CN110984390A - Connecting piece fixing insulating plug for shelter installation equipment and installation method thereof - Google Patents

Connecting piece fixing insulating plug for shelter installation equipment and installation method thereof Download PDF

Info

Publication number
CN110984390A
CN110984390A CN201911353828.4A CN201911353828A CN110984390A CN 110984390 A CN110984390 A CN 110984390A CN 201911353828 A CN201911353828 A CN 201911353828A CN 110984390 A CN110984390 A CN 110984390A
Authority
CN
China
Prior art keywords
shelter
insulating plug
insulating
plug
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911353828.4A
Other languages
Chinese (zh)
Other versions
CN110984390B (en
Inventor
赵有善
谢永堃
苏萌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangzhou Tailee Special Equipment Co ltd
Original Assignee
Yangzhou Tailee Special Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangzhou Tailee Special Equipment Co ltd filed Critical Yangzhou Tailee Special Equipment Co ltd
Priority to CN201911353828.4A priority Critical patent/CN110984390B/en
Publication of CN110984390A publication Critical patent/CN110984390A/en
Application granted granted Critical
Publication of CN110984390B publication Critical patent/CN110984390B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60PVEHICLES ADAPTED FOR LOAD TRANSPORTATION OR TO TRANSPORT, TO CARRY, OR TO COMPRISE SPECIAL LOADS OR OBJECTS
    • B60P3/00Vehicles adapted to transport, to carry or to comprise special loads or objects

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Transportation (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Thermal Insulation (AREA)
  • Insulating Bodies (AREA)

Abstract

The invention discloses a connecting piece fixing insulating plug for shelter installation equipment and an installation method thereof in the technical field of shelters, wherein the insulating plug is cylindrical, a sizing block is transversely embedded in the middle of a column body, a vertical threaded hole is arranged on the sizing block, a vertical central hole communicated with the threaded hole is arranged at the upper end of the insulating plug, a glue injection hole and an air outlet hole are arranged at the upper end of the insulating plug, the glue injection hole and the air outlet hole are respectively communicated with a first opening and a second opening which are arranged on the column body, the shelter is surrounded by six shelter large plates, the shelter large plates are formed by bonding a first mask plate, a second mask plate and a heat preservation core plate clamped between the first mask plate and the second mask plate, the height of the insulating plug is equal to the sum of the thicknesses of the first mask plate and the heat preservation core plate, the insulating plug is embedded in the shelter large plate, the column body and the bottom of the insulating plug are connected with the shelter large plate through normal-temperature curing glue, and the upper end face of the insulating plug is level to the upper surface of the first mask. The insulating plug of the invention adopts a rear-mounted installation mode, can realize the installation at any place at any time, and does not influence the heat preservation and heat insulation performance of the shelter.

Description

Connecting piece fixing insulating plug for shelter installation equipment and installation method thereof
Technical Field
The invention relates to the technical field of square cabins, in particular to a connecting piece fixing insulating plug for square cabin installation equipment and an installation method thereof.
Background
The shelter is an enclosure structure which is used for installing different equipment, realizes a certain special function, can be conveniently moved and is used for equipment and personnel to work. In the prior art, a shelter is mostly of a sandwich plate structure, and a containment shell is assembled by six sandwich plates and auxiliary connecting pieces. The basic structure of each sandwich plate consists of an inner mask plate, a heat-preservation core plate and an outer mask plate. The sandwich plate structure has higher rigidity and stronger capacity of bearing distributed load, but has weaker capacity of bearing concentrated load or point load. Therefore, when the fixing equipment is installed on the shelter, the sizing block needs to be embedded in the sandwich plate in advance, and the fixing position of the installation equipment needs to be determined before the shelter is manufactured, so that the embedding position of the sizing block is accurate in the manufacturing process of the sandwich plate, and the installation position of the equipment cannot be changed at will. The manufacture of the sandwich plate puts high demands on the manufacture of the sandwich plate, and the use requirement of flexibly adjusting the position of equipment in the shelter cannot be met, so that the use of the shelter is limited.
Disclosure of Invention
The invention aims to provide a connecting piece fixing insulating plug for shelter installation equipment and an installation method thereof, which reduce the original process of placing a sizing block in advance when a sandwich plate is pressed, improve the production efficiency and the equipment installation precision, and the insulating plug adopts a rear-mounted installation mode, can be flexibly arranged according to the installation position of the equipment, realizes the installation everywhere and meets the requirement of a user for adjusting the equipment installation position.
The purpose of the invention is realized as follows: the utility model provides a fixed insulating stopper of connecting piece for shelter erection equipment, insulating stopper is the cylinder type and the shaft middle part transversely inlays and is equipped with the parallels, be equipped with vertical screw hole on the parallels, the insulating stopper upper end is equipped with the vertical centre bore with screw hole intercommunication, the insulating stopper upper end is equipped with notes rubber hole and venthole, notes rubber hole and venthole communicate with first opening and the second opening that sets up on the shaft respectively, the shelter is enclosed by six shelter planks, the shelter planks are formed by first mask, the bonding of second mask and the heat preservation core board of clamp between first mask, the second mask, insulating stopper height equals the sum of first mask and heat preservation core plate, insulating stopper inlays and establishes in the shelter planks and shaft and bottom all pass through the normal temperature curing adhesive with the shelter planks and be connected, insulating stopper up end is level with first mask upper surface.
The connecting piece fixing insulating plug for the shelter installation equipment can be used for fixing connecting pieces inside or outside a shelter. According to the characteristic that the sandwich plate structure of the shelter large plate has good load dispersing capacity, the insulating plugs are arranged, the sizing blocks are preset in the insulating plugs, the diameter of the epoxy plugs is selected according to the required point load dispersing capacity, the local rigidity of the connecting points is improved, and therefore the bearing capacity of the sandwich plate is improved. When the insulating plug is used, the diameter of the insulating plug is selected according to the tensile force and the torque which need to be borne by the connecting point. Namely, the insulation plug with larger diameter is installed at the connecting point which needs to bear larger tension and torque. The insulation plug adopts a rear-mounted installation mode, can be installed anywhere in a non-factory environment according to the installation requirement of equipment, and is flexible and convenient. And the insulating plug forms a heat-bridge-free structure on the large plate of the shelter, and does not affect the heat-insulating performance of the shelter.
As a further improvement of the invention, a filler interlayer is arranged between the column body and the heat-insulating core plate, the outer side surface of the filler interlayer is an irregular surface, and the filler interlayer is filled with solid fillers with glue. The connection area of the insulating plug and the shelter large plate is increased by arranging the filler interlayer, the connection strength is favorably improved, and the anti-torsion capacity of the insulating plug after glue injection is fixed is improved because the outer side surface of the filler interlayer is an irregular surface. And because the shrinkage of the normal-temperature curing adhesive is large, the cured adhesive is easy to be insufficient and brittle and easy to break after being dried, and the filling of the solid filler can also increase the flexibility of the whole structure, thereby avoiding the occurrence of the above conditions. In addition, through the interbedded setting of filler, can choose for use the insulating stopper that the diameter is littleer, improve the bearing capacity of insulating stopper through setting up great filler intermediate layer to can reduce on the shelter large sheet naked insulating stopper trompil size, improve the pleasing to the eye degree of shelter.
As a further improvement of the invention, the solid filler is the residue of the heat-insulating core plate, the residue of the heat-insulating core plate generated when the large shelter plate is provided with the mounting hole of the insulating plug can be fully utilized, local materials are used, and the cost is reduced.
As a further improvement of the invention, the solid filler is a filiform or net-wire solid filler, so that the shear strength is high, the toughness is high after glue drying, and the conditions of incompetence after drying and easy brittle fracture caused by high shrinkage of the normal-temperature curing glue can be further avoided.
As a further improvement of the invention, the normal temperature curing glue is added with the powdery filler, so that the flexibility of the whole structure after the glue is dried is improved, and brittle fracture is avoided.
As a further improvement of the invention, the insulating plug is an epoxy plug, and the normal temperature curing adhesive is an epoxy normal temperature curing adhesive, so that the insulating plug has the advantages of good insulativity, low thermal conductivity and high strength, and the epoxy normal temperature curing adhesive has strong affinity, so that the insulating plug and the shelter large plate are higher in connection strength and more reliable in connection by using the epoxy normal temperature curing adhesive.
The invention also discloses an installation method of the connecting piece fixing insulating plug for the shelter installation equipment, which is characterized by comprising the following steps of:
(1) drilling a round hole on the large shelter plate by using a flat drill, wherein the aperture of the round hole is equal to the diameter of the insulating plug, and the depth of the round hole is the same as the height of the insulating plug, so that the inner surface of the second mask plate is exposed;
(2) cleaning the residues of the heat preservation core plate on the inner surface of the second mask plate;
(3) extending tools such as a pick-up knife into the round hole and picking and scratching the heat-insulation core plate on the side wall of the round hole to expand the inner diameter of the round hole and form an irregular surface on the inner wall, and cleaning residues falling on the inner surface of the second mask plate;
(4) coating normal-temperature curing glue on the inner surface of the second mask plate, filling the irregular surface with a solid filler mixed with the normal-temperature curing glue, and then plugging the insulating plug into the round hole;
(5) normal temperature curing glue is injected into the glue injection hole, and the glue can be used after the normal temperature curing glue is dried for a certain time.
According to the mounting method of the connecting piece fixing insulating plug for the shelter mounting equipment, in the step (1), in order to prevent the flat drill from punching through the second mask, a limiting sleeve can be additionally arranged on the flat drill. And (3) cleaning the residues of the heat-insulating core plate in the step (2), so that the bottommost side can be expanded when the hole expansion is carried out by using a pick-up knife in the next step, and the residues of the heat-insulating core plate are cleaned, so that the insulating plug is fixed on the second mask instead of the residues of the heat-insulating core plate after the normal-temperature curing adhesive is injected subsequently, and the connection strength is ensured. In the step (3), the inner diameter of the round hole of the heat-insulating core plate layer is further enlarged through picking and scratching by a pick knife and the like, the connecting area of the insulating plug and the shelter large plate is increased, the connecting strength is favorably improved, and the anti-torsion capability of the insulating plug after glue injection fixing is improved because the inner wall of the round hole is an irregular surface. And (4) filling the periphery of the round hole with the solid filler mixed with the normal-temperature curing adhesive, so that the round hole can be conveniently attached to an irregular surface, the subsequent adhesive injection amount can be reduced, the cost is saved, the shrinkage of the normal-temperature curing adhesive is large, the round hole is easy to be not full and brittle and easy to break after being dried, the solid filler can increase the flexibility of the whole structure, and the occurrence of the above conditions is avoided. The waiting time in the step (5) is determined according to the selected varieties of the normal temperature curing adhesive, such as epoxy normal temperature curing adhesive, and the adhesive can be used after being dried for 72 hours.
As a further improvement of the method, the solid filler is the residue or filiform or net-like solid filler which is selected and scraped in the step (3) so as to improve the toughness of the glue after drying and avoid the conditions of incompetence after drying and easy brittle fracture caused by large shrinkage of the normal-temperature curing glue.
As a further improvement of the method, the normal-temperature curing glue is added with the powdery filler, so that the flexibility of the whole structure after the glue is dried is improved, and brittle fracture is avoided.
Drawings
Fig. 1 is a schematic view showing the installation of a connector-fixing insulating plug for a shelter installation apparatus according to the present invention.
The insulation core board comprises an insulation plug 1, a sizing block 2, a threaded hole 3, a glue injection hole 4, an air outlet hole 5, a first mask 6, a second mask 7, a heat preservation core board 8 and a filler interlayer 9.
Detailed Description
A fixed insulating stopper 1 of connecting piece for shelter erection equipment as shown in figure 1 wholly is the cylinder type, and the column body middle part transversely inlays and is equipped with parallels 2, is equipped with vertical screw hole 3 on the parallels 2, and the insulating stopper 1 upper end is equipped with the vertical centre bore with screw hole 3 intercommunication. The shelter is enclosed by six shelter large plates, the shelter large plates are formed by bonding a first mask 6, a second mask 7 and a heat-preservation core plate 8 clamped between the first mask 6 and the second mask 7, the height of an insulating plug 1 is equal to the sum of the thicknesses of the first mask 6 and the heat-preservation core plate 8, the insulating plug 1 is embedded in the shelter large plates, a column body and the bottom of the insulating plug are connected with the shelter large plates through normal-temperature curing glue, and the upper end face of the insulating plug 1 is level with the upper surface of the first mask 6. In order to facilitate the connection of the insulating plug 1 and the shelter large plate, the upper end of the insulating plug 1 is provided with a glue injection hole 4 and an air outlet hole 5, and the glue injection hole 4 and the air outlet hole 5 are respectively communicated with a first opening and a second opening which are arranged on the column body. Powdered fillers are added into the normal-temperature curing glue, so that the flexibility of the whole structure after the glue is dried is improved, and brittle fracture is avoided. In this embodiment, the insulating plug 1 is an epoxy plug, and the normal temperature curing adhesive is an epoxy normal temperature curing adhesive, so that the insulating plug 1 has the advantages of good insulating property, low thermal conductivity and high strength, and the epoxy normal temperature curing adhesive has strong affinity, so that the insulating plug 1 and the shelter large plate are higher in connection strength and more reliable in connection.
The connector fixing insulating plug 1 for the shelter installation equipment of the present embodiment can be used for fixing the connectors inside or outside the shelter. When the fixing device is used for fixing the connecting piece in the shelter, the first mask 6 is an inner mask, and the second mask 7 is an outer mask; when the fixing device is used for fixing the connecting piece outside the shelter, the reverse is carried out.
As shown in the figure, a filler interlayer 9 is arranged between the column body of the insulating plug 1 and the heat-insulating core plate 8, the outer side surface of the filler interlayer 9 is an irregular surface, and solid fillers with glue are filled in the filler interlayer 9. The connection area of the insulating plug 1 and the shelter large plate is increased by arranging the filler interlayer 9, the connection strength is favorably improved, and the torsion resistance of the insulating plug 1 after glue injection is fixed is improved because the outer side surface of the filler interlayer 9 is an irregular surface. And because the shrinkage of the normal-temperature curing adhesive is large, the cured adhesive is easy to be insufficient and brittle and easy to break after being dried, and the filling of the solid filler can also increase the flexibility of the whole structure, thereby avoiding the occurrence of the above conditions. In addition, through the setting of filler intermediate layer 9, can choose for use the insulating stopper 1 that the diameter is littleer, improve insulating stopper 1's bearing capacity through setting up great filler intermediate layer 9 to can reduce on the shelter large panel naked insulating stopper 1 trompil size, improve the pleasing to the eye degree of shelter. The solid filler can be selected from residues of the heat-insulating core plate 8 generated when the installation hole of the insulating plug 1 is drilled on the large plate of the shelter, local materials are used, and the cost is reduced. The solid filler can also be selected to be filiform or net-wire-shaped, so that the shearing strength is high, the toughness is high after the glue is dried, and the conditions of incompetence after drying and easy brittle fracture caused by high shrinkage of the normal-temperature curing glue can be further avoided.
According to the characteristic that the sandwich plate structure of the shelter large plate has good load dispersing capacity, the insulating plug 1 is arranged, the sizing block 2 is preset in the insulating plug 1, the diameter of the epoxy plug is selected according to the required point load dispersing capacity, the local rigidity of a connecting point is improved, and therefore the bearing capacity of the sandwich plate is improved. And because the insulation plug 1 of this embodiment adopts the postposition type mounting means, can carry out the field installation at any time everywhere as required, it is nimble convenient. And this insulating plug 1 has formed the structure of no heat bridge on the big board of shelter, does not cause any influence to the heat preservation heat-proof quality of shelter.
The installation method of the connecting piece fixing insulation plug 1 for the shelter installation equipment comprises the following steps:
(1) drilling a round hole on the large shelter plate by using a flat drill, wherein the aperture of the round hole is equal to the diameter of the insulating plug 1, and the depth of the round hole is the same as the height of the insulating plug 1, so that the inner surface of the second mask 7 is exposed;
(2) cleaning residues of the heat preservation core plate 8 on the inner surface of the second mask 7;
(3) extending tools such as a pick-up knife into the round hole and picking and scratching the heat-insulating core plate 8 on the side wall of the round hole to enlarge the inner diameter of the round hole and form an irregular surface on the inner wall, and cleaning residues falling on the inner surface of the second mask 7;
(4) coating normal-temperature curing glue on the inner surface of the second mask 7, filling the irregular surface with a solid filler mixed with the normal-temperature curing glue, and then plugging the insulating plug 1 into the round hole;
(5) normal temperature curing glue is injected inwards through the glue injection holes 4, and the glue can be used after the normal temperature curing glue is dried for a certain time.
In the step (1) of the installation method, in order to prevent the flat drill from opening the second mask 7, a limit sleeve can be additionally arranged on the flat drill. And (3) cleaning the residues of the heat-insulating core plate 8 in the step (2), so that the bottommost side can be expanded when the picking knife is used for picking and reaming the hole in the next step, and the residues of the heat-insulating core plate 8 are cleaned, so that the insulating plug 1 is fixed on the second mask 7 instead of the residues of the heat-insulating core plate 8 after the normal-temperature curing adhesive is injected subsequently, and the connection strength is ensured. In the step (3), the inner diameter of the round hole of the 8 layers of the heat-insulating core plate is further enlarged through picking and scratching by a pick knife and the like, the connecting area of the insulating plug 1 and the shelter large plate is increased, the connecting strength is favorably improved, and the anti-torsion capability of the insulating plug 1 after glue injection fixation is improved because the inner wall of the round hole is an irregular surface. And (4) filling the periphery of the round hole with the solid filler mixed with the normal-temperature curing adhesive, so that the round hole can be conveniently attached to an irregular surface, the subsequent adhesive injection amount can be reduced, the cost is saved, the shrinkage of the normal-temperature curing adhesive is large, the round hole is easy to be not full and brittle and easy to break after being dried, the solid filler can increase the flexibility of the whole structure, and the occurrence of the above conditions is avoided. The waiting time in the step (5) is determined according to the selected varieties of the normal temperature curing adhesive, such as epoxy normal temperature curing adhesive, and the adhesive can be used after being dried for 72 hours. In this embodiment, the solid filler is the residue or filiform or mesh-line solid filler scraped in step (3) to improve the toughness of the glue after drying, and the room temperature curing glue is added with the powdered filler, so as to avoid the situation of incomplete drying and brittle fracture caused by large shrinkage of the room temperature curing glue, and improve the flexibility of the whole structure after drying.
The present invention is not limited to the above-mentioned embodiments, and based on the technical solutions disclosed in the present invention, those skilled in the art can make some substitutions and modifications to some technical features without creative efforts according to the disclosed technical contents, and these substitutions and modifications are all within the protection scope of the present invention.

Claims (9)

1. The utility model provides a fixed insulating stopper of connecting piece for shelter erection equipment which characterized in that: the utility model discloses a square cabin, including insulating stopper, column body, base, cover, base, cover, base.
2. The connector-securing insulating plug for shelter installation equipment as claimed in claim 1, wherein: and a filler interlayer is arranged between the column body and the heat-insulating core plate, the outer side surface of the filler interlayer is an irregular surface, and a solid filler with glue is filled in the filler interlayer.
3. The connector-securing insulating plug for shelter installation equipment as claimed in claim 2, wherein: the solid filler is heat-insulating core board residue.
4. The connector-securing insulating plug for shelter installation equipment as claimed in claim 2, wherein: the solid filler is a filiform or net-wire solid filler.
5. The connector-securing insulating plug for shelter installation equipment as claimed in claim 1, wherein: the normal temperature curing glue is added with a powdery filler.
6. The connector-securing insulating plug for shelter installation equipment as claimed in any one of claims 1 to 5, wherein: the insulating plug is an epoxy plug, and the normal-temperature curing adhesive is an epoxy normal-temperature curing adhesive.
7. A method of installing a connector-securing insulating plug for a shelter installation as claimed in claim 1, comprising the steps of:
(1) drilling a round hole on the large shelter plate by using a flat drill, wherein the aperture of the round hole is equal to the diameter of the insulating plug, and the depth of the round hole is the same as the height of the insulating plug, so that the inner surface of the second shelter plate is exposed;
(2) cleaning the residues of the heat preservation core plate on the inner surface of the second mask plate;
(3) extending tools such as a pick-up knife into the round hole and picking and scratching the heat-insulation core plate on the side wall of the round hole to expand the inner diameter of the round hole and form an irregular surface on the inner wall, and cleaning residues falling on the inner surface of the second mask plate;
(4) coating normal-temperature curing glue on the inner surface of the second mask plate, filling the irregular surface with a solid filler mixed with the normal-temperature curing glue, and then plugging the insulating plug into the round hole;
(5) normal temperature curing glue is injected into the glue injection hole, and the glue can be used after being dried for a certain time.
8. The method of installing a connector-securing insulation plug for a shelter installation equipment as claimed in claim 7, wherein: the solid filler is the residue picked and dropped in the step (3) or a filiform or netted filiform solid filler.
9. The method of installing a connector-securing insulation plug for a shelter installation equipment as claimed in claim 7, wherein: the normal temperature curing glue is added with powdery fillers.
CN201911353828.4A 2019-12-25 2019-12-25 Connecting piece fixing insulating plug for shelter installation equipment and installation method of connecting piece fixing insulating plug Active CN110984390B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911353828.4A CN110984390B (en) 2019-12-25 2019-12-25 Connecting piece fixing insulating plug for shelter installation equipment and installation method of connecting piece fixing insulating plug

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911353828.4A CN110984390B (en) 2019-12-25 2019-12-25 Connecting piece fixing insulating plug for shelter installation equipment and installation method of connecting piece fixing insulating plug

Publications (2)

Publication Number Publication Date
CN110984390A true CN110984390A (en) 2020-04-10
CN110984390B CN110984390B (en) 2024-05-03

Family

ID=70075300

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911353828.4A Active CN110984390B (en) 2019-12-25 2019-12-25 Connecting piece fixing insulating plug for shelter installation equipment and installation method of connecting piece fixing insulating plug

Country Status (1)

Country Link
CN (1) CN110984390B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008274666A (en) * 2007-05-01 2008-11-13 Railway Technical Res Inst Anchoring part, insert and insert anchoring method
KR20110008889A (en) * 2009-07-21 2011-01-27 김종성 Anchor bolt fixing method for stone slab
CN202435766U (en) * 2011-12-30 2012-09-12 衡阳泰豪通信车辆有限公司 Shelter allowing equipment to be mounted at any position of shelter body
CN203593058U (en) * 2013-10-26 2014-05-14 衡阳泰豪通信车辆有限公司 Light shelter
CN206971258U (en) * 2017-07-14 2018-02-06 安徽华电工程咨询设计有限公司 A kind of high rim of a cup concrete foundation
CN108891097A (en) * 2018-09-14 2018-11-27 湖北三江航天红阳机电有限公司 A kind of cellular sandwich panel forming method
CN209756900U (en) * 2019-02-22 2019-12-10 苏州芳鸿雅新材料有限公司 Standard component mounting structure for military shelter honeycomb multi-interlayer cabin body
CN211774581U (en) * 2019-12-25 2020-10-27 扬州泰利特种装备有限公司 Connecting piece fixing insulating plug for shelter installation equipment

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008274666A (en) * 2007-05-01 2008-11-13 Railway Technical Res Inst Anchoring part, insert and insert anchoring method
KR20110008889A (en) * 2009-07-21 2011-01-27 김종성 Anchor bolt fixing method for stone slab
CN202435766U (en) * 2011-12-30 2012-09-12 衡阳泰豪通信车辆有限公司 Shelter allowing equipment to be mounted at any position of shelter body
CN203593058U (en) * 2013-10-26 2014-05-14 衡阳泰豪通信车辆有限公司 Light shelter
CN206971258U (en) * 2017-07-14 2018-02-06 安徽华电工程咨询设计有限公司 A kind of high rim of a cup concrete foundation
CN108891097A (en) * 2018-09-14 2018-11-27 湖北三江航天红阳机电有限公司 A kind of cellular sandwich panel forming method
CN209756900U (en) * 2019-02-22 2019-12-10 苏州芳鸿雅新材料有限公司 Standard component mounting structure for military shelter honeycomb multi-interlayer cabin body
CN211774581U (en) * 2019-12-25 2020-10-27 扬州泰利特种装备有限公司 Connecting piece fixing insulating plug for shelter installation equipment

Also Published As

Publication number Publication date
CN110984390B (en) 2024-05-03

Similar Documents

Publication Publication Date Title
WO2006001971A3 (en) Embedded antenna connection method and system
CN211774581U (en) Connecting piece fixing insulating plug for shelter installation equipment
EP2061091A1 (en) Roof or façade section with solar panel
CN203027613U (en) Laminating structure for prepreg resin plug hole
CN104507273A (en) PCB (printed circuit board) stepped hole plugging process and jig
CN206775864U (en) A kind of integrated network data acquisition device
CN110984390A (en) Connecting piece fixing insulating plug for shelter installation equipment and installation method thereof
CN103239040A (en) Hollow extruded sheet and machining method thereof
CN210210714U (en) Plate punching and fixing device
CN209964366U (en) Enhanced composite circuit board
CN209871721U (en) Apply to automatic feed mechanism of soft-packaged electrical core
CN208918487U (en) Anti-skidding tool for placing working tools between drilling rod and drilling rod
CN217630787U (en) Impact-resistant energy-saving aerated concrete block
CN210421609U (en) Novel hollow brick
CN216478239U (en) High-strength spliced aluminum-based copper-clad plate
CN221073301U (en) Green's shock attenuation construction board for construction
CN206350242U (en) Circuit board resin consent structure
CN217782425U (en) Heat insulation board convenient to fix and install
CN218634404U (en) Cross-layer mechanical blind hole high-rise plate structure
CN216740221U (en) Enclosure component with heat preservation and water prevention functions
CN212104567U (en) Connecting device for self-insulation outer wall and main body structure
CN214165727U (en) Transfer device is used in production of wooden skylight
CN217283543U (en) Flexible circuit board based on COP material
CN219863782U (en) Green for building pin-connected panel heat preservation wall body
CN214195383U (en) Building energy-saving floor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant