Prior art keywords
submodule
management
module
company
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911305114.6A
Other languages
Chinese (zh)
Inventor
邹凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Cheng'an Times Fire Technology Co Ltd
Original Assignee
Guangdong Cheng'an Times Fire Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Cheng'an Times Fire Technology Co Ltd filed Critical Guangdong Cheng'an Times Fire Technology Co Ltd
Priority to CN201911305114.6A priority Critical patent/CN111160854A/en
Publication of CN111160854A publication Critical patent/CN111160854A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the field of block chains, and discloses a building engineering management system which protects a login interface unit, a home page unit, a system setting unit, an honest and safe person center unit, an honest and safe headquarter unit and an honest and safe construction unit which are connected with each other; the login interface unit is used for logging in the building engineering management system by inputting a user name and a password; the home page unit is used for displaying all functions through a home page menu bar and displaying tasks to be handled, specific number and attendance conditions in the month through a home page; the Chengan people center unit is used for realizing administrative, expense, character and personal information functions; the honesty and security headquarter unit is used for realizing the management of a human resource center, a financial center, a cost center, a supplier center and a cause development center; the honesty construction unit is used for realizing operation type and collection type management. The invention provides a traceability-based block chain management method, which is suitable for the management process and rule of an enterprise, realizes ordered collaboration, realizes all-round management of projects, improves the management capability of the enterprise, and has a traceability function.

Description

Construction engineering management system
Technical Field
The invention relates to the field of block chains, in particular to a building engineering management system.
Background
The construction project management system surrounds the core business of the construction enterprises, and realizes the informatization of the construction enterprise management through the digitization and the networking of the construction sites. The enterprise can realize the informatization management of project personnel, materials, mechanical equipment, subcontracting, contracts, construction data, finance and processes. The informatization of the domestic existing construction enterprises is not enough, and the management process and the management rules suitable for the enterprises do not exist, so that the orderly cooperation can not be realized, the construction enterprises are not favorable for carrying out all-round management on all projects, and the management capability of the enterprises is influenced. In addition, at present, there is no building engineering project management system using the blockchain technology, and there is no traceability function, such as: the installation time, place, and installation structure of the equipment installer cannot be tracked, and the manufacturer, quality, and life of the material cannot be tracked.
Disclosure of Invention
The technical problem to be solved by the present invention is to provide a building engineering management system with a tracing function based on a block chain, which is suitable for the management process and rule of an enterprise, realizes ordered collaboration, realizes all-round management of projects, and improves the management capability of the enterprise, aiming at the above defects of the prior art.
The technical scheme adopted by the invention for solving the technical problems is as follows: constructing a construction engineering management system comprising:
a login interface unit: the system is used for logging in the construction engineering management system by inputting a user name and a password;
a home page unit: the system is used for displaying all functions through a home page menu bar and displaying tasks to be handled, specific number and attendance conditions in the month through a home page;
a system setting unit: the system is used for realizing position management;
honesty and peaceful people center unit: the system is used for realizing the functions of administration, expense, person and personal information;
integrity bureau unit: for implementing management of human resources centers, financial centers, cost centers, supplier centers, and career development centers;
honesty and peaceful construction unit: the method is used for realizing operation type and collection type management;
the login interface unit, the home page unit, the system setting unit, the honest and safe people center unit, the honest and safe headquarter unit and the honest and safe construction unit are connected with one another.
In the construction engineering management system of the present invention, the system setting unit further includes:
the position management module: the system is used for editing the existing positions, checking the authority matched with the positions, modifying the names of the positions, starting and stopping the positions, selecting the corresponding authority for the positions to be used, and setting the authority for the positions.
In the construction engineering management system of the present invention, the honesty and safe people center unit further includes:
administrative management module: the management function is used for realizing the integrity standard, the leave-on bar, the notice or announcement, the address list and the application for the field work;
the fee management module: the management function is used for realizing sealing application, expense application and article purchasing;
the task class management module: the management function is used for realizing backlogs, transacted items, task management, task report and honesty and safe dreams;
a personal information module: the system is used for checking personal related information, positions, time of employment, contract time, superior and affiliated company conditions, and can also check personal salary details in each month;
the administrative management module, the expense management module, the task management module and the personal information module are connected with one another.
In the construction engineering management system according to the present invention, the administrative management module further includes:
an honest standard submodule: the system is used for uploading the system, standard, contract and specification of the company;
leave asking function submodule: the system is used for applying for leave by employees of the company, filling leave-applying time, days and reasons, submitting a walk-applying and examining and approving process, corresponding posts correspond to corresponding examining and approving processes, and binding a superior leader and a superior company for the positions;
a first notification advertisement submodule: the system is used for uploading the notice or announcement of the company, and the staff can check the notice sent by the name of the company;
the address list submodule: the address book is used for updating, downloading, printing and checking the address book;
an external application submodule: the system is used for applying for field work and checking field staff;
the honesty and security standard submodule, the leave asking function submodule, the notice and announcement submodule, the address list submodule and the outwork application submodule are connected with one another.
In the construction project management system according to the present invention, the fee class management module further includes:
a stamping application submodule: the system is used for applying for stamping, and can check the progress of the process, download stamping contents and print a stamping application form;
a charge application submodule: the system is used for applying for the application fee, walking the relevant application flow and completing examination and approval for printing;
an article purchasing submodule: the system is used for carrying out purchasing application of administrative goods, walking a purchasing process of sporadic materials, clicking for adding, filling related information, clicking for adding at the material bill, filling purchasing information, walking an approval process after filling, finishing clicking for downloading and printing after approval, and generating the material bill;
the stamping application submodule, the expense application submodule and the article purchasing submodule are connected with one another.
In the construction engineering management system of the present invention, the task class management module further includes:
a backlog submodule: for presenting items to be processed;
transacted items submodule: for viewing the approved item;
and the task management submodule is used for: the system is used for issuing work tasks and setting related responsibility persons and time nodes;
task report submodule: the system is used for checking the work task management and completion conditions of the current month, the previous month and the next month of each company and each department;
cheng' an Meng submodule: the system is used for checking the completion condition at the end of the year according to the life target and the work target determined in the beginning of the year;
the backlog submodule, the transacted item submodule, the task management submodule, the task report submodule and the honesty and dream submodule are connected with each other.
In the building engineering management system of the present invention, the integrity bureau unit further includes:
manpower resource center module: the system is used for realizing personnel management, company record, department record, target management and card punching address management;
financial center module: the system is used for realizing personnel cost collection, material settlement of each company, simultaneous management of branch/collection and contract approval management;
a cost center module: the system is used for realizing the information and material management of the material supplier and the management of the purchasing standing book;
supplier hub module: for management of suppliers;
cause development center module: transaction management for a utility generation center;
the human resources center module, the finance center module, the cost center module, the supplier center module and the career development center module are interconnected.
In the construction engineering management system according to the present invention, the human resource center module further includes:
leave record submodule: the system is used for inquiring the leave-asking condition and the accumulation condition of all the personnel in the current month;
staff information submodule: the system is used for transacting the enrollment on line after the employee transacts the enrollment, inputting the information required to be filled in by the system, and storing the information according to the affiliated company and department respectively;
company record submodule: for recording or modifying company information;
department records submodule: for recording or modifying department information;
a second announcement submodule: for issuing notifications or announcements;
the target management submodule is: the system is used for checking the condition of the completion target of the company personnel, has a statistical function and is convenient for relevant departments to carry out statistical evaluation;
a central recording submodule: for recording information of the personal center;
the card punching address management submodule comprises: for adding, modifying or deleting company card punching addresses;
the leave-asking recording submodule, the employee information submodule, the company recording submodule, the department recording submodule, the notice and announcement submodule, the target management submodule, the center recording submodule and the card punching address management submodule are connected with each other.
In the construction engineering management system of the present invention, the financial center module further comprises:
personnel cost collection submodule: the system is used for checking the wages of office staff, inquiring the past wages and filing wages, checking in a personal wage bar and printing a wage table;
each company material settlement submodule: the system is used for carrying out data statistics according to the material purchasing and finally reaching a payment node;
a payment contract submodule: the contract is used for counting the company payment and checking the payment condition;
contract approval submodule: the system is used for carrying out process approval on all contracts, newly adding contract information, making contract content, carrying out an approval process and printing after approval;
a contract management submodule: the system is used for realizing the contract management function, after the examination and approval of the contract is finished, the contract management has related contract information, and the basic contract information, the payment receiving condition and the payment receiving registration can be checked by clicking and modifying;
the personnel cost summarization submodule, the company material settlement submodule, the payment contract submodule, the contract approval submodule and the contract management submodule are connected with each other.
In the construction engineering management system of the present invention, the cost center module further includes:
a sub-supplier standing book sub-module: for enabling management of material supplier information;
a material management submodule: for enabling management of a material database;
purchase detail submodule: the system is used for realizing the detailed summary of all the procurement materials of the company;
the sub-supplier standing book submodule, the material management submodule and the purchasing detail submodule are connected with each other.
The building engineering management system has the following beneficial effects: the login interface unit is used for logging in the construction engineering management system by inputting a user name and a password; the home page unit is used for displaying all functions through a home page menu bar and displaying tasks to be handled, specific number and attendance conditions in the month through a home page; the system setting unit is used for realizing position management; the Chengan people center unit is used for realizing administrative, expense, character and personal information functions; the honesty and security headquarter unit is used for realizing the management of a human resource center, a financial center, a cost center, a supplier center and a cause development center; the honesty construction unit is used for realizing operation type and collection type management; the invention provides a traceability-based block chain management method, which is suitable for the management process and rule of an enterprise, realizes ordered collaboration, realizes all-round management of projects, improves the management capability of the enterprise, and has a traceability function.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic structural diagram of an embodiment of a construction project management system of the present invention;
FIG. 2 is a schematic structural diagram of a system setup unit in the embodiment;
FIG. 3 is a schematic structural diagram of the Chengan center unit in the embodiment;
FIG. 4 is a schematic structural diagram of an administration management module according to the embodiment;
FIG. 5 is a schematic structural diagram of the fee class management module in the embodiment;
FIG. 6 is a schematic structural diagram of a task class management module in the embodiment;
FIG. 7 is a schematic structural diagram of an honest and secure headquarters unit in the embodiment;
FIG. 8 is a schematic structural diagram of a human resources center module according to the embodiment;
FIG. 9 is a schematic structural diagram of a financial center module according to the embodiment;
fig. 10 is a schematic structural diagram of the cost center module in the embodiment.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the embodiment of the construction engineering management system of the invention, the structural schematic diagram of the construction engineering management system is shown in fig. 1. In fig. 1, the construction engineering management system includes a login interface unit 1, a home page unit 2, a system setting unit 3, an honest and safe people center unit 4, an honest and safe headquarter unit 5, and an honest and safe construction unit 6, which are connected with each other. Wherein the content of the first and second substances,
the login interface unit 1 is used for logging in the construction engineering management system by inputting a user name and a password. Specifically, the desktop shortcut is operated, and after the desktop shortcut is opened by double clicking, a login interface dialog box is popped up. The user can log in only by inputting the Chinese name of the user and inputting basic information in the system, and the original password is 123.
In the main page, all functions are in the column, and the common functions are in the main page. The home page unit 2 is used for displaying all functions through a home page menu bar, and displaying tasks to be handled, specific number and attendance conditions in this month through a home page. According to the user, frequently used functions are embodied in the frequently used function bar. The new user can modify the password by himself, the original password is 123, and the functions of password modification and log-out exist. And (5) clicking to input a new password, clicking to modify the password, and finishing password modification.
The system setting unit 3 is used for realizing position management; the Chengan people center unit 4 is used for realizing administrative, expense, people and personal information functions; the honesty and security headquarter unit 5 is used for realizing the management of a human resource center, a financial center, a cost center, a supplier center and a cause development center; the honesty construction unit 6 is used for realizing operation type and collection type management. The invention provides a traceability-based block chain management method, which is suitable for the management process and rule of an enterprise, realizes ordered collaboration, realizes all-round management of projects, improves the management capability of the enterprise, and has a traceability function.
Fig. 2 is a schematic structural diagram of the system setting unit in this embodiment, and in fig. 2, the system setting unit 3 further includes a job management module 31, where the job management module 31 is configured to edit an existing job, check a right matching with the job, modify a job name, and complete job change by clicking submission, and when the job set by the original system can be started and stopped; when the position is not used, all functions are not used; and selecting corresponding authority for the position to be used, hooking the position in brackets, storing the position at the back and finishing the authority setting.
Fig. 3 is a schematic structural diagram of the honest and safe people center unit in this embodiment, in fig. 3, the honest and safe people center unit 4 further includes an administrative class management module 41, a fee class management module 42, a task class management module 43 and a personal information module 44, which are connected to each other; the administrative management module 41 is configured to implement management functions of an honest and safe standard, an invitation card, a notification or announcement, an address book, and an outwork application; the fee management module 42 is used for realizing the management functions of seal application, fee application and article purchase; the task management module 43 is used for realizing the management functions of backlog, transacted items, task management, task report and honesty and safe dream; the personal information module 44 is used for checking the personal related information, position, time of employment, contract time, superior and affiliated company conditions, and can also check the personal salary details each month.
Fig. 4 is a schematic structural diagram of the administration management module in this embodiment, and in fig. 4, the administration management module 41 further includes an honest standard sub-module 411, a please leave function sub-module 412, a notice sub-module 413, an address list sub-module 414, and an outwork application sub-module 415, which are connected to each other. The honest standard sub-module 411 is used for uploading some systems, standards, contracts and specifications of the company, and is convenient for downloading, checking, updating and deleting all colleagues. The leave-asking function sub-module 412 is used for the employees of the company to apply for leave, fill out leave-asking time, days and affairs, submit application for a walk examination and approval process, correspond to corresponding examination and approval processes for corresponding posts, and bind a superior leader and a superior company for the posts; the first notification notice submodule 413 is used for uploading the notice or notice of the company, and the staff can check the notice sent by the name of the company; the address book submodule 414 is used for updating, downloading, printing and checking the address book; the field application submodule 415 is used for applying for field work and also for viewing field personnel.
Fig. 5 is a schematic structural diagram of the fee management module in this embodiment, and in fig. 5, the fee management module 42 further includes a sealing application sub-module 421, a fee application sub-module 422, and an article purchasing sub-module 423 that are connected to each other; the stamping application submodule 421 is configured to apply stamping, and can check the process progress, download stamping content, and print a stamping application form; the fee application sub-module 422 is used for applying for fee, going through the relevant application process and completing examination and approval for printing; the article purchasing submodule 423 is used for performing purchasing application of administrative articles, going through a sporadic material purchasing process, clicking for adding, filling related information, clicking for adding at a bill of materials, filling purchasing information, going through an examination and approval process after filling, completing clicking, downloading and printing after examination and approval, and generating the bill of materials.
Fig. 6 is a schematic structural diagram of the task class management module in this embodiment, and in fig. 6, the task class management module 43 further includes a backlog sub-module 431, a transacted item sub-module 432, a task management sub-module 433, a task report sub-module 434, and an honesty and dream sub-module 435, which are connected to each other; the backlog submodule 431 is used for displaying the backlog to be processed; transacted items sub-module 432 is used to view approved items; the task management submodule 433 is used for issuing work tasks, and setting related responsibility persons and time nodes; the task report sub-module 434 is used for checking the work task management and completion conditions of the current month, the previous month and the next month of each company and each department; the Cheng' an Meng submodule 435 is used to view the completion at the end of the year for the life and work goals set at the beginning of the year.
Fig. 7 is a schematic structural diagram of the honest and safe headquarters unit in this embodiment, and in fig. 7, the honest and safe headquarters unit 5 further includes a human resource center module 51, a finance center module 52, a cost center module 53, a supplier center module 54 and an enterprise development center module 55, which are connected to each other. The human resource center module 51 is used for realizing personnel management, company record, department record, target management and card punching address management; the financial center module 52 is used for realizing personnel cost collection, material settlement of each company, simultaneous management of branch/collection and contract approval management; the cost center module 53 is used for realizing information and material management of material suppliers and management of purchasing standing books; the supplier hub module 54 is for the management of suppliers; the utility development center module 55 is used for transaction management at the utility generation center.
Fig. 8 is a schematic structural diagram of the human resource center module in this embodiment, and in fig. 8, the human resource center module 51 further includes an leave-asking recording sub-module 511, an employee information sub-module 512, a company recording sub-module 513, a department recording sub-module 514, an announcement sub-module 515, a target management sub-module 516, a center recording sub-module 517, and a card-punching address management sub-module 518, which are connected to each other.
The leave-asking recording sub-module 511 is used for inquiring the leave-asking condition and the accumulation condition of all the personnel in the current month; the staff information sub-module 512 is used for the staff to transact the job on line after transacting the job, inputting the information filled in by the system requirement, storing the information according to the affiliated company and department, editing the information to perfect the personal information, and arranging a personal two-dimensional code at the upper right corner.
The company record submodule 513 is used for recording or changing company information; the department record submodule 514 is used for recording or changing department information; the second notification sub-module 515 is configured to issue a notification or an announcement; the target management submodule 516 is used for checking the condition that the company personnel complete the target, has a statistical function and is convenient for relevant departments to carry out statistical evaluation at the end of the year; the center recording sub-module 517 is used for recording information of the individual center; the punch-down address management submodule 518 is used to add, modify or delete company punch-down addresses.
Fig. 9 is a schematic structural diagram of the financial center module in this embodiment, and in fig. 9, the financial center module 52 further includes a staff cost summary sub-module 521, a company material settlement sub-module 522, a payment contract sub-module 523, a contract approval sub-module 524, and a contract management sub-module 525 that are connected to each other; the staff cost summarization submodule 521 is used for accounting the wages of office staff, inquiring the past wages and archived wages, checking the personal wage bar and printing a wage table; each company material settlement submodule 522 is used for carrying out data statistics according to the material purchasing and finally reaching a payment node; the payment contract submodule 523 is used for counting the contract paid by the company and checking detailed information such as payment condition; the contract approval submodule 524 is configured to perform process approval on all contracts, add and fill contract information first, enable relevant personnel to perform contract content, perform an approval process, and perform printing after approval; the contract management submodule 525 is used to implement contract management function, after the contract approval is completed, the contract management has related contract information, and the basic contract information, the payment receiving condition and the payment receiving registration can be checked by clicking and modifying. The management part of each company is divided into an operation class and a summary class, wherein the operation class is project management, such as: the conditions of ordering and progress of the materials are collected into statistical functions, such as: manual statistics, project operation statistics, and the like.
Fig. 10 is a schematic structural diagram of the cost center module in this embodiment, and in fig. 10, the cost center module 53 further includes a sub-supplier ledger sub-module 531, a material management sub-module 532 and a procurement detail sub-module 533 which are connected to each other; the sub-supplier standing book sub-module 531 is used for realizing management of information of material suppliers; the material management submodule 532 is used for realizing the management of a material database; the procurement details sub-module 533 is used to implement a detailed summary of the list of all procured materials of the company.
In a word, the invention provides a management process and rules suitable for an enterprise, realizes ordered collaboration, realizes all-round management of projects, improves the management capability of the enterprise, and has a traceability function based on a block chain.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (10)

1. A construction engineering management system, comprising:
a login interface unit: the system is used for logging in the construction engineering management system by inputting a user name and a password;
a home page unit: the system is used for displaying all functions through a home page menu bar and displaying tasks to be handled, specific number and attendance conditions in the month through a home page;
a system setting unit: the system is used for realizing position management;
honesty and peaceful people center unit: the system is used for realizing the functions of administration, expense, person and personal information;
integrity bureau unit: for implementing management of human resources centers, financial centers, cost centers, supplier centers, and career development centers;
honesty and peaceful construction unit: the method is used for realizing operation type and collection type management;
the login interface unit, the home page unit, the system setting unit, the honest and safe people center unit, the honest and safe headquarter unit and the honest and safe construction unit are connected with one another.
2. The construction project management system according to claim 1, wherein the system setting unit further includes:
the position management module: the system is used for editing the existing positions, checking the authority matched with the positions, modifying the names of the positions, starting and stopping the positions, selecting the corresponding authority for the positions to be used, and setting the authority for the positions.
3. The construction engineering management system according to claim 1, wherein the honesty center unit further comprises:
administrative management module: the management function is used for realizing the integrity standard, the leave-on bar, the notice or announcement, the address list and the application for the field work;
the fee management module: the management function is used for realizing sealing application, expense application and article purchasing;
the task class management module: the management function is used for realizing backlogs, transacted items, task management, task report and honesty and safe dreams;
a personal information module: the system is used for checking personal related information, positions, time of employment, contract time, superior and affiliated company conditions, and can also check personal salary details in each month;
the administrative management module, the expense management module, the task management module and the personal information module are connected with one another.
4. The construction project management system of claim 3, wherein the administration management module further comprises:
an honest standard submodule: the system is used for uploading the system, standard, contract and specification of the company;
leave asking function submodule: the system is used for applying for leave by employees of the company, filling leave-applying time, days and reasons, submitting a walk-applying and examining and approving process, corresponding posts correspond to corresponding examining and approving processes, and binding a superior leader and a superior company for the positions;
a first notification advertisement submodule: the system is used for uploading the notice or announcement of the company, and the staff can check the notice sent by the name of the company;
the address list submodule: the address book is used for updating, downloading, printing and checking the address book;
an external application submodule: the system is used for applying for field work and checking field staff;
the honesty and security standard submodule, the leave asking function submodule, the notice and announcement submodule, the address list submodule and the outwork application submodule are connected with one another.
5. The construction project management system of claim 3, wherein the fee type management module further comprises:
a stamping application submodule: the system is used for applying for stamping, and can check the progress of the process, download stamping contents and print a stamping application form;
a charge application submodule: the system is used for applying for the application fee, walking the relevant application flow and completing examination and approval for printing;
an article purchasing submodule: the system is used for carrying out purchasing application of administrative goods, walking a purchasing process of sporadic materials, clicking for adding, filling related information, clicking for adding at the material bill, filling purchasing information, walking an approval process after filling, finishing clicking for downloading and printing after approval, and generating the material bill;
the stamping application submodule, the expense application submodule and the article purchasing submodule are connected with one another.
6. The construction project management system of claim 3, wherein the task class management module further comprises:
a backlog submodule: for presenting items to be processed;
transacted items submodule: for viewing the approved item;
and the task management submodule is used for: the system is used for issuing work tasks and setting related responsibility persons and time nodes;
task report submodule: the system is used for checking the work task management and completion conditions of the current month, the previous month and the next month of each company and each department;
cheng' an Meng submodule: the system is used for checking the completion condition at the end of the year according to the life target and the work target determined in the beginning of the year;
the backlog submodule, the transacted item submodule, the task management submodule, the task report submodule and the honesty and dream submodule are connected with each other.
7. The construction engineering management system according to claim 1, wherein the integrity headquarters unit further comprises:
manpower resource center module: the system is used for realizing personnel management, company record, department record, target management and card punching address management;
financial center module: the system is used for realizing personnel cost collection, material settlement of each company, simultaneous management of branch/collection and contract approval management;
a cost center module: the system is used for realizing the information and material management of the material supplier and the management of the purchasing standing book;
supplier hub module: for management of suppliers;
cause development center module: transaction management for a utility generation center;
the human resources center module, the finance center module, the cost center module, the supplier center module and the career development center module are interconnected.
8. The construction project management system of claim 7, wherein the human resources center module further comprises:
leave record submodule: the system is used for inquiring the leave-asking condition and the accumulation condition of all the personnel in the current month;
staff information submodule: the system is used for transacting the enrollment on line after the employee transacts the enrollment, inputting the information required to be filled in by the system, and storing the information according to the affiliated company and department respectively;
company record submodule: for recording or modifying company information;
department records submodule: for recording or modifying department information;
a second announcement submodule: for issuing notifications or announcements;
the target management submodule is: the system is used for checking the condition of the completion target of the company personnel, has a statistical function and is convenient for relevant departments to carry out statistical evaluation;
a central recording submodule: for recording information of the personal center;
the card punching address management submodule comprises: for adding, modifying or deleting company card punching addresses;
the leave-asking recording submodule, the employee information submodule, the company recording submodule, the department recording submodule, the notice and announcement submodule, the target management submodule, the center recording submodule and the card punching address management submodule are connected with each other.
9. The construction project management system of claim 7, wherein the financial center module further comprises:
personnel cost collection submodule: the system is used for checking the wages of office staff, inquiring the past wages and filing wages, checking in a personal wage bar and printing a wage table;
each company material settlement submodule: the system is used for carrying out data statistics according to the material purchasing and finally reaching a payment node;
a payment contract submodule: the contract is used for counting the company payment and checking the payment condition;
contract approval submodule: the system is used for carrying out process approval on all contracts, newly adding contract information, making contract content, carrying out an approval process and printing after approval;
a contract management submodule: the system is used for realizing the contract management function, after the examination and approval of the contract is finished, the contract management has related contract information, and the basic contract information, the payment receiving condition and the payment receiving registration can be checked by clicking and modifying;
the personnel cost summarization submodule, the company material settlement submodule, the payment contract submodule, the contract approval submodule and the contract management submodule are connected with each other.
10. The construction project management system of claim 7, wherein the cost center module further comprises:
a sub-supplier standing book sub-module: for enabling management of material supplier information;
a material management submodule: for enabling management of a material database;
purchase detail submodule: the system is used for realizing the detailed summary of all the procurement materials of the company;
the sub-supplier standing book submodule, the material management submodule and the purchasing detail submodule are connected with each other.
CN201911305114.6A 2019-12-17 2019-12-17 Construction engineering management system Pending CN111160854A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911305114.6A CN111160854A (en) 2019-12-17 2019-12-17 Construction engineering management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911305114.6A CN111160854A (en) 2019-12-17 2019-12-17 Construction engineering management system

Publications (1)

Publication Number Publication Date
CN111160854A true CN111160854A (en) 2020-05-15

Family

ID=70557582

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911305114.6A Pending CN111160854A (en) 2019-12-17 2019-12-17 Construction engineering management system

Country Status (1)

Country Link
CN (1) CN111160854A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113296866A (en) * 2021-05-31 2021-08-24 珠海大横琴科技发展有限公司 Task information display method and device, electronic equipment and storage medium

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130138606A1 (en) * 2011-11-29 2013-05-30 Trimble Navigation Limited Managing information at a construction site
CN105139181A (en) * 2015-07-17 2015-12-09 苏州朗捷通智能科技有限公司 Enterprise collaborative office management system
CN105139160A (en) * 2015-10-14 2015-12-09 盐城工学院 B/S-based enterprise sales management system
CN106295968A (en) * 2016-08-01 2017-01-04 深圳市绿清物业发展有限公司 A kind of office management system
CN106557890A (en) * 2016-12-05 2017-04-05 许有为 A kind of enterprise operation platform based on affairs visual angle(EBP)Method for designing
CN106709632A (en) * 2016-12-01 2017-05-24 武汉大思想信息股份有限公司 Big data-based enterprise budget management control analysis system
CN107622376A (en) * 2017-08-31 2018-01-23 成都中建科联网络科技有限公司 A kind of building trade Human Resources Management Method
CN108335080A (en) * 2018-01-25 2018-07-27 广州建衡工程咨询有限公司 A kind of Construction Audit system and implementation method
KR101995885B1 (en) * 2018-01-23 2019-10-01 한국도로공사 Structure Information Modeling System

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130138606A1 (en) * 2011-11-29 2013-05-30 Trimble Navigation Limited Managing information at a construction site
CN105139181A (en) * 2015-07-17 2015-12-09 苏州朗捷通智能科技有限公司 Enterprise collaborative office management system
CN105139160A (en) * 2015-10-14 2015-12-09 盐城工学院 B/S-based enterprise sales management system
CN106295968A (en) * 2016-08-01 2017-01-04 深圳市绿清物业发展有限公司 A kind of office management system
CN106709632A (en) * 2016-12-01 2017-05-24 武汉大思想信息股份有限公司 Big data-based enterprise budget management control analysis system
CN106557890A (en) * 2016-12-05 2017-04-05 许有为 A kind of enterprise operation platform based on affairs visual angle(EBP)Method for designing
CN107622376A (en) * 2017-08-31 2018-01-23 成都中建科联网络科技有限公司 A kind of building trade Human Resources Management Method
KR101995885B1 (en) * 2018-01-23 2019-10-01 한국도로공사 Structure Information Modeling System
CN108335080A (en) * 2018-01-25 2018-07-27 广州建衡工程咨询有限公司 A kind of Construction Audit system and implementation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113296866A (en) * 2021-05-31 2021-08-24 珠海大横琴科技发展有限公司 Task information display method and device, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
US9020884B2 (en) Method of and system for consultant re-seller business information transfer
US11321645B2 (en) System and interfaces for managing temporary workers
US8548834B2 (en) Information capture, processing and retrieval system and method of operating the same
US7305392B1 (en) Multi-organizational project management system
US20030220806A1 (en) Information and time managing system and method
CN111507688A (en) Method and system for electronic cluster registration of economic operator of Internet platform
CN106716459A (en) System and method for tracking expenses and billing
Authority About Capital Market Authority
Perdana et al. Prototyping and implementing Robotic Process Automation in accounting firms: Benefits, challenges and opportunities to audit automation
CN111160854A (en) Construction engineering management system
CN116384724B (en) Employment patch center design method and employment patch center
US20160132818A1 (en) Signing Agent Management Software
JP2005216013A (en) Integrated job management system
US20160132807A1 (en) Method for Managing Signing Agents
JP2008123469A (en) Management system of object management information, person management information and real estate information
Paradiso et al. Process mapping for SOX and beyond
KR101869653B1 (en) Administrative task computerized publishing system connected with on-nara system, and administrative task computerized publishing method based on the same
KR102355505B1 (en) Business fund management system
WO2004003804A1 (en) Audit service managing system
Siva Developing a national single window: implementation issues and considerations
Alaydrus et al. Designing Web-based Database Applications in CV Bahagia
CN114140269A (en) Integrated building industry digital platform system
Wible Keeping building departments ahead of the curve
CN113409017A (en) Laboratory management system based on budget project pool overall planning
CN114707964A (en) Enterprise management system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200515

RJ01 Rejection of invention patent application after publication