CN111231076B - Stone mattress template device - Google Patents

Stone mattress template device Download PDF

Info

Publication number
CN111231076B
CN111231076B CN202010067913.0A CN202010067913A CN111231076B CN 111231076 B CN111231076 B CN 111231076B CN 202010067913 A CN202010067913 A CN 202010067913A CN 111231076 B CN111231076 B CN 111231076B
Authority
CN
China
Prior art keywords
bolster
fixing
fixing plates
template
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010067913.0A
Other languages
Chinese (zh)
Other versions
CN111231076A (en
Inventor
刘启亮
李荐
杨贝贝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Haiwei Engineering Construction Co Ltd of FHEC of CCCC
Original Assignee
CCCC First Highway Engineering Co Ltd
Haiwei Engineering Construction Co Ltd of FHEC of CCCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, Haiwei Engineering Construction Co Ltd of FHEC of CCCC filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN202010067913.0A priority Critical patent/CN111231076B/en
Publication of CN111231076A publication Critical patent/CN111231076A/en
Application granted granted Critical
Publication of CN111231076B publication Critical patent/CN111231076B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/22Moulds for making units for prefabricated buildings, i.e. units each comprising an important section of at least two limiting planes of a room or space, e.g. cells; Moulds for making prefabricated stair units
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Moulds, Cores, Or Mandrels (AREA)

Abstract

The invention provides a bolster template device, which relates to the technical field of prefabricated bent caps, and comprises two first fixing plates which are arranged side by side and vertically, wherein at least one pair of second fixing plates are vertically arranged between the two first fixing plates; each pair of second fixing plates and the two first fixing plates form a locating frame for locating the pouring position of the filler stone. According to the first fixing plate of the bolster template device, which is provided by the invention, the first fixing plate can be moved on the prefabricated capping beam, when the bolster is poured on the prefabricated capping beam, the first fixing plate can be repeatedly moved to adjust the position of the pre-poured bolster, and the positions of each pair of second fixing plates and the first fixing plate are relatively fixed, so that the adjustment of the spacing distance between the bollards is also completed when the pouring position of the bollards is adjusted through the first fixing plates, and the pre-burying or bar planting of the bollards is not needed, so that the deviation of the pouring position of the bollards caused by insufficient precision of pre-burying or bar planting is avoided, and the problem of correcting the pouring position through later adjustment is also avoided.

Description

Stone mattress template device
Technical Field
The invention relates to the technical field of prefabricated bent caps, in particular to a filler stone template device.
Background
The prior art needs pre-buried bars or embedded bars for positioning and fixing, when the bolster and the bent cap are poured together, positioning bars and template fixing bars are welded on the bent cap bars, then templates are installed, and concrete is poured.
The method has the problems that the positioning accuracy of the poured filler is not high, and the later adjustment is not easy.
Disclosure of Invention
The invention aims to provide a bolster template device so as to solve the technical problem that the bolster positioning accuracy is insufficient when the bolster is poured at present.
The invention provides a stone padding template device, which comprises two first fixing plates which are arranged side by side and vertically, wherein at least one pair of second fixing plates are vertically arranged between the two first fixing plates;
Each pair of second fixing plates and the two first fixing plates form a positioning frame for positioning the pouring position of the filler stone;
And a bolster template assembly for pouring bolster is arranged in the positioning frame.
Further, connecting pieces with side dies of the prefabricated bent cap are arranged at two ends of the first fixing plate.
Further, the connecting piece is a C-shaped buckle, and a locking bolt for locking is arranged on the connecting piece.
Further, the locating frame is formed by the first fixing plate and the second fixing plate to four side walls, and locating bolts for adjusting and fixing the positions of the filler template components are arranged on the side walls.
Further, the positioning bolts are correspondingly arranged relative to the side walls.
Further, the bolster template assembly includes a bolster template body and a clamp, the clamp sleeve being disposed outside the bolster template body.
Further, the bolster template assembly further includes a plurality of wedge-shaped fastening blocks, the tips of which are inserted between the clip and the bolster template body.
Further, each pair of the second fixing plates is detachably connected with the first fixing plate.
Further, the first fixing plate is provided with a plurality of adjusting holes for being connected with the second fixing plate.
Further, two pairs of second fixing plates are arranged between the two first fixing plates.
According to the first fixing plate of the bolster template device, which is provided by the invention, the first fixing plate can be moved on the prefabricated capping beam, when the bolster is poured on the prefabricated capping beam, the first fixing plate can be repeatedly moved to adjust the position of the pre-poured bolster, and the positions of each pair of second fixing plates and the first fixing plate are relatively fixed, so that the adjustment of the spacing distance between the bollards is also completed when the pouring position of the bollards is adjusted through the first fixing plates, and the pre-burying or bar planting of the bollards is not needed, so that the deviation of the pouring position of the bollards caused by insufficient precision of pre-burying or bar planting is avoided, and the problem of correcting the pouring position through later adjustment is also avoided.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings that are needed in the description of the embodiments or the prior art will be briefly described, and it is obvious that the drawings in the description below are some embodiments of the present invention, and other drawings can be obtained according to the drawings without inventive effort for a person skilled in the art.
Fig. 1 is a schematic structural diagram of a bolster plate apparatus according to an embodiment of the present invention;
Fig. 2 is a schematic view of another angle structure of a bolster plate apparatus according to an embodiment of the present invention.
Icon: 100-a first fixing plate; 200-a second fixing plate; 300-a bolster template body; 400-clamping hoop; 500-wedge-shaped fastening blocks; 600-positioning bolts; 700-connection piece.
Detailed Description
The technical solutions of the present invention will be clearly and completely described in connection with the embodiments, and it is apparent that the described embodiments are some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
As shown in fig. 1 and 2, the present invention provides a stone template device, which comprises two first fixing plates 100 arranged side by side and vertically, and at least one pair of second fixing plates 200 arranged vertically between the two first fixing plates 100;
Each pair of second fixing plates 200 and the two first fixing plates 100 form a positioning frame for positioning a laying position of the stone;
And a bolster template assembly for pouring bolster is arranged in the positioning frame.
In some embodiments, the bolster is positioned on the prefabricated capping beam, and after the prefabricated capping beam is generally poured, the bolster is poured on the prefabricated capping beam; two first fixed plates 100 placed side by side and vertically can be used for enabling the positioning frame to move to the pouring position of the filler stone after being arranged on the prefabricated bent cap, pouring is carried out after the filler stone template assembly is installed in the installation frame, and before pouring, the pouring positions can be adjusted simply and conveniently.
In the prior art, positioning steel bars and template fixing bars are welded on steel bars of a bent cap, and then a template is installed for pouring concrete; and after the template is installed, if the pouring position is found to deviate, the pouring position is not easy to adjust.
The bolster template device does not need template fixing ribs, and is convenient for adjusting the position of the bolster template assembly in the later period.
Further, on the basis of the above embodiment, the first fixing plate 100 is provided at both ends with a connection member 700 to the side form of the prefabricated capping beam.
The first fixing plate 100 is connected with the side form of the prefabricated capping beam through the connecting piece 700, so that the fixing of the position of the bolster template device is realized, and the influence of the movement of the bolster template device on the pouring accuracy when the bolster is poured is avoided.
In order to better connect the bolster template device with the side mold of the prefabricated capping beam, further, the connecting piece 700 is a C-shaped buckle, and a locking bolt for locking is arranged on the connecting piece 700.
The connecting piece 700 is C type knot, and the lower extreme of connecting piece 700 is connected with the side form of prefabricated bent cap, and the other end passes through the locking bolt and locks first fixed plate 100 to make the one end of first fixed plate 100 fix on the side form of prefabricated bent cap, the side form of the equal prefabricated bent cap in both ends of first fixed plate 100 is connected, thereby makes the filler template device fixed in position.
Further, based on the above embodiment, the positioning frame is formed by the first fixing plate 100 and the second fixing plate 200 into four side walls, and positioning bolts 600 for adjusting and fixing the positions of the stone template assembly are disposed on the side walls.
The bolster template assembly is located in the locating frame, a certain distance is reserved between the bolster template assembly and the side wall of the locating frame, in order to locate the bolster pouring position more accurately, the position of the bolster template assembly in the locating frame is adjusted through the locating bolt 600 and fixed, the position of the bolster template assembly is accurately adjusted again through the locating bolt 600, and therefore the accuracy of the bolster pouring position is higher.
Be provided with the screw hole on the lateral wall of locating frame, locating bolt 600 is located the screw hole, makes the length of the part of locating bolt 600 in deep into the locating frame adjust through rotatory locating bolt 600, and four locating bolts 600 mutually support, make the filler block module be located the position of treating pouring the filler block, improve the accuracy of pouring.
In order to make the movement of the bolster plate assembly in the positioning frame smoother and less prone to tilting, further, positioning bolts 600 are correspondingly arranged with respect to the side walls.
The positioning bolts 600 are generally arranged at the middle part of the side wall, each positioning bolt 600 can enable the bolster template to generate force moving towards the opposite side wall, and the bolster template assembly is located at the pouring position of the bolster through the mutual matching of the four positioning bolts 600, so that the poured bolster is more accurate.
Further, based on the above embodiment, the bolster template assembly includes a bolster template body 300 and a clip 400, and the clip 400 is sleeved outside the bolster template body 300.
In order to enable the bolster template assembly to keep a fixed shape when the bolster is poured, a clamp 400 is sleeved outside the bolster template assembly, and the firmness of the whole bolster template assembly is increased.
Further, based on the above embodiment, the packing stone form assembly further includes a plurality of wedge-shaped fastening blocks 500, the tips of the wedge-shaped fastening blocks 500 being inserted between the clip 400 and the packing stone form body 300.
When the bolster template device is used for pouring the bolster, the functions of positioning and serving as a template are required to be repeatedly disassembled, and the bolster template device has enough strength and can be conveniently and repeatedly disassembled.
A certain gap is formed between the clip 400 and the bolster template body 300, so that the clip 400 can be conveniently sleeved outside the bolster template body 300 and removed from the bolster template body 300.
In order to enable the clip 400 to cut the fixing effect to the stone template body 300, a wedge-shaped fastening block 500 is provided between the clip 400 and the stone template body 300, and the tip of the wedge-shaped fastening block 500 is inserted between the clip 400 and the stone template body 300 from the top down, and a plurality of wedge-shaped fastening blocks 500 are provided between the clip 400 and the stone template body 300 for firmly fixing the clip 400 outside the stone template body 300.
Further, based on the above embodiment, each pair of the second fixing plates 200 is detachably connected to the first fixing plate 100.
In order to enable the bolster template device to adapt to pouring of the bolsters on the prefabricated bent caps of different specifications, the second fixing plates 200 are detachably connected with the first fixing plates 100, different second fixing plates 200 are replaced, and different positioning frames are formed so as to position the bolsters of different specifications on different prefabricated bent caps.
Further, based on the above embodiment, the first fixing plate 100 is provided with a plurality of adjustment holes for connection with the second fixing plate 200.
The first fixing plate 100 is provided with a plurality of adjustment holes, and the second fixing plate 200 is fixed at the adjustment holes of the first fixing plate 100 by bolts; due to the fact that the plurality of adjusting holes are formed in the first fixing plate 100, the installation position of the second fixing plate 200 on the first fixing plate 100 can be adjusted at will, and therefore the position of the locating frame and the distance between the adjacent locating frames can be adjusted, and the requirements of pouring of the filler stones on various prefabricated bent caps can be met.
The first fixing plate 100 and the second fixing plate 200 are connected by using bolts, so that the later disassembly and assembly are convenient, and the prefabricated cover beams can be repeatedly applied to the stones with different specifications of the prefabricated cover beams with the same specification.
Further, based on the above embodiment, two pairs of second fixing plates 200 are disposed between the two first fixing plates 100.
A plurality of packing stones may be provided on the prefabricated capping beam, but two packing stones are generally provided in the width direction of the prefabricated capping beam, that is, two pairs of second fixing plates 200 are provided between two first fixing plates 100, as required.
A plurality of packing stones may be provided in the width direction of the prefabricated capping beam, that is, the second fixing plates 200 having the same number of pairs as the packing stones are provided between the two first fixing plates 100.
According to the first fixing plate 100 of the bolster template device provided by the invention, the first fixing plate 100 can be moved on the prefabricated capping beam, when the bolster is poured on the prefabricated capping beam, the first fixing plate 100 can be repeatedly moved to adjust the position of the pre-poured bolster, and the positions of each pair of second fixing plates 200 and the first fixing plate 100 are relatively fixed, so that the adjustment of the spacing distance between the bolsters is also completed when the pouring position of the bolster is adjusted through the first fixing plate 100, and the pouring of the bolster does not need embedding or bar planting, so that the deviation of the pouring position of the bolster caused by insufficient accuracy of embedding or bar planting is avoided, and the problem of correcting the pouring position through later adjustment is also avoided.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solution of the present invention, and not for limiting the same; although the invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some or all of the technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit of the invention.

Claims (8)

1. The bolster template device is characterized by comprising two first fixing plates which are arranged side by side and vertically, wherein at least one pair of second fixing plates are vertically arranged between the two first fixing plates;
Each pair of second fixing plates and the two first fixing plates form a positioning frame for positioning the pouring position of the filler stone;
a bolster template assembly for pouring bolster is arranged in the positioning frame;
connecting pieces connected with side dies of the prefabricated bent cap are arranged at two ends of the first fixing plate;
The locating frame is formed by the first fixing plate and the second fixing plate to four side walls, and locating bolts for adjusting and fixing the positions of the filler template components are arranged on the side walls.
2. The bolster template device of claim 1, wherein the connector is a C-clip, and a locking bolt for locking is provided on the connector.
3. The bolster plate apparatus of claim 1, wherein the locating bolts are disposed opposite the side walls.
4. The bolster plate apparatus of claim 1, wherein the bolster plate assembly includes a bolster plate body and a clamp, the clamp sleeve being disposed outside the bolster plate body.
5. The bolster plate apparatus of claim 4 wherein the bolster plate assembly further comprises a plurality of wedge-shaped fastening blocks,
The tip of the wedge-shaped fastening block is inserted between the clamp and the bolster template body.
6. The bolster plate apparatus of claim 1, wherein each pair of the second fixture plates is detachably connected to the first fixture plates.
7. The bolster plate apparatus of claim 6, wherein the first fixed plate is provided with a plurality of adjustment holes for connection with the second fixed plate.
8. The bolster template apparatus of claim 1, wherein two pairs of second fixation plates are disposed between two of the first fixation plates.
CN202010067913.0A 2020-01-20 2020-01-20 Stone mattress template device Active CN111231076B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010067913.0A CN111231076B (en) 2020-01-20 2020-01-20 Stone mattress template device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010067913.0A CN111231076B (en) 2020-01-20 2020-01-20 Stone mattress template device

Publications (2)

Publication Number Publication Date
CN111231076A CN111231076A (en) 2020-06-05
CN111231076B true CN111231076B (en) 2024-05-17

Family

ID=70878096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010067913.0A Active CN111231076B (en) 2020-01-20 2020-01-20 Stone mattress template device

Country Status (1)

Country Link
CN (1) CN111231076B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115262394A (en) * 2022-02-23 2022-11-01 中国五冶集团有限公司 Method for erecting rapid supporting and detaching template for bridge pad stone

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202064278U (en) * 2011-02-11 2011-12-07 沧州路桥工程公司 Pre-buried steel plate localizator for bridge padstone
CN203866708U (en) * 2014-02-24 2014-10-08 吴洪 Support pad stone formwork
CN205242276U (en) * 2015-12-25 2016-05-18 北京市政建设集团有限责任公司 Base stone template structure
CN107030862A (en) * 2016-12-30 2017-08-11 中铁四局集团第四工程有限公司 Pier shaft pinner embedded hole hole-forming device
CN206438413U (en) * 2017-01-07 2017-08-25 中铁十五局集团第五工程有限公司 Bridge pier pinner preformed hole alignment system
CN206448177U (en) * 2017-01-23 2017-08-29 中铁二局第四工程有限公司 A kind of bridge pinner fixture components
CN107988919A (en) * 2018-01-04 2018-05-04 中铁八局集团第三工程有限公司 A kind of and the pinner and pre-embedded bolt hole forming equipment of bridge pier cap synchronous construction
CN208219413U (en) * 2017-09-08 2018-12-11 无锡市交通工程有限公司 A kind of bridge pad pinner adjustable template device
CN110485302A (en) * 2019-08-13 2019-11-22 中铁广州工程局集团第三工程有限公司 A kind of bridge pier cap and pinner concrete synchronous construction method
CN211541689U (en) * 2020-01-20 2020-09-22 中交一公局集团有限公司 Template device for cushion stone

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2330911B1 (en) * 2008-02-01 2010-09-22 Compact-Habit, S.L. PROCEDURE AND INSTALLATION FOR THE MANUFACTURE OF PRISMATIC MODULAR ELEMENTS HOLLOW CONCRETE CONCRETE AND ELEMENT OBTAINED THROUGH THESE.

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202064278U (en) * 2011-02-11 2011-12-07 沧州路桥工程公司 Pre-buried steel plate localizator for bridge padstone
CN203866708U (en) * 2014-02-24 2014-10-08 吴洪 Support pad stone formwork
CN205242276U (en) * 2015-12-25 2016-05-18 北京市政建设集团有限责任公司 Base stone template structure
CN107030862A (en) * 2016-12-30 2017-08-11 中铁四局集团第四工程有限公司 Pier shaft pinner embedded hole hole-forming device
CN206438413U (en) * 2017-01-07 2017-08-25 中铁十五局集团第五工程有限公司 Bridge pier pinner preformed hole alignment system
CN206448177U (en) * 2017-01-23 2017-08-29 中铁二局第四工程有限公司 A kind of bridge pinner fixture components
CN208219413U (en) * 2017-09-08 2018-12-11 无锡市交通工程有限公司 A kind of bridge pad pinner adjustable template device
CN107988919A (en) * 2018-01-04 2018-05-04 中铁八局集团第三工程有限公司 A kind of and the pinner and pre-embedded bolt hole forming equipment of bridge pier cap synchronous construction
CN110485302A (en) * 2019-08-13 2019-11-22 中铁广州工程局集团第三工程有限公司 A kind of bridge pier cap and pinner concrete synchronous construction method
CN211541689U (en) * 2020-01-20 2020-09-22 中交一公局集团有限公司 Template device for cushion stone

Also Published As

Publication number Publication date
CN111231076A (en) 2020-06-05

Similar Documents

Publication Publication Date Title
US7500617B2 (en) Screw device for high-adjusting a track span
CN111231076B (en) Stone mattress template device
CN208347302U (en) The high-supported formwork structure integrally formed for concrete frame floor and beam
ZA200505623B (en) Screw device for high-adjusting a track span
CN107988919B (en) Packing stone and pre-buried bolt hole forming device for synchronous construction with bridge pier caps
CN216682712U (en) Adjustable prefabricated component beam steel bar pre-pricking jig frame
CN211541689U (en) Template device for cushion stone
KR102179294B1 (en) Transformable formwork apparatus and method for manufacturing concrete precast wall
JP2005180172A (en) Form element for circular form
CN206721587U (en) Groove profile rail adjuster at a kind of plate stitch
CN108708292A (en) A kind of I-shaped steel reinforced concrete combination beam concrete folding constructing device and construction method
CN208343138U (en) A kind of concrete mats block shaping device
CN215055310U (en) Adjustable steel column mold
CN211775790U (en) Square cylinder template reinforcing apparatus
CN110080273A (en) The method for carrying out the installation of steel construction foundation bolt using flitch
CN206448177U (en) A kind of bridge pinner fixture components
CN210173840U (en) Shear wall wallboard mould
CN211440465U (en) Steel pipe sleeper mould convenient to steel pipe location is pour
CN220266319U (en) Four-corner leveling bolt shaping steel mould
CN207314062U (en) A kind of complete frock of III plate-type unballasted track bed plates of CRTS construction
CN106481074A (en) Cast-in-situ concrete beam die clamper and concrete cast-in-situ beam mould
CN220747729U (en) Shaping die for mounting foundation bolts
CN111677003A (en) Template quick detach bearing structure of subway station
CN215518375U (en) Cantilever positioning and adjusting die carrier for wing plate of precast beam
CN105201205B (en) A kind of minor diameter high-fineness ratio clear-water concrete bundle pillar formwork structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant