CN110848089A - Installation jig, method for installing tower drum accessory and tower drum equipment - Google Patents

Installation jig, method for installing tower drum accessory and tower drum equipment Download PDF

Info

Publication number
CN110848089A
CN110848089A CN201911135924.1A CN201911135924A CN110848089A CN 110848089 A CN110848089 A CN 110848089A CN 201911135924 A CN201911135924 A CN 201911135924A CN 110848089 A CN110848089 A CN 110848089A
Authority
CN
China
Prior art keywords
tower
accessory
support
main body
tower drum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911135924.1A
Other languages
Chinese (zh)
Other versions
CN110848089B (en
Inventor
张禹
郭大冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinfeng Technology Co ltd
Original Assignee
Xinjiang Goldwind Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Goldwind Science and Technology Co Ltd filed Critical Xinjiang Goldwind Science and Technology Co Ltd
Priority to CN201911135924.1A priority Critical patent/CN110848089B/en
Publication of CN110848089A publication Critical patent/CN110848089A/en
Application granted granted Critical
Publication of CN110848089B publication Critical patent/CN110848089B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines

Abstract

The embodiment of the application provides an installation jig and a method for installing a tower drum accessory and tower drum equipment. This installation tool for to being in the tower section of thick bamboo of prone position or tower section of thick bamboo interior installation tower section of thick bamboo annex and tower section of thick bamboo equipment, include: a jig main body and a movable support; the tool main part includes: a support frame, an accessory limiting piece, a support mechanism and a moving piece; the accessory limiting piece is connected with the supporting frame and used for fixing and bearing the tower barrel accessories; the supporting mechanism is connected with the supporting frame and used for supporting tower drum equipment arranged on the tower drum accessory; the movable supporting part is used for being arranged in the tower barrel or the tower barrel section, the moving part is connected with the supporting frame, and the moving part is matched with the movable supporting part. The embodiment of the application adopts a horizontal installation mode, so that the tower barrel section breaks through the height limitation of hoisting machinery, and the number of the tower barrel sections can be reduced.

Description

Installation jig, method for installing tower drum accessory and tower drum equipment
Technical Field
The application relates to the technical field of wind power, in particular to a method for installing a jig and installing a tower drum accessory and tower drum equipment.
Background
A tower cylinder device is usually required to be installed in a tower cylinder of a wind generating set, and the existing installation mode usually adopts vertical installation of the tower cylinder, and specifically comprises the following steps: the tower cylinder is segmented, so that the tower cylinder section needing to be provided with the tower cylinder equipment is in a standing posture, the tower cylinder accessories are hoisted into the tower cylinder section, then the tower cylinder equipment is hoisted onto the tower cylinder accessories in the tower cylinder section, and then the tower cylinder section is transported and hoisted into the whole tower cylinder, and the tower cylinder section is in a standing posture.
The vertical installation has the following defects:
1. the height of the tower cylinder section is limited, and is required to be lower than the maximum hoisting height of the hoisting machinery, so that the number of segments of the tower cylinder is increased, the number of hoisting and splicing times for assembling the tower cylinder is increased when the number of the tower cylinder sections is increased, and the assembly cost of the tower cylinder is higher;
2. the construction process of vertical installation comprises the hoisting of a tower drum accessory and the hoisting of tower drum equipment, the hoisting times are multiple, the hoisting distance is long each time, and the installation efficiency is difficult to improve;
3. the tower sections are usually prone when leaving the factory, and before installation, each tower section needs to be turned over to a vertical position, so that a corresponding tower section turning tool, a supporting tool after the tower sections are erected, a rainproof tool and the like need to be designed, the construction process is complicated, and the manufacturing and using costs of the matched tools are high.
Disclosure of Invention
The application provides an installation jig, a method for installing a tower drum accessory and tower drum equipment aiming at the defects of the existing mode, and aims to solve at least one technical problem in the prior art.
In a first aspect, an embodiment of the present application provides a mounting jig for mounting a tower attachment and a tower apparatus in a prone position of a tower or a tower section, including: a jig main body and a movable support;
the tool main part includes: a support frame, an accessory limiting piece, a support mechanism and a moving piece;
the accessory limiting piece is connected with the supporting frame and used for fixing and bearing the tower barrel accessories;
the supporting mechanism is connected with the supporting frame and used for supporting tower drum equipment arranged on the tower drum accessory;
the movable supporting part is used for being arranged in the tower barrel or the tower barrel section, the moving part is connected with the supporting frame, and the moving part is matched with the movable supporting part.
In a second aspect, the present application provides a method for mounting a tower attachment and a tower apparatus based on the mounting jig provided in the first aspect, including the following steps:
laying the movable supporting piece of the mounting jig in a tower barrel or a tower barrel section in a prone position;
adjusting the tower drum accessory provided with the tower drum equipment into a prone position;
respectively loading and fixing the tower drum accessory and the tower drum equipment in the prone position at the accessory limiting part of the jig main body and the supporting mechanism of the jig main body;
the jig main body bearing and fixing the tower drum accessory and the tower drum equipment is integrally moved to a preset installation position in a tower drum or a tower drum section through the matching of the moving piece in the jig main body and the movable supporting piece;
and fixedly mounting the tower drum accessory with the tower drum or the tower drum section.
The beneficial technical effects brought by the technical scheme provided by the embodiment of the application comprise:
1. by adopting the horizontal installation mode provided by the embodiment of the application, the tower barrel section breaks through the height limit of hoisting machinery, the number of the segments of the tower barrel can be reduced, and after the number of the tower barrel sections is reduced, the hoisting and splicing times of the assembled tower barrel can be reduced, the number of connecting accessories used among the tower barrel sections can be reduced, and the assembly cost of the tower barrel is effectively reduced;
2. by adopting the horizontal installation mode provided by the embodiment of the application, the tower drum equipment can be directly installed on the tower drum accessory outside the tower drum, compared with the existing vertical installation mode, the problem of narrow construction space in the tower drum is avoided, and the installation between the tower drum equipment and the tower drum accessory is easier;
3. by adopting the horizontal installation mode provided by the embodiment of the application, the tower drum accessories provided with the tower drum equipment are integrally moved into the tower drum section for installation, and the installation of the tower drum equipment and the tower drum accessories can be completed by only one-time movement, namely, the movement times are few, the movement distance is short, the installation process is greatly simplified, and the installation efficiency is improved;
4. by adopting the horizontal installation mode provided by the embodiment of the application, the tower barrel section is always in a prone position from leaving factory to installing the tower barrel equipment and the tower barrel accessory, so that a plurality of links such as turning over or preventing rain, frequently hoisting the tower barrel equipment and the tower barrel accessory and the like in the existing vertical installation mode are omitted, the matched tool types are reduced, and the tool manufacturing and using cost is reduced.
Additional aspects and advantages of the present application will be set forth in part in the description which follows and, in part, will be obvious from the description, or may be learned by practice of the present application.
Drawings
The foregoing and/or additional aspects and advantages of the present application will become apparent and readily appreciated from the following description of the embodiments, taken in conjunction with the accompanying drawings of which:
fig. 1 is a schematic structural diagram of an installation jig, a tower attachment, a tower apparatus, and a tower or a tower segment according to an embodiment of the present disclosure;
FIG. 2 is an enlarged view taken at A in FIG. 1;
fig. 3 is a schematic structural view of another fixture main body, a tower drum accessory and tower drum equipment for mounting a fixture according to an embodiment of the present disclosure;
fig. 4 is a schematic structural diagram of a first embodiment of a jig main body according to an embodiment of the present disclosure;
FIG. 5 is an enlarged view at B in FIG. 4;
fig. 6 is a schematic structural diagram of a second embodiment of a jig main body according to an embodiment of the present application;
fig. 7 is a schematic flowchart of a first implementation manner of an installation method according to an embodiment of the present application;
fig. 8 is a schematic flowchart of a second implementation manner of an installation method according to an embodiment of the present application;
fig. 9 is a schematic flow chart of a third implementation manner of an installation method according to an embodiment of the present application;
fig. 10 is a schematic flowchart of a fourth implementation manner of an installation method according to an embodiment of the present application.
In the figure, the position of the upper end of the main shaft,
1-a tower or tower segment; 2-tower drum accessories; 3-tower equipment; 4, mounting a jig;
100-a jig main body;
110-a support frame; 120-an accessory restraint;
130-a support mechanism; 131-a flexible cable; 132-a fixed pulley; 133-a counterweight block;
140-detachable connections;
111-a base; 112-a vertical frame; 113-a diagonal brace;
110 a-a first support frame; 111 a-a first base; 112 a-a first stand; 113 a-a first diagonal brace;
110 b-a second support; 111 b-a second mount; 112 b-a second stand; 113 b-a second diagonal brace;
200-a moving support;
210-a first moving support; 220-second moving support.
Detailed Description
Reference will now be made in detail to the present application, examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to the same or similar parts or parts having the same or similar functions throughout. In addition, if a detailed description of the known art is not necessary for illustrating the features of the present application, it is omitted. The embodiments described below with reference to the drawings are exemplary only for the purpose of explaining the present application and are not to be construed as limiting the present application.
It will be understood by those within the art that, unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs. It will be further understood that terms, such as those defined in commonly used dictionaries, should be interpreted as having a meaning that is consistent with their meaning in the context of the prior art and will not be interpreted in an idealized or overly formal sense unless expressly so defined herein.
As used herein, the singular forms "a", "an", "the" and "the" are intended to include the plural forms as well, unless the context clearly indicates otherwise. It will be further understood that the terms "comprises" and/or "comprising," when used in this specification, specify the presence of stated features, components, and/or groups thereof, but do not preclude the presence or addition of one or more other features, components, and/or groups thereof. As used herein, the term "and/or" includes all or any element and all combinations of one or more of the associated listed items.
The terms referred to in this application will first be introduced and explained:
the standing posture means that the axial direction of components such as a tower drum or tower drum segments is vertical to the ground.
The prone position refers to the axial direction of the tower drum or tower drum segments and the like, which is parallel or approximately parallel to the ground.
Tower section of thick bamboo equipment, including the relevant electric cabinet body such as switch board, cubical switchboard, looped netowrk cabinet, or other equipment that need install to the tower section of thick bamboo such as water tank.
The tower cylinder accessory is a structure with certain strength and is used for being connected with the inner wall of a tower cylinder or a bearing structure in the tower cylinder, so that an installation place is provided for tower cylinder equipment.
The inventor of the application researches and discovers that in the technical field of wind power, the capacity of a wind generating set is increased day by day, and the related structure size in the wind generating set is also increased more and more. For example, the height of the tower is getting larger and larger, and the production and transportation become more difficult, especially for the offshore wind turbine generator system, and the production and transportation of the ultra-long tower are more difficult to support. In order to facilitate production and transportation, the tower barrel is manufactured in sections in a factory, and the tower barrel sections are assembled on a wind power generation site to obtain a complete tower barrel. Moreover, the necessary tower equipment needs to be installed into the tower. During installation, compared with the existing vertical installation mode of the tower drum, the horizontal installation mode of the tower drum has great advantages in the aspects of production cost, installation progress and safety.
The application provides an installation jig, a method for installing a tower drum accessory and tower drum equipment, and aims to solve the technical problems in the prior art.
The following describes the technical solutions of the present application and how to solve the above technical problems with specific embodiments.
The embodiment of the present application provides an installation jig 4, which is used for installing a tower drum accessory 2 and a tower drum device 3 in a tower drum or a tower drum section 1 in a prone position, and a schematic structural diagram of the installation jig 4 is shown in fig. 1 and 2, and includes: a jig main body 100 and a moving support 200;
the jig main body 100 includes: a support bracket 110, an accessory restraint 120, a support mechanism 130, and a moving member (not shown);
the accessory limiting member 120 is connected with the supporting frame 110, and the accessory limiting member 120 is used for fixing and carrying the tower accessory 2;
the supporting mechanism 130 is connected with the supporting frame 110 and is used for supporting the tower drum equipment 3 mounted on the tower drum accessory 2;
the movable support member 200 is used to be disposed in the tower or tower segment 1, the moving member is connected with the supporting frame 110, and the moving member is engaged with the movable support member 200.
In this embodiment, the movable support 200 of the mounting jig 4 is laid in the tower or tower section 1, and provides the jig main body 100 with a support for moving inside and outside the tower or tower section 1 in a lying position.
The moving member of the jig main body 100 is engaged with the moving support member 200 to constitute a movable coupling pair, such as a sliding coupling pair, a rolling coupling pair, or the like.
The support bracket 110 of the jig main body 100 provides mounting support for the accessory restraint member 120, the support mechanism 130, and the moving member, and provides sufficient load strength for the entire jig main body 100.
The accessory restraint 120 is used for fixing and carrying the tower accessory 2, and also can be used for fixing and carrying the tower accessory 2 provided with the tower equipment 3, and the accessory restraint 120 can be selected from structures such as hooks, beams, buckles and the like so as to adapt to the tower accessory 2.
The supporting mechanism 130 is configured to support the tower drum device 3 mounted on the tower drum accessory 2, and may share part of the load of the tower drum device 3 with the accessory limiting member 120, share all of the load of the tower drum device 3 with the accessory limiting member 120, and share the entire load of the tower drum accessory 2 partially mounted with the tower drum device 3 with the accessory limiting member 120.
In some embodiments, the supporting mechanism 130 may be a hydraulic cylinder or an air cylinder, and is disposed on the supporting frame 110 below the accessory limiting member 120, and the accessory limiting member 120 is lifted to share the stress load; in other embodiments, as shown in fig. 3, the supporting mechanism 130 may also be a combination structure of a flexible cable 131, a fixed pulley 132 and a weight 133, the fixed pulley 132 is disposed on the tower attachment 2 (the fixed pulley 132 may also be disposed on the supporting frame 110 above the attachment limiting member 120), one end of the flexible cable 131 is connected to the tower apparatus 3, and the other end of the flexible cable passes around the fixed pulley 132 and is connected to the weight 133, so as to share the load of the attachment limiting member 120 by pulling.
The installation jig 4 that this embodiment provided adopts horizontal mounting means, can make tower section break through the height restriction of hoist and mount machinery, and the segmentation number of reducible tower section, the quantity of tower section reduces the back, not only can reduce the hoist and mount, the concatenation number of times of assembling into a tower section, can also reduce the quantity of used connection accessory between the tower section, effectively reduces the assembly cost of a tower section.
The installation tool 4 that this embodiment provided adopts horizontal mounting means, can compare in current vertical mounting means with the earlier direct mount of tower section of thick bamboo equipment 3 on tower section of thick bamboo annex 2 outside a tower section of thick bamboo, has avoided the narrow and small problem in space of construction in a tower section of thick bamboo, and the installation between tower section of thick bamboo equipment 3 and tower section of thick bamboo annex 2 is easier.
The installation jig 4 that this embodiment provided adopts horizontal mounting means, will install tower section of thick bamboo annex 2 of tower section of thick bamboo equipment 3, wholly moves into the tower section of thick bamboo section and installs, can realize only once the immigration action can accomplish the installation of tower section of thick bamboo equipment 3 and tower section of thick bamboo annex 2, and the immigration action number of times is few, the immigration journey is short promptly, has simplified mounting process greatly to installation effectiveness has been improved.
The installation jig 4 that this embodiment provided makes the tower section be in the prone position all the time from dispatching from the factory to the in-process of installation tower section of thick bamboo equipment 3 and tower section of thick bamboo annex 2, has saved in the current vertical mounting means to the tower section stand up or rain-proof, to a great deal of links such as tower section of thick bamboo equipment 3 and tower section of thick bamboo annex 2 frequent hoist and mount, has reduced matched with frock kind, has reduced frock manufacturing, use cost.
The inventor of the present application considers that the jig main body 100, which is fixed and carries the tower attachment 2, needs to be smoothly moved in and out to avoid interference between the tower attachment 2 and the tower or the tower segment 1. To this end, the present embodiment provides one possible implementation of the mobile support 200 as follows:
as shown in FIG. 1, the moving support 200 of the present embodiment of the application is parallel to either generatrix or the central axis of the tower or tower section 1.
By adopting the arrangement mode of the movable supporting piece 200 provided by the embodiment, the movement direction of the jig body entering and exiting the tower drum or the tower drum section 1 is parallel to the axial direction of the tower drum or the tower drum section 1 as much as possible, the distance between the periphery of the tower drum accessory 2 and the inner wall of the tower drum is more easily kept unchanged, the interference between the tower drum accessory 2 and the tower drum or the tower drum section 1 can be avoided, and the effectiveness and the stability of the installation process are ensured.
Optionally, the movable supporting member 200 may extend from the inside of the tower or the tower segment 1 to the outside of the tower or the tower segment 1, that is, a part of the movable supporting member 200 is outside the tower or the tower segment 1, so that the operation of fixing and carrying the accessory 2 to the fixture body may be moved to the outside of the tower or the tower segment 1, so as to overcome the defect of inconvenient construction due to the narrow space in the tower or the tower segment 1.
Based on the above embodiments, the inventor of the present application considers that, even if the length of the mobile support 200 is extended, the mobile support 200 may be transported more difficult or the production cost may be increased due to the extended length of the mobile support 200 when the mobile support 200 is extended from the inside of the tower or the tower section 1. To this end, the present embodiment provides one possible implementation of the mobile support 200 as follows:
as shown in fig. 1, the moving support 200 of the embodiment of the present application includes: a first moving support 210 and a second moving support 220;
the first mobile support 210 is located within the tower or tower section 1; the second mobile support 220 is located outside the tower or tower section 1; the second moving support 220 is mated with and may be coaxially connected to the first moving support 210.
In this embodiment, the movable support 200 is divided into two sections, namely a first movable support 210 and a second movable support 220, which can be coaxially spliced, so that the length of the single-section movable support 200 is reduced while the movable support 200 is extended, and the production difficulty or the transportation difficulty is reduced.
Alternatively, the mobile support 200 may be divided into 3, 4, or even more segments to meet the need for reduced manufacturing costs or reduced transportation difficulties.
Alternatively, the first moving support 210 and the second moving support 220 of the embodiment of the present application are both guide rails, and the moving member includes a guide wheel or a slider;
in this embodiment, the guide rail can provide a guide for the movement of the jig body, and the guide wheel or the slider can form an effective movable connection pair with the guide rail.
Alternatively, the first movable supporting member 210 and the second movable supporting member 220 are supporting bodies each having a rolling surface, and the moving member includes a roller.
In this embodiment, the support body having the rolling surface may be a block with sufficient support strength, one block is disposed inside the tower or tower segment 1, and the other block is disposed outside the tower or tower segment 1, and the two blocks may be coaxially spliced. The support body with a rolling surface located inside the tower or tower segment 1 may be a part of the inner wall of the tower or tower segment 1.
The inventor of the present application considers that the support bracket 110 of the jig main body 100 provides mounting support for the accessory restrainer 120, the support mechanism 130, and the moving member, and provides sufficient load strength for the entire jig main body 100. For this reason, the present embodiment provides the following possible implementation manner for the supporting frame 110:
as shown in fig. 4 and 5, the support bracket 110 of the embodiment of the present application includes: a first support bracket 110a and a second support bracket 110 b;
the first support frame 110a includes: a first base 111a, a first stand 112a, and a first inclined bracket 113 a; one end of the first upright frame 112a is connected with the first base 111a, one end of the first inclined bracket 113a is connected with the other end of the first upright frame 112a, and the other end of the first inclined bracket 113a is connected with one end of the first base 111a far away from the first upright frame 112 a;
the second supporter 110b includes: a second base 111b, a second upright 112b, and a second inclined bracket 113 b; one end of the second upright frame 112b is connected with the second base 111b, one end of the second inclined bracket 113b is connected with the other end of the second upright frame 112b, and the other end of the second inclined bracket 113b is connected with one end of the second base 111b far away from the second upright frame 112 b;
the first stand 112a and the second stand 112b are oppositely connected through a detachable connecting piece 140;
the accessory limitation piece 120 is fixedly connected with one side of the first stand 112a facing the second stand 112 b;
the first base 111a and the second base 111b are connected with the moving part;
the support mechanism 130 is connected to a side of the second base 111b facing the accessory restriction member 120.
In this embodiment, the first base 111a, the first upright frame 112a and the first inclined bracket 113a of the first support frame 110a form a triangular rear quasi-triangular connection structure therebetween, so that the first support frame 110a is stable enough to support the tower attachment 2 and the tower equipment 3. The second supporting frame 110b has the same structure as the first supporting frame 110a, and thus, the description thereof is omitted.
The first stand 112a of the first support frame 110a is detachably connected with the second stand 112b of the second support frame 110 b. When the tower attachment 2 is installed, the first vertical frame 112a and the second vertical frame 112b are connected, and the first support frame 110a and the second support frame 110b form a whole, so that the jig main body 100 carrying the tower attachment 2 and the tower equipment 3 can be conveniently and smoothly moved into the tower or the tower section 1. In addition, the first support frame 110a and the second support frame 110b are arranged oppositely, and the first inclined support 113a and the second inclined support 113b can balance the overturning force of the first vertical frame 112a generated by bearing the tower attachment 2 and the tower device 3, so as to avoid the risk of the rollover of the whole jig main body 100. After the tower attachment 2 and the tower or the tower segment 1, on which the tower apparatus 3 is mounted, are mounted, the attachment limiting member 120 of the first support frame 110a is disconnected from the tower attachment 2, the support mechanism 130 of the second support frame 110b is disconnected from the tower apparatus 3, and the first vertical frame 112a is disconnected from the second vertical frame 112b, so that the jig main body 100 can be easily removed from the tower or the tower segment 1. Because the tower drum or the tower drum section 1 is lifted immediately after the support of the support mechanism 130 to the tower drum equipment 3 is removed, the tower drum or the tower drum section 1 is turned from a prone position to a standing position, the turning process time is short, the fixing strength between the tower drum equipment 3 and the tower drum accessory 2 and the fixing strength between the tower drum accessory 2 and the tower drum or the tower drum section 1 are enough to bear respective loads, namely after the support of the support mechanism 130 to the tower drum equipment 3 is removed, the tower drum accessory 2 cannot overturn, and the tower drum equipment 3 cannot fall off.
Alternatively, the detachable connector 140 is a split bolt, and a tie between the first stand 112a and the second stand 112b may be implemented. The split bolt can be a round steel bolt with two end mantle wires, or a flat steel bolt with two ends provided with long holes and wedged tightly by inserting wedge-shaped iron.
It should be understood that, in the present embodiment, the accessory limiting member 120 is connected to the first vertical frame 112a, and the supporting mechanism 130 is connected to the second base 111b, but it is also possible to adopt a manner that the accessory limiting member 120 is connected to the second vertical frame 112b, and the supporting mechanism 130 is connected to the first base 111a, that is: the accessory limiting member 120 is fixedly connected to a side of the second stand 112b facing the first stand 112a, and the support mechanism 130 is connected to a side of the first base 111a facing the accessory limiting member 120.
On the basis of the above-described embodiments, the inventors of the present application provide a further balancing structure for the overturning forces generated by the carrying of the tower attachment 2 and the tower apparatus 3. For this reason, the present embodiment provides one possible implementation manner for the first support frame 110a as follows:
the first support frame 110a of the embodiment of the present application further includes: a counterweight (not shown);
the counterweight block is connected with one end of the first base 111a far away from the first stand 112 a;
or, the counterweight is connected to a side of the first stand 112a facing away from the second stand 112 b.
In this embodiment, the weight block may further balance the overturning force of the jig main body 100 generated by bearing the tower drum accessory 2 and the tower drum device 3, so that the whole jig main body 100 bearing the tower drum accessory 2 and the tower drum device 3 is safer.
It is understood that if the accessory limiting member 120 is connected to the second standing frame 112b and the supporting mechanism 130 is connected to the first base 111a, the counterweight can be disposed on the second supporting frame 110b, that is: the second support bracket 110b further includes: a balancing weight; the counterweight block is connected with one end of the second base 111b far away from the second vertical frame 112 b; or, the counterweight is connected to a side of the second stand 112b facing away from the first stand 112 a.
The present embodiment further provides another possible implementation manner for the supporting frame 110 as follows:
as shown in fig. 6, the support bracket 110 of the embodiment of the present application includes: a base 111, a stand 112 and a diagonal bracket 113;
one end of the vertical frame 112 is connected with the base 111, one end of the inclined bracket 113 is connected with the other end of the vertical frame 112, and the other end of the inclined bracket 113 is connected with one end of the base 111 far away from the vertical frame 112;
the accessory limiting piece 120 is fixedly connected with one side of the stand 112 facing the base 111;
the base 111 is connected with the moving part;
the support mechanism 130 is connected to a side of the base 111 facing the accessory restraint 120.
The structure of the single support frame 110 adopted in the embodiment simplifies the structure of the jig main body 100, and can also save the manufacturing cost. The accessory limiting part 120 and the supporting mechanism 130 are located on the same side of the vertical frame 112, so that the gravity center of the jig main body 100 and the gravity center of the tower drum accessory 2 provided with the tower drum equipment 3 are kept in the space between the vertical frame 112 and the base 111, the overall balance of the jig main body 100 bearing the tower drum accessory 2 and the tower drum equipment 3 can be kept, and the overall safety of the jig main body 100 bearing the tower drum accessory 2 and the tower drum equipment 3 is also realized.
The present inventors have recognized that the accessory restraint 120 needs to provide stable securement and load bearing for the tower accessory 2. To this end, the present embodiment provides one possible implementation of the accessory restraint 120 as follows:
as shown in fig. 2 or 3, the attachment restraint 120 of the present embodiment is a bracket beam;
or the bracket beam is provided with a buckle (not shown) matched with the tower accessory 2.
In this embodiment, the accessory limitation piece 120 is of a bracket beam structure, the connection surface of the bracket beam to the supporting frame 110 is large, and the connection with the supporting frame 110 can be strong enough, that is, the accessory limitation piece 120 is of a bracket beam structure and can meet the requirement of bearing force. The buckle on the bracket beam can make tower section of thick bamboo annex 2 be difficult to drop from the bracket beam, connects more reliably.
In some embodiments, the appropriate mounting height of the bracket beam may be determined when the jig main body 100 is designed in the early stage according to the size of the tower or the tower section 1, so as to avoid interference between the tower accessory 2 and the tower or the tower section 1 during the process of mounting the tower accessory 2 on the tower or the tower section 1.
Based on the same inventive concept, the embodiment of the present application provides a method for installing a tower attachment 2 and a tower device 3 of any one of the installation jigs 4 provided in the foregoing embodiments, the flow chart of the method is shown in fig. 7, and the method includes the following steps S101 to S105:
s101: the mobile support 200 of the mounting fixture 4 is laid inside the tower or tower section 1 in the lying position.
S102: the tower attachment 2 with the tower apparatus 3 mounted thereon is adjusted to a prone position.
S103: the tower attachment 2 and the tower apparatus 3 in the prone position are loaded and fixed to the attachment restricting member 120 of the jig main body 100 and the support mechanism 130 of the jig main body 100, respectively.
S104: the jig main body 100 carrying and fixing the tower attachment 2 and the tower apparatus 3 is integrally moved to a predetermined mounting place in the tower or the tower segment 1 by the cooperation of the moving member in the jig main body 100 and the movable support member 200.
S105: the tower attachment 2 is fixedly mounted to the tower or tower segment 1.
In some embodiments, the installation method provided in fig. 7 may be implemented by first performing step S101 to lay the movable support 200 in the tower or tower segment 1 in the prone position, then performing steps S102-S103 to load the fixture body 100 with the tower accessory 2 and the tower equipment 3, and finally performing steps S104-S105 to feed the tower accessory 2 and the tower equipment 3 into the tower or tower segment 1 through the fixture body 100 for fixed installation.
In some embodiments, the installation method provided in fig. 7 may first perform steps S102-S103, load the tower attachment 2 and the tower apparatus 3 into the jig main body 100, then perform step S101, lay the movable support 200 in the tower or tower segment 1 in the prone position, and finally perform steps S104-S105, and send the tower attachment 2 and the tower apparatus 3 into the tower or tower segment 1 through the jig main body 100 for fixed installation.
In some embodiments, the installation method provided in fig. 7 may execute step S101 and finally steps S104-S105 in the process of executing steps S102-S103.
This embodiment adopts horizontal mounting means, can compare in current vertical mounting means with tower section of thick bamboo equipment 3 first direct mount on tower section of thick bamboo annex 2 outside a tower section of thick bamboo, has avoided the narrow and small problem in space of construction in a tower section of thick bamboo, and the installation between tower section of thick bamboo equipment 3 and tower section of thick bamboo annex 2 is easier.
By adopting a horizontal installation mode, the tower drum accessories 2 provided with the tower drum equipment 3 are integrally moved into the tower drum section for installation, and the installation of the tower drum equipment 3 and the tower drum accessories 2 can be completed by only one-time movement, namely, the movement times are few, the movement distance is short, the installation process is greatly simplified, and the installation efficiency is improved.
By adopting the horizontal installation mode, the tower cylinder section is always in a prone position from the process of leaving factory to installing the tower cylinder equipment 3 and the tower cylinder accessory 2, so that a plurality of links such as turning over or preventing rain for the tower cylinder section, frequent hoisting for the tower cylinder equipment 3 and the tower cylinder accessory 2 and the like in the existing vertical installation mode are omitted, the matched tool types are reduced, and the tool manufacturing and using cost is reduced.
On the basis of the above embodiment of the installation method, the embodiment of the present application provides a second possible implementation manner, and a flowchart of the method is shown in fig. 8, and includes the following steps S201 to S206:
s201: the mobile support 200 of the mounting fixture 4 is laid inside the tower or tower section 1 in the lying position.
S202: the jig main body 100 to which the jig 4 is to be mounted is engaged with the moving support 200 by the moving member.
S203: the tower attachment 2 with the tower apparatus 3 mounted thereon is adjusted to a prone position.
S204: the tower attachment 2 and the tower apparatus 3 in the prone position are loaded and fixed to the attachment restricting member 120 of the jig main body 100 and the support mechanism 130 of the jig main body 100, respectively.
S205: the jig main body 100 carrying and fixing the tower attachment 2 and the tower apparatus 3 is integrally moved to a predetermined mounting place in the tower or the tower segment 1 by the cooperation of the moving member in the jig main body 100 and the movable support member 200.
S206: the tower attachment 2 is fixedly mounted to the tower or tower segment 1.
On the basis of the above embodiments, the present embodiment provides support or guide for the jig main body 100 to enter or exit the tower or tower segment 1 in the prone position by adopting the cooperation of the moving member and the moving support member 200.
Optionally, in the installation method provided in this embodiment, steps S201 to S202 may be performed first, so that the jig main body 100 and the movable support 200 are in a matching state first, then steps S203 to S204 are performed, the tower accessory 2 and the tower device 3 are loaded onto the jig main body 100, and finally steps S205 to S206 are performed, and the tower accessory 2 and the tower device 3 are sent into the tower or the tower segment 1 to be fixedly installed through the jig main body 100.
Optionally, in the installation method provided in this embodiment, steps S203 to S204 may be performed first, the tower attachment 2 and the tower device 3 are loaded onto the jig main body 100, then steps S201 to S202 are performed, so that the jig main body 100 and the movable support 200 are engaged first, and finally steps S205 to S206 are performed, and the tower attachment 2 and the tower device 3 are sent into the tower or the tower segment 1 to be fixedly installed through the jig main body 100.
Alternatively, the installation method provided by this embodiment may execute steps S201 to S202 and finally execute steps S205 to S206 in the process of executing steps S203 to S204.
Alternatively, the moving support 200 may be a guide rail, and the moving member includes a guide wheel or a slider; alternatively, the moving support 200 may be a support body having a rolling surface, and the moving member includes a roller.
On the basis of the above embodiment of the installation method, the embodiment of the present application provides a third possible implementation manner, and a flowchart of the method is shown in fig. 9, and includes the following steps S301 to S307:
s301: the mobile support 200 of the mounting fixture 4 is laid inside the tower or tower section 1 in the lying position.
S302: the jig main body 100 to which the jig 4 is to be mounted is engaged with the moving support 200 by the moving member.
S303: the tower attachment 2 with the tower apparatus 3 mounted thereon is adjusted to a prone position.
S304: the tower attachment 2 and the tower apparatus 3 in the prone position are loaded and fixed to the attachment restricting member 120 of the jig main body 100 and the support mechanism 130 of the jig main body 100, respectively.
S305: starting the supporting mechanism 130 of the jig main body 100 to lift the tower barrel device 3 until the stress of the accessory limiting member 120 is reduced to a specified degree; and/or a balancing weight is connected to one side, facing away from the tower attachment 2, of the support frame of the jig main body 100.
S306: the jig main body 100 carrying and fixing the tower attachment 2 and the tower apparatus 3 is integrally moved to a predetermined mounting place in the tower or the tower segment 1 by the cooperation of the moving member in the jig main body 100 and the movable support member 200.
S307: the tower attachment 2 is fixedly mounted to the tower or tower segment 1.
On the basis of the above embodiments, in this embodiment, the tower barrel device 3 is lifted by using the supporting mechanism 130 of the jig main body 100, and part of the stressed load from the tower barrel device 3 may be shared by the accessory limiting member 120, all of the stressed load from the tower barrel device 3 may be shared by the accessory limiting member 120, and part of the stressed load of the whole tower barrel accessory 2 with the tower barrel device 3 installed therein may be shared by the accessory limiting member 120.
Optionally, in the installation method provided in this embodiment, steps S301 to S302 may be performed first, so that the jig main body 100 and the movable support 200 are engaged first, then steps S303 to S305 are performed, the tower accessory 2 and the tower device 3 are loaded onto the jig main body 100, and finally steps S306 to S307 are performed, and the tower accessory 2 and the tower device 3 are sent into the tower or the tower segment 1 to be fixedly installed through the jig main body 100.
Optionally, in the installation method provided in this embodiment, steps S303 to S305 may be performed first, the tower attachment 2 and the tower device 3 are loaded onto the jig main body 100, then steps S301 to S302 are performed, so that the jig main body 100 and the movable support 200 are engaged first, and finally steps S306 to S307 are performed, and the tower attachment 2 and the tower device 3 are sent into the tower or the tower segment 1 to be fixedly installed through the jig main body 100.
Alternatively, the installation method provided by this embodiment may execute steps S301 to S302 in the process of executing steps S303 to S305, and finally execute steps S306 to S307.
On the basis of the foregoing embodiment of the installation method, the embodiment of the present application provides a fourth possible implementation manner, and a flowchart of the method is shown in fig. 10, and includes the following steps S401 to S408:
s401: the mobile support 200 of the mounting fixture 4 is laid inside the tower or tower section 1 in the lying position.
S402: the jig main body 100 to which the jig 4 is to be mounted is engaged with the moving support 200 by the moving member.
S403: the tower attachment 2 with the tower apparatus 3 mounted thereon is adjusted to a prone position.
S404: the tower attachment 2 and the tower apparatus 3 in the prone position are loaded and fixed to the attachment restricting member 120 of the jig main body 100 and the support mechanism 130 of the jig main body 100, respectively.
S405: starting the supporting mechanism 130 of the jig main body 100 to lift the tower barrel device 3 until the stress of the accessory limiting member 120 is reduced to a specified degree; and/or a balancing weight is connected to one side, facing away from the tower attachment 2, of the support frame of the jig main body 100.
S406: the jig main body 100 carrying and fixing the tower attachment 2 and the tower apparatus 3 is integrally moved to a predetermined mounting place in the tower or the tower segment 1 by the cooperation of the moving member in the jig main body 100 and the movable support member 200.
S407: the tower attachment 2 is fixedly mounted to the tower or tower segment 1.
S408: the jig main body 100 is disconnected from the tower apparatus 3, the jig main body 100 is disconnected from the tower attachment 2, and the jig main body 100 and the movable support 200 are moved out of the tower or tower section 1.
On the basis of the above embodiments, in the present embodiment, after the tower attachment 2 and the tower or the tower segment 1 are fixedly installed, the connection between the jig main body 100 and the tower attachment 2 is released, and the jig main body 100 and the movable support member 200 are moved out of the tower or the tower segment 1, so that the tower or the tower segment 1 can be processed in the next step, for example, erecting the tower or erecting the tower segment to assemble the tower. The taken-out installation jig 4 can be used for installing the tower drum accessories 2 of the next tower drum or the tower drum section 1, and the installation jig 4 can be recycled.
Optionally, in the installation method provided in this embodiment, steps S401 to S402 may be performed first, so that the jig main body 100 and the movable support 200 are engaged first, then steps S403 to S405 are performed, the tower accessory 2 and the tower device 3 are loaded onto the jig main body 100, and finally steps S406 to S408 are performed, the tower accessory 2 and the tower device 3 are sent into the tower or the tower segment 1 through the jig main body 100 to be fixedly installed, and finally the installation jig 4 is taken out from the tower or the tower segment 1.
Optionally, in the installation method provided in this embodiment, steps S403 to S405 may be performed first, the tower attachment 2 and the tower device 3 are loaded onto the jig main body 100, then steps S401 to S402 are performed, so that the jig main body 100 and the movable support 200 are engaged first, and finally steps S406 to S408 are performed, the tower attachment 2 and the tower device 3 are sent into the tower or the tower segment 1 through the jig main body 100 to be fixedly installed, and finally the installation jig 4 is taken out from the tower or the tower segment 1.
Alternatively, the installation method provided by this embodiment may execute steps S401 to S402 in the process of executing steps S403 to S405, and finally execute steps S406 to S408.
By applying the embodiment of the application, at least the following beneficial effects can be realized:
1. by adopting a horizontal installation mode, the tower barrel section breaks through the height limit of hoisting machinery, the number of the segments of the tower barrel can be reduced, and after the number of the tower barrel sections is reduced, the hoisting and splicing times of the assembled tower barrel can be reduced, the number of connecting accessories used among the tower barrel sections can be reduced, and the assembly cost of the tower barrel is effectively reduced;
2. by adopting a horizontal installation mode, the tower drum equipment 3 can be directly installed on the tower drum accessory 2 outside the tower drum, compared with the existing vertical installation mode, the problem of narrow construction space in the tower drum is avoided, and the installation between the tower drum equipment 3 and the tower drum accessory 2 is easier;
3. the tower drum accessories 2 provided with the tower drum equipment 3 are integrally moved into the tower drum section for installation in a horizontal installation mode, so that the installation of the tower drum equipment 3 and the tower drum accessories 2 can be completed only by one-time moving-in action, namely the moving-in action is less in times and short in moving-in distance, the installation process is greatly simplified, and the installation efficiency is improved;
4. the tower cylinder section is always in a prone position in the process from leaving a factory to mounting the tower cylinder equipment 3 and the tower cylinder accessories 2 by adopting a horizontal mounting mode, so that various links such as turning over or preventing rain for the tower cylinder section, frequent hoisting for the tower cylinder equipment 3 and the tower cylinder accessories 2 and the like in the existing vertical mounting mode are omitted, the types of matched tools are reduced, and the manufacturing and using cost of the tools is reduced;
5. the horizontal support mechanism 130 is used for supporting the tower drum equipment 3 mounted on the tower drum accessory 2, and can be used for sharing part of the stress load from the tower drum equipment 3 for the accessory limiting part 120, sharing all the stress load from the tower drum equipment 3 for the accessory limiting part 120, and sharing the whole stress load of the tower drum accessory 2 partially mounted with the tower drum equipment 3 for the accessory limiting part 120.
Those of skill in the art will appreciate that the various operations, methods, steps in the processes, acts, or solutions discussed in this application can be interchanged, modified, combined, or eliminated. Further, other steps, measures, or schemes in various operations, methods, or flows that have been discussed in this application can be alternated, altered, rearranged, broken down, combined, or deleted. Further, steps, measures, schemes in the prior art having various operations, methods, procedures disclosed in the present application may also be alternated, modified, rearranged, decomposed, combined, or deleted.
In the description of the present application, it is to be understood that the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience in describing the present application and simplifying the description, but do not indicate or imply that the referred device or element must have a particular orientation, be constructed in a particular orientation, and be operated, and thus should not be construed as limiting the present application.
The terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present application, "a plurality" means two or more unless otherwise specified.
In the description of the present application, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present application can be understood in a specific case by those of ordinary skill in the art.
In the description herein, particular features, structures, materials, or characteristics may be combined in any suitable manner in any one or more embodiments or examples.
It should be understood that, although the steps in the flowcharts of the figures are shown in order as indicated by the arrows, the steps are not necessarily performed in order as indicated by the arrows. The steps are not performed in the exact order shown and may be performed in other orders unless explicitly stated herein. Moreover, at least a portion of the steps in the flow chart of the figure may include multiple sub-steps or multiple stages, which are not necessarily performed at the same time, but may be performed at different times, which are not necessarily performed in sequence, but may be performed alternately or alternately with other steps or at least a portion of the sub-steps or stages of other steps.
The foregoing is only a partial embodiment of the present application, and it should be noted that, for those skilled in the art, several modifications and decorations can be made without departing from the principle of the present application, and these modifications and decorations should also be regarded as the protection scope of the present application.

Claims (12)

1. An installation jig (4) for installing a tower drum accessory (2) and a tower drum device (3) into a tower drum or a tower drum section (1) in a prone position, characterized by comprising: a jig main body (100) and a movable support (200);
the jig main body (100) includes: a support frame (110), an accessory limiting piece (120), a support mechanism (130) and a moving piece;
the accessory limiting piece (120) is connected with the supporting frame (110), and the accessory limiting piece (120) is used for fixing and carrying a tower accessory (2);
the supporting mechanism (130) is connected with the supporting frame (110) and is used for supporting tower drum equipment (3) mounted on the tower drum accessory (2);
the movable supporting part (200) is used for being arranged in the tower drum or the tower drum section (1), the moving part is connected with the supporting frame (110), and the moving part is matched with the movable supporting part (200).
2. The mounting fixture (4) according to claim 1, characterized in that the mobile support (200) is parallel to either generatrix or central axis of the tower or tower segment (1).
3. The mounting jig (4) according to claim 1, characterized in that the mobile support (200) comprises a first mobile support (210) and a second mobile support (220);
-said first mobile support (210) is located inside said tower or said tower section (1); the second mobile support (220) being located outside the tower or the tower section (1); the second mobile support (220) is compatible with and coaxially connectable to the first mobile support (210).
4. The mounting fixture (4) according to claim 3, wherein the first mobile support (210) and the second mobile support (220) are both guide rails, the mobile element comprising a guide wheel or a slider;
or, the first moving support (210) and the second moving support (220) are both support bodies with rolling surfaces, and the moving member comprises a roller.
5. The mounting fixture (4) of claim 1, wherein the support bracket (110) comprises a first support bracket (110a) and a second support bracket (110 b);
the first support frame (110a) includes: a first base (111a), a first stand (112a) and a first inclined bracket (113 a); one end of the first stand (112a) is connected with the first base (111a), one end of the first inclined bracket (113a) is connected with the other end of the first stand (112a), and the other end of the first inclined bracket (113a) is connected with one end, far away from the first stand (112a), of the first base (111 a);
the second support bracket (110b) includes: a second base (111b), a second stand (112b) and a second inclined bracket (113 b); one end of the second vertical frame (112b) is connected with the second base (111b), one end of the second inclined bracket (113b) is connected with the other end of the second vertical frame (112b), and the other end of the second inclined bracket (113b) is connected with one end, far away from the second vertical frame (112b), of the second base (111 b);
the first stand frame (112a) and the second stand frame (112b) are oppositely connected through a detachable connecting piece (140);
the accessory limiting piece (120) is fixedly connected with one side of the first stand (112a) facing the second stand (112 b);
the first base (111a) and the second base (111b) are connected with the moving part;
the support mechanism (130) is connected to a side of the second mount facing the accessory restraint (120).
6. The mounting fixture (4) according to claim 5, wherein the first support frame (110a) further comprises: a balancing weight;
the counterweight block is connected with one end of the first base (111a) far away from the first stand (112 a);
or the counterweight block is connected with one side of the first vertical frame (112a) back to the second vertical frame (112 b).
7. The mounting fixture (4) according to claim 1, wherein the support frame (110) comprises: a base (111), a vertical frame (112) and an inclined bracket (113);
one end of the vertical frame (112) is connected with the base (111), one end of the inclined bracket (113) is connected with the other end of the vertical frame (112), and the other end of the inclined bracket (113) is connected with one end, far away from the vertical frame (112), of the base (111);
the accessory limiting piece (120) is fixedly connected with one side of the stand (112) facing the base (111);
the base (111) is connected with the moving part;
the support mechanism (130) is connected to a side of the base (111) facing the accessory restraint (120).
8. The mounting fixture (4) according to any one of claims 1-7, wherein the accessory restraint (120) is a bracket beam;
or the accessory limiting part (120) is a bracket beam, and a buckle matched with the tower drum accessory (2) is arranged on the bracket beam.
9. A method of mounting a tower accessory (2) and a tower equipment (3) based on a mounting fixture (4) according to any one of claims 1-8, comprising:
laying the movable supporting piece (200) of the mounting jig (4) in a tower barrel or a tower barrel section (1) in a prone position;
adjusting the tower drum accessory (2) provided with the tower drum equipment (3) into a prone position;
respectively loading and fixing the tower drum accessory (2) and the tower drum equipment (3) in a prone position at an accessory limiting piece (120) of the jig main body (100) and a supporting mechanism (130) of the jig main body (100);
the jig main body (100) bearing and fixing the tower drum accessory (2) and the tower drum equipment (3) is integrally moved to a preset installation position in the tower drum or the tower drum section (1) through the matching of a moving piece in the jig main body (100) and the movable supporting piece (200);
and fixedly mounting the tower drum accessory (2) and the tower drum or the tower drum section (1).
10. The mounting method according to claim 9, wherein said laying of the mobile support (200) of the mounting jig (4) in the lying position within the tower or tower section (1) further comprises:
and the jig main body (100) of the mounting jig (4) is matched with the movable supporting piece (200) through a moving piece.
11. The mounting method according to claim 9, wherein the step of loading and fixing the tower attachment (2) and the tower equipment (3) in the prone position at the attachment limiting member (120) of the jig main body (100) and the supporting mechanism (130) of the jig main body (100) respectively further comprises:
starting a supporting mechanism (130) of the jig main body (100) to lift the tower barrel device (3) until the stress of the accessory limiting piece (120) is reduced to a specified degree;
and/or a balancing weight is connected to one side, facing away from the tower drum accessory (2), of the support frame (110) of the jig main body (100).
12. The method for mounting according to claim 9, wherein, after the step of fixedly mounting the tower attachment (2) to the tower or the tower segment (1), further comprising:
the connection between the jig main body (100) and the tower drum equipment (3) is released, the connection between the jig main body (100) and the tower drum accessory (2) is released, and the jig main body (100) and the movable support member (200) are moved out of the tower drum or the tower drum section.
CN201911135924.1A 2019-11-19 2019-11-19 Installation jig, method for installing tower drum accessory and tower drum equipment Active CN110848089B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911135924.1A CN110848089B (en) 2019-11-19 2019-11-19 Installation jig, method for installing tower drum accessory and tower drum equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911135924.1A CN110848089B (en) 2019-11-19 2019-11-19 Installation jig, method for installing tower drum accessory and tower drum equipment

Publications (2)

Publication Number Publication Date
CN110848089A true CN110848089A (en) 2020-02-28
CN110848089B CN110848089B (en) 2022-07-05

Family

ID=69602372

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911135924.1A Active CN110848089B (en) 2019-11-19 2019-11-19 Installation jig, method for installing tower drum accessory and tower drum equipment

Country Status (1)

Country Link
CN (1) CN110848089B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101435415A (en) * 2007-11-15 2009-05-20 通用电气公司 Methods and systems for assembling a tower
CN201824125U (en) * 2010-10-27 2011-05-11 三一电气有限责任公司 Bolt tightening machine
DE102009055726A1 (en) * 2009-11-26 2011-06-01 Aerodyn Engineering Gmbh Inner installation element for tubular tower of wind turbine, has module element for allowing shifting of element along inner wall of tubular tower in axial direction, where module and supporting elements are fastened to corner posts
US20150316024A1 (en) * 2012-11-29 2015-11-05 Vestas Wind Systems A/S Method for moving wind turbine components and a transport system for moving wind turbine components
CN107923361A (en) * 2015-06-30 2018-04-17 维斯塔斯风力系统有限公司 The method of mobile wind turbine component and the transportation system for moving wind turbine component
CN110182684A (en) * 2019-06-24 2019-08-30 中国水电四局(阳江)海工装备有限公司 Tower attachment horizontal installation ancillary equipment and the horizontal installation method of tower attachment
CN209321600U (en) * 2018-12-17 2019-08-30 中国水电四局(阳江)海工装备有限公司 Fitting device is used in the horizontal transport of wind-power tower

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101435415A (en) * 2007-11-15 2009-05-20 通用电气公司 Methods and systems for assembling a tower
DE102009055726A1 (en) * 2009-11-26 2011-06-01 Aerodyn Engineering Gmbh Inner installation element for tubular tower of wind turbine, has module element for allowing shifting of element along inner wall of tubular tower in axial direction, where module and supporting elements are fastened to corner posts
CN201824125U (en) * 2010-10-27 2011-05-11 三一电气有限责任公司 Bolt tightening machine
US20150316024A1 (en) * 2012-11-29 2015-11-05 Vestas Wind Systems A/S Method for moving wind turbine components and a transport system for moving wind turbine components
CN107923361A (en) * 2015-06-30 2018-04-17 维斯塔斯风力系统有限公司 The method of mobile wind turbine component and the transportation system for moving wind turbine component
CN209321600U (en) * 2018-12-17 2019-08-30 中国水电四局(阳江)海工装备有限公司 Fitting device is used in the horizontal transport of wind-power tower
CN110182684A (en) * 2019-06-24 2019-08-30 中国水电四局(阳江)海工装备有限公司 Tower attachment horizontal installation ancillary equipment and the horizontal installation method of tower attachment

Also Published As

Publication number Publication date
CN110848089B (en) 2022-07-05

Similar Documents

Publication Publication Date Title
CN101410618B (en) Lifting tool for mounting a wind-power generator
US8469209B2 (en) Removal apparatus for a torque converter and a starting motor from an auxiliary compartment on a gas turbine
JP6285546B2 (en) Assembly and method for lifting a load
US10012005B2 (en) Crane system incorporated into a tower
ITMI20092007A1 (en) WIND POWER PLANT FOR THE GENERATION OF ELECTRICITY AND METHOD TO REALIZE A PYLON OF THE ABOVE WIND FACILITY
CN104234200A (en) Ring-by-ring lifting mounting method for suspendome cable-bar system
JP2008162749A (en) Jib crane
JP3827321B1 (en) Windmill assembling apparatus and assembling method
CN112942661B (en) Construction method of stay cable with flexible cable net boundary
CN110848089B (en) Installation jig, method for installing tower drum accessory and tower drum equipment
CN109989590B (en) Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam
US20140231067A1 (en) Base beam and self-propelled derrick rig assembly
US9212524B2 (en) Methods of supporting a self-propelled derrick rig
JP3905103B2 (en) Tower-like building erection method and erection device
US8474633B2 (en) Methods of removing a torque converter and a starting motor from an auxiliary compartment of a gas turbine
US20140232094A1 (en) Counterweight assembly for a self-propelled derrick rig assembly
US20140231609A1 (en) Base beam for supporting a self-propelled derrick rig
JP3749602B2 (en) Directly erected construction method of large roof
CN110552542A (en) Construction method of conical building structure
CN218613790U (en) Centralized photovoltaic module mounting machine
CN110002354B (en) Hoisting system and hoisting method for heavy pipeline equipment in complex space
CN108584713B (en) Novel process and equipment for hoisting assembly type component
CN218114742U (en) Carrying pole beam hoisting system and carrying pole beam hoisting system
CN219384604U (en) Auxiliary device convenient to spatial structure is assembled aloft
JP7209413B2 (en) CONCRETE FORM EQUIPMENT CONSTRUCTION METHOD, DISMOVERMENT METHOD, AND PULLEY SUPPORT MEMBER FOR CONCRETE FORM EQUIPMENT

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No.107 Shanghai Road, Urumqi Economic and Technological Development Zone, Urumqi City, Xinjiang Uygur Autonomous Region

Patentee after: Jinfeng Technology Co.,Ltd.

Address before: No.107 Shanghai Road, Urumqi Economic and Technological Development Zone, Urumqi City, Xinjiang Uygur Autonomous Region

Patentee before: XINJIANG GOLDWIND SCIENCE & TECHNOLOGY Co.,Ltd.

CP01 Change in the name or title of a patent holder