CN204781464U - Water bar between shower - Google Patents

Water bar between shower Download PDF

Info

Publication number
CN204781464U
CN204781464U CN201520398693.4U CN201520398693U CN204781464U CN 204781464 U CN204781464 U CN 204781464U CN 201520398693 U CN201520398693 U CN 201520398693U CN 204781464 U CN204781464 U CN 204781464U
Authority
CN
China
Prior art keywords
water bar
layer
basic unit
civil engineering
engineering structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520398693.4U
Other languages
Chinese (zh)
Inventor
范红蕙
吉英
张会芬
薛维波
张仕彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUADING CONSTRUCTION DECORATION ENGINEERING Co Ltd
Original Assignee
HUADING CONSTRUCTION DECORATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUADING CONSTRUCTION DECORATION ENGINEERING Co Ltd filed Critical HUADING CONSTRUCTION DECORATION ENGINEERING Co Ltd
Priority to CN201520398693.4U priority Critical patent/CN204781464U/en
Application granted granted Critical
Publication of CN204781464U publication Critical patent/CN204781464U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Curing Cements, Concrete, And Artificial Stone (AREA)

Abstract

The utility model discloses a water bar between shower, including civil engineering structure basic unit, civil engineering structure basic unit upper end is provided with water bar microlith concrete layer perpendicularly, wherein, the water bar microlith concrete layer left and right sides with combination department of civil engineering structure basic unit is all scribbled and is equipped with waterproof clay, water bar microlith concrete layer both sides civil engineering structure basic unit upper end all is provided with the cement mortar screed -coat through the waterproof layer, cement mortar screed -coat upper end all is provided with pastes the layer, pass through on the water bar microlith concrete layer the waterproof layer card is equipped with the water bar surface course, paste layer upper end and all be provided with the decorative layer, wherein, water bar microlith concrete layer upper end extends to outside the decorative layer, water bar surface course both ends extend to paste the in situ, water bar surface course upper end is provided with finished product shower room and moves the door.

Description

A kind of shower cubicle water bar
Technical field
The utility model relates to construction engineering technical field, specifically, relates to a kind of shower cubicle water bar.
Background technology
Along with the further lifting of quality of the life, people are also more and more high to the requirement of washroom function, and the requirement of the functional and comfortableness of especially wash, bathing is high especially.If shower house water bar construction wrong conventional in toilet decoration, very easily there is the phenomenon of even leaking that seeps water, and as a kind of very general common fault, the seepage problem of washroom shower house periphery has become a chronic illness of puzzlement construction party and owner, although people have developed the water bar of various antiseep, but result of use is unsatisfactory, after using a period of time, drainage can become clearly, and structure also becomes increasingly complex simultaneously.
So, develop good seepage-proof property, good stability and structure simple water bar when one uses, just become the problem that insider needs solution badly.
Utility model content
For the problem of good seepage-proof property, good stability and structure simple water bar when above-mentioned lacking in the market uses in correlation technique, the utility model proposes a kind of shower cubicle water bar, effectively can solve poor, the poor stability of anti-seepage effect and baroque problem when traditional water bar uses.
For realizing above-mentioned technical purpose, the technical solution of the utility model is achieved in that
A kind of shower cubicle water bar, comprise civil engineering structure basic unit, described civil engineering structure basic unit upper end is vertically installed with water bar pea gravel concreten layer, wherein, the described water bar pea gravel concreten layer left and right sides and described civil engineering structure basic unit junction are all coated with waterproof clay, described civil engineering structure basic unit and described water bar pea gravel concreten layer upper end are equipped with waterproofing course, above described civil engineering structure basic unit, described waterproofing course is provided with cement mortar screeding layer, described cement mortar screeding layer upper end is provided with adhered layer, described adhered layer upper end is provided with decorative layer, described water bar pea gravel concreten layer is arranged with water bar surface layer by described waterproofing course, wherein, described water bar pea gravel concreten layer upper end extends to outside described decorative layer, described water bar surface layer two ends extend in described adhered layer, described water bar surface layer upper end is provided with finished product sliding door of shower room.
Further, described decorative layer material is stone material or floor tile.
Further, described water bar surface layer material is stone material or floor tile.
Further, described water bar surface layer cross section is layer U-shaped.
Further, round steel is provided with in described water bar pea gravel concreten layer.
The beneficial effects of the utility model: by the effect of water bar pea gravel concreten layer and waterproofing course and water bar surface layer, effectively raise the anti-seepage effect of shower cubicle, and good stability and structure are simply, and then make this shower cubicle water bar have more wide development space.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment below, apparently, accompanying drawing in the following describes is only embodiments more of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the shower cubicle water bar according to the utility model embodiment.
In figure:
1, civil engineering structure basic unit; 2, water bar pea gravel concreten layer; 3, waterproofing course; 4, cement mortar screeding layer; 5, adhered layer; 6, water bar surface layer; 7, decorative layer; 8, finished product sliding door of shower room; 9, round steel.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, other embodiments all that those of ordinary skill in the art obtain, all belong to the scope of the utility model protection.
As shown in Figure 1, a kind of shower cubicle water bar according to embodiment of the present utility model, comprise civil engineering structure basic unit 1, described civil engineering structure basic unit 1 upper end is vertically installed with water bar pea gravel concreten layer 2, wherein, described water bar pea gravel concreten layer 2 left and right sides and described civil engineering structure basic unit 1 junction are all coated with waterproof clay, described civil engineering structure basic unit 1 and described water bar pea gravel concreten layer 2 upper end are equipped with waterproofing course 3, above described civil engineering structure basic unit 1, described waterproofing course 3 is provided with cement mortar screeding layer 4, described cement mortar screeding layer 4 upper end is provided with adhered layer 5, described adhered layer 5 upper end is provided with decorative layer 7, described water bar pea gravel concreten layer 2 is arranged with water bar surface layer 6 by described waterproofing course 3, wherein, described water bar pea gravel concreten layer 2 upper end extends to outside described decorative layer 7, described water bar surface layer 6 two ends extend in described adhered layer 5, described water bar surface layer 6 upper end is provided with finished product sliding door of shower room 8.
In one embodiment, described decorative layer 7 material is stone material or floor tile.
In one embodiment, described water bar surface layer 6 material is stone material or floor tile.
In one embodiment, described water bar surface layer 6 cross section is layer U-shaped.
In one embodiment, round steel 9 is provided with in described water bar pea gravel concreten layer 2.
Conveniently understand technique scheme of the present utility model, below by way of in concrete mode of occupation, technique scheme of the present utility model is described in detail.
When specifically using, when after the drying of described water bar pea gravel concreten layer 2, carry out edge sealing process to around described water bar pea gravel concreten layer 2 root with waterproof clay, receive light process with trowel to shutoff waterproof clay, shutoff clay finished surface becomes arcuation simultaneously.After waterproof clay has been constructed 7 days, adopt coating film waterproof material to carry out conventional integral waterproofing construction to the accomodation ground comprising described water bar pea gravel concreten layer 2 and described civil engineering structure basic unit 1, waterproof construction seam must not be formed.Time often all over waterproof construction, whole described waterproofing course 3 is constructed and must be completed by an overall gas, and after must not stopping over, row is continuous is again coated with, in case form construction of waterproof layer seam, affects waterproof effect.Described waterproofing course 3 is constructed complete and by after the requirement maintenance of waterproofing materials description, is carried out 48 hours closed-water tests by code requirement.
In sum, by means of technique scheme of the present utility model, by the effect of water bar pea gravel concreten layer 2 and waterproofing course 3 and water bar surface layer 6, effectively raise the anti-seepage effect of shower cubicle, and good stability and structure are simply, and then make this shower cubicle water bar have more wide development space.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (5)

1. a shower cubicle water bar, it is characterized in that, comprise civil engineering structure basic unit (1), described civil engineering structure basic unit (1) upper end is vertically installed with water bar pea gravel concreten layer (2), wherein, described water bar pea gravel concreten layer (2) left and right sides and described civil engineering structure basic unit (1) junction are all coated with waterproof clay, described civil engineering structure basic unit (1) and described water bar pea gravel concreten layer (2) upper end are equipped with waterproofing course (3), described civil engineering structure basic unit (1) top is provided with cement mortar screeding layer (4) by described waterproofing course (3), described cement mortar screeding layer (4) upper end is provided with adhered layer (5), described adhered layer (5) upper end is provided with decorative layer (7), described water bar pea gravel concreten layer (2) is arranged with water bar surface layer (6) by described waterproofing course (3), wherein, described water bar pea gravel concreten layer (2) upper end extends to described decorative layer (7) outward, described water bar surface layer (6) two ends extend in described adhered layer (5), described water bar surface layer (6) upper end is provided with finished product sliding door of shower room (8).
2. shower cubicle water bar according to claim 1, is characterized in that, described decorative layer (7) material is stone material or floor tile.
3. shower cubicle water bar according to claim 1, is characterized in that, described water bar surface layer (6) material is stone material or floor tile.
4. shower cubicle water bar according to claim 1, is characterized in that, described water bar surface layer (6) cross section is layer U-shaped.
5. shower cubicle water bar according to claim 1, is characterized in that, is provided with round steel (9) in described water bar pea gravel concreten layer (2).
CN201520398693.4U 2015-06-10 2015-06-10 Water bar between shower Active CN204781464U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520398693.4U CN204781464U (en) 2015-06-10 2015-06-10 Water bar between shower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520398693.4U CN204781464U (en) 2015-06-10 2015-06-10 Water bar between shower

Publications (1)

Publication Number Publication Date
CN204781464U true CN204781464U (en) 2015-11-18

Family

ID=54521542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520398693.4U Active CN204781464U (en) 2015-06-10 2015-06-10 Water bar between shower

Country Status (1)

Country Link
CN (1) CN204781464U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638995A (en) * 2016-11-25 2017-05-10 绿城装饰工程集团有限公司 Bath room water blocking ridge structure and construction method
CN108978897A (en) * 2018-05-18 2018-12-11 圣都家居装饰有限公司 Toilet bathyliminion component and construction
CN111519774A (en) * 2020-04-24 2020-08-11 深圳市维业装饰集团股份有限公司 Construction method of shower room water bar

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638995A (en) * 2016-11-25 2017-05-10 绿城装饰工程集团有限公司 Bath room water blocking ridge structure and construction method
CN108978897A (en) * 2018-05-18 2018-12-11 圣都家居装饰有限公司 Toilet bathyliminion component and construction
CN111519774A (en) * 2020-04-24 2020-08-11 深圳市维业装饰集团股份有限公司 Construction method of shower room water bar
CN111519774B (en) * 2020-04-24 2021-04-09 深圳市维业装饰集团股份有限公司 Construction method of shower room water bar

Similar Documents

Publication Publication Date Title
CN104264717A (en) Basement rigid material and flexible material combined waterproof construction method
CN109356295A (en) The construction technique of toilet and kitchen antiseep
CN205077752U (en) Roofing flashing waterproofing membrane of department brick wall protection architecture
CN106284706A (en) The construction method of external wall outer insulation rock cotton board
CN203834794U (en) Building heat-preservation wall board for civil engineering
CN103821296A (en) Wall plastering technique for aerated concrete block filler wall
CN204781464U (en) Water bar between shower
CN103195218B (en) Wall ceramic sand mortar external plastering construction method
CN204531883U (en) Shower house dash threshold constructs
CN208777468U (en) A kind of kitchen and bath's water-proofing anticracking structure
CN204343722U (en) swimming pool gutter
CN109763573B (en) Water stop ridge and construction method thereof
CN207017571U (en) A kind of toilet waterproofing structure
CN105239745A (en) Integral wallboard and board seam processing method
CN103526832B (en) High-rise outer wall dividing joint structure
CN205024824U (en) Bathroom mounting structure
CN205172303U (en) A novel gate manger plate platform node construction for waterproof room
CN210713273U (en) Waterproof structure for arranging falling plate for placing drainage device in toilet
CN208518097U (en) Shower cabinet waterproof construction
CN205875424U (en) Indoor bathroom bathtub dampproofing and waterproofing structure
CN204662674U (en) Shower house anti-seep water structure
CN205063236U (en) Integration wallboard
CN205314466U (en) Take dampproofing ground plate brick of self -adhesive layer
CN205804634U (en) A kind of basement bottom board waterproof construction
CN204531499U (en) Construction engineering quality model display platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant