CN111676837A - Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction - Google Patents

Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction Download PDF

Info

Publication number
CN111676837A
CN111676837A CN202010465841.5A CN202010465841A CN111676837A CN 111676837 A CN111676837 A CN 111676837A CN 202010465841 A CN202010465841 A CN 202010465841A CN 111676837 A CN111676837 A CN 111676837A
Authority
CN
China
Prior art keywords
construction
jib
sets
bracket
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010465841.5A
Other languages
Chinese (zh)
Inventor
孙茂辉
鲁成辉
张旭洋
张炜
许亮亮
戚光久
刘俊奇
万艳彬
刘万杰
李鋆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Fourth Highway First Engineering Firms Co ltd
CCCC Fourth Highway Engineering Co Ltd
Original Assignee
Cccc Fourth Highway First Engineering Firms Co ltd
CCCC Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Fourth Highway First Engineering Firms Co ltd, CCCC Fourth Highway Engineering Co Ltd filed Critical Cccc Fourth Highway First Engineering Firms Co ltd
Priority to CN202010465841.5A priority Critical patent/CN111676837A/en
Publication of CN111676837A publication Critical patent/CN111676837A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the technical field of construction of a bridge beam of a highway bridge, in particular to a hanging bracket erected on a construction platform constructed after the bridge beam of the highway bridge is constructed, which is arranged on two sides of a top bent cap of the existing pier, and comprises top brackets and hanging rods, wherein two groups of the top brackets are respectively arranged on two sides of the hanging rods, four groups of the hanging rods are arranged at two ends of the top brackets in pairs, the upper ends of two adjacent groups of the hanging rods are slidably connected with a top plate, the lower ends of two adjacent groups of the hanging rods are slidably connected with a bottom plate, two fastening nuts are respectively arranged on the upper side and the lower side of the top plate and the bottom plate, the fastening nuts are in threaded connection with the hanging rods, the traditional lower compression system is converted into an upper tension system, and the hanging bracket has the characteristics of small dead weight, convenient installation and disassembly, low cost, safety, reliability and convenient turnover utilization, and effectively solves the problems that the construction, The inner hoop with limited height is difficult to install and cannot be erected.

Description

Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction
Technical Field
The invention relates to the technical field of construction of a bridge and column tie beam of a highway, in particular to a hanging bracket erected on a construction platform constructed after the bridge and column tie beam of the highway is built.
Background
With the gradual saturation of the traffic flow in the operation of the existing highway bridge, the existing highway bridge cannot meet the requirement of future traffic flow, so the existing highway bridge needs to be widened. According to the traditional construction process, a construction platform for connecting a newly-added column tie beam with an originally-designed pier column cannot be realized, a through hole is not reserved in the originally-designed pier column in the construction of the through rod method, and the anchor ear method is limited in construction height, large in installation difficulty and large in potential safety hazard during installation.
In view of the traditional construction process, the invention actively carries out research and innovation based on the fact that the product engineering industry is engaged in the construction process and depends on the abundant practical operation experience for many years and combines the application of theoretical knowledge, and the invention designs the hanging bracket erected on the construction platform constructed after the column tie beam is tied in the limited space under the existing capping beam of the highway bridge under construction.
Disclosure of Invention
The invention aims to provide a hanging bracket erected on a construction platform constructed after a beam of a bridge column of a highway under construction, so as to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides a gallows that construction platform built of construction behind public road bridge post tie beam under construction, sets up in the both sides of current pier stud top bent cap, includes top bracket and jib, top bracket is two sets of, and is two sets of top bracket sets up the both sides at the jib respectively, the jib is four groups, four two liang of settings of jib are at the both ends of top bracket, and adjacent two sets of the upper end sliding connection of jib has a roof, the lower extreme sliding connection of adjacent two sets of jib has a bottom plate, the upper and lower both sides of roof and bottom plate all are equipped with two fastening nut, fastening nut threaded connection is in the jib.
Preferably, the top bracket is a 10# I-steel.
Preferably, the hanger rod is made of 25 phi finish-rolled deformed steel.
Preferably, the top plate and the bottom plate are made of 12 x 30 x 3cm Q235 steel plates, and holes matched with the hanging rods are reserved on the top plate and the bottom plate.
Preferably, the top plate is welded to the upper end flanges of the two sets of top brackets.
Compared with the prior art, the invention has the beneficial effects that:
1) this gallows of setting up of construction platform of construction behind public road bridge post tie beam under construction, convert the upper portion by traditional lower part pressurized system and draw the system, it is little to have the dead weight, ann tears the convenience open, low cost, safe and reliable and be convenient for have enough to meet the need the characteristics of utilization, effectively solved under the current bent cap newly-increased post tie beam construction platform because of the through hole does not reserve, the staple bolt is difficult to the installation and can't set up difficult problem in the limited height, newly-increased tie beam construction provides effectual solution for under the current bent cap, construction progress has been accelerated.
2) According to the hanging bracket erected on the construction platform constructed after the bridge and the column of the road under construction are tied, the top bracket adopts double-spliced 10# I-steel, and the top bracket, the hanging rod and the bottom plate form the whole supporting system. The main function is to transmit the constructed structure and other loads to the constructed capping beam. The steel is an economical section steel with better section mechanical property, and has wide flange, large lateral rigidity, strong bending resistance and convenient turnover.
3) According to the hanger erected on the construction platform constructed after the bridge and column tie beam of the road under construction, the hanger rod is used as a main stressed component of the whole hanger system and is made of phi 25 finish rolled deformed steel bar, the tensile strength of the hanger is high, and the hanger can be used with a matched nut to freely adjust the position of the whole support system in the vertical direction.
4) The hanging bracket erected on the construction platform constructed after the bridge columns of the highway under construction are tied is simple in erection method, and the connection of the hanging rod and the top bottom plate only needs the matched nut and the steel plate to be stably connected. The top plate steel plate and the top bracket are firmly connected by full welding.
5) This gallows of setting up of construction platform of constructing behind highway bridge post tie beam has saved at least one third cost for the construction of staple bolt method, and the staple bolt at first needs set up the support, and the turnover cycle is long, and the cost is higher. This gallows is direct two unifications, can embody its advantage more to it is ann to tear fast open, has improved the construction progress.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the overall construction structure of the present invention;
FIG. 3 is a schematic diagram of an embodiment of the present invention;
FIG. 4 is a schematic perspective view of the present invention;
in the drawings, the components represented by the respective reference numerals are listed below:
the construction method comprises the following steps of 1, top bracket, 2 top plates, 3 suspension rods, 4 bottom plates, 5 fastening nuts, 6, existing pier column top capping beams, 7 longitudinal main beams, 8 transverse distribution beams, 9 square timber, 10 bottom molds, 11 to-be-constructed column tie beams and 12 protective railings.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1, the present invention provides a technical solution: the utility model provides a gallows that construction platform built of construction behind public road bridge post tie beam under construction, the setting is in the both sides of current pier stud top bent cap 6, including top bracket 1 and jib 3, top bracket 1 is two sets of, two sets of top bracket 1 set up the both sides at jib 3 respectively, jib 3 is four groups, two liang of settings at top bracket 1 of four groups jib 3, the upper end sliding connection of two sets of adjacent jib 3 has a roof 2, the lower extreme sliding connection of two sets of adjacent jib 3 has a bottom plate 4, the upper and lower both sides of roof 2 and bottom plate 4 all are equipped with two fastening nut 5, fastening nut 5 threaded connection is in jib 3.
Wherein, the top bracket 1 is 10# I-steel.
Wherein, the suspender 3 is made of phi 25 finish-rolled deformed steel.
The top plate 2 and the bottom plate 4 are both made of 12 x 30 x 3cm Q235 steel plates, and holes matched with the hanging rods 3 are reserved on the top plate 2 and the bottom plate 4.
Wherein the top plate 2 is welded at the upper end flanges of the two groups of top brackets 1.
As shown in fig. 2 to 4, in the construction of the hanger erected on the construction platform constructed after the construction of the highway bridge post tie beam, a longitudinal main beam 7 and a transverse distribution beam 8 are laid on the upper end of the base plate 4, guard rails 12 are arranged at both ends of the longitudinal main beam 7, square timbers 9 and a bottom formwork 10 are laid on the transverse distribution beam 8, and concrete is poured to construct the post tie beam 11 on the upper end of the bottom formwork 10.
Principle of operation
As shown in fig. 2 to 4, in the hanger erected on the construction platform constructed after the bridge and column of the highway under construction is tied, firstly, two top brackets 1 are respectively fixed on the existing top bent cap 6 of the pier column, and the weight is pressed by using sandbags. Then, the hanger rods 2 are respectively inserted from the upper end of the top bracket and fixed by the top plate 3 and the fastening nuts 5, and the top plate 3 and the top bracket 1 are welded and fixed. The hanger rod 2 and the base plate 4 are fixed by a fastening nut 5. After the whole hanger is installed and erected, the longitudinal main beams 7 and the transverse distribution beams 8 can be laid on the hanger bottom plate 4, and the subsequent construction sequence is the same as that of the traditional construction method. After concrete pouring of the column tie beam 11 to be constructed is completed and the strength of the demolished template is reached, the whole hanging bracket and the bottom die can be separated from the column tie beam bottom plate by adjusting the fastening nut 5 at the top plate 3.
In the description herein, references to the description of "one embodiment," "an example," "a specific example" or the like are intended to mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
In the present invention, unless otherwise expressly specified or limited, the terms "mounted," "disposed," "connected," "secured," "screwed" and the like are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; the terms may be directly connected or indirectly connected through an intermediate, and may be communication between two elements or interaction relationship between two elements, unless otherwise specifically limited, and the specific meaning of the terms in the present invention will be understood by those skilled in the art according to specific situations.
The preferred embodiments of the invention disclosed above are intended to be illustrative only. The preferred embodiments are not intended to be exhaustive or to limit the invention to the precise embodiments disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and the practical application, to thereby enable others skilled in the art to best utilize the invention. The invention is limited only by the claims and their full scope and equivalents.

Claims (5)

1. The utility model provides a gallows that construction platform of construction was set up behind public road bridge post tie beam under construction sets up in the both sides of current pier stud top bent cap (6), its characterized in that, including top bracket (1) and jib (3), top bracket (1) is two sets of, and is two sets of top bracket (1) sets up respectively in the both sides of jib (3), jib (3) are four groups, four groups two liang of settings in the both ends of top bracket (1) of jib (3), adjacent two sets of the upper end sliding connection of jib (3) has a roof (2), the lower extreme sliding connection of adjacent two sets of jib (3) has a bottom plate (4), the upper and lower both sides of roof (2) and bottom plate (4) all are equipped with two fastening nut (5), fastening nut (5) threaded connection is in jib (3).
2. The hanging bracket set up on a construction platform constructed after a tie beam of a bridge and column of a road under construction as claimed in claim 1, wherein the top bracket (1) is a 10# I-steel.
3. The hanging bracket for building a construction platform constructed after the tie beam of the bridge column of the road under construction according to the claim 1, characterized in that the hanging rod (3) is made of phi 25 finish rolled deformed steel.
4. The hanging bracket for building the construction platform constructed after the bridge and column tie beam of the road under construction according to the claim 1 is characterized in that the top plate (2) and the bottom plate (4) are both made of 12 x 30 x 3cm Q235 steel plates, and holes matched with the hanging rods (3) are reserved on the top plate (2) and the bottom plate (4).
5. The hanging bracket set up on a construction platform constructed after construction of a bridge-column tie of a road under construction according to claim 1, characterized in that the top plate (2) is welded at the upper end flanges of the two sets of top brackets (1).
CN202010465841.5A 2020-05-28 2020-05-28 Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction Pending CN111676837A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010465841.5A CN111676837A (en) 2020-05-28 2020-05-28 Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010465841.5A CN111676837A (en) 2020-05-28 2020-05-28 Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction

Publications (1)

Publication Number Publication Date
CN111676837A true CN111676837A (en) 2020-09-18

Family

ID=72434749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010465841.5A Pending CN111676837A (en) 2020-05-28 2020-05-28 Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction

Country Status (1)

Country Link
CN (1) CN111676837A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113526322A (en) * 2021-07-01 2021-10-22 中交四公局第一工程有限公司 Top tied beam construction hanging bracket constructed after reconstruction and extension project of bridge under construction and construction method
WO2022142999A1 (en) * 2020-12-29 2022-07-07 中铁一局集团有限公司 Hoisting device for bridge water surface pile tie beam and construction method therefor
US11834852B2 (en) 2020-08-07 2023-12-05 Peri Se Striking tool and method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11834852B2 (en) 2020-08-07 2023-12-05 Peri Se Striking tool and method
WO2022142999A1 (en) * 2020-12-29 2022-07-07 中铁一局集团有限公司 Hoisting device for bridge water surface pile tie beam and construction method therefor
CN113526322A (en) * 2021-07-01 2021-10-22 中交四公局第一工程有限公司 Top tied beam construction hanging bracket constructed after reconstruction and extension project of bridge under construction and construction method
CN113526322B (en) * 2021-07-01 2024-06-11 中交第四公路工程局有限公司 Roof beam construction hanger and construction method for construction after bridge reconstruction and expansion engineering

Similar Documents

Publication Publication Date Title
CN111676837A (en) Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction
CN101787732B (en) Cable-stayed multi-layer framework structure and construction control method thereof
CN109914244B (en) Weak bracket system suitable for high-tower reinforced concrete combined beam steel structure installation and bottom and top plate concrete pouring and operation method thereof
CN111663449A (en) Combined cast-in-place box girder support system and construction method
CN101403246B (en) Large-tonnage hoisting machine one-storied factory combination column and production method thereof
CN212670345U (en) Gallows that construction platform of construction was set up behind public road bridge post tie beam under construction
CN215564318U (en) Rigid pull rod large-cantilever scaffold platform structure
CN212026598U (en) Structure system suitable for assembled steel structure building
CN211368420U (en) Main tower lower beam bracing support system
CN209742074U (en) assembled frame beam column connected node
CN112392141A (en) Large cantilever structure for balancing insufficient end pressure weight and construction method thereof
CN210177367U (en) Weak support system suitable for installation of steel structure of high tower steel-concrete combined beam
CN111946058A (en) Formwork supporting fixing device of Y-shaped high-rise concrete structure and construction method
CN111962850A (en) Construction method of overhanging scaffold
CN110805261A (en) Steel platform steel beam structure based on prestress reinforcement and construction method
CN210316537U (en) Adjustable truss for early-dismantling formwork system
CN110886223A (en) Construction method for concreting steel-concrete combined tower and concrete box girder
CN215211486U (en) Large cantilever structure for balancing insufficient end pressure weight
CN216999351U (en) Novel square pier column tie beam assembly type bracket device
CN215164707U (en) Combined bracket suitable for construction of multi-pier column large cantilever bent cap
CN212612004U (en) Modular cast-in-place box girder braced system
CN213268850U (en) Wall connecting piece system of ultra-large span frame structure
CN215714710U (en) Novel cable force anchoring conversion system
CN113186823B (en) Steel box-steel pipe lattice type concrete combined bridge tower
CN219175011U (en) Assembled prestressing force bent cap platform of encorbelmenting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination