Prior art keywords
equalizer bar
tower
attachment
horizontal installation
connection structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910553173.9A
Other languages
Chinese (zh)
Inventor
时慧
张萍
张浩然
段鹏凯
李文文
周艺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Hydropower Fourth Bureau (yangjiang) Marine Equipment Co Ltd
Original Assignee
China Hydropower Fourth Bureau (yangjiang) Marine Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Hydropower Fourth Bureau (yangjiang) Marine Equipment Co Ltd filed Critical China Hydropower Fourth Bureau (yangjiang) Marine Equipment Co Ltd
Priority to CN201910553173.9A priority Critical patent/CN110182684A/en
Publication of CN110182684A publication Critical patent/CN110182684A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/22Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Wind Motors (AREA)

Abstract

The present invention discloses a kind of horizontal installation ancillary equipment of tower attachment, including equalizer bar, clump weight and traction piece.The clump weight is along the proximal end that the length direction of the equalizer bar is in that position is adjustably assemblied in the equalizer bar, the equalizer bar has for the first connection structure with lifting appliance assembly connection and for the second connection structure with the traction piece assembly connection, second connection structure is located at the proximal end of the equalizer bar, and the traction piece is installed at second connection structure.Tower attachment horizontal installation ancillary equipment of the invention has the advantages that easy to operate, installation effectiveness is high and reduces man power and material.In addition, the invention also discloses a kind of horizontal installation methods of tower attachment.

Description

Tower attachment horizontal installation ancillary equipment and the horizontal installation method of tower attachment
Technical field
The present invention relates to the equipment of auxiliary tower attachment installation more particularly to a kind of horizontal installation auxiliary of tower attachment to set The standby and horizontal installation method of tower attachment.
Background technique
Wind-power tower is the capital equipment for supporting high altitude wind power generator group, and height generally has 80 meters or so, is divided into 4 sections, Tower diameter is about between 5 meters to 8 meters.In actual production, wind-power tower detachable accessory quantity is more, tonnage is heavier and attachment Size is larger.
Currently, there are two types of the forms of wind-power tower attachment installation: first is that tower turns over vertical installation form;Second is that tower Horizontal installation form.Wherein, the first installation form is that tower is turned over vertical placement using lifting equipment to fix, and is recycled Heavy equipment successively hangs in attachment from suitable for reading, and personnel enter the docking of cooperation accessory position and fastening in tower.And such lifting Mode has certain defect: first is that one section about 130 tons of tower, need large-tonnage lifting equipment;Second is that one section about 20 meters of tower, it rises Heavy equipment need to be lifted to attachment 20 meters or more, can just hang in attachment in tower, and attachment must be in order under in tower It is successively installed on and, lifting equipment uses frequent;Third is that attachment hang in personnel after tower to cooperate in tower dock and Fastening, personnel safety cannot be guaranteed;Fourth is that lifting personnel will appear blind area, and there is collisions in this way after attachment hangs in tower The risk that tower causes paint to damage.
Second of installation form needs more people's cooperations, and attachment is lifted in the horizontal tower put and is installed.And in this way Mounting means also there is certain defect: first is that piece attachments tonnage is heavier and size is larger, more people's cooperations is needed to lift attachment Enter in tower, recycles equipment of ascending a height to be docked and fastened, expend a large amount of manpower, and efficiency is lower, safety is also poor.
Therefore, it is badly in need of that a kind of horizontal installation method of tower attachment and the horizontal installation of tower attachment is wanted to be overcome with ancillary equipment Above-mentioned defect.
Summary of the invention
A purpose of the present invention is that provide a kind of horizontal installation ancillary equipment of tower attachment, have it is easy to operate, mention High installation effectiveness and reduce the talent and the advantages of financial resources.
Another object of the present invention is to provide a kind of horizontal installation householder method of tower attachment, have it is easy to operate, The advantages of improving installation effectiveness and reducing the talent and financial resources.
To achieve the above object, the horizontal installation ancillary equipment of tower attachment of the invention include equalizer bar, clump weight and Traction piece.The clump weight is adjustably assemblied in the proximal end of the equalizer bar in position along the length direction of the equalizer bar, The equalizer bar has for the first connection structure with lifting appliance assembly connection and is used for and the traction piece assembly connection The second connection structure, second connection structure is located at the proximal end of the equalizer bar, and the traction piece is installed on described At two connection structures.
Preferably, the horizontal installation ancillary equipment of tower attachment of the invention further includes baffle, the baffle is installed on institute The far-end of equalizer bar is stated, first connection structure is located at the baffle and described second along the length direction of the equalizer bar Between connection structure.
Preferably, the clump weight is located at immediately below the proximal end of the equalizer bar, the clump weight is also slidedly arranged on described flat At balance beam.
Preferably, the equalizer bar extends downwardly out along the first spaced apart outstanding ear of the length direction of the equalizer bar and the Two outstanding ears, the clump weight between the described first outstanding ear and the second outstanding ear, the first outstanding ear and the described second outstanding ear it Between be also equipped with guide part, the guide part is placed through the clump weight along the length direction of the equalizer bar.
Preferably, first connection structure at least two and arranged spaced apart along the length direction of the equalizer bar.
Preferably, first connection structure is to run through the lifting of the equalizer bar along the width direction of the equalizer bar Hole, alternatively, first connection structure is the upward convex lifting lug on the equalizer bar;Second connection structure is convex Ear.
Preferably, the baffle is upward convex to be set to the equalizer bar distal end.
Preferably, the traction piece is rope.
In order to achieve the above purpose, the horizontal installation method of tower attachment of the invention includes the following steps:
(1) attachment to be installed is taken from being laid flat balance beam from the distal end of equalizer bar;
(2) clump weight is adjusted in the different location of equalizer bar, is adjusted with the center of gravity to equalizer bar;
(3) lifting appliance will take the attachment to be installed being laid flat at balance beam and lift by crane and be sent into wind-power tower, and traction piece exists It is drawn during attachment lifting to be installed and feeding wind-power tower;And
(4) attachment to be installed that will be fed into wind-power tower is fixedly connected with the connector in wind-power tower;And
(5) lifting appliance makes equalizer bar be moved away from wind-power tower.
Preferably, being further comprised the steps of: in step (1)
(a) according to the weight of attachment to be installed and its installation site on the horizontal wind-power tower put, set lifting Alternative and corresponding first connection structure assembly connection.
Compared with prior art, since the horizontal installation ancillary equipment of tower attachment of the invention includes equalizer bar, counterweight Block and traction piece, clump weight is along the proximal end that the length direction of equalizer bar is in that position is adjustably assemblied in equalizer bar, equalizer bar tool Have for the first connection structure with lifting appliance assembly connection and for the second connection structure with traction piece assembly connection, Two connection structures are located at the proximal end of equalizer bar, and traction piece is installed at the second connection structure;Therefore when in use, operator is first Part to be installed is taken to the distal end for being placed on equalizer bar, by lifting appliance by the horizontal installation ancillary equipment of tower attachment of the invention and Attachment to be installed is lifted to corresponding height and position, reduces the investment of manpower and improves working efficiency;Clump weight can be according to wait pacify The tonnage of dress attachment is adjusted, and carries out the adjustment of center of gravity again to equalizer bar, keeps equilibrium state after guaranteeing equalizer bar lifting;It leads Draw part to attachment to be installed lifting after control equalizer bar shake, into wind-power tower after prevented also from attachment to be installed scratch wind-powered electricity generation Tower paint, effectively reduces economic loss;Therefore, the horizontal installation of tower attachment of the invention has operation side with ancillary equipment Just, the advantages of improving installation effectiveness and reducing the talent and financial resources.
Detailed description of the invention
Fig. 1 is that the horizontal installation of tower attachment of the invention is sent attachment to be installed under lifting appliance effect with ancillary equipment Enter the schematic perspective view in the horizontal wind-power tower put.
Fig. 2, which is the horizontal installation of tower attachment of the invention, to be put with ancillary equipment connecting with lifting appliance and take in its distal end There is schematic perspective view when attachment to be installed.
Fig. 3 is that the horizontal installation of tower attachment of the invention is shown with stereochemical structure of the ancillary equipment when connecting with lifting appliance It is intended to.
Fig. 4 is the flow chart of the horizontal installation method of tower attachment of the invention.
Specific embodiment
For the technology contents that the present invention will be described in detail, construction feature, below in conjunction with embodiment and cooperate attached drawing make into One step explanation.
It please refers to Fig.1 to Fig.3, the horizontal installation ancillary equipment 100 of tower attachment of the invention will be to be installed for auxiliary Attachment 300 is sent into the horizontal wind-power tower 400 put, and wind-power tower 400 is suspended from ground by tower carrier 500, with Ensure that wind-power tower 400 is suspended from the reliability on ground;It is preferably that tower carrier 500 is two and is respectively arranged in wind At the both ends of the axial direction of pylon cylinder 400, so that wind-power tower 400 is more reliably suspended from ground, certainly, according to reality, tower The quantity of cylinder carrier 500 can also differ for three, four or five, therefore be not limited.
As shown in Figure 1 to Figure 3, tower attachment of the invention horizontal installation ancillary equipment 100 includes equalizer bar 10, counterweight Block 20 and traction piece 30.Clump weight 20 is along the proximal end 11 that the length direction of equalizer bar 10 is in that position is adjustably assemblied in equalizer bar 10 Place, in order to which operator neatly adjusts and matches in installation site and the weight of wind-power tower 400 according to attachment 300 to be installed Pouring weight 20 is in the position of equalizer bar 10;Equalizer bar 10 has for the first connection structure 13 with 200 assembly connection of lifting appliance And for the second connection structure 14 with 30 assembly connection of traction piece, the second connection structure 14 is located at the proximal end 11 of equalizer bar 10 Place, traction piece 30 are installed at the second connection structure 14, so that operator goes to prevent equalizer bar 10 from rising by traction piece 30 It hangs equipment 200 and generates shaking when lifting by crane, when attachment 300 to be installed is sent into wind-power tower 400 and when being moved away from wind-power tower 400, So that it is guaranteed that the reliability that the horizontal installation of tower attachment of the invention is worked with ancillary equipment 100.To prevent attachment 300 to be installed It is slid from the accident of equalizer bar 100, the horizontal installation ancillary equipment 100 of tower attachment of the invention further includes baffle 40, baffle 40 are installed at the distal end 12 of equalizer bar 10, are preferably, the upward convex distal end 12 set on equalizer bar 10 of baffle 40, more reliably Prevent the accident of attachment 300 to be installed from falling off, but not limited to this;First connection structure 13 is located at along the length direction of equalizer bar 10 Between baffle 40 and the second connection structure 14, design can maximally utilise the length of equalizer bar 10 in this way, so that flat The range that balance beam 10 protrudes into wind-power tower 400 is bigger, so that the horizontal installation ancillary equipment 100 of tower attachment of the invention Adaptation range is bigger.More specifically, as follows:
As shown in Figure 1 to Figure 3, clump weight 20 is located at immediately below the proximal end 11 of equalizer bar 10, and clump weight 20 is also slidedly arranged on flat At balance beam 10, on the one hand makes the position adjusting operation of clump weight 20 easier, on the other hand make clump weight 20 to equalizer bar 10 counterweight is more reliable, and clump weight 20 is avoided to cause equalizer bar 10 is past to be equipped with because being located at side of the equalizer bar 10 in width direction The side of clump weight 20, which generates, topples over, thus influences the reliability of 10 counterweight of equalizer bar;Meanwhile when clump weight 20 is located at balance For beam 10 at the side of width direction, clump weight 20 at this time can also stop the first connection structure 13 in the arrangement of equalizer bar 10, Thus influence setting position of first connection structure 13 on equalizer bar 10.Specifically, equalizer bar 10 extends downwardly out along flat The length direction of balance beam 10 first outstanding ear 50 and the second outstanding ear 60 spaced apart, it is outstanding that clump weight 20 is located at the first outstanding ear 50 and second Between ear 60, guide part 70, length of the guide part 70 along equalizer bar 10 are also equipped between the first outstanding ear 50 and the second outstanding ear 60 Direction is placed through clump weight 20, so that the sliding adjusting of clump weight 20 is more smooth;For example, guide part 70 is guide rod or leads Column, guide part 70 at least two and along the width direction of equalizer bar 10 in being separated at intervals arrangement so that clump weight 20 can only Length direction along equalizer bar 10 slides, so that it is guaranteed that the reliability that 20 position of clump weight is adjusted, but not limited to this;In addition, first Outstanding ear 50 is adjacent to the second connection structure 14, and the first outstanding ear 60 is far from the second connection structure 14, but not limited to this.
As shown in Figure 1 to Figure 3, the first connection structure 13 is at least 19 and begins to rehearse along the length direction interval of equalizer bar 10 Column are preferably that the first all connection structures 13 is in equally spaced arrangement along the length direction of equalizer bar 10, such as but unlimited It is right with the assembly connection position and the lifting appliance 200 that neatly adjust lifting appliance 200 and equalizer bar 10 in this line The lifting position of equalizer bar 10;For example, the first connection structure 13 is the width direction along equalizer bar 10 through equalizer bar 10 Lifting eye, in order to lifting appliance 200 steel wire penetrating lifting eye and realize the assembly connection with equalizer bar 100, certainly, According to actual needs, the first connection structure 13 can equally may be implemented to lift by crane with the upward convex lifting lug on equalizer bar 10 Assembly connection between equipment 200 and equalizer bar 10;And the second connection structure 14 is lug, traction piece 30 is rope, in order to The assembly connection of traction piece 30 and the second connection structure 14.It should be noted that according to actual needs, the first connection structure 13 Quantitative range can also be 2 to 18, therefore be not limited to the above examples.
Referring to Fig. 4, the horizontal installation method of tower attachment of the invention includes the following steps:
S001, attachment 300 to be installed is taken from being laid flat balance beam 10 from the distal end of equalizer bar 10 12, specifically, by operator Attachment 300 to be installed by hand or is taken by mechanical equipment and is laid flat at balance beam 10 by member, is preferably, by attachment 300 to be installed It takes before being laid flat at balance beam 10, according to the weight of attachment 300 to be installed and its installation position on the horizontal wind-power tower 400 put It sets, makes the selection of lifting appliance 200 and corresponding first connection structure, 13 assembly connection, to adjust lifting appliance 200 to equalizer bar 10 lifting position, thus achieve the purpose that the center of gravity to equalizer bar 100 is balanced, but not limited to this.
S002, clump weight 20 is adjusted in the different location of equalizer bar 10, be adjusted with the center of gravity to equalizer bar 10, so that Equalizer bar 10 and attachment to be installed 300 are steadily reliable when being lifted by crane and conveyed by lifting appliance 200.
S003, lifting appliance 200 will take the attachment to be installed 300 being laid flat at balance beam 10 and lift by crane and be sent into wind-power tower 400 It is interior, and traction piece 30 is drawn during attachment 300 to be installed lifts by crane and is sent into wind-power tower 400, is prevented to be installed attached Part 300 shakes, thus prevents safety accident;Meanwhile by traction piece 30, moreover it is possible to attachment 300 to be installed be prevented to be sent into Wind-power tower 400 is scratched in wind-power tower 400 to paint, and effectively reduces economic loss;For example, the draw operations of traction piece 30 But by manually completing for operator, it is also possible to be completed by mechanical equipment, therefore is not limited.
S004, the connector that will be fed into the attachment to be installed 300 in wind-power tower 400 and wind-power tower 400 are (such as raw Root part is the fixing piece of wind-power tower 400) it is fixedly connected, specifically, borrowed by the operator entered in wind-power tower 400 Welding equipment is helped to weld attachment 300 to be installed with connector, to realize the purpose of fixed attachment 300 to be installed, but not It is limited to this.
S005, lifting appliance 200 make equalizer bar 10 be moved away from wind-power tower 400, for next attachment 300 to be installed to be sent into Wind-power tower 400 is prepared, so that the fastening of the attachment to be installed 300 in wind-power tower 400 and next attachment to be installed 300 Lifting carry out simultaneously, save a large amount of time.It will be appreciated that when next attachment 300 to be installed is on wind-power tower 400 Installation site and weight when not needing to adjust lifting appliance 200 to the lifting position of equalizer bar 10, at this time by adjusting counterweight Block 20 can be adjusted the center of gravity of equalizer bar 10 in the position of equalizer bar 10, so that this operation is very simple and direct, but not It is limited to this.
Compared with prior art, due to the horizontal installation of tower attachment of the invention with ancillary equipment 100 include equalizer bar 10, Clump weight 20 and traction piece 30, clump weight 20 are adjustably assemblied in the close of equalizer bar 10 in position along the length direction of equalizer bar 10 It holds at 11, equalizer bar 20 has for the first connection structure 13 with 200 assembly connection of lifting appliance and is used for and traction piece 30 Second connection structure 14 of assembly connection, the second connection structure 14 are located at the proximal end 11 of equalizer bar 10, and traction piece 30 is installed on At second connection structure 14;Therefore when in use, part 300 to be installed is first taken the distal end 12 for being placed on equalizer bar 10 by operator, by The horizontal installation ancillary equipment 100 of tower attachment of the invention and attachment to be installed 300 are lifted to corresponding height by lifting appliance 200 Degree and position reduce the investment of manpower and improve working efficiency;Clump weight 20 can be adjusted according to the tonnage of attachment 300 to be installed Section, the adjusting are adjusted before the lifting of lifting appliance 200, are carried out the adjustment of center of gravity again to equalizer bar 10, are guaranteed balance Beam 10 keeps equilibrium state after lifting by crane;Control equalizer bar 10 shakes after traction piece 30 lifts by crane attachment 300 to be installed, into wind-powered electricity generation Wind-power tower 400 is scratched prevented also from attachment 300 to be installed after tower 400 to paint, and effectively reduces economic loss;Therefore, this hair Bright tower attachment horizontal installation ancillary equipment 100 have it is easy to operate, improve installation effectiveness and reduce the talent and financial resources Advantage.
It should be noted that the arrow A direction and opposite direction in figure are the length direction of equalizer bar 10, arrow in figure Head B direction and opposite direction are the width direction of equalizer bar 10, and arrow C direction and opposite direction are equalizer bar in figure 10 short transverse.Simultaneously as attachment 300 to be installed be it is horizontal be conveyed into wind-power tower 400 and installed, therefore can be with Attachment lifting installation is carried out using the lifting appliance 200 of small tonnage, thus speed is fast and flexible operation, improves wind-power tower The installation effectiveness and safety coefficient of attachment 300 to be installed.For example, lifting appliance 200 is to be set up in rising on workshop roof beam structure Equipment is hung, which can make the horizontal installation ancillary equipment 100 of tower attachment of the invention along the length of equalizer bar 100 Direction, width direction and short transverse sliding are spent, but not limited to this.
The above disclosure is only a preferred example of the present invention, and the scope of the invention cannot be limited thereby, Therefore equivalent changes made in accordance with the claims of the present invention belong to the range that the present invention is covered.

Claims (10)

1. a kind of horizontal installation ancillary equipment of tower attachment, which is characterized in that including equalizer bar, clump weight and traction piece, institute The length direction that clump weight is stated along the equalizer bar is adjustably assemblied in the proximal end of the equalizer bar, the equalizer bar in position With for the first connection structure of lifting appliance assembly connection and for being connect with the second of the traction piece assembly connection Structure, second connection structure are located at the proximal end of the equalizer bar, and the traction piece is installed on second connection structure Place.
2. the horizontal installation ancillary equipment of tower attachment according to claim 1, which is characterized in that it further include baffle, institute The far-end that baffle is installed on the equalizer bar is stated, first connection structure is located at described along the length direction of the equalizer bar Between baffle and second connection structure.
3. the horizontal installation ancillary equipment of tower attachment according to claim 1, which is characterized in that the clump weight is located at Immediately below the proximal end of the equalizer bar, the clump weight is also slidedly arranged at the equalizer bar.
4. the horizontal installation ancillary equipment of tower attachment according to claim 3, which is characterized in that the equalizer bar is downward Extend the first outstanding ear and second outstanding ear spaced apart along the length direction of the equalizer bar, the clump weight is located at described first Between outstanding ear and the second outstanding ear, guide part, the guide part edge are also equipped between the first outstanding ear and the second outstanding ear The length direction of the equalizer bar is placed through the clump weight.
5. the horizontal installation ancillary equipment of tower attachment according to claim 1, which is characterized in that the first connection knot Structure at least two is simultaneously arranged spaced apart along the length direction of the equalizer bar.
6. the horizontal installation ancillary equipment of tower attachment according to claim 5, which is characterized in that the first connection knot Structure is the lifting eye for running through the equalizer bar along the width direction of the equalizer bar, alternatively, first connection structure is upward The lifting lug being convexly equipped on the equalizer bar;Second connection structure is lug.
7. the horizontal installation ancillary equipment of tower attachment according to claim 2, which is characterized in that the baffle is upward convex Set on the equalizer bar distal end.
8. the horizontal installation ancillary equipment of tower attachment according to claim 1, which is characterized in that the traction piece is rope Rope.
9. a kind of horizontal installation method of tower attachment, which comprises the steps of:
(1) attachment to be installed is taken from being laid flat balance beam from the distal end of equalizer bar;
(2) clump weight is adjusted in the different location of equalizer bar, is adjusted with the center of gravity to equalizer bar;
(3) lifting appliance will take the attachment to be installed being laid flat at balance beam and lift by crane and be sent into wind-power tower, and traction piece is wait pacify It is drawn during the lifting of dress attachment and feeding wind-power tower;
(4) attachment to be installed that will be fed into wind-power tower is fixedly connected with the connector in wind-power tower;And
(5) lifting appliance makes equalizer bar be moved away from wind-power tower.
10. the horizontal installation method of tower attachment according to claim 1, which is characterized in that in step (1), further comprise the steps of:
(a) according to the weight of attachment to be installed and its installation site on the horizontal wind-power tower put, select lifting appliance It selects and corresponding first connection structure assembly connection.
CN201910553173.9A 2019-06-24 2019-06-24 Tower attachment horizontal installation ancillary equipment and the horizontal installation method of tower attachment Pending CN110182684A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910553173.9A CN110182684A (en) 2019-06-24 2019-06-24 Tower attachment horizontal installation ancillary equipment and the horizontal installation method of tower attachment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910553173.9A CN110182684A (en) 2019-06-24 2019-06-24 Tower attachment horizontal installation ancillary equipment and the horizontal installation method of tower attachment

Publications (1)

Publication Number Publication Date
CN110182684A true CN110182684A (en) 2019-08-30

Family

ID=67723288

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910553173.9A Pending CN110182684A (en) 2019-06-24 2019-06-24 Tower attachment horizontal installation ancillary equipment and the horizontal installation method of tower attachment

Country Status (1)

Country Link
CN (1) CN110182684A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110848089A (en) * 2019-11-19 2020-02-28 新疆金风科技股份有限公司 Installation jig, method for installing tower drum accessory and tower drum equipment
CN113247768A (en) * 2021-03-29 2021-08-13 中船澄西船舶修造有限公司 Method for realizing safe stable hoisting of marine desulfurization tower
CN114890324A (en) * 2022-05-06 2022-08-12 江苏道达风电设备科技有限公司 High-altitude fan blade installation auxiliary device and fan blade installation method
CN115971767A (en) * 2023-01-04 2023-04-18 浙江东南绿建集成科技有限公司 Round tube inner partition plate assembling and welding tool

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0761774A (en) * 1993-08-27 1995-03-07 Fujita Corp Method for taking in carried-in goods by crane
JPH11106178A (en) * 1997-10-08 1999-04-20 Otani Kikai Seisakusho:Kk Freight suspension tool for overhead crane
CN201046881Y (en) * 2007-06-15 2008-04-16 中国第一重型机械集团公司 Adjustable frame roller changing sling
CN104140037A (en) * 2014-07-29 2014-11-12 南京奥捷墙体材料有限公司 Wallboard lifting system
CN204150929U (en) * 2014-10-17 2015-02-11 莱芜钢铁集团有限公司 A kind of suspender
CN109335949A (en) * 2018-10-18 2019-02-15 中交二航局第二工程有限公司 The method of scale beam type counter-jib suspender and its hoisting steel beam component
CN210214549U (en) * 2019-06-24 2020-03-31 中国水电四局(阳江)海工装备有限公司 Auxiliary assembly for horizontal installation of tower barrel accessory

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0761774A (en) * 1993-08-27 1995-03-07 Fujita Corp Method for taking in carried-in goods by crane
JPH11106178A (en) * 1997-10-08 1999-04-20 Otani Kikai Seisakusho:Kk Freight suspension tool for overhead crane
CN201046881Y (en) * 2007-06-15 2008-04-16 中国第一重型机械集团公司 Adjustable frame roller changing sling
CN104140037A (en) * 2014-07-29 2014-11-12 南京奥捷墙体材料有限公司 Wallboard lifting system
CN204150929U (en) * 2014-10-17 2015-02-11 莱芜钢铁集团有限公司 A kind of suspender
CN109335949A (en) * 2018-10-18 2019-02-15 中交二航局第二工程有限公司 The method of scale beam type counter-jib suspender and its hoisting steel beam component
CN210214549U (en) * 2019-06-24 2020-03-31 中国水电四局(阳江)海工装备有限公司 Auxiliary assembly for horizontal installation of tower barrel accessory

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110848089A (en) * 2019-11-19 2020-02-28 新疆金风科技股份有限公司 Installation jig, method for installing tower drum accessory and tower drum equipment
CN113247768A (en) * 2021-03-29 2021-08-13 中船澄西船舶修造有限公司 Method for realizing safe stable hoisting of marine desulfurization tower
CN113247768B (en) * 2021-03-29 2022-05-20 中船澄西船舶修造有限公司 Method for realizing safe stable hoisting of marine desulfurization tower
CN114890324A (en) * 2022-05-06 2022-08-12 江苏道达风电设备科技有限公司 High-altitude fan blade installation auxiliary device and fan blade installation method
CN115971767A (en) * 2023-01-04 2023-04-18 浙江东南绿建集成科技有限公司 Round tube inner partition plate assembling and welding tool

Similar Documents

Publication Publication Date Title
CN110182684A (en) Tower attachment horizontal installation ancillary equipment and the horizontal installation method of tower attachment
CN104284857A (en) Heavy lifting apparatus and method
CN107381379A (en) A kind of steady goods device of floating crane
EP3472092B1 (en) A crane for wind turbine blade assembly, a vessel, a hoisting method, and an assembly method
CN105460796A (en) Offshore platform fan lifting system and lifting method
CN103010407B (en) High-speed rescue boat lowering device
CN110329937B (en) Device and method for assisting hoisting and rope arranging of crane and engineering machine
CN105347206A (en) Intelligent assisting platform for gas insulated substation (GIS) dismounting
CN105366567A (en) Intelligent assisting platform for dismounting and mounting of GIS (Gas Insulated Substation)
CN104444858A (en) Tower crane with watering function and manufacturing method thereof
CN205222531U (en) GIS dismouting intelligence auxiliary platform
CN210214549U (en) Auxiliary assembly for horizontal installation of tower barrel accessory
CN103991800A (en) Roof surface crane for building
CN204434119U (en) A kind of tower crane with sprinkle water function
CN109252733A (en) Adhesion type is from climbing pole lifting system
CN203755638U (en) Suspending slippage type high-altitude inverted oblique plane operation hanging basket
CN203959697U (en) The equalizing bar of hoisting platform truss
CN112960529A (en) Tail slipping mechanism and tail slipping method of slender thin-wall equipment
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN208087079U (en) Ingot furnace furnace top cover hanging apparatus
CN105152001B (en) For lifting the special hanger and hanging method of radio telescope reflecting surface unit
CN107675890A (en) A kind of method at aerial regulation steel truss mast-up angle of inclination
CN116374804A (en) Ton bag lifting hook
CN105947910A (en) Lifting process of upper structure of FPSO crane
CN208843629U (en) A kind of crane upper mechanism is from dismantling device and crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination