CN111641262A - Power dispatching operation method and system - Google Patents

Power dispatching operation method and system Download PDF

Info

Publication number
CN111641262A
CN111641262A CN202010407497.4A CN202010407497A CN111641262A CN 111641262 A CN111641262 A CN 111641262A CN 202010407497 A CN202010407497 A CN 202010407497A CN 111641262 A CN111641262 A CN 111641262A
Authority
CN
China
Prior art keywords
check
information
rehearsal
dispatching
control system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010407497.4A
Other languages
Chinese (zh)
Other versions
CN111641262B (en
Inventor
林志贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Power Supply Bureau Co Ltd
Original Assignee
Shenzhen Power Supply Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Power Supply Bureau Co Ltd filed Critical Shenzhen Power Supply Bureau Co Ltd
Priority to CN202010407497.4A priority Critical patent/CN111641262B/en
Publication of CN111641262A publication Critical patent/CN111641262A/en
Application granted granted Critical
Publication of CN111641262B publication Critical patent/CN111641262B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00016Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using a wired telecommunication network or a data transmission bus
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/124Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wired telecommunication networks or data transmission busses

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

本发明涉及一种电力调度操作方法,所述方法包括:调度指挥控制系统获取已三审操作票信息,根据所述已三审操作票信息进行全票预演校核,并将所述已三审操作票信息发送至电网运行监控系统进行全票预演校核;如果调度指挥控制系统以及电网运行监控系统的全票预演校核均通过,则输出请求值班长批准操作的操作请求信息;如果调度指挥控制系统或电网运行监控系统的全票预演校核不通过,则中断电力调度操作,输出全票预演校核失败的提示信息;调度指挥控制系统获取值班长的批准操作信息,根据所述批准操作信息进行电力调度操作。本发明利用电网运行监控系统、调度指挥控制系统在操作票执行前及执行中进行校验,能够提高电力调度操作的安全性和可靠性。

Figure 202010407497

The present invention relates to an electric power dispatching operation method. The method comprises: a dispatching command and control system obtains the information of the operation ticket that has been checked for the third time, performs a full-ticket rehearsal check according to the information of the operation ticket that has been checked for the third time, and analyzes the operation ticket that has been checked for the third time. The ticket information is sent to the power grid operation monitoring system for full-ticket rehearsal check; if both the dispatch command and control system and the power grid operation monitoring system pass the full-ticket rehearsal check, the operation request information requesting the operation to be approved by the shift leader is output; if the dispatch command and control system or If the full-ticket rehearsal check of the power grid operation monitoring system fails, the power dispatching operation will be interrupted, and the prompt information of the failure of the full-ticket rehearsal check will be output; the dispatch command and control system obtains the approved operation information of the shift leader, and conducts the power dispatch operation according to the approved operation information. . The present invention utilizes the power grid operation monitoring system and the dispatch command and control system to perform verification before and during the execution of the operation ticket, which can improve the safety and reliability of the power dispatch operation.

Figure 202010407497

Description

一种电力调度操作方法及其系统A power dispatching operation method and system thereof

技术领域technical field

本发明涉及电力调度技术领域,具体涉及一种电力调度操作方法。The invention relates to the technical field of power dispatching, and in particular to a power dispatching operation method.

背景技术Background technique

在电网安全运行中,电网的正确操作是保障电网安全运行的一项十分重要的工作,电气误操作可能造成大面积停电、设备损坏、人身伤亡,甚至引起电网振荡瓦解等严重后果。操作票编制、审核、执行的正确是防止误操作的有力保障。故电网调度操作票操作前引入三审制度。而操作票三审往往由不同岗位调度员凭借多年经验进行审核,缺少系统维度校核。In the safe operation of the power grid, the correct operation of the power grid is a very important task to ensure the safe operation of the power grid. Electrical misoperation may cause large-scale power outages, equipment damage, personal casualties, and even cause serious consequences such as grid oscillation and collapse. The correct preparation, review and execution of the operation ticket is a powerful guarantee to prevent misoperation. Therefore, the three-trial system is introduced before the operation of the grid dispatching operation ticket. The third review of operation tickets is often reviewed by dispatchers in different positions with years of experience, and there is a lack of system dimension checking.

随着电网结构越来越复杂,电网设备计划检修工作、信号监视等与日俱增,电力调度员所承担工作量及风险越来越大。调度员在执行各项计划工作、缺陷及事故处理时,仅能依靠人工审查操作条件,存在错误评估系统潮流、厂站失压,导致电力调度误操作。为杜绝各类误调度、误遥控、误操作的发生,及时准确地识别和处理故障,引入专家推理的机制,在调控操作全过程进行安全校核,使调度以及监控工作更加有序、安全、高效,更进一步推进调控一体模式向智能化方向发展。As the power grid structure becomes more and more complex, the planned maintenance work and signal monitoring of power grid equipment are increasing day by day, and the workload and risks borne by power dispatchers are increasing. When the dispatcher performs various planned work, defects and accident handling, he can only rely on manual review of operating conditions, and there are errors in evaluating the power flow of the system and the loss of voltage at the plant, which leads to misoperation of power dispatching. In order to prevent all kinds of mis-scheduling, mis-remote control and mis-operation, and identify and deal with faults in a timely and accurate manner, the expert reasoning mechanism is introduced, and safety checks are carried out in the whole process of control and operation, so that the scheduling and monitoring work is more orderly, safe, and reliable. Efficient, and further promote the development of the integrated control model to the direction of intelligence.

在各项调度操作事件中,存在着母线方式调整(即倒母线)后,由于电网结构过于复杂、人员审查疏忽,导致部分间隔操作不到位,容易引起线路及厂站失去电源,导致失压。常规系统拓扑防误需要将每步操作令细化为操作序列,方能校核。在实际操作中,倒母线操作如细化各个间隔操作序列,一则过于繁琐占用大量工作量,二则易出错,三则实际调度工作中倒母线操作以现场为主,安全责任在现场落地,调度角度出发仅考虑倒母线之后开关分合是否引起线路、母线失压。In various dispatching operation events, after the adjustment of the busbar mode (ie, the inverted busbar), due to the complex structure of the power grid and the negligence of personnel review, some interval operations are not in place, which may easily cause power loss of lines and plants, resulting in loss of voltage. To prevent errors in the conventional system topology, it is necessary to refine the operation order of each step into an operation sequence before it can be checked. In actual operation, if the operation of the inverted bus is to refine each interval operation sequence, one is too cumbersome and takes up a lot of work, the other is error-prone, and the third is that the operation of the inverted bus is mainly on-site in the actual scheduling work, and the safety responsibility is on the spot. From the scheduling point of view, only consider whether the switch opening and closing after the busbar is inverted will cause the line and busbar to lose voltage.

发明内容SUMMARY OF THE INVENTION

本发明旨在提出一种电力调度操作方法,以利用电网运行监控系统(OCS)、调度指挥控制系统(DCCS)在操作票执行前、执行中进行校验,以此杜绝背景技术中所述风险。The purpose of the present invention is to propose a power dispatch operation method, so as to use the power grid operation monitoring system (OCS) and dispatch command and control system (DCCS) to verify the operation ticket before and during the execution, so as to eliminate the risks described in the background art .

为此,本发明实施例提出一种电力调度操作方法,包括:To this end, an embodiment of the present invention proposes a power scheduling operation method, including:

调度指挥控制系统获取已三审操作票信息,根据所述已三审操作票信息进行全票预演校核,并将所述已三审操作票信息发送至电网运行监控系统进行全票预演校核;所述已三审操作票包括倒母线操作令;The dispatching command and control system obtains the information of the third-trial operation ticket, conducts a full-vote rehearsal check according to the third-trial operation ticket information, and sends the third-trial operation ticket information to the power grid operation monitoring system for full-vote rehearsal verification; The above-mentioned third-instance operation ticket includes the busbar operation order;

如果调度指挥控制系统以及电网运行监控系统的全票预演校核均通过,则输出请求值班长批准操作的操作请求信息;如果调度指挥控制系统、电网运行监控系统的全票预演校核中任一个不通过,则中断电力调度操作,并输出全票预演校核失败的提示信息;If the unanimous rehearsal check of the dispatching command and control system and the power grid operation monitoring system is passed, the operation request information requesting the operation to be approved by the shift leader is output; , the power dispatching operation will be interrupted, and a prompt message indicating that the full-ticket rehearsal check fails will be output;

调度指挥控制系统获取值班长的批准操作信息,并根据所述批准操作信息进行电力调度操作;其中所述电力调度操作包括调度指挥控制系统以及电网运行监控系统分别依次对单条操作令进行预演校核,并在调度指挥控制系统、电网运行监控系统均预演校核通过时,下发操作指令至运行人员端,以告知运行人员根据单条操作令进行现场操作。The dispatching command and control system obtains the approved operation information of the shift leader, and performs power dispatching operation according to the approved operation information; wherein the power dispatching operation includes the dispatching command and control system and the power grid operation monitoring system respectively performing pre-rehearsal checks on a single operation order in turn. , and when the dispatching command and control system and the power grid operation monitoring system have passed the rehearsal check, the operation command will be issued to the operator to inform the operator to perform on-site operations according to a single operation command.

作为可选的一个实施方式,所述电力调度操作具体包括:As an optional implementation manner, the power scheduling operation specifically includes:

调度指挥控制系统获取当前条操作令,并对所述当前条操作令进行预演校核,并在预演校核通过时,生成一关于当前条操作令的DCCS预演校核通过信息;The dispatch command and control system obtains the current operation order, performs a pre-rehearsal check on the current operation order, and generates a DCCS rehearsal check pass information about the current operation order when the rehearsal check is passed;

调度指挥控制系统发送一预演校核信息至电网运行监控系统;The dispatch command and control system sends a rehearsal check information to the power grid operation monitoring system;

电网运行监控系统根据所述预演校核信息对所述当前条操作令进行预演校核,并在预演校核通过时,发送一关于当前条操作令的OCS预演校核通过信息至调度指挥控制系统;The power grid operation monitoring system performs a pre-rehearsal check on the current operation order according to the rehearsal check information, and when the rehearsal check is passed, sends an OCS pre-rehearsal check pass information on the current operation order to the dispatch command and control system ;

调度指挥控制系统根据所述DCCS预演校核通过信息和所述OCS预演校核通过信息生成关于当前条操作令的操作指令,并下发操作指令至运行人员端;The dispatch command and control system generates an operation instruction about the current operation order according to the DCCS rehearsal check pass information and the OCS rehearsal check pass information, and issues the operation instruction to the operator;

调度指挥控制系统获取运行人员端上传的关于当前条操作令的操作结果信息,并根据所述操作结果信息进行系统状态校核,并将所述操作结果信息发送至电网运行监控系统进行系统状态校核;The dispatch command and control system obtains the operation result information about the current operation order uploaded by the operator, and checks the system status according to the operation result information, and sends the operation result information to the power grid operation monitoring system for system status checking. nuclear;

根据所述调度指挥控制系统以及电网运行监控系统的系统状态校核结果判定是否操作成功,并在判定操作成功时判定是否进入下一条操作令的电力调度操作。According to the system state check results of the dispatching command and control system and the power grid operation monitoring system, it is determined whether the operation is successful, and when it is determined that the operation is successful, it is determined whether to enter the power dispatching operation of the next operation order.

作为可选的一个实施方式,当调度指挥控制系统对所述当前条操作令进行预演校核不通过时,则中断电力调度操作,并输出当前条操作令预演校核失败的提示信息。As an optional embodiment, when the current operation order is failed to pass the rehearsal check by the dispatch command and control system, the power dispatch operation is interrupted, and a prompt message that the rehearsal check of the current operation order fails is output.

作为可选的一个实施方式,当电网运行监控系统对所述当前条操作令进行预演校核不通过时,则中断电力调度操作,并输出当前条操作令预演校核失败的提示信息。As an optional embodiment, when the power grid operation monitoring system fails to pass the rehearsal check of the current operation order, the power dispatching operation is interrupted, and a prompt message that the rehearsal check of the current operation order fails is output.

作为可选的一个实施方式,所述调度指挥控制系统获取运行人员端上传的操作结果信息,并根据操作结果信息进行系统状态校核,并将所述操作结果信息发送至电网运行监控系统进行系统状态校核,包括:As an optional embodiment, the dispatching command and control system obtains the operation result information uploaded by the operator, checks the system state according to the operation result information, and sends the operation result information to the power grid operation monitoring system for system monitoring. Status checks, including:

调度指挥控制系统获取运行人员端上传的关于当前条操作令的操作结果信息,根据所述操作结果信息进行系统状态校核,并在系统状态校核通过时生成一关于当前操作令的DCCS系统状态校核通过信息;The dispatching command and control system obtains the operation result information about the current operation order uploaded by the operator, checks the system state according to the operation result information, and generates a DCCS system state about the current operation order when the system state check passes. Check the passed information;

调度指挥控制系统根据所述操作结果信息发送至电网运行监控系统;The dispatching command and control system sends the operation result information to the power grid operation monitoring system according to the operation result information;

电网运行监控系统根据所述操作结果信息进行系统状态校核,并在系统状态校核通过时生成一关于当前操作令的OCS系统状态校核通过信息,并将所述OCS系统状态校核通过信息发送至调度指挥控制系统。The power grid operation monitoring system performs a system state check according to the operation result information, and generates an OCS system state check pass information about the current operation order when the system state check passes, and sends the OCS system state check pass information Sent to the dispatch command and control system.

作为可选的一个实施方式,所述根据所述调度指挥控制系统以及电网运行监控系统的系统状态校核结果判定是否操作成功,并在判定操作成功时判定是否进入下一条操作令的电力调度操作,包括:As an optional implementation manner, it is determined whether the operation is successful according to the system state check results of the dispatching command and control system and the power grid operation monitoring system, and when it is determined that the operation is successful, it is determined whether to enter the power dispatching operation of the next operation order ,include:

当调度指挥控制系统获取到所述DCCS系统状态校核通过信息以及所述OCS系统状态校核通过信息时,调度指挥控制系统判定当前条操作令是否为已三审操作票信息中的最后一条操作令;若为最后一条操作令,则结束电力调度操作,若不为最后一条操作令,则进入下一条操作令的电力调度操作。When the dispatching command and control system obtains the DCCS system status check pass information and the OCS system status check pass information, the dispatch command and control system determines whether the current operation order is the last operation in the third-trial operation ticket information order; if it is the last operation order, end the power dispatching operation; if it is not the last operation order, enter the power dispatching operation of the next operation order.

作为可选的一个实施方式,所述已三审操作票具体包括根据最终目标方式进行置位操作的倒母线操作令。As an optional implementation manner, the third-trial operation ticket specifically includes a reverse bus operation order for performing a setting operation according to the final target mode.

本发明实施例还提出一种电力调度操作系统,用于实现上述实施例所述的电力调度操作方法,所述系统包括:调度指挥控制系统和电网运行监控系统;The embodiment of the present invention further provides a power dispatching operating system, which is used to realize the power dispatching operation method described in the above-mentioned embodiment, and the system includes: a dispatching command and control system and a power grid operation monitoring system;

其中,所述调度指挥控制系统用于获取已三审操作票信息,根据所述已三审操作票信息进行全票预演校核,并将所述已三审操作票信息发送至电网运行监控系统进行全票预演校核;所述已三审操作票包括倒母线操作令;Wherein, the dispatching command and control system is used to obtain the information of the third-trial operation ticket, perform a full-vote rehearsal check according to the third-trial operation ticket information, and send the third-trial operation ticket information to the power grid operation monitoring system for Full-ticket rehearsal check; the third-trial operation ticket includes the busbar operation order;

其中,如果调度指挥控制系统以及电网运行监控系统的全票预演校核均通过,则输出请求值班长批准操作的操作请求信息;如果调度指挥控制系统、电网运行监控系统的全票预演校核中任一个不通过,则中断电力调度操作,并输出全票预演校核失败的提示信息;Among them, if the unanimous rehearsal check of the dispatching command and control system and the power grid operation monitoring system is passed, the operation request information requesting the operation to be approved by the shift leader is output; If it does not pass, the power dispatching operation will be interrupted, and a prompt message that the full-ticket rehearsal check fails will be output;

其中,所述调度指挥控制系统还用于获取值班长的批准操作信息,并根据所述批准操作信息进行电力调度操作;其中所述电力调度操作包括调度指挥控制系统以及电网运行监控系统分别依次对单条操作令进行预演校核,并在调度指挥控制系统、电网运行监控系统均预演校核通过时,下发操作指令至运行人员端,以告知运行人员根据单条操作令进行现场操作。Wherein, the dispatching command and control system is also used to obtain the approved operation information of the shift supervisor, and perform power dispatching operation according to the approved operation information; wherein the power dispatching operation includes that the dispatching command and control system and the power grid operation monitoring system are respectively used to perform the power dispatching operation in turn. A single operation order is rehearsed and checked, and when both the dispatching command and control system and the power grid operation monitoring system pass the rehearsal check, an operation order is issued to the operator to inform the operator to perform on-site operations according to a single operation order.

以上实施例方案至少具有以下有益效果:The above embodiments have at least the following beneficial effects:

提出了异源校核的校核方式,在调度指挥控制系统、电网运行监控系统中构建两套不同源校核,调度指挥控制系统、电网运行监控系统分别对已三审操作票信息进行全票预演校核,并在调度指挥控制系统、电网运行监控系统均全票预演校核通过情况下,才开展电力调度操作,从而确保校核准确性,能够提高电力调度操作的安全性和可靠性。A checking method of heterogeneous checking is proposed, and two sets of checking with different sources are constructed in the dispatching command and control system and the power grid operation monitoring system. The power dispatching operation is carried out only when the dispatching command and control system and the power grid operation monitoring system have passed the full-ticket rehearsal check, so as to ensure the accuracy of the verification and improve the safety and reliability of the power dispatching operation.

本发明的其它特征和优点将在随后的说明书中阐述,并且,部分地从说明书中变得显而易见,或者通过实施本发明而得以体现。本发明的目的和其他优点可通过在说明书、权利要求书以及附图中所特别指出的结构来实现和获得。Other features and advantages of the invention will be set forth in the description which follows, and in part will be apparent from the description, or will be manifested by practice of the invention. The objectives and other advantages of the invention may be realized and attained by the structure particularly pointed out in the description, claims and drawings.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained according to these drawings without creative efforts.

图1为本发明一实施例中一种电力调度操作方法的流程示意图。FIG. 1 is a schematic flowchart of a power dispatching operation method according to an embodiment of the present invention.

图2为本发明另一实施例中一种电力调度操作方法流程示意图。FIG. 2 is a schematic flowchart of an operation method for power dispatching in another embodiment of the present invention.

图3为本发明的实施例中一种母线接线方式示例图。FIG. 3 is a diagram illustrating an example of a bus connection mode in an embodiment of the present invention.

具体实施方式Detailed ways

以下将参考附图详细说明本公开的各种示例性实施例、特征和方面。附图中相同的附图标记表示功能相同或相似的元件。尽管在附图中示出了实施例的各种方面,但是除非特别指出,不必按比例绘制附图。Various exemplary embodiments, features and aspects of the present disclosure will be described in detail below with reference to the accompanying drawings. The same reference numbers in the figures denote elements that have the same or similar functions. While various aspects of the embodiments are shown in the drawings, the drawings are not necessarily drawn to scale unless otherwise indicated.

另外,为了更好的说明本发明,在下文的具体实施例中给出了众多的具体细节。本领域技术人员应当理解,没有某些具体细节,本发明同样可以实施。在一些实例中,对于本领域技术人员熟知的手段未作详细描述,以便于凸显本发明的主旨。In addition, in order to better illustrate the present invention, numerous specific details are given in the following specific embodiments. It will be understood by those skilled in the art that the present invention may be practiced without certain specific details. In some instances, means well known to those skilled in the art have not been described in detail in order not to obscure the subject matter of the present invention.

如图1所示,本发明一实施例提出一种电力调度操作方法,本实施例所述方法包括:As shown in FIG. 1 , an embodiment of the present invention provides a power dispatching operation method. The method in this embodiment includes:

步骤S1、调度指挥控制系统获取已三审操作票信息,根据所述已三审操作票信息进行全票预演校核,并将所述已三审操作票信息发送至电网运行监控系统进行全票预演校核;所述已三审操作票包括倒母线操作令;Step S1, the dispatching command and control system obtains the information of the third-trial operation ticket, performs a full-ticket rehearsal check according to the third-trial operation ticket information, and sends the third-trial operation ticket information to the power grid operation monitoring system for full-ticket rehearsal verification. nuclear; the third-trial operation ticket includes the busbar operation order;

具体而言,所述全票预演校核为基于电网实时潮流数据,模拟操作所述已三审操作票的操作令系统相关拓扑、五防校核、潮流校核信息,提取模拟后拓扑、五防、潮流信息,校验是否存在稳控断面越限、主变过载、厂站失压、违反五防等,若存在,则校核不通过,若不存在,则校核通过。Specifically, the full-ticket rehearsal check is based on the real-time power flow data of the power grid, simulating the operation of the operation ticket that has been reviewed for the third time to make the system-related topology, five-proof check, and power flow check information, and extracting the simulated topology, five-proof check information. , power flow information, check whether there is a stability control section exceeding the limit, the main transformer is overloaded, the plant station loses pressure, and the five defenses are violated.

步骤S2、如果调度指挥控制系统以及电网运行监控系统的全票预演校核均通过,则输出请求值班长批准操作的操作请求信息;如果调度指挥控制系统、电网运行监控系统的全票预演校核中任一个不通过,则中断电力调度操作,并输出全票预演校核失败的提示信息;Step S2, if the unanimous rehearsal check of the dispatching command and control system and the power grid operation monitoring system has passed, output the operation request information requesting the supervisor on duty to approve the operation; If one fails, the power dispatching operation will be interrupted, and a prompt message indicating that the full-ticket rehearsal check fails will be output;

步骤S3、调度指挥控制系统获取值班长的批准操作信息,并根据所述批准操作信息进行电力调度操作;其中所述电力调度操作包括调度指挥控制系统以及电网运行监控系统分别依次对单条操作令进行预演校核,并在调度指挥控制系统、电网运行监控系统均预演校核通过时,下发操作指令至运行人员端,以告知运行人员根据单条操作令进行现场操作。Step S3, the dispatching command and control system obtains the approved operation information of the shift leader, and performs power dispatching operation according to the approved operation information; wherein the power dispatching operation includes that the dispatching command and control system and the power grid operation monitoring system respectively perform a single operation order in turn. Rehearsal and check, and when the dispatching command and control system and the power grid operation monitoring system pass the rehearsal check, issue an operation command to the operator to inform the operator to perform on-site operations according to a single operation command.

具体而言,电网运行监控系统(OCS)是位于安全生产I区新一代调度控制系统。OCS系统具有基础资源平台、数据中心、监视中心、控制中心、镜像控制培训等功能,通过总线和全景建模技术实现上述功能的横向集成和纵向贯通。调度指挥控制系统(DCCS)是位于安全生产II区,依托网络发令技术,为各级电力调度中心和厂站及相关单位间开展各类调度指挥业务而服务;是实现调度业务一体化运作的基础,该系统具有网络发令、智能操作票、即时沟通、机组申请、调度日志等功能,作为新一代调度模式,是电网运行控制和调度生产管理的重要技术支撑。Specifically, the power grid operation monitoring system (OCS) is a new generation dispatching control system located in the safety production zone I. The OCS system has functions such as basic resource platform, data center, monitoring center, control center, mirror control training, etc. The horizontal integration and vertical connection of the above functions are realized through bus and panoramic modeling technology. The Dispatching Command and Control System (DCCS) is located in the safety production zone II, relying on the network ordering technology to serve various dispatching and commanding operations between power dispatching centers at all levels, plants and stations and related units; it is the basis for the integrated operation of dispatching business. , the system has functions such as network command, intelligent operation ticket, instant communication, unit application, dispatch log, etc. As a new generation dispatch mode, it is an important technical support for power grid operation control and dispatch production management.

本实施例方法提出了异源校核的校核方式,在调度指挥控制系统、电网运行监控系统中构建两套不同源校核,调度指挥控制系统、电网运行监控系统分别对已三审操作票信息进行全票预演校核,并在调度指挥控制系统、电网运行监控系统均全票预演校核通过情况下,才开展电力调度操作,从而确保校核准确性,能够提高电力调度操作的安全性和可靠性。The method of this embodiment proposes a checking method of heterogeneous checking. Two sets of checking with different sources are constructed in the dispatching command and control system and the power grid operation monitoring system. The information is fully rehearsed and checked, and the power dispatching operation is carried out only when the dispatching command and control system and the power grid operation monitoring system have passed the unanimous rehearsal and verification, so as to ensure the accuracy of the verification and improve the safety and reliability of the power dispatching operation. sex.

如图2所示,作为上述实施例的一个较佳实施方式的具体流程示意图,在本实施方式中,所述电力调度操作具体包括:As shown in FIG. 2 , as a schematic flow chart of a preferred implementation of the foregoing embodiment, in this implementation, the power dispatching operation specifically includes:

调度指挥控制系统获取当前条操作令,并对所述当前条操作令进行预演校核,并在预演校核通过时,生成一关于当前条操作令的DCCS预演校核通过信息;具体而言,调度指挥控制系统对所述当前条操作令进行预演校核包括:基于电网实时潮流数据,模拟操作一次执行当前条操作令后系统相关拓扑、五防校核、潮流校核信息,并提取模拟后拓扑、五防、潮流信息,校验是否存在稳控断面越限、主变过载、厂站失压、违反五防等,若存在,则校核不通过,若不存在,则校核通过。The dispatch command and control system obtains the current operation order, performs a pre-rehearsal check on the current operation order, and when the rehearsal check passes, generates a DCCS rehearsal check pass information about the current operation order; specifically, The pre-rehearsal check of the current operation order by the dispatching command and control system includes: based on the real-time power flow data of the power grid, simulating operation once to execute the current operation order, the system related topology, five-defense check, and power flow check information, and extracting the information after the simulation. Topology, five defenses, and power flow information, check whether there is a stability control section exceeding the limit, the main transformer overload, the power loss of the plant, and the violation of the five defenses.

调度指挥控制系统发送一预演校核信息至电网运行监控系统;The dispatch command and control system sends a rehearsal check information to the power grid operation monitoring system;

电网运行监控系统根据所述预演校核信息对所述当前条操作令进行预演校核,并在预演校核通过时,发送一关于当前条操作令的OCS预演校核通过信息至调度指挥控制系统;具体而言,电网运行监控系统根据所述预演校核信息对所述当前条操作令进行预演校核的校核步骤与调度指挥控制系统对所述当前条操作令进行预演校核相同;The power grid operation monitoring system performs a pre-rehearsal check on the current operation order according to the rehearsal check information, and when the rehearsal check is passed, sends an OCS pre-rehearsal check pass information on the current operation order to the dispatch command and control system Specifically, the checking steps of the power grid operation monitoring system performing the pre-rehearsal checking of the current operation order according to the rehearsal checking information are the same as the pre-rehearsal checking of the current operation order performed by the dispatch command and control system;

调度指挥控制系统根据所述DCCS预演校核通过信息和所述OCS预演校核通过信息生成关于当前条操作令的操作指令,并下发操作指令至运行人员端;The dispatch command and control system generates an operation instruction about the current operation order according to the DCCS rehearsal check pass information and the OCS rehearsal check pass information, and issues the operation instruction to the operator;

调度指挥控制系统获取运行人员端上传的关于当前条操作令的操作结果信息,并根据所述操作结果信息进行系统状态校核,并将所述操作结果信息发送至电网运行监控系统进行系统状态校核;The dispatch command and control system obtains the operation result information about the current operation order uploaded by the operator, and checks the system status according to the operation result information, and sends the operation result information to the power grid operation monitoring system for system status checking. nuclear;

根据所述调度指挥控制系统以及电网运行监控系统的系统状态校核结果判定是否操作成功,并在判定操作成功时判定是否进入下一条操作令的电力调度操作。According to the system state check results of the dispatching command and control system and the power grid operation monitoring system, it is determined whether the operation is successful, and when it is determined that the operation is successful, it is determined whether to enter the power dispatching operation of the next operation order.

在本实施方式中,当调度指挥控制系统对所述当前条操作令进行预演校核不通过时,则中断电力调度操作,并输出当前条操作令预演校核失败的提示信息。In this embodiment, when the pre-rehearsal check of the current operation order by the dispatch command and control system fails, the power dispatch operation is interrupted, and a prompt message that the pre-rehearsal check of the current operation order fails is output.

在本实施方式中,当电网运行监控系统对所述当前条操作令进行预演校核不通过时,则中断电力调度操作,并输出当前条操作令预演校核失败的提示信息。In this embodiment, when the power grid operation monitoring system fails the rehearsal check of the current operation order, the power dispatching operation is interrupted, and a prompt message that the rehearsal check of the current operation order fails is output.

在本实施方式中,所述调度指挥控制系统获取运行人员端上传的操作结果信息,并根据操作结果信息进行系统状态校核,并将所述操作结果信息发送至电网运行监控系统进行系统状态校核,包括:In this embodiment, the dispatching command and control system obtains the operation result information uploaded by the operator, performs system status checking according to the operation result information, and sends the operation result information to the power grid operation monitoring system for system status checking. nucleus, including:

调度指挥控制系统获取运行人员端上传的关于当前条操作令的操作结果信息,根据所述操作结果信息进行系统状态校核,并在系统状态校核通过时生成一关于当前操作令的DCCS系统状态校核通过信息;The dispatching command and control system obtains the operation result information about the current operation order uploaded by the operator, checks the system state according to the operation result information, and generates a DCCS system state about the current operation order when the system state check passes. Check the passed information;

调度指挥控制系统根据所述操作结果信息发送至电网运行监控系统;The dispatching command and control system sends the operation result information to the power grid operation monitoring system according to the operation result information;

电网运行监控系统根据所述操作结果信息进行系统状态校核,并在系统状态校核通过时生成一关于当前操作令的OCS系统状态校核通过信息,并将所述OCS系统状态校核通过信息发送至调度指挥控制系统。The power grid operation monitoring system performs a system state check according to the operation result information, and generates an OCS system state check pass information about the current operation order when the system state check passes, and sends the OCS system state check pass information Sent to the dispatch command and control system.

在本实施方式中,所述根据所述调度指挥控制系统以及电网运行监控系统的系统状态校核结果判定是否操作成功,并在判定操作成功时判定是否进入下一条操作令的电力调度操作,包括:In this embodiment, determining whether the operation is successful according to the system state check results of the dispatching command and control system and the power grid operation monitoring system, and when determining whether the operation is successful, determines whether to enter the power dispatching operation of the next operation order, including: :

当调度指挥控制系统获取到所述DCCS系统状态校核通过信息以及所述OCS系统状态校核通过信息时,调度指挥控制系统判定当前条操作令是否为已三审操作票信息中的最后一条操作令;若为最后一条操作令,则结束电力调度操作,若不为最后一条操作令,则进入下一条操作令的电力调度操作。When the dispatching command and control system obtains the DCCS system status check pass information and the OCS system status check pass information, the dispatch command and control system determines whether the current operation order is the last operation in the third-trial operation ticket information order; if it is the last operation order, end the power dispatching operation; if it is not the last operation order, enter the power dispatching operation of the next operation order.

在本实施方式中,所述已三审操作票具体包括根据最终目标方式进行置位操作的倒母线操作令。In this embodiment, the third-trial operation ticket specifically includes an inverted bus operation order for performing a setting operation according to the final target mode.

具体而言,如图3接线方式为例:I母挂乙线、丁线运行;II母挂甲线、丙线、戊线运行。现需调整运行方式如下I母挂甲线、丙线、戊线运行;II母挂乙线、丁线运行。Specifically, take the wiring method as shown in Figure 3 as an example: I run with the B line and D line; II run with the A line, C line, and E line. The operation mode needs to be adjusted as follows: I mother hanging line A, C line, E line operation; II mother hanging line B, D line operation.

按照常规校核逻辑,需向校核系统发送如下操作序列:According to the conventional check logic, the following sequence of operations needs to be sent to the check system:

①甲线合上1011刀闸,拉开1012刀闸;①A wire closes the 1011 knife switch and opens the 1012 knife switch;

②乙线合上1022刀闸,拉开1021刀闸;② Line B closes the 1022 knife switch and opens the 1021 knife switch;

③丙线合上1031刀闸,拉开1032刀闸;③Close the 1031 knife switch on the C line and open the 1032 knife switch;

④丁线合上1042刀闸,拉开1041刀闸;④Close the 1042 knife switch on the D line and open the 1041 knife switch;

⑤戊线合上1051刀闸,拉开1052刀闸;⑤ Close the 1051 knife switch on the fifth line, and open the 1052 knife switch;

需要通过以上5步操作,10个合拉动作完成。Need to go through the above 5 steps, 10 pull together to complete.

该方法需要调度员将一个倒母线操作令分解为10个动作完成,动作解析过程复杂,实现难度高,容易出现人工分解令出错。This method requires the dispatcher to decompose an inverted bus operation order into 10 actions to complete, the action analysis process is complex, the implementation is difficult, and errors are prone to occur in manual decomposition of the order.

为解决此种问题,本发明提出基于强置位方式校核。即根据操作令“I母挂甲线、丙线、戊线运行;II母挂乙线、丁线运行”,直接将其解析为:In order to solve this problem, the present invention proposes checking based on the strong setting method. That is, according to the operation order "I mother hangs A line, C line, E line operation; II mother hangs B line, D line operation", it is directly parsed as:

“I母:甲线1011刀闸合位、1012刀闸分位;丙线1031刀闸合位、1032刀闸分位;戊线1051刀闸合位、1052刀闸分位”;"I mother: Line A 1011 knife switch closed position, 1012 knife gate split position; C line 1031 knife gate closed position, 1032 knife gate split position; E line 1051 knife gate closed position, 1052 knife gate split position";

“II母:乙线1022刀闸合位、1021刀闸分位;丁线1042刀闸合位、1041刀闸分位”;"II mother: B line 1022 knife switch closed position, 1021 knife switch position; D line 1042 knife switch closed position, 1041 knife switch position";

忽略中间刀闸分合动作,直接根据最终目标方式进行置位操作,符合调度工作实际,减少校核步骤和解析风险。Ignore the opening and closing action of the intermediate knife switch, and directly perform the setting operation according to the final target method, which is in line with the actual scheduling work and reduces the verification steps and analysis risks.

本实施方式针对较为繁琐的倒母线校核,从调度实际业务角度出发,对母线进行强置位,已置位之后挂线方式作为基础,针对后续操作进行校核。In this embodiment, for the complicated check of the inverted bus, from the perspective of dispatching the actual business, the bus is strongly set, and the method of hanging the line after the setting is used as the basis, and the check is carried out for the subsequent operations.

基于上述实施方式可知,本实施方式以异源校核为基础,现场运行人员操作完毕,通过DCCS系统复令,DCCS自动收令并作校核,同时与OCS系统校核结果作比对,两系统校核均通过后自动对下发下一步操作令。在不发生异常情况,则由系统自动下令收令,此过程无需人工干预,极大提升操作效率。若出现一套或两套系统校核不通过,则中断并告警,由调度员人工介入处理。从而规避人为遗漏的风险,提高操作效率和操作可靠性。Based on the above embodiment, it can be seen that this embodiment is based on heterologous verification. After the operation is completed by the on-site operator, the DCCS system returns the order, and the DCCS automatically receives the order and checks it. At the same time, it is compared with the check result of the OCS system. After the system verification is passed, the next step operation order is automatically issued. If there is no abnormal situation, the system will automatically order and receive the order. This process does not require manual intervention, which greatly improves the operation efficiency. If one or two sets of systems fail to pass the check, it will be interrupted and an alarm will be issued, and the dispatcher will manually intervene and deal with it. Thereby avoiding the risk of human omission and improving operational efficiency and operational reliability.

本发明另一实施例还提出一种电力调度操作系统,用于实现上述实施例所述的电力调度操作方法,所述系统包括:调度指挥控制系统和电网运行监控系统;Another embodiment of the present invention further provides a power dispatching operating system, which is used to implement the power dispatching operation method described in the above embodiment, and the system includes: a dispatching command and control system and a power grid operation monitoring system;

其中,所述调度指挥控制系统用于获取已三审操作票信息,根据所述已三审操作票信息进行全票预演校核,并将所述已三审操作票信息发送至电网运行监控系统进行全票预演校核;所述已三审操作票包括倒母线操作令;Wherein, the dispatching command and control system is used to obtain the information of the third-trial operation ticket, perform a full-vote rehearsal check according to the third-trial operation ticket information, and send the third-trial operation ticket information to the power grid operation monitoring system for Full-ticket rehearsal check; the third-trial operation ticket includes the busbar operation order;

其中,如果调度指挥控制系统以及电网运行监控系统的全票预演校核均通过,则输出请求值班长批准操作的操作请求信息;如果调度指挥控制系统、电网运行监控系统的全票预演校核中任一个不通过,则中断电力调度操作,并输出全票预演校核失败的提示信息;Among them, if the unanimous rehearsal check of the dispatching command and control system and the power grid operation monitoring system is passed, the operation request information requesting the operation to be approved by the shift leader is output; If it does not pass, the power dispatching operation will be interrupted, and a prompt message that the full-ticket rehearsal check fails will be output;

其中,所述调度指挥控制系统还用于获取值班长的批准操作信息,并根据所述批准操作信息进行电力调度操作;其中所述电力调度操作包括调度指挥控制系统以及电网运行监控系统分别依次对单条操作令进行预演校核,并在调度指挥控制系统、电网运行监控系统均预演校核通过时,下发操作指令至运行人员端,以告知运行人员根据单条操作令进行现场操作。Wherein, the dispatching command and control system is also used to obtain the approved operation information of the shift supervisor, and perform power dispatching operation according to the approved operation information; wherein the power dispatching operation includes that the dispatching command and control system and the power grid operation monitoring system are respectively used to perform the power dispatching operation in turn. A single operation order is rehearsed and checked, and when both the dispatching command and control system and the power grid operation monitoring system pass the rehearsal check, an operation order is issued to the operator to inform the operator to perform on-site operations according to a single operation order.

以上已经描述了本发明的各实施例,上述说明是示例性的,并非穷尽性的,并且也不限于所披露的各实施例。在不偏离所说明的各实施例的范围和精神的情况下,对于本技术领域的普通技术人员来说许多修改和变更都是显而易见的。本文中所用术语的选择,旨在最好地解释各实施例的原理、实际应用或对市场中的技术改进,或者使本技术领域的其它普通技术人员能理解本文披露的各实施例。Various embodiments of the present invention have been described above, and the foregoing descriptions are exemplary, not exhaustive, and not limiting of the disclosed embodiments. Numerous modifications and variations will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The terminology used herein was chosen to best explain the principles of the embodiments, the practical application or technical improvement in the marketplace, or to enable others of ordinary skill in the art to understand the embodiments disclosed herein.

Claims (8)

1.一种电力调度操作方法,其特征在于,包括:1. A power dispatch operation method, characterized in that, comprising: 调度指挥控制系统获取已三审操作票信息,根据所述已三审操作票信息进行全票预演校核,并将所述已三审操作票信息发送至电网运行监控系统进行全票预演校核;所述已三审操作票包括倒母线操作令;The dispatching command and control system obtains the information of the third-trial operation ticket, conducts a full-vote rehearsal check according to the third-trial operation ticket information, and sends the third-trial operation ticket information to the power grid operation monitoring system for full-vote rehearsal verification; The above-mentioned third-instance operation ticket includes the busbar operation order; 如果调度指挥控制系统以及电网运行监控系统的全票预演校核均通过,则输出请求值班长批准操作的操作请求信息;如果调度指挥控制系统、电网运行监控系统的全票预演校核中任一个不通过,则中断电力调度操作,并输出全票预演校核失败的提示信息;If the unanimous rehearsal check of the dispatching command and control system and the power grid operation monitoring system is passed, the operation request information requesting the operation to be approved by the shift leader is output; , the power dispatching operation will be interrupted, and a prompt message indicating that the full-ticket rehearsal check fails will be output; 调度指挥控制系统获取值班长的批准操作信息,并根据所述批准操作信息进行电力调度操作;其中所述电力调度操作包括调度指挥控制系统以及电网运行监控系统分别依次对单条操作令进行预演校核,并在调度指挥控制系统、电网运行监控系统均预演校核通过时,下发操作指令至运行人员端,以告知运行人员根据单条操作令进行现场操作。The dispatching command and control system obtains the approved operation information of the shift leader, and performs power dispatching operation according to the approved operation information; wherein the power dispatching operation includes the dispatching command and control system and the power grid operation monitoring system respectively performing pre-rehearsal checks on a single operation order in turn. , and when the dispatching command and control system and the power grid operation monitoring system have passed the rehearsal check, the operation command will be issued to the operator to inform the operator to perform on-site operations according to a single operation command. 2.根据权利要求1所述的电力调度操作方法,其特征在于,所述电力调度操作具体包括:2. The power dispatch operation method according to claim 1, wherein the power dispatch operation specifically comprises: 调度指挥控制系统获取当前条操作令,并对所述当前条操作令进行预演校核,并在预演校核通过时,生成一关于当前条操作令的DCCS预演校核通过信息;The dispatch command and control system obtains the current operation order, performs a pre-rehearsal check on the current operation order, and generates a DCCS rehearsal check pass information about the current operation order when the rehearsal check is passed; 调度指挥控制系统发送一预演校核信息至电网运行监控系统;The dispatch command and control system sends a rehearsal check information to the power grid operation monitoring system; 电网运行监控系统根据所述预演校核信息对所述当前条操作令进行预演校核,并在预演校核通过时,发送一关于当前条操作令的OCS预演校核通过信息至调度指挥控制系统;The power grid operation monitoring system performs a pre-rehearsal check on the current operation order according to the rehearsal check information, and when the rehearsal check is passed, sends an OCS pre-rehearsal check pass information on the current operation order to the dispatch command and control system ; 调度指挥控制系统根据所述DCCS预演校核通过信息和所述OCS预演校核通过信息生成关于当前条操作令的操作指令,并下发操作指令至运行人员端;The dispatch command and control system generates an operation instruction about the current operation order according to the DCCS rehearsal check pass information and the OCS rehearsal check pass information, and issues the operation instruction to the operator; 调度指挥控制系统获取运行人员端上传的关于当前条操作令的操作结果信息,并根据所述操作结果信息进行系统状态校核,并将所述操作结果信息发送至电网运行监控系统进行系统状态校核;The dispatch command and control system obtains the operation result information about the current operation order uploaded by the operator, and checks the system status according to the operation result information, and sends the operation result information to the power grid operation monitoring system for system status checking. nuclear; 根据所述调度指挥控制系统以及电网运行监控系统的系统状态校核结果判定是否操作成功,并在判定操作成功时判定是否进入下一条操作令的电力调度操作。According to the system state check results of the dispatching command and control system and the power grid operation monitoring system, it is determined whether the operation is successful, and when it is determined that the operation is successful, it is determined whether to enter the power dispatching operation of the next operation order. 3.根据权利要求2所述的电力调度操作方法,其特征在于,当调度指挥控制系统对所述当前条操作令进行预演校核不通过时,则中断电力调度操作,并输出当前条操作令预演校核失败的提示信息。3. The electric power dispatching operation method according to claim 2, characterized in that, when the dispatching command and control system fails to pass the rehearsal check on the current operation order, the electric power dispatching operation is interrupted, and the current operation order is output. Rehearsal check failed prompt information. 4.根据权利要求2所述的电力调度操作方法,其特征在于,当电网运行监控系统对所述当前条操作令进行预演校核不通过时,则中断电力调度操作,并输出当前条操作令预演校核失败的提示信息。4 . The power dispatch operation method according to claim 2 , wherein when the power grid operation monitoring system fails to pass the pre-rehearsal check of the current operation order, the power dispatch operation is interrupted and the current operation order is output. 5 . Rehearsal check failed prompt information. 5.根据权利要求2所述的电力调度操作方法,其特征在于,所述调度指挥控制系统获取运行人员端上传的操作结果信息,并根据操作结果信息进行系统状态校核,并将所述操作结果信息发送至电网运行监控系统进行系统状态校核,包括:5 . The power dispatching operation method according to claim 2 , wherein the dispatching command and control system obtains the operation result information uploaded by the operator, and checks the system state according to the operation result information, and the operation The result information is sent to the power grid operation monitoring system to check the system status, including: 调度指挥控制系统获取运行人员端上传的关于当前条操作令的操作结果信息,根据所述操作结果信息进行系统状态校核,并在系统状态校核通过时生成一关于当前操作令的DCCS系统状态校核通过信息;The dispatching command and control system obtains the operation result information about the current operation order uploaded by the operator, checks the system state according to the operation result information, and generates a DCCS system state about the current operation order when the system state check passes. Check the passed information; 调度指挥控制系统根据所述操作结果信息发送至电网运行监控系统;The dispatching command and control system sends the operation result information to the power grid operation monitoring system according to the operation result information; 电网运行监控系统根据所述操作结果信息进行系统状态校核,并在系统状态校核通过时生成一关于当前操作令的OCS系统状态校核通过信息,并将所述OCS系统状态校核通过信息发送至调度指挥控制系统。The power grid operation monitoring system performs a system state check according to the operation result information, and generates an OCS system state check pass information about the current operation order when the system state check passes, and sends the OCS system state check pass information Sent to the dispatch command and control system. 6.根据权利要求5所述的电力调度操作方法,其特征在于,所述根据所述调度指挥控制系统以及电网运行监控系统的系统状态校核结果判定是否操作成功,并在判定操作成功时判定是否进入下一条操作令的电力调度操作,包括:6 . The power dispatch operation method according to claim 5 , wherein, according to the system state check results of the dispatch command and control system and the power grid operation monitoring system, it is determined whether the operation is successful, and when it is determined that the operation is successful, it is determined whether the operation is successful. 7 . Whether to enter the power dispatch operation of the next operation order, including: 当调度指挥控制系统获取到所述DCCS系统状态校核通过信息以及所述OCS系统状态校核通过信息时,调度指挥控制系统判定当前条操作令是否为已三审操作票信息中的最后一条操作令;若为最后一条操作令,则结束电力调度操作,若不为最后一条操作令,则进入下一条操作令的电力调度操作。When the dispatching command and control system obtains the DCCS system status check pass information and the OCS system status check pass information, the dispatch command and control system determines whether the current operation order is the last operation in the third-trial operation ticket information order; if it is the last operation order, end the power dispatching operation; if it is not the last operation order, enter the power dispatching operation of the next operation order. 7.根据权利要求5所述的电力调度操作方法,其特征在于,所述已三审操作票具体包括根据最终目标方式进行置位操作的倒母线操作令。7 . The power dispatching operation method according to claim 5 , wherein the third-trial operation ticket specifically includes an operation order for the busbar inverting the reset operation according to the final target method. 8 . 8.一种电力调度操作系统,其特征在于,用于实现权利要求1-7任一项所述的电力调度操作方法,所述系统包括:调度指挥控制系统和电网运行监控系统;8. A power dispatching operating system, characterized in that, for realizing the power dispatching operation method according to any one of claims 1-7, the system comprises: a dispatching command and control system and a power grid operation monitoring system; 其中,所述调度指挥控制系统用于获取已三审操作票信息,根据所述已三审操作票信息进行全票预演校核,并将所述已三审操作票信息发送至电网运行监控系统进行全票预演校核;所述已三审操作票包括倒母线操作令;Wherein, the dispatching command and control system is used to obtain the information of the third-trial operation ticket, perform a full-vote rehearsal check according to the third-trial operation ticket information, and send the third-trial operation ticket information to the power grid operation monitoring system for Full-ticket rehearsal check; the third-trial operation ticket includes the busbar operation order; 其中,如果调度指挥控制系统以及电网运行监控系统的全票预演校核均通过,则输出请求值班长批准操作的操作请求信息;如果调度指挥控制系统、电网运行监控系统的全票预演校核中任一个不通过,则中断电力调度操作,并输出全票预演校核失败的提示信息;Among them, if the unanimous rehearsal check of the dispatching command and control system and the power grid operation monitoring system is passed, the operation request information requesting the operation to be approved by the shift leader is output; If it does not pass, the power dispatching operation will be interrupted, and a prompt message that the full-ticket rehearsal check fails will be output; 其中,所述调度指挥控制系统还用于获取值班长的批准操作信息,并根据所述批准操作信息进行电力调度操作;其中所述电力调度操作包括调度指挥控制系统以及电网运行监控系统分别依次对单条操作令进行预演校核,并在调度指挥控制系统、电网运行监控系统均预演校核通过时,下发操作指令至运行人员端,以告知运行人员根据单条操作令进行现场操作。Wherein, the dispatching command and control system is also used to obtain the approved operation information of the shift leader, and perform power dispatching operation according to the approved operation information; wherein the power dispatching operation includes that the dispatching command and control system and the power grid operation monitoring system are respectively used to perform the power dispatching operation in turn. A single operation order is rehearsed and checked, and when the dispatching command and control system and the power grid operation monitoring system have passed the rehearsal check, an operation order is issued to the operator to inform the operator to perform on-site operations according to a single operation order.
CN202010407497.4A 2020-05-14 2020-05-14 Power dispatching operation method and system Active CN111641262B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010407497.4A CN111641262B (en) 2020-05-14 2020-05-14 Power dispatching operation method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010407497.4A CN111641262B (en) 2020-05-14 2020-05-14 Power dispatching operation method and system

Publications (2)

Publication Number Publication Date
CN111641262A true CN111641262A (en) 2020-09-08
CN111641262B CN111641262B (en) 2022-03-04

Family

ID=72331936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010407497.4A Active CN111641262B (en) 2020-05-14 2020-05-14 Power dispatching operation method and system

Country Status (1)

Country Link
CN (1) CN111641262B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205583847U (en) * 2016-04-06 2016-09-14 国网安徽省电力公司培训中心 A switching operation simulation rehearsal system
CN109191082A (en) * 2018-09-18 2019-01-11 广东电网有限责任公司 A kind of method for programming of dispatching platform, system and computer readable storage medium
CN109245307A (en) * 2018-10-31 2019-01-18 特变电工南京智能电气有限公司 A kind of remote dispatching Programmed control method
CN110138092A (en) * 2019-06-18 2019-08-16 国网湖北省电力有限公司电力科学研究院 Transformer substation sequence control system and method with regulation main website Security Checking function
US10439434B2 (en) * 2016-03-09 2019-10-08 Florida Power & Light Company Impedance shift analysis to predict failures in an electrical power distribution network

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10439434B2 (en) * 2016-03-09 2019-10-08 Florida Power & Light Company Impedance shift analysis to predict failures in an electrical power distribution network
CN205583847U (en) * 2016-04-06 2016-09-14 国网安徽省电力公司培训中心 A switching operation simulation rehearsal system
CN109191082A (en) * 2018-09-18 2019-01-11 广东电网有限责任公司 A kind of method for programming of dispatching platform, system and computer readable storage medium
CN109245307A (en) * 2018-10-31 2019-01-18 特变电工南京智能电气有限公司 A kind of remote dispatching Programmed control method
CN110138092A (en) * 2019-06-18 2019-08-16 国网湖北省电力有限公司电力科学研究院 Transformer substation sequence control system and method with regulation main website Security Checking function

Also Published As

Publication number Publication date
CN111641262B (en) 2022-03-04

Similar Documents

Publication Publication Date Title
CN107092222B (en) Power grid regulation and control operation management system based on anti-mischecking and analysis integration
CN103441570A (en) One-button type sequential control operation control method based on integrated information platform
CN105305444A (en) Distribution network intelligent alarm and processing method based on integrated allocation
CN107819323B (en) The online O&M method and system of secondary equipment of intelligent converting station based on visual presentation
CN103679350A (en) Power grid switching operation ticket automatic generating system and method
CN101834469B (en) Transformer substation-dispatching center two-stage distribution type restoration control method
CN104678960A (en) Offline type dispatching operation ticket system and method based on field error prevention and simulated ticket training
CN104463696A (en) Power grid operating risk recognition and prevention method and system
CN108053041B (en) System and method for abnormal identification and error prevention of secondary system in substation multi-association scenario
CN104933535A (en) An intelligent monitoring operation ticket management method and a system thereof
CN110988559A (en) Online monitoring method for the whole life cycle of substation DC system based on Internet of Things
CN107332349A (en) A kind of online O&M method and system of secondary equipment of intelligent converting station
CN105955159A (en) Regulation operation anti-misoperation checking method based on anti-misoperation rule source side maintenance
CN105680441B (en) Simulation based on stimulated replacement technology is to a device
CN117277552A (en) Smart power grid one-key sequential control checking system and method
CN110349048A (en) Substation's multidimensional data runs interactive controlling platform and failure method of disposal
CN107230160A (en) A kind of 10kV line trippings wrong report is intelligent to judge implementation method
CN105759150A (en) Test system and method for transformer substation secondary device prefabricated cabin
CN103208089B (en) Electric network intelligent scheduling system and method based on mode identification technology
CN114398947A (en) Expert system-based power grid fault automatic classification method and system
CN111641262A (en) Power dispatching operation method and system
CN109861393B (en) Processing method for preventing error locking and execution terminal
CN201298172Y (en) Data synchronization fault diagnosis device for centralized control station
CN109768619B (en) Monitoring information automatic debugging system and debugging method
CN104332992B (en) Power distribution network looped network figure security verification method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant