urbanization process in China, the construction of urban underground space develops rapidly, and the transfer condition of a plurality of subway lines usually appears, so that the existing subway needs to be changed and expanded, and the side wall of the connection part of the new subway and the old subway is broken. The side wall is broken up and is under construction and can inevitably cause the disturbance to existing structure, influences existing structure's stability. The traditional manual breaking method has the disadvantages of difficult construction, long construction period and high cost; the subsequent improved mechanical breaking method also adopts a method of firstly breaking and then supporting, and has great influence on the existing structure during construction.
With the networked development of urban underground space construction, a plurality of communicated connection parts of the side wall can be encountered in the construction process of building new and old subway stations. Considering that the construction method of 'first breaking and then supporting' in the prior art has a large influence on the existing structure during the breaking period, in the case of multiple connection parts of the side wall of a new subway station and an old subway station, only a method of constructing each connection part in sequence can be adopted, and all the connection parts cannot be constructed simultaneously. Therefore, the existing breaking technology needs to be improved, so that the construction period can be shortened and the construction cost can be saved on the basis of fully ensuring the construction safety.
CN 107604941A discloses a method for removing a continuous wall and a side wall at a communication position of a new subway station and an old subway station, which comprises the following operation steps of determining the positions of cutting the underground continuous wall and the side wall at the communication position of the new subway station and the old subway station; drilling a hoisting hole and a rope threading hole; installing and fixing a guide wheel and a wire saw device; installing a diamond rope and penetrating the diamond rope into the rope threading hole; a hoisting rope is penetrated into the hoisting hole; linking an operating system and installing a safety protective guard; and cutting, hoisting and crushing the wall body in sequence. According to the method for removing the continuous wall and the side wall at the communication position of the new subway station and the old subway station, no support measure is taken in the removing process, the disturbance on the existing structure is large, and the method cannot adapt to the situation that a plurality of connection positions are removed simultaneously.
CN 109736586A, discloses a method for breaking the existing underground station side wall to open a hole and reform, the method divides the side wall into blocks, including a beam column region, a rectangular midspan region and a rectangular ending region, and carries out odd-even number numbering on all the beam column region, the rectangular midspan region and the hole region respectively in sequence, the whole process adopts the thought of 'zero-dividing into whole and zero-accumulating into whole', and combines the processes of 'odd-number first and even-number second' and 'supporting along with breaking' according to the sequence of 'supporting first and midspan'; the influence on the existing station in the transformation process is reduced, the safety of the existing structure is ensured, two vertical H-shaped steels are arranged in each horizontal hole for supporting, the one-time underpinning range is small, the operation is safe, the number of the reinforcing steel bars passing through the vertical H-shaped steels is small, and the setting speed of the reinforcing steel bars is high; the construction joint is arranged at 1/3 length positions of each span beam, so that the section with larger stress of the newly cast beam column structure is ensured to be poured by disposable concrete, and the mechanical property of the structure after modification is improved. However, the method for the beam-column integrated structure has complex construction procedures and complex stress of the beam-column structure, and particularly has higher requirement on the stress of the column when the opening and removing range is larger.
When a new subway station and an old subway station are built, a plurality of connection parts of the side wall may occur, as shown in fig. 1. When the prior art meets the condition, the common method is as follows:
firstly, breaking the connection part I, and applying a waterproof layer and a reinforcing layer of the connection part I after the breaking is finished;
after the maintenance of the reinforcing layer of the connection part I is finished, the connection part II is broken, and after the breaking is finished, a waterproof layer and a reinforcing layer of the connection part II are applied;
and after the maintenance of the reinforcing layer of the connection part II is finished, the connection part III is broken, and the waterproof layer and the reinforcing layer of the connection part III are applied after the breaking is finished.
The construction method for successively breaking the connection part needs a longer construction period, thereby increasing the construction cost.
Disclosure of Invention
In the prior art, a construction method of firstly removing and then supporting is mostly adopted, no supporting measure is taken during the removing period, and the influence on the existing structure is large, so that in the case of a plurality of connection parts of the side wall of a new subway station and an old subway station, only a method of constructing each connection part in sequence can be adopted, and all the connection parts cannot be constructed simultaneously, so that the construction period and the construction cost are increased. The construction method of the beam-column integrated structure enables the column to be stressed in a complex manner, and is particularly not beneficial to overall stability under the condition that the vertical size of the broken hole range is high.
The invention aims to provide a method for simultaneously removing a plurality of connection parts of a side wall of a new subway station and an old subway station, which can effectively reduce the influence of removal construction on an existing structure and can realize simultaneous removal construction on the plurality of connection parts of the side wall of the subway.
The technical scheme adopted by the invention is a method for simultaneously removing a plurality of connection parts of the side wall of a new subway station and an old subway station, namely simultaneously constructing a plurality of connection parts and adopting a method of firstly constructing a column, then constructing a beam and then breaking a hole. Selecting any one connection part, wherein the operation steps of breaking the connection part are as follows:
(1) transforming the pipeline at the upper part of the connection part, and determining a broken contour line, wherein the broken contour line comprises the position setting-out of a beam and a column;
(2) according to the broken contour line, breaking concrete corresponding to the position of the cylinder, reserving concrete at the position of the support, stripping required reserved steel bars, constructing a cylinder structural steel bar and a new and old steel bar lap joint structure, and erecting a template to pour concrete;
(3) the beam structure is broken by adopting a block and step mode, and the block size is determined according to the structural stress condition and the wall bearing performance, and the principle is from the middle to two sides. According to the broken contour line, the position of the broken beam body corresponds to concrete, the required reserved steel bars are stripped, a column structural steel bar and a new and old steel bar lap joint structure are constructed, and a template is erected for pouring concrete. When the strength of the middle block concrete of the beam body reaches a design value, dismantling the template and gradually constructing two side block structures;
(4) and (3) after the strength of the column concrete reaches a design value, removing the template and constructing the beam end block positioned at the top of the column. After the beam is broken, firstly arranging a support between the end block of the beam body and the column, then overlapping reinforcing steel bars, erecting a template and pouring concrete;
(5) and after the strength of the whole concrete structure reaches a design value, breaking the wall body in the range of the opening hole in one step.
Further, when the beam body is broken, the beam body is subdivided into a plurality of blocks, and the blocks are sequentially cut from the middle to two sides according to the partitioning sequence, broken and cast by supporting a mold;
further, when the beam is broken into blocks, the strength of the upper block is required to reach the designed strength, and the construction process of the next block can be performed;
furthermore, the outer side of the end block of the beam body at the top of the column is required to exceed the edge of the column by not less than 20 cm;
further, the support forms include a plate type rubber support, a basin type support and a spherical support, but are not limited to the above;
and further, the wall body is broken in the opening range, a hydraulic diamond rope saw is used for breaking and cutting, and the small pieces which are broken and cut are transported after being broken by hydraulic tongs.
Compared with the prior art, the invention provides a method for breaking the side wall of the connection part of a new subway station and an old subway station, namely, a method of breaking a hole after a column and a beam is adopted. The beam column is firstly constructed as a supporting structure, and then the reinforced concrete structure in the broken hole range is removed at one time under the supporting condition of a beam column system after the concrete strength reaches the design value, so that the simultaneous breaking of a plurality of connection parts can be met. The support is arranged between the column body and the beam body, namely the column body is regarded as hinged, the column body is prevented from being bent, and particularly the buckling of the column body can be effectively avoided under the condition of large high span ratio. This technical scheme has not only changed beam column connection structure and has been applicable to the great condition of high span ratio, can also reduce to abolish the influence of construction to existing structure to can be on the basis of fully guaranteeing construction safety, abolish a plurality of positions of plugging into simultaneously, shorten construction period, practice thrift construction cost.
Drawings
Fig. 1 is a schematic diagram of simultaneous removal of a plurality of connection parts of a side wall of a new subway station and an old subway station.
Fig. 2 is a schematic structural diagram of a beam column for simultaneously removing a plurality of connection parts of the side wall of a new subway station and an old subway station.
FIG. 3 is a schematic view of a beam body partition breaking and cutting sequence.
In the figure, 1 is a column body, and 2 is a support; 3 is a beam body; 4 is the range of opening holes; 31 is a beam middle block, 32 is a beam side block, and 33 is a beam end block.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings and examples.
Fig. 2 and 3 are schematic diagrams of beam-column structures and beam partition breaking and cutting sequences for simultaneously breaking a plurality of connection parts of the side walls of the new and old subway stations.
The invention provides a method for simultaneously removing a plurality of connection parts of a side wall of a new and old subway station, as shown in figure 1, three connection parts, namely 1, 2 and 3 of the side wall of the new and old subway station, adopt a method of firstly breaking columns and then breaking holes to carry out synchronous construction on the plurality of connection parts, firstly simultaneously remove columns of all connection parts, then apply a beam body structure, and finally remove concrete in a hole-opening range for one time.
The following will describe the present invention in further detail with reference to fig. 2 and specific embodiments, taking any one connection portion of the sidewall as an example, the operation steps of the breaking are as follows:
(1) determining a broken contour line, paying off positions of the column 1 and the beam 3, and dividing the beam into a beam middle block 31, a beam side block 32 and a beam end block 33;
(2) according to the broken contour line, breaking concrete corresponding to the position of the cylinder 1, reserving concrete at the position of the support 2, stripping the required reserved steel bar, constructing a lap joint structure of the structural steel bar of the cylinder 1 and new and old steel bars, and erecting a template to pour concrete;
(3) the structure of the beam body 3 is broken by adopting a block and step mode and is manufactured from the middle to two sides. According to the broken contour line, the position of the middle block 31 of the broken beam body corresponds to concrete, the required reserved steel bars are peeled off, the structural steel bars of the middle block 31 of the beam body and the lap joint structure of the new and old steel bars are constructed, the steel bar connector is reserved, and a template is erected for pouring concrete. When the strength of the concrete in the middle block 31 of the beam body reaches a design value, dismantling the template and gradually constructing the structures of the side blocks 32 of the beam bodies on two sides;
(4) and (3) after the strength of the column concrete reaches a design value, removing the template and constructing the beam end block 33 positioned at the top of the column. After the beam is broken, firstly arranging a support 2 between the end block of the beam body and the column, then overlapping reinforcing steel bars, erecting a template and pouring concrete;
(5) and after the strength of the whole concrete structure reaches a design value, breaking the wall body in the range of the opening hole in one step.
The size of the beam body blocks is determined according to the structural stress condition and the wall bearing performance, and the size of two sides of the beam body end block 33 exceeding the edge of the column is not less than 20 cm;
the beam body must be cut in sequence according to the partition sequence strictly, and is manufactured after the strength of the previous process meets the requirement;
the side wall is broken by a hydraulic diamond wire saw, and the cut small blocks are broken by hydraulic tongs and then transported;
when the beam concrete is poured in blocks, the positions of the adjacent block steel bar connectors are reserved by a method of a template cushion block. Taking the beam body middle block 31 as an example, when a template is built, a cushion block is arranged between the beam body middle block 31 and the beam body side block 32, and the position of the steel bar connector is reserved.
Compared with the prior art, the invention provides a method for breaking the side wall of the connection part of the new and old subway stations, namely, a method of firstly constructing a beam column and then constructing a hole is adopted, the beam column is constructed as a supporting structure, and then the reinforced concrete structure in the hole breaking range is removed at one time under the supporting condition of a beam column system after the concrete strength reaches a design value, so that a plurality of connection parts can be simultaneously broken. The support is arranged between the column and the beam body, namely the column is regarded as hinged, so that the column is prevented from bending, and particularly the buckling of the column can be effectively avoided under the condition of large high span ratio. This technical scheme has not only changed beam column connection structure and has been applicable to the great condition of high span ratio, can also reduce to abolish the influence of construction to existing structure to can be on the basis of fully guaranteeing construction safety, abolish a plurality of positions of plugging into simultaneously, shorten construction period, practice thrift construction cost.

Claims (2)

1. A method for simultaneously removing a plurality of connection parts of side walls of new and old subway stations is characterized by comprising the following steps: constructing a plurality of connection parts simultaneously by adopting a method of firstly constructing columns and then constructing beams and then breaking holes; selecting any one connection part, wherein the operation steps of breaking the connection part are as follows:
(1) transforming the pipeline at the upper part of the connection part, and determining a broken contour line, wherein the broken contour line comprises beam and column position pay-off;
(2) according to the broken contour line, breaking concrete corresponding to the position of the cylinder, reserving concrete at the position of the support, stripping required reserved steel bars, constructing a cylinder structural steel bar and a new and old steel bar lap joint structure, and erecting a template to pour concrete;
(3) the beam structure is broken, the size of blocks is determined by adopting a block and step mode according to the structural stress condition and the wall bearing performance, and the principle is from the middle to two sides; according to the broken contour line, breaking the concrete corresponding to the position of the beam body, stripping off the required reserved steel bars, constructing a beam body structural steel bar and a new and old steel bar lap joint structure, and erecting a template to pour the concrete; when the strength of the middle block concrete of the beam body reaches a design value, dismantling the template and gradually constructing two side block structures;
(4) after the strength of the column concrete reaches a design value, dismantling the template and applying a construction step of a beam end block positioned at the top of the column; after the beam is broken, firstly arranging a support between the end block of the beam body and the column, then overlapping reinforcing steel bars, erecting a template and pouring concrete;
(5) after the strength of the whole concrete structure reaches the design value, breaking the wall body in the range of opening the hole in one step;
when the beam body is broken, the beam body is subdivided into a plurality of blocks, and the blocks are sequentially cut from the middle to two sides according to the partition sequence, broken and cast by supporting a mold;
breaking the wall body in the opening range, adopting a hydraulic diamond wire saw to carry out breaking and cutting, and breaking and cutting small blocks, adopting hydraulic tongs to break and then transporting;
when the beam is broken into blocks, the strength of the previous block is required to reach the design strength, and the construction process of the next block can be performed;
the outer side of the beam body end block at the top of the column is required to exceed the edge of the column by not less than 20 cm.
2. The method for simultaneously removing a plurality of connection parts of the side wall of a new subway station and an old subway station as claimed in claim 1, wherein: the support form comprises a plate type rubber support, a basin type support or a spherical support.
CN202010378246.8A 2020-05-07 2020-05-07 Method for simultaneously removing multiple connection parts of side wall of new and old subway station Active CN111677000B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010378246.8A CN111677000B (en) 2020-05-07 2020-05-07 Method for simultaneously removing multiple connection parts of side wall of new and old subway station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010378246.8A CN111677000B (en) 2020-05-07 2020-05-07 Method for simultaneously removing multiple connection parts of side wall of new and old subway station

Publications (2)

Publication Number Publication Date
CN111677000A CN111677000A (en) 2020-09-18
CN111677000B true CN111677000B (en) 2022-03-25

Family

ID=72434165

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010378246.8A Active CN111677000B (en) 2020-05-07 2020-05-07 Method for simultaneously removing multiple connection parts of side wall of new and old subway station

Country Status (1)

Country Link
CN (1) CN111677000B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113886913B (en) * 2021-09-18 2024-02-06 中铁十八局集团有限公司 Method for reinforcing equivalent rigidity of underground engineering connection

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201406758Y (en) * 2009-05-15 2010-02-17 江苏科技大学 Light steel portal frame
CN102888814B (en) * 2012-10-16 2014-09-03 上海城建市政工程(集团)有限公司 Construction method of continuous rigid frame bridge pushing closure
KR101410471B1 (en) * 2014-01-16 2014-06-23 주식회사 백산이앤티건설 Method for buttom-up removal of underground retaining wall by using h-piles remained in earth retaining work of existed building
JP6569950B2 (en) * 2016-04-21 2019-09-04 株式会社奥村組 Concrete wall cutting equipment
CN106677330A (en) * 2016-12-16 2017-05-17 中铁第四勘察设计院集团有限公司 Underground station structure of beam column hinge system
CN107604941A (en) * 2017-01-03 2018-01-19 深圳大学 A kind of new and old subway station connectivity part diaphragm wall and side wall restructuring bankrupt
CN108385721A (en) * 2018-02-22 2018-08-10 中铁第勘察设计院集团有限公司 The construction unicom system and its construction method at new subway line station and building up station
CN109736586A (en) * 2018-12-14 2019-05-10 成都市建筑设计研究院 A method of it abolishing existing underground station side wall and punches transformation

Also Published As

Publication number Publication date
CN111677000A (en) 2020-09-18

Similar Documents

Publication Publication Date Title
CN102943678B (en) Arched subway station old and new building connection structure and construction method
CN106088148B (en) Pipe gallery template and its application
CN206722852U (en) A kind of mobile inverted arch trestle of growing up for carrying inverted arch template
CN103437791B (en) The mounting method of buried water stop in a kind of tunnel lining trolley termination
CN111677000B (en) Method for simultaneously removing multiple connection parts of side wall of new and old subway station
CN108118690A (en) A kind of integral hoisting formula coercion underground continuous wall structure and its prefabricated and construction method
CN111878095A (en) Construction method for existing underground structure of newly-built channel connection without reserved interface
CN215717163U (en) Steel form suitable for super high-rise core tube inclined shear wall
CN209227836U (en) Prefabricated concrete structure wall-column all steel is keyed structure
CN109281422A (en) Prefabricated concrete structure wall-column all steel key connection structure and assembling method
CN102936953B (en) Construction method of a bridging-arm stiffened steel structure template
CN102383598A (en) Method for section construction of building project constructional column
CN104453235B (en) Current conversion station fire wall construction technology
Zhang et al. Development and application of mechanized matching equipment for high-speed railway tunnel construction
CN112832546B (en) Transformation method of existing structure replacement concrete system
CN212506288U (en) Cast-in-place reinforced concrete foundation pit inner supporting structure
CN211714210U (en) Reconstruction and extension engineering interface structure based on C-shaped occlusion beam
CN113565533A (en) Arch subway station building connection structure and construction method
CN209817272U (en) Door and window lintel prefabricated by U-shaped building blocks
CN210597642U (en) Anchor bar invisible structure
CN109339798B (en) Core soil removing method for improving tunnel double-side-wall pit guiding method construction
CN111195977A (en) Concrete structure bay window frame plate integral casting inner formwork system and mounting and dismounting method thereof
CN113236308B (en) Construction method of underground excavation pipe row supporting structure of subway station in soft soil water-rich area
CN211806924U (en) Coincide floor production mould
CN221119136U (en) Steel platform supporting structure for dismantling local building body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Lei Shengxiang

Inventor after: Peng Shu

Inventor after: Chen Zilong

Inventor after: Gao Feipeng

Inventor after: Dai Jinghui

Inventor after: Huang Xin

Inventor after: Zhang Jingjing

Inventor after: Zhao Jingbo

Inventor after: Ji Guodong

Inventor after: Chen Yifu

Inventor after: Yue Changcheng

Inventor after: Chen Xiafei

Inventor before: Huang Xin

Inventor before: Gao Feipeng

Inventor before: Zhang Jingjing

Inventor before: Zhao Jingbo

Inventor before: Ji Guodong

Inventor before: Chen Yifu

Inventor before: Yue Changcheng

Inventor before: Chen Xiafei

Inventor before: Peng Shu

Inventor before: Chen Zilong

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant