CN111042568A - Precast beam crack repairing construction process - Google Patents

Precast beam crack repairing construction process Download PDF

Info

Publication number
CN111042568A
CN111042568A CN201911394889.5A CN201911394889A CN111042568A CN 111042568 A CN111042568 A CN 111042568A CN 201911394889 A CN201911394889 A CN 201911394889A CN 111042568 A CN111042568 A CN 111042568A
Authority
CN
China
Prior art keywords
crack
precast beam
construction process
repairing
smaller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911394889.5A
Other languages
Chinese (zh)
Inventor
柴刚强
刘炜
陈赟
付予
律振金
郭辉
李卓然
陈胜利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Harbour and Channel Engineering Bureau Group Co Ltd
Original Assignee
China Construction Harbour and Channel Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Harbour and Channel Engineering Bureau Group Co Ltd filed Critical China Construction Harbour and Channel Engineering Bureau Group Co Ltd
Priority to CN201911394889.5A priority Critical patent/CN111042568A/en
Publication of CN111042568A publication Critical patent/CN111042568A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a precast beam crack repairing construction process, which comprises the steps of dipping an anti-corrosion coating by adding silane twice on the surface of a precast beam crack which is less than or equal to 0.2 mm; for the surface with the crack of 0.2mm < 1mm, cutting and slotting along the length direction of the crack, sealing and repairing by using high-strength grouting material, and sticking 1 layer of carbon fiber cloth. The precast beam crack repairing scheme provided by the invention can be used for efficiently and high-quality repairing of the precast beam crack, and can effectively overcome the problems in the prior art.

Description

Precast beam crack repairing construction process
Technical Field
The invention relates to a precast member beam pouring technology, in particular to a crack repairing technology of a precast member beam.
Background
In recent years, port engineering has been continuously developed, and high pile cap type bank protection structures are increasingly adopted. For some high pile bearing platform type revetment structures, the upper structure of a platform adopts a beam plate structure type, a beam adopts a cast-in-place inverted T-shaped beam, a middle longitudinal beam, an edge beam and a prefabricated pipe trench are placed on a lower beam, a prefabricated electric pipe trench beam is arranged on the rear edge of the platform, and the platform surface is a laminated slab.
In the actual pouring process, cracks sometimes appear at the flange of the prefabricated member beam after the prefabricated member beam of the platform is poured, but the repairing quality of the existing crack repairing scheme cannot meet the requirements.
Therefore, the crack repairing scheme capable of effectively improving the repairing quality is an urgent problem to be solved in the field.
Disclosure of Invention
Aiming at the problems of the existing crack repairing scheme of the platform precast member beam, a new precast beam crack repairing scheme is needed.
Therefore, the invention aims to provide a precast beam crack repairing construction process to realize efficient and high-quality repair of precast beam cracks.
In order to achieve the aim, the precast beam crack repairing construction process provided by the invention comprises the following steps of
For the surface with the crack of the precast beam less than or equal to 0.2mm, silane is added for dipping the anticorrosive paint twice;
for the surface with the crack of 0.2mm < 1mm, cutting and slotting along the length direction of the crack, sealing and repairing by using high-strength grouting material, and sticking 1 layer of carbon fiber cloth.
Further, in the repair construction process, when the silane dipping anticorrosive paint is added twice on the surface with the crack less than or equal to 0.2mm, the dosage of each layer is 250-350ml/m2
Further, in the repair construction process, the repair process for the surface with 0.2mm < crack < 1mm sequentially comprises the following steps:
cleaning the surface of the crack;
cutting V-shaped grooves obliquely downwards on two sides of the crack, and cleaning;
sealing the high-strength grouting material;
and adhering a layer of carbon cloth at the crack on the side surface of the bracket of the precast beam.
Further, the construction process of the repair construction process comprises the following steps:
three types of cracks on the same prefabricated beam are firstly repaired, wherein the crack is smaller than 0.5mm and smaller than or equal to 1mm, then the crack is smaller than 0.2mm and smaller than or equal to 0.5mm, and finally the crack is repaired, wherein the width of the crack is smaller than or equal to 0.2 mm.
The precast beam crack repairing scheme provided by the invention can be used for efficiently and high-quality repairing of the precast beam crack, and can effectively overcome the problems in the prior art.
Drawings
The invention is further described below in conjunction with the appended drawings and the detailed description.
Fig. 1 is an exemplary view of a bonded carbon cloth according to an embodiment of the present invention.
Detailed Description
In order to make the technical means, the creation characteristics, the achievement purposes and the effects of the invention easy to understand, the invention is further explained below by combining the specific drawings.
Aiming at cracks appearing at the flange of the prefabricated beam after the platform prefabricated beam is poured, the corresponding repairing scheme is provided according to the size of the cracks.
When the width of the crack of the precast beam is less than or equal to 0.2mm, the precast beam is coated and sealed twice by adopting silane dipping anticorrosive paint, and the dosage of each layer is 250-350ml/m2Preferably 300ml/m2
For the crack with the thickness of 0.2mm and the thickness of less than or equal to 1mm, cutting and slotting along the length direction of the crack, sealing and repairing by using high-strength grouting material, and adhering 1 layer of carbon fiber cloth. The basic repair process is as follows: cleaning the surface of the crack → cutting a V-shaped groove downwards and obliquely in the range of 4cm at two sides of the crack → cleaning → sealing the high-strength grouting material → adhering a layer of carbon cloth at the crack on the side surface of the bracket of the precast beam.
According to the restoration scheme, the construction process comprises the following steps:
three types of cracks on the same prefabricated beam are firstly repaired, wherein the crack is smaller than 0.5mm and smaller than or equal to 1mm, then the crack is smaller than 0.2mm and smaller than or equal to 0.5mm, and finally the crack is repaired, wherein the width of the crack is smaller than or equal to 0.2 mm.
For the above scheme, the following implementation processes are exemplified as follows:
firstly, grouting material enters a field;
the crack repair in the embodiment preferably adopts high-strength grouting material repair, the strength is more than or equal to 60mpa, and the crack repair can be used after passing the supervision and acceptance after entering the field.
And (4) manufacturing grouting material test blocks on site, and sending the grouting material test blocks to a third party for detection after the maintenance period is up.
(II) cleaning cracks;
and polishing the periphery of the crack, cleaning impurities such as dust and mud on the surface, and removing floating dust in the crack by using a blower.
Thirdly, cutting and grooving at two sides of the crack;
after the surface of the crack is cleaned, cutting and grooving downwards and obliquely within the range of 4cm at two sides of the crack, wherein the grooving depth is 4 cm-5 cm, and washing and cleaning the crack. The depth of the grooves here must not exceed the thickness of the protective layer.
(IV) sealing treatment;
and (4) carrying out crack sealing along the groove by using the prepared high-strength grouting material. Before sealing, the surface of the concrete is ensured to be dry and clean and can not contain water, oil stain, scum and the like;
and supporting the formwork at the side face of the groove, fixing and sealing the formwork by using a steel bar clamp and a grout-stopping adhesive tape, pouring grout into the formwork after the grout is prepared, ensuring fullness and compactness, sending a specially-assigned person for later observation, and preventing the formwork from leaking grout, if leakage is found, remedying.
Fifthly, pasting carbon cloth;
after the high-strength grouting material is sewn, carbon fiber cloth (shown in figure 1) is adhered to the side face of the bracket, the width of the carbon fiber cloth is preferably 200mm, and the two sides of a crack are respectively ultra-adhered by 300 mm. And (3) laying along the side surface of the bracket of the precast beam, if a plurality of cracks continuously appear, carrying out common laying, wherein the direction of the carbon fiber is orthogonal to the direction of the cracks. The performance of the carbon fiber and the matched glue can meet the design and standard requirements.
The basic scheme for pasting the carbon fiber cloth in the step is as follows:
(1) carbon fiber cloth parameter requirements
The carbon fiber cloth used for repairing the precast beam adopts PAN-based single-item carbon fiber cloth, the material grade is first grade, and the specification is 300g/m2
(2) The surface should be kept dry prior to consolidation, the component dried with a blower applied to the component with the wet surface, and the relative humidity of the component surface is maintained at no greater than 70%.
(3) And (3) treating the surface of the member, namely polishing and flattening the surface of the adhered concrete, and removing impurities such as surface coating paste, oil stains and the like until a new surface of the concrete structure is completely exposed.
(4) And (4) brushing the bottom resin, and uniformly smearing the bottom resin on the surface of the concrete member by adopting a roller brush after the surface of the member is treated.
(5) The carbon fiber sheet is adhered by putting the carbon fiber cloth cut according to the required size into resin prepared according to the process specification for soaking, and uniformly smearing on the adhered part. When the carbon fiber cloth is pasted, the carbon fiber cloth is lightly pressed to the position needing pasting by hand, a special roller is adopted to roll for multiple times along the fiber direction, air bubbles are squeezed out, so that the impregnating resin fully permeates the carbon fiber cloth, the carbon fiber cloth cannot be damaged during rolling, and the direction of the unidirectional carbon fiber is orthogonal to the crack. The above steps should be repeated when the multiple layers are pasted, and the next layer of pasting is preferably carried out on the impregnating resin on the surface of the carbon fiber cloth, and then the impregnating resin is uniformly smeared on the surface of the last layer of carbon fiber cloth.
(VI) surface protection; and performing antiseptic treatment according to requirements.
(VII) checking and accepting;
before construction, product qualification certificates and product quality delivery inspection reports of carbon fiber sheets and prepared resin adhesive materials are confirmed, and various performance indexes meet the requirements of technical Specification for repair and reinforcement of harbor hydraulic structures JTS 311-2011. The actual pasting area of the carbon fiber sheet is not smaller than the design area, and the position deviation is not larger than 10 mm. The bonding quality between the carbon fiber sheet and the concrete can be checked by lightly knocking or pressing the surface of the carbon fiber sheet by hand with a small hammer, and the total effective bonding area is not less than 95%. When the carbon fiber isThe hollowing area is not more than 10000mm2In time, the needle tube can be repaired by a method of injecting glue into the needle tube. When the hollowing area is more than 10000mm2When in use, the carbon fiber sheets at the hollowing part are cut off, and the same amount of carbon fiber sheets are attached in a lap joint mode again, wherein the lap joint length is not less than 100 mm.
According to the embodiment, the precast beam crack repairing scheme provided by the embodiment can be used for efficiently and high-quality repairing of the precast beam crack; meanwhile, the whole implementation process is simple, the construction period is short, and the cost is low.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, which are described in the specification and illustrated only to illustrate the principle of the present invention, but that various changes and modifications may be made therein without departing from the spirit and scope of the present invention, which fall within the scope of the invention as claimed. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (4)

1. The precast beam crack repairing construction process is characterized by comprising the following steps
For the surface with the crack of the precast beam less than or equal to 0.2mm, silane is added for dipping the anticorrosive paint twice;
for the surface with the crack of 0.2mm < 1mm, cutting and slotting along the length direction of the crack, sealing and repairing by using high-strength grouting material, and sticking 1 layer of carbon fiber cloth.
2. The precast beam crack repairing construction process according to claim 1, wherein in the repairing construction process, when silane dipping anticorrosive paint is added twice to the surface with crack smaller than or equal to 0.2mm, the dosage of each layer is 250 ml/m-2
3. The precast beam crack repair construction process according to claim 1, wherein the repair construction process for the surface with 0.2mm < crack ≦ 1mm comprises the following steps in sequence
Cleaning the surface of the crack;
cutting V-shaped grooves obliquely downwards on two sides of the crack, and cleaning;
sealing the high-strength grouting material;
and adhering a layer of carbon cloth at the crack on the side surface of the bracket of the precast beam.
4. The precast beam crack repairing construction process according to any one of claims 1 to 3, wherein the repairing construction process comprises the following construction procedures:
three types of cracks on the same prefabricated beam are firstly repaired, wherein the crack is smaller than 0.5mm and smaller than or equal to 1mm, then the crack is smaller than 0.2mm and smaller than or equal to 0.5mm, and finally the crack is repaired, wherein the width of the crack is smaller than or equal to 0.2 mm.
CN201911394889.5A 2019-12-30 2019-12-30 Precast beam crack repairing construction process Pending CN111042568A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911394889.5A CN111042568A (en) 2019-12-30 2019-12-30 Precast beam crack repairing construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911394889.5A CN111042568A (en) 2019-12-30 2019-12-30 Precast beam crack repairing construction process

Publications (1)

Publication Number Publication Date
CN111042568A true CN111042568A (en) 2020-04-21

Family

ID=70241836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911394889.5A Pending CN111042568A (en) 2019-12-30 2019-12-30 Precast beam crack repairing construction process

Country Status (1)

Country Link
CN (1) CN111042568A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08302724A (en) * 1995-05-02 1996-11-19 Osaka Bosui Constr Co Ltd Method for repair construction of foundation pile
KR20060097293A (en) * 2005-03-05 2006-09-14 우신건축환경클리닉(주) Method for repairing the concrete
CN101275435A (en) * 2008-05-15 2008-10-01 浙江中富建筑集团股份有限公司 Method for mending building wall body slit
CN102199951A (en) * 2011-01-31 2011-09-28 云南巨和建设集团有限公司 Construction method for reinforcing concrete structure by using carbon fibers
CN104032712A (en) * 2013-03-05 2014-09-10 马倩 Hydraulic concrete crack patching construction method
CN106351459A (en) * 2016-08-26 2017-01-25 北海金匠水泥制品有限责任公司 High strength repairing method of crack on precast concrete units
CN106917515A (en) * 2015-12-24 2017-07-04 长沙科密水建筑材料科技有限公司 A kind of concrete microcrack reinforcing construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08302724A (en) * 1995-05-02 1996-11-19 Osaka Bosui Constr Co Ltd Method for repair construction of foundation pile
KR20060097293A (en) * 2005-03-05 2006-09-14 우신건축환경클리닉(주) Method for repairing the concrete
CN101275435A (en) * 2008-05-15 2008-10-01 浙江中富建筑集团股份有限公司 Method for mending building wall body slit
CN102199951A (en) * 2011-01-31 2011-09-28 云南巨和建设集团有限公司 Construction method for reinforcing concrete structure by using carbon fibers
CN104032712A (en) * 2013-03-05 2014-09-10 马倩 Hydraulic concrete crack patching construction method
CN106917515A (en) * 2015-12-24 2017-07-04 长沙科密水建筑材料科技有限公司 A kind of concrete microcrack reinforcing construction method
CN106351459A (en) * 2016-08-26 2017-01-25 北海金匠水泥制品有限责任公司 High strength repairing method of crack on precast concrete units

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
中国水利水电科学研究院等: "《DL/T 5251-2010水工混凝土建筑物缺陷检测和评估技术规程》", 30 September 2010, 中国电力出版社 *
广州四航工程技术研究院等: "《JTJ275-2000 海港工程混凝土结构防腐蚀技术规范》", 31 December 2001, 人民交通出版社 *

Similar Documents

Publication Publication Date Title
CN110607809B (en) Waterproof construction method for basement of building engineering
CN107246158A (en) The construction technology of carbon fiber cloth strengthening technology
CN112081146A (en) Construction method of polymer self-adhesive film waterproof coiled material capable of being constructed in rainy season
CN105604198A (en) Rigid-soft combined watertightness construction method
WO2022127095A1 (en) Lapping method for different waterproof materials of pedestal foot base plate and sidewall
CN110984406A (en) Waterproof leakage-repairing construction method using non-cured rubber asphalt waterproof coating
CN104762999A (en) Self-adhesion coiled material underground waterproof construction method
CN111395410B (en) Construction method for pre-paving asphalt-based waterproof coiled material through welding and bonding combined construction
CN111042568A (en) Precast beam crack repairing construction process
CN103206093B (en) Leakage repairing and preventing method for roof settlement joint
CN104912208A (en) Anticorrosion structure and treatment method of outer bottom edge board of gas chamber
CN111441391A (en) CBF reaction bonding macromolecule waterproof coiled material construction method
CN104153397A (en) Concrete wall construction joint waterproof treatment method
CN101586367B (en) Method for preventing decorative surfaces of ceramic tiles in shower room from leaking water
CN109537428A (en) A kind of beams of concrete face and its construction method with waterproof roll
CN104343137B (en) Underground waterproof engineering construction method
CN109057389B (en) Method for repairing reserved gap of building
CN112982497A (en) High-performance connecting structure for joint parts of new concrete and old concrete and construction method
CN103866990A (en) Method for reinforcing shear wall by using X-shaped basalt fiber cloth
CN103967079A (en) Device and method for reinforcing large aboveground water pool
CN114150712A (en) Pre-paved anti-adhesion waterproof structure and construction method
CN113605388A (en) Waterproof treatment method for underground engineering pile head
CN111877793A (en) Reinforcement construction method for continuous high-rise building engineering
CN111676908A (en) Concrete panel tensile joint and peripheral joint surface water stop structure and construction method thereof
CN113833500B (en) Restoration method for waterproof and impermeable layer of mountain cave depot

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200421