CN106638995A - Bath room water blocking ridge structure and construction method - Google Patents

Bath room water blocking ridge structure and construction method Download PDF

Info

Publication number
CN106638995A
CN106638995A CN201611057876.5A CN201611057876A CN106638995A CN 106638995 A CN106638995 A CN 106638995A CN 201611057876 A CN201611057876 A CN 201611057876A CN 106638995 A CN106638995 A CN 106638995A
Authority
CN
China
Prior art keywords
layer
area
water bar
blocking bank
elastic water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611057876.5A
Other languages
Chinese (zh)
Other versions
CN106638995B (en
Inventor
吴继锋
曹先文
李纯
洪先冬
张有智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Greentown Construction Technology Group Co.,Ltd.
Original Assignee
Greentown Decoration Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Greentown Decoration Engineering Group Co Ltd filed Critical Greentown Decoration Engineering Group Co Ltd
Priority to CN201611057876.5A priority Critical patent/CN106638995B/en
Publication of CN106638995A publication Critical patent/CN106638995A/en
Application granted granted Critical
Publication of CN106638995B publication Critical patent/CN106638995B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6806Waterstops

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Floor Finish (AREA)
  • Sink And Installation For Waste Water (AREA)

Abstract

The invention relates to the field of building decoration and provides a bath room water blocking ridge structure and a construction method, the bath room water blocking ridge structure is simple in structure, convenient to construct and capable of effectively preventing water molecules in a bath area in a toilet from leaking into a closestool area in the toilet, and the technical problems that in the prior art, a water blocking ridge is poor in anti-leakage effect, and normal use of the closestool area is affected are solved. The bath room water blocking ridge structure comprises a building floor base layer of the toilet and a waterproof layer laid on the building floor base layer. An elastic water blocking strip is fixed to the waterproof layer in an airtight mode and divides the building floor base layer into the bath area and the closestool area. Ground decorative pavement layers are separately laid on the portions, in the bath area and the closestool area, of the waterproof layer. The top end of the elastic water blocking strip extends to the position above the ground decorative pavement layers. The portion, above the ground decorative pavement layers, of the elastic water blocking strip is covered with a U-shaped water blocking ridge in a buckling mode. The two ends of the U-shaped water blocking ridge are fixed to the surfaces of the corresponding ground decorative pavement layers in an airtight mode, and a gap formed between the U-shaped water blocking ridge and the elastic water blocking strip is filled with cement mortar.

Description

A kind of shower room water-blocking bank structure and construction method
Technical field
The present invention relates to construction and decoration field, more particularly to a kind of simple structure, easy construction, can effectively prevent toilet The hydrone in interior shower area leaks into the shower room water-blocking bank structure and construction method for facilitating area.
Background technology
In existing interior decoration engineering, toilet is typically divided into and facilitates area and shower area Liang Ge regions, usually Enclose to form shower area, mesh with toilet body of wall by carrying out region division, i.e. water-blocking bank in accomodation ground construction water-blocking bank Front decoration market adopts traditional construction method, including flooring basic unit deashing, brushing substantially for the construction of toilet water-blocking bank Water-repellent paint, mat formation floor tile or marble, in shower room glass and door leaf side mounting finished product water bar, finally beat glass in junction Glass glue, water bar therein is that after permanent use, bonding place easily occurs seepage and shows by cement mortar or adhesive edge patch As antiseep effect is poor, and impact facilitates normally using for area, simultaneously because the external bonding of water bar, the glue for exposing easily goes mouldy Black, have impact on the overall decoration effect of toilet, reduce aesthetics.
The content of the invention
The present invention mainly provides a kind of simple structure, and easy construction can effectively prevent the water in shower area in toilet Molecule leaks into the shower room water-blocking bank structure and construction method for facilitating area, solves water-blocking bank antiseepage present in prior art Leakage effect is poor, not only affects to facilitate normally using for area, while also have impact on the overall decoration effect of toilet, reduces aesthetics Deng technical problem.
What the above-mentioned technical problem of the present invention was mainly addressed by following technical proposals:A kind of shower room water-blocking bank Structure, including building floor basic unit and the waterproof layer that is laid in building floor basic unit of toilet, it is close on the waterproof layer Fixed elastic water bar is closed, building floor basic unit is divided into shower area and facilitates area by elastic water bar, in shower Qu Hefang Just it is equipped with ground decoration pave-load layer on the waterproof layer in area respectively, the top of elastic water bar extends to ground decoration pave-load layer Top, button is covered with U-shaped water-blocking bank on the elastic water bar above ground decoration pave-load layer, and the two ends of U-shaped water-blocking bank are closed solid The ground decoration for being scheduled on respective side is mated formation layer surface, and is filled with the gap formed between U-shaped water-blocking bank and elastic water bar Cement mortar.By the sealing elasticity water bar on the waterproof layer of toilet building floor basic unit, will be defended by elastic water bar Sheng Jian building floors basic unit is divided into shower area and facilitates area Liang Ge regions, then the corresponding shower area inside and outside elastic water bar With facilitate area to lay ground decoration pave-load layer, elastic water bar is clamped between inside and outside ground decoration pave-load layer and extends to ground The top of pave-load layer is decorated in face, and closed button is covered with U-shaped water-blocking bank on elastic water bar, and between U-shaped water-blocking bank opening Cement mortar is filled with gap by the end sealing of elastic water bar in cement mortar, elastic water bar intensity therein Height, bent for shaping ability is strong, is easy to convert shower area shape according to use demand;By elastic water bar by above waterproof layer Region is separated to form shower area and facilitates the waterproof layer of area, shower area bottom to guarantee that hydrone will not ooze to building floor basic unit Leakage, so as to avoid damage to resident family living area downstairs;And shower area and convenient interval elastic water bar are locked in by two regions Completely isolated to come, again sealing in cement mortar, not only increases the sealing of elastic water bar for the end of elastic water bar, Simultaneously U-shaped water-blocking bank integral type is fixed on ground decoration pave-load layer by cement mortar, keeps integrity and U.S. of finishing The property seen, simple structure, easy construction, the hydrone in shower area is leaked into and facilitates area in effective prevention toilet, it is ensured that dress The quality repaiied.
Preferably, the elastic water bar includes T-shaped rubber matrix, under the horizontal face of T-shaped rubber matrix passes through Structural adhesive layer is closed to be bonded on waterproof layer, and the longitudinal surface of T-shaped rubber matrix extends vertically up to ground decoration pave-load layer Outward, and it is spaced in the longitudinal surface of T-shaped rubber matrix and is coated with some horizontal metal bars.By rubber matrix cladding level gold The elastic water bar that category bar is formed, intensity is high, better anti-leakage property, while easily bent for shaping;Elastic water bar is integrally in T shape When being erected in building floor basic unit, facilitate its being connected with building floor basic unit, be easy to construction.
Preferably, the U-shaped water-blocking bank includes being horizontally set with the level support platform and sealing vertical above elastic water bar The inner support platform and outer support platform of elastic water bar both sides are supported on, inner support platform and outer support platform are closed by upper structural adhesive layer It is bonded on the ground decoration pave-load layer of respective side, being provided with above level support platform can grip the limit of shower room dividing plate Position groove.Enclosed jointly by level support platform, inner support platform and outer support platform and form U-shaped water-blocking bank, simple structure, convenient processing Production;Inside and outside supporting table is bonded on ground decoration pave-load layer by the way that upper structural adhesive layer is closed, good airproof performance, and adhesive strength is high; Spacing groove in level support platform is easy to fix shower room dividing plate.
Breathing freely between inner support platform and outer support platform is turned on as it is further preferred that being provided with the bottom of the spacing groove Hole.By arranging the air-vent being connected with the cement mortar of lower section in the bottom of spacing groove, irrigating into U-shaped water-blocking bank Gas can outwards be excluded by air-vent during cement mortar, it is ensured that being poured in U-shaped water-blocking bank for cement mortar consolidation, enter one Step ensures sealing.
As it is further preferred that have in the middle part of the lower surface of the inner support platform and outer support platform glue filling groove, Upper structural adhesive layer is filled in glue filling groove.Upper structural adhesive layer is filled in into the glue in the middle part of inside and outside supporting table lower surface During filling groove, structure glue can be avoided from exposing the aesthetic property for affecting finishing.
Preferably, the corresponding ground decoration pave-load layer in the shower area includes the interior cement being laid on successively on waterproof layer Protective layer in mortar lower protective layer, shower area ground-heating thermal insulation layer, heating wire floor heating, shower area steel fabric sheet, interior cement mortar, it is interior Polymer cement-based waterproof floor, interior cement mortar up-protective layer and shower area decorative layer, facilitate the corresponding ground decoration in area to mat formation Floor includes the outer cement mortar lower protective layer being laid on successively on waterproof layer, facilitates area's ground-heating thermal insulation layer, water floor heating pipe, facilitates area Protective layer in steel fabric sheet, outer cement mortar, outer polymer cement-based waterproof floor, outer cement mortar up-protective layer and facilitates area to fill Decorations layer, wherein interpolymer cement-based waterproof layer and outer polymer cement-based waterproof layer carries over respectively the elastic water bar of respective side Surface upwardly extend and elastic water bar top surface it is relative connect, protect on interior cement mortar up-protective layer and outer cement mortar Layer carries over corresponding polymer cement-based waterproof layer again and outer polymer cement-based waterproof layer surface is upwardly extended and in elasticity gear The top face of water bar is relative to be connect.Shower area and facilitate the polymer cement-based waterproof floor and cement in area's ground decoration pave-load layer When mortar up-protective layer successively carries over the surface of the elastic water bar of respective side and upwardly extends and dock, elasticity is improved and ensured The leakage performance of water bar, it is ensured that shower area and facilitate area to separate completely.
Preferably, the two ends of the elastic water bar are extended respectively in the toilet body of wall of corresponding end.Elastic dash When the two ends of bar are extended in body of wall, it is ensured that the aesthetic property of finishing and the integrity for separating, while avoiding hydrone own elasticity Water bar and the outside seepage of body of wall seam crossing.
Preferably, the thickness of the elastic water bar is 10mm ± 2mm, the aperture pitch of U-shaped water-blocking bank be 60 mm ± 5mm, bottom surface distance is 25 mm ± 5mm between the top of elastic water bar and U-shaped water-blocking bank opening.Elastic water bar keeps reasonable Thickness, it is ensured that support strength and leakage performance;U-shaped water-blocking bank keep rational aperture pitch and its with elastic water bar Top distance, it is ensured that elastic water bar is coated on completely in cement mortar and is formed enough support strength and bonding is strong Degree.
A kind of construction method of shower room water-blocking bank structure, including order below step:
1)In the surface laying waterproof layer of building floor basic unit 1 of toilet;
2)T-shaped elastic water bar is taken, the horizontal face of elastic water bar is bonded on waterproof layer by the way that lower structural adhesive layer is closed, The longitudinal surface of elastic water bar extends vertically upwards to form shower area and facilitate area;
3)In shower area and area is facilitated to lay ground decoration pave-load layer, and the longitudinal surface top of elastic water bar extends to ground dress The top of decorations pave-load layer;
4)U-shaped water-blocking bank is taken, is applied on U-shaped water-blocking bank opening end face and is spread structural adhesive layer, then U-shaped water-blocking bank button is covered on ground On elastic water bar above the decoration pave-load layer of face, the closed ground decoration for being bonded in respective side of opening of U-shaped water-blocking bank is made Mat formation in layer surface;
5)From the two ends of U-shaped water-blocking bank to cement injection mortar between the opening of U-shaped water-blocking bank, cement mortar is set to keep off full of U-shaped The U-shaped tubular space that water bank, ground decoration pave-load layer and elastic water bar are constituted.
Preferably, interpolymer cement-based waterproof floor is carried in the corresponding ground decoration pave-load layer in the shower area, Facilitating in the corresponding ground decoration pave-load layer in area with outer polymer cement-based waterproof floor, interpolymer cement-based waterproof layer and Outer polymer cement-based waterproof layer carries over respectively the surface of the elastic water bar of respective side and upwardly extends and in elastic water bar Top surface is relative to be connect, and interior cement mortar up-protective layer and outer cement mortar up-protective layer carry over corresponding polymer cement-based waterproof again Layer and outer polymer cement-based waterproof layer surface upwardly extend the top face for being docked at elastic water bar.
Therefore, a kind of shower room water-blocking bank structure of the invention and construction method tool have the advantage that:Elastic water bar will The building floor base layer region of toilet is separated into shower area and facilitates area, by the elastic water bar of structure glue sealing by two Region is completely isolated to come, and in the end of elastic water bar and cement mortar of the sealing below U-shaped water-blocking bank, not only increases The sealing of elastic water bar, while U-shaped water-blocking bank integral type is fixed on ground decoration pave-load layer by cement mortar, is protected The integrity and aesthetic property of finishing are held, simple structure, easy construction effectively prevents the hydrone seepage in shower area in toilet Enter to facilitate area, it is ensured that the quality of finishing;The T-shaped elastic water bar that horizontal metal bar is formed is coated by rubber matrix, is easy to Construction positioning, intensity is high, better anti-leakage property, while easily bent for shaping.
Description of the drawings:
Fig. 1 is a kind of structural representation of shower room water-blocking bank structure of the invention;
Fig. 2 is the enlarged drawing at A shown in Fig. 1;
Fig. 3 is the enlarged drawing at B shown in Fig. 1.
Specific embodiment:
Below by embodiment, and accompanying drawing is combined, technical scheme is described in further detail.
Embodiment:
As shown in figures 1 and 3, a kind of shower room water-blocking bank structure of the invention, including the building floor basic unit 1 of toilet, Formation waterproof layer 2 after the surface coating monocomponent polyurethane of building floor basic unit 1, the fixed elastic water bar 3 on waterproof layer 2, As shown in Fig. 2 elastic water bar 3 includes T-shaped rubber matrix 31 of the thickness for 10mm, the horizontal face of T-shaped rubber matrix 31 It is bonded on waterproof layer 2 by the way that lower structural adhesive layer 8 is closed, the longitudinal surface of T-shaped rubber matrix 31 is extended vertically upwards, in T words Interval is coated with three horizontal metal bars 32 in the longitudinal surface of shape rubber matrix 31, and horizontal metal bar 32 is equidistant from top to bottom Building floor basic unit 1 is divided into shower area 4 and facilitates area 5 by the round steel of a diameter of φ 6mm of arrangement, elastic water bar 3, is being washed one's hair Bath area 4 and to facilitate and be equipped with ground decoration pave-load layer respectively on the waterproof layer 2 in area 5, the top of elastic water bar 3 extends to ground Decoration pave-load layer top 10mm, button is covered with U-shaped water-blocking bank 6, U-shaped gear on the elastic water bar 3 above ground decoration pave-load layer Water bank 6 is marble material, and its two ends extends respectively to 30mm in the toilet body of wall of corresponding end, and U-shaped water-blocking bank 6 includes being horizontally set with Level support platform 61 and sealing vertical in the top of elastic water bar 3 is supported on the He of inner support platform 62 of the both sides of elastic water bar 3 The aperture pitch of outer support platform 63, inner support platform 62 and outer support platform 63 is 60 mm, and top and the level of elastic water bar 3 are propped up Support platform 61 bottom surface distance has glue filling groove again for the lower surface middle part of 25mm, inner support platform 62 and outer support platform 63 66, interstitital texture glue forms structural adhesive layer 9 in glue filling groove 66, and inner support platform 62 and outer support platform 63 pass through upper knot Structure glue-line 9 is closed to be bonded on the ground decoration pave-load layer of respective side, in level support platform 61 corresponding with elastic water bar 3 Fang Kaiyou can grip the spacing groove 64 of shower room dividing plate 10, be provided with the bottom of spacing groove 64 and turn in inner support platform Air-vent 65 between 62 and the opening of outer support platform 63, between U-shaped water-blocking bank 6, inside and outside ground decoration pave-load layer and elastic water bar 3 Cement mortar 7 is filled with the gap of formation, the corresponding ground decoration pave-load layer in shower area 4 includes being laid on waterproof layer 2 successively On interior cement mortar lower protective layer 12, shower area ground-heating thermal insulation layer 13, heating wire floor heating 14, shower area steel fabric sheet 15, interior Protective layer 16 in cement mortar, interpolymer cement-based waterproof floor 17, interior cement mortar up-protective layer 18 and shower area decorative layer 19, facilitate the corresponding ground decoration pave-load layer in area 5 include be laid on successively on waterproof layer 2 outer cement mortar lower protective layer 21, Facilitate area's ground-heating thermal insulation layer 22, water floor heating pipe 23, facilitate protective layer 25 in area's steel fabric sheet 24, outer cement mortar, outer polymer Cement-based waterproof floor 26, outer cement mortar up-protective layer 27 and facilitate area's decorative layer 28, wherein interpolymer cement-based waterproof layer 17 and the surface of the outer polymer cement-based waterproof layer 26 elastic water bar 3 that carries over respective side respectively upwardly extend and in elasticity gear The top surface of water bar 3 is relative to be connected in one, and interior cement mortar up-protective layer 18 and outer cement mortar up-protective layer 27 carry over correspondence again Polymer cement-based waterproof layer 17 and the outer surface of polymer cement-based waterproof layer 26 upwardly extend and on the top of elastic water bar 3 Face top is relative to be connected in one.
A kind of construction method of shower room water-blocking bank structure, including order below step:
1)In the surface laying waterproof layer 2 of building floor basic unit 1 of toilet;
2)T-shaped elastic water bar 3 is taken, the horizontal face of elastic water bar 3 is bonded in waterproof layer by the way that lower structural adhesive layer 8 is closed On 2, the longitudinal surface of elastic water bar 3 extends vertically upwards to form shower area 4 and facilitate area 5;
3)In shower area 4 and area 5 is facilitated lay ground decoration pave-load layer respectively, and the longitudinal surface top extension of elastic water bar 3 To the top of ground decoration pave-load layer;
4)U-shaped water-blocking bank 6 is taken, is applied on the opening end face of U-shaped water-blocking bank 6 and is spread structural adhesive layer 9, then U-shaped water-blocking bank 6 is detained into cover On elastic water bar 3 above ground decoration pave-load layer, the closed ground for being bonded in respective side of opening of U-shaped water-blocking bank 6 is made Face decoration is mated formation in layer surface;
5)From the two ends of U-shaped water-blocking bank 6 to cement injection mortar 7 between the opening of U-shaped water-blocking bank 6, cement mortar 7 is set to be full of U The U-shaped tubular space that shape water-blocking bank 6, ground decoration pave-load layer and elastic water bar 3 are constituted.
Interpolymer cement-based waterproof floor 17 is wherein carried in the corresponding ground decoration pave-load layer in shower area 4, is facilitating area 5 Carry outer polymer cement-based waterproof layer 26 in corresponding ground decoration pave-load layer, interpolymer cement-based waterproof layer 17 and outer poly- Compound cement-based waterproof layer 26 carries over respectively the surface of the elastic water bar 3 of respective side and upwardly extends and in elastic water bar 3 Top surface is relative to be connect, and interior cement mortar up-protective layer 18 and outer cement mortar up-protective layer 27 carry over corresponding polyalcohol cement basis again Waterproof layer 17 and the outer surface of polymer cement-based waterproof layer 26 upwardly extend the top face for being docked at elastic water bar 3.
Specific embodiment described herein is only the design explanation for example to the present invention.Technology belonging to of the invention The technical staff in field can make various modifications to described specific embodiment or supplement or adopt similar mode Substitute, but without departing from the spiritual of the present invention or surmount scope defined in appended claims.

Claims (10)

1. a kind of building floor basic unit of shower room water-blocking bank structure, including toilet(1)And it is laid on building floor basic unit(1) On waterproof layer(2), it is characterised in that:In the waterproof layer(2)Upper closed fixed elastic water bar(3), elastic water bar (3)By building floor basic unit(1)It is divided into shower area(4)With facilitate area(5), in shower area(4)With facilitate area(5)Waterproof layer (2)It is upper to be equipped with ground decoration pave-load layer, elastic water bar respectively(3)Top extend to the top of ground decoration pave-load layer, Elastic water bar above ground decoration pave-load layer(3)Upper button is covered with U-shaped water-blocking bank(6), U-shaped water-blocking bank(6)Two ends it is close Close and be fixed on the ground decoration of respective side and mat formation layer surface, and in U-shaped water-blocking bank(6)With elastic water bar(3)Between formed between Cement mortar is filled with gap(7).
2. a kind of shower room water-blocking bank structure according to claim 1, it is characterised in that:The elastic water bar(3)Bag Include T-shaped rubber matrix(31), T-shaped rubber matrix(31)Horizontal face by lower structural adhesive layer(8)It is closed to be bonded in waterproof Layer(2)On, T-shaped rubber matrix(31)Longitudinal surface extend vertically up to outside ground decoration pave-load layer, and in T-shaped rubber Matrix(31)Longitudinal surface in interval be coated with some horizontal metal bars(32).
3. a kind of shower room water-blocking bank structure according to claim 1 and 2, it is characterised in that:The U-shaped water-blocking bank(6) Including being horizontally set with elastic water bar(3)The level support platform of top(61)And sealing vertical is supported on elastic water bar(3)Both sides Inner support platform(62)With outer support platform(63), inner support platform(62)With outer support platform(63)By upper structural adhesive layer(9)It is closed It is bonded on the ground decoration pave-load layer of respective side, in level support platform(61)Top be provided with and can grip shower room dividing plate (10)Spacing groove(64).
4. a kind of shower room water-blocking bank structure according to claim 3, it is characterised in that:In the spacing groove(64)'s Bottom is provided with and turns in inner support platform(62)With outer support platform(63)Between air-vent(65).
5. a kind of shower room water-blocking bank structure according to claim 3, it is characterised in that:In the inner support platform(62)With Outer support platform(63)Lower surface middle part have glue filling groove(66), upper structural adhesive layer(9)It is filled in glue filling Groove(66)It is interior.
6. a kind of shower room water-blocking bank structure according to claim 1 and 2, it is characterised in that:The shower area(4)Correspondence Ground decoration pave-load layer include be laid on waterproof layer successively(2)On interior cement mortar lower protective layer(12), the floor heating of shower area Heat-insulation layer(13), heating wire floor heating(14), shower area steel fabric sheet(15), protective layer in interior cement mortar(16), interpolymer Cement-based waterproof layer(17), interior cement mortar up-protective layer(18)With shower area decorative layer(19), facilitate area(5)Corresponding ground Decoration pave-load layer includes being laid on waterproof layer successively(2)On outer cement mortar lower protective layer(21), facilitate area's ground-heating thermal insulation layer (22), water floor heating pipe(23), facilitate area's steel fabric sheet(24), protective layer in outer cement mortar(25), outer polyalcohol cement basis prevent Water layer(26), outer cement mortar up-protective layer(27)With facilitate area's decorative layer(28), wherein interpolymer cement-based waterproof layer (17)With outer polymer cement-based waterproof layer(26)The elastic water bar of respective side is carried over respectively(3)Surface upwardly extend and Elastic water bar(3)Top surface it is relative connect, interior cement mortar up-protective layer(18)With outer cement mortar up-protective layer(27)It is again suitable Along corresponding polymer cement-based waterproof layer(17)With outer polymer cement-based waterproof layer(26)Surface upwardly extends and in elasticity Water bar(3)Top face relative connect.
7. a kind of shower room water-blocking bank structure according to claim 1 and 2, it is characterised in that:The elastic water bar(3) Two ends extend respectively in the toilet body of wall of corresponding end.
8. a kind of shower room water-blocking bank structure according to claim 1 and 2, it is characterised in that:The elastic water bar(3) Thickness be 10mm ± 2mm, U-shaped water-blocking bank(6)Aperture pitch be 60mm ± 5mm, elastic water bar(3)Top and U-shaped Water-blocking bank(6)Bottom surface distance is 25 mm ± 5mm between opening.
9. a kind of construction method of shower room water-blocking bank structure, it is characterised in that:Including order below step:
1)In the building floor basic unit of toilet(1)Lay waterproof layer in surface(2);
2)Take T-shaped elastic water bar(3), elastic water bar(3)Horizontal face by lower structural adhesive layer(8)It is closed to be bonded in Waterproof layer(2)On, elastic water bar(3)Longitudinal surface extend vertically upwards to form shower area(4)With facilitate area(5);
3)In shower area(4)With facilitate area(5)Laying ground decoration pave-load layer, and elastic water bar(3)Longitudinal surface top prolong Extend the top of ground decoration pave-load layer;
4)Take U-shaped water-blocking bank(6), in U-shaped water-blocking bank(6)Apply on opening end face and spread structural adhesive layer(9), then by U-shaped dash Bank(6)Button covers on the elastic water bar above ground decoration pave-load layer(3)On, make U-shaped water-blocking bank(6)The closed bonding of opening Mat formation in layer surface in the ground decoration of respective side;
5)From U-shaped water-blocking bank(6)Two ends to U-shaped water-blocking bank(6)Opening between cement injection mortar(7), make cement mortar (7)Full of U-shaped water-blocking bank(6), ground decoration pave-load layer and elastic water bar(3)The U-shaped tubular space of composition.
10. the construction method of a kind of shower room water-blocking bank structure according to claim 9, it is characterised in that:Wash one's hair described Bath area(4)Interpolymer cement-based waterproof layer is carried in corresponding ground decoration pave-load layer(17), facilitating area(5)Correspondingly Outer polymer cement-based waterproof layer is carried in the decoration pave-load layer of face(26), interpolymer cement-based waterproof layer(17)With outer polymer Cement-based waterproof layer(26)The elastic water bar of respective side is carried over respectively(3)Surface upwardly extend and in elastic water bar(3) Top surface it is relative connect, interior cement mortar up-protective layer(18)With outer cement mortar up-protective layer(27)Corresponding polymer is carried over again Cement-based waterproof layer(17)With outer polymer cement-based waterproof layer(26)Surface upwardly extends and is docked at elastic water bar(3)Top Face top.
CN201611057876.5A 2016-11-25 2016-11-25 A kind of shower room water-blocking bank structure and construction method Active CN106638995B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611057876.5A CN106638995B (en) 2016-11-25 2016-11-25 A kind of shower room water-blocking bank structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611057876.5A CN106638995B (en) 2016-11-25 2016-11-25 A kind of shower room water-blocking bank structure and construction method

Publications (2)

Publication Number Publication Date
CN106638995A true CN106638995A (en) 2017-05-10
CN106638995B CN106638995B (en) 2018-11-30

Family

ID=58811589

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611057876.5A Active CN106638995B (en) 2016-11-25 2016-11-25 A kind of shower room water-blocking bank structure and construction method

Country Status (1)

Country Link
CN (1) CN106638995B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108301519A (en) * 2018-02-06 2018-07-20 北京矿建建设集团有限公司 A kind of toilet shower area water proof building structure
CN110670739A (en) * 2019-08-22 2020-01-10 中国十七冶集团有限公司 Waterproof construction method for floor skirting line
CN112081493A (en) * 2020-09-15 2020-12-15 燕山大学 Water-stopping anti-ridge component of bathroom shower room and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202006004216U1 (en) * 2006-03-16 2007-08-02 Fwr Solutions Gmbh Form work for use in concrete building, comprises joint element bridging gap formed by reinforcing arrangement and water barrier
CN203462722U (en) * 2013-08-22 2014-03-05 上海建工一建集团有限公司 Floor water-proof structure of bathroom paved with floor heating equipment
CN204531883U (en) * 2015-04-02 2015-08-05 上海朗诗规划建筑设计有限公司 Shower house dash threshold constructs
CN204781464U (en) * 2015-06-10 2015-11-18 华鼎建筑装饰工程有限公司 Water bar between shower
CN205134568U (en) * 2015-11-30 2016-04-06 浙江亚厦装饰股份有限公司 A stagnant water structure for bathroom
CN206233387U (en) * 2016-11-25 2017-06-09 绿城装饰工程集团有限公司 A kind of shower room water-blocking bank structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202006004216U1 (en) * 2006-03-16 2007-08-02 Fwr Solutions Gmbh Form work for use in concrete building, comprises joint element bridging gap formed by reinforcing arrangement and water barrier
CN203462722U (en) * 2013-08-22 2014-03-05 上海建工一建集团有限公司 Floor water-proof structure of bathroom paved with floor heating equipment
CN204531883U (en) * 2015-04-02 2015-08-05 上海朗诗规划建筑设计有限公司 Shower house dash threshold constructs
CN204781464U (en) * 2015-06-10 2015-11-18 华鼎建筑装饰工程有限公司 Water bar between shower
CN205134568U (en) * 2015-11-30 2016-04-06 浙江亚厦装饰股份有限公司 A stagnant water structure for bathroom
CN206233387U (en) * 2016-11-25 2017-06-09 绿城装饰工程集团有限公司 A kind of shower room water-blocking bank structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108301519A (en) * 2018-02-06 2018-07-20 北京矿建建设集团有限公司 A kind of toilet shower area water proof building structure
CN110670739A (en) * 2019-08-22 2020-01-10 中国十七冶集团有限公司 Waterproof construction method for floor skirting line
CN112081493A (en) * 2020-09-15 2020-12-15 燕山大学 Water-stopping anti-ridge component of bathroom shower room and construction method thereof

Also Published As

Publication number Publication date
CN106638995B (en) 2018-11-30

Similar Documents

Publication Publication Date Title
CN106978856B (en) A kind of waterproof system and construction method of toilet
CN205077752U (en) Roofing flashing waterproofing membrane of department brick wall protection architecture
CN206233387U (en) A kind of shower room water-blocking bank structure
CN106638995A (en) Bath room water blocking ridge structure and construction method
CN202718362U (en) Waterproof base plate for toilet or shower room
CN110093989A (en) A kind of interior waterproof construction and its construction method
CN101832011A (en) Waterproof construction method of water-stopping doorsill of heating washroom with low-temperature radiation floor
CN102628291A (en) Sanitary basin
CN111042363A (en) Building heat preservation outer wall
CN104295009A (en) Deformation joint structure of planted roof
CN206233388U (en) A kind of waterproof system of toilet
CN206220272U (en) Ground hot water lays heating toilet doorway sealing damp proof insulation construction
CN205530719U (en) Building balcony seepage prevention structure
CN205259401U (en) Archaize building of grey brick wall
CN207331937U (en) A kind of floor drain mounting structure
CN206233391U (en) T-shaped rubber water bar
CN206397006U (en) A kind of parapet of roofing flashing structure
CN103526832A (en) High-rise outer wall dividing joint structure
CN210767273U (en) Node processing structure at separation position of shower room and washing room
CN102011495B (en) Anti-leakage balcony and hollow ecological garden of balcony type
CN210713273U (en) Waterproof structure for arranging falling plate for placing drainage device in toilet
CN205135250U (en) Window board that joint strength is high
CN208518097U (en) Shower cabinet waterproof construction
CN209111656U (en) A kind of edge is equipped with the waterproof roll on connection slope
CN219825909U (en) External wall surface structure for outdoor elevator shaft

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: Room 185-190, 1st Floor, Building 5, No. 199 Shuanglong Street, Xihu District, Hangzhou City, Zhejiang Province, 310030

Patentee after: Greentown Construction Technology Group Co.,Ltd.

Address before: 310012 9th Floor, Block B, United Building, No. 2 Bauhinghua Road, Xihu District, Hangzhou City, Zhejiang Province

Patentee before: GREENTOWN DECORATION ENGINEERING GROUP Co.,Ltd.