CN111379397A - Decoration process with house water seepage and humidity preventing function - Google Patents
Decoration process with house water seepage and humidity preventing function Download PDFInfo
- Publication number
- CN111379397A CN111379397A CN201811616609.6A CN201811616609A CN111379397A CN 111379397 A CN111379397 A CN 111379397A CN 201811616609 A CN201811616609 A CN 201811616609A CN 111379397 A CN111379397 A CN 111379397A
- Authority
- CN
- China
- Prior art keywords
- treatment
- waterproof
- parts
- water seepage
- waterproofing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F21/00—Implements for finishing work on buildings
-
- C—CHEMISTRY; METALLURGY
- C09—DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
- C09D—COATING COMPOSITIONS, e.g. PAINTS, VARNISHES OR LACQUERS; FILLING PASTES; CHEMICAL PAINT OR INK REMOVERS; INKS; CORRECTING FLUIDS; WOODSTAINS; PASTES OR SOLIDS FOR COLOURING OR PRINTING; USE OF MATERIALS THEREFOR
- C09D1/00—Coating compositions, e.g. paints, varnishes or lacquers, based on inorganic substances
- C09D1/06—Coating compositions, e.g. paints, varnishes or lacquers, based on inorganic substances cement
- C09D1/08—Coating compositions, e.g. paints, varnishes or lacquers, based on inorganic substances cement with organic additives
-
- C—CHEMISTRY; METALLURGY
- C09—DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
- C09D—COATING COMPOSITIONS, e.g. PAINTS, VARNISHES OR LACQUERS; FILLING PASTES; CHEMICAL PAINT OR INK REMOVERS; INKS; CORRECTING FLUIDS; WOODSTAINS; PASTES OR SOLIDS FOR COLOURING OR PRINTING; USE OF MATERIALS THEREFOR
- C09D7/00—Features of coating compositions, not provided for in group C09D5/00; Processes for incorporating ingredients in coating compositions
- C09D7/40—Additives
- C09D7/60—Additives non-macromolecular
- C09D7/61—Additives non-macromolecular inorganic
-
- C—CHEMISTRY; METALLURGY
- C09—DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
- C09D—COATING COMPOSITIONS, e.g. PAINTS, VARNISHES OR LACQUERS; FILLING PASTES; CHEMICAL PAINT OR INK REMOVERS; INKS; CORRECTING FLUIDS; WOODSTAINS; PASTES OR SOLIDS FOR COLOURING OR PRINTING; USE OF MATERIALS THEREFOR
- C09D7/00—Features of coating compositions, not provided for in group C09D5/00; Processes for incorporating ingredients in coating compositions
- C09D7/40—Additives
- C09D7/65—Additives macromolecular
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03C—DOMESTIC PLUMBING INSTALLATIONS FOR FRESH WATER OR WASTE WATER; SINKS
- E03C1/00—Domestic plumbing installations for fresh water or waste water; Sinks
- E03C1/12—Plumbing installations for waste water; Basins or fountains connected thereto; Sinks
- E03C1/122—Pipe-line systems for waste water in building
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/64—Insulation or other protection; Elements or use of specified material therefor for making damp-proof; Protection against corrosion
- E04B1/644—Damp-proof courses
- E04B1/648—Damp-proof courses obtained by injection or infiltration of water-proofing agents into an existing wall
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/18—Separately-laid insulating layers; Other additional insulating measures; Floating floors
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Organic Chemistry (AREA)
- Wood Science & Technology (AREA)
- Materials Engineering (AREA)
- Inorganic Chemistry (AREA)
- Environmental & Geological Engineering (AREA)
- Water Supply & Treatment (AREA)
- Public Health (AREA)
- Hydrology & Water Resources (AREA)
- Health & Medical Sciences (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Building Environments (AREA)
Abstract
The invention discloses a decoration process with the functions of preventing water seepage and moisture of a house, which comprises the following specific steps: firstly, performing primary drainage treatment on a bottom layer, and then performing primary waterproof treatment on the surface of the bottom layer; step two, except for the normally designed pipeline, connecting an inclined tee joint at the position of the floor drain pipe, installing a secondary drainage pipe at the position of the inclined tee joint, then carrying out backfilling process and hardening treatment to form a structure with four high surfaces and low secondary drainage pipes, then carrying out secondary waterproof treatment on the ground and the wall surface, and carrying out third waterproof treatment at the position of 25-35cm away from the ground and the wall surface after the structure is dried to enhance the waterproof property; and step three, paving ceramic tiles on the upper part of the surface subjected to the secondary waterproof treatment by using cement dry and wet slurry, ensuring that a secondary drainage pipe is not blocked, and finally paving the ceramic tiles on the threshold by using cement wet slurry. The invention adopts three waterproof treatments and cement paste for tile pasting, thereby ensuring that the house is not water seepage and damp, easy to operate, low in construction cost and wide in application range.
Description
Technical Field
The invention relates to the field of decoration, in particular to a decoration process with the functions of preventing water seepage and moisture of a house.
Background
With the increase of economic income and the improvement of living standard of people, more and more people own houses, and in order to meet the living and other requirements of people, people can decorate the houses of people, and the decoration is also regarded by many people, so that the use comfort of the users is concerned.
Decoration is also known as decoration or decoration. The decoration is carried out in a certain area and range, and comprises a whole set of construction scheme and design scheme which are realized by hydropower construction, walls, floors, ceilings, landscapes and the like and are formed according to a certain design concept and aesthetic rules, so that various benefits are brought to people, but various problems often occur in the decoration process. The water seepage of a house is a common problem in decoration.
The water seepage of a house is not good in a waterproof process, the existing decoration waterproof process does not have a unified standard, and a constructor can freely exert the water seepage according to own experience, so that the water seepage phenomenon of the house often occurs, and inconvenience is brought to house users.
Disclosure of Invention
The present invention is directed to a finishing process with the function of preventing water seepage and moisture in a house, so as to solve the problems of the background art.
In order to achieve the purpose, the invention provides the following technical scheme:
a decoration process with the function of preventing house water seepage and humidity comprises the following specific steps:
firstly, performing primary drainage treatment on a bottom layer to ensure that no water is accumulated on the bottom layer, and then performing primary waterproof treatment on the surface of the bottom layer;
step two, except for the normally designed pipeline, connecting an inclined tee joint at the position of the floor drain pipe, installing a secondary drainage pipe at the position of the inclined tee joint, then carrying out backfilling process and hardening treatment to form a structure with four high surfaces and low secondary drainage pipes, then carrying out secondary waterproof treatment on the ground and the wall surface, and carrying out third waterproof treatment at the position of 25-35cm away from the ground and the wall surface after the structure is dried to enhance the waterproof property;
and step three, paving ceramic tiles on the upper part of the surface subjected to the secondary waterproof treatment by using cement dry and wet slurry, ensuring that a secondary drainage pipe is not blocked, and finally paving the ceramic tiles on the threshold by using cement wet slurry.
As a further scheme of the invention: and replacing the backfilling process with an overhead process in the step two.
As a further scheme of the invention: and the second waterproof treatment in the second step also comprises the step of waterproof treatment of the wall surface.
As a further scheme of the invention: and the third waterproof treatment in the second step also comprises the step of performing waterproof treatment on the joint of the exhaust pipeline and the floor and the exhaust pipeline.
As a further scheme of the invention: the first waterproof treatment comprises paving a waterproof material and smearing a waterproof coating.
As a further scheme of the invention: the second waterproof treatment is to paint waterproof paint.
As a further scheme of the invention: the third waterproof treatment is to paint waterproof slurry, and the waterproof slurry comprises the following raw materials in parts by weight: 45-52 parts of ordinary portland cement, 147 parts of deionized water 135-147 parts, 16-19.5 parts of acrylic resin, 8.8-10.5 parts of fine sand, 18-21.4 parts of mica powder and 22-25.5 parts of polystyrene emulsion.
Compared with the prior art, the invention has the beneficial effects that: the invention has reasonable design process, simple process flow, easy operation, low construction cost and wide application range, can ensure that the house is not seeped and moist by adopting waterproof treatment for three times and assisting cement paste to paste the ceramic tile, and meets the use requirements of people.
Detailed Description
The technical solution of the present patent will be described in further detail with reference to the following embodiments.
Example 1
A decoration process with the function of preventing house water seepage and humidity comprises the following specific steps:
firstly, performing primary drainage treatment on a bottom layer to ensure that no water is accumulated on the bottom layer, then paving a waterproof material on the surface of the bottom layer, and smearing waterproof paint;
step two, except for a normally designed pipeline, connecting an inclined tee joint at the position of a floor drain pipe, installing a secondary drain pipe at the position of the inclined tee joint, then carrying out overhead treatment and hardening treatment to form a structure with four high surfaces and low secondary drain pipes, then carrying out secondary waterproof treatment on the ground and the wall surface, and after the structure is dried, smearing waterproof slurry at a position 30cm away from the ground and the wall, wherein the waterproof slurry comprises the following raw materials in parts by weight: 45 parts of ordinary portland cement, 135 parts of deionized water, 16 parts of acrylic resin, 8.8 parts of fine sand, 18 parts of mica powder and 22 parts of polystyrene emulsion, wherein water seepage is avoided through a layer-by-layer waterproof structure and three-time waterproof treatment;
and step three, paving ceramic tiles on the upper part of the surface subjected to the secondary waterproof treatment by using cement dry and wet slurry, ensuring that a secondary drainage pipe is not blocked, and finally paving the ceramic tiles on the threshold by using cement wet slurry.
Example 2
A decoration process with the function of preventing house water seepage and humidity comprises the following specific steps:
firstly, performing primary drainage treatment on a bottom layer to ensure that no water is accumulated on the bottom layer, and then performing primary waterproof treatment on the surface of the bottom layer;
step two, besides the normally designed pipeline, an inclined tee joint is connected at the position of the floor drain pipe, a secondary drainage pipe is installed at the position of the inclined tee joint, then a backfilling process is carried out and hardening treatment is carried out, the use strength is ensured, a structure with four high surfaces and low secondary drainage pipes is formed, so that the surrounding water can conveniently fall into the position of the secondary drainage pipe under the action of gravity, accumulated water can be discharged, waterproof paint is coated on the ground and the wall surface, after the water is dried, third waterproof treatment is carried out at 25cm positions of the ground and the wall surface, and meanwhile, the waterproof treatment is also carried out on the connecting position of the exhaust pipeline and the floor surface and the exhaust pipeline so as to;
and step three, paving the ceramic tiles on the upper part of the secondary waterproof treatment surface by using cement dry and wet slurry, ensuring that a secondary drainage pipe is not blocked, ensuring that drainage is smooth, and finally paving the ceramic tiles at the threshold by using cement wet slurry.
Example 3
A decoration process with the function of preventing house water seepage and humidity comprises the following specific steps:
firstly, performing primary drainage treatment on a bottom layer to ensure that no water is accumulated on the bottom layer, then paving a waterproof material on the surface of the bottom layer, and smearing waterproof paint;
step two, except for the normally designed pipeline, connecting an inclined tee joint at the position of a floor drain pipe, installing a secondary drain pipe at the position of the inclined tee joint, then carrying out a backfilling process and hardening treatment to form a structure with four high surfaces and low secondary drain pipes, then coating waterproof paint on the ground and the wall surface, after the structure is dried, carrying out third waterproof treatment at 35cm positions on the ground and the wall surface, and simultaneously coating waterproof slurry on the connecting position of a roof and a floor and an exhaust pipeline, so that the influence of water seepage on the building can be avoided, and the waterproof slurry comprises the following raw materials in parts by weight: 52 parts of ordinary portland cement, 147 parts of deionized water, 19.5 parts of acrylic resin, 10.5 parts of fine sand, 21.4 parts of mica powder and 25.5 parts of polystyrene emulsion;
and step three, paving ceramic tiles on the upper part of the surface subjected to the secondary waterproof treatment by using cement dry and wet slurry, ensuring that a secondary drain pipe is not blocked, and paving the ceramic tiles at the threshold by using the cement wet slurry.
Comparative example
The existing waterproof process is adopted for waterproof treatment.
The rooms using the processes of examples 1-3 and the room using the comparative example were subjected to a water-proofing test, and the results of the test are shown in Table 1.
TABLE 1
Example 1 | Example 2 | Example 3 | Comparative example | |
Water seepage phenomenon | No water penetration was observed | No water penetration was observed | No water penetration was observed | Discovery of Water seepage |
Phenomenon of wetness | Drying | Drying | Drying | Moisture content |
As can be seen from Table 1, the room waterproofing test of examples 1-3 is much more effective than the room of the comparative example, indicating that the process of the present invention has a good effect on preventing water and moisture penetration.
The working principle of the invention is as follows: according to the invention, the first waterproof treatment is carried out after the bottom layer is drained, then the secondary drain pipe is connected with the floor drain pipe and backfilled or overhead process is carried out, the second waterproof treatment is carried out, then the tile is paved on the upper part by using cement wet slurry, the third waterproof treatment is carried out, and the phenomena of water dripping and mildew in the house caused by the arrangement are ensured by progressive one layer by one layer.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (7)
1. A decoration process with the function of preventing house water seepage and humidity is characterized by comprising the following specific steps:
firstly, performing primary drainage treatment on a bottom layer, and then performing primary waterproof treatment on the surface of the bottom layer;
step two, except for the normally designed pipeline, connecting an inclined tee joint at the position of the floor drain pipe, installing a secondary drain pipe at the position of the inclined tee joint, then carrying out backfilling process and hardening treatment, then carrying out secondary waterproof treatment on the ground and the wall surface, and carrying out tertiary waterproof treatment at the position 25-35cm away from the ground and the wall surface after drying to enhance the waterproof property;
and thirdly, paving the ceramic tiles on the upper part of the surface subjected to the secondary waterproof treatment by using cement dry and wet slurry, and finally paving the ceramic tiles on the doorsill by using cement wet slurry.
2. A finishing process with house water seepage and moisture prevention function as claimed in claim 1, wherein the backfilling process in the second step is replaced by an overhead process.
3. A finishing process with the function of preventing water seepage and moisture in houses according to claim 1 or 2, characterized in that the second waterproofing treatment in the second step further comprises waterproofing the wall surface.
4. A finishing process with house moisture and water penetration preventing function as claimed in claim 1, wherein said third waterproofing treatment in said second step further comprises waterproofing treatment of the exhaust duct and the junction of the exhaust duct with the floor and the exhaust duct.
5. A finishing process with the function of preventing water infiltration and moisture in houses as claimed in claim 1, characterized by the fact that said first waterproofing treatment consists of laying of waterproofing material and painting of waterproofing paint.
6. A finishing process with the function of preventing water infiltration and moisture in houses as claimed in claim 1, characterized in that said second waterproofing treatment is the application of waterproofing paint.
7. A finishing process with house water seepage and moisture prevention functions according to claim 1, characterized in that the third waterproof treatment is smearing waterproof slurry, and the waterproof slurry comprises the following raw materials in parts by weight: 45-52 parts of ordinary portland cement, 147 parts of deionized water 135-147 parts, 16-19.5 parts of acrylic resin, 8.8-10.5 parts of fine sand, 18-21.4 parts of mica powder and 22-25.5 parts of polystyrene emulsion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811616609.6A CN111379397A (en) | 2018-12-28 | 2018-12-28 | Decoration process with house water seepage and humidity preventing function |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811616609.6A CN111379397A (en) | 2018-12-28 | 2018-12-28 | Decoration process with house water seepage and humidity preventing function |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111379397A true CN111379397A (en) | 2020-07-07 |
Family
ID=71216583
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811616609.6A Pending CN111379397A (en) | 2018-12-28 | 2018-12-28 | Decoration process with house water seepage and humidity preventing function |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111379397A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113027174A (en) * | 2021-03-12 | 2021-06-25 | 三和住品(广东)科技有限公司 | Integrated assembly public washroom waterproof installation system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10183895A (en) * | 1996-12-27 | 1998-07-14 | Nisshin Kogyo Kk | Root-preventive joint filler, drain-related root-preventive sealing material, and waterproof execution body |
CN107476448A (en) * | 2017-06-28 | 2017-12-15 | 中冶天工集团天津有限公司 | A kind of construction method for waterproof at toilet doorway |
CN107816138A (en) * | 2017-10-21 | 2018-03-20 | 浙江世贸装饰股份有限公司 | A kind of construction technology of subsided rest room |
CN107989329A (en) * | 2016-10-26 | 2018-05-04 | 兴义市巨匠装饰有限责任公司 | A kind of method of toilet and kitchen waterproof construction |
CN108755979A (en) * | 2018-06-15 | 2018-11-06 | 湖南宝家云建筑工程管理有限公司 | A kind of toilet moistureproof and waterproof processing method |
-
2018
- 2018-12-28 CN CN201811616609.6A patent/CN111379397A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10183895A (en) * | 1996-12-27 | 1998-07-14 | Nisshin Kogyo Kk | Root-preventive joint filler, drain-related root-preventive sealing material, and waterproof execution body |
CN107989329A (en) * | 2016-10-26 | 2018-05-04 | 兴义市巨匠装饰有限责任公司 | A kind of method of toilet and kitchen waterproof construction |
CN107476448A (en) * | 2017-06-28 | 2017-12-15 | 中冶天工集团天津有限公司 | A kind of construction method for waterproof at toilet doorway |
CN107816138A (en) * | 2017-10-21 | 2018-03-20 | 浙江世贸装饰股份有限公司 | A kind of construction technology of subsided rest room |
CN108755979A (en) * | 2018-06-15 | 2018-11-06 | 湖南宝家云建筑工程管理有限公司 | A kind of toilet moistureproof and waterproof processing method |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113027174A (en) * | 2021-03-12 | 2021-06-25 | 三和住品(广东)科技有限公司 | Integrated assembly public washroom waterproof installation system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101400065B1 (en) | Constructing method for waterproof using infiltrative liquid waterproofing agent | |
CN111379397A (en) | Decoration process with house water seepage and humidity preventing function | |
CN208501802U (en) | A kind of bathroom caisson internal drainage construction | |
CN207362992U (en) | Floor drain leakage preventing structure | |
CN206245458U (en) | A kind of basement is moistureproof, anti-condensation structure | |
CN103291024A (en) | Novel cement-based plastering mortar construction method | |
CN206220272U (en) | Ground hot water lays heating toilet doorway sealing damp proof insulation construction | |
CN103147547A (en) | Waterproof construction method for bathroom | |
CN204781464U (en) | Water bar between shower | |
CN206521812U (en) | A kind of anti-leakage structure of toilet | |
KR20120118450A (en) | Paint is coated with a waterproof sheet and a non-exposure using waterproof construction method | |
CN204112547U (en) | A kind of accomodation ground | |
CN101936034B (en) | Auxiliary water seepage deodorant floor drain | |
CN114575550A (en) | Wet pasting process for floor tiles in kitchens and bathrooms | |
CN204571168U (en) | A kind of decoration panel metope substrate moisture-proof construction | |
CN204754104U (en) | Bathroom floor heating cuts off waterproof construction | |
CN209025331U (en) | A kind of red tile roof parapet waterproof construction | |
CN109779204A (en) | A kind of pea gravel concreten ground surface construction method | |
CN204609214U (en) | Composite floor board | |
CN206328877U (en) | The flexible partitioning slot constructing structure of outdoor aproll | |
CN215857841U (en) | Damp-proof and mildew-proof structure of underground building | |
CN109138358A (en) | A kind of kitchen and bath's finishing waterproof construction method | |
CN104163593A (en) | Dry powder mortar | |
CN208293988U (en) | Antiseep secondary drainage structure applied to building | |
CN205907827U (en) | Passive building first floor wall body is at subaerial mounting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200707 |