CN111074786A - 一种减小钢管拱首节段与预埋段管口安装错位的方法 - Google Patents
一种减小钢管拱首节段与预埋段管口安装错位的方法 Download PDFInfo
- Publication number
- CN111074786A CN111074786A CN202010060040.0A CN202010060040A CN111074786A CN 111074786 A CN111074786 A CN 111074786A CN 202010060040 A CN202010060040 A CN 202010060040A CN 111074786 A CN111074786 A CN 111074786A
- Authority
- CN
- China
- Prior art keywords
- section
- segment
- pipe
- steel pipe
- embedded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D4/00—Arch-type bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种减小钢管拱安装时首节段与预埋段管口错位的方法;其特征在于:实施方式如下:在匹配拼装加工拱肋节段时,调整加工顺序,即先匹配加工2号节段至合龙段,最后再匹配加工首节段。首节段加工前,先由测量人员准确测量出已埋入拱座混凝土中的预埋段钢管管口(含铰轴)的相对位置和尺寸,由此控制首节段底截面管口的相对位置和尺寸,而首节段顶截面管口与2号段匹配。这样,首节段既与预埋段钢管匹配,又与2号段进行匹配,便可保证安装时首节段与预埋段的管口间的错位量尽量减小,保证预埋段—嵌补段—首节段线形平顺。本发明主要解决钢管拱肋分段匹配加工、安装时,首节段与预埋段管口错位量大的问题。
Description
技术领域
本发明涉及钢管拱桥相关施工领域,具体来讲是一种减小钢管拱安装时首节段与预埋段管口错位的方法。
背景技术
目前钢管拱桥多采用在钢结构加工厂或者工地现场分段匹配加工,逐段安装。钢管拱肋节段一般分为预埋段、首节段(1号段)、2号段…n号段、合龙段。各节段在地面先匹配拼装合格后,再运到桥位进行安装。要求匹配时达到设计要求的线形,且相邻节段间的错边量满足规范要求。匹配拼装的方式有半跨或全跨节段进行匹配的“长线法”,以及3段以上节段进行匹配的“短线法”。在匹配加工时,从首节段至合龙段的顺序加工制作。安装时,先将预埋段固定在型钢骨架上,然后浇筑拱座混凝土,待拱座混凝土达到设计强度后,再按顺序逐段安装剩余拱肋节段。目前的施工方法中,钢管拱安装常出现首节段和预埋段管口错位量大的问题,究其原因,主要有:一是预埋段安装时测量放样误差大、或者测量放样错误;二是在浇筑拱座混凝土时,预埋段钢管受外力发生位移;三是首节段下截面钢管间相对位置存在放样误差或错误、或者焊接变形等。由于以上原因,首节段与预埋段钢管管口出现超过规范规定的错位,由此导致预埋段—嵌补段—首节段线形不顺,对钢管拱的受力不利。
发明内容
因此,为了解决上述不足,本发明在此提供一种减小钢管拱安装时首节段与预埋段管口错位的方法;主要解决钢管拱肋分段匹配加工、安装时,首节段与预埋段管口错位量大的问题。
本发明是这样实现的,构造一种减小钢管拱安装时首节段与预埋段管口错位的方法,其特征在于:实施方式如下:在匹配拼装加工拱肋节段时,调整加工顺序,即先匹配加工2号节段至合龙段,最后再匹配加工首节段。首节段加工前,先由测量人员准确测量出已埋入拱座混凝土中的预埋段钢管管口(含铰轴)的相对位置和尺寸,由此控制首节段底截面管口的相对位置和尺寸,而首节段顶截面管口与2号段匹配。这样,首节段既与预埋段钢管匹配,又与2号段进行匹配,便可保证安装时首节段与预埋段的管口间的错位量尽量减小,保证预埋段—嵌补段—首节段线形平顺。
本发明具有如下优点:本发明在此提供一种减小钢管拱安装时首节段与预埋段管口错位的结构及方法;主要解决钢管拱肋分段匹配加工、安装时,首节段与预埋段管口错位量大的问题。本专利所描述的方法可大大减小钢管拱首节段和预埋段管口的错位量,保证钢管拱安装线形顺畅。
附图说明
图1是首节段与预埋段安装位置示意图;
图2是首节段与预埋段管口错位示意图。
其中:预埋段钢管1,拱座浇筑段2,拱座3,铰轴4,铰座5,嵌补段6,首节段钢管7。
具体实施方式
下面将结合附图1-图2对本发明进行详细说明,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
本发明通过改进在此提供一种减小钢管拱安装时首节段与预埋段管口错位的方法,如图1-图2所示,实施方式如下:在匹配拼装加工拱肋节段时,调整加工顺序,即先匹配加工2号节段至合龙段,最后再匹配加工首节段。首节段加工前,先由测量人员准确测量出已埋入拱座混凝土中的预埋段钢管管口(含铰轴)的相对位置和尺寸,由此控制首节段底截面管口的相对位置和尺寸,而首节段顶截面管口与2号段匹配。这样,首节段既与预埋段钢管匹配,又与2号段进行匹配,便可保证安装时首节段与预埋段的管口间的错位量尽量减小,保证预埋段—嵌补段—首节段线形平顺。
本专利具有如下优点及有益效果:本专利所描述的方法可大大减小钢管拱首节段和预埋段管口的错位量,保证钢管拱安装线形顺畅。
对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本发明。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神或范围的情况下,在其它实施例中实现。因此,本发明将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。
Claims (1)
1.一种减小钢管拱安装时首节段与预埋段管口错位的方法,其特征在于:实施方式如下:在匹配拼装加工拱肋节段时,调整加工顺序,即先匹配加工2号节段至合龙段,最后再匹配加工首节段;首节段加工前,先由测量人员准确测量出已埋入拱座混凝土中的预埋段钢管管口(含铰轴)的相对位置和尺寸,由此控制首节段底截面管口的相对位置和尺寸,而首节段顶截面管口与2号段匹配;这样,首节段既与预埋段钢管匹配,又与2号段进行匹配,便可保证安装时首节段与预埋段的管口间的错位量尽量减小,保证预埋段—嵌补段—首节段线形平顺。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010060040.0A CN111074786A (zh) | 2020-01-19 | 2020-01-19 | 一种减小钢管拱首节段与预埋段管口安装错位的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010060040.0A CN111074786A (zh) | 2020-01-19 | 2020-01-19 | 一种减小钢管拱首节段与预埋段管口安装错位的方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111074786A true CN111074786A (zh) | 2020-04-28 |
Family
ID=70323777
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010060040.0A Pending CN111074786A (zh) | 2020-01-19 | 2020-01-19 | 一种减小钢管拱首节段与预埋段管口安装错位的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111074786A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593678A (zh) * | 2020-05-08 | 2020-08-28 | 中电建十一局工程有限公司 | 一种钢管拱肋安装使用的临时铰施工方法 |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101476293A (zh) * | 2009-01-16 | 2009-07-08 | 广东省长大公路工程有限公司 | 大型桥梁拱肋无支架施工方法 |
CN101713169A (zh) * | 2008-10-06 | 2010-05-26 | 中交第三航务工程局有限公司 | 一种节段箱梁的制作方法 |
CN202390749U (zh) * | 2011-09-30 | 2012-08-22 | 腾达建设集团股份有限公司 | 埋入式拱肋竖向转动机构 |
KR20130126381A (ko) * | 2012-05-11 | 2013-11-20 | 주식회사 장헌산업 | 콘크리트 몰드와 맬란제의 합성 및 단계적 인양을 이용한 콘크리트 아치리브의 시공방법 |
JP2016023523A (ja) * | 2014-07-24 | 2016-02-08 | 株式会社Ihiインフラシステム | アーチ橋の架橋方法 |
CN206706584U (zh) * | 2017-05-03 | 2017-12-05 | 四川路桥桥梁工程有限责任公司 | 中墩不对称扣挂缆索系统安装多跨拱桥中墩拱肋 |
CN108374340A (zh) * | 2018-01-10 | 2018-08-07 | 中交第二航务工程局有限公司 | 大跨度钢桁梁上支架拼装柔性拱的方法 |
CN108532465A (zh) * | 2018-04-20 | 2018-09-14 | 中交第三航务工程局有限公司 | 一种下承式钢箱拱桥的施工方法 |
CN110468734A (zh) * | 2019-06-03 | 2019-11-19 | 中铁二院工程集团有限责任公司 | 钢拱肋顶推系统及钢拱肋顶推施工方法 |
-
2020
- 2020-01-19 CN CN202010060040.0A patent/CN111074786A/zh active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101713169A (zh) * | 2008-10-06 | 2010-05-26 | 中交第三航务工程局有限公司 | 一种节段箱梁的制作方法 |
CN101476293A (zh) * | 2009-01-16 | 2009-07-08 | 广东省长大公路工程有限公司 | 大型桥梁拱肋无支架施工方法 |
CN202390749U (zh) * | 2011-09-30 | 2012-08-22 | 腾达建设集团股份有限公司 | 埋入式拱肋竖向转动机构 |
KR20130126381A (ko) * | 2012-05-11 | 2013-11-20 | 주식회사 장헌산업 | 콘크리트 몰드와 맬란제의 합성 및 단계적 인양을 이용한 콘크리트 아치리브의 시공방법 |
JP2016023523A (ja) * | 2014-07-24 | 2016-02-08 | 株式会社Ihiインフラシステム | アーチ橋の架橋方法 |
CN206706584U (zh) * | 2017-05-03 | 2017-12-05 | 四川路桥桥梁工程有限责任公司 | 中墩不对称扣挂缆索系统安装多跨拱桥中墩拱肋 |
CN108374340A (zh) * | 2018-01-10 | 2018-08-07 | 中交第二航务工程局有限公司 | 大跨度钢桁梁上支架拼装柔性拱的方法 |
CN108532465A (zh) * | 2018-04-20 | 2018-09-14 | 中交第三航务工程局有限公司 | 一种下承式钢箱拱桥的施工方法 |
CN110468734A (zh) * | 2019-06-03 | 2019-11-19 | 中铁二院工程集团有限责任公司 | 钢拱肋顶推系统及钢拱肋顶推施工方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593678A (zh) * | 2020-05-08 | 2020-08-28 | 中电建十一局工程有限公司 | 一种钢管拱肋安装使用的临时铰施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101713168B (zh) | 一种节段箱梁制作模板的安装工艺 | |
CN106032692A (zh) | 一种钢筋混凝土柱的一体式浇筑成型施工方法 | |
CN205475352U (zh) | 一种底板收缩后浇带纵筋的直螺纹双套筒连接结构 | |
CN105365036A (zh) | 一种节段箱梁制作模板的安装工艺 | |
CN105269664A (zh) | 一种节段箱梁制作模板的安装工艺 | |
CN111074786A (zh) | 一种减小钢管拱首节段与预埋段管口安装错位的方法 | |
CN109137720B (zh) | 预制箱梁的施工方法 | |
CN108868001A (zh) | 一种预制钢管约束型钢混凝土柱拼接节点及其施工工艺 | |
CN106032706A (zh) | 一种钢筋混凝土剪力墙的一体式浇筑成型施工方法 | |
US6851245B1 (en) | Mortar-filled type reinforcing bar joint | |
CN105735467A (zh) | 一种pc梁柱节点连接装置及方法 | |
CN108385542B (zh) | 一种桥梁线形精细二次控制施工方法 | |
CN107740437B (zh) | 综合管廊预埋钢边止水带及止水钢板加固施工工艺 | |
CN106592865B (zh) | 装配式预制混凝土过梁 | |
CN113090285B (zh) | 隧道二次衬砌钢筋保护层控制及受力体系转换施工方法 | |
CN213681700U (zh) | 改进型桥梁伸缩缝缝宽施工结构 | |
CN110205943A (zh) | 预制简支小箱梁端横梁的施工方法 | |
CN213087079U (zh) | 一种混凝土梁与h型钢混凝土柱连接节点结构 | |
KR20170134846A (ko) | 메가컬럼 시공용 철골 구조물 및 이를 이용한 메가칼럼 시공방법 | |
CN210798297U (zh) | 桥架穿楼层板连接结构 | |
CN106917452A (zh) | Pc结构梁柱节点处预应力梁金属波纹管內锚施工方法 | |
KR101591804B1 (ko) | 교량거더 제작용 거푸집 유닛 및 이를 이용한 거더교 시공방법 | |
CN220058829U (zh) | 圆形柱木模板加固装置 | |
CN210066535U (zh) | 一种桥梁设计用钢筋的加固结构 | |
CN218406053U (zh) | 一种装配式预制梁的免外模结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200428 |
|
RJ01 | Rejection of invention patent application after publication |