CN111007881B - BIM-based rail transit electromechanical installation engineering system and method - Google Patents

BIM-based rail transit electromechanical installation engineering system and method Download PDF

Info

Publication number
CN111007881B
CN111007881B CN201911162757.XA CN201911162757A CN111007881B CN 111007881 B CN111007881 B CN 111007881B CN 201911162757 A CN201911162757 A CN 201911162757A CN 111007881 B CN111007881 B CN 111007881B
Authority
CN
China
Prior art keywords
module
model
coordinate
length
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911162757.XA
Other languages
Chinese (zh)
Other versions
CN111007881A (en
Inventor
吴元礼
吴璁
桑春林
王萌
丁晓锋
周健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Construction Engineering Mechanical And Electrical Installation Engineering Co ltd
Original Assignee
Chongqing Construction Engineering Mechanical And Electrical Installation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Construction Engineering Mechanical And Electrical Installation Engineering Co ltd filed Critical Chongqing Construction Engineering Mechanical And Electrical Installation Engineering Co ltd
Priority to CN201911162757.XA priority Critical patent/CN111007881B/en
Publication of CN111007881A publication Critical patent/CN111007881A/en
Application granted granted Critical
Publication of CN111007881B publication Critical patent/CN111007881B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05DSYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
    • G05D3/00Control of position or direction
    • G05D3/12Control of position or direction using feedback
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B11/00Measuring arrangements characterised by the use of optical techniques
    • G01B11/002Measuring arrangements characterised by the use of optical techniques for measuring two or more coordinates
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B21/00Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant
    • G01B21/02Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring length, width, or thickness
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B21/00Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant
    • G01B21/16Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring distance of clearance between spaced objects
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

The invention discloses a rail transit electromechanical installation engineering system and method based on BIM, belonging to the technical field of electromechanical installation engineering, and comprising a plurality of measuring devices and a control system, wherein each measuring device comprises a first transverse rod, a first longitudinal rod fixedly connected to one end of the first transverse rod and mutually vertical to the first transverse rod, a second longitudinal rod connected to the first transverse rod in a sliding manner and parallel to the first longitudinal rod, and a second transverse rod connected between the first longitudinal rod and the second longitudinal rod in a sliding manner and parallel to the first transverse rod, a coordinate box is fixedly connected at the joint of the first transverse rod and the first longitudinal rod, the control system comprises a main control end used for processing an information model and outputting a comparison mark model, an acquisition end used for acquiring image information and a controlled end used for indicating the position of the measuring device, and the invention has the effect of ensuring the accurate installation position of various electromechanical articles during construction.

Description

BIM-based rail transit electromechanical installation engineering system and method
Technical Field
The invention relates to the technical field of electromechanical installation engineering, in particular to a rail transit electromechanical installation engineering system and method based on BIM.
Background
At present, electromechanical installation engineering is one of important influence factors influencing the quality of construction engineering, and large labor input and large cost expenditure are always required behind high-quality electromechanical installation engineering. In rail transit, the installation work is particularly important because the basic equipment has the characteristics of difficult maintenance and easy causing huge loss once problems occur.
Prior art can refer to the chinese utility model patent that the grant bulletin number is CN209455535U, and it discloses a novel electromechanical installation engineering numerical control hydraulic jacking device based on BIM, the power distribution box comprises a box body, the equal fixedly connected with electric telescopic handle in both sides of box inner chamber bottom, electric telescopic handle's output runs through to the outside and the fixedly connected with bearing thick stick of box, the top of bearing thick stick is provided with the mount, the fixed conveyer belt of left side fixedly connected with at box top.
The above prior art solutions have the following drawbacks: the BIM system is called a building information model, belongs to general software in the building field, and rail transit electromechanical installation engineering in a tunnel has higher requirements on the positions of a power distribution cabinet, a cable and a lamp during construction, but the installation positions of devices such as the power distribution cabinet are manually selected by depending on the approximate positions on engineering drawings at present, and the installation positions are difficult to select accurately.
Disclosure of Invention
The invention aims to provide a BIM-based rail transit electromechanical installation engineering system which can ensure that the installation positions of various electromechanical articles are accurate during construction.
The technical purpose of the invention is realized by the following technical scheme:
a rail transit electromechanical installation engineering system based on BIM comprises a plurality of measuring devices and a control system, wherein each measuring device comprises a first transverse rod, a first longitudinal rod, a second longitudinal rod and a second transverse rod, the first longitudinal rod is fixedly connected to one end of the first transverse rod and is mutually perpendicular to the first transverse rod, the second longitudinal rod is connected to the first transverse rod in a sliding mode and is parallel to the first longitudinal rod, the second transverse rod is connected between the first longitudinal rod and the second longitudinal rod in a sliding mode and is parallel to the first transverse rod, the second longitudinal rod slides along the length direction of the first transverse rod, the second transverse rod slides along the length direction of the first longitudinal rod, and a coordinate box is fixedly connected to the joint of the first transverse rod and the first longitudinal rod;
the control system comprises a main control end, an acquisition end and a controlled end;
the controlled end is arranged in the coordinate box and comprises an internal storage module and a signal transmission module;
the internal storage module stores a serial number;
the signal transmission module is used for receiving or sending information, and calls the serial number stored by the internal storage module and sends the serial number;
the acquisition end comprises image shooting equipment arranged at the top in the channel, and the acquisition end comprises an information storage module, an image acquisition module, an image processing module and a coordinate confirmation module;
the information storage module receives and stores the area number and the coordinate model;
the image acquisition module acquires image information and transmits the image information to the information storage module for storage;
the image processing module calls the image information and the coordinate model stored by the information storage module, and the image processing module combines the image information and the coordinate model to calculate the coordinate of each coordinate box in the coordinate model;
the coordinate confirmation module calls the coordinates output by the image processing module and receives the number sent by the controlled terminal, and after the coordinates and the number are associated, the coordinate confirmation module sends the associated coordinates and the number to the main control terminal;
the main control end comprises a BIM importing module, a coordinate marking module, an area segmentation module and a model comparison module;
the BIM import module receives an imported building information model;
the coordinate marking module calls a building information model imported by the BIM pouring module and marks the building information model;
the region segmentation module calls the building information model marked by the coordinate marking module, divides the building information model into a plurality of regions, sets a region mark for each region, forms an independent coordinate model for each region, and sends the region number and the coordinate model to a corresponding acquisition end;
the model comparison module receives the associated coordinates and the serial numbers sent by the acquisition end, calls the coordinate model segmented by the region segmentation module, and marks the coordinates with the serial numbers on the coordinate model to form a comparison mark model and outputs the comparison mark model.
By adopting the scheme, after the worker adjusts the measuring device according to the size of the article to be installed, the position of the measuring device on a construction site is adjusted through the control system, so that the installation position of the articles such as a power distribution cabinet, a cable and a lamp can be accurately installed.
The invention is further configured to: the controlled end further comprises a length and width monitoring module, the signal transmission module receives length and width value information and transmits the length and width value information to the internal storage module for storage, the length and width monitoring module comprises two distance sensors arranged on the first transverse rod and the first longitudinal rod, the two distance sensors respectively monitor a distance value between the first transverse rod and the second transverse rod and a distance value between the first longitudinal rod and the second longitudinal rod, the length and width monitoring module calls the length and width value information stored by the internal storage module and compares the detected distance with the length and width value information, and when the two distance values are respectively equal to the length and width value information, the length and width monitoring module outputs an alarm signal;
the master control end also comprises a length and width input module, the length and width input module receives length and width value information and corresponding numbers input from the outside, and the length and width input module sends the input length and width values to the controlled ends corresponding to the numbers.
By adopting the scheme, the staff can input the measured length and width values of the to-be-installed object through the control system, so that the accuracy of the adjustment result of the measuring device is ensured.
The invention is further configured to: the main control end also comprises an area confirmation module, the area confirmation module calls a coordinate model divided by the area division module, the coordinate confirmation module calls image information of the image processing module and sends the image information to the area confirmation module, the area confirmation module analyzes the image information and compares the image information with the coordinate model, and when the analyzed image information does not correspond to the coordinate model, the area confirmation module outputs an error signal.
By adopting the scheme, a worker can determine the installation position of the acquisition end through the control system, and if the installation position of the acquisition end is incorrect, the control system can output an error signal.
The invention is further configured to: the area confirmation module decomposes the image information into a coordinate grid diagram, compares a reference object in the coordinate grid diagram with a reference object in the coordinate model, and if the reference object coordinates are different, the analyzed image information does not correspond to the coordinate model.
By adopting the scheme, the control system can compare the coordinate of the reference object in the image information after gridding by gridding the image information shot by the acquisition end and judging the coordinate of the reference object in the image information after gridding, so that the accuracy of a comparison result is ensured.
The invention is further configured to: the main control end also comprises a display module, and the display module receives the comparison mark model output by the model comparison module and the error signal output by the area confirmation module and displays the error signal.
By adopting the scheme, the display module is convenient for workers to check the comparison mark model and the error signal.
The invention is further configured to: the main control end is set as a server or a computer.
By adopting the scheme, the server or the computer can be used as a carrier of the main control end.
The invention is further configured to: a transverse sliding groove is formed in the first transverse rod and is arranged along the length direction of the first transverse rod, a protruding block is fixedly connected to the position, corresponding to the transverse sliding groove, of the second longitudinal rod, and the protruding block is connected into the transverse sliding groove in a sliding mode; first spout has been seted up on the first vertical pole, and first spout sets up along the length direction of first vertical pole, has seted up the second spout on the second vertical pole, and the second spout sets up along the length direction of second vertical pole, and second horizontal pole sliding connection is in first spout and second spout.
Through adopting above-mentioned scheme, second vertical pole and second horizontal pole can freely slide, can keep horizontal or vertical position relation simultaneously.
The invention is further configured to: first logical groove has been seted up on first horizontal pole, first logical groove sets up along the length direction of first horizontal pole, first logical groove and first spout intercommunication, the second vertical pole corresponds first logical groove position department threaded connection and has first bolt, first bolt passes first logical groove setting, first bolt can the butt on first horizontal pole, the logical groove of second has been seted up on the first vertical pole, the second leads to the length direction setting of groove along first vertical pole, the logical groove of second and second spout intercommunication, the second horizontal pole is close to second logical groove position department threaded connection and has the second bolt, the second bolt passes the logical groove setting of second, the second bolt can the butt on first vertical pole.
Through adopting above-mentioned scheme, the staff can be through first bolt and the fixed second horizontal pole of second bolt and second vertical pole, avoids the survey device accident that has adjusted to change.
The invention aims to provide a rail transit electromechanical installation engineering method based on BIM.
The technical purpose of the invention is realized by the following technical scheme:
a rail transit electromechanical installation engineering method based on BIM comprises the following steps:
1. building a building information model on the BIM and importing the building information model into a main control end;
2. selecting a measuring device with proper size according to the building information model, and inputting the surplus value information of the installation area to the controlled end;
3. the main control end divides the building information model, and an acquisition end is installed on a construction site according to the division;
4. adjusting the length and width of the inner ring of the measuring device until the controlled end does not give an alarm any more;
5. placing the measuring device on a construction site according to the building information model;
6. the acquisition end acquires construction site image information, and the main control end processes the image information and displays a comparison mark machine model;
7. adjusting the position of the measuring device according to the comparison mark model, and repeating the step six until the marks on the comparison mark model completely correspond to each other;
8. and installing the object to be installed in the range framed by the measuring device.
By adopting the scheme, the staff can accurately find the mounting position of the article to be mounted through the control system, and the measuring device can mark the accurate position of the article to be mounted, so that the staff is not required to measure and mark.
The invention is further configured to: the third step is further set as follows:
and thirdly, the acquisition end acquires image information of a construction site, and the main control end adjusts the installation position of the acquisition end if an error signal is displayed after the image information is processed.
By adopting the scheme, the position of the acquisition end can be adjusted by a worker so as to ensure that the image information acquired by the acquisition end is input into the divided areas.
In conclusion, the invention has the following beneficial effects:
1. after the worker finishes adjusting the measuring device according to the size of the object to be installed, the worker adjusts the position of the measuring device on a construction site through the control system so as to ensure that the installation position of the objects such as a power distribution cabinet, a cable, a lamp and the like can be accurate when the objects are installed;
2. the length and width input module receives length and width value information and corresponding numbers input from the outside, and the length and width input module sends the input length and width values to the controlled end with the corresponding numbers;
3. the staff can confirm the mounted position of collection end through control system, and if the mounted position of collection end is incorrect, control system can output error signal.
Drawings
FIG. 1 is a block diagram of an overall system of a first embodiment;
FIG. 2 is a schematic view of a highlight assay device according to one embodiment;
FIG. 3 is a cross-sectional view of the first embodiment with the first runner, the second runner and the second bolt protruding;
FIG. 4 is a cross-sectional view of a first protruding bolt according to one embodiment;
fig. 5 is a system block diagram of a master end, an acquisition end and a slave end, which are highlighted in the first embodiment;
FIG. 6 is a block diagram of the highlighted length and width input module and the length and width monitoring module according to one embodiment.
In the figure, 1, measurement apparatus; 11. a first cross bar; 111. a horizontal chute; 112. a first through groove; 12. a first longitudinal bar; 121. a first chute; 122. a second through groove; 13. a second longitudinal bar; 131. a bump; 132. a first bolt; 133. a second chute; 14. a second cross bar; 142. a second bolt; 15. a coordinate box; 2. a main control end; 21. a BIM import module; 22. a coordinate marking module; 23. a region segmentation module; 24. a model comparison module; 25. a region confirmation module; 26. a display module; 27. a length and width input module; 3. a collection end; 31. an information storage module; 32. an image acquisition module; 33. a coordinate confirmation module; 34. an image processing module; 35. an image capturing device; 4. a controlled end; 41. a signal transmission module; 42. an internal storage module; 43. a length and width monitoring module; 431. a distance sensor.
Detailed Description
The first embodiment is as follows: a BIM-based rail transit electromechanical installation engineering system is shown in figure 1 and comprises a measuring device 1 and a control system. The control system comprises a main control end 2, an acquisition end 3 and a controlled end 4. The acquisition terminal 3 includes an image shooting device 35 installed at the top in the channel, and the image shooting device 35 may be a camera, an industrial camera, or other devices capable of acquiring image information. The main control end 2 is set as a server or a computer.
As shown in fig. 2 and 3, each measuring device 1 includes a first cross bar 11, a first vertical bar 12 fixedly connected to one end of the first cross bar 11 and perpendicular to the first cross bar 11, a second vertical bar 13 slidably connected to the first cross bar 11 and parallel to the first vertical bar 12, and a second cross bar 14 slidably connected between the first vertical bar 12 and the second vertical bar 13 and parallel to the first cross bar 11. The second side rail 13 slides along the longitudinal direction of the first crossbar 11, and the second crossbar 14 slides along the longitudinal direction of the first side rail 12. The first cross bar 11 is provided with a horizontal sliding groove 111, and the horizontal sliding groove 111 is arranged along the length direction of the first cross bar 11. A projection 131 (see fig. 4) is fixedly connected to the second vertical bar 13 at a position corresponding to the horizontal sliding slot 111, and the projection 131 is slidably connected in the horizontal sliding slot 111. The first vertical rod 12 is provided with a first sliding slot 121, and the first sliding slot 121 is arranged along the length direction of the first vertical rod 12. The second vertical rod 13 is provided with a second sliding slot 133, and the second sliding slot 133 is arranged along the length direction of the second vertical rod 13. The second cross bar 14 is slidably connected to the first slide groove 121 and the second slide groove 133. The joint of the first transverse rod 11 and the first longitudinal rod 12 is fixedly connected with a coordinate box 15, and the controlled end 4 is arranged in the coordinate box 15. The second side rail 13 and the second cross rail 14 can slide freely while maintaining a horizontal or vertical positional relationship.
As shown in fig. 3 and 4, the first cross bar 11 is provided with a first through groove 112, and the first through groove 112 is disposed along the length direction of the first cross bar 11. The first through groove 112 is communicated with the first sliding groove 121, a first bolt 132 is connected to the position, corresponding to the first through groove 112, of the second vertical rod 13 in a threaded manner, and the first bolt 132 penetrates through the first through groove 112. The first bolt 132 can abut on the first crossbar 11. The first side rail 12 is provided with a second through groove 122, and the second through groove 122 is arranged along the length direction of the first side rail 12. The second through groove 122 is communicated with the second through groove 133, a second bolt 142 is screwed at a position of the second crossbar 14 close to the second through groove 122, and the second bolt 142 passes through the second through groove 122. The second bolt 142 can abut against the first side member 12. The worker can fix the second cross bar 14 and the second longitudinal bar 13 by the first bolt 132 and the second bolt 142, and the adjusted measuring device 1 is prevented from being changed accidentally.
As shown in fig. 5 and 6, the controlled terminal 4 includes an internal storage module 42, a signal transmission module 41, and a length and width monitoring module 43. The acquisition terminal 3 includes an information storage module 31, an image acquisition module 32, an image processing module 34, and a coordinate confirmation module 33. The main control end 2 comprises a BIM importing module 21, a coordinate marking module 22, an area dividing module 23, a model comparing module 24, an area confirming module 25, a display module 26 and a length and width input module 27.
As shown in fig. 5, the BIM import module 21 receives the imported building information model. The coordinate marking module 22 calls the building information model imported by the BIM pouring module and marks in the building information model. The region dividing module 23 calls the building information model marked by the coordinate marking module 22, divides the building information model into a plurality of regions, sets a region mark number for each region, forms an individual coordinate model for each region, and the region dividing module 23 sends the region number and the coordinate model to the corresponding information storage module 31.
As shown in fig. 5, the information storage module 31 receives and stores the area number and the coordinate model. The image acquisition module 32 acquires image information and transmits the image information to the information storage module 31 for storage.
As shown in fig. 5, the internal storage module 42 stores numbers. The signal transmission module 41 is used for receiving or sending information, and the signal transmission module 41 calls the number stored in the internal storage module 42 and sends the number.
As shown in fig. 5, the image processing module 34 calls the image information and the coordinate model stored in the information storage module 31, and the image processing module 34 combines the image information and the coordinate model to calculate the coordinates of each coordinate box 15 in the coordinate model. The coordinate confirmation module 33 calls the coordinates output by the image processing module 34 and receives the number sent by the controlled terminal 4, and the coordinate confirmation module 33 associates the coordinates with the number and then sends the associated coordinates and number to the model comparison module 24. The model comparison module 24 receives the associated coordinates and numbers sent by the acquisition end 3, the model comparison module 24 calls the coordinate model divided by the region division module 23, and the model comparison module 24 marks the coordinates with the numbers on the coordinate model to form a comparison mark model and outputs the comparison mark model.
After the worker finishes adjusting the measuring device 1 according to the size of the article to be installed, the position of the measuring device 1 on a construction site is adjusted through the control system, so that the installation position of the article such as a power distribution cabinet, a cable and a lamp can be accurately installed.
As shown in fig. 5, the region confirmation module 25 calls the coordinate model divided by the region division module 23, and the coordinate confirmation module 33 calls the image information of the image processing module 34 and transmits the image information to the region confirmation module 25. The area confirmation module 25 decomposes the image information into a coordinate grid map, the area confirmation module 25 compares a reference object in the coordinate grid map with a reference object in the coordinate model, and if the reference object coordinates are different, the analyzed image information does not correspond to the coordinate model. When the analyzed image information does not correspond to the coordinate model, the region confirmation module 25 outputs an error signal. The staff can confirm the mounted position of collection end 3 through control system, if the mounted position of collection end 3 is incorrect, control system can output error signal.
As shown in fig. 5, the display module 26 receives and displays the comparison mark model output by the model comparison module 24 and the error signal output by the area confirmation module 25. Display module 26 facilitates the viewing of the contrasting marking model and the error signal by a worker.
As shown in fig. 6, the length and width input module 27 receives the length and width value information and the corresponding number input from the outside, and the length and width input module 27 sends the input length and width value to the signal transmission module 41 with the corresponding number. The signal transmission module 41 receives the length and width information and transmits the information to the internal storage module 42 for storage. The length and width monitoring module 43 includes two distance sensors 431 disposed on the first cross bar 11 and the first vertical bar 12, and the two distance sensors 431 respectively monitor a distance value between the first cross bar 11 and the second cross bar 14 and a distance value between the first vertical bar 12 and the second vertical bar 13. The length and width monitoring module 43 calls the length and width value information stored in the internal storage module 42 and compares the detected distance with the length and width value information, and when the two distance values are respectively equal to the length and width value information, the length and width monitoring module 43 outputs an alarm signal. The staff can input the measured length and width values of the object to be installed through the control system to ensure that the measuring device 1 has accurate adjustment results.
Example two: a rail transit electromechanical installation engineering method based on BIM comprises the following specific steps:
step one, building information models are built on the BIM and are imported into the main control end 2.
And step two, selecting a measuring device 1 with a proper size according to the building information model, and inputting the surplus value information of the installation area to the controlled terminal 4.
And step three, the main control end 2 partitions the building information model and installs the acquisition end 3 on the construction site according to the partitions. The acquisition end 3 acquires image information of a construction site, and the main control end 2 adjusts the installation position of the acquisition end 3 if an error signal is displayed after processing the image information.
And step four, adjusting the length and the width of the inner ring of the measuring device 1 until the controlled end 4 does not give an alarm.
And step five, placing the measuring device 1 on a construction site according to the building information model.
And step six, the acquisition end 3 acquires construction site image information, and the main control end 2 processes the image information and displays a comparison marker model.
And step seven, adjusting the position of the measuring device 1 according to the comparison mark model, and repeating the step six until the marks on the comparison mark model completely correspond to each other.
And step eight, mounting the article to be mounted in the range framed by the measuring device 1.
The staff can accurately find the installation position of the article to be installed through the control system, and the measuring device 1 can mark the accurate position of the article to be installed, so that the staff is not required to measure and mark. The staff can adjust the 3 positions of collection end to the region of image information input division of guaranteeing collection end 3 collection.
The embodiments of the present invention are preferred embodiments of the present invention, and the scope of the present invention is not limited by these embodiments, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.

Claims (10)

1. The utility model provides a rail transit electromechanical installation engineering system based on BIM which characterized in that: the device comprises a plurality of measuring devices (1) and a control system, wherein each measuring device (1) comprises a first transverse rod (11), a first longitudinal rod (12) fixedly connected to one end of the first transverse rod (11) and mutually perpendicular to the first transverse rod (11), a second longitudinal rod (13) connected to the first transverse rod (11) in a sliding mode and parallel to the first longitudinal rod (12), and a second transverse rod (14) connected between the first longitudinal rod (12) and the second longitudinal rod (13) in a sliding mode and parallel to the first transverse rod (11), the second longitudinal rod (13) slides along the length direction of the first transverse rod (11), the second transverse rod (14) slides along the length direction of the first longitudinal rod (12), and a coordinate box (15) is fixedly connected to the joint of the first transverse rod (11) and the first longitudinal rod (12);
the control system comprises a main control end (2), an acquisition end (3) and a controlled end (4);
the controlled end (4) is arranged in the coordinate box (15), and the controlled end (4) comprises an internal storage module (42) and a signal transmission module (41);
the internal storage module (42) stores a number;
the signal transmission module (41) is used for receiving or sending information, and the signal transmission module (41) calls the serial number stored in the internal storage module (42) and sends the serial number;
the acquisition end (3) comprises image shooting equipment (35) arranged at the top in the channel, and the acquisition end (3) comprises an information storage module (31), an image acquisition module (32), an image processing module (34) and a coordinate confirmation module (33);
the information storage module (31) receives and stores the area number and the coordinate model;
the image acquisition module (32) acquires image information and transmits the image information to the information storage module (31) for storage;
the image processing module (34) calls the image information and the coordinate model stored by the information storage module (31), and the image processing module (34) combines the image information and the coordinate model to calculate the coordinate of each coordinate box (15) in the coordinate model;
the coordinate confirmation module (33) calls the coordinates output by the image processing module (34) and receives the number sent by the controlled terminal (4), and the coordinate confirmation module (33) associates the coordinates with the number and then sends the associated coordinates and number to the main control terminal (2);
the main control end (2) comprises a BIM import module (21), a coordinate marking module (22), an area segmentation module (23) and a model comparison module (24);
the BIM import module (21) receives an imported building information model;
the coordinate marking module (22) calls the building information model imported by the BIM import module and marks the building information model;
the region segmentation module (23) calls the building information model marked by the coordinate marking module (22) and divides the building information model into a plurality of regions, a region mark is set for each region, each region forms an independent coordinate model, and the region segmentation module (23) sends a region number and the coordinate model to the corresponding acquisition end (3);
the model comparison module (24) receives the associated coordinates and serial numbers sent by the acquisition end (3), the model comparison module (24) calls the coordinate models segmented by the region segmentation module (23), and the model comparison module (24) marks the coordinates with the serial numbers on the coordinate models to form comparison mark models and outputs the comparison mark models.
2. The BIM-based rail transit electromechanical installation engineering system of claim 1, wherein: the controlled end (4) further comprises a length and width monitoring module (43), the signal transmission module (41) receives length and width value information and transmits the length and width value information to the internal storage module (42) for storage, the length and width monitoring module (43) comprises two distance sensors (431) arranged on the first transverse rod (11) and the first longitudinal rod (12), the two distance sensors (431) respectively monitor a distance value between the first transverse rod (11) and the second transverse rod (14) and a distance value between the first longitudinal rod (12) and the second longitudinal rod (13), the length and width monitoring module (43) calls the length and width value information stored by the internal storage module (42) and compares the detected distance with the length and width value information, and when the two distance values are respectively equal to the length and width value information, the length and width monitoring module (43) outputs an alarm signal;
the main control end (2) further comprises a length and width input module (27), the length and width input module (27) receives length and width value information and corresponding numbers input from the outside, and the length and width input module (27) sends the input length and width values to the controlled end (4) corresponding to the numbers.
3. The BIM-based rail transit electromechanical installation engineering system of claim 1, wherein: the main control end (2) further comprises an area confirmation module (25), the area confirmation module (25) calls a coordinate model divided by the area division module (23), the coordinate confirmation module (33) calls image information of the image processing module (34) and sends the image information to the area confirmation module (25), the area confirmation module (25) analyzes the image information and compares the image information with the coordinate model, and when the analyzed image information does not correspond to the coordinate model, the area confirmation module (25) outputs an error signal.
4. The BIM-based rail transit electromechanical installation engineering system of claim 3, wherein: the area confirmation module (25) decomposes the image information into a coordinate grid map, the area confirmation module (25) compares a comparison object in the coordinate grid map with a comparison object in the coordinate model, and if the coordinates of the comparison objects are different, the analyzed image information does not correspond to the coordinate model.
5. The BIM-based rail transit electromechanical installation engineering system of claim 3, wherein: the main control end (2) further comprises a display module (26), and the display module (26) receives the comparison mark model output by the model comparison module (24) and the error signal output by the area confirmation module (25) and displays the error signal.
6. The BIM-based rail transit electromechanical installation engineering system of claim 1, wherein: the main control end (2) is set as a server or a computer.
7. The BIM-based rail transit electromechanical installation engineering system of claim 1, wherein: a transverse sliding groove (111) is formed in the first transverse rod (11), the transverse sliding groove (111) is arranged along the length direction of the first transverse rod (11), a convex block (131) is fixedly connected to the position, corresponding to the transverse sliding groove (111), of the second longitudinal rod (13), and the convex block (131) is connected into the transverse sliding groove (111) in a sliding mode; first spout (121) have been seted up on first vertical pole (12), and first spout (121) have been seted up along the length direction setting of first vertical pole (12), have seted up second spout (133) on second vertical pole (13), and second spout (133) set up along the length direction of second vertical pole (13), and second horizontal pole (14) sliding connection is in first spout (121) and second spout (133).
8. The BIM-based rail transit electromechanical installation engineering system of claim 7, wherein: first logical groove (112) have been seted up on first horizontal pole (11), first logical groove (112) set up along the length direction of first horizontal pole (11), first logical groove (112) and first spout (121) intercommunication, second vertical pole (13) correspond first logical groove (112) position department threaded connection have first bolt (132), first bolt (132) pass first logical groove (112) setting, first bolt (132) can the butt on first horizontal pole (11), the logical groove of second (122) has been seted up on first vertical pole (12), the logical groove of second (122) sets up along the length direction of first vertical pole (12), the logical groove of second (122) and second spout (133) intercommunication, second horizontal pole (14) are close to logical groove of second (122) position department threaded connection have second bolt (142), the logical groove of second bolt (142) passes second (122) setting, second bolt (142) can the butt on first vertical pole (12).
9. A BIM-based rail transit electromechanical installation engineering method is applied to the BIM-based rail transit electromechanical installation engineering system according to any one of claims 1 to 8, and is characterized by comprising the following steps:
1. building a building information model on the BIM and importing the building information model into a main control end (2);
2. selecting a measuring device (1) with proper size according to the building information model, and inputting length and width value information of an installation area to a controlled end (4);
3. the main control end (2) partitions the building information model, and the acquisition end (3) is installed on a construction site according to the partitions;
4. adjusting the length and width of the inner ring of the measuring device (1) until the controlled end (4) does not give an alarm any more;
5. placing the measuring device (1) on a construction site according to the building information model;
6. the acquisition end (3) acquires construction site image information, and the main control end (2) processes the image information and displays a contrast mark model;
7. adjusting the position of the measuring device (1) according to the comparison mark model, and repeating the sixth step until the marks on the comparison mark model completely correspond to each other;
8. an object to be mounted is mounted within a range framed by the measuring device (1).
10. The BIM-based rail transit electromechanical installation engineering method according to claim 9, wherein the step three is further configured to:
3. the acquisition end (3) acquires image information of a construction site, and the main control end (2) adjusts the installation position of the acquisition end (3) if an error signal is displayed after processing the image information.
CN201911162757.XA 2019-11-25 2019-11-25 BIM-based rail transit electromechanical installation engineering system and method Active CN111007881B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911162757.XA CN111007881B (en) 2019-11-25 2019-11-25 BIM-based rail transit electromechanical installation engineering system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911162757.XA CN111007881B (en) 2019-11-25 2019-11-25 BIM-based rail transit electromechanical installation engineering system and method

Publications (2)

Publication Number Publication Date
CN111007881A CN111007881A (en) 2020-04-14
CN111007881B true CN111007881B (en) 2023-04-11

Family

ID=70113228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911162757.XA Active CN111007881B (en) 2019-11-25 2019-11-25 BIM-based rail transit electromechanical installation engineering system and method

Country Status (1)

Country Link
CN (1) CN111007881B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08106359A (en) * 1994-10-04 1996-04-23 Canon Inc Processor and method for information processing
JP2007072816A (en) * 2005-09-07 2007-03-22 Takenaka Komuten Co Ltd System for supporting layout of article
CN103256923A (en) * 2013-04-16 2013-08-21 上海上安机电设计事务所有限公司 BIM (Building Information Modeling)-based surveying, mapping and lofting system
CN104499714A (en) * 2014-11-13 2015-04-08 中建三局第二建设工程有限责任公司 Mechanical and electrical installation engineering construction method based on BIM platform and measuring robot
CN105303755A (en) * 2014-07-08 2016-02-03 霍尼韦尔国际公司 System and method for auto-configuration of devices in building information model
CN107702662A (en) * 2017-09-27 2018-02-16 深圳拎得清软件有限公司 Reverse monitoring method and its system based on laser scanner and BIM
CN107806176A (en) * 2017-12-01 2018-03-16 贵州精正检测有限公司 Steel construction assembled architecture and its construction method based on BIM
CN110335173A (en) * 2019-07-06 2019-10-15 中铁二十五局集团第五工程有限公司 Based on BIM construction management platform and comprehensive monitoring system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08106359A (en) * 1994-10-04 1996-04-23 Canon Inc Processor and method for information processing
JP2007072816A (en) * 2005-09-07 2007-03-22 Takenaka Komuten Co Ltd System for supporting layout of article
CN103256923A (en) * 2013-04-16 2013-08-21 上海上安机电设计事务所有限公司 BIM (Building Information Modeling)-based surveying, mapping and lofting system
CN105303755A (en) * 2014-07-08 2016-02-03 霍尼韦尔国际公司 System and method for auto-configuration of devices in building information model
CN104499714A (en) * 2014-11-13 2015-04-08 中建三局第二建设工程有限责任公司 Mechanical and electrical installation engineering construction method based on BIM platform and measuring robot
CN107702662A (en) * 2017-09-27 2018-02-16 深圳拎得清软件有限公司 Reverse monitoring method and its system based on laser scanner and BIM
CN107806176A (en) * 2017-12-01 2018-03-16 贵州精正检测有限公司 Steel construction assembled architecture and its construction method based on BIM
CN110335173A (en) * 2019-07-06 2019-10-15 中铁二十五局集团第五工程有限公司 Based on BIM construction management platform and comprehensive monitoring system

Also Published As

Publication number Publication date
CN111007881A (en) 2020-04-14

Similar Documents

Publication Publication Date Title
CN100458359C (en) Small-displacement measuring system in long-distance plane
CN105043263B (en) Displacement detection system and displacement detecting method for railway equipment
CN104316024A (en) Simple cascading camera chain measuring method and system for monitoring multipoint settlement
CN105157595A (en) Method and device for detecting deformation and defects of existing building
CN203705021U (en) Liquid crystal display data error detector of intelligent meter
CN104713491A (en) Slope monitoring system capable of obtaining three-dimensional data of slope deformation and method for obtaining three-dimensional data of slope deformation
CN103203364B (en) Milling equipment installation method
CN106767516A (en) Automated optical white light scanning instrument
DE102010050888A1 (en) Systems and methods for determining positions of underground objects
CN109164470A (en) The method and computation of real-time high-precision deformation monitoring in a kind of boring construction
CN108198224A (en) A kind of line-scan digital camera caliberating device and scaling method for stereo-visiuon measurement
CN105651160A (en) 3D laser scanner spherical target of installation positioning device and using method thereof
CN102230311A (en) Precision detection system and method applicable to slab ballastless track plate
CN106840129A (en) A kind of quick measurement subway segment central three-dimensional sits calibration method
CN108132029A (en) A kind of accurate measurement method and device of satellite antenna development system assembling
CN104634246A (en) Floating type stereo visual measuring system and measuring method for coordinates of object space
CN206989889U (en) A kind of device based on binocular stereo vision measurement stationary body volume
CN106482636A (en) Image measuring apparatus
CN204115616U (en) A kind of 3 D measuring instrument
CN111007881B (en) BIM-based rail transit electromechanical installation engineering system and method
CN111325793A (en) System and method for dynamically calibrating pixel size based on light spot in image measurement
CN205037837U (en) Detect device of crucible inside width
CN204944448U (en) The pick-up unit of existing building distortion and defect
CN103162632A (en) Three-dimensional (3D) optical displacement measuring system for centrifugal model
CN105091710A (en) Method and device for detecting inner width of crucible

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant