CN110965585A - 一种多连拱矩形隧道分拱施工方法 - Google Patents
一种多连拱矩形隧道分拱施工方法 Download PDFInfo
- Publication number
- CN110965585A CN110965585A CN201911352354.1A CN201911352354A CN110965585A CN 110965585 A CN110965585 A CN 110965585A CN 201911352354 A CN201911352354 A CN 201911352354A CN 110965585 A CN110965585 A CN 110965585A
- Authority
- CN
- China
- Prior art keywords
- arch
- motor vehicle
- tunnel
- vehicle tunnel
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明公开了一种多连拱矩形隧道分拱施工方法,包括将多连拱隧道按照机动车隧道和非机动车隧道分拱等步骤。具有土方开挖量少,土方回填数量少,回填压实度易控制,一次性浇筑混凝土体量变小,减少冷缝,避免隧道漏水的优点。
Description
技术领域
本发明涉及隧道施工领域,具体涉及一种多连拱矩形隧道分拱施工方法。
背景技术
随着城市快速路网的不断更新,城市下穿多连拱隧道、地铁多连拱U型槽、城市综合管廊施工等地下建筑正蓬勃发展,建立地下隧道正在成为城市道路建设的主旋律。
为了节约土地资源,减小对环境的影响,城市下穿多连拱隧道开始使用,跨度也越来越大。由于多连拱隧道施工工序多,并且大多是在市区内施工,因此对施工工期要求也越来越紧。传统的多连拱施工都是整体底板施工完毕后,再整体施工侧墙和顶板,完成隧道的封闭,这样的施工方式施工周期较长。与此同时,在两侧带有非机动车遂道的多连拱隧道,传统的施工方法在底板有高程差异的时候,在错台处为填补土方开挖的缝隙往往需要浇筑更多的水泥,造成施工成本的上升。因此,为了缩短施工周期必须解决大跨度多连拱隧道施工问题。
并且,传统施工工法单次混凝土浇筑量大,浇筑时间在8~12个小时不等,在城市中由于交通问题,水泥罐车前后间隔时间也较长,往往之前的水泥已经开始初凝后面的水泥罐车才到,这样的浇筑容易出现冷缝。
发明内容
本发明提供一种多连拱矩形隧道分拱施工方法。
为了达到上述发明目的,本发明采用的技术方案为:
提供一种多连拱矩形隧道分拱施工方法,其特征在于:包括如下步骤:
步骤一:将多连拱隧道按照机动车隧道、非机动车隧道分拱;
步骤二:施工支护桩和止水帷幕;
步骤三:基坑开挖,先开挖至非机动车隧道的底板高层下20cm;
步骤四:保留非机动车隧道分拱原状土,继续机动车隧道部分的基坑至底板高层下20cm,在机动车隧道和非机动车隧道分拱原状土之间预留开挖肥槽,在原状土侧面放坡并施工土钉;
步骤五:铺设水泥垫层;
步骤六:施工机动车隧道底板钢筋和模板,并完成混凝土浇筑;
步骤七:搭设支架施工机动车隧道顶板,同时在机动车隧道侧面施工非机动车隧道的底板、顶板混凝土悬挑,在悬挑中预留止水钢板;
步骤八:机动车隧道侧墙与非机动车隧道分拱原状土之间的开挖肥槽回填、夯实;
步骤九:施工非机动车隧道。
进一步的,步骤七中,悬挑预留长度约50~80cm。
进一步的,步骤四中,开挖肥槽底部宽度80cm。
进一步的,步骤八中,夯实的压实度95%。
进一步的,步骤四中,原状土侧面放坡比1:0.5。
本发明的优点在于:
1.先施工主隧道,土方开挖量变少,少扰动原状土,便于充分发挥原状土的自承能力。
2.土方回填数量少,回填压实度易控制,确保地基承载力满足要求。
3.一次性浇筑混凝土体量变小,减少冷缝,避免隧道漏水。
4.先贯通主隧道,具备施工车辆通行条件或缓解交通压力,节约施工成本。
附图说明
此处所说明的附图用来提供对本发明实施例的进一步理解,构成本申请的一部分,并不构成对本发明实施例的限定。在附图中:
图1为本发明的结构示意图;
图2为开挖肥槽的结构示意图;
图3为工艺顺序示意图。
具体实施方式
下面对本发明的具体实施方式进行描述,以便于本技术领域的技术人员理解本发明,但应该清楚,本发明不限于具体实施方式的范围,对本技术领域的普通技术人员来讲,只要各种变化在所附的权利要求限定和确定的本发明的精神和范围内,这些变化是显而易见的,一切利用本发明构思的发明创造均在保护之列。
实施例1
如图1至图3所示,包括如下步骤:
步骤一:将多连拱隧道按照机动车隧道1、非机动车隧道2分拱;
步骤二:施工支护桩和止水帷幕;
步骤三:基坑开挖,先开挖至非机动车隧道2的底板高层下20cm;
步骤四:保留非机动车隧道1分拱原状土,继续机动车隧道1部分的基坑至底板高层下20cm,在机动车隧道1和非机动车隧道1分拱原状土之间预留开挖肥槽5,在原状土侧面放坡并施工土钉4;
步骤五:铺设水泥垫层3;
步骤六:施工机动车隧道1底板钢筋和模板,并完成混凝土浇筑;
步骤七:搭设支架施工机动车隧道1顶板,同时在机动车隧道1侧面施工非机动车隧道2的底板、顶板50cm长混凝土悬挑6,在悬挑6中预留止水钢板7;
步骤八:机动车隧道1侧墙与非机动车隧道2分拱原状土之间的开挖肥槽5回填、夯实;
步骤九:施工非机动车隧道。
如图3所示,在本施工工法中,一个施工段涉及到3三次混凝土的浇筑,依次分别是机动车隧道1底板、机动车隧道1顶板和非机动车隧道1,在保障施工一体性的情况下,一次性浇筑混凝土体量变小,避免了大方量长时间混凝土浇筑过程中冷缝的产生,避免隧道漏水。
在开挖过程中最大限度的避免了对原状土的扰动,便于充分发挥原状土的自承能力,保证主体结构的后期使用寿命。
同时在本施工工法中,机动车隧道1最先贯通,具备施工车辆通行条件。避免了传统施工工法中需要等待所有隧道全体贯通才能缓解交通压力的弊端,从而缓解了隧道施工中的交通压力,节约施工成本。
实施例2
步骤一:将多连拱隧道按照机动车隧道1、非机动车隧道2分拱;
步骤二:施工支护桩和止水帷幕;
步骤三:基坑开挖,先开挖至非机动车隧道2的底板高层下20cm;
步骤四:保留非机动车隧道1分拱原状土,继续机动车隧道1部分的基坑至底板高层下20cm,在机动车隧道1和非机动车隧道1分拱原状土之间预留开挖肥槽5,在原状土侧面放坡并施工土钉4;
步骤五:铺设水泥垫层3;
步骤六:施工机动车隧道1底板钢筋和模板,并完成混凝土浇筑;
步骤七:搭设支架施工机动车隧道1顶板,同时在机动车隧道1侧面施工非机动车隧道2的底板、顶板80cm长混凝土悬挑6,在悬挑6中预留止水钢板7;
步骤八:机动车隧道1侧墙与非机动车隧道2分拱原状土之间的开挖肥槽5回填、夯实;
步骤九:施工非机动车隧道。
实施例3
在本实施例中,步骤四中原状土侧面放坡比1:0.5。边开挖机动车隧道1部分的基坑边放坡。土钉4按规范施工。
实施例4
在本实施例中,步骤四中开挖肥槽5底部宽度80cm,即非机动车隧道2分拱原状土放坡底部与机动车隧道1侧墙之间的间距为80cm。
实施例5
在本实施例中,步骤八中采用打夯机进行夯实操作,夯实的压实度95%。在本施工工法中,主体下方的土方回填仅限于开挖肥槽5,整体回填数量数量少,回填压实度易控制,确保地基承载力满足要求。
实施例6
在本实施例中,机动车隧道1底板和顶板的结合处设有止水钢板7。
Claims (5)
1.一种多连拱矩形隧道分拱施工方法,其特征在于:包括如下步骤:
步骤一:将多连拱隧道按照机动车隧道(1)、非机动车隧道(2)分拱;
步骤二:施工支护桩和止水帷幕;
步骤三:基坑开挖,先开挖至非机动车隧道(2)的底板高层下20cm;
步骤四:保留非机动车隧道(1)分拱原状土,继续机动车隧道(1)部分的基坑至底板高层下20cm,在机动车隧道(1)和非机动车隧道(1)分拱原状土之间预留开挖肥槽(5),在原状土侧面放坡并施工土钉(4);
步骤五:铺设水泥垫层(3);
步骤六:施工机动车隧道(1)底板钢筋和模板,并完成混凝土浇筑;
步骤七:搭设支架施工机动车隧道(1)顶板,同时在机动车隧道(1)侧面施工非机动车隧道(2)的底板、顶板混凝土悬挑(6),在悬挑(6)中预留止水钢板(7);
步骤八:机动车隧道(1)侧墙与非机动车隧道(2)分拱原状土之间的开挖肥槽(5)回填、夯实;
步骤九:施工非机动车隧道。
2.根据权利要求1所述的多连拱矩形隧道分拱施工方法,其特征在于:所述步骤七中,悬挑预留长度约50~80cm。
3.根据权利要求1所述的多连拱矩形隧道分拱施工方法,其特征在于:所述步骤四中,开挖肥槽(5)底部宽度80cm。
4.根据权利要求1所述的多连拱矩形隧道分拱施工方法,其特征在于:所述步骤八中,夯实的压实度95%。
5.根据权利要求1所述的多连拱矩形隧道分拱施工方法,其特征在于:所述步骤四中,原状土侧面放坡比1:0.5。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911352354.1A CN110965585B (zh) | 2019-12-25 | 2019-12-25 | 一种多连拱矩形隧道分拱施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911352354.1A CN110965585B (zh) | 2019-12-25 | 2019-12-25 | 一种多连拱矩形隧道分拱施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110965585A true CN110965585A (zh) | 2020-04-07 |
CN110965585B CN110965585B (zh) | 2021-06-22 |
Family
ID=70036336
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911352354.1A Active CN110965585B (zh) | 2019-12-25 | 2019-12-25 | 一种多连拱矩形隧道分拱施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110965585B (zh) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0913889A (ja) * | 1995-06-30 | 1997-01-14 | Furukawa Electric Co Ltd:The | 吸音施工した歩道・車道兼用トンネル |
JP2007138702A (ja) * | 2007-01-15 | 2007-06-07 | Kunie Yuguchi | トンネルの作業筒先進全断面後退掘削工法 |
JP2009215720A (ja) * | 2008-03-07 | 2009-09-24 | Nishimatsu Constr Co Ltd | 函体ガイド装置および函体のガイド方法 |
CN201588633U (zh) * | 2009-12-24 | 2010-09-22 | 中国水电顾问集团华东勘测设计研究院 | 带有人车隔离结构的人车混行长隧道 |
CN102839980A (zh) * | 2012-08-25 | 2012-12-26 | 张双茁 | 公路隧道结构及其施工方法 |
CN203476345U (zh) * | 2013-09-11 | 2014-03-12 | 中铁第四勘察设计院集团有限公司 | 一种多层多功能市政隧道 |
CN206971274U (zh) * | 2017-04-10 | 2018-02-06 | 中铁隧道勘测设计院有限公司 | 一种机动车与非机动车并存的过江隧道断面布置 |
CN109371933A (zh) * | 2018-11-23 | 2019-02-22 | 中国电建集团成都勘测设计研究院有限公司 | 水电站地下厂房通风系统 |
-
2019
- 2019-12-25 CN CN201911352354.1A patent/CN110965585B/zh active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0913889A (ja) * | 1995-06-30 | 1997-01-14 | Furukawa Electric Co Ltd:The | 吸音施工した歩道・車道兼用トンネル |
JP2007138702A (ja) * | 2007-01-15 | 2007-06-07 | Kunie Yuguchi | トンネルの作業筒先進全断面後退掘削工法 |
JP2009215720A (ja) * | 2008-03-07 | 2009-09-24 | Nishimatsu Constr Co Ltd | 函体ガイド装置および函体のガイド方法 |
CN201588633U (zh) * | 2009-12-24 | 2010-09-22 | 中国水电顾问集团华东勘测设计研究院 | 带有人车隔离结构的人车混行长隧道 |
CN102839980A (zh) * | 2012-08-25 | 2012-12-26 | 张双茁 | 公路隧道结构及其施工方法 |
CN203476345U (zh) * | 2013-09-11 | 2014-03-12 | 中铁第四勘察设计院集团有限公司 | 一种多层多功能市政隧道 |
CN206971274U (zh) * | 2017-04-10 | 2018-02-06 | 中铁隧道勘测设计院有限公司 | 一种机动车与非机动车并存的过江隧道断面布置 |
CN109371933A (zh) * | 2018-11-23 | 2019-02-22 | 中国电建集团成都勘测设计研究院有限公司 | 水电站地下厂房通风系统 |
Also Published As
Publication number | Publication date |
---|---|
CN110965585B (zh) | 2021-06-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103741714B (zh) | 地下工程全盖挖逆作法施工方法 | |
CN102758632B (zh) | 岩质地层双初支分层法修建大型地下结构的方法 | |
CN102644466B (zh) | 岩质地层中修建超浅埋大跨度暗挖地铁车站的托梁拱盖法 | |
CN108677924B (zh) | 双排微型钢管桩注浆成墙隔断结构及方法 | |
CN108343071A (zh) | 一种钢板桩组合灌注桩的基坑支护结构及施工方法 | |
CN105735354A (zh) | 一种城市地下工程盖挖全逆作施工方法 | |
CN105201516A (zh) | 一种地铁车站主体结构及其四联拱pba暗挖施工方法 | |
CN113529752A (zh) | 泡沫混凝土生态处治隧道进出口结构的施工方法 | |
CN206752667U (zh) | 一种地下室挡墙结构 | |
JP2000008394A (ja) | 駐車場設置用地下ピット等の地下構造物工事工法 | |
CN205036380U (zh) | 一种四联拱pba暗挖地铁车站主体结构 | |
CN109778903A (zh) | 一种可拆卸装配式钢筋混凝土挡土墙结构及施工方法 | |
CN112813757A (zh) | 一种用于桥头过渡处理的泡沫轻质土复合路基施工方法 | |
CN205036388U (zh) | 一种四联拱pba暗挖地铁车站的扣拱施工结构 | |
CN109681212B (zh) | 小断面黄土隧道的开挖施工方法 | |
CN102296620B (zh) | 帷幕止水护坡墙及其施工方法 | |
CN110965585B (zh) | 一种多连拱矩形隧道分拱施工方法 | |
CN113818482A (zh) | 一种减少不均匀沉降的新旧管廊连接方法 | |
JPS6117696A (ja) | 地下坑道の構築工法 | |
CN206722391U (zh) | 基于砖胎膜的地下室挡墙造型墙支模结构 | |
CN116717271B (zh) | 一种傍山整体式中墙连拱棚洞隧道结构及施工工法 | |
CN118207884B (zh) | 既有建筑拆除与新建建筑基坑支护交叉综合施工方法 | |
CN108979645A (zh) | 桥下复合曲线双层综合管廊交通环廊暗挖暨逆作施工工艺 | |
CN219218944U (zh) | 一种用于明挖隧道软基加固结构 | |
CN215669630U (zh) | 一种基于削山填沟的基础构造 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: Room 801-1, 20 Shijingshan Road, Shijingshan District, Beijing Patentee after: China Railway Construction Group Infrastructure Construction Co., Ltd Address before: Room 801-1, 20 Shijingshan Road, Shijingshan District, Beijing Patentee before: CHINA RAILWAY CONSTRUCTION GROUP MUNICIPAL ENGINEERING Co.,Ltd. |