CN111305869A - Prefabricated lining structure of arch wall and construction method - Google Patents

Prefabricated lining structure of arch wall and construction method Download PDF

Info

Publication number
CN111305869A
CN111305869A CN202010076370.9A CN202010076370A CN111305869A CN 111305869 A CN111305869 A CN 111305869A CN 202010076370 A CN202010076370 A CN 202010076370A CN 111305869 A CN111305869 A CN 111305869A
Authority
CN
China
Prior art keywords
arch
secondary lining
arch wall
lining
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010076370.9A
Other languages
Chinese (zh)
Inventor
杨昌宇
熊国兴
卿伟宸
张慧玲
旷文涛
杨宝
曹林卫
巩江峰
邸成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN202010076370.9A priority Critical patent/CN111305869A/en
Publication of CN111305869A publication Critical patent/CN111305869A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

A prefabricated lining structure of an arch wall and a construction method are provided, which aim to effectively ensure the quality of an arch lining while improving the industrialization degree and the construction efficiency of the mine tunnel construction, solve the lining quality defect caused by difficult cast-in-place control, ensure the safety of tunnel operation and reduce the investment of renovation in the operation period. The primary support structure, the waterproof and drainage system and the secondary lining structure are arranged from inside to outside, and the secondary lining structure is composed of an inverted arch and an arch wall secondary lining structure. The inverted arch is formed by continuous casting in a segmented mode along the extending direction of the tunnel; the arch wall secondary lining structure is a reinforced concrete prefabricated structure and is formed by longitudinally assembling arch wall secondary lining sections, the two circumferential ends of the arch wall secondary lining sections are in lap joint with the two circumferential ends of an inverted arch, and each arch wall secondary lining section is formed by annularly assembling at least three arch wall secondary lining building blocks.

Description

一种拱墙预制衬砌结构及施工方法A kind of arch wall prefabricated lining structure and construction method

技术领域technical field

本发明涉及隧道衬砌结构,特别涉及一种拱墙范围内采用预制构件的 装配式隧道衬砌结构及其施工方法。The invention relates to a tunnel lining structure, in particular to a prefabricated tunnel lining structure using prefabricated components within an arch wall and a construction method thereof.

背景技术Background technique

近年来,我国铁路建设发展迅猛,特别是高速铁路的建设进入了爆发 式增长阶段。随着铁路运营里程的快速增长,以及线路标准的提高而带来 的隧线比增大,铁路隧道的数量和规模也呈迅速增长的趋势,特别是在西 南山区,隧道在铁路基建项目中的占比极高。In recent years, my country's railway construction has developed rapidly, especially the construction of high-speed railway has entered an explosive growth stage. With the rapid growth of railway operation mileage and the increase of tunnel-to-line ratio brought about by the improvement of line standards, the number and scale of railway tunnels also show a trend of rapid growth, especially in the southwestern mountainous area, where tunnels play an important role in railway infrastructure projects. The proportion is very high.

目前矿山法隧道施工过程中,由于各类工艺质量及其他因素,部分地 段存在初支或衬砌背后脱空、二衬厚度不足、裂纹、渗漏水、施工缝错台、 混凝土强度不均或不足等质量缺陷,此类质量问题在隧道拱部尤为突出, 对铁路运营安全带来极大隐患。近年来,多条已开通的高速铁路在运营期 间发生了若干起由于隧道衬砌质量缺陷带来的病害,导致降速运行甚至线 路中断的事故,引起各方高度重视,并投入了巨大的人力物力进行整治。At present, during the construction of mining tunnels, due to various process quality and other factors, some sections have initial support or void behind the lining, insufficient thickness of the secondary lining, cracks, water seepage, construction joints staggered, and uneven or insufficient concrete strength. Such quality problems are particularly prominent in the tunnel arch, which brings great hidden dangers to the safety of railway operation. In recent years, a number of high-speed railways that have been opened have suffered from several diseases caused by the quality defects of the tunnel lining during the operation period, resulting in slow-speed operation or even line interruption accidents, which have attracted great attention from all parties and invested huge manpower and material resources. remediation.

传统矿山法施工的隧道衬砌一般采用曲墙带仰拱的现浇结构形式。施 工时通常先对仰拱部位绑扎钢筋并浇筑混凝土,仰拱浇筑时两侧预留边墙 接茬钢筋,待仰拱往掌子面方向施作一定步距之后,再利用衬砌模板台车 对边墙及拱部进行钢筋绑扎并整体浇筑混凝土,边墙脚通过仰拱两侧的接 茬钢筋与仰拱连接形成整体,因此,整个衬砌均是在现场浇筑成型。传统 隧道衬砌施工存在的最大缺陷在于:由于衬砌为现场整体浇筑,浇筑工艺 对衬砌质量至关重要,然而实际施工中由于结构钢筋绑扎不到位,入模、 振捣、混凝土灌注困难等施工工艺问题,容易造成混凝土衬砌出现蜂窝、 麻面、厚度不足、浇筑振捣不密实等情况,造成运营过程中衬砌的开裂甚 至剥落掉块,极大程度上威胁着线路行车安全,此类情况在衬砌拱部位置 尤为严重,对行车安全带来的威胁也最大。The tunnel lining constructed by the traditional mining method generally adopts a cast-in-place structure with curved walls and inverted arches. During construction, the inverted arch is usually first bound with steel bars and poured into concrete. When the inverted arch is poured, the side walls are reserved for connecting the steel bars. The wall and the arch are bound with steel bars and concrete is poured as a whole, and the side wall foot is connected with the inverted arch through the stubbing steel bars on both sides of the inverted arch to form a whole. Therefore, the entire lining is cast and formed on site. The biggest defect of traditional tunnel lining construction is: because the lining is cast as a whole on site, the pouring process is very important to the quality of the lining. However, in the actual construction, due to the insufficient binding of structural steel bars, the construction process problems such as mold entry, vibration and concrete pouring are difficult. , it is easy to cause the concrete lining to appear honeycomb, pockmarked surface, insufficient thickness, poor pouring and vibrating, etc., resulting in cracking or even peeling off of the lining during operation, which greatly threatens the safety of the line. The location of the department is particularly serious, and the threat to the driving safety is also the greatest.

因此,对传统矿山法施工的隧道衬砌结构进行优化,从根本上解决隧 道衬砌质量缺陷问题,提高隧道工程质量,充分保证隧道内行车安全成为 了隧道建设的迫切需要。Therefore, it is an urgent need for tunnel construction to optimize the tunnel lining structure constructed by the traditional mining method, fundamentally solve the problem of the quality defect of the tunnel lining, improve the quality of the tunnel project, and fully ensure the driving safety in the tunnel.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的技术问题是提供了一种拱墙预制衬砌结构,以在提 高矿山法隧道施工的工业化程度和施工效率的同时有效保证拱部衬砌的 质量,解决由于现场浇筑控制困难导致的衬砌质量缺陷,确保隧道运营的 安全,减少运营期整治的投入。The technical problem to be solved by the present invention is to provide a prefabricated lining structure of an arch wall, so as to effectively ensure the quality of the arch lining while improving the industrialization degree and construction efficiency of the tunnel construction by the mine method, and solve the problem of lining caused by the difficulty of on-site pouring control. Quality defects, ensure the safety of tunnel operation, and reduce the investment in remediation during the operation period.

本发明解决其技术问题所采用的技术方案如下:The technical scheme adopted by the present invention to solve its technical problems is as follows:

本发明的一种拱墙预制衬砌结构,包括由内而外设置的初期支护结 构、防排水系统和二次衬砌结构,二次衬砌结构由仰拱和拱墙二次衬砌结 构构成,其特征是:所述仰拱沿隧道延伸方向分段连续浇筑形成;所述拱 墙二次衬砌结构为钢筋混凝土预制结构,由拱墙二次衬砌节段纵向拼装而 成,拱墙二次衬砌节段的环向两端与仰拱的环向两端形成搭接,各拱墙二 次衬砌节段由至少三块拱墙二次衬砌砌块环向拼装形成。The prefabricated lining structure of an arch wall of the present invention includes an initial support structure, a water-proof and drainage system and a secondary lining structure arranged from the inside to the outside. The secondary lining structure is composed of an inverted arch and an arch wall secondary lining structure. It is: the inverted arch is formed by continuous pouring in sections along the extension direction of the tunnel; the secondary lining structure of the arch wall is a reinforced concrete prefabricated structure, which is longitudinally assembled by the secondary lining sections of the arch wall, and the secondary lining sections of the arch wall are formed. The two circumferential ends of the arch wall are overlapped with the circumferential two ends of the inverted arch, and each secondary lining section of the arch wall is formed by at least three secondary lining blocks of the arch wall being assembled circumferentially.

发明所要解决的另一技术问题提供上述一种拱墙预制衬砌结构的施 工方法。该方法包括如下步骤:Another technical problem to be solved by the invention provides the above-mentioned construction method of the prefabricated lining structure of an arch wall. The method includes the following steps:

①隧道开挖掘进至掌子面;①The tunnel is excavated to the face of the tunnel;

②及时施作初期支护结构;② Implement the initial support structure in time;

③施作防排水系统;③ Implement waterproof and drainage system;

④滞后掌子面一定距离施作仰拱;④The inverted arch is applied at a certain distance from the lag face;

⑤滞后仰拱一定距离施作仰拱填充层;⑤ lag the inverted arch at a certain distance and apply the inverted arch filling layer;

⑥掌子面掘进到预定位置后停止掘进,待初期支护结构、防排水系统、 仰拱及仰拱填充层施作到该位置并达到相应设计强度;⑥ After the tunnel face is excavated to the predetermined position, the excavation is stopped, and the initial support structure, the waterproof and drainage system, the inverted arch and the inverted arch filling layer are applied to this position and reach the corresponding design strength;

⑦铺设拱墙二次衬砌台车走行轨道;⑦ Lay arch wall secondary lining trolley running track;

⑧在洞口完成拱墙二次衬砌节段的拼装;⑧Complete the assembly of the secondary lining segment of the arch wall at the opening;

⑨利用拱墙二次衬砌台车将一拱墙二次衬砌节段从洞口运输到掌子 面位置并完成与仰拱的拼装;⑨Using the arch wall secondary lining trolley to transport an arch wall secondary lining segment from the hole to the position of the face and complete the assembly with the inverted arch;

⑩重复步骤⑧和⑨,由掌子面向洞口方向拼装下一个拱墙二次衬砌节 段,并用纵向连接螺栓将拱墙二次衬砌节段拼装连接为一体,直至拼装到 洞口,完成拱墙二次衬砌的拼装施工。⑩Repeat steps ⑧ and ⑨, assemble the next secondary lining segment of the arch wall with the palm facing the direction of the opening, and use longitudinal connecting bolts to assemble and connect the secondary lining segment of the arch wall as a whole until it is assembled to the opening, and the second arch wall is completed. Assembly and construction of secondary lining.

本发明的有益效果是,在充分发挥矿山法隧道施工灵活的优势下,拱 墙衬砌采用预制装配件,可在工厂中批量生产,然后运到现场采用机械化 拼装,改善现场劳动条件,节约材料,提高了隧道施工的机械化水平和劳 动效率。同时,由于拱墙衬砌为工厂化预制,可以有效保证结构质量,避 免由于现浇工艺问题带来的衬砌质量缺陷,避免运营过程中拱部衬砌病 害,保证行车安全。The beneficial effect of the invention is that, under the advantage of the flexible construction of mining tunnels, the lining of the arch wall adopts prefabricated assemblies, which can be mass-produced in the factory, and then transported to the site for mechanized assembly, thereby improving the working conditions on site and saving materials. The mechanization level and labor efficiency of tunnel construction are improved. At the same time, because the arch wall lining is factory prefabricated, it can effectively ensure the structural quality, avoid lining quality defects caused by cast-in-place process problems, avoid arch lining diseases during operation, and ensure driving safety.

附图说明Description of drawings

本说明书包括如下十幅附图:This manual includes the following ten drawings:

图1是本发明一种拱墙预制衬砌结构的横断面图;Fig. 1 is the cross-sectional view of a kind of arch wall prefabricated lining structure of the present invention;

图2和图3是本发明一种拱墙预制衬砌结构中拱墙预制衬砌块之间 纵向接头部的斜螺栓连接示意图;Fig. 2 and Fig. 3 are the oblique bolt connection schematic diagrams of the longitudinal joints between the prefabricated lining blocks of the arch wall in a prefabricated lining structure of the arch wall of the present invention;

图4和图5是本发明一种拱墙预制衬砌结构中拱墙预制衬砌块之间 纵向接头部的弯螺栓连接示意图;Fig. 4 and Fig. 5 are the bending bolt connection schematic diagram of the longitudinal joint between the prefabricated lining blocks of the arch wall in a kind of arch wall prefabricated lining structure of the present invention;

图6是本发明一种拱墙预制衬砌结构中拱墙预制衬砌块与仰拱之间 的连接部示意图;Fig. 6 is the connection part schematic diagram between the prefabricated lining block of the arch wall and the inverted arch in a prefabricated lining structure of the arch wall of the present invention;

图7是本发明一种拱墙预制衬砌结构中拱墙预制衬砌块沿隧道纵向的 通缝拼装示意图;Fig. 7 is a kind of arch wall prefabricated lining structure of the present invention, the arch wall prefabricated lining block along the tunnel longitudinal direction through joint assembly schematic diagram;

图8是本发明一种拱墙预制衬砌结构中拱墙预制衬砌块沿隧道纵向 的错缝拼装示意图;Fig. 8 is the staggered assembly schematic diagram of the prefabricated lining block of the arch wall along the longitudinal direction of the tunnel in a prefabricated lining structure of the arch wall of the present invention;

图9和图10是本发明一种拱墙预制衬砌结构中拱墙预制衬砌块之间 环向接头的螺栓连接示意图;Fig. 9 and Fig. 10 are the bolted connection schematic diagrams of the annular joint between the prefabricated lining blocks of the arch wall in a prefabricated lining structure of the arch wall of the present invention;

图11至图18是本发明一种拱墙预制衬砌结构的施工步骤分解示意 图。Figures 11 to 18 are exploded schematic views of the construction steps of a prefabricated lining structure for an arch wall of the present invention.

图中出示部位、构件及所对应的标记:初期支护结构10、防排水系 统20、拱墙二次衬砌砌块30、仰拱31、仰拱填充层31a、环向连接螺栓 41、环向连接孔密封圈42、第一环向防水密封垫32、第二环向防水密封 垫33、纵向连接螺栓51、纵向连接孔密封圈52、纵向防水密封垫53、掌 子面D。Parts, components and corresponding marks are shown in the figure: initial support structure 10, waterproof and drainage system 20, secondary lining block 30 of arch wall, inverted arch 31, inverted arch filling layer 31a, circumferential connecting bolt 41, circumferential direction The connection hole sealing ring 42 , the first annular waterproof gasket 32 , the second annular waterproof gasket 33 , the longitudinal connection bolts 51 , the longitudinal connection hole sealing ring 52 , the longitudinal waterproof gasket 53 , and the face D.

具体实施方式Detailed ways

下面结合附图和实施例对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

参照图1,本发明的一种拱墙预制衬砌结构,包括由内而外设置的初 期支护结构10、防排水系统20和二次衬砌结构,二次衬砌结构由仰拱31 和拱墙二次衬砌结构构成,其特征是:所述仰拱31沿隧道延伸方向分段 连续浇筑形成;所述拱墙二次衬砌结构为钢筋混凝土预制结构,由拱墙二 次衬砌节段纵向拼装而成,拱墙二次衬砌节段的环向两端与仰拱31的环 向两端形成搭接,各拱墙二次衬砌节段由至少三块拱墙二次衬砌砌块30 环向拼装形成。在充分发挥矿山法隧道施工灵活的优势下,拱墙衬砌采用 预制装配件,可在工厂中批量生产,然后运到现场采用机械化拼装,改善 现场劳动条件,节约材料,提高了隧道施工的机械化水平和劳动效率。同 时,由于拱墙衬砌为工厂化预制,可以有效保证结构质量,避免由于现浇 工艺问题带来的衬砌质量缺陷,避免运营过程中拱部衬砌病害,保证行车 安全。Referring to Figure 1, a prefabricated lining structure of an arch wall of the present invention includes an initial support structure 10, a water-proof and drainage system 20 and a secondary lining structure that are set from the inside out, and the secondary lining structure is composed of an inverted arch 31 and an arch wall two. The secondary lining structure is formed, and it is characterized in that: the inverted arch 31 is formed by continuous pouring in sections along the extension direction of the tunnel; the secondary lining structure of the arch wall is a reinforced concrete prefabricated structure, which is longitudinally assembled by the secondary lining segments of the arch wall. , the two circumferential ends of the secondary lining section of the arch wall are overlapped with the two circumferential ends of the inverted arch 31, and each secondary lining section of the arch wall is formed by circumferentially assembling at least three secondary lining blocks 30 of the arch wall. . Taking full advantage of the flexibility of mining tunnel construction, the arch wall lining adopts prefabricated assemblies, which can be mass-produced in the factory, and then transported to the site for mechanized assembly, which improves on-site labor conditions, saves materials, and improves the mechanization level of tunnel construction. and labor efficiency. At the same time, because the lining of the arch wall is factory prefabricated, it can effectively ensure the structural quality, avoid lining quality defects caused by cast-in-place process problems, avoid arch lining diseases during operation, and ensure driving safety.

参照6,所述仰拱31环向端为下凹弧面,与之形成搭接的拱墙二次 衬砌砌块30环向端为与该下凹弧面相贴合的下凸弧面,该对下凹弧面、 下凸弧面之间设置纵向延伸的第二环向防水密封垫33。Referring to 6, the annular end of the inverted arch 31 is a concave arc surface, and the annular end of the arch wall secondary lining block 30 that forms overlap is the convex arc surface that fits with the concave arc surface. A longitudinally extending second annular waterproof gasket 33 is arranged between the lower concave arc surface and the lower convex arc surface.

参照图7、图8,所述拱墙二次衬砌结构中,各相邻拱墙二次衬砌节 段的拱墙二次衬砌砌块30按通缝拼装或者错缝拼装。Referring to Fig. 7 and Fig. 8, in the secondary lining structure of the arch wall, the secondary lining blocks 30 of the arch wall of each adjacent secondary lining segment of the arch wall are assembled according to through seam or staggered seam assembly.

参照图2至图5,所述拱墙二次衬砌节段中,相邻拱墙二次衬砌砌块 30的环向接触面呈对应的平面或者弧面,由穿过环向连接孔的环向连接 螺栓41将两相邻拱墙二次衬砌砌块30连接为一体。所述环向接触面上设 置纵向延伸的第一环向防水密封垫32,在环向连接孔两端设置环向连接 孔密封圈52。环向连接螺栓41可以采用弧形螺栓或者直螺栓Referring to FIGS. 2 to 5 , in the secondary lining section of the arch wall, the annular contact surfaces of the adjacent secondary lining blocks 30 of the arch wall are corresponding planes or arcs, and the annular contact surfaces passing through the annular connecting holes The connecting bolts 41 connect two adjacent arch wall secondary lining blocks 30 as a whole. A longitudinally extending first annular waterproof gasket 32 is arranged on the annular contact surface, and annular connecting hole sealing rings 52 are arranged at both ends of the annular connecting hole. Circumferential connecting bolts 41 can be curved bolts or straight bolts

参照图9和图10,所述拱墙二次衬砌节段中,由穿过相邻两拱墙二 次衬砌砌块30纵向连接孔的纵向连接螺栓51将相邻两拱墙二次衬砌节段 拼装为一体。所述相邻两拱墙二次衬砌砌块30的纵向接触面上设置环向 延伸的纵向防水密封垫53,在纵向连接螺栓51的外端或者两端设置纵向 连接孔密封圈52。9 and 10, in the secondary lining section of the arch wall, the secondary lining sections of the adjacent two arch walls are connected by the longitudinal connecting bolts 51 passing through the longitudinal connecting holes of the secondary lining blocks 30 of the adjacent two arch walls. The segments are assembled into one. A circumferentially extending longitudinal waterproof gasket 53 is provided on the longitudinal contact surfaces of the secondary lining blocks 30 of the adjacent two arch walls, and longitudinal connection hole sealing rings 52 are provided at the outer ends or both ends of the longitudinal connection bolts 51.

参照图11至图18,本发明一种拱墙预制衬砌结构的施工方法,包括 如下步骤:Referring to Figure 11 to Figure 18, a construction method of a prefabricated lining structure of an arch wall of the present invention comprises the following steps:

①隧道开挖掘进至掌子面D;①The tunnel is excavated to the face D;

②及时施作初期支护结构10;②The initial support structure 10 is installed in time;

③施作防排水系统20;③ Implement waterproof and drainage system 20;

④滞后掌子面D一定距离施作仰拱31;④ The inverted arch 31 is applied at a certain distance from the lag face D;

⑤滞后仰拱31一定距离施作仰拱填充层31a;⑤ lag the inverted arch 31 a certain distance and perform the inverted arch filling layer 31a;

⑥掌子面D掘进到预定位置后停止掘进,待初期支护结构10、防排 水系统20、仰拱31及仰拱填充层31a施作到该位置并达到相应设计强度;6. the face D is excavated and stops excavation after the predetermined position, treats the initial stage support structure 10, the anti-drainage system 20, the inverted arch 31 and the inverted arch filling layer 31a and is applied to this position and reaches the corresponding design strength;

⑦铺设拱墙二次衬砌台车走行轨道;⑦ Lay arch wall secondary lining trolley running track;

⑧在洞口完成拱墙二次衬砌节段的拼装;⑧Complete the assembly of the secondary lining segment of the arch wall at the opening;

⑨利用拱墙二次衬砌台车将一拱墙二次衬砌节段从洞口运输到掌子 面位置并完成与仰拱31的拼装;⑨ Utilize the arch wall secondary lining trolley to transport an arch wall secondary lining segment from the hole to the palm face position and complete the assembling with the inverted arch 31;

⑩重复步骤⑧和⑨,由掌子面D向洞口方向拼装下一个拱墙二次衬 砌节段,并用纵向连接螺栓51将拱墙二次衬砌节段拼装连接为一体,直 至拼装到洞口,完成拱墙二次衬砌的拼装施工。⑩ Repeat steps ⑧ and ⑨, assemble the next secondary lining section of the arch wall from the face D to the hole, and use the longitudinal connecting bolts 51 to assemble and connect the secondary lining section of the arch wall as a whole until the assembly reaches the hole, complete Assembled construction of secondary lining of arch walls.

以上所述只是用图解说明本发明一种拱墙预制衬砌结构及施工方法 的一些原理,并非是要将本发明局限在所示和所述的具体结构和适用范围 内,故凡是所有可能被利用的相应修改以及等同物,均属于本发明所申请 的专利范围。The above is only to illustrate some principles of an arch wall prefabricated lining structure and construction method of the present invention, and it is not intended to limit the present invention to the specific structure and scope of application shown and described. The corresponding modifications and equivalents of the present invention all belong to the scope of the patent applied for by the present invention.

Claims (8)

1.一种拱墙预制衬砌结构,包括由内而外设置的初期支护结构10、防排水系统20和二次衬砌结构,二次衬砌结构由仰拱31和拱墙二次衬砌结构构成,其特征是:所述仰拱(31)沿隧道延伸方向分段连续浇筑形成;所述拱墙二次衬砌结构为钢筋混凝土预制结构,由拱墙二次衬砌节段纵向拼装而成,拱墙二次衬砌节段的环向两端与仰拱(31)的环向两端形成搭接,各拱墙二次衬砌节段由至少三块拱墙二次衬砌砌块(30)环向拼装形成。1. a prefabricated lining structure of an arch wall, comprising the initial stage support structure 10, the waterproof and drainage system 20 and the secondary lining structure that are set from the inside out, and the secondary lining structure is made up of the inverted arch 31 and the secondary lining structure of the arch wall, It is characterized in that: the inverted arch (31) is formed by continuous pouring in sections along the extension direction of the tunnel; the secondary lining structure of the arch wall is a reinforced concrete prefabricated structure, which is longitudinally assembled by the secondary lining segments of the arch wall, and the arch wall is formed. The two circumferential ends of the secondary lining segment are overlapped with the circumferential two ends of the inverted arch (31), and each arch wall secondary lining segment is circumferentially assembled by at least three arch wall secondary lining blocks (30). form. 2.如权利要求1所述的一种拱墙预制衬砌结构,其特征是:所述仰拱(31)环向端为下凹弧面,与之形成搭接的拱墙二次衬砌砌块(30)环向端为与该下凹弧面相贴合的下凸弧面,该对下凹弧面、下凸弧面之间设置纵向延伸的第二环向防水密封垫(33)。2. a kind of arch wall prefabricated lining structure as claimed in claim 1, is characterized in that: described inverted arch (31) annular end is concave arc surface, and forms the arch wall secondary lining block of overlapping connection with it (30) The annular end is a lower convex arc surface that fits with the lower concave arc surface, and a longitudinally extending second annular waterproof gasket (33) is arranged between the pair of lower concave arc surfaces and the lower convex arc surface. 3.如权利要求1所述的一种拱墙预制衬砌结构,其特征是:所述拱墙二次衬砌结构中,各相邻拱墙二次衬砌节段的拱墙二次衬砌砌块(30)按通缝拼装或者错缝拼装。3. a kind of arch wall prefabricated lining structure as claimed in claim 1 is characterized in that: in described arch wall secondary lining structure, the arch wall secondary lining blocks ( 30) Assemble according to through seam or wrong seam. 4.如权利要求1所述的一种拱墙预制衬砌结构,其特征是:所述拱墙二次衬砌节段中,相邻拱墙二次衬砌砌块(30)的环向接触面呈对应的平面或者弧面,由穿过环向连接孔的环向连接螺栓(41)将两相邻拱墙二次衬砌砌块(30)连接为一体。4. The prefabricated lining structure of an arch wall according to claim 1, characterized in that: in the secondary lining segment of the arch wall, the circumferential contact surface of the adjacent secondary lining blocks (30) of the arch wall is in the shape of a ring. For the corresponding plane or arc surface, two adjacent secondary lining blocks (30) of the arch wall are connected together by annular connecting bolts (41) passing through the annular connecting holes. 5.如权利要求4所述的一种拱墙预制衬砌结构,其特征是:所述环向接触面上设置纵向延伸的第一环向防水密封垫(32),在环向连接孔两端设置环向连接孔密封圈(52)。5. The prefabricated lining structure of an arch wall according to claim 4, characterized in that: a longitudinally extending first annular waterproof gasket (32) is arranged on the annular contact surface, at both ends of the annular connecting hole Set the annular connecting hole sealing ring (52). 6.如权利要求4所述的一种拱墙预制衬砌结构,其特征是:所述拱墙二次衬砌节段中,由穿过相邻两拱墙二次衬砌砌块(30)纵向连接孔的纵向连接螺栓(51)将相邻两拱墙二次衬砌节段拼装为一体。6. The prefabricated lining structure of an arch wall according to claim 4, characterized in that: in the secondary lining section of the arch wall, the secondary lining blocks (30) passing through two adjacent arch walls are longitudinally connected The longitudinal connecting bolts (51) of the holes assemble the secondary lining segments of two adjacent arch walls into one body. 7.如权利要求6所述的一种拱墙预制衬砌结构,其特征是:所述相邻两拱墙二次衬砌砌块(30)的纵向接触面上设置环向延伸的纵向防水密封垫(53),在纵向连接螺栓(51)的外端或者两端设置纵向连接孔密封圈(52)。7 . The prefabricated lining structure of an arch wall according to claim 6 , wherein the longitudinal contact surfaces of the secondary lining blocks ( 30 ) of the adjacent two arch walls are provided with longitudinal waterproof gaskets extending in a circumferential direction. 8 . (53), a longitudinal connecting hole sealing ring (52) is arranged on the outer end or both ends of the longitudinal connecting bolt (51). 8.如权利要求1至7任意一项所述一种拱墙预制衬砌结构的施工方法,包括如下步骤:8. the construction method of a kind of arch wall prefabricated lining structure as described in any one of claim 1 to 7, comprises the steps: ①隧道开挖掘进至掌子面(D);①The tunnel is excavated to the face (D); ②及时施作初期支护结构(10);②The initial support structure (10) shall be installed in time; ③施作防排水系统(20);③ Implement a waterproof and drainage system (20); ④滞后掌子面(D)一定距离施作仰拱(31);④ The inverted arch (31) is applied at a certain distance from the lag face (D); ⑤滞后仰拱(31)一定距离施作仰拱填充层(31a);⑤ lag the inverted arch (31) a certain distance and apply the inverted arch filling layer (31a); ⑥掌子面(D)掘进到预定位置后停止掘进,待初期支护结构(10)、防排水系统(20)、仰拱(31)及仰拱填充层(31a)施作到该位置并达到相应设计强度;⑥The tunnel face (D) is excavated to the predetermined position and then stops excavation. After the initial support structure (10), the waterproof and drainage system (20), the inverted arch (31) and the inverted arch filling layer (31a) are applied to this position and achieve the corresponding design strength; ⑦铺设拱墙二次衬砌台车走行轨道;⑦ Lay arch wall secondary lining trolley running track; ⑧在洞口完成拱墙二次衬砌节段的拼装;⑧Complete the assembly of the secondary lining segment of the arch wall at the opening; ⑨利用拱墙二次衬砌台车将一拱墙二次衬砌节段从洞口运输到掌子面位置并完成与仰拱(31)的拼装;⑨Using the secondary lining trolley of the arch wall to transport the secondary lining segment of an arch wall from the hole to the position of the tunnel face and complete the assembly with the inverted arch (31); ⑩重复步骤⑧和⑨,由掌子面(D)向洞口方向拼装下一个拱墙二次衬砌节段,并用纵向连接螺栓(51)将拱墙二次衬砌节段拼装连接为一体,直至拼装到洞口,完成拱墙二次衬砌的拼装施工。⑩ Repeat steps ⑧ and ⑨ to assemble the next secondary lining segment of the arch wall from the face (D) to the hole, and use the longitudinal connecting bolts (51) to assemble and connect the secondary lining segment of the arch wall as a whole until the assembly is completed. At the entrance of the hole, the assembly construction of the secondary lining of the arch wall is completed.
CN202010076370.9A 2020-01-23 2020-01-23 Prefabricated lining structure of arch wall and construction method Pending CN111305869A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010076370.9A CN111305869A (en) 2020-01-23 2020-01-23 Prefabricated lining structure of arch wall and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010076370.9A CN111305869A (en) 2020-01-23 2020-01-23 Prefabricated lining structure of arch wall and construction method

Publications (1)

Publication Number Publication Date
CN111305869A true CN111305869A (en) 2020-06-19

Family

ID=71150901

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010076370.9A Pending CN111305869A (en) 2020-01-23 2020-01-23 Prefabricated lining structure of arch wall and construction method

Country Status (1)

Country Link
CN (1) CN111305869A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111852519A (en) * 2020-07-15 2020-10-30 中国水利水电第四工程局有限公司 Method for installing novel inverted arch precast block capable of improving water resistance between joints
CN112253172A (en) * 2020-10-16 2021-01-22 中铁第四勘察设计院集团有限公司 Tunnel bottom lining structure with tie beam and construction method thereof
CN113153353A (en) * 2021-04-15 2021-07-23 华能煤炭技术研究有限公司 Roadway support structure in weak rock stratum and support method
CN113294175A (en) * 2021-06-03 2021-08-24 中国建筑股份有限公司 Construction method of tunnel secondary lining structure and tunnel secondary lining structure
CN114753860A (en) * 2022-05-17 2022-07-15 中铁第一勘察设计院集团有限公司 Prefabricated and cast-in-place combined drilling and blasting tunnel lining structure and construction method thereof
CN114941542A (en) * 2022-05-20 2022-08-26 中水北方勘测设计研究有限责任公司 Full-section composite lining structure suitable for open type TBM construction tunnel and construction method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2576963Y (en) * 2002-10-15 2003-10-01 甘肃工业大学 Tunnel liner prefab
CN102140920A (en) * 2011-02-10 2011-08-03 上海师范大学 Tunnel bionic reinforcement bridge
CN105484765A (en) * 2016-01-11 2016-04-13 北京市轨道交通设计研究院有限公司 Fabricated secondary lining structure of bored tunnel and construction method of fabricated secondary lining structure
CN106150519A (en) * 2016-08-10 2016-11-23 中交第二公路勘察设计研究院有限公司 A full-section prefabricated lining structure and construction method for drilling and blasting tunnels
CN107387119A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 Prefabricated assembled tunnel inverted arch, tunnel structure and its construction method
CN107939415A (en) * 2017-10-20 2018-04-20 长安大学 Stay the micro- two step constructions method of Core Soil in the soft plastic clay tunnel of Shallow-buried Large-span
CN108894796A (en) * 2018-05-21 2018-11-27 昆明理工大学 It is a kind of to use the tunnel for overlapping plate technique without template Second Lining Construction method
CN109505624A (en) * 2018-09-27 2019-03-22 中铁隧道局集团有限公司 A kind of section of jurisdiction mortise and tenon formula shield tunnel construction
CN109538238A (en) * 2018-12-07 2019-03-29 中铁四局集团有限公司 Tunnel arch prefabricated segment construction device and control method
CN209369834U (en) * 2019-01-08 2019-09-10 四川公路桥梁建设集团有限公司 Prefabricated assembled secondary lining structure of tunnel
CN110486040A (en) * 2019-07-08 2019-11-22 重庆交通大学 A kind of prefbricated tunnel lining structure for vcehicular tunnel
CN212454439U (en) * 2020-01-23 2021-02-02 中铁二院工程集团有限责任公司 Prefabricated lining structure of arch wall

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2576963Y (en) * 2002-10-15 2003-10-01 甘肃工业大学 Tunnel liner prefab
CN102140920A (en) * 2011-02-10 2011-08-03 上海师范大学 Tunnel bionic reinforcement bridge
CN105484765A (en) * 2016-01-11 2016-04-13 北京市轨道交通设计研究院有限公司 Fabricated secondary lining structure of bored tunnel and construction method of fabricated secondary lining structure
CN106150519A (en) * 2016-08-10 2016-11-23 中交第二公路勘察设计研究院有限公司 A full-section prefabricated lining structure and construction method for drilling and blasting tunnels
CN107387119A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 Prefabricated assembled tunnel inverted arch, tunnel structure and its construction method
CN107939415A (en) * 2017-10-20 2018-04-20 长安大学 Stay the micro- two step constructions method of Core Soil in the soft plastic clay tunnel of Shallow-buried Large-span
CN108894796A (en) * 2018-05-21 2018-11-27 昆明理工大学 It is a kind of to use the tunnel for overlapping plate technique without template Second Lining Construction method
CN109505624A (en) * 2018-09-27 2019-03-22 中铁隧道局集团有限公司 A kind of section of jurisdiction mortise and tenon formula shield tunnel construction
CN109538238A (en) * 2018-12-07 2019-03-29 中铁四局集团有限公司 Tunnel arch prefabricated segment construction device and control method
CN209369834U (en) * 2019-01-08 2019-09-10 四川公路桥梁建设集团有限公司 Prefabricated assembled secondary lining structure of tunnel
CN110486040A (en) * 2019-07-08 2019-11-22 重庆交通大学 A kind of prefbricated tunnel lining structure for vcehicular tunnel
CN212454439U (en) * 2020-01-23 2021-02-02 中铁二院工程集团有限责任公司 Prefabricated lining structure of arch wall

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111852519A (en) * 2020-07-15 2020-10-30 中国水利水电第四工程局有限公司 Method for installing novel inverted arch precast block capable of improving water resistance between joints
CN112253172A (en) * 2020-10-16 2021-01-22 中铁第四勘察设计院集团有限公司 Tunnel bottom lining structure with tie beam and construction method thereof
CN113153353A (en) * 2021-04-15 2021-07-23 华能煤炭技术研究有限公司 Roadway support structure in weak rock stratum and support method
CN113294175A (en) * 2021-06-03 2021-08-24 中国建筑股份有限公司 Construction method of tunnel secondary lining structure and tunnel secondary lining structure
CN113294175B (en) * 2021-06-03 2023-12-29 中国建筑股份有限公司 Construction method of tunnel secondary lining structure and tunnel secondary lining structure
CN114753860A (en) * 2022-05-17 2022-07-15 中铁第一勘察设计院集团有限公司 Prefabricated and cast-in-place combined drilling and blasting tunnel lining structure and construction method thereof
CN114753860B (en) * 2022-05-17 2024-07-16 中铁第一勘察设计院集团有限公司 Prefabricated cast-in-situ combined drilling and blasting tunnel combined lining structure and construction method thereof
CN114941542A (en) * 2022-05-20 2022-08-26 中水北方勘测设计研究有限责任公司 Full-section composite lining structure suitable for open type TBM construction tunnel and construction method

Similar Documents

Publication Publication Date Title
CN111305869A (en) Prefabricated lining structure of arch wall and construction method
CN111456759A (en) A prefabricated tunnel lining structure
CN103643966B (en) A kind of assembling tunnel lining segment
CN204609900U (en) A kind of corrugated steel preliminary bracing structure being applicable to benching tunnelling method excavation
CN111271087B (en) Construction method for arch prefabricated lining structure with post-cast strip connection
CN111878115B (en) A kind of cavity assembled tunnel inverted arch and construction method
CN104790970A (en) Method for utilizing combined structure to conduct shield tunnel strengthening
CN113294171B (en) Prefabricated tunnel lining structure combined with corrugated steel plate and UHPC and its construction method
CN106930777A (en) Construction method of prefabricated secondary lining for main line of underground excavation section of subway
CN107313455B (en) Cast-in-place and prefabricated combined single-bin comprehensive pipe gallery node and construction method
CN211648183U (en) Assembled tunnel lining structure
CN113006822A (en) Special-shaped shield segment structure penetrating through yellow land cracks and construction method thereof
CN201407054Y (en) Segment Connection Structure of Metro Shield Tunnel
CN110242313B (en) Tunnel portal sealing safety structure and construction method
CN111236965A (en) In-situ jacking and assembling construction method for fabricated tunnel lining structure
CN207161094U (en) A kind of new construction for reinforcing Existing Railway Line tunnel rhegma lining cutting
CN106337530B (en) A kind of construction of frame beam seams stifled construction method
CN111287764A (en) Tunnel secondary lining structure and construction method thereof
CN109236319B (en) Post-pouring enlarged head type ground crack area shield tunnel and construction method thereof
CN214836386U (en) A special-shaped shield constructs section of jurisdiction structure for wearing yellow land crack
CN111271078B (en) Construction method for assembling sectional longitudinal translation in prefabricated tunnel lining structure tunnel
CN212454439U (en) Prefabricated lining structure of arch wall
CN108049425A (en) A kind of pipe gallery temporary plugging wall construction and construction method
CN212898516U (en) Cavity assembled tunnel invert
CN114753860B (en) Prefabricated cast-in-situ combined drilling and blasting tunnel combined lining structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200619

RJ01 Rejection of invention patent application after publication