CN110516963A - A kind of whole process engineering consulting project risk management method - Google Patents

A kind of whole process engineering consulting project risk management method Download PDF

Info

Publication number
CN110516963A
CN110516963A CN201910786486.9A CN201910786486A CN110516963A CN 110516963 A CN110516963 A CN 110516963A CN 201910786486 A CN201910786486 A CN 201910786486A CN 110516963 A CN110516963 A CN 110516963A
Authority
CN
China
Prior art keywords
project
stage
responsible person
risk
database
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910786486.9A
Other languages
Chinese (zh)
Inventor
张力力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaxin Project Management Group Co Ltd
Original Assignee
Huaxin Project Management Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaxin Project Management Group Co Ltd filed Critical Huaxin Project Management Group Co Ltd
Priority to CN201910786486.9A priority Critical patent/CN110516963A/en
Publication of CN110516963A publication Critical patent/CN110516963A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/24Querying
    • G06F16/245Query processing
    • G06F16/2455Query execution
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities

Abstract

The present invention relates to a kind of whole process engineering consulting project risk management methods, it is related to big data applied technical field big data applied technical field, solve the problems, such as that staff can ignore risk due to individual's carelessness etc. comprising: S100: building first database;S200: the second database of building, while constructing third database;S300: in real time based on the current time as query object, the initial time of project stage corresponding to current time and next project stage are inquired in first database, risk existing for next project is inquired in the second database simultaneously, and the responsible person of next project stage is inquired in third database;S400: its risk for being responsible for project of the responsible person of next project stage is notified in the preset time of next project stage initial time in advance.The present invention can risk present in prior notice to responsible person's respective item stage project stage, so that project stage responsible person be made preferably to evade project risk.

Description

A kind of whole process engineering consulting project risk management method
Technical field
The present invention relates to big data applied technical fields, more particularly, to a kind of whole process engineering consulting project risk management Method.
Background technique
Whole process engineering consulting is in government's pilot and vectoring phase at present, obtains us there are many problem values and thinks It examines and studies.As is generally known the quality of design, progress and economic rationality are the important contents of design management.All the time, right Working in the design management of designing unit is managed by passing through mark system.
Although in the prior art, about whole process engineering consulting business have that it relies on that program file carried out from upper and Under pyramid way to manage, also contemplated the wind in the presence of whole process engineering consulting course of work in program file Danger, but real work personnel usually can ignore overall process engineering due to personal carelessness etc. in the presence of risk, also Improved space.
Summary of the invention
The object of the present invention is to provide a kind of whole process engineering consulting project risk management method, can prior notice to item Risk present in responsible person's respective item stage in mesh stage, so that project stage responsible person be made preferably to evade project risk.
Foregoing invention purpose of the invention has the technical scheme that
A kind of whole process engineering consulting project risk management method, comprising the following steps:
S100: the first database of building engineering project stage and respective stage institute's match time section, engineering project stage press Be divided into according to logical order: the project planning stage in the prospective design stage, in the bid and purchase stage, Construction stage, is completed and hands over Pay stage, operation and maintenance stage;
S200: the second database of risk existing for project corresponding to building engineering project stage and respective stage, while structure Build engineering project stage and respective stage matched responsible person third database;
S300: it is inquired corresponding to current time in first database based on the current time as query object in real time The initial time of project stage and next project stage, while being looked into the second database using next project as query object Risk existing for next project is ask out, the responsible person of next project stage is inquired in third database;
S400: notify the responsible person of next project stage that it is responsible in the preset time of next project stage initial time in advance The risk of project.
By using above-mentioned technical proposal, notified needed for effectively being obtained by step S100, step S200, step S300 The project risk of the contact method of project stage responsible person and required notice, and it is negative in the project stage when step S400 Prior notice in place, to effectively reduce project risk, realizes the management to project risk before duty people starts.
The present invention is further arranged to: step S400 includes:
S410: the 4th data of the default advance notification times of building project stage responsible person and corresponding project stage responsible person Library;
S420: analyzing and determining whether project stage responsible person is stored with its corresponding preset time in the 4th database, if item The mesh stage, responsible person was prestored into corresponding preset time in the 4th database, then transferred the 4th number in actual application It is on the contrary then have step S430 according to the corresponding preset time that respective item responsible person in library is prestored into;
S430: the 5th based on respective item stage responsible person preset time account of the history set by same type project is constructed Database, while transferring respective item stage responsible person preset time situation set by same type project, if it exists 3 and Above data, then have a step S440, on the contrary then have step S450;
S440: going through three times is closed on based on corresponding project stage responsible person preset time situation set by same type project History data, and take the average of historical data three times as the preset time for predicting corresponding project stage responsible person;
S450: in advance in corresponding preset time notice to the risk of corresponding project leader's respective item.
By using above-mentioned technical proposal, project is based on by step S410, step S420, step S430, step S440 Stage responsible person provides 3 times in project stage responsible person and when the above historical data, can be responsible for based on the project stage The historical data of people predicts the preset time of project stage responsible person.
The present invention is further arranged to: step S450 the following steps are included:
S451: history number present in respective item stage responsible person's preset time situation set by same type project is transferred According to, and using three historical datas as required data count;
S452: the 6th data of the predetermined time data situation of building project stage and respective item stage difference responsible person Library, the preset time of the different responsible persons of number needed for adjacent time residue is transferred in the 6th data;
S453: the preset historical data of respective item stage responsible person if it exists then carries out weight calculation, and specific weight calculating is shown in S454;Conversely, then take the average time of the preset time of 3 different responsible persons as correspondence project stage responsible person it is default when Between.
It, can be negative in the project stage by the combination setting of step S451, S452, S453 by using above-mentioned technical proposal When duty people does not provide the historical data of corresponding number, project can be gone out by Weight prediction in conjunction with the data of different responsible persons The preset time of stage responsible person.
The present invention is further arranged to: step S454 the following steps are included:
S454.A: establishing Weight algorithm, i.e. Z=a*i+b*j, and wherein Z is weight calculation numerical value, namely the project stage predicted The preset time of responsible person, a are the preset historical data of respective item stage responsible person, and i is respective item stage responsible person The weight coefficient of preset historical data, b are the predetermined time data of remaining different responsible person, and j is remaining different responsible person The weight coefficient of preset time;
S454.B: the specific data for obtaining a, i, j, b are transferred respectively into Weight algorithm, calculate the pre- of project stage responsible person If the time.
By using above-mentioned technical proposal, weight is effectively disclosed by the setting of step S454.A and step S454.B Calculation effectively discloses the preset time of project stage responsible person.
The present invention is further arranged to: further including the step S500 of and then step S400, specific steps S500 includes:
S510: the 8th database of building project stage risk and project stage risk occurrence time;
S520: inquiring the opportunity of project stage risk generation using the project stage as query object in the 8th database, and Load is in the information of responsible person for notifying the next project stage;
S530: the opportunity based on the generation of project stage risk calculates the opportunity that each project risk occurs, and prior notice is corresponding Project stage responsible person.
By using above-mentioned technical proposal, project risk is based on by the setting of step S510, S520, S530 and is notified in time Project stage responsible person, and the opportunity that can be occurred based on project stage risk notifies project stage responsible person in time.
The present invention is further arranged to: the occasions section of responsible person being notified to carry out red-label in step S520.
By using above-mentioned technical proposal, due to notifying the occasions section of responsible person to carry out red-label in step S520, Project stage responsible person can be notified in time.
The present invention is further arranged to: the advice method that responsible person is notified in step S530 is verbal announcement mode.
By using above-mentioned technical proposal, due to notifying that the advice method of responsible person is verbal announcement side in step S530 Formula can reduce cost while guaranteeing verbal announcement effect.
In conclusion advantageous effects of the invention are as follows:
1. prior notice may go out in actual application to its practical phased project being responsible for of project stage responsible person Existing risk is simultaneously evaded in advance;
2. actual items stage responsible person is practical execute specific phased project during, can be based on the appearance of project risk Opportunity is reminded in time.
Detailed description of the invention
Fig. 1 is the step schematic diagram of whole process engineering consulting project risk management method of the present invention.
Fig. 2 is the specific method step schematic diagram of step S400 in Fig. 1.
Fig. 3 is the specific method step schematic diagram of step S450 in Fig. 2.
Fig. 4 is the specific method step schematic diagram of step S454.
Fig. 5 is the specific method step schematic diagram of step S500.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
It referring to Fig.1, is a kind of whole process engineering consulting project risk management method disclosed by the invention, including following step It is rapid: S100: building the engineering project stage and respective stage institute's match time section first database, the engineering project stage according to Logical order is divided into: the project planning stage in the prospective design stage, in the bid and purchase stage, Construction stage, is completed and delivers Stage, operation and maintenance stage;S200: second of risk existing for project corresponding to building engineering project stage and respective stage Database, at the same construct engineering project stage and respective stage matched responsible person third database;S300: real-time base In the current time as query object, project stage corresponding to current time and next is inquired in first database The initial time of project stage, while inquiring next project in the second database using next project as query object and existing Risk, the responsible person of next project stage is inquired in third database;S400: in advance when the starting of next project stage Between preset time notify its risk for being responsible for project of the responsible person of next project stage.
As shown in Fig. 2, further contemplate prior notice phased project responsible person opportunity and corresponding risk, step S400 includes: S410: the of the default advance notification times of building project stage responsible person and corresponding project stage responsible person Four databases;S420: analyzing and determining whether project stage responsible person is stored with its corresponding preset time in the 4th database, If project stage responsible person is prestored into corresponding preset time in the 4th database, is transferred in actual application The corresponding preset time that respective item responsible person is prestored into four databases, it is on the contrary then have step S430;S430: building is based on phase The 5th database of project stage responsible person preset time account of the history set by same type project is answered, while being transferred corresponding Project stage responsible person preset time situation set by same type project, 3 and above data, then have step if it exists S440, it is on the contrary then have step S450;S440: based on corresponding project stage responsible person preset time set by same type project The historical data of situation closed on three times, and take the average of historical data three times as the corresponding project stage responsible person's of prediction Preset time;S450: in advance in corresponding preset time notice to the risk of corresponding project leader's respective item.
As shown in figure 3, further contemplate the exact moment that prior notice corresponds to project leader, step S450 include with Lower step: it S451: transfers and is gone through present in respective item stage responsible person's preset time situation set by same type project History data, and using three historical datas as required data count;S452: building project stage and respective item stage are different 6th database of the predetermined time data situation of responsible person, number needed for adjacent time residue is transferred in the 6th data is not With the preset time of responsible person;S453: the preset historical data of respective item stage responsible person if it exists then carries out weight meter It calculates, S454 is shown in specific weight calculating;Conversely, then taking the average time of the preset time of 3 different responsible persons as corresponding project The preset time of stage responsible person.
As shown in figure 4, step S454 is the following steps are included: S454.A: establishing Weight algorithm, i.e. Z=a*i+b*j, wherein Z For weight calculation numerical value, namely the preset time of project stage responsible person predicted, a default for respective item stage responsible person Historical data, i is the weight coefficient of the respective item stage preset historical data of responsible person, and b is remaining different responsible person Predetermined time data, j is the weight coefficient of the preset time of remaining different responsible person;S454.B: transfer respectively obtain a, i, J, the specific data of b calculate the preset time of project stage responsible person into Weight algorithm.
Furthermore the moments notice that can be occurred based on project stage risk when considering notification phase project leader To the corresponding project risk of phased project responsible person.
As shown in figure 5, a kind of whole process engineering consulting project risk management method further includes the step of and then step S400 Rapid S500, specific steps S500 include: S510: the 8th number of building project stage risk and project stage risk occurrence time According to library;S520: inquiring the opportunity of project stage risk generation using the project stage as query object in the 8th database, and Load is in the information of responsible person for notifying the next project stage;S530: the opportunity occurred based on project stage risk is calculated often The opportunity that a project risk occurs, and prior notice corresponds to project stage responsible person.
Wherein, it notifies the occasions section of responsible person to carry out red-label in step S520, notifies responsible person in step S530 Advice method be verbal announcement mode, the verbal announcement mode in step S530 uses voice prompting device.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it It is interior.

Claims (8)

1. a kind of whole process engineering consulting project risk management method, which comprises the following steps:
S100: the first database of building engineering project stage and respective stage institute's match time section, engineering project stage press Be divided into according to logical order: the project planning stage in the prospective design stage, in the bid and purchase stage, Construction stage, is completed and hands over Pay stage, operation and maintenance stage;
S200: the second database of risk existing for project corresponding to building engineering project stage and respective stage, while structure Build engineering project stage and respective stage matched responsible person third database;
S300: it is inquired corresponding to current time in first database based on the current time as query object in real time The initial time of project stage and next project stage, while being looked into the second database using next project as query object Risk existing for next project is ask out, the responsible person of next project stage is inquired in third database;
S400: notify the responsible person of next project stage that it is responsible in the preset time of next project stage initial time in advance The risk of project.
2. a kind of whole process engineering consulting project risk management method according to claim 1, which is characterized in that step S400 includes:
S410: the 4th data of the default advance notification times of building project stage responsible person and corresponding project stage responsible person Library;
S420: analyzing and determining whether project stage responsible person is stored with its corresponding preset time in the 4th database, if item The mesh stage, responsible person was prestored into corresponding preset time in the 4th database, then transferred the 4th number in actual application It is on the contrary then have step S430 according to the corresponding preset time that respective item responsible person in library is prestored into;
S430: the 5th based on respective item stage responsible person preset time account of the history set by same type project is constructed Database, while transferring respective item stage responsible person preset time situation set by same type project, if it exists 3 and Above data, then have a step S440, on the contrary then have step S450;
S440: going through three times is closed on based on corresponding project stage responsible person preset time situation set by same type project History data, and take the average of historical data three times as the preset time for predicting corresponding project stage responsible person;
S450: in advance in corresponding preset time notice to the risk of corresponding project leader's respective item.
3. a kind of whole process engineering consulting project risk management method according to claim 2, which is characterized in that step S450 the following steps are included:
S451: history number present in respective item stage responsible person's preset time situation set by same type project is transferred According to, and using three historical datas as required data count;
S452: the 6th data of the predetermined time data situation of building project stage and respective item stage difference responsible person Library, the preset time of the different responsible persons of number needed for adjacent time residue is transferred in the 6th data;
S453: the preset historical data of respective item stage responsible person if it exists then carries out weight calculation, and specific weight calculating is shown in S454;Conversely, then take the average time of the preset time of 3 different responsible persons as correspondence project stage responsible person it is default when Between.
4. a kind of whole process engineering consulting project risk management method according to claim 3, which is characterized in that step S454 the following steps are included:
S454.A: establishing Weight algorithm, i.e. Z=a*i+b*j, and wherein Z is weight calculation numerical value, namely the project stage predicted The preset time of responsible person, a are the preset historical data of respective item stage responsible person, and i is respective item stage responsible person The weight coefficient of preset historical data, b are the predetermined time data of remaining different responsible person, and j is remaining different responsible person The weight coefficient of preset time;
S454.B: the specific data for obtaining a, i, j, b are transferred respectively into Weight algorithm, calculate the pre- of project stage responsible person If the time.
5. a kind of whole process engineering consulting project risk management method according to claim 1, which is characterized in that further include And then the step S500 of step S400, specific steps S500 include:
S510: the 8th database of building project stage risk and project stage risk occurrence time;
S520: inquiring the opportunity of project stage risk generation using the project stage as query object in the 8th database, and Load is in the information of responsible person for notifying the next project stage;
S530: the opportunity based on the generation of project stage risk calculates the opportunity that each project risk occurs, and prior notice is corresponding Project stage responsible person.
6. a kind of whole process engineering consulting project risk management method according to claim 5, which is characterized in that step The occasions section of responsible person is notified to carry out red-label in S520.
7. a kind of whole process engineering consulting project risk management method according to claim 6, which is characterized in that step The advice method that responsible person is notified in S530 is verbal announcement mode.
8. a kind of whole process engineering consulting project risk management method according to claim 7, it is characterised in that: step Verbal announcement mode in S530 uses voice prompting device.
CN201910786486.9A 2019-08-23 2019-08-23 A kind of whole process engineering consulting project risk management method Pending CN110516963A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910786486.9A CN110516963A (en) 2019-08-23 2019-08-23 A kind of whole process engineering consulting project risk management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910786486.9A CN110516963A (en) 2019-08-23 2019-08-23 A kind of whole process engineering consulting project risk management method

Publications (1)

Publication Number Publication Date
CN110516963A true CN110516963A (en) 2019-11-29

Family

ID=68627674

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910786486.9A Pending CN110516963A (en) 2019-08-23 2019-08-23 A kind of whole process engineering consulting project risk management method

Country Status (1)

Country Link
CN (1) CN110516963A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111242378A (en) * 2020-01-15 2020-06-05 湖南日升工程咨询有限公司 Engineering process dynamic cost control method based on BIM technology
CN112307081A (en) * 2020-10-24 2021-02-02 上海东方投资监理有限公司 Project budget cost management system, method, electronic device and readable storage medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102521709A (en) * 2011-12-22 2012-06-27 上海建科工程咨询有限公司 Building construction quality safety online risk management system
CN105373896A (en) * 2015-11-24 2016-03-02 杭州构家网络科技有限公司 Project management system
CN109345076A (en) * 2018-09-04 2019-02-15 上海建科工程咨询有限公司 A kind of whole process engineering consulting project risk management method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102521709A (en) * 2011-12-22 2012-06-27 上海建科工程咨询有限公司 Building construction quality safety online risk management system
CN105373896A (en) * 2015-11-24 2016-03-02 杭州构家网络科技有限公司 Project management system
CN109345076A (en) * 2018-09-04 2019-02-15 上海建科工程咨询有限公司 A kind of whole process engineering consulting project risk management method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111242378A (en) * 2020-01-15 2020-06-05 湖南日升工程咨询有限公司 Engineering process dynamic cost control method based on BIM technology
CN111242378B (en) * 2020-01-15 2023-09-15 正茂日升工程咨询有限公司 Engineering process dynamic cost management and control method based on BIM technology
CN112307081A (en) * 2020-10-24 2021-02-02 上海东方投资监理有限公司 Project budget cost management system, method, electronic device and readable storage medium

Similar Documents

Publication Publication Date Title
Karimi et al. A fully fuzzy best–worst multi attribute decision making method with triangular fuzzy number: A case study of maintenance assessment in the hospitals
Stock et al. Industry 4.0 as enabler for a sustainable development: A qualitative assessment of its ecological and social potential
Mikulakova et al. Knowledge-based schedule generation and evaluation
Liao et al. Metaheuristics for project and construction management–A state-of-the-art review
CN110516963A (en) A kind of whole process engineering consulting project risk management method
Ning et al. A multi-attribute model for construction site layout using intuitionistic fuzzy logic
JPH03168865A (en) Pattern learning type ordering device and cad device
CN109557934A (en) A kind of control method and device of the unmanned plane cruise based on assembled architecture platform
US20210073695A1 (en) Production scheduling system and method
Gohar et al. Identifying and evaluating risks of construction projects in fuzzy environment: a case study in Iranian construction industry
CN107590561A (en) A kind of orderly costume changing method of electric energy meter based on power network line kinematic error remote calibration
CN109272140A (en) A kind of transformer equipment runtime forecasting of cost method based on big data analysis
CN105184490A (en) Power grid dispatching operation process risk auxiliary pre-control system
Li et al. Effective methods for integrated process planning and scheduling
Tang et al. A digital twin-assisted collaborative capability optimization model for smart manufacturing system based on Elman-IVIF-TOPSIS
Jin et al. A new framework for MRP systems to be effective in engineered-to-order environments
Pisz Controlling of logistics projects
JP2005182558A (en) Cost prediction/evaluation method
Ungureanu et al. Quantitative lean assessment of line of balance schedules’ quality
Jafari Ashlaghi A new approach to green supplier selection based on fuzzy multi-criteria decision making method and linear physical programming
Hossain et al. PSO-based harmony search algorithm to aggregate production planning under possibilistic environment
Gon Choi et al. Framework development for optimizing responses to NPD risks
Leu et al. A Novel Development of TRIZ-Analogic Construction Interface Problem Identification and Solutions Framework
Golany et al. An interactive goal programming procedure for operational recovery problems
US20230259843A1 (en) Methods, internet of things systems and storage media for visualizing work orders of smart gas platforms

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191129

RJ01 Rejection of invention patent application after publication