CN111242444A - Project progress monitoring method and system - Google Patents

Project progress monitoring method and system Download PDF

Info

Publication number
CN111242444A
CN111242444A CN202010010492.8A CN202010010492A CN111242444A CN 111242444 A CN111242444 A CN 111242444A CN 202010010492 A CN202010010492 A CN 202010010492A CN 111242444 A CN111242444 A CN 111242444A
Authority
CN
China
Prior art keywords
project
concrete
progress
data
information model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010010492.8A
Other languages
Chinese (zh)
Inventor
郭伟
方宏伟
杜会军
王宽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN202010010492.8A priority Critical patent/CN111242444A/en
Publication of CN111242444A publication Critical patent/CN111242444A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/901Indexing; Data structures therefor; Storage structures
    • G06F16/9024Graphs; Linked lists
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Databases & Information Systems (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Data Mining & Analysis (AREA)
  • Game Theory and Decision Science (AREA)
  • Software Systems (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A method and a system for monitoring engineering progress are disclosed. In an embodiment of the present application, a method for monitoring a progress of a project may include: associating a premixed concrete file of a project with a pre-established building information model, wherein the premixed concrete file comprises planned concrete pouring data of different parts in the project; acquiring actual concrete pouring data of a project site; generating a double-code network diagram by using actual concrete pouring data and planned concrete pouring data of corresponding components in the building information model; determining the progress state of the parts in the engineering by using the double-code network diagram; and visually displaying the progress state of the part in the project. The method and the device have the advantages that the dynamic progress management of the project is realized, the timeliness is good, the information integrity is strong, the accuracy is high, and related personnel can supervise and manage the implementation condition of the project conveniently according to the progress state of the project.

Description

Project progress monitoring method and system
Technical Field
The invention relates to the technical field of engineering construction, in particular to an engineering progress monitoring method and system.
Background
In the technical field of engineering at present, the project progress needs to be supervised in real time. In the related technology, a construction progress management platform based on a Building Information Model (BIM) technology is used for manually inputting the actual progress of a node, so that the input workload of field personnel is increased, on one hand, due to personnel inertia and responsibility, the situations of untimely data updating, missing report and the like are easy to occur, and on the other hand, timeliness and Information integrity are not guaranteed. In addition, after the actual progress is input into the BIM-based construction progress management platform, the management of the whole construction progress is performed on the basis of Gantt charts, although the management is visual, the identification of a key path is not obvious, the generated conclusive data reflecting the actual construction progress is low in timeliness, integrity and accuracy and lack of referential property, and company managers and project managers are likely to be misled.
Disclosure of Invention
In order to solve the technical problems, it is desirable to provide a method and a system for monitoring engineering progress, which have the advantages of good timeliness, strong information integrity and high accuracy, realize dynamic progress management of engineering, and facilitate related personnel to supervise and manage the implementation situation of the engineering according to the state of the engineering progress.
According to one aspect of the application, a project progress monitoring method is provided, which comprises the following steps:
associating a premixed concrete file of a project with a pre-established building information model, wherein the premixed concrete file comprises planned concrete pouring data of different parts in the project;
acquiring actual concrete pouring data of a project site;
generating a double-code network diagram by using actual concrete pouring data and planned concrete pouring data of corresponding components in the building information model;
determining the progress state of the parts in the engineering by using the double-code network diagram;
and visually displaying the progress state of the part in the project.
According to an aspect of the present application, there is provided a project progress monitoring system, including:
the system comprises a building information model platform, a progress state determination system and a progress state determination system, wherein the building information model platform is configured to associate a premixed concrete file of a project with a pre-established building information model, the premixed concrete file comprises planned concrete pouring data of different parts in the project, the actual concrete pouring data of a project site is obtained, and the actual concrete pouring data of the project site and the planned concrete pouring data of corresponding components in the building information model are provided for the progress state determination system; the system is configured to receive the progress state of the part in the project returned by the progress state determining system and visually display the progress state of the part in the project;
a progress status determination system configured to generate a double-code network map using actual concrete placement data and planned concrete placement data of corresponding components in the building information model, determine a progress status of a component in a project using the double-code network map, and provide the progress status of the component in the project to the building information model platform.
According to the embodiment of the application, the building information model is firstly associated with the ready-mixed concrete file, then the actual concrete pouring data of the engineering site and the planned concrete pouring data in the building information model are utilized to generate the double-code network diagram, and finally the progress states of the parts in the engineering are determined by utilizing the double-code network diagram, so that the dynamic progress management of the engineering is realized, the timeliness is good, the information integrity is strong, the accuracy is high, the reference value is high, and related personnel can conveniently supervise and manage the implementation condition of the engineering according to the progress states of the engineering.
Drawings
FIG. 1 is a schematic flow chart of a method for monitoring engineering progress according to an embodiment of the present application;
FIG. 2 is a schematic structural diagram of a project progress monitoring system according to an embodiment of the present application;
FIG. 3 is a functional diagram of an embodiment of a system for monitoring progress of a project;
fig. 4 is a schematic diagram of an exemplary specific implementation flow of engineering progress monitoring according to an embodiment of the present application.
Detailed Description
Hereinafter, embodiments of the present application will be described in detail with reference to the accompanying drawings. It should be noted that, in the present application, the embodiments and the features thereof may be arbitrarily combined with each other without conflict.
Fig. 1 shows an exemplary flow of a project progress monitoring method in an embodiment of the present application. As shown in fig. 1, an exemplary process of the project progress monitoring method in the embodiment of the present application may include:
step S101, associating a premixed concrete file of a project with a pre-established BIM, wherein the premixed concrete file comprises planned concrete pouring data of different parts in the project;
step S102, acquiring actual concrete pouring data of a project site;
step S103, generating a double-code network diagram by using the actual concrete pouring data and the planned concrete pouring data of the corresponding member in the BIM;
step S104, determining the progress state of the parts in the project by using the double-code network diagram;
and S105, visually displaying the progress state of the part in the project.
Fig. 2 shows an exemplary structure of a project progress monitoring system according to an embodiment of the present application. As shown in fig. 2, the project progress monitoring system according to the embodiment of the present application may include:
a BIM platform 21 configured to associate a premixed concrete file of a project with a previously created building information model, the premixed concrete file including planned concrete placement data of different components in the project, acquire actual concrete placement data of the project site, and provide the actual concrete placement data of the project site and the planned concrete placement data of corresponding members in the building information model to a progress status determination system; and the system is configured to receive the progress state of the part in the project returned by the progress state determining system and visually display the progress state of the part in the project.
A progress status determination system 22 configured to generate a double-code network map using the actual concrete placement data and the planned concrete placement data of the corresponding component in the building information model, determine a progress status of the component in the project using the double-code network map, and provide the progress status of the component in the project to the building information model platform.
In some examples, the above-mentioned project progress monitoring system may further include: a weighbridge weighing system 23 configured to collect actual concrete placement data at the construction site by scanning a two-dimensional code generated when the ready-mixed concrete file is generated and provide the actual concrete placement data to the building information model platform.
In the embodiment of the present application, the BIM platform 21 may communicate with the progress status determining system 22 through a data interface, and the weighbridge weighing system 23 may communicate with the BIM platform 21 through a data interface. In practical applications, the above-mentioned engineering progress monitoring system and its various parts may be implemented by an electronic device or an electronic device cluster, and the electronic device or the electronic device cluster may include but is not limited to: servers, computers, sensors, or other similar devices. Fig. 3 shows a specific functional diagram of the project progress monitoring system in the embodiment of the present application.
Before step S101, the method may further include: a BIM of the project is created. In the embodiment of the application, the BIM can be a digital expression including all geometric, physical and performance information of the building, all information related to the building is stored in a single model, and what information different project participants need to use at different project stages can be obtained from the BIM model, and the BIM includes all information of the building. Building respective BIM models in different stages and in different professions of engineering construction, including but not limited to: building models, structural models, electromechanical models, site models, construction models, as built models, and the like.
In the embodiment of the present application, there may be various ways to create the BIM. In specific application, the BIM of the project in the construction stage can be established according to engineering requirements, and detailed nodes are optimized. Specifically, when building the BIM, the engineering civil engineering model in the BIM is built by Revit software, the steel structure part is built by Tekla, all part models are integrated after being built, the parts are exported into an obj format file in a data output mode, and the integrated BIM is imported into a BIM platform.
In some examples, the names of the various components in the BIM are identical to the names of the placement locations in the ready mix concrete file.
Before step 101, the method may further include: the method comprises the steps of receiving ready-mixed concrete information input by workers, and generating a ready-mixed concrete file in a preset format and a two-dimensional code thereof, wherein the ready-mixed concrete information input by the workers is recorded in the ready-mixed concrete file and comprises the two-dimensional code. In practice, the ready-mixed concrete file may be in the form of an electronic version of the ready-mixed concrete order or the like.
Specifically, the staff can fill the premixed concrete entrustment book in a system, and automatically generate a two-dimensional code at the upper left corner of the premixed concrete entrustment book through the system, wherein the two-dimensional code contains all information in the premixed concrete entrustment book, and the method comprises the following steps: and the related information such as casting position, casting time, concrete volume, concrete label and the like. Here, the names of the pouring positions in the premixed concrete order are consistent with the names of the corresponding parts in the BIM, so that the actual pouring time of the relevant positions can be collected by scanning the two-dimensional code when the actual concrete pouring data is collected and automatically recorded into the BIM platform through the interface.
In the embodiment of the application, in order to ensure that the name of the pouring position in the premixed concrete file is consistent with the name of the corresponding component in the BIM, a naming rule can be preset in advance and configured in the BIM platform in the project start preparation stage, and the naming rule is used for naming the position when the BIM is established and the premixed concrete file is generated. In other examples, the part names may also be directly derived from the BIM, and the copied commands are used to fill in when creating the ready-mixed concrete file. The condition that the input error occurs because the punctuation coincidence does not correspond to the information in and out of the individual characters is prevented.
In practical applications, project technicians can send an electronic version of the ready-mixed concrete order to concrete mixing plant personnel as a basis for applying for concrete pouring, and the mixing plant personnel can distribute concrete according to the requirements in the ready-mixed concrete order and according to the specified time.
In step S101, the method may include: and associating the planned concrete pouring data in the ready-mixed concrete file with the components in the building information model one by one. In practical application, the intelligent association between the WBS nodes and the model can be realized by importing the premixed concrete file into the BIM platform 21, adding the WBS node name information into the model attributes to be associated, and searching the attributes, so that the planned concrete pouring data representing the project plan progress is associated with the members in the BIM one by one. Like this, carry out the intelligence with BIM and WBS node and associate the back, when typing into the actual progress of node (being actual concrete placement data) and all being automatic typing, reduced personnel and interfered to ensure that engineering progress monitoring timeliness is better, information integrality is stronger, the degree of accuracy is higher.
In step S102, the method may include: actual concrete placement data at the project site is collected by scanning a two-dimensional code, which may be generated when creating a ready-mixed concrete file. In this example, the workload of personnel and other human factors may be effectively reduced by using a weighbridge weighing system or the like to automatically collect actual concrete placement data.
In practical application, the concrete tank truck enters a project site, and is loaded on a weighbridge weighing system to obtain the weight of the entering tank truck. When concrete of a relevant part is poured, when the concrete tank truck leaves a factory, the weight of the tank truck leaving the factory is obtained, meanwhile, a scanning gun is used for scanning the filled two-dimensional code at the upper left corner of the consignment book of the premixed concrete, the BIM platform or other third-party systems can automatically input the pouring time and the pouring part of the concrete, the pouring time and the pouring part are automatically associated with the BIM in the BIM platform, the actual progress time of the BIM in the BIM platform is automatically updated, the actual progress time can be automatically and intelligently input, the workload of information technicians can be reduced, and the situations of missing report, late report and the like are effectively avoided.
In the embodiment of the present application, the planned concrete placement data or the actual concrete placement data may include one of the following data or any combination thereof: the method comprises the steps of representing a pouring position of a concrete pouring position, indicating pouring time of the concrete pouring time, concrete volume and concrete label. In particular, the present invention relates to a method for producing,
in some examples, the specific implementation process of step S102 may include: measuring the weight of an incoming tank car when the concrete tank car enters a project site and the weight of an outgoing tank car when the concrete tank car leaves the project site by a weighbridge weighing system; and scanning the two-dimensional code on the entrusted book of the ready-mixed concrete carried on the concrete tank truck by using a scanning gun, and recording the pouring position and the pouring time.
In step S104, the method may include: identifying a key path in the double-code network graph, comparing front edges, and determining the progress state of each part in the project on a key node and the total construction period, wherein the progress state can be one of the following states: advanced status and days in advance; a normal state; hysteresis status and hysteresis days. Therefore, the method and the device can identify the key path through the double-code network diagram and automatically calculate the conclusive data of the engineering construction progress through the front-line method.
In this embodiment of the present application, the progress status determining system 22 may be specifically configured to identify a critical path in the double-code network graph, perform a frontier comparison, and determine the progress status of each part in the project on a critical node and a total construction period; the progress status is one of: advanced status and days in advance; a normal state; hysteresis status and hysteresis days.
Specifically, the BIM platform 21 and the core data of the progress status determining system 22 may be docked in a data interface form, the planned concrete pouring data and the actual concrete pouring data are imported into the progress status determining system 22, the double-code network diagram is generated by the progress status determining system 22, the critical path is automatically identified, and the conclusive data reflecting the progress status is generated by a frontier comparison method.
In step S105, the advanced or delayed state and the number of days of different parts may be displayed in a form of deepening color, so as to achieve the function of three-dimensional visual early warning. For some examples, step S105 may include one or any combination of the following: 1) rendering a part in the building information model through a first set color when the progress state of the part is an advanced state; 2) when the progress state of a part is a normal state, rendering the part in the building information model through a second set color; 3) rendering a part in the building information model through a third set color when the progress state of the part is a lagging state and the lagging days are less than or equal to a preset threshold value; 4) when the progress state of a part is a lagging state and the lagging days are larger than the preset threshold value, rendering the part in the building information model through a fourth set color; wherein, the color depth of the fourth setting color can be larger than the third setting color, and/or the color depth of the third setting color can be larger than the second setting color, and/or the color depth of the second setting color can be larger than the first setting color. Therefore, the early warning device can display the early, normal and lagging states of different parts through different colors, and quickly identify different lagging days in the lagging state through the depth of the color, so as to achieve the early warning effect. By checking the color of each part in the BIM, related personnel can intuitively and clearly know the advance or delay condition of each part of the construction progress in the construction site. Particularly, the method is more visual and clear aiming at the delay condition of the key nodes of the milestone, and is convenient for managers to take corresponding measures in time, so that the aims of early warning and correcting the delay of the construction period in time are fulfilled.
For example, the first setting color may be set to "green" in advance, the second setting color may be set to "blue" in advance, the predetermined threshold may be set to n (n is an integer not less than 1 indicating the number of days), the third setting color may be set to "red", the fourth setting color may be set to "deep red", so that a component whose progress status is an advanced status will appear to be "green", a component whose progress status is a normal status (i.e., actual progress is performed according to the original progress plan) will appear to be "blue", a component whose progress status is a delayed status and the number of delayed days is less than or equal to n will appear to be "red", a component whose progress status is a delayed status and the number of delayed days is greater than n will appear to be "deep red", so that the advanced and delayed statuses are intuitively judged through the display color display of the BIM, and when the time lags for different days, the BIM model has different deepening degrees and is clear at a glance, and the function of early warning is achieved through color inspection.
In practical applications, the predetermined threshold may be freely set according to practical situations, and the predetermined threshold may be set as a fixed value (e.g., an empirical value) or may be set as a dynamically changing value, for example, the data may be dynamically adjusted based on the engineering-related information.
In the embodiment of the application, the BIM platform can also display the progress state through the data link behind the platform project list, so that managers can conveniently and visually see the progress condition of the project so as to manage the project. Or the BIM platform can display the progress status in a navigation bar in the form of an interface, so that managers such as project leaders and company leaders can conveniently view the progress status.
FIG. 4 illustrates an exemplary implementation flow of project progress monitoring. As shown in fig. 4, a specific implementation process of the engineering progress monitoring in the embodiment of the present application may include:
step S401, building a BIM of an engineering project according to engineering requirements;
step S402, writing a project schedule, and generating a ready-mixed concrete file (for example, the ready-mixed concrete order mentioned above);
S403-S404, importing the BIM and the ready-mixed concrete file into a BIM platform, and associating the planned concrete pouring data in the ready-mixed concrete file with the members in the BIM one by one;
and S405, enabling the concrete tank truck to enter a project site, automatically acquiring and inputting actual concrete pouring data of corresponding parts by scanning the two-dimensional code on the concrete pouring application form, and automatically hooking the actual concrete pouring data with corresponding BIMs in the BIM platform.
And S406-S408, importing the planned concrete pouring data and the actual concrete pouring data into a progress state determining system through a data interface, wherein the progress state determining system automatically generates a double-code network diagram and automatically identifies a key path, so that the dynamic adjustment of the key path is realized through the real-time entry of the actual progress, the progress states (including advanced, normal and lagging states) of project milestone nodes and the total construction period are judged through a frontier comparison method, the number of days in advance and the number of days behind are automatically calculated for reference of project managers, and a decision is made in time.
And step S409, the progress state determination system is linked to the BIM platform through an interface, data related to the progress state are transmitted to the BIM platform, and the BIM platform displays the corresponding progress state for company management personnel and project management personnel to refer to, so that the purpose of dynamically managing the project progress is achieved.
In the embodiment of the application, the weighbridge weighing system is used for automatically acquiring actual concrete pouring data capable of representing the actual progress of a project and transmitting the actual concrete pouring data to the BIM platform through the data interface, the BIM platform manages the actual concrete pouring data by combining a BIM model carrier and a double-code network diagram, the states (including the advanced state, the normal state and the lagging state and the corresponding days) of a milestone node and the total construction period are automatically judged by a front line comparison method, finally the advanced state, the lagging days and the like of the corresponding parts are visually displayed by different color deepening degrees of the parts in the BIM, all the actual progress data entry, the model color display, the progress state display and the like are carried out under the automatic condition, so that the progress state is intelligently monitored, the workload of personnel and other human factors are effectively reduced, and real and effective data are provided for the project department so as to guarantee the smooth completion of the construction period.
Furthermore, embodiments of the present application may further include a computer-readable storage medium having a computer program stored thereon, where the computer program, when executed by a processor, causes the processor to execute the steps in the project progress monitoring method described above in this specification.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope of the present invention are also included in the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (10)

1. A project progress monitoring method comprises the following steps:
associating a premixed concrete file of a project with a pre-established building information model, wherein the premixed concrete file comprises planned concrete pouring data of different parts in the project;
acquiring actual concrete pouring data of a project site;
generating a double-code network diagram by using actual concrete pouring data and planned concrete pouring data of corresponding components in the building information model;
determining the progress state of the parts in the engineering by using the double-code network diagram;
and visually displaying the progress state of the part in the project.
2. The method of claim 1, wherein the planned concrete placement data or the actual concrete placement data includes at least one of: pouring position, pouring time, concrete volume and concrete label.
3. The method of claim 1 or 2, wherein determining a progress status of a project using the double code network graph comprises:
identifying a key path in the double-code network graph, comparing front lines, and determining the progress state of each part in the project on key nodes and the total construction period;
the progress status is one of: advanced status and days in advance; a normal state; hysteresis status and hysteresis days.
4. The method of claim 3, wherein the progress status is visually presented, including at least one of:
rendering a part in the building information model through a first set color when the progress state of the part is an advanced state;
when the progress state of a part is a normal state, rendering the part in the building information model through a second set color;
rendering a part in the building information model through a third set color when the progress state of the part is a lagging state and the lagging days are less than or equal to a preset threshold value;
when the progress state of a part is a lagging state and the lagging days are larger than the preset threshold value, rendering the part in the building information model through a fourth set color;
wherein the color depth of the fourth setting color is greater than the third setting color, and/or the color depth of the third setting color is greater than the second setting color, and/or the color depth of the second setting color is greater than the first setting color.
5. The method of claim 1, wherein obtaining actual concrete placement data at a project site comprises:
and acquiring actual concrete pouring data of an engineering site by scanning a two-dimensional code, wherein the two-dimensional code is generated when the premixed concrete file is generated.
6. The method of claim 5, wherein collecting actual concrete placement data at the project site by scanning the two-dimensional code comprises:
measuring the weight of an incoming tank car when the concrete tank car enters a project site and the weight of an outgoing tank car when the concrete tank car leaves the project site by a weighbridge weighing system;
and scanning the two-dimensional code on the entrusted book of the ready-mixed concrete carried on the concrete tank truck by using a scanning gun, and recording the pouring position and the pouring time.
7. The method of claim 1 or 2, wherein the associating the ready-mixed concrete file of the project with the pre-created building information model comprises:
and associating the planned concrete pouring data in the ready-mixed concrete file with the components in the building information model one by one.
8. A project progress monitoring system comprising:
the system comprises a building information model platform, a progress state determination system and a progress state determination system, wherein the building information model platform is configured to associate a premixed concrete file of a project with a pre-established building information model, the premixed concrete file comprises planned concrete pouring data of different parts in the project, the actual concrete pouring data of a project site is obtained, and the actual concrete pouring data of the project site and the planned concrete pouring data of corresponding components in the building information model are provided for the progress state determination system; the system is configured to receive the progress state of the part in the project returned by the progress state determining system and visually display the progress state of the part in the project;
a progress status determination system configured to generate a double-code network map using actual concrete placement data and planned concrete placement data of corresponding components in the building information model, determine a progress status of a component in a project using the double-code network map, and provide the progress status of the component in the project to the building information model platform.
9. The system of claim 8, wherein the progress status determination system is specifically configured to: identifying a key path in the double-code network graph, comparing front lines, and determining the progress state of each part in the project on key nodes and the total construction period; the progress status is one of: advanced status and days in advance; a normal state; hysteresis status and hysteresis days.
10. The system of claim 8, further comprising:
a weighbridge weighing system configured to collect actual concrete placement data at a project site and provide the actual concrete placement data to the building information model platform by scanning a two-dimensional code generated when the ready-mixed concrete file is generated.
CN202010010492.8A 2020-01-06 2020-01-06 Project progress monitoring method and system Pending CN111242444A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010010492.8A CN111242444A (en) 2020-01-06 2020-01-06 Project progress monitoring method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010010492.8A CN111242444A (en) 2020-01-06 2020-01-06 Project progress monitoring method and system

Publications (1)

Publication Number Publication Date
CN111242444A true CN111242444A (en) 2020-06-05

Family

ID=70864842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010010492.8A Pending CN111242444A (en) 2020-01-06 2020-01-06 Project progress monitoring method and system

Country Status (1)

Country Link
CN (1) CN111242444A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113362029A (en) * 2021-06-05 2021-09-07 浙江宏诚工程咨询管理有限公司 Unmanned aerial vehicle-based project progress supervision method and device and electronic equipment
CN115526739A (en) * 2022-09-16 2022-12-27 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130155058A1 (en) * 2011-12-14 2013-06-20 The Board Of Trustees Of The University Of Illinois Four-dimensional augmented reality models for interactive visualization and automated construction progress monitoring
CN105404966A (en) * 2015-11-06 2016-03-16 中国十七冶集团有限公司 Construction method of construction process quality color rendering module based on BIM
CN110599027A (en) * 2019-09-09 2019-12-20 中铁建设集团有限公司 Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system
CN110782124A (en) * 2019-09-20 2020-02-11 中铁二十一局集团电务电化工程有限公司 BIM-based task processing method and device, server and storage medium

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130155058A1 (en) * 2011-12-14 2013-06-20 The Board Of Trustees Of The University Of Illinois Four-dimensional augmented reality models for interactive visualization and automated construction progress monitoring
CN105404966A (en) * 2015-11-06 2016-03-16 中国十七冶集团有限公司 Construction method of construction process quality color rendering module based on BIM
CN110599027A (en) * 2019-09-09 2019-12-20 中铁建设集团有限公司 Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system
CN110782124A (en) * 2019-09-20 2020-02-11 中铁二十一局集团电务电化工程有限公司 BIM-based task processing method and device, server and storage medium

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113362029A (en) * 2021-06-05 2021-09-07 浙江宏诚工程咨询管理有限公司 Unmanned aerial vehicle-based project progress supervision method and device and electronic equipment
CN115526739A (en) * 2022-09-16 2022-12-27 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision
CN115526739B (en) * 2022-09-16 2023-06-30 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision

Similar Documents

Publication Publication Date Title
US10754688B2 (en) Systems and methods of a production environment tool
Lin et al. Developing Mobile‐and BIM‐Based Integrated Visual Facility Maintenance Management System
Getuli et al. A BIM-based construction supply chain framework for monitoring progress and coordination of site activities
Su et al. Enhancing maintenance management using building information modeling in facilities management
US20130335413A1 (en) System and method for estimating construction duration
US20130246113A1 (en) Project management and measuring performance using deliverables
CN113626914A (en) Engineering project management method, device and system based on digital twins
EP0165291A1 (en) Structural graphics representation
CN114037097A (en) BIM model-based equipment operation and maintenance management method
CN111242444A (en) Project progress monitoring method and system
KR20190140759A (en) Vitual Construction Simulation Method
CN110704705A (en) Method and system for displaying project progress in real time
RU2686006C1 (en) Method and system for information modeling of business processes of a life cycle of a production facility
CN114971437B (en) Building engineering project risk assessment system and method
WO2012162736A1 (en) Construction management system and method
Peiris et al. Digitalising modular construction: Enhancement of off-site manufacturing productivity via a manufacturing execution & control (MEC) system
Chacón et al. Digital twinning of building construction processes. Case study: A reinforced concrete cast-in structure
US20140278639A1 (en) System and method for interface management
RU2755520C1 (en) Automated logistical intelligent information decision-making system in manufacturing and logistical complex
CN110472103B (en) Construction business form management method, system, storage medium and electronic terminal
AU2016202814A1 (en) Systems and methods for managing cpu usage during qualitatively assessment of task data
JP4926211B2 (en) Project management system and project management program
CN116797183B (en) Engineering progress management method, system and device based on BIM technology
Peiris et al. Digitalising Modular Construction: Action Research Study on Manufacturing Execution & Control (Mec) System to Enhance Offsite Manufacturing (Osm) Productivity
US20170270459A1 (en) Device, System, and Method for Tracking Job Management

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200605

RJ01 Rejection of invention patent application after publication