CN206267087U - A kind of multi-functional device for reducing dust of building engineering construction - Google Patents
A kind of multi-functional device for reducing dust of building engineering construction Download PDFInfo
- Publication number
- CN206267087U CN206267087U CN201621230328.3U CN201621230328U CN206267087U CN 206267087 U CN206267087 U CN 206267087U CN 201621230328 U CN201621230328 U CN 201621230328U CN 206267087 U CN206267087 U CN 206267087U
- Authority
- CN
- China
- Prior art keywords
- instrumentation tubes
- supervisor
- functional device
- engineering construction
- building engineering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000000428 dust Substances 0.000 title claims abstract description 36
- 238000010276 construction Methods 0.000 title claims abstract description 34
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 6
- 238000009435 building construction Methods 0.000 claims description 7
- 229920001155 polypropylene Polymers 0.000 claims description 6
- 230000000630 rising effect Effects 0.000 claims description 4
- 238000000151 deposition Methods 0.000 abstract description 16
- 230000000694 effects Effects 0.000 abstract description 4
- 238000009434 installation Methods 0.000 abstract description 2
- 238000000034 method Methods 0.000 description 6
- 239000000463 material Substances 0.000 description 5
- 239000012943 hotmelt Substances 0.000 description 4
- 238000003915 air pollution Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
A kind of multi-functional device for reducing dust of building engineering construction, including gate valve, the gate valve is arranged on water supply line interface, gate valve connection level supervisor, force (forcing) pump is set on level supervisor, and level supervisor connects supervisor vertically by the first joint, and supervisor connects instrumentation tubes by the second joint vertically, multiple branch pipes are arranged in equal spacing with the instrumentation tubes, atomizer is installed on each branch pipe.A kind of the utility model multi-functional device for reducing dust of building engineering construction, the device depositing dust is applied widely, and effect is good, and low cost is lightweight, making, simple installation, simple to operate, easy to use.
Description
Technical field
The utility model is related to a kind of construction field device for reducing dust, particularly a kind of multi-functional depositing dust of building engineering construction
Device.
Background technology
In building engineering construction, inevitably need to carry out earthwork evacuation, backfill, material transportation.Construction area
Interior large scale equipment is more, vehicle flowrate big, tail gas of airborne dust and jumbo generation for generation of constructing etc., and certain air will be caused dirty
Dye, certain negative effect is caused to workmen and the healthy of resident.And architectural engineering, especially Bases in High Building Construction
Engineering is built in busy city mostly, populous.Colony involved by air pollution is bigger, and influence face is wider.It is traditional at present
Depositing dust method, in setup of entrances and exits vehicle wash platform, sprinkler etc., these methods of the prior art are difficult to satisfaction and apply
The depositing dust requirement from front to back, from left to right, comprehensive from top to bottom of work scene.
The content of the invention
In order to reduce the airborne dust produced in building engineering construction, improve the Working Life ring of workmen and nearby residents
Border, improves air quality.The utility model provides a kind of multi-functional device for reducing dust of building engineering construction, and the device depositing dust is applicable
Scope is wide, and effect is good, and low cost is lightweight, making, simple installation, simple to operate, easy to use.
The technical scheme that the utility model is taken is:
A kind of multi-functional device for reducing dust of building engineering construction, including gate valve, the gate valve are arranged on water supply line interface
Place, gate valve connection level supervisor, sets force (forcing) pump on level supervisor, level supervisor connects supervisor vertically, erects by the first joint
Straight supervisor connects instrumentation tubes by the second joint, and multiple branch pipes are arranged in equal spacing with the instrumentation tubes, pacifies on each branch pipe
Equipped with atomizer.
The branch pipe tilts upward angle and is connected with instrumentation tubes in 45 °.
The level supervisor, vertically supervisor, instrumentation tubes, branch pipe are lighter, the convenient to assemble and disassemble PP-R pipe of material, connection side
Formula is hot melt.
First joint, the second joint are lighter, the convenient to assemble and disassemble PP-R pipe of material, and connected mode is hot melt.
First joint is bent sub;Second joint is bent sub or swivel joint.
The instrumentation tubes are fixed on construction road both sides fence, building construction outrigger or tower crane arm;Instrumentation tubes are located at
During both sides of the road, supervisor sets height 1.8m~2.0m vertically;When instrumentation tubes are located at building construction outrigger, supervisor can be with building vertically
Build the rising adjustment height of thing;Instrumentation tubes are located at when on tower crane arm, and supervisor can be with the liter height adjustment of tower crane highly vertically, instrumentation tubes
It is connected using swivel joint with supervisor vertically.
The level supervisor, vertical supervisor, instrumentation tubes, branch pipe are multiple;First joint, the second joint are many
Individual, the pipeline, joint connect and compose depositing dust pipe network.
A kind of the utility model multi-functional device for reducing dust of building engineering construction, technique effect is as follows:
1:When the device is located at both sides of the road, height 1.8m~2.0m is set, whole construction road can be covered;It is located at room
Height regulation can be carried out with the rising of building during room construction exterior rack, whole building thing periphery can be covered;It is located at construction tower crane arm
When upper, can entirely be constructed overhead with the revolving coverage method of tower crane;According to on-site actual situations, each position can be set simultaneously, meet
The comprehensive depositing dust requirement in whole job site.
2:The device can not only effectively depositing dust, protection construction environment, while be may also function as in hot weather construction reduce construction
Temperature, the booster action for ensureing concrete construction quality.
3:Using the three-way elbow of finished product, the number and length of directly first-class increase level supervisor, vertically supervisor, instrumentation tubes
Degree, forms depositing dust pipe network, the depositing dust requirement comprehensive to meet whole construction site.
Brief description of the drawings
Fig. 1 is the utility model apparatus structure schematic diagram;
Fig. 2 is the A-A direction views of Fig. 1.
Specific embodiment
As shown in Figure 1 and Figure 2, a kind of multi-functional device for reducing dust of building engineering construction, including gate valve 2, the gate valve 2 sets
Put in the interface of water supply line 1, the connection level of gate valve 2 supervisor 4 sets force (forcing) pump 3 on level supervisor 4, level supervisor 4 is by the
One joint 5 connects supervisor 6 vertically, and supervisor 6 connects instrumentation tubes 8, equidistant cloth in the instrumentation tubes 8 by the second joint 7 vertically
Multiple branch pipes 9 are equipped with, atomizer 10 is installed on each branch pipe 9.
The branch pipe 9 tilts upward angle and is connected with instrumentation tubes 8 in 45 °.
The level supervisor 4, vertically supervisor 6, instrumentation tubes 8, branch pipe 9 are lighter, the convenient to assemble and disassemble PP-R pipe of material, even
Mode is connect for hot melt.
First joint 5, the second joint 7 are lighter, the convenient to assemble and disassemble PP-R pipe of material, and connected mode is hot melt
Method.
First joint 5 is bent sub.
Second joint 7 is bent sub or swivel joint.
The instrumentation tubes 8 are fixed on construction road both sides fence, building construction outrigger or tower crane arm;
When instrumentation tubes 8 are located at both sides of the road, supervisor 6 sets height 1.8m~2.0m vertically, can cover whole construction road.
When instrumentation tubes 8 are located at building construction outrigger, supervisor 6 can adjust height with the rising of building vertically, meet whole
Building periphery depositing dust needs.
Instrumentation tubes 8 are located at when on tower crane arm, and 6 are responsible for vertically can be with the liter height adjustment of tower crane highly, instrumentation tubes 8 and vertically master
Pipe 6 is connected using swivel joint, instrumentation tubes 8 is entirely constructed overhead with the revolving coverage method of tower crane.
The level is responsible for 4, supervisor 6, instrumentation tubes 8, branch pipe 9 are multiple vertically;First joint 5, the second joint 7
Multiple is, the pipeline, joint connect and compose depositing dust pipe network.
A kind of the utility model multi-functional device for reducing dust of building engineering construction, after arranging depositing dust pipe network, opens gate valve 2
With force (forcing) pump 3, water under high pressure is responsible for 4 by level and supervisor 6 is delivered to instrumentation tubes 8 and branch pipe 9 vertically, then by installed in branch
Atomizer 10 on pipe 9 ejects atomized water and carries out depositing dust.
The utility model can also need the aperture of regulation gate valve 2 and the pressure of force (forcing) pump 3 according to scene, adjust atomized dust settling
Scope and degree.
The utility model according to site operation needs, using the three-way elbow of finished product, directly be responsible for by first-class increase level
4th, 6, the number and length of instrumentation tubes 8 are responsible for vertically, form depositing dust pipe network, will to meet the comprehensive depositing dust in whole construction site
Ask.
Claims (7)
1. a kind of multi-functional device for reducing dust of building engineering construction, including gate valve(2), it is characterised in that:The gate valve(2)Set
In water supply line(1)Interface, gate valve(2)Connection level is responsible for(4), level supervisor(4)Upper setting force (forcing) pump(3), level master
Pipe(4)By the first joint(5)Connection is responsible for vertically(6), it is responsible for vertically(6)By the second joint(7)Connection instrumentation tubes(8),
The instrumentation tubes(8)On be arranged in equal spacing with multiple branch pipes(9), each branch pipe(9)On atomizer is installed(10).
2. the multi-functional device for reducing dust of a kind of building engineering construction according to claim 1, it is characterised in that:The branch pipe
(9)With instrumentation tubes(8)Angle is tilted upward in 45 ° to connect.
3. the multi-functional device for reducing dust of a kind of building engineering construction according to claim 1, it is characterised in that:The level master
Pipe(4), vertically supervisor(6), instrumentation tubes(8), branch pipe(9)It is PP-R pipe.
4. the multi-functional device for reducing dust of a kind of building engineering construction according to claim 1, it is characterised in that:Described first connects
Head(5), the second joint(7)It is PP-R pipe.
5. the multi-functional device for reducing dust of a kind of building engineering construction according to claim 1 or 4, it is characterised in that:Described
One joint(5)It is bent sub.
6. the multi-functional device for reducing dust of a kind of building engineering construction according to claim 1 or 4, it is characterised in that:Described
Two joints(7)It is bent sub or swivel joint.
7. the multi-functional device for reducing dust of a kind of building engineering construction according to claim 1, it is characterised in that:The instrumentation tubes
(8)It is fixed on construction road both sides fence, building construction outrigger or tower crane arm;Instrumentation tubes(8)When being located at both sides of the road,
It is responsible for vertically(6)Height 1.8m~2.0m is set;Instrumentation tubes(8)When being located at building construction outrigger, it is responsible for vertically(6)Can be with building
The rising adjustment height of thing;Instrumentation tubes(8)It is located at when on tower crane arm, vertically supervisor(6)Can be with the liter height adjustment of tower crane highly, work
Manage(8)With supervisor vertically(6)Connected using swivel joint.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621230328.3U CN206267087U (en) | 2016-11-16 | 2016-11-16 | A kind of multi-functional device for reducing dust of building engineering construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621230328.3U CN206267087U (en) | 2016-11-16 | 2016-11-16 | A kind of multi-functional device for reducing dust of building engineering construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206267087U true CN206267087U (en) | 2017-06-20 |
Family
ID=59040739
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621230328.3U Expired - Fee Related CN206267087U (en) | 2016-11-16 | 2016-11-16 | A kind of multi-functional device for reducing dust of building engineering construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206267087U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107700932A (en) * | 2017-11-06 | 2018-02-16 | 武汉毳雨环保科技有限责任公司 | The construction method and enclosing module of enclosing with dust detection formula spray equipment |
-
2016
- 2016-11-16 CN CN201621230328.3U patent/CN206267087U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107700932A (en) * | 2017-11-06 | 2018-02-16 | 武汉毳雨环保科技有限责任公司 | The construction method and enclosing module of enclosing with dust detection formula spray equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205444458U (en) | Integrated assembled steel construction building | |
CN104264995A (en) | Automatic spraying conservation system for high-rise building shear wall structure | |
CN204844444U (en) | Concrete tower crane high altitude sprays maintenance system | |
CN206267087U (en) | A kind of multi-functional device for reducing dust of building engineering construction | |
CN216517007U (en) | High-rise building outer wall concrete construction maintenance and spray dust fall system | |
CN104389429A (en) | Intelligent garden type concrete spray maintenance device and concrete maintenance method thereof | |
CN207379672U (en) | A kind of window for building rain-proof sprays detection machine | |
CN205915494U (en) | System is protected in prefab production precuring | |
CN104328898A (en) | Rendering maintenance device for building external wall | |
CN203834809U (en) | Steel pipe column structure for steel pipe column concrete side pouring method | |
CN208201919U (en) | A kind of piping lane monoblock type, which is quickly pacified, tears aluminium alloy mould bases support construction open | |
CN208897847U (en) | One kind pushing and pulling closed atomizing refuse depot entirely | |
CN217175304U (en) | Tubular well plugging structure | |
CN206655544U (en) | Intelligent monitoring dust fall environment-friendly construction enclosure | |
CN201695548U (en) | Large steam lightweight aerated concrete panel | |
CN212327756U (en) | Dust device for construction site | |
CN104314311B (en) | For the liftable level of tower machine of constructing 360 ° of spray equipments | |
CN104372877A (en) | Construction method for tall vertical stone water curtain wall | |
CN205976514U (en) | Interim simple tool formula carwash factory in building site | |
CN114888923A (en) | Concrete prefabricated baffle processing platform for civil engineering construction and implementation method thereof | |
CN204212380U (en) | A kind of external wall whitewashes curing means | |
CN210976491U (en) | Building engineering spraying device | |
CN209891129U (en) | Multifunctional protective railing | |
CN210916936U (en) | Bridge floor patching device is used in bridge construction | |
CN207789282U (en) | A kind of integrated final-assembly die of concrete prefabricated element |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170620 |