CN110593590A - In-situ protection method for existing high-voltage line pole in deep foundation pit excavation area - Google Patents

In-situ protection method for existing high-voltage line pole in deep foundation pit excavation area Download PDF

Info

Publication number
CN110593590A
CN110593590A CN201910754817.0A CN201910754817A CN110593590A CN 110593590 A CN110593590 A CN 110593590A CN 201910754817 A CN201910754817 A CN 201910754817A CN 110593590 A CN110593590 A CN 110593590A
Authority
CN
China
Prior art keywords
voltage line
steel bar
foundation pit
deep foundation
bar bundle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910754817.0A
Other languages
Chinese (zh)
Other versions
CN110593590B (en
Inventor
郭文峰
张玉波
隗磊
闻艳萍
李长贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd, PowerChina 11th Bureau Engineering Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN201910754817.0A priority Critical patent/CN110593590B/en
Publication of CN110593590A publication Critical patent/CN110593590A/en
Application granted granted Critical
Publication of CN110593590B publication Critical patent/CN110593590B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/30Safety or protective measures preventing damage to building parts or finishing work during construction against mechanical damage or dirt, e.g. guard covers of stairs

Abstract

The invention belongs to the technical field of municipal engineering, and particularly relates to an in-situ reinforcement and protection method for an existing high-voltage line pole in a deep foundation pit excavation area, which comprises the following steps: step 1, pile positions are measured; step 2, drilling a fixing hole; step 3, manufacturing a steel bar bundle; step 4, mounting the reinforcing steel bar bundles; and step 5, grouting: step 5.1, mixing cement paste: the water-cement ratio of the cement paste is 0.8: 1-1: 1, and the cement paste is mixed by a cement paste mixer; step 5.2, adopting a phi 2.5 polyethylene plastic pipe as a grouting pipe, penetrating the grouting pipe to a position 50-80 cm away from the bottom of the fixing hole along the middle part of the steel bar bundle, firmly fixing the grouting pipe on the steel bar bundle by using an iron wire, continuously pouring grout from bottom to top until the grouting pipe is full, pulling out the grouting pipe, and finishing the anchor bar pile; and 6, integrally welding, namely, integrally welding the exposed part of the anchor bar bundle into a whole in an annular shape. The protection method can ensure the normal operation of the existing high-voltage line pole and the electric shock prevention safety of constructors in the construction period, and enables the high-voltage line pole to be firmer.

Description

In-situ protection method for existing high-voltage line pole in deep foundation pit excavation area
Technical Field
The invention belongs to the technical field of municipal engineering, and relates to an in-situ reinforcement and protection method for an existing high-voltage line pole in a deep foundation pit excavation area.
Background
The protection of high-voltage line poles around the deep foundation pit is mostly solved by adopting a changing mode, if the changing mode is difficult, the modes of steel sheet piles, jet grouting piles and the like are mostly adopted to carry out enclosure reinforcement on the excavation edge of the foundation pit so as to ensure the safety of the line poles around the foundation pit. In order to ensure the safety of enclosure construction, the construction of large equipment such as steel sheet piles, jet grouting piles and the like has special requirements on the level of a high-voltage line, clearance safety distance and the like, and the construction has more limited conditions and great potential safety hazard.
The existing high-voltage line pole in the deep foundation pit excavation area needs to be solved by adopting a relocation method, but the line relocation construction of the power department often has the characteristics of complex procedures, low efficiency, long implementation period and the like, and the requirements on the construction progress of the deep foundation pit are difficult to meet. Before the high-voltage line pole in the deep foundation pit excavation area scope has not been changed and is accomplished, how to guarantee not influencing deep foundation pit construction progress in, can also ensure existing high-voltage line's normal operating and constructor's protection against electric shock safety, is the technical problem that the skilled person needs a urgent need to solve.
The Chinese patent application numbers are: the patent of CN201510430135.6 discloses a method for reinforcing and protecting a foundation of a utility pole adjacent to a deep foundation pit, which comprises the following steps: s1: driving a high-pressure jet grouting pile into one side of the telegraph pole close to the foundation pit along the direction of the underground wall; s2: inserting a plurality of channel steels into the high-pressure jet grouting pile; s3: a plurality of channel steel is driven into the two sides of the telegraph pole in a direction perpendicular to the underground wall, and the channel steel with three sides forms a surround on three sides of the telegraph pole; s4: and arranging a steel purlin along the outer side of the channel steel, and welding the steel purlin and the steel channel into a whole. The method for foundation reinforcement of the telegraph pole by the high-pressure jet grouting pile and the channel steel ensures the safety of the telegraph pole and constructors in the excavation process of the foundation pit, and does not need a long process for transferring the telegraph pole by an electric power department, thereby accelerating the construction progress, saving the cost, having high flexibility, being suitable for various construction conditions, but not being directly suitable for protection of the existing high-pressure line pole in the excavation area of the deep foundation pit.
Disclosure of Invention
The invention aims to provide an in-situ reinforcement and protection method for an existing high-voltage line pole in a deep foundation pit excavation area, so that the normal operation of the existing high-voltage line pole and the electric shock prevention safety of construction personnel in a construction period are ensured, and the high-voltage line pole is firmer.
The in-situ reinforcement and protection method for the existing high-voltage line pole in the deep foundation pit excavation area comprises the following steps:
step 1, pile position determination: paying off the line pole to be reinforced with the radius of 1.5m as the circle center, determining the range of the enclosure anchor bar pile, and marking the pile positions one by one on the circular line according to the distance of 30 cm;
step 2, drilling a fixing hole: digging soil at the pile position marked in the step 1 by using a Luoyang shovel to form a fixed hole, wherein the depth of the fixed hole is increased by 5m on the basis of the depth of the foundation pit to be excavated, and the aperture of the fixed hole is 15 cm;
step 3, manufacturing the steel bar bundles: cutting a phi 25 steel bar into supporting ribs with the length of 4.5m at each section, cutting a phi 16 steel bar into reinforcing ribs with the length of 0.1m at each section, arranging the supporting ribs in a delta shape with 3 supporting ribs, spacing every two reinforcing ribs by 0.1m, welding and fixing the reinforcing ribs by 3 reinforcing ribs, and welding the reinforcing ribs at the spacing distance of 1.5m to form a whole; the positioning ribs are made into a shape like a Chinese character ji by adopting phi 10 steel bars with the length of 40cm, are welded on the outer sides of the supporting ribs, are arranged in groups of every 2m, and each group comprises 3 positioning ribs, so that the anchoring ribs are not directly contacted with the hole wall after being bound into the holes, and a protective layer is reserved;
step 4, mounting the reinforcing steel bar: hoisting the single-section steel bar bundle to the position above the fixing hole, vertically hoisting the steel bar bundle to the position in the fixing hole, lowering the steel bar bundle at a constant speed, and keeping the top of the steel bar bundle at 0.5m outside the fixing hole;
hoisting the next section of the reinforcing steel bar bundle to the position above the fixing hole, vertically arranging the reinforcing steel bar bundle, welding and fixing the reinforcing steel bar bundle and the previous reinforcing steel bar bundle, and lowering the reinforcing steel bar bundle at a constant speed, wherein 0.5m is reserved outside the fixing hole;
repeating the operation, mounting the reinforcing steel bar bundles to the bottoms of the fixing holes, and mounting the reinforcing steel bar bundles in each fixing hole;
and step 5, grouting:
step 5.1, mixing cement paste: the water-cement ratio of the cement paste is 0.8: 1-1: 1, and the cement paste is mixed by a cement paste mixer;
step 5.2, adopting a phi 2.5 polyethylene plastic pipe as a grouting pipe, penetrating the grouting pipe to a position 50-80 cm away from the bottom of the fixing hole along the middle part of the steel bar bundle, firmly fixing the grouting pipe on the steel bar bundle by using an iron wire, continuously pouring grout from bottom to top until the grouting pipe is full, pulling out the grouting pipe, and finishing the anchor bar pile;
and 6, integrally welding, wherein the exposed part of the anchor bar bundle is integrally annular, phi 16 steel bars are adopted to surround and weld one by one along the periphery of the exposed anchor bar bundle, the phi 16 steel bars are cut out to manufacture tie bars, and opposite anchor bar bundles are welded and fixed in a split-pulling manner to form an integral body.
Further, all the steps are organized and implemented within a safe distance range under the high-voltage line, and the specific construction safe distance is as follows: the safe distance of the high-voltage line below 1kV is 4 meters; the safe distance of the 1-10kV high-voltage line is 6 meters; the safe distance of the 35-110kV high-voltage line is 8 meters; the safe distance of the 154-220kV high-voltage line is 10 meters; the safe distance of the 350-500kV high-voltage line is 15 meters.
Further, in step 3, the positioning steel bars adopt a semicircular structure.
Further, in step 5.2, the grout tube is held 0.5m below the grout surface.
Further, in step 6, the high-voltage wire rods and the peripheral tendons are welded and fixed one by using phi 16 steel bars.
Further, step 6 includes the following steps:
a wire rod steel sleeve is fixedly arranged on the high-voltage wire rod;
and C-shaped steel is welded on the wire rod steel sleeve and the anchor bar bundle which is annular as a whole.
Further, step 6 includes the following steps:
a hoop is arranged at 2/3 of the height of the high-voltage line pole body, 3-5 pull rings are welded on the hoop, and the pull rings are fixed on the outer wall of the hoop in a central symmetry manner;
selecting an anchoring point on the ground in the direction opposite to the pull ring, and mounting a ground anchor on the anchoring point, wherein the anchoring point is outside the excavation area of the deep foundation pit, and the height of the anchoring point is lower than that of the hoop;
and connecting the pull ring and the ground anchor in the direction opposite to the pull ring by using a steel wire rope, and tensioning the steel wire rope.
Further, the step 1 also comprises the step of measuring the verticality of the high-voltage line rod, if the verticality is larger than 10/300mm, the high-voltage line rod is firstly aligned until the verticality is not larger than 10/300mm, and then the construction of drilling a fixing hole is carried out.
Further, step 1 also includes the following steps:
rolling a circular ring area which takes a wire pole to be reinforced as a circle center and has a radius of 60 cm;
drilling a cast-in-place pile hole in the annular area, wherein the aperture of the cast-in-place pile hole is 6-8cm, and the depth of the cast-in-place pile hole is 100 cm;
pouring concrete into the cast-in-place pile hole, wherein the concrete comprises 1 part of water, 1 part of cement and 1 part of sand, and the particle size of the sand is 1.0-2.0 cm;
and when the concrete in the cast-in-place pile hole is not completely solidified, pouring concrete into the circular ring area to enable the poured concrete to surround the periphery of the wire pole to be reinforced, and building the poured concrete into an inverted funnel shape till the poured concrete is solidified.
The invention has the beneficial effects that:
1. according to the in-situ reinforcement and protection method for the existing high-voltage wire rods in the deep foundation pit excavation area, the steel bar bundles are arranged around the wire rods to be reinforced and are subjected to grouting reinforcement, so that the operation safety of a power line in the bridge foundation construction and the deep foundation pit excavation construction process is ensured.
2. The in-situ reinforcement and protection method for the existing high-voltage line pole in the deep foundation pit excavation area can effectively provide in-situ protection for the existing high-voltage line pole in the deep foundation pit excavation area, and is simple in process, economical, applicable, safe and reliable.
3. According to the in-situ reinforcement and protection method for the existing high-voltage line pole in the deep foundation pit excavation area, the high-voltage line pole is firmer through the construction steps of drilling a cast-in-place pile hole in the circular ring area, grouting and pouring concrete into the circular ring area.
Drawings
Fig. 1 is a schematic structural diagram of a reinforcement bundle in the method for in-situ reinforcement and protection of an existing high-voltage line pole in an excavation area of a deep foundation pit;
fig. 2 is a sectional view of a reinforcement bundle in the method for in-situ reinforcement and protection of an existing high-voltage line pole in an excavation area of a deep foundation pit.
In the figure: 1-reinforcing bar bundle, 11-supporting bar, 12-reinforcing bar and 13-positioning bar.
Detailed Description
In order that the above objects, features and advantages of the present invention can be more clearly understood, the present invention will be described in further detail below with reference to the accompanying drawings and specific embodiments, it being understood that the embodiments and features of the embodiments of the present application can be combined with each other without conflict.
Examples
The in-situ reinforcement and protection method for the existing high-voltage line pole in the deep foundation pit excavation area comprises the following steps:
step 1, pile position determination: paying off the line pole to be reinforced with the radius of 1.5m as the circle center, determining the range of the enclosure anchor bar pile, and marking the pile positions one by one on the circular line according to the distance of 30 cm;
step 2, drilling a fixing hole: digging soil at the pile position marked in the step 1 by using a Luoyang shovel to form a fixed hole, wherein the depth of the fixed hole is increased by 5m on the basis of the depth of the foundation pit to be excavated, and the aperture of the fixed hole is 15 cm;
step 3, manufacturing the reinforcing steel bar bundle 1: as shown in fig. 1 and 2, a phi 25 steel bar is cut into a support rib 11 with a length of 4.5m per section, a phi 16 steel bar is cut into a reinforcing rib 12 with a length of 0.1m per section, the support ribs 11 are arranged in a delta shape with 3 support ribs, every two reinforcing ribs are spaced by 0.1m and welded and fixed by 3 reinforcing ribs 12, and the welding spacing distance of the reinforcing ribs 12 is 1.5m, so that a whole is formed; the positioning ribs 13 are made into a shape like a Chinese character ji by adopting phi 10 steel bars 40cm long, are welded on the outer sides of the support ribs 11, are arranged in groups of every 2m, are 3 in each group, ensure that the anchor ribs are not directly contacted with the hole wall after being tied into the holes, and leave a protective layer;
step 4, installing the reinforcing steel bar bundle 1: hoisting a single-section steel bar bundle 1 above the fixing hole, vertically hoisting the steel bar bundle 1 into the fixing hole, lowering the steel bar bundle at a constant speed, and keeping 0.5m of the top of the steel bar bundle 1 outside the fixing hole;
hoisting the next section of the reinforcing steel bar bundle 1 to the position above the fixing hole, vertically arranging, welding and fixing the next section of the reinforcing steel bar bundle 1 with the previous reinforcing steel bar bundle 1, and lowering the next section of the reinforcing steel bar bundle at a constant speed, wherein 0.5m is reserved outside the fixing hole;
repeating the above operation, installing the tendons 1 to the bottoms of the fixing holes, and installing the tendons 1 in each fixing hole;
and step 5, grouting:
step 5.1, mixing cement paste: the water-cement ratio of the cement paste is 0.8: 1-1: 1, and the cement paste is mixed by a cement paste mixer;
step 5.2, adopting a phi 2.5 polyethylene plastic pipe as a grouting pipe, penetrating the middle of the steel bar bundle 1 to a position 50-80 cm away from the bottom of the fixing hole, firmly fixing the steel bar bundle 1 on the steel bar bundle 1 by using an iron wire, continuously pouring grout from bottom to top until the steel bar bundle is filled, and pulling out the grouting pipe to finish the anchor bar pile;
and 6, integrally welding, wherein the exposed part of the anchor bar bundle is integrally annular, phi 16 steel bars are adopted to surround and weld one by one along the periphery of the exposed anchor bar bundle, the phi 16 steel bars are cut out to manufacture tie bars, and opposite anchor bar bundles are welded and fixed in a split-pulling manner to form an integral body.
All steps of the method are organized and implemented within a safe distance range under the high-voltage line, and the specific construction safe distance is as follows: the safe distance of the high-voltage line below 1kV is 4 meters; the safety distance of the 1-10kV high-voltage line is 6 meters; the safe distance of the 35-110kV high-voltage line is 8 meters; the safe distance of the 154-220kV high-voltage line is 10 meters; the safe distance of the 350-500kV high-voltage line is 15 meters.
In step 3 of this embodiment, the positioning bars are in a semicircular structure. As a modification of step 5.1 in this embodiment, the cement slurry further comprises medium sand of equal mass with ash.
In step 5.2 of this example, the grout tube was held 0.5m below the grout surface.
In step 6 of this embodiment, the high-voltage wire rods and the peripheral tendons are welded and fixed one by using the Φ 16 steel bars.
Step 6 of this embodiment further includes the following steps:
a wire rod steel sleeve is fixedly arranged on the high-voltage wire rod;
and C-shaped steel is welded on the wire rod steel sleeve and the anchor bar bundle which is annular as a whole.
The wire rod steel sleeve is made of a steel plate with the thickness of 2cm through rolling into a C shape, the two C-shaped steel plates are welded to be sleeved on the high-voltage wire rod, and the installation height of the wire rod steel sleeve is higher than the height of the anchor tendon.
Step 6 of this embodiment further includes the following steps:
a hoop is arranged at 2/3 of the height of the high-voltage line pole body, 3-5 pull rings are welded on the hoop, and the pull rings are fixed on the outer wall of the hoop in a central symmetry manner;
selecting an anchoring point on the ground in the direction opposite to the pull ring, and mounting a ground anchor on the anchoring point, wherein the anchoring point is outside the excavation area of the deep foundation pit, and the height of the anchoring point is lower than that of the hoop;
and connecting the pull ring and the ground anchor in the direction opposite to the pull ring by using a steel wire rope, and tensioning the steel wire rope.
In this embodiment, preferably 4 tabs are provided, and the angle between each two adjacent tabs is 90 ° where construction site permits.
In step 1 of this embodiment, the method further includes the step of measuring the perpendicularity of the high-voltage line rod, and if the perpendicularity is greater than 10/300mm, the high-voltage line rod is firstly aligned until the perpendicularity is not greater than 10/300mm, and then the construction of drilling the fixing hole is performed.
Step 1 of this embodiment further includes the following steps:
rolling a circular ring area with the radius of 60cm and taking a wire rod to be reinforced as a circle center, wherein the perpendicularity of the wire rod to be reinforced needs to be ensured in the rolling process;
drilling bored concrete pile holes in the annular area, wherein the diameter of each bored concrete pile hole is 6-8cm, the depth of each bored concrete pile hole is 100cm, the bored concrete pile holes are arrayed in a central array mode by taking the high-voltage line pole as the center, and the bored concrete pile holes are preferably 6 holes;
pouring concrete into the cast-in-place pile hole, wherein the concrete comprises 1 part of water, 1 part of cement and 1 part of sand, and the particle size of the sand is 1.0-2.0 cm;
and when the concrete in the cast-in-place pile hole is not completely solidified, pouring concrete into the circular ring area to enable the poured concrete to surround the periphery of the wire pole to be reinforced, and building the poured concrete into an inverted funnel shape till the poured concrete is solidified.
The present invention is not limited to the above-described embodiments, which are described in the specification and illustrated only for illustrating the principle of the present invention, but various changes and modifications may be made within the scope of the present invention as claimed without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims.

Claims (9)

1. The in-situ reinforcement and protection method for the existing high-voltage line pole in the deep foundation pit excavation area is characterized by comprising the following steps of:
step 1, pile position determination: paying off the line pole to be reinforced with the radius of 1.5m as the circle center, determining the range of the enclosure anchor bar pile, and marking the pile positions one by one on the circular line according to the distance of 30 cm;
step 2, drilling a fixing hole: digging soil at the pile position marked in the step 1 by using a Luoyang shovel to form a fixed hole, wherein the depth of the fixed hole is increased by 5m on the basis of the depth of the foundation pit to be excavated, and the aperture of the fixed hole is 15 cm;
step 3, manufacturing the steel bar bundles: cutting a phi 25 steel bar into supporting ribs with the length of 4.5m at each section, cutting a phi 16 steel bar into reinforcing ribs with the length of 0.1m at each section, arranging the supporting ribs in a delta shape with 3 supporting ribs, spacing every two reinforcing ribs by 0.1m, welding and fixing the reinforcing ribs by 3 reinforcing ribs, and welding the reinforcing ribs at the spacing distance of 1.5m to form a whole; the positioning ribs are made into a shape like a Chinese character ji by adopting phi 10 steel bars with the length of 40cm, are welded on the outer sides of the supporting ribs, are arranged in groups of every 2m, and each group comprises 3 positioning ribs, so that the anchoring ribs are not directly contacted with the hole wall after being bound into the holes, and a protective layer is reserved;
step 4, mounting the reinforcing steel bar: hoisting the single-section steel bar bundle to the position above the fixing hole, vertically hoisting the steel bar bundle to the position in the fixing hole, lowering the steel bar bundle at a constant speed, and keeping the top of the steel bar bundle at 0.5m outside the fixing hole;
hoisting the next section of the reinforcing steel bar bundle to the position above the fixing hole, vertically arranging the reinforcing steel bar bundle, welding and fixing the reinforcing steel bar bundle and the previous reinforcing steel bar bundle, and lowering the reinforcing steel bar bundle at a constant speed, wherein 0.5m is reserved outside the fixing hole;
repeating the operation, mounting the reinforcing steel bar bundles to the bottoms of the fixing holes, and mounting the reinforcing steel bar bundles in each fixing hole;
and step 5, grouting:
step 5.1, mixing cement paste: the water-cement ratio of the cement paste is 0.8: 1-1: 1, and the cement paste is mixed by a cement paste mixer;
step 5.2, adopting a phi 2.5 polyethylene plastic pipe as a grouting pipe, penetrating the grouting pipe to a position 50-80 cm away from the bottom of the fixing hole along the middle part of the steel bar bundle, firmly fixing the grouting pipe on the steel bar bundle by using an iron wire, continuously pouring grout from bottom to top until the grouting pipe is full, pulling out the grouting pipe, and finishing the anchor bar pile;
and 6, integrally welding, wherein the exposed part of the anchor bar bundle is integrally annular, phi 16 steel bars are adopted to surround and weld one by one along the periphery of the exposed anchor bar bundle, the phi 16 steel bars are cut out to manufacture tie bars, and opposite anchor bar bundles are welded and fixed in a split-pulling manner to form an integral body.
2. The in-situ reinforcement and protection method for the existing high-voltage line pole in the deep foundation pit excavation area according to claim 1, wherein all the steps are organized and implemented within a safety distance range under the high-voltage line, and the specific construction safety distance is as follows: the safe distance of the high-voltage line below 1kV is 4 meters; the safe distance of the 1-10kV high-voltage line is 6 meters; the safe distance of the 35-110kV high-voltage line is 8 meters; the safe distance of the 154-220kV high-voltage line is 10 meters; the safe distance of the 350-500kV high-voltage line is 15 meters.
3. The in-situ reinforcement and protection method for the existing high-voltage line pole in the excavation area of the deep foundation pit according to claim 1, wherein in the step 3, the positioning steel bars are of a semicircular structure.
4. The method for in-situ reinforcement and protection of the existing high-voltage line pole in the excavation area of the deep foundation pit according to claim 1, wherein in the step 5.2, the grouting pipe is kept 0.5m below the surface of cement paste.
5. The in-situ reinforcement and protection method for the existing high-voltage wire rods in the excavation area of the deep foundation pit according to claim 1, wherein in the step 6, the high-voltage wire rods and the peripheral reinforcing steel bundles are welded and fixed one by using phi 16 reinforcing steel bars.
6. The in-situ reinforcement and protection method for the existing high-voltage line pole in the excavation area of the deep foundation pit according to claim 1, wherein the step 6 further comprises the following steps:
a wire rod steel sleeve is fixedly arranged on the high-voltage wire rod;
and C-shaped steel is welded on the wire rod steel sleeve and the anchor bar bundle which is annular as a whole.
7. The in-situ reinforcement and protection method for the existing high-voltage line pole in the excavation area of the deep foundation pit according to claim 1, wherein the step 6 further comprises the following steps:
a hoop is arranged at 2/3 of the height of the high-voltage line pole body, 3-5 pull rings are welded on the hoop, and the pull rings are fixed on the outer wall of the hoop in a central symmetry manner;
selecting an anchoring point on the ground in the direction opposite to the pull ring, and mounting a ground anchor on the anchoring point, wherein the anchoring point is outside the excavation area of the deep foundation pit, and the height of the anchoring point is lower than that of the hoop;
and connecting the pull ring and the ground anchor in the direction opposite to the pull ring by using a steel wire rope, and tensioning the steel wire rope.
8. The in-situ reinforcement and protection method for the existing high-voltage wire rods in the deep foundation pit excavation area as claimed in claim 1, wherein the step 1 further comprises the step of measuring the verticality of the high-voltage wire rods, if the verticality is greater than 10/300mm, the high-voltage wire rods are aligned to the verticality which is not greater than 10/300mm, and then the construction of drilling fixing holes is carried out.
9. The in-situ reinforcement and protection method for the existing high-voltage line pole in the excavation area of the deep foundation pit according to claim 1, wherein the step 1 further comprises the following steps:
rolling a circular ring area which takes a wire pole to be reinforced as a circle center and has a radius of 60 cm;
drilling a cast-in-place pile hole in the annular area, wherein the aperture of the cast-in-place pile hole is 6-8cm, and the depth of the cast-in-place pile hole is 100 cm;
pouring concrete into the cast-in-place pile hole, wherein the concrete comprises 1 part of water, 1 part of cement and 1 part of sand, and the particle size of the sand is 1.0-2.0 cm;
and when the concrete in the cast-in-place pile hole is not completely solidified, pouring concrete into the circular ring area to enable the poured concrete to surround the periphery of the wire pole to be reinforced, and building the poured concrete into an inverted funnel shape till the poured concrete is solidified.
CN201910754817.0A 2019-08-15 2019-08-15 In-situ protection method for existing high-voltage line pole in deep foundation pit excavation area Active CN110593590B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910754817.0A CN110593590B (en) 2019-08-15 2019-08-15 In-situ protection method for existing high-voltage line pole in deep foundation pit excavation area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910754817.0A CN110593590B (en) 2019-08-15 2019-08-15 In-situ protection method for existing high-voltage line pole in deep foundation pit excavation area

Publications (2)

Publication Number Publication Date
CN110593590A true CN110593590A (en) 2019-12-20
CN110593590B CN110593590B (en) 2021-05-18

Family

ID=68854448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910754817.0A Active CN110593590B (en) 2019-08-15 2019-08-15 In-situ protection method for existing high-voltage line pole in deep foundation pit excavation area

Country Status (1)

Country Link
CN (1) CN110593590B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195076A (en) * 2013-03-28 2013-07-10 中国建筑第八工程局有限公司 Method for constructing silt deep foundation pit tower crane foundation
CN105064428A (en) * 2015-07-21 2015-11-18 上海建工七建集团有限公司 Foundation reinforcement and protection method for telegraph pole near deep foundation pit
CN105715094A (en) * 2016-02-16 2016-06-29 国家电网公司 Protecting device for high-voltage line pole

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195076A (en) * 2013-03-28 2013-07-10 中国建筑第八工程局有限公司 Method for constructing silt deep foundation pit tower crane foundation
CN105064428A (en) * 2015-07-21 2015-11-18 上海建工七建集团有限公司 Foundation reinforcement and protection method for telegraph pole near deep foundation pit
CN105715094A (en) * 2016-02-16 2016-06-29 国家电网公司 Protecting device for high-voltage line pole

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张琴: "微型钢管桩在临近基坑的基础加固中的应用 ", 《科技经济市场》 *
王立伟: "10kV输电杆基础加固工程的设计与施工 ", 《建筑技术》 *

Also Published As

Publication number Publication date
CN110593590B (en) 2021-05-18

Similar Documents

Publication Publication Date Title
CN106320346B (en) Campshed adds anchor cable grouting behind shaft or drift lining deep foundation pit supporting construction method
CN102031784B (en) Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN102635120A (en) Supportless construction structure and supportless construction method for round deep base pit
CN103195076A (en) Method for constructing silt deep foundation pit tower crane foundation
CN203222809U (en) Pre-stressed concrete pipe pile foundation for pole and tower of power transmission line
CN111119198A (en) A reinforced structure that is used for SMW worker method stake to strut system
CN115012426B (en) Steel pipe pile support and construction method for existing telegraph pole during four-week full excavation
CN108005097B (en) High-steep slope top construction/building anchor raft foundation structure and construction method
CN104074197B (en) The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure
CN104264683A (en) Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building
CN108118689B (en) Prefabricated underground diaphragm wall capable of being partially recycled, lifting appliance and construction method
CN214883687U (en) Foundation pit supporting structure
KR102223856B1 (en) Foundation structure of waste landfill site and construction method thereof
CN110593590B (en) In-situ protection method for existing high-voltage line pole in deep foundation pit excavation area
CN108221955B (en) Prefabricated underground diaphragm wall capable of being recycled integrally, lifting appliance and construction method
CN214940212U (en) Deep foundation pit supporting device
CN111851510B (en) Earth rock foundation pit blasting excavation system and construction method applying same
CN212452655U (en) A reinforced structure that is used for SMW worker method stake to strut system
CN210066763U (en) Foundation pit side wall structure reinforcing and supporting device
CN110106930B (en) Iron tower foundation reinforcement protection method
CN102518130B (en) Manufacturing method of and construction process of reinforcement cage cement plaster pile casing
CN105064357A (en) Embedding type anchoring device and anchoring method for pre-stressed anchor cable
CN206457827U (en) A kind of shaped steel coupling beam structure detachably reclaimed
CN217517600U (en) Deep foundation pit supporting structure for supporting inclined struts in pit
CN214883595U (en) Anti-floating pile structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant