CN111409185A - Movable integrated device for producing precast concrete plates and production process - Google Patents

Movable integrated device for producing precast concrete plates and production process Download PDF

Info

Publication number
CN111409185A
CN111409185A CN202010324485.5A CN202010324485A CN111409185A CN 111409185 A CN111409185 A CN 111409185A CN 202010324485 A CN202010324485 A CN 202010324485A CN 111409185 A CN111409185 A CN 111409185A
Authority
CN
China
Prior art keywords
gantry
mould
precast concrete
sling
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010324485.5A
Other languages
Chinese (zh)
Inventor
郑永春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010324485.5A priority Critical patent/CN111409185A/en
Publication of CN111409185A publication Critical patent/CN111409185A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/04Discharging the shaped articles
    • B28B13/06Removing the shaped articles from moulds
    • B28B13/065Removing the shaped articles from moulds by applying electric current or other means of discharging, e.g. pneumatic or hydraulic discharging means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/14Producing shaped prefabricated articles from the material by simple casting, the material being neither forcibly fed nor positively compacted
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/02Feeding the unshaped material to moulds or apparatus for producing shaped articles
    • B28B13/0215Feeding the moulding material in measured quantities from a container or silo
    • B28B13/026Feeding the moulding material in measured quantities from a container or silo by using a movable hopper transferring the moulding material to the moulding cavities
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/42Gripping members engaging only the external or internal surfaces of the articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C5/00Base supporting structures with legs
    • B66C5/02Fixed or travelling bridges or gantries, i.e. elongated structures of inverted L or of inverted U shape or tripods

Abstract

The invention belongs to the technical field of precast concrete plate production, and particularly relates to a movable integrated device for producing precast concrete plates and a production process. The device comprises a mould table, a walking portal frame, a mould table lifting appliance, a gantry sling, a distributing machine, a mould table base and a demoulding lifting appliance, wherein the mould table is arranged on a mould table station and used for forming a precast concrete plate; the mould table base is used for overlapping the mould tables; the traveling portal frame stretches across two sides of the die table and can travel, and a gantry sling is arranged at the top of the traveling portal frame; the die table lifting appliance is connected to a gantry sling on the traveling gantry frame and is used for lifting the die table; the distributing machine is connected to a gantry sling on the traveling gantry frame and is used for pouring concrete on the die table; the demoulding lifting appliance is used for lifting the formed precast concrete plate. The invention has low basic construction requirement, can be produced in the open air, and can adopt a standardized temporary factory building; the occupied area is greatly reduced, the same capacity is only about 20 percent of the prior production mode, and the space is fully utilized.

Description

Movable integrated device for producing precast concrete plates and production process
Technical Field
The invention belongs to the technical field of precast concrete plate production, and particularly relates to a movable integrated device for producing precast concrete plates and a production process.
Background
The rapid development of assembly type buildings is the basic direction for upgrading the building industry in China, and the consumption of concrete prefabricated parts, particularly floor slabs, wall plates and the like is increased more and more. The traditional production process and the traditional production mode not only have large investment, low efficiency and energy consumption, but also have capacity which can not meet the market demand more and more.
The assembly type building is generally known as building a house like a car, namely, the building is disassembled into various components (such as beams, plates, columns and the like), processed and produced in a factory and then transported to a construction site for field assembly. Among them, the concrete precast slabs, including floor slabs, wall slabs, air conditioning slabs, etc., are currently used in the largest amount.
The necessary technical process comprises the following steps: the method comprises the steps of positioning a mold table, assembling a mold, placing steel bars and embedded parts, pouring concrete, maintaining a member (available steam), demoulding the member, hoisting and leaving a factory. The existing production process of the concrete prefabricated part comprises fixed mould table flat laying production and flat mould flow line production.
Flat laying production of a fixed die table: as shown in fig. 1, the mold platform is flatly paved in a workshop of a factory building and is fixed, the mold assembly and pouring are finished, the single-layer plane maintenance is carried out, and the energy consumption is high; finished products are hoisted in situ one by one, so that the occupied area is large, the basic investment is large, the production efficiency is low, and the personnel demand is large.
Flat die assembly line production: as shown in fig. 2, the mold table is placed on the rail, the production station personnel are not moved, and the mold table moves on the rail and is lifted to a centralized point for maintenance through complicated mechanical devices. The method has high requirements on factory buildings and infrastructure, large investment and long construction period; the production equipment investment is high, and the installation period is long; the electric control equipment is complex, and the requirement of operators is high; the occupied area of the production area is large; products produced in different periods are maintained in the same maintenance area, so that the energy consumption is high, and the product quality is not easy to guarantee; the mold table can only move in a plane and only move in a specified route, so that the space is not reasonably utilized, and the production efficiency is low. Single-line flow production, once any link goes wrong, the whole production line can form blockage; the material organization, the finished product transportation line is too long, the efficiency is low, and the waste is serious; and cannot be operated in a crossed manner.
Therefore, the defects of the existing concrete prefabricated part production mode are as follows: the permanent facilities are added in the fixed factory building, so that the investment of basic construction is huge, the construction period is long, the moving is not easy, the transportation is limited, the long-distance project cannot be made, and the environment is not protected.
Disclosure of Invention
In view of the above problems, the present invention provides a mobile integrated apparatus for producing precast concrete panels and a production process thereof.
In order to achieve the purpose, the invention adopts the following technical scheme:
an integrated mobile precast concrete panel production apparatus comprising:
the mould platform is arranged on the mould platform station and used for forming the precast concrete slab;
the mould table base is used for overlapping the mould tables;
the traveling portal frame stretches across two sides of the die table and can travel; the top of the walking portal frame is provided with a portal sling;
the die table lifting appliance can be connected to a gantry sling on the traveling gantry frame and is used for lifting the die table;
the distributing machine can be connected to a gantry sling on the traveling gantry frame and is used for pouring concrete on the die table;
and the demolding hanger is used for hoisting the formed precast concrete plate.
The walking portal frame comprises a top frame and portal columns arranged on two sides of the top frame, and driving wheels are arranged at the bottoms of the portal columns.
The mould platform includes the mould platform body and sets up in a plurality of mould platform support columns on the mould platform body, the upper end of mould platform support column is equipped with the annular groove.
The die table lifting appliance comprises a die table lifting frame, a clamp, a guide plate and a die table lifting ring, wherein the die table lifting ring used for being connected with the gantry sling is arranged at the top of the die table lifting frame; the bottom of the mould platform hanger is provided with a plurality of clamps for clamping the mould platform supporting column; and guide plates for positioning the die table are arranged at the four corners of the die table hanging bracket.
The clamp comprises a guide rod, a spring, a telescopic guide sleeve, a chuck, a clamping guide sleeve, a clamping pin shaft and a clamping driving mechanism, wherein the telescopic guide sleeve is arranged on the die table hanger, the guide rod is slidably inserted into the telescopic guide sleeve, the upper end and the lower end of the guide rod are respectively connected with a limiting block and the chuck, the spring is sleeved outside the telescopic guide sleeve, and two ends of the spring are respectively abutted against the telescopic guide sleeve and the limiting block at the upper end of the guide rod;
two clamping guide sleeves are radially arranged on the side wall of the chuck, a clamping pin shaft is respectively matched in the two clamping guide sleeves in a sliding manner, and the outer side end of the clamping pin shaft is connected with the clamping driving mechanism; the clamping driving mechanism drives the clamping pin shaft to stretch, so that the clamping and releasing of the die table supporting column are realized.
The chuck is of a hollow structure, and an opening at the lower end of the chuck is in a horn shape.
The cloth machine includes hopper track, fixed beam and hopper, and wherein the bottom of fixed beam is equipped with the hopper track, the hopper pass through the translation wheel with hopper rail connection, the top of fixed beam be equipped with be used for with gantry cable connects's connection rings.
The demolding lifting appliance comprises a demolding lifting frame, a pulley block and a demolding lifting ring, wherein the demolding lifting ring used for being connected with the gantry sling is arranged at the top of the demolding lifting frame; the bottom of the demoulding hanging bracket is provided with a pulley block;
the pulley block comprises a steel wire rope, a plurality of fixed pulleys and a plurality of movable pulleys, wherein the fixed pulleys are arranged on the demoulding hanging bracket at intervals; one end of the steel wire rope is connected with the fixed pulley positioned at the end part of one side, the other end of the steel wire rope is sequentially and alternately connected with the movable pulley and the fixed pulley, and the end part of the steel wire rope is connected with the fixed pulley positioned at the end part of the other side; each movable pulley is provided with a lifting hook.
A mobile precast concrete panel production process comprising an integrated mobile precast concrete panel production apparatus as described above, the production process comprising the steps of:
1) station arrangement: arranging a base station and a plurality of mould station stations along the walking route of the walking portal frame;
2) arranging a mould platform: connecting a mould platform lifting appliance on a gantry sling of the walking gantry frame, and lifting the mould platform to each mould platform station through the mould platform lifting appliance;
3) pouring concrete: a distributing machine is connected to a gantry sling of the travelling gantry frame, the travelling gantry frame travels along a travelling track, and concrete is distributed and poured on each mould platform through the distributing machine;
4) molding: forming a precast concrete plate on the mould platform, wherein a plurality of hoisting points are pre-installed on the precast concrete plate;
5) shifting and stacking: connecting a mould table lifting appliance on a gantry sling of the walking gantry frame, lifting the mould table through the mould table lifting appliance, and sequentially stacking the mould table on a mould table base;
6) shifting and maintaining: hoisting the base of the mould table and the mould table superposed on the base by using a gantry sling of the walking gantry frame and moving the mould table to a maintenance station;
7) demoulding of a finished product: connecting a demoulding sling on a gantry sling of the walking gantry frame, sequentially hooking a plurality of lifting points on the precast concrete plate by a plurality of lifting hooks on a pulley block, and tightening the gantry sling to lift according to an operation schedule;
8) and (3) empty die table transfer: and after the die is disassembled, connecting a die table lifting appliance on a gantry sling of the traveling gantry frame, and sequentially stacking the die tables on a die table base through the die table lifting appliance.
In step 2), the die table lifting appliance clamps the die table supporting column on the die table through the clamp.
The invention has the advantages and beneficial effects that:
the invention has low basic construction requirement, can be produced in the open air, and can adopt a standardized temporary factory building; the occupied area is greatly reduced, the same capacity is only about 20 percent of the prior production mode, and the space is fully utilized.
The invention has simple equipment and less investment; raw materials can be purchased in a commercial mode, and the environment is protected and the efficiency is high; the product quality is fully ensured.
The invention has the advantages of three-dimensional partition maintenance, low energy consumption and flexible operation; the vertical and horizontal transportation modes are adopted, the transportation distance is shortened, and the production efficiency is greatly improved; and can be operated in a crossed manner;
the invention is convenient for the whole moving and has no construction waste in the factory; the coverage range of the project is wide; the production mode is flexible: the construction site nomadic production can be carried out, and the factory house type production can also be fixed.
Drawings
FIG. 1 is a schematic diagram of a conventional flat production of a fixed mold table;
FIG. 2 is a schematic block diagram of a prior art flat die flow line production;
fig. 3 is one of the structural schematic views of the mobile precast concrete panel producing integrated apparatus of the present invention;
fig. 4 is a second schematic structural view of the mobile precast concrete panel production integrated apparatus of the present invention;
FIG. 5 is a schematic structural view of a traveling gantry of the present invention;
FIG. 6 is a side view of FIG. 5;
FIG. 7 is a schematic view of the structure of a mold table according to the present invention;
FIG. 8 is a top view of FIG. 7;
FIG. 9 is an enlarged view taken at A in FIG. 7;
FIG. 10 is a schematic view of the base of the mold table of the present invention;
FIG. 11 is a top view of FIG. 10;
FIG. 12 is a schematic view of the construction of the die table spreader of the present invention;
FIG. 13 is a bottom view of FIG. 12;
FIG. 14 is a schematic view of the structure of the jig of the present invention;
FIG. 15 is a top view of FIG. 14;
FIG. 16 is a cross-sectional view A-A of FIG. 15;
FIG. 17 is a cross-sectional view B-B of FIG. 15;
FIG. 18 is a schematic view of the structure of the distributing machine of the present invention;
fig. 19 is a schematic structural view of a stripper sling according to the present invention;
FIG. 20 is a cross-sectional view C-C of FIG. 19;
FIG. 21 is a schematic view of the precast concrete panel forming of the present invention;
FIG. 22 is a cross-sectional view taken along line D-D of FIG. 21;
FIG. 23 is a schematic view of the mold table of the present invention shifted for stacking;
FIG. 24 is a schematic view of the stacking and lifting of the mold tables of the present invention;
FIG. 25 is a schematic illustration of the demolded lifting of a formed precast concrete panel according to the present invention;
FIG. 26 is a schematic view of the hollow mold table stacking and lifting of the present invention;
fig. 27 is a block diagram of a process for producing precast concrete panels according to the present invention.
In the figure: 1 is a die table, 101 is a die table body, 102 is a die table support column, 1021 is an annular groove, 2 is a walking portal frame, 201 is a driving wheel, 202 is a portal column, 203 is a side support beam, 204 is a reinforcing rib, 205 is a top frame, 3 is a die table hanger, 301 is a die table hanger, 302 is a clamp, 3021 is a guide rod, 3022 is a spring, 3023 is a telescopic guide sleeve, 3024 is a chuck, 3025 is a clamping guide sleeve, 3026 is a clamping pin shaft, 303 is a deflector, 304 is a die table lifting ring, 4 is a gantry sling, 5 is a spreader, 501 is a hopper rail, 502 is a fixed beam, 503 is a hopper, 504 is a translation wheel, 505 is a connecting lifting ring, 6 is a die table base, 601 is a die table base body, 602 is a die table base lifting ring, 7 is a stripping hanger, 701 is a stripping hanger, 702 is a pulley block, 7021 is a fixed pulley, 7022 is a steel wire rope, 7023 is a movable pulley, 7024 is a lifting hook, and 703 is a stripping lifting ring, 8 is precast concrete board, 9 is hoisting point.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in detail with reference to the accompanying drawings and specific embodiments.
As shown in fig. 3-4, the mobile integrated device for producing precast concrete panels provided by the invention comprises a mould table 1, a traveling portal frame 2, a mould table hanger 3, a gantry sling 4, a spreader 5, a mould table base 6 and a demoulding hanger 7, wherein the mould table 1 is arranged on a mould table station and is used for forming precast concrete panels; the mould table base 6 is used for overlapping the mould table 1; the traveling portal frame 2 stretches across two sides of the die table 1 and can travel, and a gantry sling 4 is arranged at the top of the traveling portal frame 2; the mould platform lifting appliance 3 is connected to a gantry sling 4 on the traveling gantry frame 2, and the mould platform lifting appliance 3 is used for lifting the mould platform 1; the distributing machine 5 is connected to a gantry sling 4 on the walking gantry frame 2, and the distributing machine 5 is used for pouring concrete on the die table 1; the demoulding sling 7 is used for hoisting the formed precast concrete plate.
As shown in fig. 5-6, the traveling gantry 2 can perform lifting, loading, translation, distribution, transportation, palletizing, and the like. The walking portal frame 2 comprises a top frame 205 and portal columns 202 arranged on two sides of the top frame 205, driving wheels 201 are arranged at the bottoms of the portal columns 202, side supporting beams 203 are connected between the portal columns 202 on the two sides, the stability of the side surface of the portal frame is guaranteed, and meanwhile, the walking portal frame is responsible for fixing power pipelines and the like. And reinforcing ribs 204 are connected between the top frame 205 and the portal columns 202 on the two sides. The gantry 202 supports the top frame 205 and transmits the load of the top frame 205 to the driving wheel 201 while ensuring strength and stability. The top frame 205 is a high-strength, high-rigidity planar steel frame that is responsible for suspending hangers, lifting points, and the like.
As shown in fig. 7-9, the form stand 1 is a platform for making concrete slabs. The mould platform 1 comprises a mould platform body 101 and a plurality of mould platform support columns 102 arranged on the mould platform body 101, wherein the upper ends of the mould platform support columns 102 are provided with annular grooves 1021, the annular grooves 1021 are used for hoisting the mould platform 1, the mould platform support columns 102 are used for supporting the mould platform 1 when being stacked, and the mould platform support columns 102 are supporting points for supporting the upper mould platform and are hoisting points of the mould platform.
Specifically, the mold table body 101 is a plate structure, the upper surface of which is required to be flat, and is used as a bottom table for manufacturing a concrete prefabricated part, and the lower surface of which is arranged on the mold table base or the mold table support column 102. The die table thickness depends on the size of the spacing of the die table support posts 102: the larger the spacing between the die table support posts 102, the larger the die table thickness to ensure its planar stiffness requirements.
As shown in fig. 10-11, the mold base 6 includes a mold base body 601 and mold base lifting rings 602 disposed on two sides of the mold base body 601, and the traveling gantry 2 is connected to the mold base lifting rings 602 on two sides of the mold base body 601 through gantry slings 4, so as to realize the lifting of the mold base 6.
The mould table base 6 is a base of the stacking mould table 1, and the plane size is the same as that of the mould table 1. The mold base body 601 is a high-strength and high-rigidity platform frame on which the plurality of layers of mold tables 1 are stacked. The die table base 6 not only bears the weight, but also ensures the stability of the upper multi-layer die table 1. The mould base lifting ring 602 is firmly fixed on the side surface of the mould base body 601, and the demoulding lifting appliance 7 lifts the mould base 6 and the upper load through the mould base lifting ring 602.
As shown in fig. 12-13, the die table spreader 3 comprises a die table hanger 301, a clamp 302, a deflector 303 and a die table lifting ring 304, wherein the top of the die table hanger 301 is provided with the die table lifting ring 304 for connecting with the gantry sling 4; the bottom of the mould platform hanger 301 is provided with a plurality of clamps 302 for clamping the mould platform supporting column 102; the four corners of the mould platform hanger 301 are provided with guide plates 303 for positioning the mould platform 1.
As shown in fig. 14 to 17, the clamp 302 includes a guide rod 3021, a spring 3022, a telescopic guide sleeve 3023, a collet 3024, a clamping guide sleeve 3025, a clamping pin shaft 3026, and a clamping driving mechanism, wherein the telescopic guide sleeve 3023 is disposed on the die table hanger 301, the guide rod 3021 is slidably inserted into the telescopic guide sleeve 3023, the upper end and the lower end of the guide rod 3021 are respectively connected with a stopper and the collet 3024, the spring 3022 is sleeved outside the telescopic guide sleeve 3023, and two ends of the spring 3022 are respectively abutted to the stoppers at the upper ends of the telescopic guide sleeve 3023 and the guide rod 3021. The spring 3022 acts as a buffer when the collet 3024 is in contact with the die table support post 102.
In the embodiment of the invention, two clamping guide sleeves 3025 are radially arranged on the side wall of the chuck 3024, a clamping pin shaft 3026 is respectively matched in the two clamping guide sleeves 3025 in a sliding manner, and the outer end of the clamping pin shaft 3026 is connected with a clamping driving mechanism; the clamping driving mechanism drives the clamping pin 3026 to extend and retract, so that the clamping and releasing of the mold table supporting column 102 are realized.
When the clamp drive mechanism drives the two clamp pin shafts 3026 out, they enter the annular recess 1021 in the die table support column 102, clamping the die table support column 102. The clamping driving mechanism can be driven by a hydraulic cylinder.
Further, the clamp 3024 has a hollow structure, and the lower opening of the clamp is flared to facilitate positioning and connection with the mold base support column 102.
The mould platform hanger 301 is a plane rigid frame, which ensures synchronous stress of each hanging point and keeps balance and stability. The clamps 302 are fixed at the lower part of the mould platform hanger 301, the positions and the number of the clamps are the same as those of the mould platform support columns 102, and the grooves of the clamping heads 3024 are butted, locked and lifted with the tops of the mould platform support columns 102.
Guide plate 303 is fixed in the four corners of mould platform gallows 301, counterpoints through the four corners of guide plate 303 and mould platform base or mould platform 1, and four corners parallel and level about guaranteeing, then inside anchor clamps 302 and mould platform support column 102 can accurate butt joint.
As shown in fig. 18, the distributor 5 is used for casting concrete, and includes a hopper track 501, a fixed beam 502 and a hopper 503, wherein the bottom of the fixed beam 502 is provided with the hopper track 501, the hopper 503 is connected with the hopper track 501 through a translation wheel 504, and the top of the fixed beam 502 is provided with a connection hanging ring 505 for connecting with the gantry sling 4. The hopper 503 travels on the hopper rail 501 via the translation wheel 504, and the position of the hopper 503 is adjusted.
Specifically, the hopper track 501 may be a single-beam or double-beam track, the upper portion of which is connected to the steel frame at the top of the gantry via a connecting suspension ring 505, and the height of which can be adjusted up and down; a lower suspension hopper 503. The fixed beam 502 is fixed on the support of the side surface of the gantry, so that the stability of the hopper track 501 is ensured, and the hopper track does not transversely shake. The hopper 503 is used for storing concrete, and the bottom of the hopper is provided with a switch distributing device. The upper part of the translation wheel 504 is connected with the hopper track 501, and the lower part is connected with the hopper 503, so that the hopper 503 can slide along the hopper track 501, and the accurate distribution position is ensured. The connecting hoisting ring 505 is connected with the hopper track 501 and the gantry bottom steel frame and keeps stable.
As shown in fig. 19-20, the demoulding slings 7 lift the concrete precast slabs 8, i.e. finished product slings. The demolding hanger 7 comprises a demolding hanger 701, a pulley block 702 and a demolding hanging ring 703, wherein the demolding hanging ring 703 for connecting with the gantry sling 4 is arranged at the top of the demolding hanger 701; the bottom of the demoulding hanging bracket 701 is provided with a pulley block 702.
As shown in fig. 19, the pulley block 702 comprises a steel wire rope 7022, a plurality of fixed pulleys 7021 and a plurality of movable pulleys 7023, wherein the plurality of fixed pulleys 7021 are arranged on the demoulding hanger 701 at intervals; one end of a steel wire rope 7022 is connected with a fixed pulley 7021 positioned at the end part of one side, the other end of the steel wire rope 7022 is sequentially and alternately connected with a movable pulley 7023 and the fixed pulley 7021, and the end part is connected with the fixed pulley 7021 positioned at the end part of the other side; each movable pulley 7023 is provided with a hook 7024 to form a pulley block lifting appliance with uniform stress.
Specifically, the demolding hanger 701 is a square-shaped or a reversed-square-shaped welded steel frame.
A movable production process for producing precast concrete plates comprises the integrated device for producing precast concrete plates, and comprises the following steps:
1) station arrangement: as shown in fig. 27, a base station and a plurality of die table stations are arranged along the traveling route of the traveling gantry 2;
in this embodiment, six die table stations and one base station are arranged.
2) Arranging a mould platform: as shown in fig. 3, a die table hanger 3 is connected to a gantry sling 4 of the traveling gantry frame 2, and the die table 1 is lifted to each die table station by the die table hanger 3;
specifically, the gantry sling 4 sags, and the guide plate 303 of the die table sling 3 is aligned with four corners of the die table 1; the clamp 302 on the lower portion of the die table spreader 3 clamps the die table support post 102 at the annular recess 1021 by means of two clamp pins 3026 at the clamp 3024. Then lifting the mould table 1, moving the walking portal frame 2, and sequentially placing the mould table 1 on each mould table station; at this time, according to the design drawing of the precast concrete slab, marking, supporting side dies (side dies), binding reinforcing steel bars, placing embedded parts, checking with the drawing again on the die table 1, and waiting for pouring concrete after accuracy is correct.
3) Pouring concrete: as shown in fig. 4, a spreader 5 is connected to a gantry sling 4 of the travelling gantry 2, the travelling gantry 2 travels along a travelling rail, and concrete is spread and poured on each die table 1 through the spreader 5;
specifically, the gantry sling 4 is connected with a connecting lifting ring 505 at the upper part of the distributing machine 5, the distributing machine 5 is lifted to a proper height, the fixed beam 502 is locked with the gantry side support or the upright post, and then the material is received.
4) Molding: as shown in fig. 21 to 22, a precast concrete plate 8 is formed on a formwork table 1, and a plurality of hanging points 9 are pre-installed on the precast concrete plate 8;
because of the different sizes of precast concrete panels 8, some of the formwork support columns 102 are cast in concrete (two or more rows in this embodiment) and need to be protected so that the finished product can be easily separated from the concrete during demolding. The common method is to brush release agent or place isolation sleeve before pouring. The concrete slab is a semi-finished product, is not maintained and has no strength; the pre-installed lifting points 9 of the precast concrete slab 8 are typically hook bars, stirrup bars or truss bars, and the lifting points 9 are evenly distributed on the concrete slab.
5) Shifting and stacking: as shown in fig. 23, the die table hangers 3 are connected to the gantry slings 4 of the traveling gantry 2, the die tables 1 are lifted by the die table hangers 3 and sequentially stacked on the die table base 6, and the upper die table 1 is supported by the die table support columns 102 on the lower die table 1.
6) Shifting and maintaining: as shown in fig. 24, the mold table base 6 and the mold table 1 stacked thereon are lifted by the gantry slings 4 of the traveling gantry 2 and moved to the maintenance station;
specifically, after the die tables 1 are stacked to the designed number of layers, the steel frame at the top of the gantry hangs down the base sling, and the whole stack is moved to a maintenance station; the whole stack of the curing cover is generally made of materials such as rain cloth and plastic films, and the main purpose is to prevent the unset concrete from being cracked due to water loss. If the demolding strength is required to be reached as soon as possible, high-temperature steam can be introduced into the cover to accelerate the concrete solidification process; because the whole stack maintenance is adopted, the requirement on the maintenance stations is not high, the maintenance stations can be centralized and dispersed, and the operation is very flexible and efficient.
7) Demoulding of a finished product: as shown in fig. 25, a demoulding sling 7 is connected to the gantry sling 4 of the traveling gantry frame 2, the demoulding sling 7 is sequentially hooked on a plurality of lifting points 9 on the precast concrete plate 8 through a plurality of lifting hooks 7024 on the pulley block 702, the gantry sling 4 is tightened and lifted according to the operation schedule;
specifically, the concrete slab is maintained for a certain time, and the form can be removed after the designed corresponding strength is reached, wherein the form removal is that the finished product is separated from the form platform 1, and the concrete slab is the finished product at the moment; the walking portal frame 2 hangs down the demoulding lifting appliance 7, and a plurality of lifting hooks 7024 of the pulley block 702 are sequentially and uniformly hooked on corresponding lifting points 9.
8) And (3) empty die table transfer: as shown in fig. 26, after the mold is removed, the mold table is cleaned; and a gantry sling 4 of the walking gantry frame 2 is connected with a die table sling 3, and the die tables 1 are sequentially stacked on a die table base 6 through the die table sling 3. And then the gantry is hoisted in a whole stack by a gantry vertical sling and is transferred to a pouring area from a formwork removal area. The vacant die tables are arranged near the pouring station in a whole-stacking mode and can be used at any time.
And circulating in sequence.
The invention can realize a production mode of the precast concrete component with low investment, high output, quick effect, easy popularization and low energy consumption, has great influence on the popularization and the application of the assembly type building in China, and simultaneously realizes the double harvest of economic benefit and social benefit.
The above description is only an embodiment of the present invention, and is not intended to limit the scope of the present invention. Any modification, equivalent replacement, improvement, extension, etc. made within the spirit and principle of the present invention are included in the protection scope of the present invention.

Claims (10)

1. An integrated mobile device for producing precast concrete panels, comprising:
the mould platform (1) is arranged on a mould platform station and is used for forming a precast concrete plate;
a mould table base (6) for overlapping the mould table (1);
the traveling portal frame (2) stretches across two sides of the die table (1) and can travel; the top of the walking portal frame (2) is provided with a gantry sling (4);
the die table lifting appliance (3) can be connected to a gantry sling (4) on the walking gantry frame (2), and the die table lifting appliance (3) is used for lifting the die table (1);
the distributing machine (5) can be connected to a gantry sling (4) on the walking gantry frame (2), and the distributing machine (5) is used for pouring concrete on the die table (1);
and the demolding lifting appliance (7) is used for lifting the formed precast concrete plate.
2. Integrated mobile precast concrete panel production plant according to claim 1 characterized by the fact that said travelling gantry (2) comprises a top frame (205) and gantry columns (202) placed on both sides of said top frame (205), the bottom of said gantry columns (202) being provided with driving wheels (201).
3. The mobile precast concrete panel production integrated device according to claim 1, wherein the mold table (1) comprises a mold table body (101) and a plurality of mold table support columns (102) provided on the mold table body (101), the upper ends of the mold table support columns (102) being provided with an annular groove (1021).
4. The mobile integrated precast concrete slab production device according to claim 3, wherein the mould platform hanger (3) comprises a mould platform hanger (301), a clamp (302), a guide plate (303) and a mould platform lifting ring (304), wherein the top of the mould platform hanger (301) is provided with the mould platform lifting ring (304) for connecting with the gantry sling (4); the bottom of the mould platform hanger (301) is provided with a plurality of clamps (302) for clamping the mould platform supporting column (102); and guide plates (303) used for positioning the die table (1) are arranged at the four corners of the die table hanger (301).
5. The integrated mobile precast concrete slab production device according to claim 4, wherein the clamp (302) comprises a guide rod (3021), a spring (3022), a telescopic guide sleeve (3023), a collet (3024), a clamping guide sleeve (3025), a clamping pin shaft (3026) and a clamping driving mechanism, wherein the telescopic guide sleeve (3023) is arranged on the mould platform hanger (301), the guide rod (3021) is slidably inserted into the telescopic guide sleeve (3023), the upper end and the lower end of the guide rod (3021) are respectively connected with a limit block and the collet (3024), the spring (3022) is sleeved outside the telescopic guide sleeve (3023), and the two ends of the spring are respectively abutted against the limit blocks at the upper ends of the telescopic guide sleeve (3023) and the guide rod (3021);
two clamping guide sleeves (3025) are arranged on the side wall of the chuck (3024) along the radial direction, a clamping pin (3026) is respectively arranged in the two clamping guide sleeves (3025) in a sliding fit manner, and the outer side end of the clamping pin (3026) is connected with the clamping driving mechanism; the clamping driving mechanism drives the clamping pin shaft (3026) to stretch and retract, so that the clamping and releasing of the die table supporting column (102) are realized.
6. The integrated mobile precast concrete panel production plant according to claim 5, characterized in that the clip head (3024) is a hollow structure and the lower end opening is trumpet-shaped.
7. The integrated mobile precast concrete panel production plant according to claim 1, characterized in that said spreader (5) comprises a hopper track (501), a fixed beam (502) and a hopper (503), wherein the bottom of the fixed beam (502) is provided with the hopper track (501), said hopper (503) is connected with said hopper track (501) by a translation wheel (504), and the top of the fixed beam (502) is provided with a connecting ring (505) for connecting with said gantry sling (4).
8. The mobile integrated precast concrete panel production plant according to claim 1, characterized in that the demold spreader (7) comprises a demold hanger (701), a pulley block (702) and a demold lifting ring (703), wherein the top of the demold hanger (701) is provided with the demold lifting ring (703) for connection with the gantry sling (4); the bottom of the demolding hanging bracket (701) is provided with a pulley block (702);
the pulley block (702) comprises a steel wire rope (7022), a plurality of fixed pulleys (7021) and a plurality of movable pulleys (7023), wherein the fixed pulleys (7021) are arranged on the demoulding hanging frame (701) at intervals; one end of the steel wire rope (7022) is connected with the fixed pulley (7021) positioned at the end part of one side, the other end of the steel wire rope (7022) is sequentially and alternately connected with the movable pulley (7023) and the fixed pulley (7021), and the end part of the steel wire rope is connected with the fixed pulley (7021) positioned at the end part of the other side; each movable pulley (7023) is provided with a lifting hook (7024).
9. A mobile precast concrete panel production process comprising an integrated mobile precast concrete panel production apparatus according to any one of claims 1 to 7, comprising the steps of:
1) station arrangement: a base station and a plurality of die table stations are arranged along the traveling route of the traveling portal frame (2);
2) arranging a mould platform: a gantry sling (4) of the walking gantry frame (2) is connected with a mould platform sling (3), and the mould platform (1) is hoisted to each mould platform station through the mould platform sling (3);
3) pouring concrete: a spreader (5) is connected on a gantry sling (4) of the travelling gantry frame (2), the travelling gantry frame (2) travels along a travelling track, and concrete is spread and poured on each mould table (1) through the spreader (5);
4) molding: forming a precast concrete plate (8) on the mould table (1), wherein a plurality of hoisting points (9) are pre-installed on the precast concrete plate (8);
5) shifting and stacking: a gantry sling (4) of the walking gantry frame (2) is connected with a mould table lifting appliance (3), the mould table (1) is lifted through the mould table lifting appliance (3) and the mould table lifting appliance are sequentially stacked on a mould table base (6);
6) shifting and maintaining: hoisting a mould table base (6) and a mould table (1) superposed on the mould table base through a gantry sling (4) of a walking gantry frame (2) and moving to a maintenance station;
7) demoulding of a finished product: connecting a demoulding sling (7) on a gantry sling (4) of a walking gantry frame (2), sequentially hooking a plurality of lifting points (9) on a precast concrete plate (8) by the demoulding sling (7) through a plurality of lifting hooks (7024) on a pulley block (702), and tightening the gantry sling (4) to lift according to an operation schedule;
8) and (3) empty die table transfer: after the die is disassembled, a die table lifting appliance (3) is connected to a gantry sling (4) of the walking gantry frame (2), and the die tables (1) are sequentially stacked on a die table base (6) through the die table lifting appliance (3).
10. The mobile precast concrete panel production process according to claim 9, wherein in step 2), the mold table hoist (3) clamps the mold table support column (102) on the mold table (1) by means of the clamp (302).
CN202010324485.5A 2020-04-23 2020-04-23 Movable integrated device for producing precast concrete plates and production process Pending CN111409185A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010324485.5A CN111409185A (en) 2020-04-23 2020-04-23 Movable integrated device for producing precast concrete plates and production process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010324485.5A CN111409185A (en) 2020-04-23 2020-04-23 Movable integrated device for producing precast concrete plates and production process

Publications (1)

Publication Number Publication Date
CN111409185A true CN111409185A (en) 2020-07-14

Family

ID=71486927

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010324485.5A Pending CN111409185A (en) 2020-04-23 2020-04-23 Movable integrated device for producing precast concrete plates and production process

Country Status (1)

Country Link
CN (1) CN111409185A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111975973A (en) * 2020-08-26 2020-11-24 广东博智林机器人有限公司 Plate-shaped member production line and production method
CN113843886A (en) * 2021-10-11 2021-12-28 北京好运达智创科技有限公司 Cover beam lifting and moving demolding device and demolding method
CN114434609A (en) * 2021-12-23 2022-05-06 重庆中航建设(集团)有限公司 Movable rail shaping steel die without support
CN117124430A (en) * 2023-10-27 2023-11-28 湖南恒运建筑科技发展有限公司 Prefabricated equipment is used in processing of haydite concrete prefabricated wallboard

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111975973A (en) * 2020-08-26 2020-11-24 广东博智林机器人有限公司 Plate-shaped member production line and production method
CN113843886A (en) * 2021-10-11 2021-12-28 北京好运达智创科技有限公司 Cover beam lifting and moving demolding device and demolding method
CN113843886B (en) * 2021-10-11 2022-12-06 北京好运达智创科技有限公司 Cover beam lifting and moving demolding device and demolding method
CN114434609A (en) * 2021-12-23 2022-05-06 重庆中航建设(集团)有限公司 Movable rail shaping steel die without support
CN117124430A (en) * 2023-10-27 2023-11-28 湖南恒运建筑科技发展有限公司 Prefabricated equipment is used in processing of haydite concrete prefabricated wallboard
CN117124430B (en) * 2023-10-27 2024-01-05 湖南恒运建筑科技发展有限公司 Prefabricated equipment is used in processing of haydite concrete prefabricated wallboard

Similar Documents

Publication Publication Date Title
CN111409185A (en) Movable integrated device for producing precast concrete plates and production process
CN107059640B (en) Bridge girder erection machine for prefabricated segmental beam span-by-span construction and construction method thereof
CN107650258A (en) A kind of bidirectional circulating structure prefabricated components production line and control method
CN108381746B (en) Construction method of sliding type pedestal prefabricated box girder
CN111452208A (en) Section beam prefabricating assembly line adopting stub matching method
CN109968521A (en) A kind of packaged type bridges prefabricated components production method and industrial production line
CN113232144A (en) High-speed railway prefabricated box girder production line and production process
CN109773952B (en) Short line matching segment beam circulating flow production line and production method thereof
CN101486091A (en) Integral replacing method of ladle turret with limited upper lifting space
CN212919859U (en) Nomadic three-dimensional production system of concrete prefabricated part
CN113752379B (en) Concrete T beam prefabrication construction method adopting secondary tensioning process and movable pedestal
CN116198010A (en) Intelligent sleeper production line
CN109968516B (en) Comprehensive production system and production method for PC (polycarbonate) components
CN111996916A (en) Cast-in-place box girder integrated construction equipment and construction method thereof
CN112454643A (en) Modularized disassembly-free wall formwork automatic production system
CN211594267U (en) PC coincide floor stacking machine
CN109291229B (en) Modularized mobile multilayer stacking steam curing PC component production system and production method
CN112223493A (en) Prefabricated component forming equipment
CN212421717U (en) Movable integrated device for producing precast concrete plates
CN112123554A (en) PC component automation line
CN215920863U (en) High-speed railway precast box girder production line
CN1713970A (en) Moulding of concrete articles
CN109203216A (en) Rail-free kiln car and its method of operation for PC component production line
CN112356259B (en) High-strength high-performance concrete pipe pile automatic production line
CN209832088U (en) Combined curing kiln for concrete product production line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination