CN111666433A - Railway four-electrical engineering BIM model Web lightweight method - Google Patents
Railway four-electrical engineering BIM model Web lightweight method Download PDFInfo
- Publication number
- CN111666433A CN111666433A CN202010364529.7A CN202010364529A CN111666433A CN 111666433 A CN111666433 A CN 111666433A CN 202010364529 A CN202010364529 A CN 202010364529A CN 111666433 A CN111666433 A CN 111666433A
- Authority
- CN
- China
- Prior art keywords
- model
- railway
- lightweight
- data
- web
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/50—Information retrieval; Database structures therefor; File system structures therefor of still image data
- G06F16/51—Indexing; Data structures therefor; Storage structures
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/50—Information retrieval; Database structures therefor; File system structures therefor of still image data
- G06F16/54—Browsing; Visualisation therefor
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
- G06T17/10—Constructive solid geometry [CSG] using solid primitives, e.g. cylinders, cubes
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Geometry (AREA)
- Software Systems (AREA)
- Data Mining & Analysis (AREA)
- Databases & Information Systems (AREA)
- General Engineering & Computer Science (AREA)
- Computer Graphics (AREA)
- Toys (AREA)
Abstract
The invention relates to a railway four-electrical engineering BIM model Web lightweight method, which comprises the following steps: establishing a standard unit library based on a railway four-electricity BIM model, and respectively defining model attributes and establishing a corresponding unit model library; carrying out total building of a railway four-electrical engineering BIM model on each professional standard unit model; after classification, different lightweight optimization schemes are used according to different classes to generate SIM data files; js technology is used for building a Web lightweight platform, SIM data files are read, railway four-electric engineering models are displayed on Web, and detection of key characteristic information of railway four-electric engineering models on the Web lightweight platform is achieved. According to the invention, the railway four-electricity BIM model file is subjected to lightweight processing through the BIM lightweight plug-in, geometric information and attribute information are simultaneously extracted from the model data in the processing process, and then the displayed content is deeply optimized through the instantiation technology, so that the loading efficiency and the smoothness are ensured.
Description
Technical Field
The invention belongs to the technical field of rail transit engineering information management, and particularly relates to a BIM (building information modeling) model Web lightweight method for railway four-electric engineering.
Background
The rail transit is a complex system integrating multiple specialties and multiple kinds, generally comprises a rail route, stations, vehicles, maintenance and repair bases, power supply and transformation, communication signals, a command control center and the like, and relates to multiple specialties such as lines, stations, bridges, tunnels, locomotives, vehicles, power supply, communication, signals, electromechanical equipment, fire fighting systems and the like. The four-electric engineering comprises the specialties of communication, signals, electric power, electrification and the like, and mainly takes equipment as main equipment. These devices are mainly installed on the line, commonly called trackside devices, or in dedicated machine rooms and various operating rooms. The technical characteristics of the construction of the track traffic four-electric engineering are as follows: the equipment is distributed on a long and narrow line, and dozens of kilometers are distributed in a few lines, and hundreds of kilometers are distributed in a more line; the multiple specialties relate to dozens of specialties, the association degree of each speciality is high, and the professional interface is complex; the four-electric professional equipment is various in types, and is flexible and loose to lay; the building area of the house special for the four-electric engineering equipment is large, the collection of each internal professional indoor building is complex, and the equipment combination is complex and large in quantity.
The construction of the four-electric engineering needs the multi-department and multi-unit cooperative work of design, construction, factory and operation, and the 'cooperation' realized by relying on manual work through network, telephone and paper file transmission can not ensure good engineering quality when the rapid construction is carried out.
The BIM (building information model) technology has the characteristics of visualization, harmony, simulation and optimization, can improve the production efficiency of four-electric engineering construction, improve the building quality, shorten the construction period, reduce the construction cost and the like, and realizes high-quality collaboration.
However, the characteristics of the four-electrical engineering cause the existing quantity of the BIM model of the four-electrical engineering to be large; long and narrow lines need to be displayed in a segmented and fragmented manner; the quantity of indoor equipment is huge, the structure is complicated, and the blocking is serious when the BIM model is checked, so that the lightweight platform developed in the society cannot process the problem.
In addition, the lack of hands for detecting, evaluating and authenticating railway four-electric BIM technology and results
In the section, the rationality and the usability of the research and application results of the BIM technology of the four-electric engineering and even the rail transit engineering cannot be verified, and the benign development of the technology is greatly influenced.
In view of this, research on a light weight processing method for a rail transit four-electric engineering BIM model is urgently needed, so that the BIM technology is more fully applied to four-electric engineering construction, and the engineering construction quality is ensured.
Disclosure of Invention
The invention aims to provide a railway four-electric engineering BIM model Web lightweight method, which solves the problems of non-intuitive visualization and large size of a railway four-electric engineering BIM model and solves the intuitive expression of the railway four-electric engineering BIM model on a Web platform and the recognition and detection of the railway four-electric engineering BIM model on the Web platform.
The technical scheme adopted by the invention is as follows:
a railway four-electrical engineering BIM model Web lightweight method is characterized by comprising the following steps:
the method comprises the following steps:
step 1, establishing a standard unit library based on a railway four-electricity BIM model, and respectively performing model attribute definition on models of professional requirements of lines, stations, bridges, tunnels, communication and signals in a four-electricity engineering model and establishing a corresponding unit model library;
step 2, carrying out total building of a railway four-electric engineering BIM model on each professional standard unit model built in the step 1;
step 3, dividing the built railway four-electric-engineering BIM model in the step 2 into nine types, namely, a regional rail sleeper, a regional roadbed, a regional bridge, a regional tunnel, regional equipment, a station yard rail sleeper, station yard equipment, a station yard house and equipment in the station yard house;
step 4, carrying out respective lightweight processing on the four-electric railway engineering models divided into nine types in the step 3, using different lightweight optimization schemes according to different types, and storing lightweight data in an SIM format; storing the non-geometric information in the SIM format at the tail end of the data;
and 5, building a Web lightweight platform by using a three.js technology, reading the SIM data file generated in the step 4, and displaying the railway four-electric engineering model on the Web to realize the detection of the key characteristic information of the railway four-electric engineering model on the Web lightweight platform.
The step 1 specifically comprises the following steps:
step 1.1, determining the standard equipment specification, standard parameters, design logic elements, aggregation parameters, association parameters and constraint relations of each railway four-electric component;
and 1.2, setting the attribute of the model according to the professional requirements of the railway four-station system, and generating the model by using different insertion units and functional methods for generating the model.
The step 4 specifically comprises the following steps:
step 4.1, adopting an instant Instance lightweight technology for the inter-block rail sleeper, the inter-block equipment, the station rail sleeper, the station equipment and the station indoor equipment model: only light weight data of one model of the same models are taken, only corresponding rotation matrix parameters are taken for other same models, and a large number of same models are compressed into a group of 4 x 4 space transformation matrix arrays;
step 4.2, taking lightweight data for each of the regional roadbed, the regional bridge, the regional tunnel and the station building model;
step 4.3, the attribute data obtained from various BIM model data correspond to the entity ID of each individual model one by one, and the attribute data comprises type, size, name and length;
and 4.4, storing the lightweight data in an SIM format, wherein the geometric data structure is as follows: starting with s, writing the number of Instance instantiation devices after s, namely the number of s, and ending with se;
v represents a set of endpoints (vX coordinate, Y coordinate, Z coordinate);
f represents a triangular surface set (f point set ID);
m represents a color and material feature (m color RGB material ID);
i denotes the transformation matrix and attribute data of the device (i 4 x 4 transformation matrix attribute data);
finally, ending with ie;
and 4.5, storing non-geometric data including connection relation and topological relation.
The step 5 specifically comprises the following steps:
step 5.1, establishing a railway four-electrical engineering Web lightweight platform by using a three.js technology, reading SIM lightweight data, and displaying a railway four-electrical engineering model in the platform;
and 5.2, reading all connection and topological relation data from the SIM on the basis of the model attributes and the geometric data on the lightweight platform, and realizing the detection function of the key characteristic information of the railway four-electrical engineering model on the Web lightweight platform by taking a Three.
The invention has the following advantages:
according to the invention, geometric information and attribute information of the railway four-electricity BIM model file are separated through the BIM lightweight engine, then the graph part is subjected to lightweight processing, and then the graph part is connected in a database mode. Meanwhile, the displayed three-dimensional scene graph part and the data content are deeply optimized according to the data organization characteristics and the component type conditions of the BIM, and the loading efficiency and the loading fluency are ensured. The aim of ensuring that most of the current BIM model files can be smoothly displayed in a common notebook, a smart phone or a PAD is fulfilled on the premise of keeping the integrity of all information. Even for an ultra-large data model, the data model can be loaded and displayed smoothly on a common notebook computer at the same time, the attractive effect of display is ensured, and the management of a large scene and a large space is guaranteed.
The method is combined with the Three.js technology to construct the BIM lightweight Web platform, SIM data files are read on the platform, the BIM 3D model is reconstructed, the functions of the Three.js scene, the camera, the illumination, the rendering and the like are utilized to realize the display of a large number of railway four-electric engineering models, and the recognition and the detection of the models are realized by combining the professional characteristics of the four-electric engineering.
The invention provides a technical means for detecting, evaluating, authenticating and other institutions to check the compliance of the railway four-electricity BIM model (the compliance of BIM standard, availability and the like).
Drawings
FIG. 1 is a flow chart of the technical structure of the present invention.
Fig. 2 is a schematic diagram of a SIM lightweight format.
FIG. 3 is a schematic diagram of a BIM lightweight Web platform according to the present invention.
Detailed Description
The present invention will be described in detail with reference to specific embodiments.
The invention relates to a railway four-electric engineering BIM model Web lightweight method, which is used for carrying out lightweight processing and displaying on a rail traffic engineering information BIM model, is a detection technology for key characteristic information of a railway four-electric engineering model, and specifically comprises the following steps:
step 1, establishing a standard unit library based on a railway four-electric BIM model, and respectively defining model attributes of models with professional requirements such as lines, stations, bridges, tunnels, communication, signals and the like in a four-electric engineering model and establishing a corresponding unit model library.
And 2, carrying out total building of the BIM model of the railway four-electric engineering on each professional standard unit model built in the step 1. And (4) developing functions of the unit-free model, and realizing function generation, such as rails, interval roadbeds, interval bridges, interval tunnels and the like in the four-electric engineering.
And 3, dividing the built railway four-electric-engineering BIM model in the step 2 into nine types, namely, a regional rail sleeper, a regional roadbed, a regional bridge, a regional tunnel, regional equipment, a station yard rail sleeper, station yard equipment, a station yard house and equipment in the station yard house.
And 4, respectively carrying out light weight treatment on the four railway electrical engineering models divided into nine types in the step 3, using different light weight optimization schemes according to different types, and storing light weight data in an SIM format. The non-geometric information in the SIM format is stored at the very end.
And 5, building a Web lightweight platform by using a three.js technology, reading the SIM data file generated in the step 4, and displaying the railway four-electric engineering model on the Web to realize the detection of the key characteristic information of the railway four-electric engineering model on the Web lightweight platform.
The steps are as follows:
the step 1 specifically comprises the following steps:
step 1.1, determining the standard equipment specification, standard parameters, design logic elements, aggregation parameters, association parameters and constraint relations of each railway four-electric component;
and 1.2, setting the attribute of the model according to the professional requirements of the railway four-station system, and generating the model by using different insertion units and functional methods for generating the model.
The step 4 specifically comprises the following steps:
and 4.1, the models of the interval rail sleepers, the interval equipment, the station rail sleepers, the station equipment and the equipment in the station house have the characteristics of large quantity and identical geometric shapes of a large number of models. Adopting an instant Instance lightweight technology according to the characteristics: only light weight data of one model of the same models are taken, only corresponding rotation matrix parameters are taken for other same models, and a large number of same models are compressed into a group of 4 x 4 space transformation matrix arrays;
step 4.2, the interval roadbed, the interval bridge, the interval tunnel and the station house model have the characteristics of large volume and simple data structure, and because the geometric shapes of the models are different, light weight data are required to be acquired for each model;
and 4.3, according to the characteristics of the four-electrical engineering model, corresponding attribute data acquired from various BIM model data to each other according to the entity ID of each individual model, wherein the attribute data can comprise type/size/name/length and the like.
And 4.4, storing the lightweight data in an SIM format according to the characteristics of the four-electrical engineering model, wherein the geometric data structure is as follows: starting with s, written after s is the number of Instance instantiated devices (s number), ending with se;
v represents a set of endpoints (v X coordinate Y coordinate Z coordinate);
f represents a triangular surface set (f point set ID);
m represents a color and material feature (m color RGB material ID);
i denotes the transformation matrix and attribute data of the device (i 4 x 4 transformation matrix attribute data);
finally, end with ie.
Step 4.5, according to the characteristics of the four-electrical engineering model, besides geometric attribute data, a plurality of non-geometric data are required to be stored, such as cable connection relations among equipment, topological relations of grooves and the like, and the data structure is as follows:
connection relationship, L device ID cable ID device ID … … is written from the originating device to the terminating device.
Topological relation, T-trench ID (start, end) … … is written from the topological relation of the starting trench to the ending trench.
The step 5 specifically comprises the following steps:
and 5.1, establishing a railway four-electrical engineering Web lightweight platform by using a three.js technology, reading SIM lightweight data, and displaying a railway four-electrical engineering model in the platform.
And 5.2, reading all connection and topological relation data from the SIM on the basis of the model attributes and the geometric data on the lightweight platform, and realizing the detection function of the key characteristic information of the railway four-electrical engineering model on the Web lightweight platform by taking a Three.
The working principle of the invention is as follows:
the present invention provides an example lightweight technology (organizing): the multiple instances are very common rendering technologies, and the principle of the multiple instances is that only one piece of geometric data is stored for the same geometric object, rendering effects of multiple similar geometric objects in the same frame are obtained by respectively drawing for several times in a rendering pipeline and applying different geometric changes and material information each time. In practical terms, if many identical tables are to be drawn, we need only use one copy of the table's geometry data and then draw multiple passes, each to place the table in a different location. The current rendering pipeline completely puts and executes the instruction in a hardware pipeline, so that the memory overhead of a GPU and the calculation overhead of a CPU (mainly initiating a drawcall to use CPU resources) are greatly saved.
By utilizing the technical characteristics, only the patch lightweight data of one model of the same model is taken, only the corresponding rotation matrix parameters are taken for other same models, a large number of same models are compressed into a group of 4 x 4 space transformation matrix arrays, and the lightweight efficiency is improved.
The invention creates a light weight data format SIM, and light weight data is stored through the format SIM, and the format SIM has the characteristics of simple storage, clear structure and small data volume.
The invention is not limited to the examples, and any equivalent changes to the technical solution of the invention by a person skilled in the art after reading the description of the invention are covered by the claims of the invention.
Claims (4)
1. The railway four-electrical engineering BIM model Web lightweight method is characterized by comprising the following steps:
the method comprises the following steps:
step 1, establishing a standard unit library based on a railway four-electricity BIM model, and respectively performing model attribute definition on models of professional requirements of lines, stations, bridges, tunnels, communication and signals in a four-electricity engineering model and establishing a corresponding unit model library;
step 2, carrying out total building of a railway four-electric engineering BIM model on each professional standard unit model built in the step 1;
step 3, dividing the built railway four-electric-engineering BIM model in the step 2 into nine types, namely, a regional rail sleeper, a regional roadbed, a regional bridge, a regional tunnel, regional equipment, a station yard rail sleeper, station yard equipment, a station yard house and equipment in the station yard house;
step 4, carrying out respective lightweight processing on the four-electric railway engineering models divided into nine types in the step 3, using different lightweight optimization schemes according to different types, and storing lightweight data in an SIM format; storing the non-geometric information in the SIM format at the tail end of the data;
and 5, building a Web lightweight platform by using a three.js technology, reading the SIM data file generated in the step 4, and displaying the railway four-electric engineering model on the Web to realize the detection of the key characteristic information of the railway four-electric engineering model on the Web lightweight platform.
2. The railway four-electrical engineering BIM model Web lightweight method according to claim 1, characterized in that:
the step 1 specifically comprises the following steps:
step 1.1, determining the standard equipment specification, standard parameters, design logic elements, aggregation parameters, association parameters and constraint relations of each railway four-electric component;
and 1.2, setting the attribute of the model according to the professional requirements of the railway four-station system, and generating the model by using different insertion units and functional methods for generating the model.
3. The railway four-electrical engineering BIM model Web lightweight method according to claim 2, characterized in that:
the step 4 specifically comprises the following steps:
step 4.1, adopting an instant Instance lightweight technology for the inter-block rail sleeper, the inter-block equipment, the station rail sleeper, the station equipment and the station indoor equipment model: only light weight data of one model of the same models are taken, only corresponding rotation matrix parameters are taken for other same models, and a large number of same models are compressed into a group of 4 x 4 space transformation matrix arrays;
step 4.2, taking lightweight data for each of the regional roadbed, the regional bridge, the regional tunnel and the station building model;
step 4.3, the attribute data obtained from various BIM model data correspond to the entity ID of each individual model one by one, and the attribute data comprises type, size, name and length;
and 4.4, storing the lightweight data in an SIM format, wherein the geometric data structure is as follows: starting with s, writing the number of Instance instantiation devices after s, namely the number of s, and ending with se;
v represents a set of endpoints (v X coordinate Y coordinate Z coordinate);
f represents a triangular surface set (f point set ID);
m represents a color and material feature (m color RGB material ID);
i denotes the transformation matrix and attribute data of the device (i 4 x 4 transformation matrix attribute data);
finally, ending with ie;
and 4.5, storing non-geometric data including connection relation and topological relation.
4. The BIM model Web lightweight method for railway four-electric engineering according to claim 3, characterized in that:
the step 5 specifically comprises the following steps:
step 5.1, establishing a railway four-electrical engineering Web lightweight platform by using a three.js technology, reading SIM lightweight data, and displaying a railway four-electrical engineering model in the platform;
and 5.2, reading all connection and topological relation data from the SIM on the basis of the model attributes and the geometric data on the lightweight platform, and realizing the detection function of the key characteristic information of the railway four-electrical engineering model on the Web lightweight platform by taking a Three.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010364529.7A CN111666433B (en) | 2020-04-30 | 2020-04-30 | Railway four-electrical engineering BIM model Web lightweight method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010364529.7A CN111666433B (en) | 2020-04-30 | 2020-04-30 | Railway four-electrical engineering BIM model Web lightweight method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111666433A true CN111666433A (en) | 2020-09-15 |
CN111666433B CN111666433B (en) | 2023-03-17 |
Family
ID=72383087
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010364529.7A Active CN111666433B (en) | 2020-04-30 | 2020-04-30 | Railway four-electrical engineering BIM model Web lightweight method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111666433B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112417023A (en) * | 2020-12-04 | 2021-02-26 | 北京构力科技有限公司 | Method, apparatus, electronic device, storage medium, and program product for processing IFC file |
CN112634452A (en) * | 2020-12-31 | 2021-04-09 | 佳讯飞鸿(北京)智能科技研究院有限公司 | Railway BIM model lightweight method and device |
CN112989458A (en) * | 2021-02-22 | 2021-06-18 | 中铁二院工程集团有限责任公司 | Method for converting BIM (building information modeling) model into 3DTiles file |
CN115238345A (en) * | 2022-07-13 | 2022-10-25 | 上海方联技术服务有限公司 | BIM (building information modeling) model processing method and device, storage medium and electronic device |
CN116502321A (en) * | 2023-06-28 | 2023-07-28 | 中铁第一勘察设计院集团有限公司 | BIM forward design method and system for railway communication machine room |
CN116611149A (en) * | 2023-05-26 | 2023-08-18 | 中南大学 | Parameterized modeling method for high-precision railway fastener system |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6034455B1 (en) * | 2015-07-10 | 2016-11-30 | 東芝エレベータ株式会社 | BIM system and method |
CN108074274A (en) * | 2017-12-26 | 2018-05-25 | 深圳拎得清软件有限公司 | BIM model real-time rendering method and devices based on browser |
CN108804768A (en) * | 2018-05-08 | 2018-11-13 | 中建隧道建设有限公司 | One kind making the light-weighted method of BIM models |
CN110706345A (en) * | 2019-08-28 | 2020-01-17 | 中国铁道科学研究院集团有限公司电子计算技术研究所 | Railway BIM model lightweight method and system based on component instance combination |
-
2020
- 2020-04-30 CN CN202010364529.7A patent/CN111666433B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6034455B1 (en) * | 2015-07-10 | 2016-11-30 | 東芝エレベータ株式会社 | BIM system and method |
CN108074274A (en) * | 2017-12-26 | 2018-05-25 | 深圳拎得清软件有限公司 | BIM model real-time rendering method and devices based on browser |
CN108804768A (en) * | 2018-05-08 | 2018-11-13 | 中建隧道建设有限公司 | One kind making the light-weighted method of BIM models |
CN110706345A (en) * | 2019-08-28 | 2020-01-17 | 中国铁道科学研究院集团有限公司电子计算技术研究所 | Railway BIM model lightweight method and system based on component instance combination |
Non-Patent Citations (1)
Title |
---|
杨建伟: "BIM技术在铁路"四电"工程项目管理中的应用", 《铁道经济研究》 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112417023A (en) * | 2020-12-04 | 2021-02-26 | 北京构力科技有限公司 | Method, apparatus, electronic device, storage medium, and program product for processing IFC file |
CN112634452A (en) * | 2020-12-31 | 2021-04-09 | 佳讯飞鸿(北京)智能科技研究院有限公司 | Railway BIM model lightweight method and device |
CN112634452B (en) * | 2020-12-31 | 2024-05-28 | 佳讯飞鸿(北京)智能科技研究院有限公司 | Railway BIM model light weight method and device |
CN112989458A (en) * | 2021-02-22 | 2021-06-18 | 中铁二院工程集团有限责任公司 | Method for converting BIM (building information modeling) model into 3DTiles file |
CN112989458B (en) * | 2021-02-22 | 2022-09-06 | 中铁二院工程集团有限责任公司 | Method for converting BIM (building information modeling) model into 3DTiles file |
CN115238345A (en) * | 2022-07-13 | 2022-10-25 | 上海方联技术服务有限公司 | BIM (building information modeling) model processing method and device, storage medium and electronic device |
CN116611149A (en) * | 2023-05-26 | 2023-08-18 | 中南大学 | Parameterized modeling method for high-precision railway fastener system |
CN116611149B (en) * | 2023-05-26 | 2024-09-24 | 中南大学 | Parameterized modeling method for high-precision railway fastener system |
CN116502321A (en) * | 2023-06-28 | 2023-07-28 | 中铁第一勘察设计院集团有限公司 | BIM forward design method and system for railway communication machine room |
CN116502321B (en) * | 2023-06-28 | 2023-08-29 | 中铁第一勘察设计院集团有限公司 | BIM forward design method and system for railway communication machine room |
Also Published As
Publication number | Publication date |
---|---|
CN111666433B (en) | 2023-03-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111666433B (en) | Railway four-electrical engineering BIM model Web lightweight method | |
CN103530826B (en) | BIM (Building Information Modeling)-based shield method tunnel construction management method | |
CN102509330B (en) | Application of virtual three-dimensional system of transformer substation on the basis of electric power geographic information system (GIS) | |
CN102750618B (en) | A kind of comprehensive pipeline of metro construction aided management system and implementation method | |
CN111950066B (en) | Digital twin data driving system based on BIM and GIS technology | |
CN108491936A (en) | Subway Facilities equipment operation management system based on BIM and method | |
CN109491735B (en) | Integrated data generation and verification integrated monitoring human-computer interface configuration implementation method | |
KR20120072183A (en) | System for simulating train operation | |
CN110175368A (en) | A kind of rail traffic data display systems based on BIM+GIS | |
CN103077282A (en) | Rapid modeling method for high-speed railway scene based on basic-element combination and multilevel semantic constraint | |
CN112528590A (en) | Distribution line multi-primitive text single-line diagram depth layout algorithm | |
CN106447789A (en) | Method and system of line data and GIS combination of train operation monitoring system | |
CN111667575A (en) | Method for creating accurate model of rail traffic engineering based on standard | |
CN105630571A (en) | Virtual machine creating method and device | |
CN106428125B (en) | Navigation-type operation pathway data organization method based on GIS map and system | |
Wu et al. | Visualization of railway transportation engineering management using bim technology under the application of internet of things edge computing | |
KR101352216B1 (en) | Apparatus for Simulating Train Operation Based on Pattern and System for Simulating Train Operation Including That Apparatus | |
CN104091034A (en) | Automatic circuit contact graph forming system and method based on graph matching | |
CN111625944B (en) | Normalization verification method for G file of transformer substation main wiring diagram | |
Zhu et al. | A procedural modelling method for virtual high-speed railway scenes based on model combination and spatial semantic constraint | |
CN103247087A (en) | City distribution network graphical intelligent anti-misoperation system and method of system | |
CN110143223A (en) | A kind of 3 D monitoring O&M method of rail traffic | |
Li et al. | Research on integrated management of urban rail transit project based on digital twin | |
CN103544863B (en) | Track traffic synthetic Training of Monitoring simulation system data interaction module and method of work | |
Lingling et al. | Research and application of key technologies of bim+ gis virtual-reality interaction for high-speed railway integration test |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |