CN111663449A - Combined cast-in-place box girder support system and construction method - Google Patents

Combined cast-in-place box girder support system and construction method Download PDF

Info

Publication number
CN111663449A
CN111663449A CN202010445207.5A CN202010445207A CN111663449A CN 111663449 A CN111663449 A CN 111663449A CN 202010445207 A CN202010445207 A CN 202010445207A CN 111663449 A CN111663449 A CN 111663449A
Authority
CN
China
Prior art keywords
hoop
pier
bridge
steel pipe
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010445207.5A
Other languages
Chinese (zh)
Inventor
章从旭
董俭召
刘永松
刘波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge East China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202010445207.5A priority Critical patent/CN111663449A/en
Publication of CN111663449A publication Critical patent/CN111663449A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明提供一种组合式现浇箱梁支架系统及施工方法,在桥梁的每个中桥墩上安装有上抱箍和下抱箍,上抱箍和下抱箍的牛腿间设有支撑杆,靠近桥梁每个边墩分别设一钢管立柱,钢管立柱的底部支撑在地面混凝土基础上,横桥向上抱箍及钢管立柱顶部分别搭设承重横梁,顺桥向在每跨的两承重横梁顶部搭设贝雷纵梁,在贝雷纵梁上横桥向搭设分配梁,分配梁上安装满堂支架,满堂支架顶部安装现浇箱梁模板系统。本发明适用于山区地形条件复杂、地基处理难度大、墩柱较高等地质条件,结构简单,材料投入少,安全性高。

Figure 202010445207

The invention provides a combined cast-in-place box girder support system and a construction method. An upper hoop and a lower hoop are installed on each middle pier of a bridge, and a support rod is provided between the corbels of the upper hoop and the lower hoop , a steel pipe column is installed near each side pier of the bridge, the bottom of the steel pipe column is supported on the ground concrete foundation, the upper hoop of the transverse bridge and the top of the steel pipe column are respectively set up with load-bearing beams, and the top of the two load-bearing beams of each span is erected along the bridge direction. Bailey longitudinal beam, the distribution beam is erected on the Bailey longitudinal beam in the transverse direction, the distribution beam is installed with a full house support, and the cast-in-place box girder formwork system is installed on the top of the full house support. The invention is suitable for geological conditions such as complex terrain conditions in mountainous areas, difficult foundation treatment, high pier columns, etc., and has simple structure, less material input and high safety.

Figure 202010445207

Description

一种组合式现浇箱梁支架系统及施工方法A combined cast-in-place box girder support system and construction method

技术领域technical field

本发明属于桥梁工程中现浇箱梁施工技术领域,具体涉及一种组合式浇箱梁支架系统及施工方法,特别适用于山区地形条件复杂、地基处理难度大、墩柱较高等情况下的现浇箱梁施工。The invention belongs to the technical field of cast-in-place box girder construction in bridge engineering, and in particular relates to a combined cast-in-place box girder support system and a construction method, which are particularly suitable for existing constructions under the conditions of complex terrain conditions in mountainous areas, difficult foundation treatment, high pier columns and the like. Casting box girder construction.

背景技术Background technique

目前现浇箱梁施工支架常用的主要有满堂支架和钢管支架。满堂支架安全性高,但仅适用于下方无通行要求、墩高在15m以内、地基条件较好、地形较平坦的地区;钢管支架只要桥下净空可以满足搭设要求均可以应用,但在地形陡峭、软弱地质条件下,钢管立柱基础施工难度较大,增加了施工成本,而且墩柱较高的情况下,钢管立柱搭设较高,高空作业工作量大,材料投入大,施工风险高。在山区地形条件复杂、地基处理难度大、墩柱较高等情况下,如何既保证现浇箱梁施工的安全性,又能降低成本投入,保证工期,是施工单位面临的现实问题。At present, the commonly used supports for cast-in-place box girder construction mainly include full-chamber supports and steel pipe supports. The full hall support has high safety, but it is only suitable for areas with no traffic requirements below, the pier height is within 15m, the foundation conditions are good, and the terrain is relatively flat; the steel pipe support can be used as long as the clearance under the bridge can meet the erection requirements, but in steep terrain , Under the weak geological conditions, the construction of the steel pipe column foundation is more difficult, which increases the construction cost, and when the pier column is high, the steel pipe column erection is relatively high, the high-altitude operation workload is large, the material input is large, and the construction risk is high. In the case of complex terrain conditions in mountainous areas, difficult foundation treatment, and high piers and columns, how to not only ensure the safety of cast-in-place box girder construction, but also reduce the cost input and ensure the construction period is a practical problem faced by the construction unit.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提供一种适用于山区地形条件复杂、地基处理难度大、墩柱较高等情况下的组合式现浇箱梁支架系统及施工方法,并在保证安全性的前提下,简化支架结构设计,减少临时材料投入少,缩短施工周期。The purpose of the present invention is to provide a combined cast-in-place box girder support system and construction method suitable for complex terrain conditions in mountainous areas, difficult foundation treatment, high pier columns, etc., and simplify the support under the premise of ensuring safety. Structural design, reducing the investment of temporary materials and shortening the construction period.

为实现上述目的,本发明提供一种组合式现浇箱梁支架系统,其特征在于:在桥梁的每个中桥墩上安装有上抱箍和下抱箍,上抱箍和下抱箍的牛腿间设有支撑杆,靠近桥梁每个边墩分别设一钢管立柱,所述钢管立柱的底部支撑在地面混凝土基础上,钢管立柱的顶部与所述上抱箍的顶部标高一致;横桥向在中墩上的上抱箍顶部,以及靠近边墩的钢管立柱顶部分别搭设一承重横梁,顺桥向在每跨的两承重横梁顶部搭设贝雷纵梁,在所述贝雷纵梁上横桥向每隔一定间距搭设有一根工字钢分配梁,所述分配梁上安装有满堂支架,满堂支架的每根竖杆下端支撑在工字钢分配梁的上翼缘板上,满堂支架顶部安装有现浇箱梁模板系统。In order to achieve the above purpose, the present invention provides a combined cast-in-place box girder support system, which is characterized in that: an upper hoop and a lower hoop are installed on each middle pier of the bridge, and the cows of the upper hoop and the lower hoop are installed. There are support rods between the legs, and a steel pipe column is set near each side pier of the bridge. The bottom of the steel pipe column is supported on the ground concrete foundation, and the top of the steel pipe column is at the same elevation as the top of the upper hoop; A load-bearing beam is set up on the top of the upper hoop on the middle pier and on the top of the steel pipe column close to the side pier, and a Bailey longitudinal beam is set up on the top of the two load-bearing beams of each span along the bridge direction. The bridge is provided with an I-beam distribution beam at a certain interval, and a full hall bracket is installed on the distribution beam. The lower end of each vertical rod of the full hall bracket is supported on the upper flange plate of the I-beam distribution beam, and the top of the full hall bracket is supported. A cast-in-place box girder formwork system is installed.

采用上述组合式现浇箱梁支架系统进行施工的方法,其特征在于,包括如下步骤:The method of using the above-mentioned combined cast-in-place box girder support system for construction is characterized in that, comprising the following steps:

(1)根据桥墩尺寸制备抱箍、承重横梁、分配梁、钢管立柱;在地面将贝雷纵梁拼装成整体,并将加强弦杆通过配套螺栓固定在贝雷纵梁下弦杆上;(1) Prepare the hoop, load-bearing beam, distribution beam, and steel pipe column according to the size of the bridge pier; assemble the Bailey longitudinal beam into a whole on the ground, and fix the reinforcing chord on the lower chord of the Bailey longitudinal beam through matching bolts;

(2)利用起重设备将上抱箍和下抱箍按设计位置安装固定在中跨墩柱上,先安装下抱箍,再安装上抱箍;(2) Use lifting equipment to install and fix the upper hoop and the lower hoop on the mid-span pier column according to the design position, install the lower hoop first, and then install the upper hoop;

(3)在边墩底部一侧施工混凝土扩大基础,待混凝土强度达到规范要求后,利用起重设备将钢管立柱吊放在边墩扩大基础上,并安装相应加固构配件;(3) Construct the concrete expansion foundation on the bottom side of the side pier. After the concrete strength reaches the specification requirements, use the lifting equipment to hoist the steel pipe column on the side pier expansion foundation, and install the corresponding reinforcing structural accessories;

(4)横桥向中墩上抱箍上安装桁架式承重横梁,在上下抱箍的牛腿间安装支撑杆,将桁架式承重横梁的下弦杆限定在支撑杆和墩身外壁之间;(4) A truss-type load-bearing beam is installed on the upper hoop of the middle pier of the transverse bridge, and a support rod is installed between the corbels of the upper and lower hoop, and the lower chord of the truss-type load-bearing beam is limited between the support rod and the outer wall of the pier body;

(5)利用起重设备将贝雷纵梁顺桥向吊放在每跨的承重横梁上,并安装相应加固构配件;(5) Use lifting equipment to hoist the Bailey longitudinal beams along the bridge on the load-bearing beams of each span, and install corresponding reinforcement components;

(6)在贝雷纵梁上按设计要求铺设型钢分配梁,并安装相应加固构配件;(6) Lay profiled steel distribution beams on the Bailey longitudinal beams according to the design requirements, and install corresponding reinforcement components;

(7)在型钢分配梁上搭设满堂支架;(7) A full hall support is erected on the profile steel distribution beam;

(8)在满堂支架上按设计要求搭设模板系统;(8) Set up a formwork system on the full hall support according to the design requirements;

(9)支架经预压符合规范要求后,进行现浇箱梁施工;中墩处两侧混凝土浇筑时,应控制两侧不平衡重量不超过墩柱自身承载能力;(9) After the preloading of the support meets the requirements of the specification, the cast-in-place box girder construction shall be carried out; when the concrete on both sides of the middle pier is poured, the unbalanced weight on both sides shall be controlled so as not to exceed the bearing capacity of the pier column itself;

(10)待现浇箱梁的混凝土强度达到规范要求或预应力张拉完成后,拆除整个支架。(10) After the concrete strength of the cast-in-place box girder reaches the specification requirements or the prestressed tension is completed, the entire support is removed.

本发明与现有技术相比,有益效果体现在以下几方面:Compared with the prior art, the present invention has beneficial effects in the following aspects:

(1)经济性:若采用钢管支架或满堂支架施工,搭设单跨支架所使用的钢管和型钢材料约为40t,投入的人工、机械费用高,同时还需增加地基加固处理的费用;且随着桥墩高度的增加,消耗的钢材数量及施工费用将进一步增加;本发明单跨所需材料主要是8个重量约2t的抱箍,节省了大量的临时材料与地基处理费用。(1) Economy: If steel pipe supports or full-house supports are used for construction, the steel pipes and section steel materials used for erecting single-span supports are about 40t, and the labor and machinery costs are high, and the cost of foundation reinforcement treatment needs to be increased at the same time; As the height of the bridge pier increases, the amount of steel consumed and the construction cost will further increase; the materials required for a single span of the present invention are mainly 8 hoops with a weight of about 2t, which saves a lot of temporary materials and foundation treatment costs.

(2)施工工期:钢管支架或满堂支架施工需进行地基处理、钢管立柱地面加工、平联高空焊接等工序,搭设的构件较多,施工工期长,本发明则很好的避免了上述问题,可大大节省施工时间。(2) Construction period: the construction of steel pipe supports or full house supports needs to carry out processes such as foundation treatment, steel pipe column ground processing, parallel high-altitude welding, etc., there are many components erected, and the construction period is long, and the present invention avoids the above-mentioned problems well, Can greatly save construction time.

(3)施工安全及质量:在山区地形条件复杂、地基处理难度大、墩柱较高等情况下,采用钢管支架或满堂支架施工,地基处理难度大,质量难以把控;吊装高度高,高空作业量大,支架安拆作业安全风险大;本发明施工工艺简单,质量容易控制,施工难度低,安全风险小。(3) Construction safety and quality: In the case of complex terrain conditions in mountainous areas, difficult foundation treatment, and high piers and columns, steel pipe supports or full hall supports are used for construction, which is difficult to deal with the foundation and difficult to control the quality; high hoisting height, high-altitude operation The quantity is large, and the safety risk of the bracket installation and dismantling operation is large; the invention has simple construction technology, easy quality control, low construction difficulty and low safety risk.

附图说明Description of drawings

图1是本发明的一种实施例的顺桥向结构示意图;1 is a schematic diagram of a structure along the bridge direction according to an embodiment of the present invention;

图2是本发明在中墩处的横桥向结构示意图;Fig. 2 is the cross-bridge structural schematic diagram of the present invention at the middle pier;

图3是本发明在边墩处的横桥向结构示意图。FIG. 3 is a schematic diagram of the transverse bridge structure at the side pier of the present invention.

具体实施方式Detailed ways

如图1、图2、图3所示,本发明提供的一种组合式现浇箱梁支架系统,在桥梁的每个中跨桥墩1上安装有上抱箍3和下抱箍4,每个抱箍包括两个半圆形的抱箍板,抱箍板两侧设有连接板,两抱箍板对扣在墩身上,两抱箍板的连接板间通过高强螺栓连接,两抱箍板与墩身抱紧固定,两抱箍板的连接板组合成抱箍牛腿;上抱箍2和下抱箍3的牛腿间设有支撑杆5,支撑杆5的上下端分别与上抱箍的牛腿底部和下抱箍的牛腿顶部顶紧;靠近桥梁每个边墩2分别设一钢管立柱6,所述钢管立柱6的底部支撑在地面混凝土基础7上,钢管立柱的顶部与所述上抱箍3的顶部标高一致;横桥向在中墩上的上抱箍3顶部,以及靠近边墩的钢管立柱6顶部分别搭设一承重横梁8,顺桥向在桥梁每跨的两承重横梁8顶部搭设贝雷纵梁9,在所述贝雷纵梁9上横桥向每隔一定间距搭设有一根工字钢分配梁10,工字钢分配梁采用常规I20a型钢,分配梁10上安装有满堂支架11,满堂支架11的每根竖杆下端支撑在工字钢分配梁的上翼缘板上,满堂支架10顶部安装有现浇箱梁模板系统12。As shown in Figure 1, Figure 2, Figure 3, a combined cast-in-place box girder support system provided by the present invention is provided with an upper hoop 3 and a lower hoop 4 on each mid-span pier 1 of the bridge. Each hoop includes two semi-circular hoop plates. There are connecting plates on both sides of the hoop plates. The two hoop plates are fastened to the pier. The connecting plates of the two hoop plates are connected by high-strength bolts. The plate and the pier body are tightly fixed, and the connecting plates of the two hoop plates are combined to form a hoop corbel; a support rod 5 is arranged between the corbels of the upper hoop 2 and the lower hoop 3, and the upper and lower ends of the support rod 5 are respectively connected with the upper and lower ends of the hoop. The bottom of the corbel of the hoop and the top of the corbel of the lower hoop are tight; close to each side pier 2 of the bridge, a steel pipe column 6 is respectively set, and the bottom of the steel pipe column 6 is supported on the ground concrete foundation 7, and the top of the steel pipe column Consistent with the top elevation of the upper hoop 3; the top of the upper hoop 3 on the middle pier and the top of the steel pipe column 6 close to the side pier are respectively set up with a load-bearing beam 8 along the bridge direction at the top of each span of the bridge. The top of the two load-bearing beams 8 is erected with a Bailey longitudinal beam 9, and on the Bailey longitudinal beam 9, an I-beam distribution beam 10 is erected at a certain interval in the transverse bridge direction. The I-beam distribution beam adopts conventional I20a steel, and the distribution beam A full house bracket 11 is installed on the full house bracket 10 , the lower end of each vertical rod of the full house bracket 11 is supported on the upper flange plate of the I-beam distribution beam, and a cast-in-place box girder formwork system 12 is installed on the top of the full house bracket 10 .

满堂支架采用碗扣或盘扣结构均可,用以调整支架的纵、横坡,以保证梁体线形满足要求。The full house bracket can be of bowl buckle or disc buckle structure, which can be used to adjust the vertical and horizontal slope of the bracket to ensure that the beam shape meets the requirements.

具体实施时,上抱箍3上搭设的承重横梁7可采用桁架式承结构,其上弦杆支撑在上抱箍顶部,下弦杆位于上下抱箍间的连接杆和桥墩外壁之间,上弦杆和下弦杆间采用斜撑焊接;钢管立柱6顶部搭设的承重横梁7可采用单杠式承重梁,其规格型号与上抱箍上搭设的桁架结构承重梁的上弦杆一致。During specific implementation, the load-bearing beam 7 erected on the upper hoop 3 can adopt a truss-type bearing structure, the upper chord is supported on the top of the upper hoop, the lower chord is located between the connecting rod between the upper and lower hoop and the outer wall of the pier, the upper chord and Diagonal bracing is adopted between the lower chords; the load-bearing beam 7 erected on the top of the steel pipe column 6 can be a horizontal bar-type load-bearing beam, and its specification and model are consistent with the upper chord of the truss structure load-bearing beam erected on the upper hoop.

采用上述组合式现浇箱梁支架系统进行浇箱梁施工,具体方法如下:The above-mentioned combined cast-in-place box girder support system is used for the construction of the cast box girder, and the specific method is as follows:

(1)根据桥墩尺寸制备抱箍、承重横梁、分配梁、钢管立柱;在地面将贝雷纵梁拼装成整体,并将加强弦杆通过配套螺栓固定在贝雷纵梁下弦杆上;(1) Prepare the hoop, load-bearing beam, distribution beam, and steel pipe column according to the size of the bridge pier; assemble the Bailey longitudinal beam into a whole on the ground, and fix the reinforcing chord on the lower chord of the Bailey longitudinal beam through matching bolts;

(2)利用起重设备将上抱箍和下抱箍按设计位置安装固定在中跨墩柱上,先安装下抱箍,再安装上抱箍;(2) Use lifting equipment to install and fix the upper hoop and the lower hoop on the mid-span pier column according to the design position, install the lower hoop first, and then install the upper hoop;

(3)在边墩底部一侧施工混凝土扩大基础,待混凝土强度达到规范要求后,利用起重设备将钢管立柱吊放在边墩扩大基础上,并安装相应加固构配件;(3) Construct the concrete expansion foundation on the bottom side of the side pier. After the concrete strength reaches the specification requirements, use the lifting equipment to hoist the steel pipe column on the side pier expansion foundation, and install the corresponding reinforcing structural accessories;

(4)横桥向中墩上抱箍上安装桁架式承重横梁,在上下抱箍的牛腿间安装支撑杆,将桁架式承重横梁的下弦杆限定在支撑杆和墩身外壁之间;(4) A truss-type load-bearing beam is installed on the upper hoop of the middle pier of the transverse bridge, and a support rod is installed between the corbels of the upper and lower hoop, and the lower chord of the truss-type load-bearing beam is limited between the support rod and the outer wall of the pier body;

(5)利用起重设备将贝雷纵梁顺桥向吊放在每跨的承重横梁上,并安装相应加固构配件;(5) Use lifting equipment to hoist the Bailey longitudinal beams along the bridge on the load-bearing beams of each span, and install corresponding reinforcement components;

(6)在贝雷纵梁上按设计要求铺设型钢分配梁,并安装相应加固构配件;(6) Lay profiled steel distribution beams on the Bailey longitudinal beams according to the design requirements, and install corresponding reinforcement components;

(7)在型钢分配梁上搭设满堂支架;(7) A full hall support is erected on the profile steel distribution beam;

(8)在满堂支架上按设计要求搭设模板系统;(8) Set up a formwork system on the full hall support according to the design requirements;

(9)支架经预压符合规范要求后,进行现浇箱梁施工;中墩处两侧混凝土浇筑时,应控制两侧不平衡重量不超过墩柱自身承载能力;(9) After the preloading of the support meets the requirements of the specification, the cast-in-place box girder construction shall be carried out; when the concrete on both sides of the middle pier is poured, the unbalanced weight on both sides shall be controlled so as not to exceed the bearing capacity of the pier column itself;

(10)待现浇箱梁的混凝土强度达到规范要求或预应力张拉完成后,拆除整个支架。(10) After the concrete strength of the cast-in-place box girder reaches the specification requirements or the prestressed tension is completed, the entire support is removed.

Claims (3)

1.一种组合式现浇箱梁支架系统,其特征在于:在桥梁的每个中桥墩上安装有上抱箍和下抱箍,上抱箍和下抱箍的牛腿间设有支撑杆,靠近桥梁每个边墩分别设一钢管立柱,所述钢管立柱的底部支撑在地面混凝土基础上,钢管立柱的顶部与所述上抱箍的顶部标高一致;横桥向在中墩上的上抱箍顶部,以及靠近边墩的钢管立柱顶部分别搭设一承重横梁,顺桥向在每跨的两承重横梁顶部搭设贝雷纵梁,在所述贝雷纵梁上横桥向每隔一定间距搭设有一根工字钢分配梁,所述分配梁上安装有满堂支架,满堂支架的每根竖杆下端支撑在工字钢分配梁的上翼缘板上,满堂支架顶部安装有现浇箱梁模板系统。1. a combined cast-in-place box girder support system is characterized in that: an upper hoop and a lower hoop are installed on each middle pier of the bridge, and a support rod is provided between the corbels of the upper hoop and the lower hoop , a steel pipe column is set near each side pier of the bridge, the bottom of the steel pipe column is supported on the ground concrete foundation, and the top of the steel pipe column is at the same elevation as the top of the upper hoop; A load-bearing beam is set up on the top of the hoop and on the top of the steel pipe column close to the side pier, and Bailey longitudinal beams are erected on the top of the two load-bearing beams of each span along the bridge direction, and on the Bailey longitudinal beams, the horizontal bridge direction is at regular intervals. An I-beam distribution beam is set up on which a full house support is installed, the lower end of each vertical rod of the full house support is supported on the upper flange plate of the I-beam distribution beam, and a cast-in-place box beam is installed on the top of the full house support. Template system. 2.根据权利要求1所述的组合式现浇箱梁支架系统,其特征在于:上抱箍上搭设的承重横梁为桁架式结构,其上弦杆支撑在上抱箍顶部,下弦杆位于上下抱箍间的支撑杆和桥墩外壁之间,上弦杆和下弦杆间采用斜撑焊接;钢管立柱顶部搭设的承重横梁为单杆结构,其规格型号与上抱箍上搭设的桁架式承重梁的上弦杆一致。2. The combined cast-in-situ box girder support system according to claim 1 is characterized in that: the load-bearing beam erected on the upper hoop is a truss structure, the upper chord is supported on the top of the upper hoop, and the lower chord is located on the upper and lower hoop. Between the support rod between the hoops and the outer wall of the pier, the upper chord and the lower chord are welded by diagonal bracing; the load-bearing beam erected on the top of the steel pipe column is a single-bar structure, and its specification and model are the same as the upper chord of the truss-type load-bearing beam erected on the upper hoop. Rods are consistent. 3.一种采用权利要求1所述的组合式现浇箱梁支架系统进行施工的方法,其特征在于包括如下步骤:3. a method that adopts the combined cast-in-place box girder support system of claim 1 to carry out construction, is characterized in that comprising the steps: (1)根据桥墩尺寸制备抱箍、承重横梁、分配梁、钢管立柱;在地面将贝雷纵梁拼装成整体,并将加强弦杆通过配套螺栓固定在贝雷纵梁下弦杆上;(1) Prepare the hoop, load-bearing beam, distribution beam, and steel pipe column according to the size of the bridge pier; assemble the Bailey longitudinal beam into a whole on the ground, and fix the reinforcing chord on the lower chord of the Bailey longitudinal beam through matching bolts; (2)利用起重设备将上抱箍和下抱箍按设计位置安装固定在中跨墩柱上,先安装下抱箍,再安装上抱箍;(2) Use lifting equipment to install and fix the upper hoop and the lower hoop on the mid-span pier column according to the design position, install the lower hoop first, and then install the upper hoop; (3)在边墩底部一侧施工混凝土扩大基础,待混凝土强度达到规范要求后,利用起重设备将钢管立柱吊放在边墩扩大基础上,并安装相应加固构配件;(3) Construct the concrete expansion foundation on the bottom side of the side pier. After the concrete strength reaches the specification requirements, use the lifting equipment to hoist the steel pipe column on the side pier expansion foundation, and install the corresponding reinforcing structural accessories; (4)横桥向中墩上抱箍上安装桁架式承重横梁,在上下抱箍的牛腿间安装支撑杆,将桁架式承重横梁的下弦杆限定在支撑杆和墩身外壁之间;(4) A truss-type load-bearing beam is installed on the upper hoop of the middle pier of the transverse bridge, and a support rod is installed between the corbels of the upper and lower hoop, and the lower chord of the truss-type load-bearing beam is limited between the support rod and the outer wall of the pier body; (5)利用起重设备将贝雷纵梁顺桥向吊放在每跨的承重横梁上,并安装相应加固构配件;(5) Use lifting equipment to hoist the Bailey longitudinal beams along the bridge on the load-bearing beams of each span, and install corresponding reinforcement components; (6)在贝雷纵梁上按设计要求铺设型钢分配梁,并安装相应加固构配件;(6) Lay profiled steel distribution beams on the Bailey longitudinal beams according to the design requirements, and install corresponding reinforcement components; (7)在型钢分配梁上搭设满堂支架;(7) A full hall support is erected on the profile steel distribution beam; (8)在满堂支架上按设计要求搭设模板系统;(8) Set up a formwork system on the full hall support according to the design requirements; (9)支架经预压符合规范要求后,进行现浇箱梁施工;中墩处两侧混凝土浇筑时,应控制两侧不平衡重量不超过墩柱自身承载能力;(9) After the preloading of the support meets the requirements of the specification, the cast-in-place box girder construction shall be carried out; when the concrete on both sides of the middle pier is poured, the unbalanced weight on both sides shall be controlled so as not to exceed the bearing capacity of the pier column itself; (10)待现浇箱梁的混凝土强度达到规范要求或预应力张拉完成后,拆除整个支架。(10) After the concrete strength of the cast-in-place box girder reaches the specification requirements or the prestressed tension is completed, the entire support is removed.
CN202010445207.5A 2020-05-23 2020-05-23 Combined cast-in-place box girder support system and construction method Pending CN111663449A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010445207.5A CN111663449A (en) 2020-05-23 2020-05-23 Combined cast-in-place box girder support system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010445207.5A CN111663449A (en) 2020-05-23 2020-05-23 Combined cast-in-place box girder support system and construction method

Publications (1)

Publication Number Publication Date
CN111663449A true CN111663449A (en) 2020-09-15

Family

ID=72384419

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010445207.5A Pending CN111663449A (en) 2020-05-23 2020-05-23 Combined cast-in-place box girder support system and construction method

Country Status (1)

Country Link
CN (1) CN111663449A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112411386A (en) * 2020-11-26 2021-02-26 中铁三局集团有限公司 Method for erecting and dismantling continuous beam No. 0 block reinforced concrete-filled steel tube support
CN112411343A (en) * 2020-11-30 2021-02-26 中交路桥建设有限公司 Cast-in-situ box girder composite support and erection method for ultra-high and secure-pass curve in mountainous areas
CN112726415A (en) * 2021-01-05 2021-04-30 中交路桥建设有限公司 Steel box girder up-and-down crossing construction support structure and construction method
CN112779864A (en) * 2020-12-31 2021-05-11 中交二公局第六工程有限公司 Combined cast-in-place box girder support structure and construction method thereof
CN112900273A (en) * 2021-01-20 2021-06-04 浙江交工集团股份有限公司 Non-contact platform for erecting cast-in-place beam support on separated old bridge and construction method thereof
CN113957795A (en) * 2021-09-18 2022-01-21 中铁大桥局集团有限公司 A method and system for making beams by large-span beam-type bracket method
CN115323894A (en) * 2022-08-09 2022-11-11 中国建筑第二工程局有限公司 Elevated U-turn test platform supporting and connecting structure and construction method thereof
CN115538309A (en) * 2022-08-22 2022-12-30 中铁七局集团有限公司 A shared support and construction method for steel girder assembly and box girder cast-in-place
CN115748496A (en) * 2022-12-06 2023-03-07 中交第一航务工程局有限公司 Cast-in-place box girder assembled support system and mounting and dismounting method thereof
CN115821784A (en) * 2022-12-19 2023-03-21 中交第一航务工程局有限公司 Cantilever bent cap construction system and construction method
CN115897410A (en) * 2022-12-22 2023-04-04 中建四局贵州投资建设有限公司 Large-scale equal-section cast-in-place box girder fast-moving formwork system and construction method
CN116289593A (en) * 2023-03-20 2023-06-23 中铁六局集团有限公司 A new composite support structure and construction method of small and medium-sized curved cast-in-place box girders
CN116289608A (en) * 2023-04-01 2023-06-23 中铁六局集团路桥建设有限公司 A construction method of beam-column cast-in-place beam support in narrow area
CN117248461A (en) * 2023-10-31 2023-12-19 中铁十七局集团第四工程有限公司 Cast-in-place beam supports for side spans of cable-stayed bridges and how to use them
CN117328340A (en) * 2023-11-17 2024-01-02 四川嘉阜泰建筑工程有限公司 A support and bridge structure with adjustable cross slope and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202482767U (en) * 2011-12-29 2012-10-10 中国建筑第四工程局有限公司 Steel tube bailey beam column type support
CN106120559A (en) * 2016-06-14 2016-11-16 江苏燕宁建设工程有限公司 A kind of bridge limited bracket construction method and bridge
WO2017045223A1 (en) * 2015-09-18 2017-03-23 河海大学 Prefabricated pier column member with steel-concrete composite structure
CN106638336A (en) * 2016-10-21 2017-05-10 中国水利水电第八工程局有限公司 Over-line continuous beam removing method and support for removing
CN106930191A (en) * 2017-04-21 2017-07-07 中交公局第工程有限公司 A kind of cast-in-situ box girder hoop bracket system and its construction method
CN108842628A (en) * 2018-07-09 2018-11-20 广西长长路桥建设有限公司 In conjunction with the construction method of anchor ear and the non-floor-bracket of Bailey beam cast-in-situ box girder
CN208748534U (en) * 2018-08-31 2019-04-16 中铁二十四局集团安徽工程有限公司 A kind of concrete box girder cast-in-place construction anchor ear support frame
CN210395119U (en) * 2019-07-18 2020-04-24 中国水利水电第八工程局有限公司 Face novel bridge beam supports frame that combines forever
CN212612004U (en) * 2020-05-23 2021-02-26 中交路桥建设有限公司 Modular cast-in-place box girder braced system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202482767U (en) * 2011-12-29 2012-10-10 中国建筑第四工程局有限公司 Steel tube bailey beam column type support
WO2017045223A1 (en) * 2015-09-18 2017-03-23 河海大学 Prefabricated pier column member with steel-concrete composite structure
CN106120559A (en) * 2016-06-14 2016-11-16 江苏燕宁建设工程有限公司 A kind of bridge limited bracket construction method and bridge
CN106638336A (en) * 2016-10-21 2017-05-10 中国水利水电第八工程局有限公司 Over-line continuous beam removing method and support for removing
CN106930191A (en) * 2017-04-21 2017-07-07 中交公局第工程有限公司 A kind of cast-in-situ box girder hoop bracket system and its construction method
CN108842628A (en) * 2018-07-09 2018-11-20 广西长长路桥建设有限公司 In conjunction with the construction method of anchor ear and the non-floor-bracket of Bailey beam cast-in-situ box girder
CN208748534U (en) * 2018-08-31 2019-04-16 中铁二十四局集团安徽工程有限公司 A kind of concrete box girder cast-in-place construction anchor ear support frame
CN210395119U (en) * 2019-07-18 2020-04-24 中国水利水电第八工程局有限公司 Face novel bridge beam supports frame that combines forever
CN212612004U (en) * 2020-05-23 2021-02-26 中交路桥建设有限公司 Modular cast-in-place box girder braced system

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112411386A (en) * 2020-11-26 2021-02-26 中铁三局集团有限公司 Method for erecting and dismantling continuous beam No. 0 block reinforced concrete-filled steel tube support
CN112411343A (en) * 2020-11-30 2021-02-26 中交路桥建设有限公司 Cast-in-situ box girder composite support and erection method for ultra-high and secure-pass curve in mountainous areas
CN112779864A (en) * 2020-12-31 2021-05-11 中交二公局第六工程有限公司 Combined cast-in-place box girder support structure and construction method thereof
CN112726415A (en) * 2021-01-05 2021-04-30 中交路桥建设有限公司 Steel box girder up-and-down crossing construction support structure and construction method
CN112900273A (en) * 2021-01-20 2021-06-04 浙江交工集团股份有限公司 Non-contact platform for erecting cast-in-place beam support on separated old bridge and construction method thereof
CN112900273B (en) * 2021-01-20 2022-06-10 浙江交工集团股份有限公司 Non-contact platform for erecting cast-in-place beam support on separated old bridge and construction method thereof
CN113957795A (en) * 2021-09-18 2022-01-21 中铁大桥局集团有限公司 A method and system for making beams by large-span beam-type bracket method
CN115323894B (en) * 2022-08-09 2024-05-14 中国建筑第二工程局有限公司 Overhead turning test platform supporting and connecting structure and construction method thereof
CN115323894A (en) * 2022-08-09 2022-11-11 中国建筑第二工程局有限公司 Elevated U-turn test platform supporting and connecting structure and construction method thereof
CN115538309A (en) * 2022-08-22 2022-12-30 中铁七局集团有限公司 A shared support and construction method for steel girder assembly and box girder cast-in-place
CN115748496A (en) * 2022-12-06 2023-03-07 中交第一航务工程局有限公司 Cast-in-place box girder assembled support system and mounting and dismounting method thereof
CN115821784A (en) * 2022-12-19 2023-03-21 中交第一航务工程局有限公司 Cantilever bent cap construction system and construction method
CN115897410A (en) * 2022-12-22 2023-04-04 中建四局贵州投资建设有限公司 Large-scale equal-section cast-in-place box girder fast-moving formwork system and construction method
CN116289593A (en) * 2023-03-20 2023-06-23 中铁六局集团有限公司 A new composite support structure and construction method of small and medium-sized curved cast-in-place box girders
CN116289608A (en) * 2023-04-01 2023-06-23 中铁六局集团路桥建设有限公司 A construction method of beam-column cast-in-place beam support in narrow area
CN117248461A (en) * 2023-10-31 2023-12-19 中铁十七局集团第四工程有限公司 Cast-in-place beam supports for side spans of cable-stayed bridges and how to use them
CN117328340A (en) * 2023-11-17 2024-01-02 四川嘉阜泰建筑工程有限公司 A support and bridge structure with adjustable cross slope and construction method thereof

Similar Documents

Publication Publication Date Title
CN111663449A (en) Combined cast-in-place box girder support system and construction method
CN100567644C (en) A truss-type cable-arch bridge structure and its construction method
CN110004832B (en) Large-span cantilever truss type bent cap bracket system and construction method
CN111364350A (en) A light-weight steel-concrete composite cover beam with quick installation of large cantilever arm
CN104631343A (en) Self-travelling diamond-shaped pin-connected truss-type form traveler structure and form traveler travelling and constructing method
CN211947993U (en) Support for large-span cast-in-situ bridge construction
CN211228066U (en) A connection structure of prefabricated steel pier and foundation
CN115162358B (en) A prefabricated steel-concrete composite support system and construction method for foundation pit engineering
CN103410102A (en) H-shaped double column pier wide-bridge-surface cantilever temporary consolidation structure and construction method thereof
CN103469735B (en) The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation
CN113914223A (en) High-pier arc-shaped upper cross beam light-weight bracket system and mounting method thereof
CN210066504U (en) Large-span cantilever truss type bent cap support system
CN109881587B (en) Integral installation method of beam support on main tower in strong wind environment
CN103243638B (en) Bridge space radioactive concrete-filled steel tube bridge pier and construction method thereof
CN212925807U (en) Cast-in-place continuous box girder side span straightway template support system
CN213204915U (en) Overweight overhanging suspended component supporting system of super high-rise residential conversion layer
CN211772868U (en) Pier temporary consolidation device in large-span continuous beam
CN222990595U (en) Multifunctional portal for suspension bridge construction
CN109972512A (en) A kind of cast-in-situ construction method of profiled sheet-concrete combined bridge deck
CN211772934U (en) Zero number block support system of bridge
CN209816632U (en) Arch foot structure for special-shaped space arch bridge
CN207277211U (en) Large steel pipe truss for bent cap cast-in-place construction
CN212612004U (en) Modular cast-in-place box girder braced system
CN211922324U (en) Prefabricated bent cap wet joint construction hangs mould system
CN115748469A (en) Anti-overturn support platform for bridge construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200915