CN110748065A - Assembling tool type truss composite slab and construction method thereof - Google Patents

Assembling tool type truss composite slab and construction method thereof Download PDF

Info

Publication number
CN110748065A
CN110748065A CN201911184957.5A CN201911184957A CN110748065A CN 110748065 A CN110748065 A CN 110748065A CN 201911184957 A CN201911184957 A CN 201911184957A CN 110748065 A CN110748065 A CN 110748065A
Authority
CN
China
Prior art keywords
truss
steel bar
support
reinforcing steel
shear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911184957.5A
Other languages
Chinese (zh)
Other versions
CN110748065B (en
Inventor
胡兆文
唐志勃
杨玉桐
于付振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG DEJIAN GROUP CO Ltd
Original Assignee
SHANDONG DEJIAN GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG DEJIAN GROUP CO Ltd filed Critical SHANDONG DEJIAN GROUP CO Ltd
Priority to CN201911184957.5A priority Critical patent/CN110748065B/en
Publication of CN110748065A publication Critical patent/CN110748065A/en
Application granted granted Critical
Publication of CN110748065B publication Critical patent/CN110748065B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0627Three-dimensional reinforcements composed of a prefabricated reinforcing mat combined with reinforcing elements protruding out of the plane of the mat
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/065Light-weight girders, e.g. with precast parts
    • E04C5/0653Light-weight girders, e.g. with precast parts with precast parts
    • E04C5/0656Light-weight girders, e.g. with precast parts with precast parts with lost formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

A construction method for assembling tool type truss composite slabs comprises the steps of sequentially manufacturing a shear steel bar support, a supporting upright rod, a truss supporting beam and a bottom plate; the shear steel bar support, the support upright stanchion and the truss support beam are connected and combined; laying truss support beam assemblies on the longitudinal and transverse steel bars; pouring concrete on the prestressed laminated slab; mounting the prestressed laminated slab; pouring second laminated concrete; and disassembling the truss support beam. The assembly tool type truss composite slab further comprises a shear steel bar support, a supporting upright rod, a truss supporting beam and a bottom plate; there is the bottom plate bottom the shear steel bar support of equipment instrument formula truss superimposed sheet, sets up on the bottom plate and moves about freely and quickly end muscle, and the muscle is prestressing tendons at the bottom of the long edge orientation, and the minor face orientation is non-prestressing tendons, shear steel bar support with move about freely and quickly end muscle ligature connection.

Description

一种组装工具式桁架叠合板及其施工方法A kind of assembly tool type truss laminated board and construction method thereof

技术领域technical field

本发明属于建筑技术领域,具体涉及一种组装工具式桁架叠合板,此叠合板为免支撑叠合板。The invention belongs to the technical field of construction, and in particular relates to an assembly tool-type truss laminated board, which is a support-free laminated board.

背景技术Background technique

建筑领域经常使用的传统叠合板构件,能够减少施工过程中的湿作业步骤和施工模板,提高施工效率。传统叠合板的不足之处在于整体刚度低,抗弯性能差、易开裂、钢筋用量多、板底支撑设置较多。传统钢筋桁架叠合板结构,在吊装过程中产生较大挠度变形,甚至导致基板开裂。叠合层施工过程中,板底须设置大量支撑来提高叠合板整体竖向承载力,减小基板挠度、避免基板开裂。因此,传统叠合板在施工中,需要大量人力、物力的投入,造成综合建造成本偏高。The traditional laminated plate components often used in the construction field can reduce wet work steps and construction templates in the construction process and improve construction efficiency. The shortcomings of the traditional laminated board are that the overall stiffness is low, the bending resistance is poor, it is easy to crack, the amount of steel bars is large, and the bottom support is provided more. The traditional reinforced truss composite plate structure produces large deflection and deformation during the hoisting process, and even causes the base plate to crack. During the construction of the laminated layer, a large number of supports must be provided at the bottom of the plate to improve the overall vertical bearing capacity of the laminated plate, reduce the deflection of the substrate, and prevent the substrate from cracking. Therefore, the construction of traditional laminated panels requires a lot of manpower and material resources, resulting in high comprehensive construction costs.

现有的传统钢筋桁架叠合板由预先制作的钢筋桁架和钢筋混凝土底板组成,钢筋混凝土底板浇筑时将由上弦杆、腹杆和下弦杆组成的钢筋桁架的下弦杆埋入,形成整体受力叠合板构件。叠合板中的钢筋桁架在浇筑叠合层现浇混凝土时起到提供竖向刚度作用,可提高施工过程叠合板承载能力。腹杆连接上下弦杆形成空间稳定结构并兼具提高新旧混凝土结合面抗剪性能。在混凝土浇筑完成后,钢筋桁架全部埋入混凝土,造成楼板钢筋配置过渡冗余,形成钢筋“浪费”,造成叠合板构件综合制造成本增加。The existing traditional reinforced truss composite panel is composed of prefabricated reinforced truss and reinforced concrete bottom plate. When the reinforced concrete bottom plate is poured, the bottom chord of the reinforced truss composed of upper chord, web and lower chord is buried to form an overall stress-bearing composite panel. member. The reinforced trusses in the composite slab provide vertical stiffness when pouring the cast-in-place concrete of the composite layer, which can improve the bearing capacity of the composite slab during construction. The webs connect the upper and lower chords to form a spatially stable structure and simultaneously improve the shear resistance of the new and old concrete joint surfaces. After the concrete pouring is completed, the steel trusses are all buried in the concrete, resulting in a transitional redundancy in the configuration of the steel reinforcement on the floor, resulting in a "waste" of steel reinforcement, resulting in an increase in the comprehensive manufacturing cost of the composite panel components.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提供一种组装工具式桁架叠合板及其施工方法,它能解决现有技术的不足。The purpose of the present invention is to provide an assembly tool type truss laminated board and its construction method, which can solve the deficiencies of the prior art.

本发明提供一种组装工具式桁架,其包括抗剪钢筋支架、支撑立杆、桁架支撑梁组成,The invention provides an assembly tool-type truss, which comprises a shear-resistant steel bar bracket, a supporting vertical rod, and a truss supporting beam.

其中的抗剪钢筋支架,由第一弯折钢筋、第二弯折钢筋、第三弯折钢筋、竖直筋组成,抗剪钢筋支架形状为三角形。在现场叠合层施工时抗剪钢筋支架与支撑立杆主要作用为将叠合板混凝土与组装工具式桁架支撑梁连接成整体,形成桁架结构,从而使叠合板具有承担浇筑混凝土过程中施工荷载、结构自重的能力,以及整体强度未达设计要求时提供刚度保证。The shear-resisting steel bar bracket is composed of a first bending bar, a second bending bar, a third bending bar and a vertical bar, and the shear-resisting bar bracket is triangular in shape. During the construction of the superimposed layer on site, the main function of the shear steel support and the supporting vertical rod is to connect the composite slab concrete and the assembly tool truss support beam into a whole to form a truss structure, so that the composite slab has the ability to bear the construction load in the process of pouring concrete, The self-weight capacity of the structure and the rigidity guarantee when the overall strength does not meet the design requirements.

所述第一弯折钢筋、第二弯折钢筋、第三弯折钢筋为三角形结构,第一弯折钢筋端部与第三弯折钢筋尾部焊接固定,第三弯折钢筋尾部与竖直筋相连接。The first bending steel bar, the second bending steel bar and the third bending steel bar are of triangular structure, the end of the first bending steel bar and the tail of the third bending steel bar are welded and fixed, and the tail of the third bending steel bar is connected to the vertical bar. connected.

所述第一弯折钢筋、第二弯折钢筋、第三弯折钢筋之间夹角为45-75度,竖直筋与第二弯折钢筋垂直,竖直筋端部设置有螺纹;The included angle between the first bending steel bar, the second bending steel bar and the third bending steel bar is 45-75 degrees, the vertical bar is perpendicular to the second bending steel bar, and the end of the vertical bar is provided with a thread;

所述第一弯折钢筋、第二弯折钢筋、第三弯折钢筋、竖直筋为一体成型。The first bending steel bar, the second bending steel bar, the third bending steel bar and the vertical bar are integrally formed.

所述支撑立杆为倒T型结构,其包括水平杆、竖向立杆,竖向立杆内侧设有螺纹,竖向立杆底部水平方向开孔,水平杆穿过孔洞,并在交叉位置焊接固定;The supporting pole is an inverted T-shaped structure, which includes a horizontal pole and a vertical pole. The inner side of the vertical pole is provided with a thread, and the bottom of the vertical pole is opened in a horizontal direction. Welding and fixing;

本发明提供一种组装工具式桁架,其中的桁架支撑梁,为组装工具式结构,所述桁架支撑梁为矩形钢管,与抗剪钢筋支架连接位置设置圆孔;桁架支撑梁分段布置,桁架支撑梁之间通过承插方式连接。The invention provides an assembly tool type truss, wherein the truss support beam is an assembly tool type structure, the truss support beam is a rectangular steel pipe, and a circular hole is set at the connection position with the shear steel support; The support beams are connected by sockets.

所述桁架支撑梁为矩形钢管,一端设置承插端,承插端尺寸略小于矩形钢管内径,且承插端端部设置坡面,方便桁架支撑梁之间的承插,在桁架支撑梁另一端外侧焊接耳板,通过敲击耳板的形式保证桁架支撑梁之间的可靠连接。The truss support beam is a rectangular steel pipe, one end is provided with a socket end, the size of the socket end is slightly smaller than the inner diameter of the rectangular steel pipe, and the end of the socket end is provided with a slope to facilitate the socket and socket between the truss support beams. The lug plate is welded on the outside of one end, and the reliable connection between the truss support beams is ensured by tapping the lug plate.

所述抗剪钢筋支架竖直筋穿过桁架支撑梁孔洞后通过螺母拧紧固定,竖直筋与第三弯折钢筋折弯位置设置螺母垫块,保证抗剪钢筋支架与桁架支撑梁紧密结合、连接牢固。The vertical bars of the shear-resisting steel bars pass through the holes of the truss support beams and are then tightened and fixed by nuts. Nut spacers are set at the bending positions of the vertical bars and the third bending bars to ensure that the shear-resistance steel bars are tightly combined with the truss support beams. The connection is firm.

所述支撑立杆与桁架支撑梁之间通过加长螺杆连接,加长螺杆可拧入支撑立杆,另一端穿过桁架支撑梁通过螺母拧紧固定。The support rod and the truss support beam are connected by an extension screw, the extension rod can be screwed into the support rod, and the other end passes through the truss support beam and is fastened and fixed by a nut.

本发明提供一种组装工具式桁架叠合板,其包括上述抗剪钢筋支架、桁架支撑梁、支撑立杆、底板。The present invention provides an assembly tool-type truss composite panel, which includes the above-mentioned shear-resisting steel bar bracket, a truss supporting beam, a supporting vertical rod, and a bottom plate.

抗剪钢筋支架底部有底板,底板上设置纵横底筋,长边方向底筋为预应力筋,短边方向为非预应力筋,抗剪钢筋支架与纵横底筋绑扎连接。There is a bottom plate at the bottom of the shear-resisting steel bar support, and vertical and horizontal bottom bars are arranged on the bottom plate.

所述抗剪钢筋支架的第一弯折钢筋全部、第二弯折钢筋、第三弯折钢筋的部分埋入底板,形成一定的锚固长度,底板加工完成后与抗剪钢筋支架形成一整体。All of the first bending steel bars, the second bending steel bars and the third bending steel bars of the shear steel reinforcement bracket are embedded in the bottom plate to form a certain anchoring length.

所述支撑立杆的水平杆全部、竖向立杆部分埋入底板,形成一定的锚固长度,底板加工完成后与支撑立杆形成一整体,施工现场浇筑混凝土时螺栓连接紧密,可减少组装桁架自身连接变形,组装刚度大,施工时在荷载作用下叠合板挠度小优点。All of the horizontal rods and part of the vertical rods of the support rods are buried in the bottom plate to form a certain anchoring length. After the bottom plate is processed, it forms a whole with the support rods. When the concrete is poured at the construction site, the bolts are tightly connected, which can reduce the number of trusses assembled. It has the advantages of self-connection deformation, high assembly rigidity, and small deflection of the laminated board under the load during construction.

一种组装工具式桁架叠合板的施工方法包括以下步骤:A construction method for assembling a tool-type truss composite board comprises the following steps:

步骤一:抗剪钢筋支架的制作Step 1: Fabrication of Shear Rebar Brackets

A:根据施工要求,将直径为6-10mm的钢筋截断;A: According to the construction requirements, cut off the steel bars with a diameter of 6-10mm;

B:将截断后的钢筋一端进行螺纹处理,螺纹长度为30-50mm;B: Thread one end of the truncated steel bar, and the thread length is 30-50mm;

C: 将第一弯折钢筋、第二弯折钢筋、第三弯折钢筋连续弯折组成三角形结构,再进行竖直筋弯折,竖直筋与第二弯折钢筋垂直,第一弯折钢筋、第三弯折钢筋、竖直筋交叉位置焊接连接。C: Continuously bend the first bending steel bar, the second bending steel bar, and the third bending steel bar to form a triangular structure, and then bend the vertical bar. The vertical bar is perpendicular to the second bending steel bar, and the first bending The steel bar, the third bending steel bar, and the vertical bar are welded and connected at the intersection.

步骤二:支撑立杆的制作Step 2: Fabrication of support poles

A:根据施工要求制作水平杆;A: Make horizontal rods according to construction requirements;

B:竖向立杆内部设置螺纹,螺纹深度约为竖向立杆长度的三分之二,竖向立杆另一端设置水平孔洞;B: A thread is set inside the vertical pole, the depth of the thread is about two-thirds of the length of the vertical pole, and a horizontal hole is set at the other end of the vertical pole;

C:水平杆穿过水平孔洞,在交叉位置焊接固定;C: The horizontal rod passes through the horizontal hole and is welded and fixed at the cross position;

步骤三:制作桁架支撑梁Step 3: Making the Truss Support Beam

A:桁架支撑梁采用矩形钢管,在矩形钢管设有与支撑立杆、抗剪钢筋支架对应位置开孔;A: The truss support beam is made of rectangular steel pipe, and the rectangular steel pipe is provided with openings corresponding to the supporting vertical rod and the shear steel bracket;

B:桁架支撑梁的始端安装耳板;B: The ear plate is installed at the beginning of the truss support beam;

C:桁架支承梁的末端制作承插部,承插部端部为棱台形,方便桁架支承梁插入。C: The end of the truss support beam is made into a socket part, and the end of the socket part is prismatic, which is convenient for the insertion of the truss support beam.

步骤四:制作底板Step 4: Making the Base Plate

A: 底板的制作在模台上完成,在制作之前在底板四边安装模板,控制叠合板尺寸;A: The production of the bottom plate is completed on the mold table. Before the production, the template is installed on the four sides of the bottom plate to control the size of the laminated board;

B: 安装完多块底板模板后铺设短边方向钢筋,再铺设长边通长钢筋,并对通长钢筋采用张拉设备对钢筋张拉,并对纵横向钢筋进行绑扎链接。B: After installing multiple base plate formworks, lay the short-side direction steel bars, and then lay the long-side full-length steel bars, and use the tensioning equipment to tension the steel bars for the full-length steel bars, and bind the vertical and horizontal steel bars.

步骤五:抗剪钢筋支架、支撑立杆及桁架支撑梁的连接组合。Step 5: The connection combination of shear steel support, support pole and truss support beam.

A:根据需求,将桁架支撑梁进行拼装组合A: Assemble and combine truss support beams according to requirements

B:通过螺母及螺母垫片将抗剪钢筋支架与桁架支撑梁连接固定,通过螺母及加长螺栓将支撑立杆与桁架支撑梁连接牢固;B: The shear steel support and the truss support beam are connected and fixed by nuts and nut washers, and the support rod and the truss support beam are firmly connected by nuts and extension bolts;

步骤六:在纵横钢筋上铺设桁架支撑梁组合件Step 6: Lay the truss support beam assembly on the longitudinal and transverse reinforcement

A:按照要求在相应位置将抗剪钢筋支架、支撑立杆及桁架支撑梁组合件放置到相应位置,抗剪钢筋支架与纵横钢筋绑扎连接;A: According to the requirements, place the shear-resisting steel support bracket, the support pole and the truss support beam assembly in the corresponding position, and connect the shear-resistant steel support bracket with the vertical and horizontal steel bars;

步骤七:预应力叠合板混凝土浇筑Step 7: Concrete pouring of prestressed composite slabs

A:钢筋桁架及桁架支撑梁放置完成后浇筑混凝土,混凝土厚度3.5-5cm,混凝土浇筑完成后对上表面毛化处理。A: Concrete is poured after the reinforced trusses and truss support beams are placed. The thickness of the concrete is 3.5-5cm. After the concrete is poured, the upper surface is textured.

B:浇筑完混凝土后对叠合板进行养护,达到一定强度后将预应力钢筋截断并拆除模板,达到吊装强度后将桁架支撑梁拆除,并将叠合板运至堆场或施工现场。在本步骤中所用桁架支撑梁只为生产叠合板中固定抗剪钢筋支架位置、标高作用,不承担施工过程荷载,与现场吊装浇筑混凝土叠合层的桁架支撑梁规格不同,作用不同。B: After the concrete is poured, the laminated board is maintained. After reaching a certain strength, the prestressed steel bars are cut off and the formwork is removed. After the hoisting strength is reached, the truss support beam is removed, and the laminated board is transported to the storage yard or construction site. The truss support beam used in this step is only used to fix the position and elevation of the shear reinforcement support in the production of the laminated slab, and does not bear the load during the construction process.

步骤八:预应力叠合板安装Step 8: Prestressed Laminated Panel Installation

A:预应力叠合板安装前将桁架支撑梁组合件安装到叠合板并进行固定,再按照图纸位置要求将叠合板吊装至相应位置,叠合板两端放置于两侧结构梁上。A: Before installing the prestressed laminated board, install the truss support beam assembly to the laminated board and fix it, and then hoist the laminated board to the corresponding position according to the position requirements of the drawing, and place the two ends of the laminated board on the structural beams on both sides.

B:叠合板吊装完成后绑扎叠合板上部钢筋;B: After the hoisting of the laminated board is completed, the upper steel bars of the laminated board are bound;

步骤九:浇注第二层叠合混凝土Step 9: Pouring the Second Layer of Laminated Concrete

绑扎完上部钢筋后浇筑上部第二层叠合混凝土,混凝土浇筑高度距离桁架支撑梁底部2-3cm。After binding the upper steel bars, pour the upper second layer of laminated concrete, and the concrete pouring height is 2-3cm from the bottom of the truss support beam.

步骤十:拆卸桁架支撑梁Step 10: Remove the truss support beam

浇筑完上部混凝土后对混凝土表面收光处理,待混凝度达到一定强度后将桁架支撑梁拆除,拆除桁架支撑梁时首先将螺母拆除,拆除螺母后依次将桁架支撑梁及加长螺栓拆除。螺母、桁架支撑梁、加长螺栓拆除后再进行后续叠合板的使用。After the upper concrete is poured, the surface of the concrete is polished. After the concrete reaches a certain strength, the truss support beam is removed. When the truss support beam is removed, the nut is first removed. After the nut is removed, the truss support beam and extension bolts are removed in turn. Nuts, truss support beams, and extension bolts are removed before subsequent use of the laminated board.

本发明的优点在于:它能够在生产线上流水化加工,叠合板构件抗弯强度提高、刚度大,不容易产生过大的挠度变形;钢筋桁架用量少,节约了大量钢材;现场施工无需搭设底部支撑架体,施工方便;桁架支撑梁在混凝土浇筑完成后可拆除,能够循环使用。以上特点能够降低叠合板的加工及建造成本,有助于推动装配式行业的快速高效发展。The advantages of the invention are: it can be processed in the production line, the flexural strength of the laminated plate member is improved, the rigidity is large, and it is not easy to cause excessive deflection; The bottom support frame is convenient for construction; the truss support beam can be dismantled after concrete pouring and can be recycled. The above features can reduce the processing and construction costs of laminated panels, and help promote the rapid and efficient development of the prefabricated industry.

附图说明Description of drawings

下面结合附图对本发明进一步说明:Below in conjunction with accompanying drawing, the present invention is further described:

附图1是本发明的结构示意图。1 is a schematic structural diagram of the present invention.

附图2 是本发明的正视图。Figure 2 is a front view of the present invention.

附图3 是本发明的侧视图。Figure 3 is a side view of the present invention.

附图4是本发明的抗剪钢筋支架节点放大图。FIG. 4 is an enlarged view of the node of the shear-resistant reinforcement support of the present invention.

附图5是本发明的支撑立杆节点放大图。FIG. 5 is an enlarged view of a support pole node of the present invention.

附图6是本发明的桁架支撑梁的部分示意图。FIG. 6 is a partial schematic view of the truss support beam of the present invention.

附图7是本发明支撑立杆的结构示意图。FIG. 7 is a schematic view of the structure of the support pole of the present invention.

附图8是本发明抗剪钢筋支架的结构示意图。FIG. 8 is a schematic structural diagram of the shear-resistant steel bar support of the present invention.

图中pictured

1为底板1 is the bottom plate

2为抗剪钢筋支架2 is the shear steel support

3为桁架支撑梁3 is the truss support beam

4为支撑立杆4 is the support pole

5为预应力筋5 is the prestressed tendon

6为螺母6 is the nut

7为加长螺栓。7 is the extension bolt.

21为第一弯折钢筋21 is the first bending steel bar

22为第二弯折钢筋22 is the second bending steel bar

23为第三弯折钢筋23 is the third bending steel bar

24为竖直筋24 is vertical rib

25为螺母垫块25 is the nut spacer

31为承插端31 is the socket end

32为耳板。32 is the ear plate.

41为竖向立杆41 is a vertical pole

42为水平杆42 is the horizontal rod

以下通过特定的具体实例说明本发明的实施方式,本领域技术人员可由本说明书所揭露的内容轻易地了解本发明的其他优点与功效。本发明还可以通过另外不同的具体实施方式加以实施或应用,本说明书中的各项细节也可以基于不同观点与应用,在没有背离本发明的精神下进行各种修饰或改变。The embodiments of the present invention are described below through specific specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and various details in this specification can also be modified or changed based on different viewpoints and applications without departing from the spirit of the present invention.

请参阅图1至图8。须知,本说明书所附图式所绘示的结构、比例、大小等,均仅用以配合说明书所揭示的内容,以供熟悉此技术的人士了解与阅读,并非用以限定本发明可实施的限定条件,故不具技术上的实质意义,任何结构的修饰、比例关系的改变或大小的调整,在不影响本发明所能产生的功效及所能达成的目的下,均应仍落在本发明所揭示的技术内容得能涵盖的范围内。同时,本说明书中所引用的如“上”、“下”、“左”、“右”、“中间”及“一”等的用语,亦仅为便于叙述的明了,而非用以限定本发明可实施的范围,其相对关系的改变或调整,在无实质变更技术内容下,当亦视为本发明可实施的范畴。See Figures 1 through 8. It should be noted that the structures, proportions, sizes, etc. shown in the drawings in this specification are only used to cooperate with the contents disclosed in the specification, so as to be understood and read by those who are familiar with the technology, and are not used to limit the implementation of the present invention. Restricted conditions, it does not have technical substantive significance, any structural modification, proportional relationship change or size adjustment, without affecting the effect that the present invention can produce and the purpose that can be achieved, should still fall within the present invention. The disclosed technical content must be within the scope of coverage. At the same time, the terms such as "up", "down", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description and clarity, and are not used to limit this specification. The implementable scope of the invention, and the change or adjustment of the relative relationship thereof, shall also be regarded as the implementable scope of the present invention without substantially changing the technical content.

本发明提供一种组装工具式桁架,其包括抗剪钢筋支架、支撑立杆、桁架支撑梁组成,The invention provides an assembly tool-type truss, which comprises a shear-resistant steel bar bracket, a supporting vertical rod, and a truss supporting beam.

其中的抗剪钢筋支架,由第一弯折钢筋、第二弯折钢筋、第三弯折钢筋、竖直筋组成,抗剪钢筋支架形状为三角形。在现场叠合层施工时抗剪钢筋支架与支撑立杆主要作用为将叠合板混凝土与组装工具式桁架支撑梁连接成整体,形成桁架结构,从而使叠合板具有承担浇筑混凝土过程中施工荷载、结构自重的能力,以及整体强度未达设计要求时提供刚度保证。The shear-resisting steel bar bracket is composed of a first bending bar, a second bending bar, a third bending bar and a vertical bar, and the shear-resisting bar bracket is triangular in shape. During the construction of the superimposed layer on site, the main function of the shear steel support and the supporting vertical rod is to connect the composite slab concrete and the assembly tool truss support beam into a whole to form a truss structure, so that the composite slab has the ability to bear the construction load in the process of pouring concrete, The self-weight capacity of the structure and the rigidity guarantee when the overall strength does not meet the design requirements.

所述第一弯折钢筋、第二弯折钢筋、第三弯折钢筋为三角形结构,第一弯折钢筋端部与第三弯折钢筋尾部焊接固定,第三弯折钢筋尾部与竖直筋相连接。The first bending steel bar, the second bending steel bar and the third bending steel bar are of triangular structure, the end of the first bending steel bar and the tail of the third bending steel bar are welded and fixed, and the tail of the third bending steel bar is connected to the vertical bar. connected.

所述第一弯折钢筋、第二弯折钢筋、第三弯折钢筋之间夹角为45-75度,竖直筋与第二弯折钢筋垂直,竖直筋端部设置有螺纹;The included angle between the first bending steel bar, the second bending steel bar and the third bending steel bar is 45-75 degrees, the vertical bar is perpendicular to the second bending steel bar, and the end of the vertical bar is provided with a thread;

所述第一弯折钢筋、第二弯折钢筋、第三弯折钢筋、竖直筋为一体成型。The first bending steel bar, the second bending steel bar, the third bending steel bar and the vertical bar are integrally formed.

所述支撑立杆为倒T型结构,其包括水平杆、竖向立杆,竖向立杆内侧设有螺纹,竖向立杆底部水平方向开孔,水平杆穿过孔洞,并在交叉位置焊接固定;The support pole is an inverted T-shaped structure, which includes a horizontal pole and a vertical pole. The inner side of the vertical pole is provided with a thread, and the bottom of the vertical pole is opened in a horizontal direction. Welding and fixing;

本发明提供一种组装工具式桁架,其中的桁架支撑梁,为组装工具式结构,所述桁架支撑梁为矩形钢管,与抗剪钢筋支架连接位置设置圆孔;桁架支撑梁分段布置,桁架支撑梁之间通过承插方式连接。The invention provides an assembly tool type truss, wherein the truss support beam is an assembly tool type structure, the truss support beam is a rectangular steel pipe, and a circular hole is set at the connection position with the shear steel support; The support beams are connected by sockets.

所述桁架支撑梁为矩形钢管,一端设置承插端,承插端尺寸略小于矩形钢管内径,且承插端端部设置坡面,方便桁架支撑梁之间的承插,在桁架支撑梁另一端外侧焊接耳板,通过敲击耳板的形式保证桁架支撑梁之间的可靠连接。The truss support beam is a rectangular steel pipe, one end is provided with a socket end, the size of the socket end is slightly smaller than the inner diameter of the rectangular steel pipe, and the end of the socket end is provided with a slope to facilitate the socket and socket between the truss support beams. The lug plate is welded on the outside of one end, and the reliable connection between the truss support beams is ensured by tapping the lug plate.

所述抗剪钢筋支架竖直筋穿过桁架支撑梁孔洞后通过螺母拧紧固定,竖直筋与第三弯折钢筋折弯位置设置螺母垫块,保证抗剪钢筋支架与桁架支撑梁紧密结合、连接牢固。The vertical bars of the shear-resisting steel bars pass through the holes of the truss support beams and are then tightened and fixed by nuts. Nut spacers are set at the bending positions of the vertical bars and the third bending bars to ensure that the shear-resistance steel bars are tightly combined with the truss support beams. The connection is firm.

所述支撑立杆与桁架支撑梁之间通过加长螺杆连接,加长螺杆可拧入支撑立杆,另一端穿过桁架支撑梁通过螺母拧紧固定。The support rod and the truss support beam are connected by an extension screw, the extension rod can be screwed into the support rod, and the other end passes through the truss support beam and is fastened and fixed by a nut.

本发明提供一种组装工具式桁架叠合板,其包括上述抗剪钢筋支架、桁架支撑梁、支撑立杆、底板。The present invention provides an assembly tool-type truss composite panel, which includes the above-mentioned shear-resisting steel bar bracket, a truss supporting beam, a supporting vertical rod, and a bottom plate.

抗剪钢筋支架底部有底板,底板上设置纵横底筋,长边方向底筋为预应力筋,短边方向为非预应力筋,抗剪钢筋支架与纵横底筋绑扎连接。There is a bottom plate at the bottom of the shear-resisting steel bar support, and vertical and horizontal bottom bars are arranged on the bottom plate.

所述抗剪钢筋支架的第一弯折钢筋全部、第二弯折钢筋、第三弯折钢筋的部分埋入底板,形成一定的锚固长度,底板加工完成后与抗剪钢筋支架形成一整体。All the first bending steel bars, the second bending steel bars and the third bending steel bars of the shearing steel reinforcement bracket are embedded in the bottom plate to form a certain anchoring length.

所述支撑立杆的水平杆全部、竖向立杆部分埋入底板,形成一定的锚固长度,底板加工完成后与支撑立杆形成一整体,施工现场浇筑混凝土时螺栓连接紧密,可减少组装桁架自身连接变形,组装刚度大,施工时在荷载作用下叠合板挠度小优点。All of the horizontal rods and part of the vertical rods of the support rods are buried in the bottom plate to form a certain anchoring length. After the bottom plate is processed, it forms a whole with the support rods. When the concrete is poured at the construction site, the bolts are tightly connected, which can reduce the number of trusses assembled. It has the advantages of self-connection deformation, high assembly rigidity, and small deflection of the laminated board under the load during construction.

一种组装工具式桁架叠合板的施工方法包括以下步骤:A construction method for assembling a tool-type truss composite board comprises the following steps:

步骤一:抗剪钢筋支架的制作Step 1: Fabrication of Shear Rebar Brackets

A:根据施工要求,将直径为6-10mm的钢筋截断;A: According to the construction requirements, cut off the steel bars with a diameter of 6-10mm;

B:将截断后的钢筋一端进行螺纹处理,螺纹长度为30-50mm;B: Thread one end of the truncated steel bar, and the thread length is 30-50mm;

C: 将第一弯折钢筋、第二弯折钢筋、第三弯折钢筋连续弯折组成三角形结构,再进行竖直筋弯折,竖直筋与第二弯折钢筋垂直,第一弯折钢筋、第三弯折钢筋、竖直筋交叉位置焊接连接。C: Continuously bend the first bending steel bar, the second bending steel bar, and the third bending steel bar to form a triangular structure, and then bend the vertical bar. The vertical bar is perpendicular to the second bending steel bar, and the first bending The steel bar, the third bending steel bar, and the vertical bar are welded and connected at the intersection.

步骤二:支撑立杆的制作Step 2: Fabrication of support poles

A:根据施工要求制作水平杆;A: Make horizontal rods according to construction requirements;

B:竖向立杆内部设置螺纹,螺纹深度约为竖向立杆长度的三分之二,竖向立杆另一端设置水平孔洞;B: A thread is set inside the vertical pole, the depth of the thread is about two-thirds of the length of the vertical pole, and a horizontal hole is set at the other end of the vertical pole;

C:水平杆穿过水平孔洞,在交叉位置焊接固定;C: The horizontal rod passes through the horizontal hole and is welded and fixed at the cross position;

步骤三:制作桁架支撑梁Step 3: Making the Truss Support Beam

A:桁架支撑梁采用矩形钢管,在矩形钢管设有与支撑立杆、抗剪钢筋支架对应位置开孔;A: The truss support beam is made of rectangular steel pipe, and the rectangular steel pipe is provided with openings corresponding to the supporting vertical rod and the shear steel bracket;

B:桁架支撑梁的始端安装耳板;B: The ear plate is installed at the beginning of the truss support beam;

C:桁架支承梁的末端制作承插部,承插部端部为棱台形,方便桁架支承梁插入。C: The end of the truss support beam is made into a socket part, and the end of the socket part is prismatic, which is convenient for the insertion of the truss support beam.

步骤四:制作底板Step 4: Making the Base Plate

A: 底板的制作在模台上完成,在制作之前在底板四边安装模板,控制叠合板尺寸;A: The production of the bottom plate is completed on the mold table. Before the production, the template is installed on the four sides of the bottom plate to control the size of the laminated board;

B: 安装完多块底板模板后铺设短边方向钢筋,再铺设长边通长钢筋,并对通长钢筋采用张拉设备对钢筋张拉,并对纵横向钢筋进行绑扎链接。B: After installing multiple base plate formworks, lay the short-side direction steel bars, and then lay the long-side full-length steel bars, and use the tensioning equipment to tension the steel bars for the full-length steel bars, and bind the vertical and horizontal steel bars.

步骤五:抗剪钢筋支架、支撑立杆及桁架支撑梁的连接组合。Step 5: The connection combination of shear steel support, support pole and truss support beam.

A:根据需求,将桁架支撑梁进行拼装组合A: Assemble and combine truss support beams according to requirements

B:通过螺母及螺母垫片将抗剪钢筋支架与桁架支撑梁连接固定,通过螺母及加长螺栓将支撑立杆与桁架支撑梁连接牢固;B: The shear steel support and the truss support beam are connected and fixed by nuts and nut washers, and the support rod and the truss support beam are firmly connected by nuts and extension bolts;

步骤六:在纵横钢筋上铺设桁架支撑梁组合件Step 6: Lay the truss support beam assembly on the longitudinal and transverse reinforcement

A:按照要求在相应位置将抗剪钢筋支架、支撑立杆及桁架支撑梁组合件放置到相应位置,抗剪钢筋支架与纵横钢筋绑扎连接;A: According to the requirements, place the shear-resisting steel support bracket, the support pole and the truss support beam assembly in the corresponding position, and connect the shear-resistant steel support bracket with the vertical and horizontal steel bars;

步骤七:预应力叠合板混凝土浇筑Step 7: Concrete pouring of prestressed composite slabs

A:钢筋桁架及桁架支撑梁放置完成后浇筑混凝土,混凝土厚度3.5-5cm,混凝土浇筑完成后对上表面毛化处理。A: Concrete is poured after the reinforced trusses and truss support beams are placed. The thickness of the concrete is 3.5-5cm. After the concrete is poured, the upper surface is textured.

B:浇筑完混凝土后对叠合板进行养护,达到一定强度后将预应力钢筋截断并拆除模板,达到吊装强度后将桁架支撑梁拆除,并将叠合板运至堆场或施工现场。在本步骤中所用桁架支撑梁只为生产叠合板中固定抗剪钢筋支架位置、标高作用,不承担施工过程荷载,与现场吊装浇筑混凝土叠合层的桁架支撑梁规格不同,作用不同。B: After the concrete is poured, the laminated board is maintained. After reaching a certain strength, the prestressed steel bars are cut off and the formwork is removed. After the hoisting strength is reached, the truss support beam is removed, and the laminated board is transported to the storage yard or construction site. The truss support beam used in this step is only used to fix the position and elevation of the shear steel support in the production of the laminated slab, and does not bear the load during the construction process.

步骤八:预应力叠合板安装Step 8: Prestressed Laminated Panel Installation

A:预应力叠合板安装前将桁架支撑梁组合件安装到叠合板并进行固定,再按照图纸位置要求将叠合板吊装至相应位置,叠合板两端放置于两侧结构梁上。A: Before installing the prestressed laminated board, install the truss support beam assembly to the laminated board and fix it, and then hoist the laminated board to the corresponding position according to the position requirements of the drawing, and place the two ends of the laminated board on the structural beams on both sides.

B:叠合板吊装完成后绑扎叠合板上部钢筋;B: After the hoisting of the laminated board is completed, the upper steel bars of the laminated board are bound;

步骤九:浇注第二层叠合混凝土Step 9: Pouring the Second Layer of Laminated Concrete

绑扎完上部钢筋后浇筑上部第二层叠合混凝土,混凝土浇筑高度距离桁架支撑梁底部2-3cm。After binding the upper steel bars, pour the upper second layer of laminated concrete, and the concrete pouring height is 2-3cm from the bottom of the truss support beam.

步骤十:拆卸桁架支撑梁Step 10: Remove the truss support beam

浇筑完上部混凝土后对混凝土表面收光处理,待混凝度达到一定强度后将桁架支撑梁拆除,拆除桁架支撑梁时首先将螺母拆除,拆除螺母后依次将桁架支撑梁及加长螺栓拆除。螺母、桁架支撑梁、加长螺栓拆除后再进行后续叠合板的使用。After the upper concrete is poured, the surface of the concrete is polished. After the concrete reaches a certain strength, the truss support beam is removed. When the truss support beam is removed, the nut is first removed. After the nut is removed, the truss support beam and extension bolts are removed in turn. Nuts, truss support beams, and extension bolts are removed before subsequent use of the laminated board.

实施例2Example 2

与实施例1的不同之处主要在于,桁架支撑梁的结构为圆形钢管,所涉及的抗剪钢筋支架底部有底板,底板上设置纵横底筋,长边方向底筋为非预应力筋,短边方向为非预应力筋,抗剪钢筋支架与纵横底筋绑扎连接。The main difference from Example 1 is that the structure of the truss support beam is a circular steel pipe, the involved shear reinforcement support has a bottom plate at the bottom, vertical and horizontal bottom bars are arranged on the bottom plate, and the bottom bars in the long side direction are non-prestressed tendons, The direction of the short side is the non-prestressed reinforcement, and the shear reinforcement support is bound with the vertical and horizontal bottom reinforcement.

桁架的结构不限于矩形钢管,还可以采用圆形钢管,也可以不限制材质,另外采用工字钢和槽钢也可;连接件的结构不限于采用销子、螺纹连接。The structure of the truss is not limited to rectangular steel pipes, but can also be circular steel pipes, or not limited in material. In addition, I-beam and channel steel can also be used; the structure of the connector is not limited to the use of pins and threads.

上述实施例仅例示性说明本发明的原理及其功效,而非用于限制本发明。任何熟悉此技术的人士皆可在不违背本发明的精神及范畴下,对上述实施例进行修饰或改变。因此,举凡所属技术领域中具有通常知识者在未脱离本发明所揭示的精神与技术思想下所完成的一切等效修饰或改变,仍应由本发明的权利要求所涵盖。The above-mentioned embodiments merely illustrate the principles and effects of the present invention, but are not intended to limit the present invention. Anyone skilled in the art can modify or change the above embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or changes made by those with ordinary knowledge in the technical field without departing from the spirit and technical idea disclosed in the present invention should still be covered by the claims of the present invention.

Claims (6)

1. A construction method for assembling tool type truss composite slabs is characterized in that,
the method comprises the following steps:
the method comprises the following steps: manufacturing method of shear-resistant steel bar support
A: cutting off the steel bars with the diameter of 6-10mm according to the construction requirements;
b: performing thread processing on one end of the cut steel bar, wherein the length of the thread is 30-50 mm;
c, continuously bending the first bent reinforcing steel bar, the second bent reinforcing steel bar and the third bent reinforcing steel bar to form a triangular structure, and then bending the vertical reinforcing steel bar, wherein the vertical reinforcing steel bar is vertical to the second bent reinforcing steel bar, and the crossing positions of the first bent reinforcing steel bar, the third bent reinforcing steel bar and the vertical reinforcing steel bar are welded and connected;
step two: production of supporting vertical rod
A: manufacturing a horizontal rod according to construction requirements;
b: threads are arranged in the vertical upright rod, the depth of the threads is about two thirds of the length of the vertical upright rod, and a horizontal hole is formed in the other end of the vertical upright rod;
c: the horizontal rod passes through the horizontal hole and is welded and fixed at the crossed position;
step three: truss support beam manufacturing method
A: the truss supporting beam is a rectangular steel pipe, and the rectangular steel pipe is provided with holes corresponding to the supporting upright rods and the shear steel bar supports;
b: an ear plate is arranged at the starting end of the truss supporting beam;
c: the end part of the socket part is in a frustum pyramid shape, so that the truss supporting beam can be conveniently inserted;
step four: making the sole
A, finishing the manufacture of a bottom plate on a mould table, installing templates on four sides of the bottom plate before the manufacture, and controlling the size of a laminated plate;
b, laying short-side direction reinforcing steel bars after a plurality of bottom plate templates are installed, laying long-side through long reinforcing steel bars, tensioning the through long reinforcing steel bars by adopting tensioning equipment, and binding and linking longitudinal and transverse reinforcing steel bars;
step five: the shear steel bar support, the support upright stanchion and the truss support beam are connected and combined;
a, assembling and combining the truss support beams according to requirements
B: the shear steel bar support is fixedly connected with the truss supporting beam through nuts and nut gaskets, and the supporting upright rods are firmly connected with the truss supporting beam through nuts and lengthened bolts;
step six: truss support beam assembly for laying longitudinal and transverse steel bars
A: placing the shear steel bar support, the support upright stanchion and the truss support beam assembly at corresponding positions according to requirements, and binding and connecting the shear steel bar support and the longitudinal and transverse steel bars;
step seven: concrete pouring of prestressed superimposed plate
A: after the steel bar truss and the truss supporting beam are placed, pouring concrete, wherein the thickness of the concrete is 3.5-5cm, and after the concrete is poured, roughening the upper surface;
b: after the concrete is poured, maintaining the laminated slab, cutting off the prestressed reinforcement and removing the template after certain strength is achieved, removing the truss supporting beam after the hoisting strength is achieved, and transporting the laminated slab to a storage yard or a construction site; the truss support beam used in the step only plays roles in fixing the position and the elevation of the shear steel bar support in the production of the composite slab, does not bear the load in the construction process, and has different specifications and different roles compared with the truss support beam for hoisting and pouring the concrete composite layer on site;
step eight: prestressed laminated slab installation
A: before the prestressed composite slab is installed, the truss support beam assembly is installed on the composite slab and fixed, then the composite slab is hoisted to a corresponding position according to the position requirement of a drawing, and two ends of the composite slab are placed on the structural beams on two sides;
b: binding the upper steel bars of the laminated slabs after the hoisting of the laminated slabs is finished;
step nine: pouring second layer laminated concrete
After binding the upper reinforcing steel bars, pouring second laminated concrete on the upper part, wherein the pouring height of the concrete is 2-3cm away from the bottom of the truss supporting beam;
after the upper concrete is poured, performing light collection treatment on the surface of the concrete, dismantling the truss supporting beam after the concrete degree reaches a certain strength, dismantling the nut firstly when dismantling the truss supporting beam, and dismantling the truss supporting beam and the lengthened bolt in sequence after dismantling the nut;
and the nuts, the truss supporting beams and the lengthened bolts are removed and then the subsequent laminated plate is used.
2. The utility model provides an assembly tool formula truss superimposed sheet which characterized in that, assembly tool formula truss superimposed sheet still includes shear steel bar support, supports pole setting, truss supporting beam and bottom plate.
3. The assembly tool type truss composite slab as claimed in claim 2, wherein the shear reinforcement bracket of the assembly tool type truss composite slab is composed of a first bent reinforcement, a second bent reinforcement, a third bent reinforcement, and a vertical reinforcement, and the shear reinforcement bracket is triangular;
the first bent reinforcing steel bar, the second bent reinforcing steel bar and the third bent reinforcing steel bar are of triangular structures, the end part of the first bent reinforcing steel bar is fixedly welded with the tail part of the third bent reinforcing steel bar, and the tail part of the third bent reinforcing steel bar is connected with the vertical bar;
the included angle among the first bent reinforcing steel bar, the second bent reinforcing steel bar and the third bent reinforcing steel bar is 45-75 degrees, the vertical reinforcing steel bar is perpendicular to the second bent reinforcing steel bar, and the end part of the vertical reinforcing steel bar is provided with a thread;
the first bent reinforcing steel bar, the second bent reinforcing steel bar, the third bent reinforcing steel bar and the vertical reinforcing steel bar are integrally formed.
4. The assembly tool type truss composite slab as claimed in claim 3, wherein the supporting vertical rods are of an inverted T-shaped structure and comprise horizontal rods and vertical rods, wherein threads are arranged on the inner sides of the vertical rods, holes are formed in the bottoms of the vertical rods in the horizontal direction, and the horizontal rods penetrate through the holes and are welded and fixed at the crossing positions.
5. The assembly tool type truss composite slab as claimed in claim 3, wherein the truss support beam is of an assembly tool type structure, and the connecting position of the truss support beam and the shear-resistant steel bar support is provided with a circular hole; the truss support beams are arranged in sections and connected in a socket mode;
one end of each truss supporting beam is provided with a socket end, the size of each socket end is slightly smaller than the inner diameter of the steel pipe, the end part of each socket end is provided with a slope, socket joint between the truss supporting beams is facilitated, and an ear plate is welded on the outer side of the other end of each truss supporting beam;
the vertical ribs of the shear steel bar support penetrate through the holes of the truss support beams and are screwed and fixed through nuts, and nut cushion blocks are arranged at the bending positions of the vertical ribs and the third bent steel bars;
the supporting vertical rod is connected with the truss supporting beam through a lengthened screw rod, the lengthened screw rod can be screwed into the supporting vertical rod, and the other end of the lengthened screw rod penetrates through the truss supporting beam and is screwed and fixed through a nut.
6. The assembly tool type truss composite slab as claimed in claim 2, wherein the shear reinforcement support of the assembly tool type truss composite slab has a bottom plate at the bottom, the bottom plate is provided with longitudinal and transverse bottom ribs, the bottom rib in the long side direction is a prestressed rib, the bottom rib in the short side direction is a non-prestressed rib, and the shear reinforcement support is bound and connected with the longitudinal and transverse bottom ribs;
the shear steel bar support is characterized in that all the first bent steel bars, the second bent steel bars and the third bent steel bars of the shear steel bar support are embedded into the bottom plate to form a certain anchoring length, and the bottom plate and the shear steel bar support form a whole after being processed.
CN201911184957.5A 2019-11-27 2019-11-27 An assembly tool type truss composite plate and construction method thereof Active CN110748065B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911184957.5A CN110748065B (en) 2019-11-27 2019-11-27 An assembly tool type truss composite plate and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911184957.5A CN110748065B (en) 2019-11-27 2019-11-27 An assembly tool type truss composite plate and construction method thereof

Publications (2)

Publication Number Publication Date
CN110748065A true CN110748065A (en) 2020-02-04
CN110748065B CN110748065B (en) 2025-04-15

Family

ID=69284826

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911184957.5A Active CN110748065B (en) 2019-11-27 2019-11-27 An assembly tool type truss composite plate and construction method thereof

Country Status (1)

Country Link
CN (1) CN110748065B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031239A (en) * 2020-09-03 2020-12-04 四川省佳宇建设集团有限公司 Precast concrete composite floor slab and manufacturing method thereof
CN112976256A (en) * 2021-02-05 2021-06-18 王示 Production process of prestressed concrete laminated slab bottom plate
CN113931364A (en) * 2021-10-29 2022-01-14 筑友智造建设科技集团有限公司 Construction method of prestressed thin plate with detachable ribs and laminated slab
CN114059702A (en) * 2021-11-30 2022-02-18 山东乾元泽孚科技股份有限公司 Laminated plate
CN114075851A (en) * 2020-08-15 2022-02-22 长沙巨星轻质建材股份有限公司 A kind of prefabricated concrete prestressed base plate
CN114215099A (en) * 2021-12-17 2022-03-22 中国十七冶集团有限公司 Method for efficiently laying through long steel bars at bottom of converter high-span foundation
CN114673287A (en) * 2022-04-20 2022-06-28 中建三局集团有限公司 Novel laminated slab construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080060294A1 (en) * 2006-09-11 2008-03-13 Cox Brian L Concrete slab modular reinforcing panels
CN101161955A (en) * 2006-10-13 2008-04-16 杨峰 Bidirectional girder compound floor construction method
KR20080001375U (en) * 2007-10-19 2008-05-27 진언식 Shear reinforcement structure of flat slab
KR100901766B1 (en) * 2009-02-05 2009-06-11 주식회사 반석티비에스 2-way slab using 1-way half PC and construction method
CN202298891U (en) * 2011-08-12 2012-07-04 清华大学 Large hidden grid type or truss type mixed component
CN107558382A (en) * 2017-10-16 2018-01-09 中交路桥建设有限公司 A kind of heavy type truss pipe support system
CN109667377A (en) * 2019-01-29 2019-04-23 天津城建大学 The construction method and prestressed concrete overlapped slab of prestressed concrete overlapped slab
CN110185182A (en) * 2019-06-13 2019-08-30 天津城建大学 Concrete folding plate construction is with being stably connected with structure and construction method
CN211341358U (en) * 2019-11-27 2020-08-25 山东德建集团有限公司 Assembling tool type truss laminated slab

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080060294A1 (en) * 2006-09-11 2008-03-13 Cox Brian L Concrete slab modular reinforcing panels
CN101161955A (en) * 2006-10-13 2008-04-16 杨峰 Bidirectional girder compound floor construction method
KR20080001375U (en) * 2007-10-19 2008-05-27 진언식 Shear reinforcement structure of flat slab
KR100901766B1 (en) * 2009-02-05 2009-06-11 주식회사 반석티비에스 2-way slab using 1-way half PC and construction method
CN202298891U (en) * 2011-08-12 2012-07-04 清华大学 Large hidden grid type or truss type mixed component
CN107558382A (en) * 2017-10-16 2018-01-09 中交路桥建设有限公司 A kind of heavy type truss pipe support system
CN109667377A (en) * 2019-01-29 2019-04-23 天津城建大学 The construction method and prestressed concrete overlapped slab of prestressed concrete overlapped slab
CN110185182A (en) * 2019-06-13 2019-08-30 天津城建大学 Concrete folding plate construction is with being stably connected with structure and construction method
CN211341358U (en) * 2019-11-27 2020-08-25 山东德建集团有限公司 Assembling tool type truss laminated slab

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114075851A (en) * 2020-08-15 2022-02-22 长沙巨星轻质建材股份有限公司 A kind of prefabricated concrete prestressed base plate
CN112031239A (en) * 2020-09-03 2020-12-04 四川省佳宇建设集团有限公司 Precast concrete composite floor slab and manufacturing method thereof
CN112976256A (en) * 2021-02-05 2021-06-18 王示 Production process of prestressed concrete laminated slab bottom plate
CN113931364A (en) * 2021-10-29 2022-01-14 筑友智造建设科技集团有限公司 Construction method of prestressed thin plate with detachable ribs and laminated slab
CN114059702A (en) * 2021-11-30 2022-02-18 山东乾元泽孚科技股份有限公司 Laminated plate
WO2023098310A1 (en) * 2021-11-30 2023-06-08 山东乾元泽孚科技股份有限公司 Lattice girder slab
CN114215099A (en) * 2021-12-17 2022-03-22 中国十七冶集团有限公司 Method for efficiently laying through long steel bars at bottom of converter high-span foundation
CN114673287A (en) * 2022-04-20 2022-06-28 中建三局集团有限公司 Novel laminated slab construction method

Also Published As

Publication number Publication date
CN110748065B (en) 2025-04-15

Similar Documents

Publication Publication Date Title
CN110748065A (en) Assembling tool type truss composite slab and construction method thereof
CN100482892C (en) Lower chord opening beam type corrugated steel web combination beam
CN201087480Y (en) Prestressed concrete composite beam
CN111648512B (en) An assembly tool type truss composite plate and construction method thereof
CN108571071A (en) Prefabricated PC beams of concrete column connected node and construction method
CN113653235A (en) Laminated slab, connecting structure of laminated slab and combination beam and construction method
CN111705987B (en) A large-span prefabricated ribbed prestressed hollow bidirectional composite slab
CN111705650A (en) Cast-in-place joint structure of UHPC beam-slab with pre-embedded reinforcing steel parts and its construction method
CN110005109A (en) A kind of open flume type prestressed concrete overlapped slab
CN111794424A (en) A kind of integral laminated board honeycomb composite beam and manufacturing method
CN101435237A (en) Novel hollow combined board
CN111794425A (en) A kind of separated laminated board honeycomb composite beam and method
CN111794423A (en) A steel-concrete composite beam structure, building and construction method
CN208039577U (en) Half prefabricated prestressed concrete floor slab of figure of eight steel bar girder
CN108755929A (en) A kind of assembled pre-tensioned prestressed concrete frame and its construction technology
CN220565527U (en) Assembled rib plate structure
CN219365020U (en) Combined assembly type concrete shear wall
CN117779944A (en) Support-free assembled reinforced concrete frame structure adopting hybrid connection
CN217580713U (en) A prefabricated combined shear wall
CN215630973U (en) Rib key full-splicing type assembled integral type steel concrete combined hollow sandwich plate
CN110748066A (en) A support-free laminated board including truss and truss processing device and method
CN211341358U (en) Assembling tool type truss laminated slab
CN211341356U (en) Assembling tool type truss laminated slab
CN212772980U (en) A prefabricated composite wall based on C-shaped steel
CN113700153A (en) Connecting structure of assembled laminated slab and combination beam and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 253000 Dejian building, East Sanba Road, Dezhou Economic Development Zone, Shandong Province

Applicant after: Shandong Expressway Dejian Group Co.,Ltd.

Address before: 253000 Dejian building, East Sanba Road, Dezhou Economic Development Zone, Shandong Province

Applicant before: SHANDONG DEJIAN GROUP Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant