CN211283445U - Cable carries loop wheel machine installation mechanism - Google Patents

Cable carries loop wheel machine installation mechanism Download PDF

Info

Publication number
CN211283445U
CN211283445U CN201921221558.7U CN201921221558U CN211283445U CN 211283445 U CN211283445 U CN 211283445U CN 201921221558 U CN201921221558 U CN 201921221558U CN 211283445 U CN211283445 U CN 211283445U
Authority
CN
China
Prior art keywords
hoisting
distribution beam
pulling
walkway
top surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921221558.7U
Other languages
Chinese (zh)
Inventor
何加江
涂满明
刘润泽
宋小三
冯健翔
李兴华
郑大超
马晓东
江涛
赵子龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN201921221558.7U priority Critical patent/CN211283445U/en
Application granted granted Critical
Publication of CN211283445U publication Critical patent/CN211283445U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a cable carries loop wheel machine installation mechanism relates to bridge construction technical field, and this cable carries loop wheel machine installation mechanism includes: a walkway distribution beam; the hoisting distribution beam is arranged on the walkway distribution beam in a sliding mode and is configured to move in the horizontal direction on the top surface of the walkway distribution beam under the pulling of the pulling mechanism; the hoisting pulley block is hung at the bottom of the hoisting distribution beam and is configured to move in the horizontal direction below the pavement distribution beam under the driving of the hoisting distribution beam; a hoisting steel wire rope wound on the hoisting pulley block; the pulling mechanism is arranged on the top surface of the hoisting distribution beam; and the pull-back pulleys are arranged on the top surface of the hoisting distribution beam and are respectively positioned on different sides of the hoisting distribution beam with the pulling mechanism. The utility model discloses change current cable and carry loop wheel machine installation mechanism's structure, under the prerequisite that conveniently removes, more guaranteed certain stability, improve the factor of safety of construction.

Description

Cable carries loop wheel machine installation mechanism
Technical Field
The utility model relates to a bridge construction technical field, concretely relates to cable carries loop wheel machine installation mechanism.
Background
In the traditional cable crane installation construction process, because two tower top portal main trusses are positioned on the tower top, the space between the tower top portal main trusses is small and is influenced by the width of a catwalk, the cable crane cannot be hoisted at the position between the two tower top portal main trusses, a walkway distribution beam must be overhung out, a cable crane walking mechanism and a cable crane load beam are vertically hoisted at the position where the walkway distribution beam is overhung out, and after the vertical hoisting is completed, in the transverse moving process, due to the blocking effect of the tower top portal main trusses in the middle, the cable crane walking mechanism can only be moved to the position right above a main cable in a skew pulling and oblique hoisting mode and then is lowered for walking installation. The hoisting construction method of the traditional cable crane walking mechanism comprises the following steps: when the cable crane walking mechanism is vertically hoisted to the position above the main cable through the hoisting steel wire rope, the movable pulley group and the hoisting distribution beam, the movable pulley group and the hoisting steel wire rope which are positioned at the position of the main cable on the pavement distribution beam are hooked on the cable crane walking mechanism, at the moment, the cable crane walking mechanism is simultaneously under the hanging action of the hoisting steel wire rope and the hoisting steel wire rope, then the movable pulley group is slowly tightened, the movable pulley group is loosened, the cable crane walking mechanism gradually moves to the position of the main cable, and finally the cable crane walking mechanism swings to the position right above the main cable to finish the transverse movement of the cable crane walking mechanism. The transverse moving mode of the load beam of the cable crane is the same as that of the running mechanism of the cable crane.
However, when the traditional cable crane running mechanism and the load beam transverse moving method are used for installing and constructing the cable crane, the following defects exist:
(1) the traditional hoisting method that the pavement distribution beam is cantilevered outside and then vertically hoisted at the cantilevered position is used, the hoisting weight is very limited, the simultaneous hoisting of the cable crane traveling mechanism and the cable crane load beam cannot be completed, and other equipment such as a steel strand, a winding and unwinding device and the like are hoisted simultaneously in the process of hoisting the cable crane main beam, so that the construction period is greatly prolonged;
(2) when the traditional method of obliquely pulling and obliquely lifting is used for swinging the cable carrier running mechanism and the cable carrier load beam, two winches are needed to respectively pull the pulley block and the pulley block, in the swinging process, the winches of the pulley block are pulled to continuously take up ropes so as to tighten the pulley block, the winches of the pulley block are pulled to continuously release the ropes so as to loosen the pulley block, and the swinging of the cable carrier running mechanism and the cable carrier load beam is to be completed, the two winches are required to be matched with each other, the rope winding and unwinding speed is kept the same, the construction difficulty is high, and the construction process is complex;
(3) in the swinging process, the cable crane walking mechanism or the cable crane load beam is always positioned between the hoisting distribution beam and is in an inclined hoisting state, the safety is low, the transverse force borne by the pavement distribution beam is very large, and measures are needed to prevent the hoisting distribution beam 5 and the hoisting distribution beam from sliding on the pavement distribution beam;
(4) two groups of hoisting distribution beams, two sets of power-driven pulley sets and two winches need to be prepared at the same time, so that the investment of material equipment is large, and the required cost is high;
therefore, there is a need for a cable crane mounting mechanism to solve the current technical problems.
Disclosure of Invention
To the defect that exists among the prior art, the utility model aims to provide a cable carries loop wheel machine installation mechanism changes current cable and carries loop wheel machine installation mechanism's structure, under the prerequisite of convenient removal, has more guaranteed certain stability, improves the factor of safety of construction.
In order to achieve the above purpose, the utility model adopts the technical proposal that:
in a first aspect, the utility model discloses a cable crane installation mechanism, cable crane installation mechanism includes:
a walkway distribution beam;
the hoisting distribution beam is arranged on the pavement distribution beam in a sliding mode and is configured to move in the horizontal direction on the top surface of the pavement distribution beam under the pulling of the pulling mechanism;
the hoisting pulley block is hoisted at the bottom of the hoisting distribution beam and is configured to move in the horizontal direction below the pavement distribution beam under the driving of the hoisting distribution beam;
the hoisting steel wire rope is wound on the hoisting pulley block and used for hoisting target equipment;
the pulling mechanism is arranged on the top surface of the hoisting distribution beam and used for pulling the hoisting distribution beam to enable the hoisting distribution beam to move towards the pulling mechanism on the top surface of the walkway distribution beam;
the lifting distribution beam top surface and the pulling mechanism are respectively located on pull-back pulleys on different sides of the lifting distribution beam, the pull-back pulleys are used for being matched with the pulling mechanism to pull the lifting distribution beam, so that the lifting distribution beam is deviated from the top surface of the walkway distribution beam when the pulling mechanism moves.
On the basis of the technical scheme, the cable crane mounting mechanism comprises two pulling mechanisms; the pulling directions of the two pulling mechanisms are mutually vertical.
On the basis of the technical scheme, a moving channel is arranged in the walkway distributing beam along the length direction of the walkway distributing beam, and the hoisting pulley block is spaced from the inner wall of the moving channel.
On the basis of the above technical solution, the pulling mechanism includes:
the winch is fixedly arranged on one side of the top surface of the pavement distribution beam;
a first pulling rope wound on the winch, wherein one end of the first pulling rope is connected with the hoisting distribution beam;
the winch is used for pulling the hoisting distribution beam to move towards the winch on the top surface of the walkway distribution beam through the first pulling rope.
On the basis of the above technical solution, the pulling mechanism further includes:
one end of the second pulling rope is wound on the winch, and the other end of the second pulling rope penetrates through the pullback pulley to be connected with the hoisting distribution beam;
the winch is used for matching with the pull-back pulley, and the hoisting distribution beam is pulled to move away from the pulling mechanism on the top surface of the walkway distribution beam through the second pulling rope.
On the basis of the above technical solution, the pulling mechanism includes:
the feed-through jack is fixedly arranged on the top surface of the walkway distribution beam;
one end of the third pulling rope is arranged on the through jack in a penetrating mode, and the other end of the third pulling rope is connected with the hoisting distribution beam;
the penetrating jack is used for pulling the hoisting distribution beam to move towards or away from the penetrating jack on the top surface of the walkway distribution beam through the third pulling rope.
On the basis of the technical scheme, the hoisting distribution beam comprises:
a cross beam;
the vertical beams are vertically arranged on the bottom surface of the cross beam and are arranged in pairs, and the number of the vertical beams is at least two;
the vertical beam can be slidably arranged on the walkway distribution beam, and the hoisting pulley block is hung at the bottom of the cross beam;
the pulling mechanism is connected with the cross beam or any vertical beam.
Compared with the prior art, the utility model has the advantages of:
the utility model discloses change current cable and carry loop wheel machine installation mechanism's structure, under the prerequisite that conveniently removes, more guaranteed certain stability, improve the factor of safety of construction.
Drawings
Fig. 1 is a schematic structural view of a mounting mechanism of a cable crane according to an embodiment of the present invention;
fig. 2 is a schematic structural view of a walkway distribution beam in the installation mechanism of the cable crane according to the embodiment of the present invention;
fig. 3 is a schematic structural view of a distribution beam hoisted in the installation mechanism of the cable crane according to the embodiment of the present invention;
fig. 4 is a schematic bottom structure view of a distribution beam hoisted in the installation mechanism of the cable crane according to the embodiment of the present invention;
fig. 5 is a schematic structural view illustrating a first operation performed when the cable crane mounting mechanism of the embodiment of the present invention employs a hoist;
fig. 6 is a schematic structural view illustrating a second operation performed when the cable crane mounting mechanism of the embodiment of the present invention employs a hoist;
fig. 7 is a schematic structural view illustrating a first operation performed when the cable crane mounting mechanism of the embodiment of the present invention employs a center-penetrating jack;
FIG. 8 is a schematic structural view of a second embodiment of the present invention in which a center-feed jack is used as the cable crane mounting mechanism;
fig. 9 is a schematic structural view of a conventional installation scheme of a cable crane according to an embodiment of the present invention;
fig. 10 is a schematic structural view of a first pulling mechanism of the cable crane mounting mechanism according to an embodiment of the present invention;
fig. 11 is a schematic structural view of a second pulling mechanism of the cable crane mounting mechanism according to an embodiment of the present invention;
fig. 12 is an illustration of the orientation of the first and second pulling mechanisms of the cable crane mounting mechanism in an embodiment of the present invention;
in the figure: 1. a walkway distribution beam; 10. a moving channel; 2. hoisting the distribution beam; 20. a cross beam; 21. erecting a beam; 3. hoisting a pulley block; 4. hoisting a steel wire rope; 5. a pulling mechanism; 50. a winch; 51. a first pulling rope; 52. a second pulling rope; 53. a feed-through jack; 54. A third pulling rope; 5a, a first pulling mechanism; 5b, a second pulling mechanism; 6. pulling back the pulley; 7. a tower top portal; 80. a main truss of the tower top portal; 81. a catwalk; 82. a walkway distribution beam; 83. a first hoisting steel wire rope; 84. a first set of mobile trolleys; 85. a first hoisting distribution beam; 86. a second hoisting distribution beam; 87. a second set of mobile trolleys; 88. a second hoisting steel wire rope; 91. A target device; 92. a main cable.
Detailed Description
The embodiments of the present invention will be described in further detail below with reference to the accompanying drawings.
In order to achieve the technical effects, the general idea of the application is as follows:
a cable loader mounting mechanism, comprising:
a walkway distribution beam 1;
the hoisting distribution beam 2 is slidably arranged on the pavement distribution beam 1, and the hoisting distribution beam 2 is configured to move in the horizontal direction on the top surface of the pavement distribution beam 1 under the pulling of the pulling mechanism 5;
the hoisting pulley block 3 is hung at the bottom of the hoisting distribution beam 2, and the hoisting pulley block 3 is configured to move in the horizontal direction below the pavement distribution beam 1 under the driving of the hoisting distribution beam 2;
a hoisting steel wire rope 4 wound on the hoisting pulley block 3, wherein the hoisting steel wire rope 4 is used for hoisting the target equipment 91;
the pulling mechanism 5 is arranged on the top surface of the hoisting distribution beam 2, and the pulling mechanism 5 is used for pulling the hoisting distribution beam 2 so that the hoisting distribution beam 2 moves towards the pulling mechanism 5 on the top surface of the walkway distribution beam 1;
the pulling mechanism is arranged on the top surface of the hoisting distribution beam 2 and is respectively positioned on the different sides of the hoisting distribution beam 2 with the pulling mechanism 5, and the pulling pulley 6 is used for matching with the pulling mechanism 5 to pull the hoisting distribution beam 2, so that the hoisting distribution beam 2 deviates from the pulling mechanism 5 on the top surface of the walkway distribution beam 1 to move.
The embodiment of the utility model provides a, change current cable and carry loop wheel machine installation mechanism's structure, under the prerequisite that conveniently removes, more guaranteed certain stability, improve the factor of safety of construction.
Referring to fig. 1 to 9, a structural embodiment of the present invention provides a cable crane mounting mechanism, comprising:
a walkway distribution beam 1;
the hoisting distribution beam 2 is slidably arranged on the pavement distribution beam 1, and the hoisting distribution beam 2 is configured to move in the horizontal direction on the top surface of the pavement distribution beam 1 under the pulling of the pulling mechanism 5;
the hoisting pulley block 3 is hung at the bottom of the hoisting distribution beam 2, and the hoisting pulley block 3 is configured to move in the horizontal direction below the pavement distribution beam 1 under the driving of the hoisting distribution beam 2;
a hoisting steel wire rope 4 wound on the hoisting pulley block 3, wherein the hoisting steel wire rope 4 is used for hoisting the target equipment 91;
the pulling mechanism 5 is arranged on the top surface of the hoisting distribution beam 2, and the pulling mechanism 5 is used for pulling the hoisting distribution beam 2 so that the hoisting distribution beam 2 moves towards the pulling mechanism 5 on the top surface of the walkway distribution beam 1;
the pulling mechanism is arranged on the top surface of the hoisting distribution beam 2 and is respectively positioned on the different sides of the hoisting distribution beam 2 with the pulling mechanism 5, and the pulling pulley 6 is used for matching with the pulling mechanism 5 to pull the hoisting distribution beam 2, so that the hoisting distribution beam 2 deviates from the pulling mechanism 5 on the top surface of the walkway distribution beam 1 to move.
In the embodiment of the utility model, on the basis of the walkway distributing beam 1, the hoisting distributing beam 2 is slidably arranged on the walkway distributing beam 1, on one hand, the hoisting distributing beam 2 can slide on the walkway distributing beam 1, on the other hand, the hoisting pulley block 3 and the hoisting steel wire rope 4 at the bottom can be hoisted, when the target equipment 91 needs to be hoisted, the target equipment 91 is connected with the hoisting steel wire rope 4, and the hoisting steel wire rope 4 is hoisted through the hoisting pulley block 3 and is connected with the bottom of the hoisting distributing beam 2;
when it is necessary to move the hoist distribution beam 2 and thus the target device 91 at the bottom of the hoist distribution beam 2, there are two cases:
the first working condition is that when the target equipment 91 needs to move towards the pulling mechanism 5, the pulling mechanism 5 is directly utilized and connected with the hoisting distribution beam 2 through a rope structure, the pulling mechanism 5 is started, the hoisting distribution beam 2 is directly pulled by the pulling mechanism 5, so that the hoisting distribution beam 2 moves towards the pulling mechanism 5, and the target equipment 91 is driven to move towards the pulling mechanism 5;
the second working condition is that when the target device 91 needs to be moved away from the pulling mechanism 5, a pullback pulley 6 is arranged on the top surface of the hoisting distribution beam 2 and on the different side of the hoisting distribution beam 2 from the pulling mechanism 5 respectively, that is, the hoisting distribution beam 2 is arranged between the pulling mechanism 5 and the pullback pulley 6, the pullback pulley 6 can be a fixed pulley which is vertically arranged, the pulling mechanism 5 is wound on the pullback pulley 6 through a rope structure and is connected with the hoisting distribution beam 2 in a turning manner, the pulling mechanism 5 is started, the hoisting distribution beam 2 is pulled by the pulling mechanism 5 in cooperation with the pullback pulley 6, so that the hoisting distribution beam 2 is moved away from the pulling mechanism 5, and the target device 91 is driven to move away from the pulling mechanism 5;
the embodiment of the utility model changes the structure of the existing cable crane mounting mechanism, thereby ensuring certain stability and improving the safety factor of construction on the premise of convenient movement;
the problem that different winches are difficult to regulate and control in the prior art is solved, the structure of the walkway distributing beam 1 does not need to be modified, and the construction difficulty is reduced.
As shown in fig. 6, in the conventional cable crane installation and construction process, because two tower top portal main girders 80 are both located on the top of the tower, the space between the tower top portal main girders 80 is small, and the cable crane cannot be hoisted at the position between the two tower top portal main girders 80 due to the width of the catwalk 81, the walkway distributing beam 82 must be cantilevered out, the target equipment 91, such as a cable crane running mechanism and a cable crane load beam, is vertically hoisted at the position where the walkway distributing beam 82 is cantilevered out, and in the traversing process after the vertical hoisting is completed, the target equipment 91, such as a cable crane running mechanism, can only be swung to the position right above the main cable 92 in a skew-pulling and oblique-hoisting manner due to the blocking effect of the tower top portal main girders 80 in the middle, and then is lowered and installed;
the hoisting construction method of the traditional cable crane walking mechanism comprises the following steps: when the cable crane running mechanism is vertically hoisted to the position above the main cable 92 through the first hoisting steel wire rope 83, the first movable pulley group 84 and the first hoisting distribution beam 85, the second hoisting distribution beam 86, the second movable pulley group 87 and the second hoisting steel wire rope 88 which are positioned at the position of the main cable 92 on the walkway distribution beam 82 are used for hooking on the target equipment 91, namely the cable crane running mechanism, at the moment, the target equipment 91, namely the cable crane running mechanism, is subjected to the hanging action of the first hoisting steel wire rope 83 and the second hoisting steel wire rope 88 at the same time, then the second movable pulley group 87 is slowly tightened, the first movable pulley group 84 is loosened, the target equipment 91, namely the cable crane running mechanism, gradually moves to the position of the main cable 92, and finally the target equipment 91, namely the cable crane running mechanism, moves to the position right above the main cable 92, so that the target equipment 91, namely the cable crane running mechanism, is transversely moved;
similarly, the transverse moving mode of the load beam of the cable crane is the same as that of the running mechanism of the cable crane;
and the embodiment of the utility model provides a, then simplified target device 91, the sideslip operation of cable load crane walking mechanism or cable load crane load beam has improved the mechanism of sideslip promptly for the mounting means is more convenient, and provides the safety guarantee.
In another embodiment of the present invention, a moving channel 10 is disposed inside the walkway distributing beam 1 along the length direction of the walkway distributing beam 1, and the hoisting pulley block 3 is spaced from the inner wall of the moving channel 10;
the moving channel 10 is mainly used for providing a moving space for the hoisting pulley block 3 below the hoisting distribution beam 2, and the hoisting pulley block 3 does not collide with the inner wall of the moving channel 10 in the moving process of the hoisting pulley block 3.
In another embodiment of the present invention, the pulling mechanism 5 includes:
a winch 50 fixedly arranged on one side of the top surface of the walkway distributing beam 1;
a first pulling rope 51 wound on the winch 50, wherein one end of the first pulling rope 51 is connected with the hoisting distribution beam 2;
the hoist 50 is used for pulling the hoist distribution beam 2 to move toward the hoist 50 on the top surface of the walkway distribution beam 1 by the first pulling rope 51.
In the embodiment of the present invention, to the first working condition, that is, when the target device 91 needs to be moved toward the pulling mechanism 5, the winch 50 and the first pulling rope 51 can be specifically used to realize the first working condition, so that the horizontal movement of the target device 91 can be realized only by using a simple operation procedure.
In another embodiment of the present invention, the pulling mechanism 5 further comprises:
one end of a second pulling rope 52 is wound on the winch 50, and the other end of the second pulling rope 52 passes through the pullback pulley 6 to be connected with the hoisting distribution beam 2;
the hoist 50 is used for matching with the pullback pulley 6, and pulling the hoisting distribution beam 2 to move away from the pulling mechanism 5 on the top surface of the walkway distribution beam 1 through the second pulling rope 52.
The embodiment of the present invention provides an embodiment, to the second kind of behavior, when need deviate from pulling mechanism 5 with target device 91 and move, specifically can use hoist engine 50, second to draw and draw rope 52 and cooperate pull-back pulley 6 to realize to only utilize simple operation, can realize the horizontal migration work of target device 91.
In another embodiment of the present invention, the center line of gravity of the winch 50 coincides with the center line of gravity of the tower top gantry 7 located on the bottom surface of the walkway distribution beam 1;
the gravity line is a vertical line passing through the center of gravity of the object, i.e., the gravity line passes through the center of gravity of the object even if vertical.
In another embodiment of the present invention, the pulling mechanism 5 includes:
a feed-through jack 53 fixedly arranged on one side of the top surface of the walkway distribution beam 1;
one end of a third pulling rope 54 penetrates through the through jack 53, and the other end of the third pulling rope 54 is connected with the hoisting distribution beam 2;
the penetrating jack 53 is used for pulling the hoisting distribution beam 2 to move towards or away from the penetrating jack 53 on the top surface of the walkway distribution beam 1 through a third pulling rope 54;
the hoisting distribution beam 2 is pulled by the center-penetrating jack 53 in cooperation with the third pulling rope 54;
it should be noted that the center-penetrating jack 53 needs to be used in cooperation with other tension providers, and may specifically adopt a manual pulling method,
in addition, when the core component of the pulling mechanism 5 adopts the center-through jack 53, the pulling effect is poorer than that of the winch 50, and the pulling force is more, so that the use scene needs to be adjusted according to the actual situation.
The embodiment of the utility model provides an in another kind of embodiment, hoist and mount distributive girder 2 includes:
a cross member 20;
the vertical beams 21 are vertically arranged on the bottom surface of the cross beam 20 and are arranged in pairs, and the number of the vertical beams 21 is at least two;
wherein, the vertical beam 21 can be arranged on the pavement distribution beam 1 in a sliding way, and the hoisting pulley block 3 is hung at the bottom of the cross beam 20;
this structure enables the hoist distribution beam 2 to have a certain stability, the cross beam 20 is mainly used to participate in the work of hoisting the target equipment 91, and the vertical beam 21 mainly carries the weight and provides a structural foundation for horizontal movement.
The embodiment of the utility model provides an in another kind of embodiment, the quantity of founding roof beam 21 is a plurality of, and the tie point of respectively founding roof beam 21 top and crossbeam 20 bottom surface is regular polygon and arranges.
In another embodiment of the present invention, the pulling mechanism 5 is connected to the cross beam 20 or any of the vertical beams 21;
the specific connection mode can be winding, and the specific connection point can be adjusted according to the actual situation.
Referring to fig. 10 to 12, based on the same concept of the present invention, the present invention provides another structural embodiment of a cable crane mounting mechanism, specifically as follows:
this cable carries loop wheel machine installation mechanism includes:
a walkway distribution beam 1;
the hoisting distribution beam 2 is slidably arranged on the pavement distribution beam 1, and the hoisting distribution beam 2 is configured to move in the horizontal direction on the top surface of the pavement distribution beam 1 under the pulling of the pulling mechanism 5;
the hoisting pulley block 3 is hung at the bottom of the hoisting distribution beam 2, and the hoisting pulley block 3 is configured to move in the horizontal direction below the pavement distribution beam 1 under the driving of the hoisting distribution beam 2;
a hoisting steel wire rope 4 wound on the hoisting pulley block 3, wherein the hoisting steel wire rope 4 is used for hoisting the target equipment 91;
the two pulling mechanisms 5 are arranged on the top surfaces of the hoisting distribution beams 2, and the pulling mechanisms 5 are used for pulling the hoisting distribution beams 2 so that the hoisting distribution beams 2 move towards the pulling mechanisms 5 on the top surfaces of the walkway distribution beams 1;
the pulling directions of the two pulling mechanisms 5 are perpendicular to each other, and the two pulling mechanisms 5 are a first pulling mechanism 5a and a second pulling mechanism 5b respectively;
the pulling-back pulleys 6 are arranged on the top surface of the hoisting distribution beam 2 and are respectively located on different sides of the hoisting distribution beam 2 with the first pulling mechanism 5a, and the pulling-back pulleys 6 are used for being matched with the first pulling mechanism 5a to pull the hoisting distribution beam 2, so that the hoisting distribution beam 2 deviates from the first pulling mechanism 5a to move on the top surface of the walkway distribution beam 1.
In the embodiment of the present invention, during specific operation, the pulling direction of the first pulling mechanism 5a may be the same as the length direction of the main cable 92 corresponding to the cable crane, and the pulling direction of the second pulling mechanism 5b may be perpendicular to the length direction of the main cable 92 corresponding to the cable crane, so that the first pulling mechanism 5a and the second pulling mechanism 5b can adjust the position of the hoisting distribution beam 2 from two directions;
the embodiment of the utility model provides a change current cable and carry loop wheel machine installation mechanism's structure, under the prerequisite that conveniently removes, more guaranteed certain stability, improve the factor of safety of construction.
In another embodiment of the present invention, the first pulling mechanism 5a includes:
a winch 50 fixedly arranged on one side of the top surface of the walkway distributing beam 1;
a first pulling rope 51 wound on the winch 50, wherein one end of the first pulling rope 51 is connected with the hoisting distribution beam 2;
the winch 50 is used for pulling the hoisting distribution beam 2 to move towards the winch 50 on the top surface of the walkway distribution beam 1 through a first pulling rope 51;
specifically, the pulling direction of the winch 50 may be the same as the length direction of the main cable 92 corresponding to the cable crane;
in the embodiment of the present invention, for the first working condition, that is, when the target device 91 needs to be moved toward the first pulling mechanism 5a, the winch 50 and the first pulling rope 51 can be specifically used to realize the first pulling, so that the horizontal movement of the target device 91 can be realized only by using a simple operation procedure.
In another embodiment of the present invention, the first pulling mechanism 5a further comprises:
one end of a second pulling rope 52 is wound on the winch 50, and the other end of the second pulling rope 52 passes through the pullback pulley 6 to be connected with the hoisting distribution beam 2;
the hoist 50 is used for matching with the pullback pulley 6, and pulling the hoisting distribution beam 2 to move away from the pulling mechanism 5 on the top surface of the walkway distribution beam 1 through the second pulling rope 52.
The embodiment of the present invention provides an embodiment, to the second kind of behavior, when need deviate from first pulling mechanism 5a with target device 91 and move, specifically can use hoist engine 50, second to draw and drag rope 52 and cooperate pullback pulley 6 to realize to only utilize simple operation, can realize target device 91's horizontal migration work.
In another embodiment of the present invention, the center line of gravity of the winch 50 coincides with the center line of gravity of the tower top gantry 7 located on the bottom surface of the walkway distribution beam 1;
the gravity line is a vertical line passing through the center of gravity of the object, i.e., the gravity line passes through the center of gravity of the object even if vertical.
In another embodiment of the present invention, the second pulling mechanism 5b includes:
a penetrating jack 53 fixedly arranged on the top surface of the walkway distributing beam 1;
one end of a third pulling rope 54 penetrates through the through jack 53, and the other end of the third pulling rope 54 is connected with the hoisting distribution beam 2;
the penetrating jack 53 is used for pulling the hoisting distribution beam 2 to move towards or away from the penetrating jack 53 on the top surface of the walkway distribution beam 1 through a third pulling rope 54;
the hoisting distribution beam 2 is pulled by the center-penetrating jack 53 in cooperation with the third pulling rope 54;
it should be noted that the center-penetrating jack 53 needs to be used in cooperation with other tension providers, and may specifically adopt a manual pulling method,
in addition, when the core component of the pulling mechanism 5 adopts the center-through jack 53, the pulling effect is poorer than that of the winch 50, and the pulling force is more, so that the use scene needs to be adjusted according to the actual situation.
Similarly, the through jack 53 may be matched with the pullback pulley 6, and the installation mode is similar to the installation mode between the winch 50 and the pullback pulley 6, firstly, one end of the rope is penetrated on the through jack 53, and the other end of the rope is wound around the pullback pulley 6 and connected with the hoisting distribution beam 2, so that the moving direction of the hoisting distribution beam 2 can be changed without changing the pulling direction of the through jack 53.
It should be noted that, since the pulling force provided by the center-penetrating jack 53 is not as high as that provided by the winch 50, the pulling direction of the center-penetrating jack 53 may be perpendicular to the length direction of the main cable 92 corresponding to the cable crane, and is mainly responsible for the pulling operation in this direction.
Referring to fig. 10 to 12 of the specification, in practice, the cable crane may be used to move the cable crane over the main cable 92, and the hoist 50 of the first pulling mechanism 5a is responsible for pulling along the length of the main cable 92, while the penetrating jack 53 of the second pulling mechanism 5b is responsible for pulling perpendicular to the length of the main cable 92.
It will be apparent to those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (7)

1. A cable hoist mounting mechanism, comprising:
a walkway distribution beam (1);
a hoisting distribution beam (2) slidably arranged on the walkway distribution beam (1), the hoisting distribution beam (2) being configured to move in a horizontal direction on the top surface of the walkway distribution beam (1) under the pull of a pulling mechanism (5);
the hoisting pulley block (3) is hoisted at the bottom of the hoisting distribution beam (2), and the hoisting pulley block (3) is configured to move in the horizontal direction below the walkway distribution beam (1) under the driving of the hoisting distribution beam (2);
the hoisting steel wire rope (4) is wound on the hoisting pulley block (3), and the hoisting steel wire rope (4) is used for hoisting target equipment;
the pulling mechanism (5) is arranged on the top surface of the hoisting distribution beam (2), and the pulling mechanism (5) is used for pulling the hoisting distribution beam (2) so that the hoisting distribution beam (2) moves towards the pulling mechanism (5) on the top surface of the walkway distribution beam (1);
the lifting distribution beam (2) top surface and the pulling mechanism (5) are respectively located pull-back pulleys (6) on different sides of the lifting distribution beam (2), the pull-back pulleys (6) are used for being matched with the pulling mechanism (5) to pull the lifting distribution beam (2), so that the lifting distribution beam (2) is located on the top surface of the walkway distribution beam (1) and deviates from the pulling mechanism (5) to move.
2. The cable crane mounting mechanism of claim 1, wherein:
the cable crane mounting mechanism comprises two pulling mechanisms (5);
the pulling directions of the two pulling mechanisms (5) are mutually vertical.
3. The cable crane mounting mechanism of claim 1, wherein:
a moving channel (10) is arranged inside the walkway distributing beam (1) along the length direction of the walkway distributing beam (1), and the hoisting pulley block (3) is spaced from the inner wall of the moving channel (10).
4. The cable crane mounting mechanism of claim 1, wherein the pulling mechanism (5) comprises:
the winch (50) is fixedly arranged on one side of the top surface of the walkway distributing beam (1);
a first pulling rope (51) wound on the winch (50), wherein one end of the first pulling rope (51) is connected with the hoisting distribution beam (2);
the winch (50) is used for pulling the hoisting distribution beam (2) to move towards the winch (50) on the top surface of the walkway distribution beam (1) through the first pulling rope (51).
5. The cable crane mounting mechanism of claim 4, wherein the pulling mechanism (5) further comprises:
one end of the second pulling rope (52) is wound on the winch (50), and the other end of the second pulling rope (52) penetrates through the pull-back pulley (6) to be connected with the hoisting distribution beam (2);
the winch (50) is used for being matched with the pull-back pulley (6), and the hoisting distribution beam (2) is pulled to move away from the pulling mechanism (5) on the top surface of the walkway distribution beam (1) through the second pulling rope (52).
6. The cable crane mounting mechanism of claim 1, wherein the pulling mechanism (5) comprises:
a feed-through jack (53) fixedly arranged on the top surface of the walkway distributing beam (1);
one end of the third pulling rope (54) penetrates through the through jack (53), and the other end of the third pulling rope (54) is connected with the hoisting distribution beam (2);
the penetrating jack (53) is used for pulling the hoisting distribution beam (2) to move towards or away from the penetrating jack (53) on the top surface of the walkway distribution beam (1) through the third pulling rope (54).
7. The cable crane mounting mechanism of claim 1, wherein the hoist distribution beam (2) comprises:
a cross member (20);
the vertical beams (21) are vertically arranged on the bottom surface of the cross beam (20) and are arranged in pairs, and the number of the vertical beams (21) is at least two;
the vertical beam (21) can be slidably arranged on the walkway distributing beam (1), and the hoisting pulley block (3) is hoisted at the bottom of the cross beam (20);
the pulling mechanism (5) is connected with the cross beam (20) or any upright beam (21).
CN201921221558.7U 2019-07-30 2019-07-30 Cable carries loop wheel machine installation mechanism Active CN211283445U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921221558.7U CN211283445U (en) 2019-07-30 2019-07-30 Cable carries loop wheel machine installation mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921221558.7U CN211283445U (en) 2019-07-30 2019-07-30 Cable carries loop wheel machine installation mechanism

Publications (1)

Publication Number Publication Date
CN211283445U true CN211283445U (en) 2020-08-18

Family

ID=72032923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921221558.7U Active CN211283445U (en) 2019-07-30 2019-07-30 Cable carries loop wheel machine installation mechanism

Country Status (1)

Country Link
CN (1) CN211283445U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110436335A (en) * 2019-07-30 2019-11-12 中铁大桥局集团有限公司 A kind of deck unit erection gantry installing mechanism and its application method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110436335A (en) * 2019-07-30 2019-11-12 中铁大桥局集团有限公司 A kind of deck unit erection gantry installing mechanism and its application method

Similar Documents

Publication Publication Date Title
CN101786577B (en) Dual-machine loading-and-walking type hydraulic numerical control deck erection gantry and control system and control method
CN105645248B (en) A kind of steel reinforcement cage lifting device and method
CN108265628A (en) One kind rides cable-styled erection crane lifting cable-stayed bridge girder steel and bridge floor board construction method
CN105256728B (en) A kind of cantilever erection method of the Chinese human relations formula steel truss girder of cable-stayed bridge
CN101446074B (en) Installation and closure construction method for steel sliding roadway arch on top surface of steel trussed beam bridge
CN106241618A (en) A kind of curtain wall profiles boom hoisting
CN107476195B (en) Girder transporting pulley system for transporting stiffening girder by suspension bridge
CN112064662A (en) Offshore wind power suction tube jacket installation method and device
CN105484168A (en) Rotary hoisting equipment for stiffening beam of suspension bridge and erecting method of stiffening beam
CN211283445U (en) Cable carries loop wheel machine installation mechanism
CN102587293A (en) System and method for cradle cantilever construction of variable-width section concrete girder
CN107344697A (en) Cable boom hoisting
CN116654795B (en) Component lifting device for steel structure factory building assembly
CN211142840U (en) Suspension bridge main push-towing rope erects system
CN205527302U (en) Steel reinforcement cage hoisting accessory
CN110002343B (en) Self-driven urban underground prefabricated comprehensive pipe gallery laying hoisting machine and construction method
CN102587292B (en) System and method for cradle cantilever construction
CN216235734U (en) Vertical transportation hoisting structure for curtain wall unit plate
CN110436335A (en) A kind of deck unit erection gantry installing mechanism and its application method
CN210216177U (en) Anchor machine dragging system for beam erecting
CN107245957B (en) Method and equipment for erecting stiffening beam of suspension bridge in air without track
CN105438958B (en) Rotating lifting steel-fastening structure component boom hoisting
CN114182633B (en) Suspension bridge catwalk span-setting method
CN111977522B (en) Ground reeving and lifting installation method for cable crane crown block
CN217264459U (en) Pulley block hoisting equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant