Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010336706.0A
Other languages
Chinese (zh)
Other versions
CN111439673A (en
Inventor
冯大阔
陈璐
陈静
程晟钊
李佳男
郜玉芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Engineering Corp Ltd CSCEC
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China State Construction Engineering Corp Ltd CSCEC
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Engineering Corp Ltd CSCEC, China Construction Seventh Engineering Division Corp Ltd filed Critical China State Construction Engineering Corp Ltd CSCEC
Priority to CN202010336706.0A priority Critical patent/CN111439673B/en
Publication of CN111439673A publication Critical patent/CN111439673A/en
Application granted granted Critical
Publication of CN111439673B publication Critical patent/CN111439673B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C11/00Trolleys or crabs, e.g. operating above runways
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C7/00Runways, tracks or trackways for trolleys or cranes
    • B66C7/12Devices for changing direction of travel or for transferring from one runway to another; Crossings; Combinations of tracks of different gauges

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The invention relates to a building hoisting system, which effectively solves the problems of low hoisting efficiency, small load capacity and poor safety of a tower crane; the technical scheme includes that the device comprises a supporting unit, a hoisting unit and a vertical transportation platform, wherein the supporting unit is composed of a plurality of vertical first supporting masts and a plurality of top beams, the plurality of top beams are erected at the upper ends of the plurality of first supporting masts and are erected according to the outline of a building, a plurality of groups of truss tracks are installed on the top beams, the hoisting unit comprises a truss and a crane installed on the truss, arc-shaped conversion tracks are arranged between the plurality of groups of truss tracks on the first supporting masts, two ends of the conversion tracks are respectively connected with the two groups of truss tracks, and the truss can be converted between the truss tracks through the conversion tracks; the invention improves the lifting load capacity and the lifting safety, improves the material transportation efficiency and saves the equipment cost.

Description

Building handling system
Technical Field
The invention relates to the field of assembly type building construction, in particular to a building hoisting system.
Background
Building assembly is an important way for realizing building industry modernization; during the construction of the fabricated building, the accurate, efficient and safe hoisting of the prefabricated components is one of the key problems of the site construction of the fabricated building; at present, for high-rise buildings, a tower crane is mainly adopted for hoisting materials, the tower crane is of a cantilever type structure, the weight of the tower crane reaches more than several times of the weight of an object to be hoisted, and the hoisting efficiency and the hoisting load capacity are limited. Compared with a cast-in-place structure, the size and the weight of a material to be hoisted in an assembly type building are larger, and a tower crane cannot meet the requirements of accurate, efficient and safe hoisting. In addition, the potential safety hazard of the tower crane is large, and the collapse accident becomes one of the main safety accidents of building construction.
Disclosure of Invention
Aiming at the situation, the invention provides a novel building hoisting system for solving the problems in the prior art, which can effectively solve the problems of low hoisting efficiency, small load capacity and large potential safety hazard of a tower crane.
The technical scheme for solving the problem is that the building hoisting system comprises a supporting unit, a hoisting unit and a vertical transportation platform, wherein the supporting unit consists of a plurality of vertical first supporting masts and a plurality of top beams, the plurality of top beams are erected at the upper ends of the plurality of first supporting masts and are erected according to the outline of a building, a plurality of groups of trussed car tracks are installed on the top beams, and each group of trussed car tracks comprises two trussed car tracks which are arranged side by side; the lifting unit comprises a truss car and a crane arranged on the truss car, and the truss car can run on each group of truss car tracks; the vertical transportation platform is arranged on the first supporting mast and can climb upwards; arc-shaped conversion tracks are arranged among the plurality of groups of truss car tracks, two ends of each conversion track are respectively connected with the two groups of truss car tracks, and the truss cars can be converted among the truss car tracks through the conversion tracks.
According to the invention, by building the hoisting system, the problems of small hoisting load capacity, low hoisting efficiency, difficulty in safety guarantee, low automation degree, high labor intensity and the like existing when the tower crane carries out hoisting on the prefabricated part are solved, the hoisting load capacity and the hoisting safety are improved, the full-coverage transportation of materials at each part of the building construction layer can be realized by only one truss vehicle 5, the material transportation efficiency is improved, and the equipment cost is saved.
Drawings
Fig. 1 is a plan view of a support unit for a conventional building.
Fig. 2 is a front view of the support unit for a conventional building.
Fig. 3 is a top view of the present invention.
Fig. 4 is an enlarged view of the position a in fig. 3.
Fig. 5 is an enlarged view of the position B in fig. 3.
Detailed Description
The following description will explain embodiments of the present invention in further detail with reference to the accompanying drawings.
As shown in fig. 1 to 5, the lifting device comprises a supporting unit, a lifting unit and a vertical transportation platform 1, wherein the supporting unit consists of a plurality of vertical first supporting masts 2 and a plurality of top beams 3, the plurality of top beams 3 are erected at the upper ends of the plurality of first supporting masts 2, the plurality of top beams 3 are built according to the outline of a building, a plurality of groups of trussed vehicle tracks 4 are installed on the top beams 3, and each group of trussed vehicle tracks 4 comprises two trussed vehicle tracks which are arranged side by side; the lifting unit comprises a truss car 5 and a crane 6 arranged on the truss car 5, and the truss cars 5 can run on each group of truss car tracks 4; the vertical transportation platform 1 is arranged on the first supporting mast 2 and can climb upwards; arc-shaped conversion tracks 7 are arranged among the plurality of groups of truss car tracks 4, two ends of each conversion track 7 are respectively connected with the two groups of truss car tracks 4, and the truss cars 5 can be converted among the truss car tracks 4 through the conversion tracks 7.
The outer side of each conversion track 7 is fixed with a support frame 8, two ends of each support frame 8 are respectively provided with a second support mast 9 fixed on the top beam 3, and two ends of each support frame 8 are respectively lapped on the corresponding second support mast 9 and can climb upwards; support frame 8 is used for supporting conversion track 7 and guarantees conversion track 7's stability, and support frame 8 upwards climbs when conversion track 7 does not use and makes conversion track 7 rise to back timber 3 top to not influence the normal construction on construction layer, when the purlin car 5 need change between two sets of purlin car tracks 4, thereby corresponding support frame 8 moves down and makes conversion track 7 connect two sets of purlin car tracks 4 in two sets of purlin car tracks 4 parallel and levels.
One end of each group of the truss car tracks 4 connected with the conversion track 7 is provided with a transition track 10, and the truss car tracks 4 are smoothly connected with the conversion track 7 through the transition tracks 10.
The first supporting mast 2 and the top beam 3 are assembled in a modularized mode and can be built flexibly according to the building shape.
The first supporting mast 2, the top beam 3, the second supporting mast 9 and the supporting frame 8 are all steel structures.
The climbing device for the vertical transportation platform 1 and the support frame 8 is the prior art, and is not described in detail in the application.
The working process of the invention is described below by taking a Y-shaped building as an example: during construction, a supporting unit is built according to the building outline, the truss car tracks 4 on the top beam 3 are divided into three groups, namely an upper group, a lower group and a lower group, the conversion tracks 7 are arranged in three groups, and can also be arranged according to the actual condition, if the truss cars 5 only need to be converted on the two groups of truss car tracks 4 at the lower left and the lower right, only a group of conversion tracks 7 for connecting the lower left and the lower right are required to be arranged.
During normal construction, conversion track 7 upwards climbs along second support mast 9, avoid influencing the normal construction on construction layer, perpendicular transport platform 1 promotes the material to construction layer, purlin car 5 and loop wheel machine 6 carry out the handling material on purlin car track 4, when purlin car 5 needs to transport between different group purlin car track 4, for example purlin car 5 need follow the lower right transfer to the lower left purlin car track 4 on, make and connect the lower right and lower left conversion track 7 and descend to with purlin car track 4 parallel and level, connect lower left and lower right purlin car track 4, purlin car 5 can follow conversion track 7 and transfer to lower left purlin car track 4 from lower right purlin car track 4 this moment, make after the transfer completion conversion track 7 climb.
The first supporting masts 2 with different numbers can be arranged according to the shape and the area of a building, the whole area coverage of the hoisting construction of the prefabricated part is realized through the conversion of the conversion track 7, and the conversion track 7 is not required to be arranged for the building with regular concave-convex surfaces.
An intelligent control system can be arranged to realize the controllable corresponding relation between the position of the component and the operation parameters of the hoisting device, realize the functions of self-learning of the hoisting path of the component, real-time monitoring and re-correcting of the position and the posture of the component, judgment of the in-place position of the component, monitoring and early warning of operation safety and the like, and realize the safe hoisting of the prefabricated component.
According to the invention, the hoisting system is built, the hoisting load capacity and the hoisting safety are improved, and the full-coverage transportation of materials at each part of the special-shaped building construction layer can be realized only by one truss car 5 by arranging the conversion track 7, so that the material transportation efficiency is improved, and the equipment cost is saved.

Claims (2)

1. The building hoisting system is characterized by comprising a supporting unit, a hoisting unit and a vertical transportation platform (1), wherein the supporting unit consists of a plurality of vertical first supporting masts (2) and a plurality of top beams (3), the plurality of top beams (3) are erected at the upper ends of the plurality of first supporting masts (2), the plurality of top beams (3) are erected according to the outline of a building, a plurality of groups of trussed vehicle tracks (5) (4) are installed on the top beams (3), and each group of trussed vehicle tracks (5) comprises two trussed vehicle tracks (4) which are arranged side by side; the lifting unit comprises truss cars (5) and lifting machines (6) arranged on the truss cars (5), and the truss cars (5) can run on the tracks (4) of each group of truss cars (5); the vertical transportation platform (1) is arranged on the first supporting mast (2) and can climb upwards; arc-shaped conversion tracks (7) are arranged among the tracks (4) of the plurality of groups of truss cars (5), two ends of each conversion track (7) are respectively connected with the tracks (4) of the two groups of truss cars (5), and the truss cars (5) can be converted among the tracks (4) of each group of truss cars (5) through the conversion tracks (7);
the outer side of each conversion track (7) is fixed with a support frame (8), two ends of each support frame (8) are respectively provided with a second support mast (9) fixed on the top beam (3), and two ends of each support frame (8) are respectively erected on the corresponding second support mast (9) and can climb upwards;
the first supporting mast (2) and the top beam (3) are assembled in a modularized mode and can be flexibly built according to the building shape.
2. The building hoisting system of claim 1, wherein one end of each set of the truss car (5) rails (4) connected with the conversion rail (7) is provided with a transition rail (10), and the truss car (5) rails (4) are smoothly connected with the conversion rail (7) through the transition rails (10).
CN202010336706.0A 2020-04-26 2020-04-26 Building handling system Active CN111439673B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010336706.0A CN111439673B (en) 2020-04-26 2020-04-26 Building handling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010336706.0A CN111439673B (en) 2020-04-26 2020-04-26 Building handling system

Publications (2)

Publication Number Publication Date
CN111439673A CN111439673A (en) 2020-07-24
CN111439673B true CN111439673B (en) 2022-03-11

Family

ID=71656260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010336706.0A Active CN111439673B (en) 2020-04-26 2020-04-26 Building handling system

Country Status (1)

Country Link
CN (1) CN111439673B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115095166A (en) * 2022-06-16 2022-09-23 中国一冶集团有限公司 Large-span special-shaped shell structure installation carrying device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000053375A (en) * 1998-08-17 2000-02-22 Ohbayashi Corp Vertical carrier system corresponding to slewing overhead crane
CN1654305A (en) * 2005-02-04 2005-08-17 镇江市水利局 Flexible bend running technology for electric single-beam crane
CN102330497A (en) * 2011-08-04 2012-01-25 杨武龙 Building truss car
CN206188171U (en) * 2016-11-11 2017-05-24 北京燕山中海建筑安装有限公司 Perpendicular feeding system
CN106869473A (en) * 2017-04-06 2017-06-20 北京建筑机械化研究院 The liftable operation platform and its construction method of assembled architecture
CN209967657U (en) * 2019-05-29 2020-01-21 新疆维吾尔自治区特种设备检验研究院 Amusement roller coaster track auto-change over device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000053375A (en) * 1998-08-17 2000-02-22 Ohbayashi Corp Vertical carrier system corresponding to slewing overhead crane
CN1654305A (en) * 2005-02-04 2005-08-17 镇江市水利局 Flexible bend running technology for electric single-beam crane
CN102330497A (en) * 2011-08-04 2012-01-25 杨武龙 Building truss car
CN206188171U (en) * 2016-11-11 2017-05-24 北京燕山中海建筑安装有限公司 Perpendicular feeding system
CN106869473A (en) * 2017-04-06 2017-06-20 北京建筑机械化研究院 The liftable operation platform and its construction method of assembled architecture
CN209967657U (en) * 2019-05-29 2020-01-21 新疆维吾尔自治区特种设备检验研究院 Amusement roller coaster track auto-change over device

Also Published As

Publication number Publication date
CN111439673A (en) 2020-07-24

Similar Documents

Publication Publication Date Title
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN203639826U (en) Steel truss girder bridge inspection vehicle
CN102493352A (en) Method for bridge-spanning construction by using tyre carrier
CN104986171A (en) Through operation platform for railway engineering truck
CN205205685U (en) Span wire pier is function portal device at most
CN113348289B (en) Multi-column wind turbine tower and erection method
CN111439673B (en) Building handling system
CN103086276B (en) Construction method for hoisting bridge type crane in high-rise well tower type building
CN216336227U (en) Device for high-rise building construction by adopting hydraulic jacking assembly
CN202745356U (en) Hydraulic climb material platform
CN201817201U (en) Trolley slippage construction device
CN212374745U (en) Low-clearance steel reinforcement cage hoisting device
CN101664963B (en) Multifunctional operating platform for large-volume prestressed concrete box girder tensioning
CN212535058U (en) Be used for construction machinery and construction grouping synchronous elevation structure
CN210856930U (en) Maintenance system of cable-stay bridge inverted Y-shaped tower column
CN111847264B (en) Low-clearance steel reinforcement cage lifting device and construction method thereof
CN113135502A (en) Method and device for high-rise building construction by adopting hydraulic jacking assembly
CN209922694U (en) Lifting appliance
CN109761137B (en) Shallow water area steel box girder swinging construction method and system and lifting appliance
CN220414000U (en) Simply supported truss work platform for bridge maintenance
CN212222105U (en) Automobile lifter
CN220848631U (en) Movable double-construction platform for mounting small steel plate girder cross beam
CN205531262U (en) Steel construction construction platform can rise automatically
CN111809534A (en) Full-length bailey type bridge-dismantling hoisting equipment and construction method
CN218595965U (en) Gantry hoisting system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Applicant after: CHINA STATE CONSTRUCTION ENGINEERING Corp.,Ltd.

Address before: 450000 No. 116 Chengdong Road, Jinshui District, Henan, Zhengzhou

Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Applicant before: CHINA STATE CONSTRUCTION ENGINEERING Corp.,Ltd.

GR01 Patent grant
GR01 Patent grant