CN111236622A - Building template and assembly of building template and layering - Google Patents

Building template and assembly of building template and layering Download PDF

Info

Publication number
CN111236622A
CN111236622A CN202010227717.5A CN202010227717A CN111236622A CN 111236622 A CN111236622 A CN 111236622A CN 202010227717 A CN202010227717 A CN 202010227717A CN 111236622 A CN111236622 A CN 111236622A
Authority
CN
China
Prior art keywords
wall
layering
base
rigid coupling
horizontal pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010227717.5A
Other languages
Chinese (zh)
Other versions
CN111236622B (en
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Guanghe New Material Technology Co.,Ltd.
Original Assignee
Cao Xiaoai
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cao Xiaoai filed Critical Cao Xiaoai
Priority to CN202010227717.5A priority Critical patent/CN111236622B/en
Publication of CN111236622A publication Critical patent/CN111236622A/en
Application granted granted Critical
Publication of CN111236622B publication Critical patent/CN111236622B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/02Forming boards or similar elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)
  • Finishing Walls (AREA)

Abstract

The invention discloses a building template and an assembly of the building template and a pressing strip, which comprises plates, coatings, the pressing strip and clamping grooves, wherein the coatings are sprayed on the upper surfaces and the lower surfaces of the two plates, the pressing strip is attached to the top end of each plate, the clamping grooves are formed in the pressing strip, and a connecting mechanism is arranged in the pressing strip. This assembly of building templates and layering, through the montant, the pull ring, the dop, the cooperation of spout and baffle etc. is used, change traditional threaded connection mode, easy to assemble, and then increase the practicality of whole mechanism, through the protective case, a spring, the horizontal pole, the cooperation of cardboard etc. is used, make frid and riser pass through the horizontal pole and link together, and is simple in operation, high durability and convenient use, through the base, the through-hole, rubber circle and the cooperation of even board etc. are used, connect the base on the building body surface through the through-hole, install panel again, the convenience is fixed to panel, the user demand to building templates and layering in the life is greatly improved.

Description

Building template and assembly of building template and layering
Technical Field
The invention relates to the technical field of building templates, in particular to a building template and an assembly of the building template and a pressing strip.
Background
The building template is a temporary supporting structure, which is manufactured according to the design requirement, so that a concrete structure and a component are formed according to the specified position and the geometric dimension, the correct position of the concrete structure and the component is kept, the self weight of the building template and the external load acting on the building template are borne, the purpose of template engineering is realized, the quality and the construction safety of a concrete engineering are ensured, the construction progress is accelerated, and the engineering cost is reduced.
Disclosure of Invention
The invention aims to provide a building template and an assembly of the building template and a pressing strip, and aims to solve the problem that the practicability of the whole mechanism is reduced because the pressing strip is fixed on the template directly by using screws and is inconvenient to disassemble in the prior building template and the assembly of the building template and the pressing strip in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a building template and an assembly of the building template and a pressing strip comprise plates, coatings, the pressing strip and clamping grooves, wherein the coatings are sprayed on the upper surfaces and the lower surfaces of the two plates, the pressing strip is attached to the top ends of the plates, the clamping grooves are formed in the pressing strip, and a connecting mechanism is arranged in the pressing strip;
the connecting mechanism comprises a vertical rod, a pull ring, a clamping head, a sliding groove and a baffle plate;
the top rigid coupling of montant has the pull ring, the outer wall and the draw-in groove clearance fit of pull ring, the outer wall and the layering clearance fit of montant, the bottom rigid coupling of montant has the dop, the spout has been seted up to the outer wall of dop, the outer wall rigid coupling of montant has the baffle.
Preferably, the outer wall of panel is equipped with the backing plate, the outer wall of backing plate passes through bolt and panel threaded connection, the one end rigid coupling that the panel was kept away from to the backing plate has the U-shaped board, the bottom rigid coupling of layering has the frid.
Preferably, the outer wall of the groove plate is provided with a fixing mechanism;
the fixing mechanism comprises a protective shell, a cross rod, a clamping plate and a spring;
two the outer wall of protective case all with frid looks rigid coupling, the horizontal pole has been cup jointed to the inside of protective case, horizontal pole and protective case clearance fit, the outer wall rigid coupling of horizontal pole has the cardboard, the outer wall and the protective case clearance fit of cardboard, the spring has been cup jointed to the outer wall of horizontal pole, spring and horizontal pole clearance fit, the one end and the protective case of spring are laminated mutually, the other end and the cardboard of spring are laminated mutually.
Preferably, the protective shell is arranged perpendicular to the groove plate.
Preferably, the bottom end of the U-shaped plate is provided with a mounting mechanism;
the mounting mechanism comprises a base, a through hole, a rubber ring, a vertical plate and a connecting plate;
the through-hole has all been seted up at both ends about the base, the outer wall of base has cup jointed the rubber circle, rubber circle and base clearance fit, the upper surface rigid coupling of base has the riser, two the inside recess of riser all with horizontal pole clearance fit, the upper surface rigid coupling of base has even board, two the outer wall and the U-shaped board clearance fit of even board.
Preferably, the risers are symmetrically distributed about the base.
Compared with the prior art, the invention has the beneficial effects that: this building templates and assembly of layering compare traditional technique, have following advantage:
1. this assembly of building templates and layering uses through the cooperation of montant, pull ring, dop, spout and baffle etc. and the montant drives the dop and moves down in the layering, and the horizontal pole moves in the protective housing along the spout, rotates the pull ring and makes the horizontal pole card at the upper surface of dop, changes traditional threaded connection mode, and is easy to assemble, and then increases whole mechanism's practicality.
2. This building templates and assembly of layering use through the cooperation of backing plate, bolt, U-shaped seat and frid etc. and use the bolt to install the backing plate at the lateral wall of panel, and the convenience is favorable to using widely to the connection of panel.
3. This building templates and assembly of layering use through the cooperation of protecting crust, spring, horizontal pole, cardboard etc. and during the horizontal pole inserted the riser in the top under the spring action of spring, make frid and riser pass through the horizontal pole and link together easy operation, convenient to use.
4. This building templates and assembly of layering uses through the cooperation of base, through-hole, rubber circle and even board etc. and connects the base on the building body surface through the through-hole, installs panel again, and the convenience is fixed to panel, improves the user demand to building templates and layering in the life greatly.
5. This building templates and assembly of building templates and layering, when needs use the layering to link together two panels, at first use two bolted connection on the lateral wall of panel with the backing plate, insert the U-shaped board with the base together with the tie plate afterwards, the rubber circle is laminated with two panels mutually this moment, then insert between two risers with the layering that has the frid, promote the montant downwards in the layering, the montant drives two horizontal poles of dop oppression and moves in the spout, the horizontal pole atress removes in the protective housing, the horizontal pole drives the cardboard and compresses the spring in the protective housing, meanwhile the horizontal pole runs through the protective housing and enters into the recess of riser, and then realize being connected between base and the riser.
6. This building templates and assembly of layering drive the horizontal pole under the spring force effect of spring and push into in the recess between dop and the riser, and the baffle presses the upper surface at the protecting crust, rotates the pull ring and drives the montant and rotate in the layering, and the montant drives the dop simultaneously and rotates, and positional deviation appears with the spout in two horizontal poles, and then connects the layering on the upper surface of panel.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of a connecting structure of the connecting mechanism and the pressing bar in FIG. 1;
FIG. 3 is a schematic view of the connection structure between the fixing mechanism and the trough plate in FIG. 1;
FIG. 4 is a schematic view of the connection structure between the mounting mechanism and the U-shaped seat in FIG. 1;
FIG. 5 is a schematic view of a connection structure between the backing plate and the plate in FIG. 1;
fig. 6 is a schematic view of the connection structure between the connection mechanism and the fixing mechanism in fig. 1.
In the figure: 1. the plate comprises a plate body, 2, paint, 3, a batten, 4, a clamping groove, 5, a connecting mechanism, 501, a vertical rod, 502, a pull ring, 503, a clamping head, 504, a sliding groove, 505, a baffle, 6, a fixing mechanism, 601, a protective shell, 602, a cross rod, 603, a clamping plate, 604, a spring, 7, an installation mechanism, 701, a base, 702, a through hole, 703, a rubber ring, 704, a vertical plate, 705, a connecting plate, 8, a base plate, 9, a bolt, 10, a U-shaped plate, 11 and a groove plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-6, the present invention provides a technical solution: the utility model provides a building templates and assembly of layering, including panel 1, coating 2, layering 3 and draw-in groove 4, two upper surface and the lower surface of panel 1 all spray paint 2, panel 1 is the building templates, the laminating of the top of panel 1 has layering 3, draw-in groove 4 has been seted up to the inside of layering 3, the internally mounted of layering 3 has coupling mechanism 5, coupling mechanism 5 includes montant 501, pull ring 502, dop 503, spout 504 and baffle 505, the top rigid coupling of montant 501 has pull ring 502, pull ring 502 drives montant 501 to remove in layering 3, the outer wall and the 4 clearance fit of draw-in groove of pull ring 502, the outer wall and the 3 clearance fit of layering of montant 501, the bottom rigid coupling of montant 501 has dop 503, spout 504 has been seted up to the outer wall of dop 503, dop 503 is semi-circular, the outer wall rigid.
The outer wall of panel 1 is equipped with backing plate 8, and the outer wall of backing plate 8 passes through bolt 9 and 1 threaded connection of panel, and bolt 9 connects backing plate 8 at the lateral wall of panel 1, and the one end rigid coupling that panel 1 was kept away from to backing plate 8 has U-shaped board 10, and the bottom rigid coupling of layering 3 has frid 11.
Fixed establishment 6 is installed to the outer wall of frid 11, fixed establishment 6 includes protecting casing 601, horizontal pole 602, cardboard 603 and spring 604, the outer wall of two protecting casings 601 all with frid 11 looks rigid coupling, horizontal pole 602 has been cup jointed to the inside of protecting casing 601, horizontal pole 602 drives cardboard 603 and removes in protecting casing 601 and compress spring 604, horizontal pole 602 and protecting casing 601 clearance fit, the outer wall rigid coupling of horizontal pole 602 has cardboard 603, the outer wall and the protecting casing 601 clearance fit of cardboard 603, the outer wall of horizontal pole 602 has cup jointed spring 604, spring 604 and horizontal pole 602 clearance fit, the one end and the protecting casing 601 of spring 604 are laminated mutually, the other end and the cardboard 603 of spring 604 are laminated mutually, horizontal pole 502 inserts in the recess of riser 704, protecting casing 601 sets up with frid 11 is perpendicular.
Installation mechanism 7 is installed to U-shaped plate 10's bottom, installation mechanism 7 includes base 701, through-hole 702, rubber circle 703, riser 704 and even board 705, through-hole 702 has all been seted up at both ends about base 701, base 701's outer wall has cup jointed rubber circle 703, be connected base 701 and the external world through-hole 702, rubber circle 703 and base 701 clearance fit, base 701's upper surface rigid coupling has riser 704, two riser 704's inside recess all with horizontal pole 602 clearance fit, base 701's upper surface rigid coupling has even board 705, two outer walls and the U-shaped plate 10 clearance fit that link board 705, riser 704 is about base 701 symmetric distribution, install two riser 704 on base 701's top.
In this example, when two plates 1 need to be connected together by using the bead 3, the backing plate 8 is first connected to the side walls of the plates 1 by using two bolts 9, then the base 701 and the connecting plate 705 are inserted into the U-shaped plate 10, at this time, the rubber ring 703 is attached to the two plates 1, then the bead 3 with the groove plate 11 is inserted between the two vertical plates 704, the vertical rod 501 is pushed downwards in the bead 3, the vertical rod 501 drives the clip 503 to press the two cross rods 602 to move in the sliding groove 504, the cross rod 602 is forced to move in the protective shell 601, the cross rod 602 drives the clip 603 to compress the spring 604 in the protective shell 601, meanwhile, the cross rod 602 penetrates through the protective shell 601 to enter the groove of the vertical plate 704, thereby realizing the connection between the base 701 and the vertical plate 704, the cross rod 602 is driven to be pushed into the groove between the clip 503 and the vertical plate 501 under the elastic force of the spring 604, and the baffle 505 is pressed on the upper surface, the vertical rod 501 is driven to rotate in the pressing strip 3 by rotating the pull ring 502, meanwhile, the vertical rod 501 drives the chuck 503 to rotate, and the two cross rods 602 and the sliding groove 504 have position deviation, so that the pressing strip 3 is connected to the upper surface of the plate 1.
In the description of the present invention, it is to be understood that the terms "coaxial", "bottom", "one end", "top", "middle", "other end", "upper", "one side", "top", "inner", "front", "center", "both ends", and the like, indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be construed as limiting the present invention.
In the present invention, unless otherwise expressly specified or limited, the terms "mounted," "disposed," "connected," "secured," "screwed" and the like are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; the terms may be directly connected or indirectly connected through an intermediate, and may be communication between two elements or interaction relationship between two elements, unless otherwise specifically limited, and the specific meaning of the terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides an assembly of building templates and layering, includes panel (1), coating (2), layering (3) and draw-in groove (4), two the upper surface and the lower surface of panel (1) all spray paint (2), the top laminating of panel (1) has layering (3), draw-in groove (4), its characterized in that have been seted up to the inside of layering (3): a connecting mechanism (5) is arranged in the pressing bar (3);
the connecting mechanism (5) comprises a vertical rod (501), a pull ring (502), a clamping head (503), a sliding groove (504) and a baffle plate (505);
the top rigid coupling of montant (501) has pull ring (502), the outer wall and draw-in groove (4) clearance fit of pull ring (502), the outer wall and layering (3) clearance fit of montant (501), the bottom rigid coupling of montant (501) has dop (503), spout (504) have been seted up to the outer wall of dop (503), the outer wall rigid coupling of montant (501) has baffle (505).
2. The building panel and batten assembly according to claim 1, wherein: the outer wall of panel (1) is equipped with backing plate (8), the outer wall of backing plate (8) passes through bolt (9) and panel (1) threaded connection, the one end rigid coupling that panel (1) were kept away from in backing plate (8) has U-shaped board (10), the bottom rigid coupling of layering (3) has frid (11).
3. The building template and the assembly of building templates and battens as claimed in claim 2, wherein: the outer wall of the groove plate (11) is provided with a fixing mechanism (6);
the fixing mechanism (6) comprises a protective shell (601), a cross rod (602), a clamping plate (603) and a spring (604);
two the outer wall of protective case (601) all with frid (11) looks rigid coupling, horizontal pole (602) have been cup jointed to the inside of protective case (601), horizontal pole (602) and protective case (601) clearance fit, the outer wall rigid coupling of horizontal pole (602) has cardboard (603), the outer wall and the protective case (601) clearance fit of cardboard (603), spring (604) have been cup jointed to the outer wall of horizontal pole (602), spring (604) and horizontal pole (602) clearance fit, the one end and the protective case (601) of spring (604) are laminated mutually, the other end and cardboard (603) of spring (604) are laminated mutually.
4. The building template and batten assembly according to claim 3, wherein: the protective shell (601) is perpendicular to the groove plate (11).
5. The building template and the assembly of building templates and battens as claimed in claim 2, wherein: the bottom end of the U-shaped plate (10) is provided with an installation mechanism (7);
the mounting mechanism (7) comprises a base (701), a through hole (702), a rubber ring (703), a vertical plate (704) and a connecting plate (705);
through-hole (702) have all been seted up at both ends about base (701), rubber circle (703) have been cup jointed to the outer wall of base (701), rubber circle (703) and base (701) clearance fit, the upper surface rigid coupling of base (701) has riser (704), two the inside recess of riser (704) all with horizontal pole (602) clearance fit, the upper surface rigid coupling of base (701) has even board (705), two the outer wall and the U-shaped board (10) clearance fit of even board (705).
6. The building template and batten assembly according to claim 5, wherein: the risers (704) are symmetrically distributed about the base (701).
CN202010227717.5A 2020-03-27 2020-03-27 Building template and assembly of building template and layering Active CN111236622B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010227717.5A CN111236622B (en) 2020-03-27 2020-03-27 Building template and assembly of building template and layering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010227717.5A CN111236622B (en) 2020-03-27 2020-03-27 Building template and assembly of building template and layering

Publications (2)

Publication Number Publication Date
CN111236622A true CN111236622A (en) 2020-06-05
CN111236622B CN111236622B (en) 2021-08-27

Family

ID=70873857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010227717.5A Active CN111236622B (en) 2020-03-27 2020-03-27 Building template and assembly of building template and layering

Country Status (1)

Country Link
CN (1) CN111236622B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112431403A (en) * 2020-12-22 2021-03-02 陈晓芳 Building template of quick detach formula aluminum alloy
CN113513158A (en) * 2021-08-24 2021-10-19 广东奕佳建设工程有限公司 Building template connecting method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3048009A3 (en) * 2016-02-23 2017-08-25 Flores Garcia Claudia MOLD SYSTEM FOR THE FORMATION OF MONOLITHIC CONCRETE ELEMENTS
CN206859678U (en) * 2017-07-02 2018-01-09 焦作大学 A kind of civil engineering building template link
CN207092544U (en) * 2017-08-14 2018-03-13 李明宏 New civil engineering formwork connection device
CN107825681A (en) * 2017-12-20 2018-03-23 中山市雅乐思商住电器有限公司 Mold closing sequence control mechanism
CN108049630A (en) * 2018-01-26 2018-05-18 成都魔童童工业设计有限公司 A kind of civil engineering work formwork connection device
CN208235954U (en) * 2018-05-24 2018-12-14 杨玉龙 Civil engineering building template attachment device
CN209669970U (en) * 2019-02-17 2019-11-22 青岛瑞安建工集团有限公司 A kind of building machinery with offset hopper rear wall
CN209874485U (en) * 2019-01-31 2019-12-31 肖曼 Building templates link for civil engineering
CN210013480U (en) * 2019-05-27 2020-02-04 周爱国 Civil engineering building templates link

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3048009A3 (en) * 2016-02-23 2017-08-25 Flores Garcia Claudia MOLD SYSTEM FOR THE FORMATION OF MONOLITHIC CONCRETE ELEMENTS
CN206859678U (en) * 2017-07-02 2018-01-09 焦作大学 A kind of civil engineering building template link
CN207092544U (en) * 2017-08-14 2018-03-13 李明宏 New civil engineering formwork connection device
CN107825681A (en) * 2017-12-20 2018-03-23 中山市雅乐思商住电器有限公司 Mold closing sequence control mechanism
CN108049630A (en) * 2018-01-26 2018-05-18 成都魔童童工业设计有限公司 A kind of civil engineering work formwork connection device
CN208235954U (en) * 2018-05-24 2018-12-14 杨玉龙 Civil engineering building template attachment device
CN209874485U (en) * 2019-01-31 2019-12-31 肖曼 Building templates link for civil engineering
CN209669970U (en) * 2019-02-17 2019-11-22 青岛瑞安建工集团有限公司 A kind of building machinery with offset hopper rear wall
CN210013480U (en) * 2019-05-27 2020-02-04 周爱国 Civil engineering building templates link

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112431403A (en) * 2020-12-22 2021-03-02 陈晓芳 Building template of quick detach formula aluminum alloy
CN112431403B (en) * 2020-12-22 2022-01-18 中铁建工集团有限公司 Building template of quick detach formula aluminum alloy
CN113513158A (en) * 2021-08-24 2021-10-19 广东奕佳建设工程有限公司 Building template connecting method
CN113513158B (en) * 2021-08-24 2024-06-04 广州和铭建设有限公司 Building template connection method

Also Published As

Publication number Publication date
CN111236622B (en) 2021-08-27

Similar Documents

Publication Publication Date Title
CN111236622B (en) Building template and assembly of building template and layering
CN209742174U (en) Mounting structure of curtain
CN210216980U (en) Aluminium alloy section with decorative panel
CN218920358U (en) Solar photovoltaic module frame
CN210888068U (en) Combined building template
CN214364526U (en) Detachable indoor stair for architecture
CN213174339U (en) Aluminum veneer convenient to installation
CN216288395U (en) Fastener for power electronic module
CN212089130U (en) Novel article carrier
CN217325817U (en) Movable house plate convenient to assemble for house
CN211007424U (en) High-efficient panel installation fastener
CN212464363U (en) Special solid wheel subassembly of sprinkling irrigation equipment
CN216276859U (en) Safe and stable's frame I shape connecting piece of climbing
CN212613240U (en) Aluminum veneer with clamping groove structure
CN112431403B (en) Building template of quick detach formula aluminum alloy
CN211859187U (en) Combined type cabinet frame for power distribution cabinet
CN216476978U (en) Composite glass partition wall section bar fast-assembling structure
CN215563397U (en) Corner connector for light steel building
CN213174383U (en) Adapter of decorative panel for curtain wall
CN215634209U (en) Multifunctional rod piece equipment fixing locker
CN215631764U (en) Prefabricated hollow slab for fabricated building
CN216077826U (en) Positioning and stabilizing combined frame for aluminum oxide conveying equipment
CN221002478U (en) Upper opening aluminum frame structure for mutually buckling and installing U-shaped glass component
CN215167995U (en) Corrosion-resistant building template with connecting piece
CN212836668U (en) Non-deforming PE plastic building template

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20210809

Address after: 043000 intersection of Jiangting 2nd Road and Tongyi street, Houma Development Zone, Houma City, Linfen City, Shanxi Province

Applicant after: Shanxi Guanghe New Material Technology Co.,Ltd.

Address before: 030000 No.31, Xinlan Road, Jiancaoping District, Taiyuan City, Shanxi Province

Applicant before: Cao Xiaoai

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant