CN111364479A - Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof - Google Patents

Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof Download PDF

Info

Publication number
CN111364479A
CN111364479A CN202010294474.7A CN202010294474A CN111364479A CN 111364479 A CN111364479 A CN 111364479A CN 202010294474 A CN202010294474 A CN 202010294474A CN 111364479 A CN111364479 A CN 111364479A
Authority
CN
China
Prior art keywords
threaded
pile
threaded pile
foundation pit
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010294474.7A
Other languages
Chinese (zh)
Inventor
翁功伟
代坤
汪发军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Kunlei Construction Co ltd
Original Assignee
Ningbo Kunlei Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Kunlei Construction Co ltd filed Critical Ningbo Kunlei Construction Co ltd
Priority to CN202010294474.7A priority Critical patent/CN111364479A/en
Publication of CN111364479A publication Critical patent/CN111364479A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种用于基坑围护的斜向支撑螺纹桩支护结构,包括支护桩、位于土层下方的基础底板和多个螺纹桩,每个螺纹桩的上端与支护桩的上端连接,每个螺纹桩穿过基础底板而至少部分进入基础底板下方的撑力土层,所述螺纹桩由上至下逐渐相向倾斜,其特征在于:所述基础底板内、在被螺纹桩贯穿处设置有止水套管,所述止水套管设置在螺纹桩外周、并且与螺纹桩可拆卸连接。还公开了该斜向支撑螺纹桩支护结构的施工方法。与现有技术相比,本发明的优点在于:通过在基础底板内设置止水套管、止水套管与螺纹桩可拆卸连接,可便于螺纹桩拆除回收,降低了施工成本,无需考虑施工缝的问题,后期结构处理简便、质量可靠。

Figure 202010294474

The invention discloses an obliquely supporting threaded pile supporting structure for foundation pit enclosure, comprising supporting piles, a foundation bottom plate located under the soil layer and a plurality of threaded piles, the upper end of each threaded pile is connected to the supporting pile The upper ends of the threaded piles are connected to each other, each threaded pile passes through the foundation bottom plate and at least partially enters the supporting soil layer below the foundation bottom plate, and the threaded piles are gradually inclined toward each other from top to bottom. A water-stop casing is arranged at the penetration of the pile, and the water-stop casing is arranged on the outer periphery of the threaded pile and is detachably connected with the threaded pile. Also disclosed is a construction method of the obliquely bracing threaded pile supporting structure. Compared with the prior art, the present invention has the advantages that: by arranging a water-stop casing in the base plate, and the water-stop casing and the threaded pile are detachably connected, the threaded pile can be easily dismantled and recovered, the construction cost is reduced, and the construction need not be considered. The problem of seam is easy to handle in the later stage, and the quality is reliable.

Figure 202010294474

Description

用于基坑围护的斜向支撑螺纹桩支护结构及其施工方法Oblique support threaded pile support structure for foundation pit enclosure and construction method thereof

技术领域technical field

本发明涉及基坑围护领域,尤其是一种用于基坑围护的斜向支撑螺纹桩支护结构,以及该结构的施工方法。The invention relates to the field of foundation pit enclosure, in particular to an oblique support threaded pile supporting structure for foundation pit enclosure, and a construction method of the structure.

背景技术Background technique

深基坑工程中往往需要增加支护系统来增加基坑工程的安全、稳定,确保基坑周边环境、基坑内工程桩等不产生影响,也需要确保施工人员、机械等安全。目前常见几种支护形式:平撑、斜撑以及锚拉。In the deep foundation pit project, it is often necessary to add a support system to increase the safety and stability of the foundation pit project, to ensure that the surrounding environment of the foundation pit and the engineering piles in the foundation pit will not be affected, and it is also necessary to ensure the safety of construction personnel and machinery. There are several common forms of support: flat support, diagonal support and anchor pull.

平撑是目前深基坑应用最广泛的一种支护形式,但是平撑一般跨度大、施工周期长、成本高,支护结构体系复杂,而且极不利于土方开挖与主体结构施工。同时该支护形式后期需全部拆除,环境污染严重、存在诸多安全隐患。Flat bracing is currently the most widely used form of support for deep foundation pits. However, flat bracing generally has large span, long construction period, high cost, complex supporting structure system, and is extremely unfavorable for earthwork excavation and main structure construction. At the same time, this support form needs to be completely dismantled in the later stage, causing serious environmental pollution and many potential safety hazards.

锚拉常见的如旋喷锚杆索或土钉墙,但该种支护形式对于软土等土性较差或挖深较深的基坑并不适用,安全系数低、施工质量安全隐患大;而且由于锚固长度较长,往往需伸出建筑红线十几或数十米范围外,场地周边环境对其有相当制约性。Anchor pulls are common, such as jetting bolts or soil nailing walls, but this type of support is not suitable for soft soil and other poor soil or deep excavation foundation pits, with low safety factor and great hidden dangers to construction quality and safety. Moreover, due to the long anchoring length, it is often necessary to extend beyond the red line of the building by a dozen or tens of meters, and the surrounding environment of the site has considerable constraints on it.

目前常见的斜撑如钢筋混凝土、钢管或型钢斜撑,均是支撑于地下室底板上,较为经济。该种支护形式常用于中心岛开挖、二次围护后施工区或局部加强处,待地下室底板强度达到75%以上才能发挥作用,施工周期长,变形控制反应慢。后期拆除与该处结构处理困难。At present, the common diagonal bracing such as reinforced concrete, steel pipe or section steel diagonal bracing is supported on the basement floor, which is more economical. This type of support is often used in excavation of the central island, construction areas after secondary enclosures, or local reinforcement. It can only play a role when the strength of the basement floor reaches more than 75%. The construction period is long and the deformation control response is slow. It is difficult to dismantle and deal with the structure in the later stage.

申请号为201410107071.1的中国专利公开了一种用于基坑围护的斜向支撑桩结构及其施工方法,该结构包括围护桩、冠梁、基坑底板、建筑结构、斜向支撑桩、止水装置以及土壤改良结构,其中斜向支撑桩呈一定角度斜向植入于基坑底板以下的原始土壤中,原始土壤通过高压旋喷桩或土壤固化剂进行硬化处理;斜向支撑桩顶端与围护桩顶端固定连接嵌入冠梁内部并于冠梁整体现浇,穿过建筑结构底板与剪力墙处设置了止水环。The Chinese patent with the application number of 201410107071.1 discloses an oblique support pile structure for foundation pit enclosure and a construction method thereof. The structure includes enclosure piles, crown beams, foundation pit floor, building structure, oblique support piles, Water stop device and soil improvement structure, in which the oblique support pile is obliquely implanted into the original soil below the foundation pit floor at a certain angle, and the original soil is hardened by high-pressure rotary spray pile or soil curing agent; the top of the oblique support pile is It is fixedly connected with the top of the retaining pile and embedded in the crown beam and is cast in place on the crown beam as a whole, and a water stop ring is set through the bottom plate of the building structure and the shear wall.

该发明专利相对于平撑能够有利土方开挖、缩短工期,相对于传统抛撑可节约施工周期;但是该专利的装置是一次性使用的,无法进行回收再利用,无法实现节材,势必增加基坑成本;支撑底部的土壤虽进行了土壤改良,但采用H型钢结构、钢格构柱结构或钢管结构均是依靠摩擦阻力提供斜向支撑力,支撑效果依旧难易保障,特别是饱和软土地区,并且H型钢结构、钢格构柱结构或钢管结构割除后会导致后期地下室结构渗漏水或影响结构的耐久性;该支护在基坑发生较大变形时自身无法提供有效的调节加固措施,需采取附加措施或加固措施后方可解决,这对于基坑这类风险较大的项目而言,处置效率上是极为不利的。Compared with the flat support, the invention patent can facilitate earthwork excavation and shorten the construction period, and compared with the traditional throwing support, it can save the construction period; however, the device of this patent is one-time use, cannot be recycled and reused, and cannot realize material saving, which is bound to increase. The cost of foundation pit; although the soil at the bottom of the support has been improved, the H-shaped steel structure, steel lattice column structure or steel pipe structure all rely on frictional resistance to provide oblique support force, and the support effect is still difficult to ensure, especially when saturated soft materials are used. If the H-shaped steel structure, steel lattice column structure or steel pipe structure is cut off, it will cause water leakage in the basement structure in the later stage or affect the durability of the structure; the support itself cannot provide effective adjustment when the foundation pit is greatly deformed. Reinforcement measures can only be solved after additional measures or reinforcement measures are taken, which is extremely unfavorable in terms of disposal efficiency for projects with high risks such as foundation pits.

然而,由于目前基坑所处的周边环境越来越复杂,例如:周边林立建筑物距离建筑红线近、基坑四周管线种类数量繁多、场地狭小后导致材料堆场加工区紧邻基坑变形等。当基坑出现变形较大时往往存在无法通过围护自身提供加固保障,需增设外部支护体系才能控制变形。However, because the surrounding environment of the foundation pit is becoming more and more complex, for example: the surrounding buildings are close to the red line of the building, there are many types of pipelines around the foundation pit, and the material storage yard processing area is close to the foundation pit after the small site is deformed. When the deformation of the foundation pit is large, it is often impossible to provide reinforcement protection through the enclosure itself, and an external support system needs to be added to control the deformation.

此外,“建设节约资料,加快建设节约型社会”是我国长期坚持的一项基本国策,而在保障基坑安全的前提下降低基坑造价更是项目投资者的追求。传统基坑工程中存在诸多材料、人工资源浪费的现象,支护形式工程量大、造价高、后期固体粉尘污染严重。In addition, "constructing materials-saving and accelerating the construction of a conservation-minded society" is a basic national policy that my country has adhered to for a long time, and reducing the cost of foundation pits on the premise of ensuring the safety of foundation pits is the pursuit of project investors. There are many wastes of materials and artificial resources in traditional foundation pit engineering. The supporting form has a large amount of engineering work, high cost and serious solid dust pollution in the later stage.

为此,需要进一步改进。For this, further improvements are required.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的第一个技术问题是针对上述现有技术存在的不足,提供一种用于基坑围护的斜向支撑螺纹桩支护结构,能够提供高支撑力,可根据基坑变形情况进行加固调节,同时还便于回收再利用。The first technical problem to be solved by the present invention is to provide an oblique support threaded pile support structure for foundation pit enclosure, which can provide high support force, and can adapt to the deformation of foundation pit. It is also easy to recycle and reuse.

本发明所要解决的第二个技术问题是提供一种上述斜向支撑螺纹桩支护结构的施工方法。The second technical problem to be solved by the present invention is to provide a construction method for the above-mentioned obliquely braced threaded pile support structure.

本发明解决上述第一个技术问题所采用的技术方案为:一种用于基坑围护的斜向支撑螺纹桩支护结构,包括支护桩、位于土层下方的基础底板和多个螺纹桩,每个螺纹桩的上端与支护桩的上端连接,每个螺纹桩从基础底板上方穿过基础底板而至少部分进入基础底板下方的撑力土层,所述螺纹桩由上至下逐渐相向倾斜,其特征在于:所述基础底板内、在被螺纹桩贯穿处设置有止水套管,所述止水套管设置在螺纹桩外周、并且与螺纹桩可拆卸连接。The technical solution adopted by the present invention to solve the above-mentioned first technical problem is as follows: an oblique support threaded pile support structure for foundation pit enclosure, comprising a support pile, a foundation bottom plate located under the soil layer and a plurality of threads Pile, the upper end of each threaded pile is connected with the upper end of the supporting pile, each threaded pile passes through the foundation base plate from above the foundation base plate and at least partially enters the supporting soil layer below the foundation base plate, and the threaded pile gradually goes from top to bottom. Oppositely inclined, it is characterized in that a water-stop sleeve is arranged in the base bottom plate where the threaded pile penetrates, and the water-stop sleeve is arranged on the outer periphery of the threaded pile and is detachably connected to the threaded pile.

优选的,为便于螺纹桩的旋退回收,所述止水套管内侧设置有内螺纹,从而与螺纹桩螺纹连接,螺纹桩旋转回收时便于旋退,止水套管内的内螺纹也有利于增加基础底板的止水性。Preferably, in order to facilitate the unscrewing and retracting of the threaded pile, the inside of the water-stop casing is provided with an internal thread, so as to be threadedly connected to the threaded pile, and the threaded pile is easy to unscrew when the threaded pile is rotated and recovered, and the internal thread in the water-stop casing is also conducive to Increase the water stop of the base plate.

优选的,为提供足够的支撑力,所述止水套管的壁厚≥2.0mm。Preferably, in order to provide sufficient supporting force, the wall thickness of the water stop sleeve is ≥2.0 mm.

优选的,为便于控制基坑的变形,所述支护桩的上端设置有冠梁,所述冠梁和螺纹桩之间通过能调节的锚固装置连接。Preferably, in order to control the deformation of the foundation pit, the upper end of the support pile is provided with a crown beam, and the crown beam and the threaded pile are connected by an adjustable anchoring device.

优选的,为便于冠梁和螺纹桩连接,沿所述冠梁的方向间隔设置有与螺纹桩连接的牛腿,所述冠梁上开设有供螺纹桩的端部进入的孔或开口槽。Preferably, in order to facilitate the connection between the crown beam and the threaded pile, corbels connected to the threaded pile are arranged at intervals along the direction of the crown beam, and the crown beam is provided with a hole or an open groove for the end of the threaded pile to enter.

优选的,为提供较好的斜向支撑力以及抗拔承载力,同时便于拆除,每个螺纹桩包括互相连接的第一螺纹桩段和第二螺纹桩段,第一螺纹桩段位于第二螺纹桩段上方,所述第二螺纹桩段穿过基础底板而拧入土层中,所述第二螺纹桩段与止水套管连接、并且通过螺叶与土层机械咬合,所述第二螺纹桩段的螺叶的宽度≥120mm。Preferably, in order to provide better oblique support force and anti-pulling bearing capacity, and at the same time facilitate dismantling, each threaded pile includes a first threaded pile section and a second threaded pile section that are connected to each other, and the first threaded pile section is located in the second threaded pile section. Above the threaded pile section, the second threaded pile section is screwed into the soil layer through the foundation bottom plate, the second threaded pile section is connected with the water stop casing, and mechanically engaged with the soil layer through the screw blade, the second threaded pile section is The width of the screw blade of the threaded pile section is greater than or equal to 120mm.

本发明解决上述第二个技术问题所采用的技术方案为:一种如上所述的斜向支撑螺纹桩支护结构的施工方法,包括如下步骤:The technical solution adopted by the present invention to solve the above-mentioned second technical problem is: a construction method of the above-mentioned oblique support threaded pile supporting structure, comprising the following steps:

1)支护桩施工:在基坑周围施工支护桩,在支护桩的上端部浇筑用于与螺纹桩连接的冠梁;1) Construction of supporting piles: construct supporting piles around the foundation pit, and pour the crown beams used to connect with the threaded piles at the upper end of the supporting piles;

2)安装螺纹桩:将第一螺纹桩段和第二螺纹桩段互相连接成一整体的螺纹桩,将螺纹桩呈一定角度旋拧植入土层中,直到达到设计要求的基础底板以下一定深度;2) Installation of threaded piles: Connect the first threaded pile section and the second threaded pile section to form an integral threaded pile, and screw the threaded pile into the soil layer at a certain angle until it reaches a certain depth below the base plate required by the design ;

3)检测承载力:抽取若干数量的螺纹桩进行斜向受压承载力检测,同时确定螺纹桩的支撑富余量;3) Detection of bearing capacity: extract a number of threaded piles to test the bearing capacity of oblique compression, and determine the supporting margin of the threaded piles at the same time;

4)对螺纹桩锚固:对螺纹桩的锚固位置进行处理,并套入锚固装置,待冠梁混凝土强度达到一定程度后,沿着基坑通过锚固装置对螺纹桩间隔均匀地与冠梁拧紧锚固,由此使得支护桩和螺纹桩形成为具有相互作用力的整体结构;4) Anchoring the threaded pile: Treat the anchoring position of the threaded pile, and insert the anchoring device. After the concrete strength of the crown beam reaches a certain level, the threaded pile is evenly spaced along the foundation pit through the anchoring device. Tighten the anchorage to the crown beam , so that the supporting pile and the threaded pile are formed into an integral structure with interaction force;

5)开挖基坑:待冠梁达到一定强度后,进行基坑土方开挖;5) Excavation of the foundation pit: After the crown beam reaches a certain strength, the earthwork of the foundation pit is excavated;

6)基础底板施工:待基坑开挖完成,进行基础底板的施工,在施工基础底板时,将止水套管置于基础底板中、并固定;6) Construction of the foundation floor: After the excavation of the foundation pit is completed, the construction of the foundation floor is carried out. When the foundation floor is constructed, the water stop sleeve is placed in the foundation floor and fixed;

7)拆除螺纹桩:待基础底板施工完毕并且达到围护设计要求的支撑拆除条件后,先间隔拧松锚固装置,随即进行基坑变形监测,如果数据稳定则将螺纹桩拆除回收,如果数据不稳定则对基坑采用加固措施以保障基坑安全。7) Removal of threaded piles: After the construction of the base plate is completed and the support removal conditions required by the enclosure design are met, loosen the anchoring device at intervals, and then monitor the deformation of the foundation pit. If the data is stable, the threaded piles are removed and recycled. For stability, reinforcement measures are adopted for the foundation pit to ensure the safety of the foundation pit.

优选的,为便于控制基坑变形,在步骤5)和6)中,如果基坑变形超出围护设计及规范要求的数值时,采用对锚固装置进一步旋拧拧紧的方式控制基坑变形,此后基坑变形得到控制则无需采取加固措施,如果基坑变形未得到控制则需采取加固措施。Preferably, in order to control the deformation of the foundation pit, in steps 5) and 6), if the deformation of the foundation pit exceeds the value required by the enclosure design and specification, the deformation of the foundation pit is controlled by further screwing and tightening the anchoring device, and thereafter If the deformation of the foundation pit is controlled, it is not necessary to take reinforcement measures. If the deformation of the foundation pit is not controlled, reinforcement measures should be taken.

优选的,在步骤7)中,在拆除螺纹桩时,逐个进行拆除回收,每个螺纹桩卸下第一螺纹桩段,清理止水套管后将第二螺纹桩段旋拧回收。Preferably, in step 7), when dismantling the threaded piles, the threaded piles are dismantled and recovered one by one, the first threaded pile section is removed from each threaded pile, and the second threaded pile section is screwed and recovered after cleaning the water stop casing.

优选的,为避免基础底板渗漏水,在止水套管内壁设有与螺纹桩的螺叶匹配的螺板,在螺纹桩回收后通过混凝土封闭止水套管内部。Preferably, in order to avoid water leakage from the base plate, the inner wall of the water stop casing is provided with a screw plate matching the screw blades of the threaded pile, and the interior of the water stop casing is sealed by concrete after the threaded pile is recovered.

与现有技术相比,本发明的优点在于:通过在基础底板内设置止水套管、止水套管与螺纹桩可拆卸连接,可便于螺纹桩拆除回收,降低了施工成本,无需考虑施工缝的问题,后期结构处理简便、质量可靠;通过可调节的锚固装置将螺纹桩和支护桩连接,在土方开挖及基础施工期间可根据基坑变形情况进行自我调节,保障基坑安全;围护结构与斜向支撑结构施工工序上无先后性,可大大缩短工期;该支撑体系不需要大量的钢筋混凝土结构;可实现无障碍挖土及结构施工;斜向支撑体系拆除时可边卸载边监测,有效解决了支撑拆除而产生的应力释放不均或瞬时卸载的问题。Compared with the prior art, the present invention has the advantages that: by arranging a water-stop casing in the base plate, and the water-stop casing and the threaded pile are detachably connected, the threaded pile can be easily dismantled and recovered, the construction cost is reduced, and the construction need not be considered. To solve the problem of joints, the later structural processing is simple and the quality is reliable; the threaded pile and the supporting pile are connected by an adjustable anchoring device, and the self-adjustment can be performed according to the deformation of the foundation pit during the earthwork excavation and foundation construction to ensure the safety of the foundation pit; There is no sequence in the construction process of the enclosure structure and the oblique support structure, which can greatly shorten the construction period; the support system does not require a large number of reinforced concrete structures; barrier-free excavation and structural construction can be realized; the oblique support system can be unloaded while being dismantled Edge monitoring effectively solves the problem of uneven stress release or instantaneous unloading caused by support removal.

附图说明Description of drawings

图1为本发明实施例的斜向支撑螺纹桩支护结构的示意图;Fig. 1 is the schematic diagram of the support structure of the obliquely supported threaded pile according to the embodiment of the present invention;

图2为本发明实施例的斜向支撑螺纹桩支护结构的止水内螺纹套管剖示图;2 is a cross-sectional view of a water-stop internal threaded casing of an obliquely supporting threaded pile support structure according to an embodiment of the present invention;

图3为本发明实施例的斜向支撑螺纹桩支护结构的两段螺纹桩连接节点图;Fig. 3 is the connection node diagram of two sections of threaded piles of the obliquely supported threaded pile support structure according to the embodiment of the present invention;

图4为本发明实施例的斜向支撑螺纹桩支护结构的螺纹桩与冠梁连接节点图;Fig. 4 is the connection node diagram of the threaded pile and the crown beam of the obliquely supported threaded pile support structure according to the embodiment of the present invention;

图5为本发明实施例的斜向支撑螺纹桩支护结构的螺纹桩局部示意图。FIG. 5 is a partial schematic diagram of a threaded pile of an obliquely supporting threaded pile supporting structure according to an embodiment of the present invention.

具体实施方式Detailed ways

下面详细描述本发明的实施例,所述实施例的示例在附图中示出,其中相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。The following describes in detail the embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein the same or similar reference numerals refer to the same or similar elements or elements having the same or similar functions.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,由于本发明所公开的实施例可以按照不同的方向设置,所以这些表示方向的术语只是作为说明而不应视作为限制,比如“上”、“下”并不一定被限定为与重力方向相反或一致的方向。此外,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", " Rear, Left, Right, Vertical, Horizontal, Top, Bottom, Inner, Outer, Clockwise, Counterclockwise, Axial, The orientations or positional relationships indicated by "radial direction", "circumferential direction", etc. are based on the orientations or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the indicated devices or elements. must have a specific orientation, be constructed and operated in a specific orientation, and since the disclosed embodiments of the present invention may be arranged in different orientations, these directional terms are for illustration only and should not be regarded as limiting, such as "up", "Down" is not necessarily defined as a direction opposite or in line with the direction of gravity. Furthermore, features delimited with "first", "second" may expressly or implicitly include one or more of that feature.

参见图1,一种用于基坑围护的斜向支撑螺纹桩支护结构,包括支护桩1、基础底板2和螺纹桩3。支护桩1纵向延伸,基础底板2位于土层下方、基坑底部,其周边与支护桩1之间设置有便于进行力传导的换撑带21。Referring to FIG. 1 , an oblique support threaded pile supporting structure for foundation pit enclosure includes supporting piles 1 , foundation bottom plates 2 and threaded piles 3 . The supporting pile 1 extends longitudinally, and the foundation bottom plate 2 is located under the soil layer and at the bottom of the foundation pit.

参见图1和图3,螺纹桩3具有多个,为由金属制成的钢管,每个螺纹桩3包括第一螺纹桩段31和第二螺纹桩段32,其中,第一螺纹桩段31位于第二螺纹桩段32上方,第一螺纹桩段31的下端和第二螺纹桩段32的上端连接而构成完整的螺纹桩3。第一螺纹桩段31和第二螺纹桩段32通过钢管套管螺纹连接,并在连接节点处做加强处理,拆除时则可分段拆除回收。每个螺纹桩3的上端与支护桩1的上端连接,每个螺纹桩3的下端进入基础底板2以下的撑力土层中。每个螺纹桩3与竖直方向呈一定角度的倾斜,通过旋拧的方式穿过基础底板2标高进入土层中。两个螺纹桩3由上至下逐渐相向倾斜。1 and 3 , there are a plurality of threaded piles 3 , which are steel pipes made of metal, and each threaded pile 3 includes a first threaded pile section 31 and a second threaded pile section 32 , wherein the first threaded pile section 31 Located above the second threaded pile section 32 , the lower end of the first threaded pile section 31 and the upper end of the second threaded pile section 32 are connected to form a complete threaded pile 3 . The first threaded pile section 31 and the second threaded pile section 32 are threadedly connected by steel pipe casings, and are reinforced at the connection nodes, and can be dismantled and recovered in sections when dismantled. The upper end of each threaded pile 3 is connected to the upper end of the supporting pile 1 , and the lower end of each threaded pile 3 enters into the supporting soil layer below the base plate 2 . Each threaded pile 3 is inclined at a certain angle to the vertical direction, and enters the soil layer through the elevation of the foundation bottom plate 2 by screwing. The two threaded piles 3 are gradually inclined towards each other from top to bottom.

参见图1和图4,支护桩1的上端设置有冠梁11,冠梁11上预留有孔或开口槽12,第一螺纹桩段31的上端通过锚固装置13与冠梁11连接,第一螺纹桩段31的上端部分进入孔或开口槽12内。锚固装置13优选的为可调节螺母。由此,螺纹桩3与支护桩1形成整体。如果后期基坑变形较大时可通过旋拧加紧该锚固装置13达到控制基坑变形的效果。优选的,冠梁11处设置钢筋混凝土或钢结构的牛腿14。牛腿14与螺纹桩3呈90度设置,便于锚固装置13固定以及后期调节。1 and 4, the upper end of the support pile 1 is provided with a crown beam 11, a hole or an open groove 12 is reserved on the crown beam 11, and the upper end of the first threaded pile section 31 is connected with the crown beam 11 through the anchoring device 13, The upper end portion of the first threaded pile section 31 enters the hole or open slot 12 . The anchoring device 13 is preferably an adjustable nut. Thereby, the threaded pile 3 is integrally formed with the support pile 1 . If the deformation of the foundation pit is relatively large in the later stage, the anchoring device 13 can be tightened by screwing to achieve the effect of controlling the deformation of the foundation pit. Preferably, the crown beam 11 is provided with a corbel 14 of reinforced concrete or steel structure. The corbel 14 and the threaded pile 3 are arranged at 90 degrees, which is convenient for the anchoring device 13 to be fixed and adjusted later.

参见图5,螺纹桩3属于不规则桩,通过沿桩身四周形成的螺纹嵌合进土体,极大的改善受力形式。第一螺纹桩段31可为浅螺纹或光圆钢管,但在与冠梁11的锚固区域则设置成浅粗螺纹,并配备相应型号的锚固装置13。第二螺纹桩段32采用宽螺叶,斜向支撑力绝大部分由螺纹桩3螺叶与土体机械咬合形成的螺旋线性桩端承提供,加上增加螺叶厚度可提高整体刚度,从而能够提供很大的斜向支撑力以及抗拔承载力。Referring to Figure 5, the threaded pile 3 is an irregular pile, and the force-bearing form is greatly improved by fitting into the soil through the threads formed around the pile body. The first threaded pile section 31 can be a shallow thread or a smooth round steel pipe, but in the anchoring area with the crown beam 11 , it is provided with a shallow thick thread, and is equipped with a corresponding type of anchoring device 13 . The second threaded pile section 32 adopts a wide screw blade, and most of the oblique support force is provided by the helical linear pile end bearing formed by the mechanical engagement of the screw blade of the threaded pile 3 with the soil. It can provide great diagonal support and pull-out bearing capacity.

螺纹桩3下端的土层应当视其物理力学性能而定,如果支承在颗粒土层中,通过螺纹桩3螺叶的旋拧可对土体产生剪切挤密作用,能够提供高支撑力;在抗剪性能较好的土层中,只要对土体不进行扰动,螺纹桩3是依靠固定的螺纹路径旋拧进入与旋拧退出的,能够提供高支撑力;当遇到土层物理力学性能较差的,如软土时,可在螺纹桩3钢管内腔设置注浆管,第二螺纹桩段32的钢管壁上及钻头位置开设注浆孔321,随着螺纹桩3的旋拧,并搅拌边喷射水泥浆进行土层加固,从而形成硬质土壤支撑结构。The soil layer at the lower end of the threaded pile 3 should be determined according to its physical and mechanical properties. If it is supported in the granular soil layer, the screwing of the screw blade of the threaded pile 3 can produce a shearing and compacting effect on the soil, which can provide high support force; In the soil layer with good shear resistance, as long as the soil is not disturbed, the threaded pile 3 is screwed in and out by means of a fixed thread path, which can provide high support force; when encountering the physical mechanics of the soil layer For those with poor performance, such as soft soil, a grouting pipe can be installed in the inner cavity of the steel pipe of the threaded pile 3, and a grouting hole 321 is opened on the steel pipe wall of the second threaded pile section 32 and at the position of the drill bit. , and spray cement slurry while stirring to reinforce the soil layer to form a hard soil support structure.

优选的,螺纹桩3的壁厚为5~15mm,钢管直径需≥80mm,螺叶厚度需≥3.5mm,螺叶宽度具体根据工程试验确定,优选的宽度≥120mm。Preferably, the wall thickness of the threaded pile 3 is 5-15mm, the diameter of the steel pipe should be ≥80mm, and the thickness of the screw blade should be ≥3.5mm.

参见图1和图2,基础底板2内、在被第二螺纹桩段32贯穿处设置有止水套管4,止水套管4位于第二螺纹桩段32外周。止水套管4优选的为两个半圆形管件,通过焊接拼接成整圆形,设置于螺纹桩3的外周。通过设置止水套管4,一则起到了后期止水的效果,二则通过止水套管4的设置可使得螺纹桩3后期能够旋退回收利用。止水套管4具有内螺纹,第二螺纹桩段32穿过止水套管4、并且螺纹连接。止水套管4的内螺纹也有利于增加基础底板2的止水性。止水套管4外周一圈焊接有钢筋条,以加强止水套管4与基础底板2的连接,内部则设置与螺纹桩3的螺叶相匹配的螺板41,内螺纹形成在螺板41上,后期可通过高于基础底板2一个等级标高的微膨胀混凝土对止水套管4进行封闭,由此避免基础底板2漏水问题。Referring to FIGS. 1 and 2 , in the foundation bottom plate 2 , a water-stop sleeve 4 is provided at the place penetrated by the second threaded pile section 32 , and the water-stop sleeve 4 is located on the outer periphery of the second threaded pile section 32 . The water stop casing 4 is preferably two semi-circular pipe fittings, which are spliced into a full circle by welding, and are arranged on the outer periphery of the threaded pile 3 . By arranging the water-stop casing 4, firstly, the effect of water-stopping is achieved in the later stage, and secondly, the threaded pile 3 can be rotated back and recycled in the later stage through the arrangement of the water-stop casing 4. The water stop sleeve 4 has an internal thread, and the second threaded pile section 32 passes through the water stop sleeve 4 and is threadedly connected. The internal thread of the water stop sleeve 4 is also beneficial to increase the water stop of the foundation bottom plate 2 . The outer circumference of the water-stop casing 4 is welded with steel bars to strengthen the connection between the water-stop casing 4 and the base plate 2, and a screw plate 41 that matches the screw blade of the threaded pile 3 is arranged inside, and the internal thread is formed on the screw plate. 41, in the later stage, the water stop casing 4 can be sealed by the micro-expansion concrete one grade higher than the foundation floor 2, thereby avoiding the problem of water leakage of the foundation floor 2.

优选的,止水套管4的壁厚需≥2.0mm,其内部的内螺纹的螺距、螺宽需与第二螺纹桩段32的螺距、螺宽相对应,埋设角度需与螺纹桩3相同。止水套管4需在螺纹桩3固定前套入基础底板2内并做好后期的防护措施。止水套管4与基础底板2连接时,需采用四周钢筋焊接固定,以防基础底板2施工时错位或损坏,导致后期螺纹桩3无法旋拧回收。Preferably, the wall thickness of the water stop casing 4 needs to be ≥ 2.0 mm, the pitch and width of the internal thread of the water-stop casing 4 need to correspond to the pitch and width of the second threaded pile section 32 , and the embedding angle needs to be the same as the threaded pile 3 . . Before the threaded pile 3 is fixed, the water stop sleeve 4 needs to be inserted into the foundation bottom plate 2 and take protective measures in the later stage. When the water stop sleeve 4 is connected to the base plate 2, it is necessary to use the surrounding steel bars to weld and fix it, so as to prevent the base plate 2 from being dislocated or damaged during construction, so that the threaded piles 3 cannot be screwed and recovered in the later stage.

可替代的,止水套管4的内侧壁面也可以为光面,此时螺纹桩3穿过止水套管4并能相对止水套管4活动。止水套管4可在内侧壁面设置环形的止水钢板条,来起到止水的作用。只要在基础底板2内设置止水套管4,止水套管4和螺纹桩3之间为非固定的可拆卸连接方式,即可实现螺纹桩3的旋退回收。Alternatively, the inner wall surface of the water-stop sleeve 4 can also be a smooth surface, and the threaded pile 3 passes through the water-stop sleeve 4 and can move relative to the water-stop sleeve 4 at this time. The water-stop sleeve 4 can be provided with an annular water-stop steel strip on the inner side wall surface to play the role of water-stop. As long as the water-stop casing 4 is arranged in the foundation bottom plate 2, and the water-stop casing 4 and the threaded pile 3 are connected in a non-fixed and detachable manner, the screw pile 3 can be retracted and recovered.

上述斜向支撑螺纹桩支护结构的施工方法,包括如下步骤:The construction method of the above-mentioned obliquely braced threaded pile support structure includes the following steps:

1)支护桩1施工:在预设的基坑周围施工支护桩1,在支护桩1的上端部浇筑钢筋混凝土冠梁11,并沿冠梁11方向间隔一定距离设置钢筋混凝土牛腿14,冠梁11上预留有孔或开口槽12,以构成螺纹桩3旋拧用直通孔,牛腿14的位置、数量分别与孔或开口槽12对应;牛腿14的间距等于螺纹桩3的间距,冠梁11处优选的设置加强钢筋;1) Construction of the supporting pile 1: construct the supporting pile 1 around the preset foundation pit, pour the reinforced concrete crown beam 11 on the upper end of the supporting pile 1, and set the reinforced concrete corbel at a certain distance along the direction of the crown beam 11 14. There are holes or open grooves 12 reserved on the crown beam 11 to form straight through holes for screwing the threaded piles 3. The position and number of the corbels 14 correspond to the holes or the open grooves 12 respectively; the spacing of the corbels 14 is equal to the threaded piles. The spacing of 3, the reinforcement bars are preferably set at 11 of the crown beams;

2)安装螺纹桩3:将第一螺纹桩段31和第二螺纹桩段32互相连接成一整体的螺纹桩3,采用钻机将螺纹桩3呈一定角度旋拧植入土层中,直到达到设计要求的基础底板2以下一定深度(土层下一定深度);本实施例中土层为颗粒土,旋拧到位后无需高压注浆加固土层;钻机优选可90度调节角度的钻机,提供支撑力的第二螺纹桩段32的长度、螺叶距离、螺叶宽度等均需在事前进行斜向抗压检测确定标准,检测时需在上段土方开挖区设置隔离套管,从而测得可靠支撑力数据;2) Install the threaded pile 3: Connect the first threaded pile section 31 and the second threaded pile section 32 to form an integral threaded pile 3, and use a drilling rig to screw the threaded pile 3 into the soil layer at an angle until the design is achieved. A certain depth below the required base plate 2 (a certain depth under the soil layer); in this embodiment, the soil layer is granular soil, after screwing in place, no high-pressure grouting is required to reinforce the soil layer; the drilling rig is preferably a 90-degree angle-adjustable drilling rig to provide support The length of the second threaded pile section 32, the distance of the screw blade, the width of the screw blade, etc. shall be determined by the oblique compression test in advance. During the test, an isolation casing shall be installed in the excavation area of the upper section, so as to measure reliably. support data;

3)检测承载力:抽取若干数量的螺纹桩3进行斜向受压承载力检测,以保障基坑安全;进行抗压检测时,可在牛腿14位置设置加压装置,确保施加的力与螺纹桩3处于同一受力轴线上;检测时还需确定螺纹桩3的支撑富余量,以确保后期当基坑出现较大变形时可利用富余量进行自调节加固;3) Detection of bearing capacity: Extract a number of threaded piles 3 for oblique compressive bearing capacity detection to ensure the safety of the foundation pit; when performing compressive testing, a pressurizing device can be installed at the position of the corbel 14 to ensure that the applied force is consistent with the The threaded piles 3 are on the same force axis; the support allowance of the threaded piles 3 needs to be determined during the detection, so as to ensure that the surplus can be used for self-adjustment reinforcement when the foundation pit is greatly deformed in the later stage;

4)对螺纹桩3锚固:对螺纹桩3的锚固位置进行处理,并套入锚固装置13,待冠梁11混凝土强度达到一定程度、如75%后,沿着基坑通过锚固装置13对螺纹桩3间隔均匀地进行拧紧锚固,此时,支护桩1、螺纹桩3形成为具有相互作用力的整体结构;4) Anchoring the threaded pile 3: The anchoring position of the threaded pile 3 is processed, and the anchoring device 13 is inserted. After the concrete strength of the crown beam 11 reaches a certain level, such as 75%, the thread is passed through the anchoring device 13 along the foundation pit. The piles 3 are tightened and anchored evenly at intervals. At this time, the supporting piles 1 and the threaded piles 3 are formed into an integral structure with interaction force;

5)开挖基坑:待冠梁11达到一定强度后,按照规范及土方开挖专项施工方案进行土方开挖,由于已经采用了斜向支撑螺纹桩3,并且可根据基坑及土方开挖情况通过旋拧施加一定的预应力,基坑土方开挖可一次性全部开挖至设计标高处,不必局部开挖后做斜向支撑,再进行大面积土方开挖;5) Excavation of foundation pit: After the crown beam 11 reaches a certain strength, carry out earthwork excavation according to the specifications and the special construction plan for earthwork excavation. Since the oblique support threaded pile 3 has been adopted, and the foundation pit and earthwork excavation can be carried out If a certain prestress is applied by screwing, the excavation of the foundation pit can be excavated to the design elevation at one time, and it is not necessary to do oblique support after partial excavation, and then carry out large-scale earthwork excavation;

6)基础底板2施工:待基坑开挖完成,进行基础底板2的施工,如垫层、砖胎膜、底板防水、底板钢筋绑扎、换撑带等施工;在施工基础底板2时,将止水套管4置于基础底板2中、并采用钢筋焊接固定牢靠,在基础底板2浇筑混凝土时直接将止水套管4整体浇筑进基础底板2内;浇筑过程中需采取措施保障止水套管4内不进混凝土与水泥浆,确保后期第二螺纹桩段32能够顺利旋拧回收;6) Construction of the base plate 2: After the excavation of the foundation pit is completed, the construction of the base plate 2 is carried out, such as the construction of the cushion layer, the brick tire membrane, the waterproofing of the base plate, the binding of the steel bars of the base plate, and the replacement of the support belt; when constructing the foundation plate 2, the The water-stop sleeve 4 is placed in the foundation base plate 2 and is firmly welded by steel bars. When the concrete is poured into the foundation base plate 2, the water-stop sleeve 4 is directly poured into the foundation base plate 2 as a whole; measures shall be taken to ensure water-stopping during the pouring process No concrete and cement slurry are introduced into the casing 4 to ensure that the second threaded pile section 32 can be smoothly screwed and recovered in the later stage;

7)拆除螺纹桩:待基础底板2施工完毕并且达到围护设计要求的支撑拆除条件后,先间隔拧松锚固装置13,随即进行基坑变形监测,如果数据稳定则可将螺纹桩3逐个进行拆除回收,如果数据不稳定则需采用其他加固措施以保障基坑安全;拆除时,逐个进行拆除回收,每个螺纹桩先卸下第一螺纹桩段31,清理止水套管4后将第二螺纹桩段32旋拧回收;在螺纹桩3回收后,采用高标号微膨胀混凝土封闭桩孔,并做好养护工作;7) Removal of threaded piles: After the construction of the base plate 2 is completed and the support removal conditions required by the enclosure design are met, the anchoring devices 13 are loosened at intervals, and then the deformation monitoring of the foundation pit is carried out. If the data is stable, the threaded piles 3 can be carried out one by one. Demolition and recycling, if the data is unstable, other reinforcement measures shall be taken to ensure the safety of the foundation pit; when demolishing, demolition and recycling shall be carried out one by one, and the first threaded pile section 31 of each threaded pile shall be removed first, and the first threaded pile section 31 shall be removed after cleaning the water stop casing 4. The second threaded pile section 32 is screwed and recovered; after the threaded pile 3 is recovered, the pile hole is closed with high-grade micro-expanded concrete, and the maintenance work is done well;

在步骤5)和6)中,如果基坑变形较大,已超出围护设计及规范要求的数值时,可采用对锚固装置13进一步旋拧拧紧的方式控制基坑变形,此后基坑变形得到控制则无需采取加固措施,如果基坑变形未得到控制则需采取加固方式。In steps 5) and 6), if the deformation of the foundation pit is large and exceeds the value required by the enclosure design and specification, the deformation of the foundation pit can be controlled by further screwing and tightening the anchoring device 13, and then the deformation of the foundation pit is obtained. If the deformation of the foundation pit is not controlled, reinforcement measures are not required.

本发明的斜向支撑螺纹桩结构,具备可回收性、可提供高支撑力、可根据基坑变形情况进行加固调节斜向支撑桩结构,解决了常规基坑支护工艺繁琐、造价高昂、资源浪费等情况,保证了基坑施工的安全性、经济性和环保性。在斜向支撑完成并加压支撑力检测完成后,基坑可一次性开挖完成,机械开挖操作空间大;基坑底板施工时,由于埋设有止水内螺纹套管,可与斜向支撑桩交叉部位一体施工,利用套管外部止水钢板内部凹凸螺纹的构造可有效解决该交叉部位后期渗漏水的问题。斜向支撑体系拆除时可边卸载边监测,有效解决了支撑拆除而产生的应力释放不均或瞬时卸载的问题。The oblique support threaded pile structure of the present invention has recyclability, can provide high support force, and can be reinforced and adjusted according to the deformation of the foundation pit. Waste and other situations ensure the safety, economy and environmental protection of foundation pit construction. After the oblique support is completed and the pressure support force test is completed, the foundation pit can be excavated at one time, and the mechanical excavation operation space is large. The cross section of the support pile is constructed in one piece, and the internal concave-convex thread structure of the water-stop steel plate outside the casing can effectively solve the problem of water leakage in the cross section in the later stage. When the oblique support system is dismantled, it can be monitored while unloading, which effectively solves the problem of uneven stress release or instantaneous unloading caused by the dismantling of the support.

Claims (10)

1.一种用于基坑围护的斜向支撑螺纹桩支护结构,包括支护桩(1)、位于土层下方的基础底板(2)和多个螺纹桩(3),每个螺纹桩(3)的上端与支护桩(1)的上端连接,每个螺纹桩(3)穿过基础底板(2)而至少部分进入基础底板(2)下方的撑力土层,所述螺纹桩(3)由上至下逐渐相向倾斜,其特征在于:所述基础底板(2)内、在被螺纹桩(3)贯穿处设置有止水套管(4),所述止水套管(4)设置在螺纹桩(3)外周、并且与螺纹桩(3)可拆卸连接。1. An obliquely supported threaded pile support structure for foundation pit enclosure, comprising a support pile (1), a foundation bottom plate (2) located below the soil layer, and a plurality of threaded piles (3), each threaded The upper end of the pile (3) is connected with the upper end of the supporting pile (1), and each threaded pile (3) passes through the foundation bottom plate (2) and at least partially enters the supporting soil layer below the foundation bottom plate (2). The piles (3) are gradually inclined toward each other from top to bottom, and it is characterized in that a water-stop casing (4) is arranged in the foundation bottom plate (2) at the place where the threaded pile (3) penetrates, and the water-stop casing (4) It is arranged on the outer periphery of the threaded pile (3) and is detachably connected to the threaded pile (3). 2.根据权利要求1所述的用于基坑围护的斜向支撑螺纹桩支护结构,其特征在于:所述止水套管(4)内侧设置有内螺纹,从而与螺纹桩(3)螺纹连接。2. The oblique support threaded pile support structure for foundation pit enclosure according to claim 1, characterized in that: the inner side of the water stop casing (4) is provided with an internal thread, so as to be connected with the threaded pile (3). ) threaded connection. 3.根据权利要求2所述的用于基坑围护的斜向支撑螺纹桩支护结构,其特征在于:所述止水套管(4)的壁厚≥2.0mm。3. The oblique support threaded pile support structure for foundation pit enclosure according to claim 2, characterized in that: the wall thickness of the water stop casing (4) is ≥2.0 mm. 4.根据权利要求1所述的用于基坑围护的斜向支撑螺纹桩支护结构,其特征在于:所述支护桩(1)的上端设置有冠梁(11),所述冠梁(11)和螺纹桩(3)之间通过能调节的锚固装置(13)连接。4. The obliquely supported threaded pile support structure for foundation pit enclosure according to claim 1, wherein the upper end of the support pile (1) is provided with a crown beam (11), and the crown beam (11) is provided on the upper end of the support pile (1). The beam (11) and the threaded pile (3) are connected by an adjustable anchoring device (13). 5.根据权利要求4所述的用于基坑围护的斜向支撑螺纹桩支护结构,其特征在于:沿所述冠梁(11)的方向间隔设置有与螺纹桩(3)连接的牛腿(14),所述冠梁(11)上开设有供螺纹桩(3)的端部进入的孔或开口槽(12)。5. The oblique support threaded pile support structure for foundation pit enclosure according to claim 4, characterized in that: along the direction of the crown beam (11), there are spaced threaded piles (3) connected to each other. A corbel (14), the crown beam (11) is provided with a hole or an open groove (12) for the end of the threaded pile (3) to enter. 6.根据权利要求1所述的用于基坑围护的斜向支撑螺纹桩支护结构,其特征在于:每个螺纹桩(3)包括互相连接的第一螺纹桩段(31)和第二螺纹桩段(32),第一螺纹桩段(31)位于第二螺纹桩段(32)上方,所述第二螺纹桩段(32)穿过基础底板(2)而拧入土层中,所述第二螺纹桩段(32)与止水套管(4)连接、并且通过螺叶与土层机械咬合,所述第二螺纹桩段(32)的螺叶的宽度≥120mm。6. The obliquely braced threaded pile support structure for foundation pit enclosure according to claim 1, wherein each threaded pile (3) comprises a first threaded pile section (31) and a first threaded pile section (31) that are connected to each other. Two threaded pile sections (32), the first threaded pile section (31) is located above the second threaded pile section (32), and the second threaded pile section (32) passes through the foundation bottom plate (2) and is screwed into the soil layer, The second threaded pile section (32) is connected to the water-stop casing (4), and mechanically engaged with the soil layer through the screw blade, and the width of the screw blade of the second threaded pile section (32) is ≥120 mm. 7.一种如权利要求1~6中任一项所述的斜向支撑螺纹桩支护结构的施工方法,包括如下步骤:7. A construction method for the obliquely bracing threaded pile support structure according to any one of claims 1 to 6, comprising the steps of: 1)支护桩(1)施工:在基坑周围施工支护桩(1),在支护桩(1)的上端部浇筑用于与螺纹桩(3)连接的冠梁(11);1) Construction of supporting piles (1): The supporting piles (1) are constructed around the foundation pit, and the crown beams (11) for connecting with the threaded piles (3) are poured at the upper end of the supporting piles (1); 2)安装螺纹桩(3):将第一螺纹桩段(31)和第二螺纹桩段(32)互相连接成一整体的螺纹桩(3),将螺纹桩(3)呈一定角度旋拧植入土层中,直到达到设计要求的基础底板(2)以下一定深度;2) Install the threaded pile (3): connect the first threaded pile section (31) and the second threaded pile section (32) to form an integral threaded pile (3), and screw the threaded pile (3) at a certain angle. into the soil layer until it reaches a certain depth below the base plate (2) required by the design; 3)检测承载力:抽取若干数量的螺纹桩(3)进行斜向受压承载力检测,同时确定螺纹桩(3)的支撑富余量;3) Testing the bearing capacity: extract a number of threaded piles (3) for oblique compressive bearing capacity testing, and at the same time determine the supporting margin of the threaded piles (3); 4)对螺纹桩(3)锚固:对螺纹桩(3)的锚固位置进行处理,并套入锚固装置(13),待冠梁(11)混凝土强度达到一定程度后,沿着基坑通过锚固装置(13)对螺纹桩(3)间隔均匀地与冠梁(11)拧紧锚固,由此使得支护桩(1)和螺纹桩(3)形成为具有相互作用力的整体结构;4) Anchoring the threaded pile (3): The anchoring position of the threaded pile (3) is processed, and the anchoring device (13) is inserted. After the concrete strength of the crown beam (11) reaches a certain level, the anchoring is carried out along the foundation pit. The device (13) tightens and anchors the threaded piles (3) with the crown beams (11) evenly at intervals, thereby making the retaining piles (1) and the threaded piles (3) form an integral structure with an interaction force; 5)开挖基坑:待冠梁(11)达到一定强度后,进行基坑土方开挖;5) Excavation of the foundation pit: After the crown beam (11) reaches a certain strength, the foundation pit excavation is carried out; 6)基础底板(2)施工:待基坑开挖完成,进行基础底板(2)的施工,在施工基础底板(2)时,将止水套管(4)置于基础底板(2)中、并固定;6) Construction of the foundation floor (2): After the excavation of the foundation pit is completed, the construction of the foundation floor (2) is carried out. When the foundation floor (2) is constructed, the water stop sleeve (4) is placed in the foundation floor (2). , and fixed; 7)拆除螺纹桩(3):待基础底板(2)施工完毕并且达到围护设计要求的支撑拆除条件后,先间隔拧松锚固装置(13),随即进行基坑变形监测,如果数据稳定则将螺纹桩(3)拆除回收,如果数据不稳定则对基坑采用加固措施以保障基坑安全。7) Removal of threaded piles (3): After the construction of the foundation bottom plate (2) is completed and the support removal conditions required by the enclosure design are met, first loosen the anchoring device (13) at intervals, and then monitor the deformation of the foundation pit. Remove the threaded pile (3) for recycling, and if the data is unstable, take reinforcement measures for the foundation pit to ensure the safety of the foundation pit. 8.根据权利要求7所述的斜向支撑螺纹桩支护结构的施工方法,其特征在于:在步骤5)和6)中,如果基坑变形超出围护设计及规范要求的数值时,采用对锚固装置(13)进一步旋拧拧紧的方式控制基坑变形,此后基坑变形得到控制则无需采取加固措施,如果基坑变形未得到控制则需采取加固措施。8. the construction method of the obliquely braced threaded pile supporting structure according to claim 7, is characterized in that: in step 5) and 6), if the foundation pit deformation exceeds the numerical value of enclosure design and specification requirements, adopt The anchoring device (13) is further screwed and tightened to control the deformation of the foundation pit. After that, the deformation of the foundation pit is controlled and no reinforcement measures are required. If the deformation of the foundation pit is not controlled, reinforcement measures are required. 9.根据权利要求7所述的斜向支撑螺纹桩支护结构的施工方法,其特征在于:在步骤7)中,在拆除螺纹桩(3)时,逐个进行拆除回收,每个螺纹桩(3)卸下第一螺纹桩段(31),清理止水套管(4)后将第二螺纹桩段(32)旋拧回收。9. The construction method of the obliquely braced threaded pile supporting structure according to claim 7, characterized in that: in step 7), when removing the threaded pile (3), dismantling and recycling is carried out one by one, and each threaded pile (3). 3) Remove the first threaded pile section (31), clean the water stop casing (4), and then screw and recover the second threaded pile section (32). 10.根据权利要求9所述的斜向支撑螺纹桩支护结构的施工方法,其特征在于:在止水套管(4)内壁设有与螺纹桩(3)的螺叶匹配的螺板,在螺纹桩(3)回收后通过混凝土封闭止水套管(4)内部。10. The construction method of the obliquely supported threaded pile support structure according to claim 9, characterized in that: a screw plate matching the screw blade of the threaded pile (3) is provided on the inner wall of the water stop casing (4), After the threaded pile (3) is recovered, the inside of the water stop casing (4) is sealed by concrete.
CN202010294474.7A 2020-04-15 2020-04-15 Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof Pending CN111364479A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010294474.7A CN111364479A (en) 2020-04-15 2020-04-15 Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010294474.7A CN111364479A (en) 2020-04-15 2020-04-15 Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof

Publications (1)

Publication Number Publication Date
CN111364479A true CN111364479A (en) 2020-07-03

Family

ID=71203286

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010294474.7A Pending CN111364479A (en) 2020-04-15 2020-04-15 Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof

Country Status (1)

Country Link
CN (1) CN111364479A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114438999A (en) * 2022-03-01 2022-05-06 江苏建院营造股份有限公司 Intelligent composite supporting method and system for deep foundation pit with strong support
CN114482016A (en) * 2022-03-11 2022-05-13 中国十九冶集团有限公司 Threaded steel pipe pile and deep foundation pit construction method
CN116427424A (en) * 2023-04-10 2023-07-14 上海申元岩土工程有限公司 A foundation pit oblique cast support system and construction method without staged pouring of the floor

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101406217B1 (en) * 2013-05-21 2014-06-12 고강이앤씨(주) Building foundation slab and pile jointing device and construction method for preventing building subsidence
CN103882869A (en) * 2014-03-21 2014-06-25 郭永 Inclined supporting pile structure for foundation pit support and construction method thereof
CN207032875U (en) * 2017-05-22 2018-02-23 青岛瑞源工程集团有限公司 A kind of sealing up screw that can be recycled
CN110792095A (en) * 2019-11-11 2020-02-14 山东建筑大学 Multi-pile bearing platform-spiral anchor composite foundation
CN110857559A (en) * 2018-08-24 2020-03-03 宁波地铁产业工程有限公司 Reinforcing device for foundation
CN210152260U (en) * 2019-06-06 2020-03-17 四川省第一建筑工程有限公司 Novel pre-buried stagnant water sleeve of structure
CN212452659U (en) * 2020-04-15 2021-02-02 宁波市锟磊建设有限公司 A diagonal bracing screw thread pile supporting construction for foundation ditch enclosure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101406217B1 (en) * 2013-05-21 2014-06-12 고강이앤씨(주) Building foundation slab and pile jointing device and construction method for preventing building subsidence
CN103882869A (en) * 2014-03-21 2014-06-25 郭永 Inclined supporting pile structure for foundation pit support and construction method thereof
CN207032875U (en) * 2017-05-22 2018-02-23 青岛瑞源工程集团有限公司 A kind of sealing up screw that can be recycled
CN110857559A (en) * 2018-08-24 2020-03-03 宁波地铁产业工程有限公司 Reinforcing device for foundation
CN210152260U (en) * 2019-06-06 2020-03-17 四川省第一建筑工程有限公司 Novel pre-buried stagnant water sleeve of structure
CN110792095A (en) * 2019-11-11 2020-02-14 山东建筑大学 Multi-pile bearing platform-spiral anchor composite foundation
CN212452659U (en) * 2020-04-15 2021-02-02 宁波市锟磊建设有限公司 A diagonal bracing screw thread pile supporting construction for foundation ditch enclosure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
闫富有: "地下工程施工(第2版)", vol. 2, 30 June 2018, 黄河水利出版社, pages: 20 - 24 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114438999A (en) * 2022-03-01 2022-05-06 江苏建院营造股份有限公司 Intelligent composite supporting method and system for deep foundation pit with strong support
CN114482016A (en) * 2022-03-11 2022-05-13 中国十九冶集团有限公司 Threaded steel pipe pile and deep foundation pit construction method
CN116427424A (en) * 2023-04-10 2023-07-14 上海申元岩土工程有限公司 A foundation pit oblique cast support system and construction method without staged pouring of the floor

Similar Documents

Publication Publication Date Title
CN101634149B (en) Prestressed anchor foundation pit support and construction method
CN111364479A (en) Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof
CN101250886B (en) Method for reinforcing masonry structure building base
CN104763454A (en) Built-in type full-length anticorrosion anchor rod
CN204753570U (en) High pile platform bored concrete pile construction equipment of formula is maked somebody a mere figurehead to storage tank
CN114737559A (en) Multidirectional-load-resistant small precast pile foundation and construction method
CN212452659U (en) A diagonal bracing screw thread pile supporting construction for foundation ditch enclosure
CN212224604U (en) Wall connecting assembly for connecting outer wall scaffold and wall structure
CN204266572U (en) Scaffold wall connecting piece
CN211773604U (en) Pile sealing device for water gushing pile position hole on anchor rod static pressure pile
CN217536992U (en) Grouting inclined strut enclosure structure capable of being repeatedly used in engineering
CN214741347U (en) Be used for hydraulic shield to construct building structure and strengthen fixing device
CN214464212U (en) A tunnel temporary support structure
CN110258514A (en) A kind of steel of diaphram wall leads wall and its construction method
CN109958460A (en) A kind of multifunctional anchoring waterproof structure and its anchoring method
CN212200511U (en) Deep foundation pit plugging device
CN209924089U (en) A well device of riding on horse for pipeline construction
CN113638598A (en) Anti-radiation concrete opposite-pulling bolt with reserved labyrinth-type holes and construction method
CN220394584U (en) Temporary side slope reinforcement system in grading excavation process
CN208219670U (en) A kind of support system of deep basal pit
CN222500362U (en) Basement outer wall screw thread enlarges body steel pile sealing device
CN219280717U (en) Novel pull-press combined type detachable spiral drill pipe diagonal bracing structure
CN222350208U (en) Outer scaffold wall connecting system suitable for have PCF board outer wall structure
CN221276619U (en) Foundation pit supporting structure and building foundation pit
CN222295008U (en) Leakage plugging and repairing device for construction of river-like deep foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination