CN110472103B - Construction business form management method, system, storage medium and electronic terminal - Google Patents

Construction business form management method, system, storage medium and electronic terminal Download PDF

Info

Publication number
CN110472103B
CN110472103B CN201910641744.4A CN201910641744A CN110472103B CN 110472103 B CN110472103 B CN 110472103B CN 201910641744 A CN201910641744 A CN 201910641744A CN 110472103 B CN110472103 B CN 110472103B
Authority
CN
China
Prior art keywords
construction
business
project
visual
electronic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910641744.4A
Other languages
Chinese (zh)
Other versions
CN110472103A (en
Inventor
张海波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Landau Xinke Intelligent Technology Co ltd
Original Assignee
Beijing Landau Xinke Intelligent Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Landau Xinke Intelligent Technology Co ltd filed Critical Beijing Landau Xinke Intelligent Technology Co ltd
Priority to CN201910641744.4A priority Critical patent/CN110472103B/en
Publication of CN110472103A publication Critical patent/CN110472103A/en
Application granted granted Critical
Publication of CN110472103B publication Critical patent/CN110472103B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/901Indexing; Data structures therefor; Storage structures
    • G06F16/9017Indexing; Data structures therefor; Storage structures using directory or table look-up
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/904Browsing; Visualisation therefor
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/906Clustering; Classification
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Databases & Information Systems (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • General Engineering & Computer Science (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a construction business form management method, a system, a storage medium and an electronic terminal, wherein the method comprises the following steps: collecting all service forms required by the construction engineering; classifying the business table according to a construction object; establishing a table rule knowledge base, and establishing an association mapping relation between each type of electronic table and the classification of the constructed project, the procedures and the steps; establishing a visual business table engine, inputting the table rule knowledge base into the visual business table engine, and converting the business table into an electronic table through the visual business table engine; storing the electronic form or the form link in a visual position where the corresponding project classification, process and step are located, and visually displaying; the invention can carry out standardized management on the business form in the construction project, organically combine the business form with the specific steps, procedures and project division of construction, and carry out unified visual management on the business form in the construction industry.

Description

Construction business form management method, system, storage medium and electronic terminal
Technical Field
The invention relates to the field of buildings and computer application, in particular to a construction business form management method, a construction business form management system, a storage medium and an electronic terminal.
Background
Along with the development of economy in China, urbanization steps are faster and faster, the requirement on the construction speed of infrastructure is higher and higher, and along with the development of construction and civil engineering construction, the construction management mode, method and technology of the construction industry are continuously developed and advanced. In the process of construction project management, management modes and methods of progress, quality, cost, safety and the like are continuously innovated.
At present, in the management process of construction engineering, from project establishment to final project completion, the number of business forms is hundreds, and the traditional form filling usually adopts a manual mode, which causes a great deal of waste of manpower and material resources. However, the conventional method cannot meet the actual engineering project requirements, so that many problems occur in the management of the business table. Therefore, a new business form management method is needed to meet the actual engineering project requirements.
Disclosure of Invention
In view of the above-mentioned shortcomings of the prior art, the present invention provides a construction business form management method, system, storage medium and electronic terminal to solve the above technical problems.
The construction business form management method provided by the invention comprises the following steps:
collecting all service forms required by the construction engineering;
classifying the business table according to a construction object;
establishing a table rule knowledge base according to table parameters of the collected business table, wherein the table parameters at least comprise visualization parameters used for representing shape characteristics of the table and data logic parameters used for representing logic relations among data frames in the table;
establishing an association mapping relation between each type of spreadsheet and the classification, process and step of the constructed project;
establishing a visual business table engine, inputting the table rule knowledge base into the visual business table engine, and converting the business table into an electronic table through the visual business table engine;
and storing the electronic forms or the form links in the visual positions of the corresponding project classification, process and step for visual display.
Optionally, the form parameters further include data source parameters for representing data sources in data boxes in the electronic form, where the data sources include custom data content and reference-specific database content.
Optionally, the method further comprises the step of performing project classification on the construction projects according to the construction objects in advance;
dividing the construction process into a plurality of independent minimum movable units according to the construction action, and taking each minimum movable unit as a step;
collecting construction procedure requirement information preset by each project classification;
combining all the steps meeting the requirement information for each procedure in sequence until the configuration of all the procedures is completed to form a construction procedure of each project classification;
collecting position information of a construction object in the project classification;
and carrying out visual display on all the procedures, steps, project classification and corresponding position information.
Optionally, in the construction process, after each step is completed, the confirmation is performed through the terminal device, the step completion certification information is uploaded, and the step completion certification information is stored in the visual position where the corresponding step is located to perform visual display.
Optionally, the logic relationship between the electronic form and the step, procedure or subentry is preset, after each step, procedure or subentry is completed, the electronic form is filled in through the terminal device, the filling state of the corresponding electronic form is monitored, and the next step, procedure or subentry is triggered according to the filling state and the preset logic relationship.
The invention also provides a construction business form management system, which comprises:
the acquisition module is used for acquiring all service forms required by the construction engineering;
the classification module is used for classifying the business table according to the construction object;
the form rule knowledge base module is used for establishing a form rule knowledge base according to form parameters of the collected business forms, and the form parameters at least comprise visualization parameters used for representing form shape characteristics and data logic parameters used for representing logic relations among data frames in the forms;
the relation configuration module is used for establishing the incidence mapping relation between each type of spreadsheet and the classification of the constructed project, the working procedures and the steps;
the visual business table engine module is used for establishing a visual business table engine, inputting the table rule knowledge base into the visual business table engine and converting the business table into an electronic table through the visual business table engine;
the display module is used for carrying out visual display;
and the storage module is used for storing the electronic forms or the form links in the visualization positions of the corresponding project classifications, procedures and steps.
Optionally, the method further includes:
the terminal equipment is used for confirming after finishing one step in the construction process and uploading the step completion certification information;
the monitoring module is used for monitoring the filling state of the electronic form;
the method comprises the steps of setting logical relations between electronic forms and steps, procedures or project sub-projects in advance through a relation configuration module, filling the electronic forms through terminal equipment after each step, procedure or project sub-project is completed, monitoring filling states of the corresponding electronic forms through a monitoring module, and triggering the next step, procedure or project sub-project according to the filling states and the preset logical relations.
Optionally, the method further includes: and the authority management module is used for configuring the user roles and carrying out authentication management on the user roles filled in the form.
The invention also provides a computer-readable storage medium, on which a computer program is stored, which program, when being executed by a processor, carries out the method of any one of the above.
The present invention also provides an electronic terminal, comprising: a processor and a memory;
the memory is adapted to store a computer program and the processor is adapted to execute the computer program stored by the memory to cause the terminal to perform the method as defined in any one of the above.
The invention has the beneficial effects that: the construction business form management method, the system, the storage medium and the electronic terminal can carry out unified visual management on all construction project services in the construction industry, divide construction projects into different working procedures according to project categories, divide the working procedures into different steps, establish corresponding relations between business forms and the working procedures, do not need to manage hundreds of business forms one by one when facing different construction projects, can organically combine the business forms with the specific steps, working procedures and project sub-projects of construction, can complete filling of corresponding forms after completing the corresponding steps, working procedures or project sub-projects, enables all business forms from starting of the construction projects to finishing of the projects to be matched with the progress of construction, can complete filling of all forms when the projects are finished, and realizes standardized management on the business forms in the construction projects, greatly improving the working efficiency and reducing the waste of manpower and material resources.
Drawings
Fig. 1 is a flowchart illustrating a construction business form management method according to an embodiment of the present invention.
Detailed Description
The embodiments of the present invention are described below with reference to specific embodiments, and other advantages and effects of the present invention will be easily understood by those skilled in the art from the disclosure of the present specification. The invention is capable of other and different embodiments and of being practiced or of being carried out in various ways, and its several details are capable of modification in various respects, all without departing from the spirit and scope of the present invention. It is to be noted that the features in the following embodiments and examples may be combined with each other without conflict.
It should be noted that the drawings provided in the following embodiments are only for illustrating the basic idea of the present invention, and the components related to the present invention are only shown in the drawings rather than drawn according to the number, shape and size of the components in actual implementation, and the type, quantity and proportion of the components in actual implementation may be changed freely, and the layout of the components may be more complicated.
In the following description, numerous details are set forth to provide a more thorough explanation of embodiments of the present invention, however, it will be apparent to one skilled in the art that embodiments of the present invention may be practiced without these specific details, and in other embodiments, well-known structures and devices are shown in block diagram form, rather than in detail, in order to avoid obscuring embodiments of the present invention.
As shown in fig. 1, the method for managing a construction business form in this embodiment includes:
collecting all service forms required by the construction engineering;
classifying the business table according to a construction object;
establishing a table rule knowledge base according to table parameters of the collected business table, wherein the table parameters at least comprise visualization parameters used for representing shape characteristics of the table and data logic parameters used for representing logic relations among data frames in the table;
establishing an association mapping relation between each type of spreadsheet and the classification, process and step of the constructed project;
establishing a visual business table engine, inputting the table rule knowledge base into the visual business table engine, and converting the business table into an electronic table through the visual business table engine;
and storing the electronic forms or the form links in the visual positions of the corresponding project classification, process and step for visual display.
In this embodiment, the business form management method in the construction project mainly includes classification of business forms, setting of visualization parameters, setting of data logic parameters, and authority management. The classification of the business table may be classified according to the project, the procedure, and the step, for example, the main project is a bridge project, the detailed subdivision of the project may be performed according to the main body of the bridge project, for example, the detailed project classification includes a capping beam, a T-shaped beam, a pile foundation, a tie beam, an upright column, and the like, and after the project classification is determined, the procedure needs to be determined next, where the procedure in this embodiment refers to the sequence of construction in the construction process, for example: in order to solve the problem, in the embodiment, the working procedures are decomposed, the construction process is divided into a plurality of independent minimum movable units according to construction actions, each minimum movable unit is taken as a step, all the steps which meet the required information are combined in sequence aiming at each working procedure, until the configuration of all the working procedures is completed, the construction working procedures classified by each project are formed, and the steps in the embodiment are in the construction process, minimum active unit of work, for example: measurement of a certain position, concrete transportation, self-checking, final inspection and the like. And organically combining the steps to form a working procedure, organically combining the working procedure to form the subentry project, and finishing the whole project after finishing all the subentry projects. In the actual project, the specific division rule is project-unit project-subsection project, the subsection project is used as the minimum project unit of a project and comprises working procedures-steps, therefore, by the mode from bottom to top, the control of each link in the construction process can be realized, meanwhile, all projects can be integrated, the comprehensive management of all built projects can be realized, hundreds of business tables can be generated in the process from project starting to project completion acceptance, the tables are tables with legal effectiveness and meeting the national standards of the construction industry, but at present, a unified and standardized management mode for the business tables is not realized, the embodiment inputs the rule table knowledge base into the visual business table engine by establishing the visual business table engine, converting the business form into an electronic form through the visual business form engine; and storing the electronic forms or the form links in visual positions of corresponding project classification, working procedures and steps for visual display, thereby realizing standardized unified management of the business forms.
In this embodiment, all business forms required by a construction project are collected, the business forms are converted into spreadsheets, a mapping relationship between each spreadsheet and a corresponding step is established, and the spreadsheets or table links are stored in a visualization position where the corresponding step is located, so as to perform visualization display. In an actual engineering project, also taking a bridge engineering as an example, several hundreds of tables are required from the beginning to the end of the project to be completed and accepted, although the tables are national standard, for the same construction project, the tables are different due to different standard note tables of local governments or administrative units, at present, the traditional method is to supplement and fill the tables according to recorded data after the project is completed, and cannot be linked with the construction progress in time, in the embodiment, on one hand, a visual business table engine is established, the table rule knowledge base is input into the visual business table engine, the business table is converted into an electronic table through the visual business table engine, on the other hand, the tables can be linked with steps and procedures, and after the corresponding steps are completed, the corresponding table filling can be performed, through the visual platform, the filling condition of the form can be monitored in real time.
In this embodiment, the problem of how to convert the business form into a spreadsheet needs to be solved first, in the prior art, it is very easy to convert a business form into an electronic form, but in a construction project, the number of business forms involved is too large, if the efficiency is too low by adopting a customized mode of converting the business forms one by one, the embodiment realizes the conversion of the business forms into the electronic forms by establishing a form rule knowledge base and a visual business form engine, in the embodiment, the table rule knowledge base is established by the table parameters of the collected business table, wherein the table parameters at least comprise a visualization parameter for representing the shape characteristic of the table, a data logic parameter for representing the logic relationship between data boxes in the table and a data source parameter, the data source is used for representing data sources in a data frame in the spreadsheet, and the data sources comprise custom data contents and reference specified database contents; the shape characteristics of the form, such as the position (coordinates of a starting point and an end point), the length, the thickness and the like of a line, can be defined through the visualization parameters, and the data logic parameters can define the logic relationship between data frames of the spreadsheet and certainly also include the type of the form data. The data source parameters can define the data source, for example, if the data source of the database is the self-defined data content, manual filling is needed, if the data source refers to the specified database content, the data in the corresponding database is directly referred by the preset reference relationship, so that the form filling efficiency is greatly improved.
In this embodiment, after the problem of how to convert the business form into the spreadsheet is solved, the spreadsheet needs to be associated with steps, processes and project sub-projects in the construction process, and the spreadsheet or the form is linked and stored in the visual position where the corresponding project sub-project classification, process and step are located, so as to perform visual display, thereby achieving unified management. In this embodiment, after all the steps meeting the requirement information are combined for each process, the logical relationship between the steps in the process is preset according to the execution sequence of the construction requirements. And presetting a logical relationship among all processes according to the execution sequence of the construction requirement to complete the establishment of a visual process engine, wherein the logical relationship among the steps and the processes is defined by setting a control node, and the control node comprises logical relationship information with the next step or process. The control node may define the relation between steps or processes, for example, whether the sequence of the step or process and the next step or process may be implemented in parallel or may have to be implemented in series after the first step or process. Correspondingly, the service table may also be provided with a control node, for example: in case that the corresponding form is not filled in, the next step cannot be performed.
In this embodiment, after a step is completed, the confirmation is performed by the terminal device, the step completion certification information is uploaded, and the step completion certification information is stored in the visual position where the corresponding step is located, so as to perform visual display. For example, in the concrete pouring process, the concrete transportation process includes many steps, and for example, after the concrete transportation process is completed, the implementer of the step confirms the completion through the terminal device, takes a picture on site, and uploads the picture to the system through the terminal device, and the certification information may include other certification materials such as a seal file, and correspondingly, the certification materials are recorded and stored in a form related to the concrete transportation process. Preferably, the terminal device may adopt a smart phone, a tablet computer or other proprietary terminal devices.
Correspondingly, the embodiment further provides a construction business form management system, including:
the acquisition module is used for acquiring all service forms required by the construction engineering;
the classification module is used for classifying the business table according to the construction object;
the table engine module is used for establishing a table engine according to table parameters, converting the business table into an electronic table through the table engine, wherein the table parameters at least comprise visualization parameters for representing the shape characteristics of the table and data logic parameters for representing the logic relationship among data frames in the table;
the relation configuration module is used for establishing the incidence mapping relation between each type of spreadsheet and the classification of the constructed project, the working procedures and the steps;
the display module is used for carrying out visual display;
and the storage module is used for storing the electronic forms or the form links in the visualization positions of the corresponding project classifications, procedures and steps.
The terminal equipment is used for confirming after finishing one step in the construction process and uploading the step completion certification information;
the monitoring module is used for monitoring the filling state of the electronic form;
and the authority management module is used for configuring the user roles and carrying out authentication management on the user roles filled in the form.
In this embodiment, the relationship configuration module is used to preset a logical relationship between an electronic form and a step, a procedure, or a project, and after each step, procedure, or project is completed, the terminal device is used to fill the electronic form, and the monitoring module is used to monitor the filling state of the corresponding electronic form, and trigger the next step, procedure, or project according to the filling state and the preset logical relationship. In the embodiment, the visualization parameters, the data logic parameters and the data source parameters are input into the visualization business form engine, so that a form can be automatically converted into an electronic form.
In the embodiment, the process is formed by combining M steps, the project is formed by N processes, the construction project is formed by L projects, the construction projects are formed by J construction projects, the classified visual display is performed, the electronic map is combined, the actual geographic positions of all the projects are marked in the electronic map, and the geographic positions are distinguished to realize the platform unified management. In this embodiment, before the start of each construction project, the construction refers to the production activities at the construction implementation stage of the engineering construction, and is the construction process of various buildings, and is a process of changing various relations on the design drawing into a real object at a designated place, so that the information of the construction flow direction, the construction sequence, the construction stage division, the construction method and construction machine selection, the safe construction design, and the like, must be specified before the construction, and through the step modules in this embodiment, the construction process is divided into a plurality of independent minimum activity units according to the construction actions, each minimum activity unit is taken as a step, in the construction process at the present stage, all the processes can be divided into specific steps, and the specific steps can be basically formulated in advance, if there are no preset steps in the actual construction process, the step module in this embodiment can be used to enter new step information, so that a new process is formed through one or some new steps, and then layer-by-layer combination is performed from bottom to top, and finally a process engine is formed. The main reason that unified management cannot be achieved in the existing construction management is that each construction project is different, specific processes of the same project are different, and the steps of the same process are different.
In this embodiment, the classification items of the specific items, the information of the specific implementation positions of the processes and the steps, and the business table may be visually displayed by combining with an electronic map, for example, the existing open source map software is used to mark on the map through an electronic map module, or may be replaced by various professional electronic maps or self-developed electronic maps.
In the embodiment, all business forms required by a construction project are converted into electronic forms, the mapping relation between each electronic form and corresponding steps is established, the electronic forms or the forms are linked and stored in the visual positions of the corresponding steps for visual display, the problem that the number of the forms is excessive from starting construction to final completion acceptance of the construction project is solved, the forms are established in the corresponding relation with the steps, so that form filling operation can be performed in the process of the project, on one hand, state monitoring of the forms can be realized, on the other hand, effective reminding can be realized, when the current forms are necessary to be filled, reasonable and overall arrangement of construction can be effectively performed in the mode, and after the project is completed, all the forms are correspondingly completed, manpower and material resources are greatly saved.
The present embodiment also provides a computer-readable storage medium on which a computer program is stored, which when executed by a processor implements any of the methods in the present embodiments.
The present embodiment further provides an electronic terminal, including: a processor and a memory;
the memory is used for storing computer programs, and the processor is used for executing the computer programs stored by the memory so as to enable the terminal to execute the method in the embodiment.
The computer-readable storage medium in the present embodiment can be understood by those skilled in the art as follows: all or part of the steps for implementing the above method embodiments may be performed by hardware associated with a computer program. The aforementioned computer program may be stored in a computer readable storage medium. When executed, the program performs steps comprising the method embodiments described above; and the aforementioned storage medium includes: various media that can store program codes, such as ROM, RAM, magnetic or optical disks.
The electronic terminal provided by the embodiment comprises a processor, a memory, a transceiver and a communication interface, wherein the memory and the communication interface are connected with the processor and the transceiver and are used for completing mutual communication, the memory is used for storing a computer program, the communication interface is used for carrying out communication, and the processor and the transceiver are used for operating the computer program so that the electronic terminal can execute the steps of the method.
In this embodiment, the Memory may include a Random Access Memory (RAM), and may also include a non-volatile Memory (non-volatile Memory), such as at least one disk Memory.
The Processor may be a general-purpose Processor, and includes a Central Processing Unit (CPU), a Network Processor (NP), and the like; the Integrated Circuit may also be a Digital Signal Processor (DSP), an Application Specific Integrated Circuit (ASIC), a Field Programmable Gate Array (FPGA) or other Programmable logic device, a discrete Gate or transistor logic device, or a discrete hardware component.
In the corresponding figures of the above embodiments, the connecting lines may represent the connection relationship between the various components to indicate that more constituent signal paths (consistent _ signal paths) and/or one or more ends of some lines have arrows to indicate the main information flow direction, the connecting lines being used as a kind of identification, not a limitation on the scheme itself, but rather to facilitate easier connection of circuits or logic units using these lines in conjunction with one or more example embodiments, and any represented signal (determined by design requirements or preferences) may actually comprise one or more signals that may be transmitted in any one direction and may be implemented in any suitable type of signal scheme.
In the above-described embodiments, reference in the specification to "the embodiment," "an embodiment," "another embodiment," or "other embodiments" means that a particular feature, structure, or characteristic described in connection with the embodiments is included in at least some embodiments, but not necessarily all embodiments. The various appearances of the phrase "the present embodiment," "one embodiment," or "another embodiment" are not necessarily all referring to the same embodiment. If the specification states a component, feature, structure, or characteristic "may", "might", or "could" be included, that particular component, feature, structure, or characteristic is not necessarily included. If the specification or claim refers to "a" or "an" element, that does not mean there is only one of the element. If the specification or claim refers to "a further" element, that does not preclude there being more than one of the further element.
In the embodiments described above, although the present invention has been described in conjunction with specific embodiments thereof, many alternatives, modifications, and variations of these embodiments will be apparent to those skilled in the art in light of the foregoing description. For example, other memory structures (e.g., dynamic ram (dram)) may use the discussed embodiments. The embodiments of the invention are intended to embrace all such alternatives, modifications and variances that fall within the broad scope of the appended claims.
The embodiments in the present specification are described in a progressive manner, and the same and similar parts among the embodiments are referred to each other, and each embodiment focuses on the differences from the other embodiments. In particular, for the system embodiment, since it is substantially similar to the method embodiment, the description is simple, and for the relevant points, reference may be made to the partial description of the method embodiment.
The invention is operational with numerous general purpose or special purpose computing system environments or configurations. For example: personal computers, server computers, hand-held or portable devices, tablet-type devices, multiprocessor systems, microprocessor-based systems, set top boxes, programmable consumer electronics, network PCs, minicomputers, mainframe computers, distributed computing environments that include any of the above systems or devices, and the like.
The invention may be described in the general context of computer-executable instructions, such as program modules, being executed by a computer. Generally, program modules include routines, programs, objects, components, data structures, etc. that perform particular tasks or implement particular abstract data types. The invention may also be practiced in distributed computing environments where tasks are performed by remote processing devices that are linked through a communications network. In a distributed computing environment, program modules may be located in both local and remote computer storage media including memory storage devices.
The foregoing embodiments are merely illustrative of the principles and utilities of the present invention and are not intended to limit the invention. Any person skilled in the art can modify or change the above-mentioned embodiments without departing from the spirit and scope of the present invention. Accordingly, it is intended that all equivalent modifications or changes which can be made by those skilled in the art without departing from the spirit and technical spirit of the present invention be covered by the claims of the present invention.

Claims (10)

1. A construction business form management method is characterized by comprising the following steps:
collecting all service forms required by the construction engineering;
classifying the business table according to a construction object;
establishing a table rule knowledge base according to table parameters of the collected business table, wherein the table parameters at least comprise visualization parameters used for representing shape characteristics of the table and data logic parameters used for representing logic relations among data frames in the table;
establishing an association mapping relation between each type of spreadsheet and the classification, process and step of the constructed project;
establishing a visual business table engine, inputting the table rule knowledge base into the visual business table engine, and converting the business table into an electronic table through the visual business table engine;
and storing the electronic forms or the form links in the visual positions of the corresponding project classification, process and step for visual display.
2. The construction business form management method of claim 1, wherein the form parameters further comprise data source parameters for representing data sources within data frames in an electronic form, the data sources comprising custom data content and reference-specific database content.
3. The construction business form management method of claim 1, further comprising
Classifying construction projects according to construction processes;
collecting construction procedure requirement information preset by each project classification, and establishing a table rule knowledge base;
dividing the construction process of the construction procedure into a plurality of independent minimum movable units according to the construction action, and taking each minimum movable unit as a step;
combining all the steps meeting the requirement information for each procedure in sequence until the configuration of all the procedures is completed to form a construction procedure of each project classification;
collecting position information of a construction object in the project classification;
and carrying out visual display on all the procedures, steps, project classification and corresponding position information.
4. The construction business form management method according to claim 3, wherein in the construction process, after each step is completed, the confirmation is performed through the terminal device, the step completion certification information is uploaded, and the step completion certification information is stored in the visual position where the corresponding step is located for visual display.
5. The construction business form management method according to claim 4, wherein logical relations between the electronic form and the steps, the processes or the project sub-projects are preset, the electronic form is filled in through the terminal device after each step, process or project sub-project is completed, filling states of the corresponding electronic form are monitored, and the next step, process or project sub-project is triggered according to the filling states and the preset logical relations.
6. A construction business form management system, comprising:
the acquisition module is used for acquiring all service forms required by the construction engineering;
the classification module is used for classifying the business table according to the construction object;
the form rule knowledge base module is used for establishing a form rule knowledge base according to form parameters of the collected business forms, and the form parameters at least comprise visualization parameters used for representing form shape characteristics and data logic parameters used for representing logic relations among data frames in the forms;
the relation configuration module is used for establishing the incidence mapping relation between each type of spreadsheet and the classification of the constructed project, the working procedures and the steps;
the visual business table engine module is used for establishing a visual business table engine, inputting the table rule knowledge base into the visual business table engine and converting the business table into an electronic table through the visual business table engine;
the display module is used for carrying out visual display;
and the storage module is used for storing the electronic forms or the form links in the visualization positions of the corresponding project classifications, procedures and steps.
7. The construction business form management system of claim 6, further comprising:
the terminal equipment is used for confirming after finishing one step in the construction process and uploading the step completion certification information;
the monitoring module is used for monitoring the filling state of the electronic form;
the method comprises the steps of setting logical relations between electronic forms and steps, procedures or project sub-projects in advance through a relation configuration module, filling the electronic forms through terminal equipment after each step, procedure or project sub-project is completed, monitoring filling states of the corresponding electronic forms through a monitoring module, and triggering the next step, procedure or project sub-project according to the filling states and the preset logical relations.
8. The construction business form management system of claim 6, further comprising: and the authority management module is used for configuring the user roles and carrying out authentication management on the user roles filled in the form.
9. A computer-readable storage medium having stored thereon a computer program, characterized in that: the program when executed by a processor implements the method of any one of claims 1 to 5.
10. An electronic terminal, comprising: a processor and a memory;
the memory is for storing a computer program and the processor is for executing the computer program stored by the memory to cause the terminal to perform the method of any of claims 1 to 5.
CN201910641744.4A 2019-07-16 2019-07-16 Construction business form management method, system, storage medium and electronic terminal Active CN110472103B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910641744.4A CN110472103B (en) 2019-07-16 2019-07-16 Construction business form management method, system, storage medium and electronic terminal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910641744.4A CN110472103B (en) 2019-07-16 2019-07-16 Construction business form management method, system, storage medium and electronic terminal

Publications (2)

Publication Number Publication Date
CN110472103A CN110472103A (en) 2019-11-19
CN110472103B true CN110472103B (en) 2021-09-14

Family

ID=68508672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910641744.4A Active CN110472103B (en) 2019-07-16 2019-07-16 Construction business form management method, system, storage medium and electronic terminal

Country Status (1)

Country Link
CN (1) CN110472103B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113553680B (en) * 2021-06-22 2022-09-30 广东顺德电力设计院有限公司 Statistical editing method, system, storage medium and equipment for cable line design

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002073742A (en) * 2000-09-05 2002-03-12 Sekisui House Ltd Progress control device for building work, and method of preparing progress control chart
KR20140121145A (en) * 2013-04-05 2014-10-15 서울대학교산학협력단 BIM based Integrated Management System for Constrcution Data
CN106845919A (en) * 2016-12-16 2017-06-13 上海建工集团股份有限公司 Construction information collection processing method
CN108376376A (en) * 2018-02-02 2018-08-07 北京筑业志远软件开发有限公司 Construction engineering quality management standardized method based on BIM models
CN109829241A (en) * 2019-02-20 2019-05-31 中建一局集团第二建筑有限公司 Construction method by using management technology based on constructional engineering process data

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002073742A (en) * 2000-09-05 2002-03-12 Sekisui House Ltd Progress control device for building work, and method of preparing progress control chart
KR20140121145A (en) * 2013-04-05 2014-10-15 서울대학교산학협력단 BIM based Integrated Management System for Constrcution Data
CN106845919A (en) * 2016-12-16 2017-06-13 上海建工集团股份有限公司 Construction information collection processing method
CN108376376A (en) * 2018-02-02 2018-08-07 北京筑业志远软件开发有限公司 Construction engineering quality management standardized method based on BIM models
CN109829241A (en) * 2019-02-20 2019-05-31 中建一局集团第二建筑有限公司 Construction method by using management technology based on constructional engineering process data

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
可视化表格在群体工程工期管理中的应用;唐伟耀、刘火明、顾福明;《建筑施工》;20161025;第1473-1475页 *

Also Published As

Publication number Publication date
CN110472103A (en) 2019-11-19

Similar Documents

Publication Publication Date Title
WO2016141685A1 (en) Telecommunications engineering drawing generation method and drawing design client
CN104850596A (en) Distribution network data processing method based on mobile GIS (Geographic Information System) and RTK (Real Time Kinematic) positioning
CN109658510B (en) Substation site selection method, device and server
CN106294562A (en) A kind of electric network information methods of exhibiting and device
CN114969935B (en) Method and system for calculating capital construction graphs, electronic equipment and storage medium
CN117035691B (en) Engineering construction digital project management method and system based on BIM technology
CN111176642B (en) Interactive visualization processing system based on plane graph and application method
CN103118114A (en) BIM (building information modeling) collaborative designing system based on cloud servers
CN110880097A (en) Project progress simulation display method and device
CN108154340A (en) Prefabricated component informationization management system based on BIM cloud platforms
CN114841662A (en) Infrastructure construction project management and control method and device, computer equipment and storage medium
CN104217306A (en) Computer modeling method of full operation flow based on structuralization
CN113642850B (en) Data fusion method and terminal for power distribution network planning
CN109447466B (en) Overall process visual management and control system based on power distribution network communication network construction
CN115563341A (en) Spatial video field for electric power operation violation identification and intelligent data processing system and method thereof
CN110472103B (en) Construction business form management method, system, storage medium and electronic terminal
CN114970176A (en) Virtual simulation method and device for power operation, computer equipment and storage medium
CN114238545A (en) Two-three-dimensional park integrated display method and device and computer equipment
CN112288171A (en) Data processing method, device and system
CN216014298U (en) Building supervisory systems based on BIM
CN113126866B (en) Object determination method, device, electronic equipment and storage medium
CN115471582A (en) Map generation method and device, computer equipment and storage medium
CN107123075A (en) Road structure thing data interactive method and device
Xiao et al. Study on Construction Engineering Management Based on BIM from the perspective of big data
Jiamin et al. Application of open source GIS technology in seismic analysis and forecasting system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant