CN111622121A - Reeving method for hoisting single-tower cable - Google Patents

Reeving method for hoisting single-tower cable Download PDF

Info

Publication number
CN111622121A
CN111622121A CN202010494537.3A CN202010494537A CN111622121A CN 111622121 A CN111622121 A CN 111622121A CN 202010494537 A CN202010494537 A CN 202010494537A CN 111622121 A CN111622121 A CN 111622121A
Authority
CN
China
Prior art keywords
cable
hoisting
rope
traction
river
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010494537.3A
Other languages
Chinese (zh)
Inventor
马欣
曾凡福
陈慧
白利勇
吉俊华
骆国建
孙学帅
赵恒恒
郝江平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Engineering Group Co Ltd
Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Original Assignee
China Railway First Engineering Group Co Ltd
Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Engineering Group Co Ltd, Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd filed Critical China Railway First Engineering Group Co Ltd
Priority to CN202010494537.3A priority Critical patent/CN111622121A/en
Publication of CN111622121A publication Critical patent/CN111622121A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Control And Safety Of Cranes (AREA)

Abstract

The invention provides a reeving method for hoisting a single tower cable, which comprises the following steps: 1) arranging a tower crane on one side of a river bank, and bringing the guide rope to the opposite bank of the river by a ferry; 2) the head end of the guide rope is pulled to the mountain top of the opposite bank of the river by a first winch; the tail end of the guide rope is connected with a traction rope; 3) the first winch continues to pull the traction rope, the traction rope is driven to cross the valley, and then the traction rope is driven to return to one side of the river bank through the guide rope after passing through the steering wheel of the first ground anchor on the mountain top; the traction cable is attached with a main cable through a rope clamp; 4) the traction cable drives the main cable to penetrate through a steering wheel of a second ground anchor arranged on one side of the river bank, turn over a cable saddle on the top of the tower crane, penetrate into the crown block, cross the valley and reach the first ground anchor at the top of the mountain to be fixed. The single-tower cable hoisting method can be applied to complex terrains which are difficult to reach for traffic on one side of a valley.

Description

Reeving method for hoisting single-tower cable
Technical Field
The invention relates to a construction method, in particular to a cable threading method for hoisting a cable.
Background
For a single-tower cable plain crane with one shore being a combination of a hanging hook and a tower, the other shore is in a complex terrain and has a steep mountain terrain, and when traffic cannot reach, a cable penetrating process without a tower rock anchor is adopted, which cannot be realized by the prior art.
The existing reeving process construction has the defects that the reeving construction speed of the main rope with large diameter and heavy weight is low, the safety construction guarantee rate is low, and the non-uniformity of the tightening degree cannot be effectively controlled and adjusted when several main ropes (bearing ropes) form a group and work simultaneously.
The traction cable is unreasonably arranged for traction routing, and the reduction of traction force and the adjustment of speed cannot be realized.
For the arrangement of the crane cable routing, the number of the pulley blocks is too small, the tension of the crane cable is too large, and the arrangement of the cable tail is different, so that the lifting hook cannot be lowered in the no-load process, and the like.
Disclosure of Invention
The invention aims to solve the main technical problem of providing a reeving method for hoisting a single tower cable, which can be applied to a complex terrain with traffic not easy to reach on one side of a valley.
In order to solve the technical problem, the invention provides a reeving method for hoisting a single tower cable, which comprises the following steps:
1) arranging a tower crane on one side of a river bank, and bringing the guide rope to the opposite bank of the river by a ferry;
2) the head end of the guide rope is pulled to the mountain top of the opposite bank of the river by a first winch; the tail end of the guide rope is connected with a traction rope;
3) the first winch continues to pull the traction rope, the traction rope is driven to cross the valley, and then the traction rope is driven to return to one side of the river bank through the guide rope after passing through the steering wheel of the first ground anchor on the mountain top; the traction cable is attached with a main cable through a rope clamp;
4) the traction cable drives the main cable to penetrate through a steering wheel of a second ground anchor arranged on one side of the river bank, turn over a cable saddle on the top of the tower crane, penetrate through the crown block, cross a valley and reach a first ground anchor on the top of a mountain to be fixed;
5) a plurality of main cables are repeatedly installed, and each main cable is fixedly connected with two adjacent main cables through a cable clamp;
6) installing a tightening pulley on a main cable on one side of a river bank and performing tightening operation to adjust the sag of the main cable;
7) installing a circulating cable, wherein the circulating cable passes through a second winch, and two ends of the circulating cable are connected with the crown block after passing through a first movable pulley respectively;
8) and installing a hoisting cable, wherein one end of the hoisting cable is connected with the third winch, and the other end of the hoisting cable is steered through the fixed pulley and then is anchored on the hoisting cable counter weight through the second movable pulley.
In a preferred embodiment: and two ends of the circulating cable respectively pass through the 4 first movable pulleys.
In a preferred embodiment: the hoisting cable passes through 16 second movable pulleys.
Compared with the prior art, the technical scheme of the invention has the following beneficial effects:
1. the invention provides a single tower cable hoisting method, which is characterized in that a guide rope and a temporary traction rope are used for threading, so that the construction difficulty is reduced, the safety and reliability of construction are ensured, and the construction speed is accelerated.
2. The invention provides a single-tower cable hoisting method, wherein 6 main cables are mutually communicated during installation of the main cables, and a group of main cables are tightened together by using a tightening pulley on a left bank, so that the stress uniformity of each main cable is ensured, and the safety accident caused by overlarge stress of a single main cable during construction is avoided.
3. The invention provides a single tower cable hoisting method, wherein a traction cable is arranged by adopting a '4' walking line, so that the moving stability is ensured, and the traction tension of a winch is reduced.
4. The invention provides a single-tower cable hoisting method, a hoisting cable is arranged along a '16' line, the hoisting stability is greatly improved, and the hoisting force of a winch is reduced. The hoisting cable is arranged in a threading way by adopting a flexible threading method, so that the hoisting cable is prevented from being stirred.
5. The invention provides a single tower cable hoisting method, which is characterized in that a bearing cable of a hoisting cable is installed, so that the horizontal section of the hoisting cable cannot bulge.
6. The invention provides a single tower cable hoisting method, which anchors the rope head of a hoisting rope on the counterweight of the hoisting rope, and solves the problem of the descending of the no-load hoisting rope.
Drawings
FIG. 1 is a view showing the overall layout of a cable crane according to a preferred embodiment of the present invention;
FIG. 2 is a schematic view of the installation of the endless cable according to the preferred embodiment of the present invention;
FIG. 3 is an elevation view of the installation of the endless cable in the preferred embodiment of the invention;
FIG. 4 is a schematic illustration of the installation of a hoist cable in accordance with a preferred embodiment of the present invention;
fig. 5 is a general layout of cables in a preferred embodiment of the invention.
Detailed Description
The invention is further described below with reference to the accompanying drawings.
Referring to fig. 1-5, the present invention provides a single tower cable hoisting method, comprising the following steps:
1) arranging a tower crane 1 on one side of a river bank, and bringing a guide rope to the opposite bank of the river by a ferry;
2) the head end of the guide rope is pulled to the mountain top of the opposite bank of the river by a first winch; the tail end of the guide rope is connected with a traction rope;
3) the first winch continues to pull the traction rope, the traction rope is driven to cross the valley, and then the traction rope is driven to return to one side of the river bank through the guide rope after passing through the steering wheel of the first ground anchor 2 on the mountain top; the main rope 3 is attached to the traction rope through a rope clamp;
4) the traction cable drives the main cable 3 to pass through a steering wheel of a second ground anchor 4 arranged on one side of a river bank, turn over a cable saddle 5 on the top of the tower crane 1, penetrate through a crown block 6, cross a valley and reach a first ground anchor 2 on the top of a mountain for fixing;
5) a plurality of main ropes 3 are repeatedly installed, and each main rope 3 is fixedly connected with two adjacent main ropes 3 through rope clamps;
6) installing a tightening pulley on the main cable 3 on one side of the river bank and performing tightening operation to adjust the sag of the main cable 3;
7) installing a circulating cable 7, wherein the circulating cable 7 passes through a second winch 8, and both ends of the circulating cable are respectively connected with a crown block 6 after passing through 4 first movable pulleys 9; the rope penetrating mode of 'walking 4' enables the overhead travelling crane 6 to longitudinally move for 0.25 circle every time the second winch 8 rotates for one circle, so that the movement is more stable, and the traction force used by the second winch 8 can be reduced by 75%.
7) And installing a hoisting cable 10, wherein one end of the hoisting cable 10 is connected with a third winch 11, and the other end of the hoisting cable 10 is steered by a fixed pulley and then anchored on a hoisting cable counterweight by 16 second movable pulleys 12. The 16-running rope penetrating mode enables the overhead travelling crane 6 to longitudinally move for 0.0625 circle every time the third winch 11 rotates for one circle, so that the hoisting is more stable and the precision is higher, but the traction force used by the winch is reduced by 93.75 percent. Meanwhile, when the sports car moves too far away from the cable tower, in order to prevent redundant ropes from stirring and bulging when the horizontal section of the hoisting cable 10 is too long, cable bearing devices are installed at intervals of 10m and are connected through phi 8 thin steel wire ropes. When the sports car moves to the opposite bank of the river, the distance between the cable bearing devices is opened, and the hoisting cable 10 is supported. When the sports car runs back on the same day, the cable bearing devices are gathered together under the action of self weight, and the longitudinal movement of the sports car is not influenced. Meanwhile, in order to ensure that the lifting hook can fall to the ground when no load exists, the rope head of the hoisting rope 10 is anchored on the counterweight of the hoisting rope 10, so that the hoisting rope 10 is lighter.
The above examples are provided only for illustrating the present invention and are not intended to limit the present invention. Changes, modifications, etc. to the above-described embodiments are intended to fall within the scope of the claims of the present invention as long as they are in accordance with the technical spirit of the present invention.

Claims (3)

1. A reeving method for hoisting a single tower cable is characterized by comprising the following steps:
1) arranging a tower crane on one side of a river bank, and bringing the guide rope to the opposite bank of the river by a ferry;
2) the head end of the guide rope is pulled to the mountain top of the opposite bank of the river by a first winch; the tail end of the guide rope is connected with a traction rope;
3) the first winch continues to pull the traction rope, the traction rope is driven to cross the valley, and then the traction rope is driven to return to one side of the river bank through the guide rope after passing through the steering wheel of the first ground anchor on the mountain top; the traction cable is attached with a main cable through a rope clamp;
4) the traction cable drives the main cable to penetrate through a steering wheel of a second ground anchor arranged on one side of the river bank, turn over a cable saddle on the top of the tower crane, penetrate through the crown block, cross a valley and reach a first ground anchor on the top of a mountain to be fixed;
5) a plurality of main cables are repeatedly installed, and each main cable is fixedly connected with two adjacent main cables through a cable clamp;
6) installing a tightening pulley on a main cable on one side of a river bank and performing tightening operation to adjust the sag of the main cable;
7) installing a circulating cable, wherein the circulating cable passes through a second winch, and two ends of the circulating cable are connected with the crown block after passing through a first movable pulley respectively;
8) and installing a hoisting cable, wherein one end of the hoisting cable is connected with the third winch, and the other end of the hoisting cable is steered through the fixed pulley and then is anchored on the hoisting cable counter weight through the second movable pulley.
2. The reeving method for single tower cable hoisting according to claim 1, wherein: and two ends of the circulating cable respectively pass through the 4 first movable pulleys.
3. The reeving method for single tower cable hoisting according to claim 1, wherein: the hoisting cable passes through 16 second movable pulleys.
CN202010494537.3A 2020-06-03 2020-06-03 Reeving method for hoisting single-tower cable Pending CN111622121A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010494537.3A CN111622121A (en) 2020-06-03 2020-06-03 Reeving method for hoisting single-tower cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010494537.3A CN111622121A (en) 2020-06-03 2020-06-03 Reeving method for hoisting single-tower cable

Publications (1)

Publication Number Publication Date
CN111622121A true CN111622121A (en) 2020-09-04

Family

ID=72257252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010494537.3A Pending CN111622121A (en) 2020-06-03 2020-06-03 Reeving method for hoisting single-tower cable

Country Status (1)

Country Link
CN (1) CN111622121A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3071519D1 (en) * 1979-06-29 1986-05-07 Walter Freller Construction element adjustable in length
JPS6429507A (en) * 1987-07-24 1989-01-31 Ishikawajima Harima Heavy Ind Method of supporting catwalk for suspension bridge cable erection in method of air spinning construction
RU2309216C2 (en) * 2005-09-30 2007-10-27 Открытое акционерное общество ОАО "Институт по изысканиям и проектированию мостовых переходов"-"Гипротрансмост" Bridge span structure protrusion device
CN101224856A (en) * 2007-12-20 2008-07-23 中铁大桥局股份有限公司 Long-span load-carrying cable lifting machine and mounting method therefor
CN101323419A (en) * 2008-04-23 2008-12-17 中铁十三局集团有限公司 Non-tower cable crane
CN101684639A (en) * 2009-08-28 2010-03-31 中国第一冶金建设有限责任公司 Process method for construction of steel-structured suspension bridge and light type cable carrying crane specially used in same
CN102808382A (en) * 2012-08-28 2012-12-05 中铁七局集团第五工程有限公司 Method for constructing arch bridge in V-shaped valley without tower
CN105565176A (en) * 2016-02-03 2016-05-11 中铁港航局集团有限公司 Single-tower asymmetric cable crane
CN106638326A (en) * 2017-01-19 2017-05-10 中铁十六局集团第二工程有限公司 Construction system for hoisting cable tower-free bridge cable and construction method
CN106672786A (en) * 2017-03-20 2017-05-17 福建农林大学 Wheel penetrated counter-weight light travelling car for logging in mountainous region
CN208088097U (en) * 2018-03-08 2018-11-13 中交武汉港湾工程设计研究院有限公司 A kind of three-tower suspension bridge erection of main beam constructing structure
CN109853394A (en) * 2019-03-25 2019-06-07 安徽省路港工程有限责任公司 Arch bridge cable hoisting tower button integrated construction engineering method

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3071519D1 (en) * 1979-06-29 1986-05-07 Walter Freller Construction element adjustable in length
JPS6429507A (en) * 1987-07-24 1989-01-31 Ishikawajima Harima Heavy Ind Method of supporting catwalk for suspension bridge cable erection in method of air spinning construction
RU2309216C2 (en) * 2005-09-30 2007-10-27 Открытое акционерное общество ОАО "Институт по изысканиям и проектированию мостовых переходов"-"Гипротрансмост" Bridge span structure protrusion device
CN101224856A (en) * 2007-12-20 2008-07-23 中铁大桥局股份有限公司 Long-span load-carrying cable lifting machine and mounting method therefor
CN101323419A (en) * 2008-04-23 2008-12-17 中铁十三局集团有限公司 Non-tower cable crane
CN101684639A (en) * 2009-08-28 2010-03-31 中国第一冶金建设有限责任公司 Process method for construction of steel-structured suspension bridge and light type cable carrying crane specially used in same
CN102808382A (en) * 2012-08-28 2012-12-05 中铁七局集团第五工程有限公司 Method for constructing arch bridge in V-shaped valley without tower
CN105565176A (en) * 2016-02-03 2016-05-11 中铁港航局集团有限公司 Single-tower asymmetric cable crane
CN106638326A (en) * 2017-01-19 2017-05-10 中铁十六局集团第二工程有限公司 Construction system for hoisting cable tower-free bridge cable and construction method
CN106672786A (en) * 2017-03-20 2017-05-17 福建农林大学 Wheel penetrated counter-weight light travelling car for logging in mountainous region
CN208088097U (en) * 2018-03-08 2018-11-13 中交武汉港湾工程设计研究院有限公司 A kind of three-tower suspension bridge erection of main beam constructing structure
CN109853394A (en) * 2019-03-25 2019-06-07 安徽省路港工程有限责任公司 Arch bridge cable hoisting tower button integrated construction engineering method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张世保等: "《缆索起重机管理总结》", 31 July 2017, 中国三峡出版社 *

Similar Documents

Publication Publication Date Title
CN212670303U (en) Stay cable beam end mounting structure
CN111691305A (en) Method for installing main beam of suspension bridge
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN107476195A (en) A kind of suspension bridge transports the fortune beam tackle system of stiff girder
CN107344697A (en) Cable boom hoisting
CN111101448A (en) Quick traction equipment and traction method for stay cable beam end winch
CN212475874U (en) Bridge cable crane system
CN209194361U (en) A kind of fixed structure of suspension cable bridge section lifting hoisting platform
CN111622121A (en) Reeving method for hoisting single-tower cable
CN208994999U (en) Mobile cable crane device
CN115806244A (en) Cable saddle transverse sliding device, cable saddle system and transverse moving method
CN108018778B (en) Catwalk cable erection traction system and catwalk cable rapid erection method for non-navigable water area
CN109322251A (en) A kind of fixed structure and fixing means of suspension cable bridge section lifting hoisting platform
CN116201010A (en) Crawling type construction platform for main cable of suspension bridge and travelling control method of crawling type construction platform
CN211283445U (en) Cable carries loop wheel machine installation mechanism
CN113529579A (en) Cableway transfer device based on circulation type steel wire rope catenary structure
CN113845043A (en) Cable crane and installation method thereof
CN107178044A (en) A kind of method that I-shaped gooseneck is worn under during jacking bridge and culvert track strengthening
CN220847103U (en) Suspension bridge overhead portal hoisting system
CN108221639B (en) Three tower suspension bridge girder installation construction structures
CN207090834U (en) Cable boom hoisting
CN212174274U (en) Large-span suspension bridge cable crane traction system with combined type sports car and traction tackle
CN109264588B (en) Lower hanging type multi-tower continuous span cable crane with C-shaped crown block and crown block tower span method thereof
CN113789730B (en) Arch bridge tie rod suspension installation method
CN114525739B (en) Long heavy cable hanging installation method for multi-point hanging of under-bridge span cables

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200904