CN111173315A - Climb tower crane pedestrian access structure on frame - Google Patents

Climb tower crane pedestrian access structure on frame Download PDF

Info

Publication number
CN111173315A
CN111173315A CN202010117898.6A CN202010117898A CN111173315A CN 111173315 A CN111173315 A CN 111173315A CN 202010117898 A CN202010117898 A CN 202010117898A CN 111173315 A CN111173315 A CN 111173315A
Authority
CN
China
Prior art keywords
tower crane
keel
plate
climbing frame
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010117898.6A
Other languages
Chinese (zh)
Inventor
魏冬
刘青
杨博文
全祥文
谢枫云
王杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority to CN202010117898.6A priority Critical patent/CN111173315A/en
Publication of CN111173315A publication Critical patent/CN111173315A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G27/00Temporary arrangements for giving access from one level to another for men or vehicles, e.g. steps, ramps
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • E04G21/3209Temporary tunnels specially adapted against falling objects

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ladders (AREA)

Abstract

The invention discloses a pedestrian passage structure of a tower crane on a climbing frame, which comprises an integral type lifting climbing frame arranged on one side of the tower crane, wherein a keel plate is fixedly connected to one side of the integral type lifting climbing frame close to the tower crane, a hanging ring is welded at the outer end of the keel plate, a cross keel is fixed above the keel plate on the integral type lifting climbing frame, the lower end of a steel wire rope is connected with the hanging ring, the upper end of the steel wire rope is fixed with the cross keel in a pulling mode, a turning plate is hinged to the outer end of the keel plate, and the turning plate is erected on a standard section of the tower crane after being unfolded. According to the invention, the pedestrian passage of the tower crane is arranged on the integral type lifting climbing frame, and can be lifted along with the lifting of the integral type lifting climbing frame, so that a worker is prevented from building the pedestrian passage of the tower crane for many times when the worker is at high altitude, the problems of complicated process of building the pedestrian passage of the tower crane for many times at high altitude and the like are solved, the safety and reliability of the pedestrian passage of the tower crane are improved, the risk and time of climbing a vertical ladder by a driver are reduced, and the working efficiency is improved.

Description

Climb tower crane pedestrian access structure on frame
Technical Field
The invention relates to a pedestrian passageway structure of a tower crane on a climbing frame, belonging to the technical field of building construction.
Background
At present, along with the change of modern science and technology, a large number of new processes and new equipment appear in the rapid development process of the building industry in China, a tower crane is indispensable large-scale equipment on a construction site, and a tower body can rise along with the rise of the building height due to the fact that the building height breaks through the new height continuously at present. The vertical ladder that the driver about the tower crane need be taken from the tower crane body in the middle of from the vertical ladder climbing bare-handed climbing, has very big potential safety hazard, especially meets under the circumstances such as sleet weather, severe cold weather, the ladder bench freezes, moist, and the driver receives the influence of many factors such as climatic conditions, self health and mental condition, climbs the in-process about and very easily causes the incident. The interim passageway of current tower crane generally adopts the steel pipe to set up, and the passageway is usually selected in adhering to a position, and the steel pipe sets up safe passage's main shortcoming is: the channel needs to be erected for many times along with the rising of the tower body and the height of the floor, and meanwhile, the channel needs to be erected in the high altitude, so that certain safety risks exist.
Disclosure of Invention
The invention aims to provide a pedestrian passageway structure of a tower crane on a climbing frame, which has the advantages of simple structure, convenience in installation, safety and reliability, solves the problems of complicated procedures for multiple high-altitude erection of the pedestrian passageway on the tower crane and the like, improves the safety and reliability of the pedestrian passageway on the tower crane, and reduces the height and the up-down time for climbing the vertical ladder by a tower crane.
In order to achieve the purpose, the invention adopts the following technical scheme: the utility model provides a climb frame and go up pedestrian's access structure of tower crane, climbs the frame including the integral promotion that sets up in tower crane one side, climbs the frame at integral promotion and is close to one side fixedly connected with keel plate of tower crane, has rings in keel plate's outer end welding, lies in keel plate top and is fixed with cross keel on integral promotion climbs the frame, wire rope's lower extreme and rings be connected, wire rope's upper end and cross keel drawknot are fixed, have at keel plate's outer end hinged joint and turn over the board, turn over and set up on the standard of tower crane festival after the board expandes.
Furthermore, vertical keels are fixedly installed on two sides of the keel plate, and safety meshes are erected on the vertical keels.
Further, the cross keel is fixed on a walkway plate of the integral type lifting climbing frame.
Furthermore, skirting boards and protective nets are installed on two sides of the turning plate.
Due to the adoption of the technical scheme, the invention has the following advantages: according to the invention, the pedestrian passage of the tower crane is arranged on the integral type lifting climbing frame, and can be lifted along with the lifting of the integral type lifting climbing frame, so that a worker is prevented from building the pedestrian passage of the tower crane for many times when the worker is at high altitude, the problems of complicated process of building the pedestrian passage of the tower crane for many times at high altitude and the like are solved, the safety and reliability of the pedestrian passage of the tower crane are improved, the risk and time of climbing a vertical ladder by a driver are reduced, and the working efficiency is improved.
Drawings
FIG. 1 is a schematic structural diagram of the present invention.
Description of reference numerals: the method comprises the following steps of 1-keel plate, 2-hanging ring, 3-turning plate, 4-skirting board, 5-vertical keel, 6-protective net, 7-safety net piece, 8-steel wire rope, 9-horizontal keel, 10-integral lifting climbing frame and 11-tower crane standard knot.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The embodiment of the invention comprises the following steps: please refer to fig. 1, a pedestrian passageway structure of a tower crane on a climbing frame comprises an integral lifting climbing frame 10 arranged on one side of the tower crane, a keel plate 1 is fixedly connected on one side of the integral lifting climbing frame 10 close to the tower crane, a hanging ring 2 is welded on the outer end of the keel plate 1, a cross keel 9 is fixed above the keel plate 1 on the integral lifting climbing frame 10, the lower end of a steel wire rope 8 is connected with the hanging ring 2, the upper end of the steel wire rope 8 is fixed with the cross keel 9 in a pulling manner, a turning plate 3 is hinged to the outer end of the keel plate 1, and the turning plate 3 is erected on a standard joint 11 of the tower crane after being unfolded. The keel plate is characterized in that vertical keels 5 are fixedly arranged on two sides of the keel plate 1, and safety meshes 7 are erected on the vertical keels 5. The cross keel 9 is fixed on the walkway plate of the integral type lifting climbing frame 10. Skirting boards 4 and protective nets 6 are arranged on two sides of the turning plate 3.
The main structure height can constantly rise in the construction city, and the integral tower crane pedestrian passageway that promotes on climbing frame 10 also can rise along with integral promotion climbing frame 10 risees and rise, will turn over board 3 and draw in when integral promotion climbing frame 10 risees, will turn over board 3 and open when needs use, makes it fall on tower crane standard festival 11, like this alright climb and establish tower crane pedestrian passageway between frame 10 and the tower crane in integral promotion, be convenient for the driver gets into on the tower crane.
In conclusion, the tower crane pedestrian passage is arranged on the integral type lifting climbing frame 10 and can be lifted along with the lifting of the integral type lifting climbing frame 10, so that a worker is prevented from building the tower crane pedestrian passage for multiple times when the worker is high, the problems that the process of building the tower crane pedestrian passage for multiple times is complicated and the like are solved, the safety and reliability of the tower crane pedestrian passage are improved, the risk and time of climbing a vertical ladder by a driver are reduced, and the working efficiency is improved.

Claims (4)

1. The utility model provides a climb frame and go up tower crane pedestrian access structure, climbs frame (10) including the integral promotion that sets up in tower crane one side, its characterized in that: one side fixedly connected with keel plate (1) that is close to the tower crane in integral promotion climbing frame (10), the welding has rings (2) in the outer end of keel plate (1), lies in keel plate (1) top and is fixed with horizontal keel (9) on integral promotion climbing frame (10), the lower extreme and rings (2) of wire rope (8) be connected, the upper end and horizontal keel (9) drawknot of wire rope (8) are fixed, have in the outer end hinged joint of keel plate (1) and turn over board (3), set up on tower crane standard festival (11) after turning over board (3) expand.
2. The climbing tower crane pedestrian passageway structure of claim 1, characterized in that: the keel plate is characterized in that vertical keels (5) are fixedly mounted on two sides of the keel plate (1), and safety meshes (7) are erected on the vertical keels (5).
3. The climbing tower crane pedestrian passageway structure of claim 1, characterized in that: the cross keel (9) is fixed on the walkway plate of the integral type lifting climbing frame (10).
4. The climbing tower crane pedestrian passageway structure of claim 1, characterized in that: skirting boards (4) and protective nets (6) are arranged on two sides of the turning plate (3).
CN202010117898.6A 2020-02-25 2020-02-25 Climb tower crane pedestrian access structure on frame Pending CN111173315A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010117898.6A CN111173315A (en) 2020-02-25 2020-02-25 Climb tower crane pedestrian access structure on frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010117898.6A CN111173315A (en) 2020-02-25 2020-02-25 Climb tower crane pedestrian access structure on frame

Publications (1)

Publication Number Publication Date
CN111173315A true CN111173315A (en) 2020-05-19

Family

ID=70651467

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010117898.6A Pending CN111173315A (en) 2020-02-25 2020-02-25 Climb tower crane pedestrian access structure on frame

Country Status (1)

Country Link
CN (1) CN111173315A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113044741A (en) * 2021-04-02 2021-06-29 浙江城建建设集团有限公司 Safety channel for connecting integrated climbing frame and tower crane and lifting method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009023077A1 (en) * 2007-08-13 2009-02-19 Richard Hayes Stairtower and method for erecting the same
KR20090025737A (en) * 2007-09-07 2009-03-11 (주)대진가설산업 A prefabricated foothold
CN203429783U (en) * 2013-07-25 2014-02-12 中国建筑第八工程局有限公司 Tower crane driver high-altitude walking passageway
CN106437153A (en) * 2016-08-08 2017-02-22 中建四局第三建筑工程有限公司 Telescopic and transferrable crane climbing passageway for tower crane driver
CN108750970A (en) * 2018-06-07 2018-11-06 重庆工业职业技术学院 A kind of tower crane occasional passage and its installation method
CN212002458U (en) * 2020-02-25 2020-11-24 中建四局第一建筑工程有限公司 Climb tower crane pedestrian passageway on frame

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009023077A1 (en) * 2007-08-13 2009-02-19 Richard Hayes Stairtower and method for erecting the same
KR20090025737A (en) * 2007-09-07 2009-03-11 (주)대진가설산업 A prefabricated foothold
CN203429783U (en) * 2013-07-25 2014-02-12 中国建筑第八工程局有限公司 Tower crane driver high-altitude walking passageway
CN106437153A (en) * 2016-08-08 2017-02-22 中建四局第三建筑工程有限公司 Telescopic and transferrable crane climbing passageway for tower crane driver
CN108750970A (en) * 2018-06-07 2018-11-06 重庆工业职业技术学院 A kind of tower crane occasional passage and its installation method
CN212002458U (en) * 2020-02-25 2020-11-24 中建四局第一建筑工程有限公司 Climb tower crane pedestrian passageway on frame

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113044741A (en) * 2021-04-02 2021-06-29 浙江城建建设集团有限公司 Safety channel for connecting integrated climbing frame and tower crane and lifting method thereof
CN113044741B (en) * 2021-04-02 2023-12-01 浙江城建建设集团有限公司 Safety channel for connecting integrated climbing frame and tower crane and lifting method thereof

Similar Documents

Publication Publication Date Title
CN105226560B (en) A kind of crossing frame and its construction method
CN212002458U (en) Climb tower crane pedestrian passageway on frame
CN111608382A (en) Temporary attachment device for climbing frame in free area
CN111173315A (en) Climb tower crane pedestrian access structure on frame
CN106655009A (en) Hydraulic lifting type crossing structure
CN206664894U (en) One kind auxiliary hatch board middle hinge latch mounting operation platform
CN208918231U (en) A kind of safe and stable type welding operating platform for steel column top
CN204629405U (en) Navigational lighting aid tower fragile stem jacking system
CN107128808A (en) The harbour gantry of Da Jian sightseeing towers
CN105932601A (en) Method for repairing break strand of overhead ground wire
CN205892416U (en) Communication tower with operating system
CN203569906U (en) Anti-sliding device of canopy sloping roof without column
CN203361737U (en) Electric power tower facilitating overhauling
CN202745356U (en) Hydraulic climb material platform
CN207553565U (en) A kind of crosshead of truss
CN107795185A (en) Chimney reinforces pylon high-altitude installation node security construction method
CN207296349U (en) Steel stove shell installation flashing, wind proofing structure
CN203802994U (en) Combined type safety belt with double protection functions
CN101560826A (en) Elevation type tail water overhauling platform and manufacturing method and application thereof
CN103899078B (en) Attachment automatic lifting protecting screen mounting method
CN107270253A (en) A kind of elevating mechanism of construction illumination lamp
CN207776393U (en) Lighting roof steel construction operating platform
CN209778232U (en) Self-elevating gantry lifter
CN207890940U (en) A kind of derrick tower based on engineering mechanics
CN219012007U (en) Temporary protection device for large-gradient overhanging roof modeling eave

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination