CN111335649B - Hoisting method of building dome structure - Google Patents

Hoisting method of building dome structure Download PDF

Info

Publication number
CN111335649B
CN111335649B CN202010247672.8A CN202010247672A CN111335649B CN 111335649 B CN111335649 B CN 111335649B CN 202010247672 A CN202010247672 A CN 202010247672A CN 111335649 B CN111335649 B CN 111335649B
Authority
CN
China
Prior art keywords
ring beam
hoisting
building
dome structure
top frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010247672.8A
Other languages
Chinese (zh)
Other versions
CN111335649A (en
Inventor
王冬平
舒真理
祁迹
王玉麒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN202010247672.8A priority Critical patent/CN111335649B/en
Publication of CN111335649A publication Critical patent/CN111335649A/en
Application granted granted Critical
Publication of CN111335649B publication Critical patent/CN111335649B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/08Vaulted roofs

Abstract

A hoisting method of a building dome structure comprises the steps of pouring a hoisting support platform and an anchoring platform in a building, then building a ring beam support tower on the hoisting support platform, anchoring the ring beam support tower through a steel cable, an anchoring piece and the anchoring platform, building a ring beam support at the top of the ring beam support tower, hoisting ring beam sections by a crane in multiple times, bearing each ring beam section through the ring beam support, and splicing the ring beam supports into a ring beam; the top frame pieces are simultaneously and symmetrically hoisted through two cranes in a split manner, one end of each top frame piece is lapped on the ring beam, the other end of each top frame piece is connected with the building wall/frame body, and the top frame pieces are connected through the members among the top frames to form an integral top frame and are connected with the ring beam to form a dome structure; and then all the auxiliary devices are dismantled, and the hoisting of the building dome structure can be completed. The invention can efficiently, safely and economically finish the hoisting of the building, in particular to the large building dome structure under the condition of lacking the equipment for hoisting the dome structure at one time.

Description

Hoisting method of building dome structure
Technical Field
The invention relates to a building construction method, in particular to a hoisting method of a building dome structure, and belongs to the technical field of building construction production.
Background
The hoisting of the building dome structure is an important part in the building engineering, and is also one of the parts with higher difficulty and requirements in the building construction process, and is directly related to the progress of the engineering, the quality of the building and the construction cost.
In recent years, as large buildings are built more and larger, building dome structures are more and more complex, and the hoisting difficulty is higher and more, on the contrary, the construction period is shorter and higher, and the quality requirement is higher and higher, in particular, the mechanical equipment and the construction conditions and the construction period required by building construction never meet the imagination of designers and requirements of owners, so that the hoisting of the building dome structures is always a major problem for builders.
For example, with the increase of environmental requirements, small cement plants are eliminated, while the devices and equipment of large cement plants are usually large, the matched buildings are also large, and production and transportation equipment is usually required to be installed inside and on the top of the buildings, the dome structure is very complex, and therefore, the difficulty in hoisting the dome structure becomes very difficult.
Some huge cement manufacturing enterprises producing ten thousand tons per day need to be matched with and build a plurality of hundred thousand-ton-level clinker warehouses, the clinker warehouses are very huge, the height of an outer wall of each clinker warehouse from the bottom to the top reaches 40m, a dome adopts an all-steel truss structure, the all-steel truss structure consists of an upper ring beam and a lower top frame and is an inverted bowl-shaped structure, the overall weight of the dome structure exceeds 300 tons, the diameter reaches 50m, and the height reaches 17 m.
In the prior similar building with similar shape and smaller volume, a dome structure is generally constructed by adopting a method of ground assembly and integral hoisting by using a crane, but the weight of the dome structure of a hundred thousand-ton-level clinker silo is 300 tons, so that the dome structure with the weight is hoisted by using a 1200-ton crawler crane, the renting cost of the large crane is extremely high, and the time required for early preparation and reservation is extremely long, so that the traditional hoisting scheme does not accord with the principles of high efficiency, safety and economy.
Of course, there are many hoisting methods worth referring to in the prior art, such as:
the invention discloses a hoisting method of prefabricated parts of an assembly type building (application number 201510171091.X) which utilizes a three-dimensional laser scanning technology to ensure the high precision of construction and shorten the working time, and an operator works according to tower crane parameters to avoid the defects of commanding by people and the defects of repeated hoisting;
the invention discloses a lifting method of a top ring in dome structure installation (application number 201210221120.5), which comprises the steps of correctly selecting a proper crane and a proper lifting appliance, lifting and arranging a temporary steel bracket of the top ring, arranging a steel wire rope on the temporary steel bracket to serve as a wind-holding rope for stabilizing the temporary steel bracket before the top ring is in place, configuring a 2t inverted chain as a tensioning device for each wind-holding rope, and determining the type and the model of the crane according to the weight, the maximum diameter, the height of a body and the installation height of the top ring;
the invention discloses a hoisting method of a large-span asymmetric rectangular space twisted pipe truss (application number 201210460439.3). the method can place the asymmetric rectangular space twisted pipe truss in one step when being installed at high altitude, and ensures that the whole installation work is simple and practical, the construction period can be greatly shortened, and the construction cost is reduced;
the invention discloses a special lifting appliance and a lifting method for a steel containment vessel head of a nuclear island of a nuclear power station, which are disclosed by the patent application number 201210177992.6, and can ensure that the deformation of the head in the lifting process is reduced to the minimum, thereby meeting the lifting requirements of large components and equipment of the nuclear power station;
the invention discloses a roof truss hoisting method disclosed in the patent application (application number 201910693610.7), which effectively solves the problems that a construction area is limited, large-scale hoisting equipment cannot be used, an operation field is narrow, and conventional hoisting operation is difficult by reasonably planning a limited operation space and scientifically formulating a hoisting process.
In spite of the above prior art, the problems encountered in the prior art can be solved, but no construction scheme is provided for efficiently, safely and inexpensively completing the hoisting of a building, particularly a large building dome structure under the difficult conditions of no large hoisting equipment, short construction period, complex dome structure and the like, and no clear and direct suggestion is provided.
Disclosure of Invention
Aiming at the defects of the prior art, the embodiment of the invention provides a hoisting method of a building dome structure, which aims to: under the condition that equipment capable of hoisting the dome structure at one time is lacked, the hoisting of the dome structure of the building, particularly a large building, is efficiently, safely and economically completed, the construction period is shortened, the construction cost is reduced and the economic benefit is improved on the premise of ensuring safety.
In order to achieve the above purpose, the embodiments of the present invention provide the following technical solutions:
a method for hoisting a building dome structure, wherein the building comprises a wall body/frame body surrounded on the periphery, an anchoring part capable of fixing a traction reinforcing steel cable is arranged on the wall body/frame body, a field capable of arranging a hoisting support platform and an anchoring platform is arranged in the building, a crane capable of hoisting the dome structure component in a segmented/piece mode is arranged outside the building, the dome structure comprises a top frame of a truss structure and a ring beam connected to the upper portion of the top frame, and the top frame and the ring beam form an inverted bowl-shaped structure body, and the method is characterized by comprising the following steps:
s1) pouring the hoisting support platform and the anchoring table in the building;
s2) a ring beam supporting tower is built on the hoisting supporting platform, and the ring beam supporting tower is anchored through a steel cable, an anchoring piece and an anchoring table;
s3) building a ring beam bracket on the top of the ring beam supporting tower;
s4) manufacturing ring beam sections on the ground in sections, hoisting the ring beam sections by the crane in a plurality of times, respectively bearing each ring beam section through the ring beam support, and then splicing each ring beam section on the ring beam support to form the ring beam integrally;
s5) manufacturing fan-shaped roof pieces on the ground in a piece dividing manner, simultaneously and symmetrically hoisting each roof piece through two cranes in a piece dividing manner, overlapping one end of each roof piece on the ring beam, and connecting the other end of each roof piece with the wall/frame body;
s6) connecting the top frame pieces into a whole by an inter-top frame member to form the top frame, and connecting the upper part of the top frame with the ring beam to form the dome structure;
s7) connection detection of each connection point of the dome structure is completed, and unloading of each support point of the ring beam support to the dome structure support is completed after each connection point is detected to be qualified;
s8) dismantling the ring beam support, the ring beam support tower, the support platform and the anchoring table one by one, and completing the hoisting of the building dome structure.
Furthermore, steel structure supporting embedded parts are arranged in the hoisting supporting platform and the anchoring platform, the steel structure supporting embedded parts are embedded in a mold before concrete pouring of the hoisting supporting platform and the anchoring platform, and the steel structure supporting embedded parts are used for being connected with the steel structural part of the ring beam supporting tower and anchoring the reinforcing steel cable.
Furthermore, the anchoring table is arranged around the hoisting support platform.
As an optional technical scheme:
and the reinforced steel cable is tensioned through a hoist after being connected with the ring beam supporting tower and the anchoring piece or the anchoring table.
Further, the hoist has a tension of 2-5 tons.
Furthermore, the diameter of the reinforced steel cable is 16-25 mm, the middle upper part of the ring beam supporting tower is reinforced by the reinforced steel cable of 16mm, and the middle lower part of the ring beam supporting tower is reinforced by the reinforced steel cable of 25 mm.
As an optional technical scheme, the ring beam supporting tower is built by adopting a tower crane standard knot.
Furthermore, the ring beam support is a groined-shaped structure frame, a square structure in the groined-shaped structure frame is connected to the ring beam supporting tower, and a protruding part in the groined-shaped structure frame is used for bearing the ring beam section.
As an optional technical scheme, the ring beam support is built by channel steel or I-steel.
As an optional technical scheme:
the ring beam is divided into four equal sections to be manufactured, the top frame is divided into eight equal sections to be manufactured, the two cranes can hoist the top frame piece one at a time respectively, and one crane can hoist the ring beam section one at a time.
The invention has the beneficial effects and remarkable progress that:
1) the hoisting method of the building dome structure provided by the embodiment of the invention comprises the steps of pouring a hoisting support platform and an anchoring table in a building, then building a ring beam support tower on the hoisting support platform, anchoring the ring beam support tower through a steel cable, an anchoring piece and the anchoring table, building a ring beam support at the top of the ring beam support tower, hoisting ring beam sections by times through a crane, carrying the ring beam sections through the ring beam supports, and splicing the ring beam supports to form a ring beam; the top frame pieces are symmetrically hoisted simultaneously by two cranes in a split manner, one end of each top frame piece is connected to the ring beam, the other end of each top frame piece is connected with the building wall/frame body, the top frame pieces are connected through the components among the top frames to form an integral top frame, the integral top frame is connected with the ring beam to form a dome structure, and then all auxiliary devices are dismantled, so that the building dome structure can be hoisted;
2) the hoisting method of the building dome structure provided by the embodiment of the invention is novel and unique, is simple and quick to construct, can complete the hoisting construction of the large building dome structure by only lapping one ring beam supporting tower, ring beam bracket and other auxiliary devices, namely two light hoisting machines which only have hoisting top frame pieces and one of which can hoist the ring beam section, is low in time consumption and can be controlled by the light hoisting machines, mechanical equipment such as a large crane and the like is not required to be rented, a large amount of construction cost can be saved, the hoisting process is safe and reliable, the high-efficiency, safe and economic benefit principle is met, the construction period can be shortened, the construction cost can be reduced, and the economic benefit can be improved on the premise of ensuring safety;
3) the hoisting method of the building dome structure provided by the embodiment of the invention is simple and practical, has high efficiency and strong operability and adaptability, can meet the hoisting requirements of various building dome structures, and has demonstration significance and heuristic significance, so that the hoisting method has popularization and application values.
Drawings
To more clearly illustrate the technical solution of the present invention, the drawings required for the embodiment of the present invention will be briefly described below.
It should be apparent that the drawings in the following description are only drawings of some embodiments of the invention, and that other drawings can be obtained by those skilled in the art without inventive exercise, and the other drawings also belong to the drawings required by the embodiments of the invention.
Fig. 1 is a schematic configuration diagram of a construction site and construction equipment of a hoisting method for a building dome structure according to an embodiment of the present invention;
FIG. 2 is a schematic block diagram of a construction process of a method for hoisting a building dome structure according to an embodiment of the present invention;
fig. 3 is a schematic distribution diagram of a hoisting support platform and an anchoring platform of the hoisting method for the building dome structure according to the embodiment of the present invention;
fig. 4 is a schematic structural diagram of a ring beam support of a method for hoisting a building dome structure according to an embodiment of the present invention;
fig. 5 is a schematic view of a ring beam hoisting sequence of a hoisting method for a building dome structure according to an embodiment of the present invention;
fig. 6 is a schematic view of a hoisting sequence of a top frame of a hoisting method for a building dome structure according to an embodiment of the present invention.
In the figure:
100-building, 110-wall/frame, 111-anchor;
120-top frame, 120 ' -top frame sheet, 120 "-corresponding top frame sheet, 121 ' -first top frame sheet, 121" -first corresponding top frame sheet, 122 ' -second top frame sheet, 122 "-second corresponding top frame sheet, 123 ' -third top frame sheet, 123" -third corresponding top frame sheet, 124 ' -fourth top frame sheet, 124 "-fourth corresponding top frame sheet;
130-ring beam, 130 ' -ring beam section, 131 ' -first ring beam section, 132 ' -second ring beam section, 133 ' -third ring beam section, 134 ' -fourth ring beam section;
210-hoisting a supporting platform, 220-an anchoring table, 230-a ring beam supporting tower, 240-a steel cable, 250-a ring beam bracket, 260-a steel structure supporting embedded part and 270-a hoist;
310-a first crane, 320-a second crane.
Detailed Description
In order to make the objects, technical solutions, beneficial effects and significant advances of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings provided in the embodiments of the present invention, and it is obvious that all the described embodiments are only some embodiments of the present invention, but not all embodiments; all other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that the terms "first," "second," and "again" (if present) and the like in the description and the claims of the present invention and the drawings of the embodiments of the present invention are used for distinguishing between different objects and not for describing a particular order. Furthermore, the terms "comprises" and any variations thereof, are intended to cover non-exclusive inclusions. For example, a process, method, system, article, or apparatus that comprises a list of steps or elements is not limited to only those steps or elements listed, but may alternatively include other steps or elements not listed, or inherent to such process, method, article, or apparatus.
It is to be understood that in the description of the embodiments of the present invention, the terms "upper", "lower", "top", "bottom", and other indicative orientations and positions are only used based on the orientation and position relationship shown in the drawings of the embodiments of the present invention, and are used for convenience of describing the embodiments of the present invention and simplifying the description, but do not indicate or imply that the device or element in question must have a specific orientation, a specific orientation configuration and operation, and therefore, should not be taken as limiting the present invention.
In the present invention, unless otherwise specifically stated or limited, the terms "mounted," "connected," "fixed," and the like are to be understood broadly, and for example, may be fixedly connected, detachably connected, movably connected, or integrated; they may be directly connected or indirectly connected through intervening media, or they may be interconnected or otherwise interacting with the two elements unless expressly stated otherwise. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
It should be further noted that the following embodiments may be combined with each other, and the same or similar concepts or processes may not be repeated in some embodiments.
Examples
Fig. 1 shows a schematic configuration diagram of a construction site and construction equipment of a hoisting method for a building dome structure according to an embodiment of the present invention:
the method for hoisting the building dome structure provided by the embodiment comprises the steps that a building 100 comprises a wall body/frame body 110 which is surrounded on the periphery, an anchoring piece 111 capable of fixing a traction reinforcing steel cable is arranged on the wall body/frame body 110, a field capable of arranging a hoisting supporting platform 210 and an anchoring platform 220 is arranged in the building 100, a first crane 310 and a second crane 320 capable of hoisting dome structure components in a segmented/piece mode are arranged outside the building 100, the dome structure comprises a top frame 120 of a truss structure and a ring beam 130 connected to the upper portion of the top frame 120, and the top frame 120 and the ring beam 130 form an inverted bowl-shaped structure body.
With reference to fig. 1 and fig. 2, a schematic block diagram of a construction process of a hoisting method for a building dome structure according to an embodiment of the present invention is shown:
the hoisting method of the building dome structure provided by the embodiment comprises the following steps:
s1) pouring the hoisting support platform 210 and the anchoring table 220 in the building 100;
s2) building a ring beam support tower 230 on the hoisting support platform 210, and anchoring the ring beam support tower 230 through a steel cable 240, an anchor 111 and an anchor table 220;
s3) building a ring beam bracket 250 on top of the ring beam support tower 230;
s4) manufacturing ring beam sections 130 'on the ground in sections, hoisting the ring beam sections 130' by a first crane 310 in sections, respectively bearing each ring beam section 130 'through a ring beam support 240, and then splicing each ring beam section 130' on a ring beam support 250 to form a ring beam 130;
s5) manufacturing fan-shaped top frame pieces 120 ' on the ground in a piece dividing manner, symmetrically hoisting each top frame piece 120 ' and the corresponding top frame piece 120 ' by a first crane 310 and a second crane 320 in a piece dividing manner, overlapping one end of each top frame piece 120 ' and the corresponding top frame piece 120 ' on the ring beam 130, and connecting the other end of each top frame piece 120 ' and the corresponding top frame piece 120 ' with the wall/frame body 110;
s6) connecting each roof piece 120' and the corresponding roof piece 120 ″ by an inter-roof member to be an integral body to constitute the roof 120, and connecting the upper portion of the roof 120 and the ring beam 130 to constitute a dome structure;
s7) connection detection of each connection point of the dome structure is completed, and unloading of each support point of the ring beam support 250 to the support of the dome structure is completed after each connection point is detected to be qualified;
s8) the ring beam supports 250, the ring beam support towers 230, the support platforms 210 and the anchoring platforms 220 are dismantled one by one, namely, the hoisting of the building dome structure is completed.
From the above description, it can be seen that:
according to the hoisting method of the building dome structure provided by the embodiment, a hoisting support platform and an anchoring table are poured in a building, then a ring beam support tower is built on the hoisting support platform and is anchored by a steel cable, an anchoring piece and the anchoring table, a ring beam support is built at the top of the ring beam support tower, ring beam sections are hoisted by a crane in multiple times, the ring beam supports are used for bearing the ring beam sections, and then the ring beam supports are spliced to form ring beams; the method comprises the steps that the two cranes are used for slicing and simultaneously and symmetrically hoisting the top frame pieces, one ends of the top frame pieces are connected to the ring beam, the other ends of the top frame pieces are connected with the building wall/frame, the top frame pieces are connected through the members among the top frames to form an integral top frame, the integral top frame is connected with the ring beam to form a dome structure, and then all auxiliary devices are dismantled, so that the hoisting of the dome structure of the building, particularly a large building, can be efficiently, safely and economically completed under the condition that equipment capable of hoisting the dome structure at one time is lacked;
the hoisting method for the building dome structure provided by the embodiment is novel, unique, simple and quick in construction, only one ring beam supporting tower, a ring beam support and other auxiliary devices are required to be built in the whole construction process, the hoisting construction of the large building dome structure can be completed by two light hoisting machines which only have hoisting top frame pieces and one of which can hoist the ring beam section, the time is short, the hoisting construction can be controlled by the light hoisting machines, and mechanical equipment such as a large crane is not required to be rented, so that a large amount of construction cost can be saved, the hoisting process is safe and reliable, the high-efficiency, safe and economic benefit principle is met, the construction period can be shortened, the construction cost can be reduced, and the economic benefit can be improved on the premise of ensuring safety;
obviously, the hoisting method of the building dome structure provided by the embodiment is simple and practical, high in efficiency, high in operability and adaptability, capable of meeting hoisting requirements of various building dome structures, and very significant in demonstration and revelation, and therefore has popularization and application values.
In order to guarantee that the ring beam supporting tower can be smoothly and safely built on the hoisting supporting platform and guarantee that the anchoring platform can better exert the anchoring effect, further, the following steps can be seen in fig. 1:
steel structure supporting embedded parts 260 are arranged in the hoisting supporting platform 210 and the anchoring platform 220, the steel structure supporting embedded parts 260 are embedded in a mold before concrete pouring of the hoisting supporting platform 210 and the anchoring platform 220, and the steel structure supporting embedded parts 260 are used for connecting with steel structural parts of the ring beam supporting tower 230 and anchoring the reinforcing steel cables 240.
In order to fully exert the function of the anchoring table and ensure the safety of the ring beam supporting tower, further, as shown in fig. 3, the distribution schematic diagram of the hoisting supporting platform and the anchoring table of the hoisting method for the building dome structure provided by the embodiment of the invention is as follows: the anchoring table 220 is arranged around the hoisting support platform.
We can further see from fig. 1: as an alternative solution, the reinforcing steel cable 240 is connected to the ring beam support tower 230 and the anchor 111 or the anchor table 260 and then tensioned by the hoist 270.
Further, in this embodiment, the hoist 270 has a tension of 2 to 5 tons.
In this embodiment, the diameter of the reinforcing steel cable 240 is 16 to 25mm, wherein, as shown in fig. 1:
the middle upper part of the ring beam supporting tower 230 is reinforced by a 16mm reinforcing steel cable 240, and the middle lower part of the ring beam supporting tower 230 is reinforced by a 25mm reinforcing steel cable 240.
As an optional technical solution, the ring beam support tower 230 is built by using a tower crane standard section.
Adopt tower crane standard festival to build ring beam support tower 230, because building body structure etc. build the back that finishes, general tower crane is idle just not used, at this moment, utilizes tower crane standard festival to build ring beam support tower 230, can make full use of on the one hand the on-the-spot idle equipment, on the other hand can accelerate the construction progress, practice thrift construction cost, can also satisfy ring beam support tower 230's safety requirement and intensity requirement, guarantee construction safety.
Further, as shown in fig. 4, a schematic structural diagram of a ring beam support of the method for hoisting a building dome structure according to the embodiment of the present invention, and fig. 5, a schematic diagram of a ring beam hoisting sequence of the method for hoisting a building dome structure according to the embodiment of the present invention are shown:
the ring beam support 250 is a # -shaped structural frame, the square-shaped structure in the # -shaped structural frame is connected to the ring beam support tower 230, and the extension part in the # -shaped structural frame is used for bearing the ring beam section 130'.
As an optional technical solution, in this embodiment, the ring beam bracket 250 is constructed by using channel steel and/or i-steel.
As an alternative solution, in this embodiment, the ring beam 130 is divided into four equal ring beam segments 130 ', and then the ring beam segments 130 ' are hoisted by a first crane 310 in several times, as shown in fig. 5, the first ring beam segment 131 ' is hoisted to be placed on the ring beam support 250, then the second ring beam segment 132 ' is hoisted to be placed on the ring beam support 250 on the opposite side of the first ring beam segment 131 ', then the third ring beam segment 133 ' is hoisted to be placed on the ring beam support 250, finally the fourth ring beam segment 134 ' is hoisted to be placed on the ring beam support 250 on the opposite side of the third ring beam segment 133 ', and then the ring beam segments 130 ' are spliced together on the ring beam support 250 to form the ring beam 130.
As an optional technical solution, in this embodiment, the top frame 120 is divided into eight equal top frame pieces 120' and corresponding top frame pieces 120 ″ to be manufactured, and then, as shown in fig. 6, a schematic diagram of a top frame hoisting sequence of the hoisting method for the building dome structure according to the embodiment of the present invention is shown:
respectively and simultaneously hoisting a first top frame piece 121 'and a first corresponding top frame piece 121 "by using a first crane 310 and a second crane 320, respectively, so that the first top frame piece 121' and the first corresponding top frame piece 121" are respectively placed at two corresponding sides of the ring beam 130, one end of each of the first top frame piece 121 'and the first corresponding top frame piece 121 "is lapped on the ring beam 130, and the other end of each of the first top frame piece 121' and the first corresponding top frame piece 121" is connected with the wall/frame body 110;
similar to the hoisting operation of the first top frame piece 121 ' and the first corresponding top frame piece 121 ", a second top frame piece 122 ' and a second corresponding top frame piece 122" are hoisted and placed on a vertical line of a connecting line of the first top frame piece 121 ' and the first corresponding top frame piece 121 ";
subsequently, a third roof piece 123 ' and a third corresponding roof piece 123 ″ are installed between the first roof piece 121 ' and the second roof piece 122 ', and between the first corresponding roof piece 121 ″ and the second corresponding roof piece 122 ″;
then, a fourth roof piece 124 ' and a fourth corresponding roof piece 124 "are installed between the first roof piece 121 ' and the second corresponding roof piece 122", and between the second roof piece 122 ' and the first corresponding roof piece 121 ";
finally, each roof piece 120' and the corresponding roof piece 120 ″ are connected by an inter-roof member (not shown) to be integrated into a roof 120, and the upper portion of the roof 120 is connected to the ring beam 130 to form a dome structure, thereby completing the lifting of the dome structure of the entire building.
In the above description:
the descriptions of the terms "this embodiment," "an embodiment of the invention," "as shown at … …," "further modified technical solution," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention;
in this specification, the schematic representations of the terms used above are not necessarily for the same embodiment or example, and the particular features, structures, materials, or characteristics described, etc., may be combined or brought together in any suitable manner in any one or more embodiments or examples;
furthermore, those of ordinary skill in the art may combine or combine features of different embodiments or examples and features of different embodiments or examples described in this specification without undue conflict.
Finally, it should be noted that:
the above embodiments are only used for illustrating the technical solution of the present invention, and not for limiting the same;
although the present invention has been described in detail with reference to the foregoing embodiments, it should be understood by those skilled in the art that various changes and modifications may be made, and equivalents may be substituted for elements thereof without departing from the scope of the embodiments of the present invention.

Claims (10)

1. A method for hoisting a building dome structure, wherein the building comprises a wall body/frame body which is surrounded on the periphery, an anchoring part which can fix a traction reinforcing steel cable is arranged on the wall body/frame body, a field which can be provided with a hoisting support platform and an anchoring platform is arranged in the building, a crane which can hoist the dome structure component in a segmented/sheet mode is arranged outside the building, the dome structure comprises a top frame of a truss structure and a ring beam which is connected with the upper part of the top frame, and the top frame and the ring beam form an inverted bowl-shaped structure body, and the method is characterized by comprising the following steps:
s1) pouring the hoisting support platform and the anchoring table in the building;
s2) a ring beam supporting tower is built on the hoisting supporting platform, and the ring beam supporting tower is anchored through a steel cable, an anchoring piece and an anchoring table;
s3) building a ring beam bracket on the top of the ring beam supporting tower;
s4) manufacturing ring beam sections on the ground in sections, hoisting the ring beam sections by the crane in a plurality of times, respectively bearing each ring beam section through the ring beam support, and then splicing each ring beam section on the ring beam support to form the ring beam integrally;
s5) manufacturing fan-shaped roof pieces on the ground in a piece dividing manner, simultaneously and symmetrically hoisting each roof piece through two cranes in a piece dividing manner, overlapping one end of each roof piece on the ring beam, and connecting the other end of each roof piece with the wall/frame body;
s6) connecting the top frame pieces into a whole by an inter-top frame member to form the top frame, and connecting the upper part of the top frame with the ring beam to form the dome structure;
s7) connection detection of each connection point of the dome structure is completed, and unloading of each support point of the ring beam support to the dome structure support is completed after each connection point is detected to be qualified;
s8) dismantling the ring beam support, the ring beam support tower, the hoisting support platform and the anchoring table one by one, and completing hoisting of the building dome structure.
2. A method of erecting a building dome structure as recited in claim 1, wherein:
the steel structure supporting and pre-embedding method is characterized in that steel structure supporting and pre-embedding parts are arranged in the hoisting supporting platform and the anchoring table, the steel structure supporting and pre-embedding parts are pre-embedded in a mold before concrete pouring of the hoisting supporting platform and the anchoring table, and the steel structure supporting and pre-embedding parts are used for being connected with a steel structural part of the ring beam supporting tower and anchoring a reinforced steel cable.
3. A method of erecting a building dome structure as recited in claim 1, wherein: the anchoring table is arranged around the hoisting support platform.
4. A method of erecting a building dome structure as recited in claim 1, wherein: and the reinforced steel cable is tensioned through a hoist after being connected with the ring beam supporting tower and the anchoring piece or the anchoring table.
5. A method of erecting a building dome structure as recited in claim 4, wherein: the hoist has a tension of 2-5 tons.
6. A method of erecting a building dome structure as recited in claim 1, wherein: the diameter of the reinforced steel cable is 16-25 mm, the upper middle part of the ring beam supporting tower is reinforced by the reinforced steel cable of 16mm, and the middle lower part of the ring beam supporting tower is reinforced by the reinforced steel cable of 25 mm.
7. A method of erecting a building dome structure as recited in claim 1, wherein: the ring beam supporting tower is built by adopting a tower crane standard knot.
8. A method of erecting a building dome structure as recited in claim 1, wherein: the ring beam support is a groined structure frame, a square structure in the groined structure frame is connected to the ring beam supporting tower, and a protruding part in the groined structure frame is used for bearing the ring beam section.
9. A method of erecting a building dome structure as recited in claim 1, wherein: the ring beam support is built by channel steel or I-steel.
10. A method of erecting a building dome structure as recited in claim 1, wherein: the ring beam is divided into four equal sections to be manufactured, the top frame is divided into eight equal sections to be manufactured, the two cranes can hoist the top frame piece one at a time respectively, and one crane can hoist the ring beam section one at a time.
CN202010247672.8A 2020-03-31 2020-03-31 Hoisting method of building dome structure Active CN111335649B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010247672.8A CN111335649B (en) 2020-03-31 2020-03-31 Hoisting method of building dome structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010247672.8A CN111335649B (en) 2020-03-31 2020-03-31 Hoisting method of building dome structure

Publications (2)

Publication Number Publication Date
CN111335649A CN111335649A (en) 2020-06-26
CN111335649B true CN111335649B (en) 2022-06-24

Family

ID=71182704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010247672.8A Active CN111335649B (en) 2020-03-31 2020-03-31 Hoisting method of building dome structure

Country Status (1)

Country Link
CN (1) CN111335649B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103061506A (en) * 2012-12-28 2013-04-24 中国华冶科工集团有限公司 Construction method of steel structure dome
CN206692235U (en) * 2017-04-11 2017-12-01 杭州建工集团有限责任公司 A kind of steel structure dome lifts by crane erecting device
CN208803740U (en) * 2018-08-13 2019-04-30 华星钢构股份有限公司 A kind of support system of dome structure
CN110230393A (en) * 2019-06-18 2019-09-13 中建三局第二建设工程有限责任公司 A kind of large-sized concrete tank dome can climb high-supported formwork support system and installation method
CN110259150A (en) * 2019-05-22 2019-09-20 山东核电设备制造有限公司 A kind of steel containment vessel of nuclear power station cover head assembling support and assembling method
CN110258803A (en) * 2019-06-21 2019-09-20 南通大学 A kind of dome steel structure construction method of installation based on BIM technology
CN110306670A (en) * 2018-05-29 2019-10-08 中国建筑第二工程局有限公司 A kind of construction method of overlength primary and secondary truss and annulus truss dome steel structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103061506A (en) * 2012-12-28 2013-04-24 中国华冶科工集团有限公司 Construction method of steel structure dome
CN206692235U (en) * 2017-04-11 2017-12-01 杭州建工集团有限责任公司 A kind of steel structure dome lifts by crane erecting device
CN110306670A (en) * 2018-05-29 2019-10-08 中国建筑第二工程局有限公司 A kind of construction method of overlength primary and secondary truss and annulus truss dome steel structure
CN208803740U (en) * 2018-08-13 2019-04-30 华星钢构股份有限公司 A kind of support system of dome structure
CN110259150A (en) * 2019-05-22 2019-09-20 山东核电设备制造有限公司 A kind of steel containment vessel of nuclear power station cover head assembling support and assembling method
CN110230393A (en) * 2019-06-18 2019-09-13 中建三局第二建设工程有限责任公司 A kind of large-sized concrete tank dome can climb high-supported formwork support system and installation method
CN110258803A (en) * 2019-06-21 2019-09-20 南通大学 A kind of dome steel structure construction method of installation based on BIM technology

Also Published As

Publication number Publication date
CN111335649A (en) 2020-06-26

Similar Documents

Publication Publication Date Title
CN107697818B (en) Construction method and special construction equipment for wall of prestressed concrete wind power tower
CN109958195B (en) Construction method for reactor vessel supporting embedded part of nuclear power station
CN109184030B (en) Assembly type concrete shear wall superposed structure system and installation method
CN102337782B (en) Lift system for constructing truss platform on top of tall and large space
CN113752379A (en) Concrete T-beam prefabricating method adopting secondary tensioning process and movable pedestal
CN114575589B (en) Construction method for electric hoist lifting formwork of steel reinforced concrete structural column
CN115030046A (en) Hydraulic creeping formwork for hollow thin-wall pier and construction method thereof
CN208932821U (en) A kind of erecting beam construction height leg gantry crane
CN110847599A (en) Special-shaped column formwork filling reinforcement device and construction method thereof
CN111335649B (en) Hoisting method of building dome structure
CN111424967A (en) Construction method of high-altitude ring beam cantilever structure
CN208152583U (en) A kind of high-building construction ancillary equipment
CN112412154B (en) Ultra-high voltage transmission line construction process with floating type overwater platform as operation surface
CN212176243U (en) Cast-in-place roof does not need overhead layer structure of formwork
WO2008000054A1 (en) Autoliftable bridge crane system for building and tower construction
CN211735477U (en) A tower crane foundation structure for bridge tower construction
CN211472175U (en) Aerial working platform device suitable for steel bridge construction
CN113137102A (en) Assembled type warehouse roof structure and installation method thereof
CN111648255A (en) Variable-section cantilever formwork suitable for rapid construction and construction method adopting variable-section cantilever formwork
CN110805346A (en) Shallow round bin assembly type bin top cover and construction process thereof
US4242850A (en) Metal water tower
CN217810515U (en) T roof beam wet joint exempts from high altitude construction and turns over device of mould
CN216766964U (en) Shaped steel and two cable atress system in coordination among back taper water tank concrete placement process
CN218597854U (en) Simple and easy steel construction brickmaking machine factory building of being suitable for
CN113718654B (en) Installation structure for ropeless beam section of bridge tower area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230920

Address after: No.9, Wuye Road, Jinjiang District, Chengdu, Sichuan 610023

Patentee after: CHINA MCC5 GROUP Corp.,Ltd.

Address before: 201900 Fujin Industrial Development Zone, Baoshan District, Shanghai, 8 East Road.

Patentee before: MCC5 Group CORPORATION LIMITED (SHANGHAI)

TR01 Transfer of patent right