CN110700854B - Tunnel secondary lining vault concrete longitudinal continuous pouring construction method - Google Patents

Tunnel secondary lining vault concrete longitudinal continuous pouring construction method Download PDF

Info

Publication number
CN110700854B
CN110700854B CN201910759507.8A CN201910759507A CN110700854B CN 110700854 B CN110700854 B CN 110700854B CN 201910759507 A CN201910759507 A CN 201910759507A CN 110700854 B CN110700854 B CN 110700854B
Authority
CN
China
Prior art keywords
concrete
pouring
lining
longitudinal
trolley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910759507.8A
Other languages
Chinese (zh)
Other versions
CN110700854A (en
Inventor
熊小锋
聂清文
梁彬彬
冯小竹
周立新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
First Engineering Co Ltd of China Railway No 12 Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
First Engineering Co Ltd of China Railway No 12 Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, First Engineering Co Ltd of China Railway No 12 Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201910759507.8A priority Critical patent/CN110700854B/en
Publication of CN110700854A publication Critical patent/CN110700854A/en
Application granted granted Critical
Publication of CN110700854B publication Critical patent/CN110700854B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Abstract

The invention belongs to the technical field of tunnel engineering construction, and particularly relates to a tunnel secondary lining vault concrete longitudinal continuous pouring construction method. The method solves the problems that arch concrete can not be filled compactly, and the lining quality such as insufficient thickness of a second lining, back void, incompact lining and the like is formed, and comprises the following steps of S100-measurement lofting, S200-walking, positioning and reinforcing of a second lining trolley, and S300-longitudinal continuous pouring of the trolley in place; s400, pouring concrete of the two lining side walls; s500, after the concrete of the second lining side wall part is poured and vibrated layer by layer window by window, the concrete pump pipe interface is replaced to a longitudinal continuous pouring trolley, and the performance of the concrete of the second lining vault on site is detected, and the slump of the concrete entering the mould is required to be controlled to be 170-190 mm. S600, starting a concrete delivery pump, and S700, longitudinally and continuously pouring the second liner vault concrete in a retreating way; s800, exiting the station to clean the pipeline, and finishing the filling; and S900-RPC belt mold pressing slurry.

Description

Tunnel secondary lining vault concrete longitudinal continuous pouring construction method
Technical Field
The invention belongs to the technical field of tunnel engineering construction, and particularly relates to a tunnel secondary lining vault concrete longitudinal continuous pouring construction method.
Background
With the deep and continuous development of railway construction work, the engineering construction in China has been transformed from the previous scale speed type to the quality benefit type. The traditional construction process of the two linings of the tunnel at present adopts a full-hydraulic lining trolley to carry out layered pouring by windows and vault concrete top-flushing pouring construction process from bottom to top, and the two linings are poured and then are timely subjected to mould-pressing slurry.
Disclosure of Invention
The invention provides a longitudinal continuous pouring construction method for arch crown concrete of a tunnel with two linings, which aims to solve the problems that arch concrete cannot be filled compactly easily and the lining quality such as insufficient thickness of the two linings, back void, incompact lining and the like is formed by adopting a full-hydraulic lining trolley according to a window-by-window layered pouring and arch crown concrete top-punching pouring construction process from bottom to top.
The invention adopts the following technical scheme: a tunnel secondary lining vault concrete longitudinal continuous pouring construction method comprises the following steps.
S100, measuring and lofting, wherein a measurer releases the position of the central line of the inner outline tunnel of the secondary lining of the tunnel, determines the positioning elevation of the trolley, and guides the site trolley to be in place according to the designed position.
S200, walking, positioning and reinforcing the secondary lining trolley, walking the secondary lining trolley to a design position of a secondary lining profile of the tunnel according to the field measurement condition, positioning under the guidance of a measuring person, and reinforcing the secondary lining trolley and setting and reinforcing a secondary lining end head die of the tunnel after the positioning is finished.
S300, longitudinally and continuously pouring a trolley into position; the longitudinal cast-in-place concrete gun of the cast-in-place trolley is conveyed to the bottom of the two lining ends in the longitudinal direction by the cast-in-place travelling trolley, the distance between the end of the longitudinal cast-in-place concrete gun and the bottom of the two lining ends is 60cm, and a visual monitoring system and a concrete pressure detection sensor are mounted on the longitudinal cast-in-place concrete gun.
S400, pouring concrete of the two lining side walls; and (3) adopting a two-lining trolley to pour layer by layer window by window, feeding materials layer by layer window by window, symmetrically pouring partial concrete of the two lining side walls, and pouring layer by layer and vibrating and compacting layer by layer.
S500, after the concrete of the second lining side wall part is poured and vibrated layer by layer window by window, the concrete pump pipe interface is replaced to a longitudinal continuous pouring trolley, and the performance of the concrete of the second lining vault on site is detected, and the slump of the concrete entering the mould is required to be controlled to be 170-190 mm.
S600, starting a concrete delivery pump, and starting longitudinal continuous pouring of the concrete with the two lining vault tops, wherein in the pouring process, a longitudinal pouring concrete gun moves back and forth every 5 minutes to ensure that the longitudinal pouring concrete gun can freely move in the concrete, and the longitudinal pouring concrete gun is always buried in the concrete in the pouring process to ensure that the interior of the pouring concrete is kept under pressure for pouring.
S700-pouring second-lining vault concrete longitudinally and continuously in a retreating mode; when concrete is poured to the high position of the arch top of the secondary lining of the tunnel, detecting the pressure of the concrete backing flooding wrapping pouring gun through a concrete pressure sensor, and backing the longitudinal pouring concrete gun according to the step pitch of 0.6 m; and (3) starting the two-lining trolley attached vibrators one by one in the filling process, and carrying out layering and regional vibration compaction on the two-lining concrete until the two-lining concrete is fully filled.
S800, exiting the station to clean the pipeline, and finishing the filling; and cleaning the longitudinal poured concrete pipeline by using a piston, driving the longitudinal continuous pouring trolley to exit the station, and finishing the longitudinal continuous pouring of the concrete with the two lining vault tops.
S900-RPC belt mold pressing slurry; and after the secondary lining concrete is poured for 2 hours, hole-by-hole tape mold grouting is carried out on the vault of the secondary lining by using RPC pipe tape mold grouting until the grouting hole and the exhaust hole are plugged after the slurry overflows from the end of the secondary lining, the grouting system is dismantled, and grouting is finished.
Compared with the prior art, the invention has the following beneficial effects:
1. and the construction cost is saved. Compared with the traditional vertical pouring construction method, although the cost of one-time investment of matched equipment is about 100 ten thousand yuan, the process can greatly reduce the cost of two-lining vault grouting, the economic benefit of the process for the long and large tunnel is more obvious, and the construction cost can be greatly saved.
2. Effectively improving the construction quality of the tunnel secondary lining. Compared with the traditional vertical pouring construction method, the construction method can greatly improve the construction quality of the vault concrete of the tunnel secondary lining, avoid the problem of red lines of the tunnel secondary lining, greatly reduce the quality defects and greatly improve the construction quality of the tunnel secondary lining.
3. The operation is simple, safe and reliable. Compared with the traditional vertical pouring construction method, the construction method adopts a full-automatic detection and process conversion system to replace frequent pipe replacement, pipe inversion and other manual matching processes in the vault concrete construction process of the traditional tunnel secondary lining construction process, so that the safety risk in the construction process is avoided from the aspect of intrinsic safety, and the construction method is simple to operate, easy to master and small in safety risk.
4. Accelerating the construction progress of the tunnel secondary lining. Compared with the traditional construction method, the construction method can save the time spent on frequent pipe replacement, pipe inversion and other manual matching procedures in the vault concrete construction process of the traditional tunnel secondary lining construction process, and quickens the site construction progress.
5. Is easy to be popularized and applied. Compared with the traditional vertical pouring construction method, the construction method has no difference on the construction conditions of people, materials, machines, rings and the like required by the tunnel secondary lining construction except that the longitudinal continuous pouring matched equipment is required to be put into the construction method along with the sleeve, and is easy to popularize and apply.
Drawings
FIG. 1 is a process flow diagram of the invention;
fig. 2 is a schematic diagram of the longitudinal continuous perfusion profile principle.
Detailed Description
A tunnel secondary lining vault concrete longitudinal continuous pouring construction method comprises the following steps:
s100, measuring and lofting, wherein a measurer releases the position of the central line of the inner outline tunnel of the secondary lining of the tunnel, determines the positioning elevation of the trolley, and guides the site trolley to be in place according to the designed position.
S200, walking, positioning and reinforcing the secondary lining trolley, walking the secondary lining trolley to a design position of a secondary lining profile of the tunnel according to the field measurement condition, positioning under the guidance of a measuring person, and reinforcing the secondary lining trolley and setting and reinforcing a secondary lining end head die of the tunnel after the positioning is finished.
S300, longitudinally and continuously pouring a trolley into position; the longitudinal pouring concrete gun of the pouring trolley is conveyed to the bottom of the end of the two lining ends by the pouring travelling trolley in the longitudinal direction, and the visual monitoring system and the concrete pressure detection sensor are installed on the longitudinal pouring concrete gun.
S400, pouring concrete of the two lining side walls; and (3) adopting a two-lining trolley to pour layer by layer window by window, feeding materials layer by layer window by window, symmetrically pouring partial concrete of the two lining side walls, and pouring layer by layer and vibrating and compacting layer by layer.
S500-after the concrete of the two lining side walls is poured and vibrated layer by layer window by window, the concrete pump pipe interface is replaced to a longitudinal continuous pouring trolley for longitudinal pouring.
S600, starting a concrete delivery pump, starting longitudinal continuous pouring of the concrete with the two lining vault tops, and enabling a longitudinal pouring concrete gun to move back and forth every 5 minutes in the pouring process to ensure that the longitudinal pouring concrete can freely move in the concrete.
S700-pouring second-lining vault concrete longitudinally and continuously in a retreating mode; when concrete is poured to the high position of the arch top of the secondary lining of the tunnel, detecting the pressure of the concrete backing flooding wrapping pouring gun through a concrete pressure sensor, and backing the longitudinal pouring concrete gun according to the step pitch of 0.6 m; and (3) starting the two-lining trolley attached vibrators one by one in the filling process, and carrying out layering and regional vibration compaction on the two-lining concrete until the two-lining concrete is fully filled.
S800, exiting the station to clean the pipeline, and finishing the filling; and cleaning the longitudinal poured concrete pipeline by using a piston, driving the longitudinal continuous pouring trolley to exit the station, and finishing the longitudinal continuous pouring of the concrete with the two lining vault tops.
S900-RPC belt mold pressing slurry; and after the secondary lining concrete is poured for 2 hours, hole-by-hole tape mold grouting is carried out on the vault of the secondary lining by using RPC pipe tape mold grouting until the grouting hole and the exhaust hole are plugged after the slurry overflows from the end of the secondary lining, the grouting system is dismantled, and grouting is finished.
In the step S300, the distance between the tip of the longitudinal concrete pouring gun and the top of the upper plate or the bottom of the two lining tips is 60 cm. The method aims to ensure that the concrete has certain degree of freedom after entering a mould from a longitudinal pouring gun, and meanwhile, when the concrete is continuously poured to the arch crown high position, the pouring gun can be quickly wrapped to form a pile base layer which is reversely backfilled and wraps the natural gradient of the concrete required by flooding type pouring, so that a principle foundation is formed for a longitudinal continuous pouring process, and the subsequent process of the process is realized; if the distance is too large, the principle foundation is not formed quickly, and the failure of the longitudinal continuous perfusion process is easily caused; if the distance is too small, the degree of freedom of the concrete entering the mold is too small, and the early formation principle foundation can cause that the concrete at the end of the two lining ends is not easy to fill compactly, so that the problems of void, insufficient thickness or non-compact quality are formed.
In the step S500, in the longitudinal pouring process, the performance of the on-site second-lining vault concrete needs to be detected, and the slump of the concrete entering the mold needs to be controlled to 170 mm-190 mm. The slump control of the concrete entering the mould is a control range determined by repeated contrast tests, the concrete entering the mould with different slump is prepared one by one according to the performance requirements of the railway concrete construction quality acceptance standard on the concrete of the second liner, the contrast tests are respectively carried out, and the concrete entering the mould can form a stable concrete natural slope accumulation layer by finally determining that the concrete entering the mould can form the stable concrete natural slope accumulation layer when the slump of the concrete entering the mould is 170-190 mm through actual observation by taking whether the stable concrete natural slope accumulation layer can be formed in the longitudinal continuous pouring process. The performance of the concrete is a key factor of process success or failure, and the control of the cohesiveness, the workability and the slump of the concrete determines whether the process can form a natural gradient accumulation layer of the concrete, so that a back-pressure backfill package flooding type continuous retreat pouring is formed by wrapping a longitudinal pouring concrete gun. The pouring mode is that after the longitudinal continuous pouring process is switched, when the concrete entering the mould needs to meet the process requirement performance, the concrete enters the space of the two lining arch parts from the longitudinal pouring gun, and forms concrete stacking layer according to a certain natural gradient under the action of gravity, and the concrete stacking layer gradually extends and stacks to the arch top high position along with the continuous pouring of the concrete, and gradually wraps the longitudinal pouring gun; at the moment, the end of the filling gun is buried in the concrete, the concrete is continuously filled through the filling gun, the concrete is extruded out from the inside of the accumulation layer, and a space of the two lining arches is backfilled by back pressure; along with the continuous filling of the longitudinal continuous filling process, the concrete stacking layer filled with the space of the two lining arches gradually retreats in a flooding mode, the length of the wrapped longitudinal continuous filling gun is longer and longer, in order to ensure that the longitudinal filling gun can move freely and be pulled out, when the length of the flooded wrapped filling gun is detected by a pressure sensor to exceed 1m, the longitudinal continuous filling gun retreats in time at a step distance of 0.6m, and the longitudinal filling gun is ensured to be always buried in the concrete with the length not less than 1m before the process pipe drawing is finally completed; and the longitudinal concrete pouring gun is buried in the concrete all the time in the pouring process, so that the inside of the poured concrete is kept to be poured under pressure until the longitudinal continuous pouring is finished. The two-lining vault concrete longitudinal continuous pouring construction process needs to strictly control the raw material quality and the construction mix proportion of concrete, the raw material of the concrete needs to meet the requirements of the railway concrete construction quality acceptance standard, the construction mix proportion needs to be implemented according to the concrete mix proportion determined and approved by tests strictly, and the slump of the concrete entering a mold is controlled to be 170-190 mm.
In the step S600, the longitudinal concrete pouring gun is buried in the concrete during the pouring process, so as to ensure that the inside of the poured concrete is kept poured under pressure.
Economic benefits are as follows:
by adopting the method for construction, the cycle time of second lining construction of the tunnel is saved, the construction efficiency is increased, the ubiquitous lining construction quality problem of the vault of the tunnel is greatly reduced, the quality problem improvement construction cost is greatly reduced, the cost of the grouting material with the mould can be greatly reduced, the economic benefit is good, the operation is simple, the safety and the reliability are realized, the construction is convenient, the grasping is easy, and the better economic benefit is obtained.
Compared with the traditional vertical hole-by-hole top punching construction process, the quality problem and red line problem commonly existing in the tunnel secondary lining vault are thoroughly solved, the quantity of general quality problems at the back of the tunnel secondary lining vault is reduced from 0.35 per plate to 0 per plate, the quantity of red line quality problems is reduced from 0.15 per plate to 0 per plate, and the quality problem renovation construction cost is greatly reduced; the two-lining construction cycle time is shortened, the traditional construction process is adopted, the two-lining vault concrete top punching cycle time is generally 4 hours, the cycle time is only 2 hours, 50% of cycle time can be saved, and the construction efficiency is greatly improved; in addition, the construction method can ensure that the arch crown concrete of the tunnel secondary lining is fully dense, the consumption of the grouting material with the mould is reduced to 300 kg/plate from the original 800 kg/plate, and the cost of the grouting material with the mould is greatly reduced; meanwhile, the longitudinal continuous pouring matched equipment which is put into once can be used in a turnover mode, the economic benefit is obvious through comparison, and the economic benefit reflected by the construction method is more obvious when the tunnel is longer.
By adopting the construction method, the frequent procedure handover and function conversion required by the traditional construction method are omitted, all actions such as the extension and extraction of a filling gun, the position detection of the poured concrete, the trolley walking positioning and the like are automatically completed by the corresponding control system, the labor intensity of manpower is greatly reduced, the construction of the two-lining vault concrete is completely undertaken by the mechanical equipment matched with the construction method, the quality and safety technology monitoring in the aspects of starting the control system and implementing the process is realized, the construction safety risk is greatly reduced from the aspect of 'intrinsic safety', good safety benefit is created, and the safety benefit is actually economic benefit in the construction field.
Environmental and energy-saving benefits:
compared with the traditional vertical interval top-punching construction method, the method fully utilizes the existing construction elements such as construction materials, machines, equipment and personnel allocation, reduces pollution and waste caused by frequent procedure handover, and reduces damage to the ecological environment; the turnover materials and the machine tool equipment are fully utilized, so that the energy consumption is reduced while the waste is avoided; the construction progress is accelerated, the construction cost is reduced, and meanwhile, the environmental and energy-saving benefits are obvious.
Engineering example:
the new construction of the kuncao energy-expanding project is in the southwest region of China, and the project can be worried about the mountains and the ravines along the line, the conditions are extremely complex, and the project is called as a geological museum. The railway of Chengquan railway and Chengqing, Chengqing railway of Chengquan railway and Chengyun railway of Chengquan city north section, Chenglan railway, Xichengke railway, ChengYuke railway and planning Sichuan Qing, Chuanhang etc. form the railway big channel to the areas of Sichuan west, northwest Guangdong area and North China, northeast China, east China, etc. intersect with the Zhao Panli railway planned, can lead to the direction of Lijiang and Yunnan northeast China, Qianxi district, connect with Kunming hub southward, reach Yunnan, Qian, Gui and Zhujiang triangular district, it is an important component of the skeleton road network in the southwest area, have very important strategic significance to the national economic development.
Aiming at the lining quality problem commonly existing in the current tunnel engineering, a new process for developing secondary lining construction of the tunnel is developed by twelve Central iron office group Limited company relying on Kuntze railway Emei-Mi section Laitian tunnel engineering, aiming at solving the problem of quality defects of vault lining of the tunnel, a new process for changing a vertical pouring mode into a longitudinal continuous pouring mode is provided, the Laitian tunnel has the total length of 13579 meters and is positioned in the Emei county of le mountain City in Sichuan province, and the process is a full-line hard control engineering.
Construction conditions are as follows: the old nose mountain tunnel exit work area bears the construction task of 2580 meters of old nose mountain tunnel, and is successfully applied in the construction process of the secondary lining of the tunnel with the residual 1240 meters.
Engineering detection and result evaluation: the quality of 1240 m second-lining construction entities in the finished old mountain tunnel exit working area is subjected to engineering detection by qualified third-party detection units, all indexes meet the design and specification requirements, the construction process and results are ideal, and the expected purpose is achieved.

Claims (3)

1. A tunnel secondary lining vault concrete longitudinal continuous pouring construction method is characterized in that: comprises the following steps of (a) carrying out,
s100, measuring and lofting, wherein a measurer releases the position of the central line of the inner outline tunnel of the secondary lining of the tunnel, determines the positioning elevation of the trolley, and guides the site trolley to be in place according to the designed position;
s200, walking, positioning and reinforcing the secondary lining trolley, walking the secondary lining trolley to a design position of a secondary lining profile of the tunnel according to the field measurement condition, positioning under the guidance of a measuring person, and reinforcing the secondary lining trolley and setting and reinforcing a head die of the secondary lining of the tunnel after the positioning is finished;
s300, longitudinally and continuously pouring a trolley into position; a longitudinal pouring concrete gun of the pouring trolley is longitudinally conveyed to the bottom of the end of the two lining ends by a pouring travelling trolley, and a visual monitoring system and a concrete pressure detection sensor are arranged on the longitudinal pouring concrete gun;
s400, pouring concrete of the two lining side walls; adopting a two-lining trolley to pour layer by layer window by window, feeding materials layer by layer window by window, symmetrically pouring partial concrete of two lining side walls, and pouring layer by layer and vibrating and compacting layer by layer;
s500-after the concrete of the second lining side wall part is poured and vibrated layer by layer window by window, replacing a concrete pump pipe interface to a longitudinal continuous pouring trolley for longitudinal pouring;
s600, starting a concrete delivery pump, starting longitudinal continuous pouring of the second liner vault concrete, wherein in the pouring process, a longitudinal pouring concrete gun moves back and forth every 5 minutes to ensure that the longitudinal pouring concrete gun can freely move in the concrete, and the longitudinal pouring concrete gun is always buried in the concrete in the pouring process to ensure that the interior of the pouring concrete is kept in pressure and poured;
s700-pouring second-lining vault concrete longitudinally and continuously in a retreating mode; when concrete is poured to the high position of the arch top of the secondary lining of the tunnel, the pressure of a concrete backing flooding wrapping pouring gun is detected through a concrete pressure detection sensor, and the longitudinal pouring concrete gun backs according to the step pitch of 0.6 meter; in the pouring process, the attached vibrators of the two lining trolleys are started one by one, and the two lining concrete is layered and vibrated in different areas to be compacted until the two lining concrete is fully poured;
s800, exiting the station to clean the pipeline, and finishing the filling; cleaning a longitudinal pouring concrete gun pipeline by using a piston, erecting a longitudinal continuous pouring trolley to exit a station, and finishing longitudinal continuous pouring of the concrete with the second lining vault;
S900-RPC belt mold pressing slurry; and after the secondary lining concrete is poured for 2 hours, hole-by-hole tape mold grouting is carried out on the vault of the secondary lining by using RPC pipe tape mold grouting until the grouting hole and the exhaust hole are plugged after the slurry overflows from the end of the secondary lining, the grouting system is dismantled, and grouting is finished.
2. The tunnel secondary lining vault concrete longitudinal continuous pouring construction method according to claim 1, characterized in that: in the step S300, the tip of the longitudinal concrete pouring gun is 60cm away from the bottom of the tip of the second liner.
3. The tunnel secondary lining vault concrete longitudinal continuous pouring construction method according to claim 2, characterized in that: in the step S500, during the longitudinal pouring process, the performance of the on-site second-lining vault concrete is detected, and the slump of the concrete entering the mold is required to be controlled to 170 mm-190 mm.
CN201910759507.8A 2019-08-16 2019-08-16 Tunnel secondary lining vault concrete longitudinal continuous pouring construction method Active CN110700854B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910759507.8A CN110700854B (en) 2019-08-16 2019-08-16 Tunnel secondary lining vault concrete longitudinal continuous pouring construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910759507.8A CN110700854B (en) 2019-08-16 2019-08-16 Tunnel secondary lining vault concrete longitudinal continuous pouring construction method

Publications (2)

Publication Number Publication Date
CN110700854A CN110700854A (en) 2020-01-17
CN110700854B true CN110700854B (en) 2022-02-15

Family

ID=69193371

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910759507.8A Active CN110700854B (en) 2019-08-16 2019-08-16 Tunnel secondary lining vault concrete longitudinal continuous pouring construction method

Country Status (1)

Country Link
CN (1) CN110700854B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939463B (en) * 2019-11-21 2023-07-18 中铁隧道局集团有限公司 Movable full-section integral steel mould lining trolley and application thereof in pumping pouring of secondary lining concrete
CN112983481A (en) * 2021-03-05 2021-06-18 成都锐龙机械制造有限公司 Tunnel secondary lining trolley system and concrete continuous pouring method
CN112879037A (en) * 2021-04-22 2021-06-01 黄河交通学院 Safe construction method for mine tunnel
CN113847065A (en) * 2021-10-09 2021-12-28 中铁十九局集团第六工程有限公司 Longitudinal pouring construction method for secondary lining vault

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11125012A (en) * 1997-10-22 1999-05-11 Shimizu Corp Concrete placing device
KR101415106B1 (en) * 2013-02-05 2014-07-04 조향래 The back feel grouting apparatus for upper part of tunnel
CN204645658U (en) * 2015-04-08 2015-09-16 深圳市富斯遥控模型技术有限公司 A kind of automatic cement irrigation system controlled based on Remote
CN105822325A (en) * 2016-04-18 2016-08-03 浙江省交通工程建设集团有限公司 Tunnel secondary lining arch crown concrete filling machine and construction method thereof
CN106014454A (en) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 Grouting device and grouting technique for tunnel lining vault with mould
CN108071406A (en) * 2018-02-08 2018-05-25 中铁五局集团有限公司 A kind of tunnel of follow shot is without empty lining trolley
CN207715189U (en) * 2017-11-30 2018-08-10 中铁十一局集团第四工程有限公司 A kind of high ferro tunnel double-lining concrete is rushed to summit plumpness digital monitoring alarm system
CN108442938A (en) * 2018-02-01 2018-08-24 中铁十二局集团有限公司 A kind of two lining band of full hydraulic flat car is molded into pulp grinder structure and its grouting process
CN108457671A (en) * 2018-02-01 2018-08-28 中铁十二局集团有限公司 One kind two serves as a contrast sliding slot and enters mould constructing device by window
CN207920633U (en) * 2018-03-06 2018-09-28 中交第二公路工程局有限公司 Tunnel-liner vault band is molded into sizing device
CN208473883U (en) * 2018-06-13 2019-02-05 北京鸿锐嘉科技发展有限公司 Monitoring system is perfused in tunnel vault lining concrete
CN208831013U (en) * 2018-07-20 2019-05-07 北京鸿锐嘉科技发展有限公司 Intelligent slip casting management system
CN109826649A (en) * 2019-01-11 2019-05-31 中铁十一局集团第四工程有限公司 Tunnel double-lining concrete casting system construction method
CN209083293U (en) * 2018-11-16 2019-07-09 中铁隧道集团一处有限公司 Endoscopic bomb shelter monitoring device for tunnel-liner vault

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4459637B2 (en) * 2004-01-29 2010-04-28 前田建設工業株式会社 Vibrator system for concrete compaction
JP4557941B2 (en) * 2006-08-31 2010-10-06 株式会社奥村組 Tunnel lining concrete placement method and placement structure
JP4931777B2 (en) * 2007-11-21 2012-05-16 株式会社奥村組 Tunnel lining concrete placement management method
JP6074219B2 (en) * 2012-10-17 2017-02-01 鹿島建設株式会社 Tunnel crown lining concrete placement system and method
JP6937162B2 (en) * 2017-05-25 2021-09-22 大成建設株式会社 Concrete placing method

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11125012A (en) * 1997-10-22 1999-05-11 Shimizu Corp Concrete placing device
KR101415106B1 (en) * 2013-02-05 2014-07-04 조향래 The back feel grouting apparatus for upper part of tunnel
CN204645658U (en) * 2015-04-08 2015-09-16 深圳市富斯遥控模型技术有限公司 A kind of automatic cement irrigation system controlled based on Remote
CN105822325A (en) * 2016-04-18 2016-08-03 浙江省交通工程建设集团有限公司 Tunnel secondary lining arch crown concrete filling machine and construction method thereof
CN106014454A (en) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 Grouting device and grouting technique for tunnel lining vault with mould
CN207715189U (en) * 2017-11-30 2018-08-10 中铁十一局集团第四工程有限公司 A kind of high ferro tunnel double-lining concrete is rushed to summit plumpness digital monitoring alarm system
CN108442938A (en) * 2018-02-01 2018-08-24 中铁十二局集团有限公司 A kind of two lining band of full hydraulic flat car is molded into pulp grinder structure and its grouting process
CN108457671A (en) * 2018-02-01 2018-08-28 中铁十二局集团有限公司 One kind two serves as a contrast sliding slot and enters mould constructing device by window
CN108071406A (en) * 2018-02-08 2018-05-25 中铁五局集团有限公司 A kind of tunnel of follow shot is without empty lining trolley
CN207920633U (en) * 2018-03-06 2018-09-28 中交第二公路工程局有限公司 Tunnel-liner vault band is molded into sizing device
CN208473883U (en) * 2018-06-13 2019-02-05 北京鸿锐嘉科技发展有限公司 Monitoring system is perfused in tunnel vault lining concrete
CN208831013U (en) * 2018-07-20 2019-05-07 北京鸿锐嘉科技发展有限公司 Intelligent slip casting management system
CN209083293U (en) * 2018-11-16 2019-07-09 中铁隧道集团一处有限公司 Endoscopic bomb shelter monitoring device for tunnel-liner vault
CN109826649A (en) * 2019-01-11 2019-05-31 中铁十一局集团第四工程有限公司 Tunnel double-lining concrete casting system construction method

Also Published As

Publication number Publication date
CN110700854A (en) 2020-01-17

Similar Documents

Publication Publication Date Title
CN110700854B (en) Tunnel secondary lining vault concrete longitudinal continuous pouring construction method
CN113802424B (en) Sedimentation bag type grouting lifting repair method for ballastless track of high-speed railway
CN105332710B (en) Suitable for the overlapping tunnel construction method up and down of small interval long range under Unfavorable geology
CN102345461B (en) Subsequent project and shield driving parallel construction method for long-distance railway tunnel
CN206722852U (en) A kind of mobile inverted arch trestle of growing up for carrying inverted arch template
CN110374630B (en) Construction method for concrete vibration of tunnel vault
CN104278841B (en) The method of casting concrete in steel pipe column
CN106979021B (en) Large-section loess tunnel excavates and preliminary bracing quick closure cyclization method
CN108716189A (en) Large span T-steel structure beam sections for joining island bridge install closure method
CN110439286A (en) A kind of liner is put more energy into joint steel pipe concrete column drag reduction jack-up construction method of weakening
CN106337688A (en) Sleeved inner liner reinforcing structure for electrical operation of cable tunnel and construction method thereof
CN115369778A (en) Construction method of steel cross beam rotating body structure
CN103437772A (en) Pipe-jacking construction method of underground passage and tunnel structure
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN110485218A (en) It is a kind of to help wide construction method for railway bed
CN210977514U (en) Tunnel secondary lining anti-hollow longitudinal belt mold grouting pipe drawing device
CN112609584A (en) Prefabricated small box girder installation construction method for intelligent express way
CN110468744B (en) Channel bridge reinforcement construction method
CN114855831B (en) Equipment for laying plastic geotextile and construction method thereof
CN111271078A (en) Construction method for assembling sectional longitudinal translation in prefabricated tunnel lining structure tunnel
CN114876515A (en) Two lining platform trucks in tunnel are pour fast
CN115256615A (en) Intelligent shower maintenance standard construction system for prefabricated box girder of expressway
CN111577345B (en) Construction method and construction system for multilayer anti-seepage tunnel bottom structure
CN114961336A (en) Protective demolition construction method for basement pile foundation next to existing subway line
CN203320810U (en) Steel tube concrete structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant