CN111306366A - Universal type comprehensive pipeline support mounting method - Google Patents

Universal type comprehensive pipeline support mounting method Download PDF

Info

Publication number
CN111306366A
CN111306366A CN201911144973.1A CN201911144973A CN111306366A CN 111306366 A CN111306366 A CN 111306366A CN 201911144973 A CN201911144973 A CN 201911144973A CN 111306366 A CN111306366 A CN 111306366A
Authority
CN
China
Prior art keywords
pipe
pipeline
comprehensive
layer
distance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911144973.1A
Other languages
Chinese (zh)
Inventor
秦东旭
徐瑞卿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201911144973.1A priority Critical patent/CN111306366A/en
Publication of CN111306366A publication Critical patent/CN111306366A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
    • F16L3/22Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets specially adapted for supporting a number of parallel pipes at intervals
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)

Abstract

The invention discloses a general comprehensive pipeline bracket mounting method, and belongs to the technical field of building construction. Comprises a ventilation air pipe which is horizontally and vertically arranged; the upper, lower, left and right spaces of the pipeline bridge frame of the comprehensive bracket on the left side of the roadway are arranged; the upper, lower, left and right spaces of the comprehensive support pipeline bridge frame on the right side of the roadway are arranged. In the figure 1, the distance between the main air pipe pipeline and the frame beam body is set to be 1-B, namely 180mm, so that each professional pipeline can be ensured to be unobstructed between the air pipe and the beam body, the distance between the upper cross arm and the lower cross arm of the comprehensive support is set to be 1-A and 350mm, the space requirements of upturning and left-right turning of all bridges and various pipelines are ensured, and the advancement and the practicability of the installation method are ensured through 2 core distance sizes and 2 core contents.

Description

Universal type comprehensive pipeline support mounting method
Technical Field
The invention relates to the technical field of building construction, in particular to a method for installing a universal comprehensive pipeline bracket.
Background
Because the functional requirements on the building are higher and higher, the installation design of the building is more and more complex, related professions are more and more involved, careful and careful consideration is difficult to be achieved in the design process of each profession, the problems of disordered arrangement, unreasonable space utilization and the like exist in pipeline arrangement, the architectural decoration effect is influenced, even the use and maintenance are influenced, the reasonable utilization of the space of the building is well solved by applying the comprehensive pipeline balancing technology, the rationality of pipeline arrangement is enhanced, but compared with large-scale projects with complex design and large pipeline quantity, the functional requirements of the comprehensive pipeline balancing technology can cause different space divisions of each layer, the common space is divided into blocks and divided into pieces, the cross distribution and the pipeline balancing are difficult to be systematically and deeply achieved, and deeply, and how to make pipeline balancing before construction is particularly important. The comprehensive arrangement of pipelines is a technology and construction preparation work which must be done at the early stage of installation engineering construction, is also a macroscopic control measure, and has important significance for ensuring engineering quality and good use function. Therefore, before engineering construction, each professional needs to pay attention, closely cooperate and repeatedly demonstrate, and determine the optimal scheme to guide project construction, thereby laying a good foundation for constructing high-quality projects.
Disclosure of Invention
The invention aims to provide a universal comprehensive pipeline support mounting method aiming at the purposes that the pipelines of the existing basement are complicated and intricate, the pipelines are densely distributed, the pipelines are reasonably arranged, the pipeline arrangement is attractive and compact, the space problem of the basement is solved to the maximum extent, heavy workload is reduced during mounting, and the goal of achieving twice the result with half the effort is achieved.
In order to achieve the purpose, the invention adopts the following technical scheme:
a method for installing a universal comprehensive pipeline support comprises an installation frame beam body, a secondary beam body between the frame beam bodies, a galvanized suspender, a comprehensive support, a strong-current bridge, a weak-current bridge, a ventilation air pipe, a living water supply pipe, an intelligent bridge, a spraying main pipe, a fire hydrant main pipe, a small-pipe-diameter pressure drain pipe and a large-pipe-diameter pressure drain pipe.
Firstly, judging the distance between the air pipe and the beam body according to the length relation of the frame beam body and the secondary beam between the frame beams, and fixing the air pipe by using a galvanized hanging rod; the sectional area of the air pipe is considered to be the largest in practice, the distance between the upper part of the air pipe and the column beam is controlled to be 180mm, and the error is controlled to be less than or equal to plus or minus 5 mm.
Secondly, the pipelines are arranged in a double-layer mode through the pipeline comprehensive support, the first layer and the bottom layer both adopt 10# galvanized channel steel cross arms, the stability of the comprehensive support is guaranteed, the distance between the first layer and the bottom layer is controlled to be 350mm, the error is controlled to be less than or equal to plus or minus 10mm, and the space during installation is guaranteed;
and finally, a strong-current bridge frame and a weak-current bridge frame are arranged above the first-layer cross arm, a certain space is left between the strong-current bridge frame and the weak-current bridge frame, the space is 650mm, and the error is controlled to be less than or equal to plus or minus 15mm, so that the spray pipe mechanical tee joint can be normally turned upwards after being arranged, the fire hydrant pipe can be normally turned upwards, and the lower pipeline sequentially comprises a living water supply pipe, an intelligent professional bridge frame, a spray main pipe, a fire hydrant main pipe, a small-pipe-diameter pressure drain pipe and a large-pipe-.
Furthermore, the comprehensive supports and the pipeline arrangement on the left side and the right side of the air pipe adopt a symmetrical form, so that the symmetry, the harmony, the attractiveness and the space sense of a main driving area in the garage are ensured;
furthermore, the gap between the upper part of the air pipe and the main beam body is 180mm, and the 180mm is used as the core size of the project, so that all the main spray pipes and a plurality of spray branch pipes can smoothly pass through the main beam, the original mechanical four-way arrangement of the spray pipes is changed into a mechanical three-way arrangement, and the main spray pipes can be freely arranged; secondly, the fire hydrant pipe, the bridge frame, the pressure drainage pipe and the living water supply pipe can freely pass through the upper part of the air pipe, which is one of the core contents of the invention;
the intelligent bridge frame is arranged on the lower side and can freely turn within the range of 350mm, so that all pipelines are guaranteed to be reasonably arranged and can freely turn, and the intelligent bridge frame has operability and is one of the core contents.
Compared with the prior art, the invention provides a universal type comprehensive pipeline bracket mounting method, which has the following beneficial effects:
the method has the advantages of high construction speed and strong specialization, the comprehensive pipeline support is produced in a prefabricated mode or produced on site by professional units, the comprehensive pipeline support is collected and arranged according to various professional drawings, the integration is strong, the comprehensiveness is good, the method is suitable for large and medium-sized projects and prize-creating projects, the small projects are constructed in a template mode, compared with the traditional process, the method has the outstanding performance of the specialty of the installation method, and the requirement of the use space of the basement is met to the greatest extent.
The parts which are not involved in the device are the same as or can be realized by adopting the prior art, and the device has the advantages of simple structure and convenient operation.
Drawings
FIG. 1 is a general type comprehensive pipe support
In the figure: 1. a frame beam body; 2, secondary beam bodies between the frame beam bodies; 3. a galvanized hanger rod; 4. a comprehensive bracket; 5. a strong current bridge frame; 6. a weak current bridge frame; 7. a ventilation air duct; 8. a living water supply pipe; 9. an intelligent bridge frame 10 and a spraying main pipe; 11. a fire hydrant main pipe; 12. a small-caliber pressure drain pipe; 13. big pipe diameter pressure drain pipe.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention.
Example one
Referring to fig. 1, the method for installing the universal comprehensive pipeline support comprises an installation frame beam body 1, a secondary beam body 2 between the frame beam bodies, a galvanized hanger rod 3, a comprehensive support 4, a strong current bridge 5, a weak current bridge 6, a ventilation air pipe 7, a living water supply pipe 8, an intelligent bridge 9, a spraying main pipe 10, a fire hydrant main pipe 11, a small-pipe-diameter pressure drain pipe 12 and a large-pipe-diameter pressure drain pipe 13, wherein the ventilation air pipe 7 is horizontally and vertically arranged; the left comprehensive bracket 4 on the left side of the roadway is arranged in the upper, lower, left and right spaces of the pipeline bridge; the upper, lower, left and right spaces of the pipeline bridge frame of the comprehensive support 4 on the right side of the roadway are arranged.
As shown in figure 1, through setting up 1-B, namely 180mm, the interval between beam body 1 of frame and the pipeline of the main air hose, has guaranteed that every professional pipeline can be unblocked between air hose and beam body, through setting up 1-A of the interval of upper and lower cross arms of the comprehensive support 4, and 350mm, have guaranteed all bridges and various pipelines turn over and turn the space requirement left and right again, through two core interval size and two kernel contents, have guaranteed the advance and practicability of this installation method; the specific operation method comprises the following steps:
firstly, judging the distance between an air pipe and a beam body according to the length relation of a secondary beam between a frame beam body 1 and the frame beam, and fixing the air pipe by using a galvanized suspender 3; the sectional area of the air pipe is considered to be the largest in practice, and the distance between the upper part of the air pipe and the column beam is controlled to be 180 mm.
Secondly, the pipelines are arranged in a double-layer mode through the pipeline comprehensive support 4, the first layer and the bottom layer both adopt 10# galvanized channel steel cross arms, the stability of the comprehensive support 4 is guaranteed, the distance between the first layer and the bottom layer is controlled to be 350mm, and the space during installation is guaranteed;
and finally, a strong-current bridge frame 5 and a weak-current bridge frame 6 are arranged above the first-layer cross arm, a certain space and a distance of 650mm are left between the strong-current bridge frame and the weak-current bridge frame, so that the spray pipe can be normally turned upwards after the mechanical tee joint is arranged, the fire hydrant pipe can be normally turned upwards, and the lower pipeline sequentially comprises a living water supply pipe 8, an intelligent professional bridge frame, a spray main pipe 10, a fire hydrant main pipe 11, a small-pipe-diameter pressure drain pipe 12 and a large-pipe-diameter pressure drain pipe 13 from left to right.
The implementation is as follows:
on the basis of the first embodiment, the comprehensive supports 4 on the left side and the right side of the air pipe and the pipeline arrangement adopt a symmetrical form, so that the symmetry, the coordination, the attractiveness and the space sense of a main driving area in the garage are guaranteed;
the gap between the upper part of the air pipe and the main beam body is 180mm, the error is controlled to be less than or equal to plus or minus 5mm and is taken as the core size of the project, the 180mm ensures that all the main spray pipes 10 and a plurality of spray branch pipes can smoothly pass under the main beam, the original mechanical four-way arrangement of the spray pipeline is changed into a mechanical three-way arrangement, and the main spray pipes 10 can be freely arranged; secondly, the fire hydrant pipe, the bridge frame, the pressure drainage and the living water supply pipe 8 can freely pass through the upper part of the air pipe, which is one of the core contents of the invention;
the strong current bridge frame 5 and the weak current bridge frame 6 are spaced at a certain distance of 650mm, and the error is controlled to be less than or equal to plus or minus 15 mm.
The intelligent fire-fighting spray system comprises double-layer cross arms, a strong and weak electric bridge frame 6 arranged at the upper part, a living water supply pipe 8 arranged at the lower part, a large-caliber pressure drain pipe 13 arranged at the edge, a fire-fighting spray main pipe 10, a fire hydrant pipe and a small-caliber pressure drain pipe 12 arranged at the middle part, and an intelligent bridge frame 9 arranged at the lower part, wherein the intelligent bridge frame can freely turn within the range of 350mm (the error is controlled to be less than or equal to plus or minus 10mm), so that all pipelines are guaranteed to be reasonably arranged and can freely turn, and the intelligent fire-fighting spray system has operability, and is one of the core.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (6)

1. A universal integrated pipeline bracket mounting method comprises mounting a frame beam body, a secondary beam body between the frame beam bodies, a galvanized suspender, an integrated bracket, a strong current bridge, a weak current bridge, a ventilation air pipe, a living water supply pipe, an intelligent bridge, a spray main pipe, a fire hydrant main pipe, a small-pipe-diameter pressure drain pipe and a large-pipe-diameter pressure drain pipe,
firstly, judging the distance between the air pipe and the beam body according to the length relation of the frame beam body and the secondary beam between the frame beams, and fixing the air pipe by using a galvanized hanging rod; the sectional area of the air pipe is considered to be the largest in practice, the distance between the upper part of the air pipe and the column beam is controlled to be 180mm,
secondly, the pipelines are arranged in a double-layer mode through the pipeline comprehensive support, the first layer and the bottom layer both adopt 10# galvanized channel steel cross arms, the stability of the comprehensive support is guaranteed, the distance between the first layer and the bottom layer is controlled to be 350mm, and the space during installation is guaranteed;
and finally, a strong-current bridge frame and a weak-current bridge frame are arranged above the first-layer cross arm, a certain space is left between the strong-current bridge frame and the weak-current bridge frame, the space is 650mm, the spraying pipe can be normally turned upwards after the mechanical tee joint is arranged, the fire hydrant pipe is normally turned upwards, and the lower pipeline sequentially comprises a domestic water supply pipe, an intelligent professional bridge frame, a spraying main pipe, a fire hydrant main pipe, a small-pipe-diameter pressure drain pipe and a large-pipe-diameter pressure drain pipe from left to right.
2. The method for installing a universal integrated piping bracket according to claim 1, wherein the integrated bracket and the piping arrangement on the left and right sides of the air duct are symmetrical.
3. The method for installing the universal comprehensive pipeline bracket as claimed in claim 1, wherein the distance between the upper part of the air duct and the column beam is controlled to be 180mm, the error is controlled to be less than or equal to plus or minus 5mm, the pipeline comprehensive bracket is used for double-layer arrangement of the pipeline, the first layer and the bottom layer are both provided with No. 10 galvanized channel steel cross arms, the stability of the comprehensive bracket is ensured, the distance between the first layer and the bottom layer is controlled to be 350mm, the error is controlled to be less than or equal to plus or minus 10mm, the strong current bridge frame and the weak current bridge frame are spaced at a certain distance between the two, the distance is 650mm, and the error is controlled to be less than.
4. The method for installing the universal comprehensive pipeline bracket according to claim 1, wherein a gap between the upper part of the air pipe and the main girder body is 180mm, so that all the main spray pipes and a plurality of the branch spray pipes can smoothly pass under the main girder.
5. The mounting method of the universal comprehensive pipeline bracket according to claim 4, wherein a mechanical tee is arranged at the joint of the spray pipeline, so that the arrangement of the main spray pipe can be freely arranged; and the fire hydrant pipe, the bridge frame, the pressure drainage pipe and the living water supply pipe can freely pass through the upper part of the air pipe.
6. The method for installing the universal comprehensive pipeline bracket according to claim 4, wherein the double-layer cross arm is arranged: the upper portion sets up strong and weak electric crane span structure, and the life feed pipe of lower part sets up the edge, and big pipe diameter pressure drain pipe sets up the edge, will the fire sprinkler be responsible for, fire hydrant pipe, and in the middle of little pipe diameter pressure drain pipe sets up, and the intelligent crane span structure setting of lower part is in the downside, can freely turn at 350mm within range, has guaranteed that all pipelines not only set up rationally, and can freely turn.
CN201911144973.1A 2019-11-21 2019-11-21 Universal type comprehensive pipeline support mounting method Pending CN111306366A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911144973.1A CN111306366A (en) 2019-11-21 2019-11-21 Universal type comprehensive pipeline support mounting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911144973.1A CN111306366A (en) 2019-11-21 2019-11-21 Universal type comprehensive pipeline support mounting method

Publications (1)

Publication Number Publication Date
CN111306366A true CN111306366A (en) 2020-06-19

Family

ID=71152510

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911144973.1A Pending CN111306366A (en) 2019-11-21 2019-11-21 Universal type comprehensive pipeline support mounting method

Country Status (1)

Country Link
CN (1) CN111306366A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113529932A (en) * 2021-08-25 2021-10-22 陈雨 Novel basement that structural system and equipment pipeline were arranged overall

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE69715949T2 (en) * 1996-04-10 2003-06-12 Erico Int Corp Deck hanger
CN204459464U (en) * 2015-02-14 2015-07-08 江苏省华建建设股份有限公司 A kind of electromechanical pipeline fixed support
CN107687541A (en) * 2016-08-05 2018-02-13 五冶集团上海有限公司 A kind of pipeline provided with people's row access path shares suspension bracket
CN208503354U (en) * 2018-06-28 2019-02-15 浙江甬泰工程技术有限公司 A kind of comprehensive pipeline shock-absorbing support
CN110332372A (en) * 2019-06-21 2019-10-15 苏州金螳螂建筑装饰股份有限公司 A kind of comprehensive suspension and support of the multi-functional finished product of suspended ceilings

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE69715949T2 (en) * 1996-04-10 2003-06-12 Erico Int Corp Deck hanger
CN204459464U (en) * 2015-02-14 2015-07-08 江苏省华建建设股份有限公司 A kind of electromechanical pipeline fixed support
CN107687541A (en) * 2016-08-05 2018-02-13 五冶集团上海有限公司 A kind of pipeline provided with people's row access path shares suspension bracket
CN208503354U (en) * 2018-06-28 2019-02-15 浙江甬泰工程技术有限公司 A kind of comprehensive pipeline shock-absorbing support
CN110332372A (en) * 2019-06-21 2019-10-15 苏州金螳螂建筑装饰股份有限公司 A kind of comprehensive suspension and support of the multi-functional finished product of suspended ceilings

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113529932A (en) * 2021-08-25 2021-10-22 陈雨 Novel basement that structural system and equipment pipeline were arranged overall

Similar Documents

Publication Publication Date Title
CN102296736B (en) Self-supporting heat-insulation hollow floor slab and construction method thereof
WO2015043310A1 (en) Floorslab system
CN103437556B (en) Building water supply and drainage and heating engineering waterproofing and insulation construction method
CN203963265U (en) Pipeline layout support
CN216517007U (en) High-rise building outer wall concrete construction maintenance and spray dust fall system
CN111306366A (en) Universal type comprehensive pipeline support mounting method
CN208718313U (en) A kind of inner corner trim plastering utensil
CN112482779B (en) Integral hoisting construction method for cornice bucket arch of antique building
CN202430879U (en) Perforated panel connecting mechanism
CN205956559U (en) Pipeline gallows
CN206154492U (en) Bury shower nozzle intelligence maintenance system
CN201695468U (en) Air-conditioner condensed water pipe embedded in shear wall of high-rise building
CN212004564U (en) Pipeline positioning support for water supply and drainage engineering
CN114351872A (en) Adjustable electromechanical engineering support and hanger embedded part
CN113293857A (en) Basement for reducing floor height by laying channels through overall pipelines
CN111895184A (en) Comprehensive pipeline supporting and hanging frame in limited space
CN203296279U (en) Drainage structure of orthogonal intersecting portion of light steel factory
CN212441817U (en) Landscape water spraying device
CN216196671U (en) A hang mould construction structures for super narrow hydroelectric well
CN220470941U (en) Water supply and drainage pipeline structure for building
CN206267087U (en) A kind of multi-functional device for reducing dust of building engineering construction
CN217871458U (en) Novel eaves position waterproof node structure of metal roof board
CN203547126U (en) Floor slab construction formwork component
CN212926268U (en) Concrete frame structure building maintenance system
CN205261040U (en) Direct -burried breaking of contact formula sleeve pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200619

RJ01 Rejection of invention patent application after publication