CN110513112A - A kind of flowing hole forms device and shaft construction method - Google Patents

A kind of flowing hole forms device and shaft construction method Download PDF

Info

Publication number
CN110513112A
CN110513112A CN201910830416.9A CN201910830416A CN110513112A CN 110513112 A CN110513112 A CN 110513112A CN 201910830416 A CN201910830416 A CN 201910830416A CN 110513112 A CN110513112 A CN 110513112A
Authority
CN
China
Prior art keywords
flowing hole
baffle ring
sealing
housing
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910830416.9A
Other languages
Chinese (zh)
Inventor
孟亚运
李红文
张金婉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Zhongnan Engineering Corp Ltd
Original Assignee
PowerChina Zhongnan Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Zhongnan Engineering Corp Ltd filed Critical PowerChina Zhongnan Engineering Corp Ltd
Priority to CN201910830416.9A priority Critical patent/CN110513112A/en
Publication of CN110513112A publication Critical patent/CN110513112A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of flowing holes to form device and shaft construction method, and flowing hole forms the intersection that device is set to vertical shaft and tunnel;It includes baffle ring and embedded water stop structure that flowing hole, which forms device,;The space that baffle ring inner wall surrounds forms flowing hole, and the outer wall of baffle ring with the bar construction of the vertical shaft one phase lining cutting of flowing hole periphery for connecting;Embedded water stop structure includes housing and sealing piece;Housing is set on the outer wall of baffle ring, and sealing piece includes fixed section and sealing section, and fixed section protrudes into phase lining cutting casting space after passing through housing, and sealing section bending is placed in housing;Sealing section can restore original shape after baffle ring removal and protrude into flowing hole the sealing element formed for sealing gap between flowing hole and plug.The present invention can avoid slotting on fist stage concrete, and easy for construction, water-stagnating effect is reliable, not only reduce the damage to fist stage concrete, while meet the requirement of the overcurrent before second stage concrete pours.

Description

A kind of flowing hole forms device and shaft construction method
Technical field
The present invention relates to water conservancy and hydropower facility technology fields more particularly to a kind of flowing hole to form device and Construction of Silo side Method.
Background technique
In hydraulic and hydroelectric engineering, frequently involving concrete structure needs substage construction and needs before second stage concrete pours full The case where sufficient overcurrent requires.The case where being combined such as currently a popular shaft spillway with diversion tunnel, as shown in Figure 1, with perpendicular The diversion tunnel 500 that well 100 is connected to divides vertical shaft 100 for upper semisection and lower semisection, and construction time diversion tunnel 500 is generally using permanent perpendicular Subsequent 200 overcurrent of tunnel of well 100.For the overcurrent requirement for meeting construction time diversion tunnel, traditional method is usually in vertical shaft 100 1 After the completion of phase lining concrete layer pours, flowing hole 300 is opened on a phase lining concrete layer, coagulation is used after the completion of overcurrent Native plug 400 blocks, due to concrete plug water penetration is strong and plug 400 and flowing hole 300 there are structure gaps, to avoid this 300 leak of flowing hole meets 100 later period of vertical shaft service requirement, and water sealing structure need to be arranged at flowing hole 300.It is more actual Way is fixed water sealing structure in flowing hole structural joint position, then pour second stage concrete lining cutting layer before the second phase pours.I.e. The waterstop sealing of flowing hole 300 can be achieved.
However, traditional method need to slot in fist stage concrete, fluting need to cut off the surface layer reinforcing bar of fist stage concrete, not only Construction is inconvenient, causes construction efficiency low;And fluting can damage the overall structure of vertical shaft 100, be unfavorable for the long-term fortune of vertical shaft 100 Row.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the deficiencies in the prior art, provide a kind of simplified Construction of Silo process, Construction of Silo efficiency is improved, and reduces the damage to fist stage concrete, while meeting the overcurrent before second stage concrete pours and seam The flowing hole that gap waterstop sealing requires forms device.
In order to solve the above technical problems, the invention adopts the following technical scheme:
A kind of flowing hole formation device, the flowing hole form the intersection that device is set to vertical shaft and tunnel;The flowing hole shape It include baffle ring and multiple embedded water stop structures at device;
The space that the baffle ring inner wall surrounds forms flowing hole, and the outer wall of the baffle ring is for one phase of vertical shaft with flowing hole periphery Liner structure connection;
The embedded water stop structure includes housing and sealing piece;The housing is set on the outer wall of baffle ring, the sealing piece Including fixed section and sealing section, the fixed section protrudes into phase lining cutting casting space after passing through housing, the sealing section folding It is placed in after curved in the housing;
The sealing section can restore original shape and protrude into flowing hole to be formed for sealing flowing hole and blocking up after baffle ring removal The sealing element in gap between head.
Flowing hole, and embedded water stop piece, one phase of vertical shaft lining are formed before vertical shaft one phase lining cutting pours by the device as a result, After block pours, diversion tunnel overcurrent can be completed without fluting and check and accept, it is not only small to the damage of fist stage concrete, but also Construction of Silo Process is simplified, Construction of Silo efficiency is improved.
Sealing piece is bent in housing, it is ensured that is not destroyed when overcurrent;After overcurrent before pouring plug, straight sealing is broken Piece forms water sealing structure, prevent seam leak.Water sealing structure setting is integrated in a procedure with flowing hole formation, and It is easy for construction, construction is further simplified, construction efficiency is improved.As a further improvement of the above technical scheme:
The embedded water stop structure be equipped with it is multiple, multiple embedded water stop structures along the baffle ring circumferentially, multiple sealing sections The sealing element for sealing gap between flowing hole and plug is enclosed after recovery original shape.
To dismantle convenient for baffle ring, the two sides of the housing are arranged with connecting plate, and the outer wall of the connecting plate and baffle ring is solid It is fixed.Connecting plate is preferably connect with baffle ring spot welding.
To guarantee that the present apparatus is connected firmly with phase lining cutting, high-velocity flow is avoided when overcurrent to destroy by rush of water the present apparatus, the connection The more dowels connecting with the bar construction of vertical shaft one phase lining cutting are fixed on plate.
There is negative pressure to avoid overcurrent or pouring in the too fast housing cavity of flow velocity, causes baffle ring deformation even to destroy, institute It states and is equipped with filler, the preferred coarse sand of the filler in housing.On the one hand can be to avoid the above problem, it on the other hand can also be right Steel plate forms support, improves the reliability of the present apparatus.
It is preferred that the baffle ring is enclosed by muti-piece baffle.
The inventive concept total as one forms device progress vertical shaft using above-mentioned flowing hole the present invention also provides a kind of The method of construction, comprising the following steps:
S1: the outer wall of the baffle ring is connect with the bar construction of the vertical shaft one phase lining cutting of flowing hole periphery, in a phase, lining cutting is poured Casting concrete in space is built, a phase lining concrete layer is formed;
S2: it completes diversion tunnel overcurrent and checks and accepts;
S3: baffle ring is removed, and the lower part of sealing piece is restored to the original state, pours the plug for blocking the flowing hole, is made described Plug and sealing element are connected.
As a further improvement of the above technical scheme:
Its spy is, further comprising the steps of:
S4: pouring the second stage of lining concrete layer, completes Construction of Silo.
Compared with the prior art, the advantages of the present invention are as follows:
1, the invention avoids slotting on fist stage concrete, easy for construction, water-stagnating effect is reliable, not only reduces mixed to a phase The damage of soil is coagulated, while meeting the requirement of the overcurrent before second stage concrete pours.
2, the present invention, which is suitable for concrete structure, needs substage construction, and by stages during have the case where overcurrent requirement, have wide General engineering application value.
Detailed description of the invention
Fig. 1 is the structural schematic diagram that shaft spillway is combined with diversion tunnel.
Fig. 2 is the structural schematic diagram that the flowing hole that the embodiment of the present invention is arranged in the intersection of vertical shaft and tunnel forms device (merely illustrating sealing piece and baffle ring).
Fig. 3 is that the flowing hole of the embodiment of the present invention forms the structural schematic diagram of device.
Marginal data: 1, sealing piece;11, fixed section;12, sealing section;2, housing;3, connecting plate;4, baffle ring;5, it fills Object;6, dowel;7, phase lining cutting casting space;100, vertical shaft;200, tunnel;300, flowing hole;400, plug;500, water conservancy diversion Hole.
Specific embodiment
Below in conjunction with specific preferred embodiment, the invention will be further described, but not thereby limiting the invention Protection scope.
Embodiment 1:
As shown in Fig. 2, the flowing hole of the present embodiment forms device, set on the intersection of vertical shaft 100 and tunnel 200.
As shown in figure 3, it includes baffle ring 4 and embedded water stop structure that flowing hole, which forms device,.
Baffle ring 4 is enclosed by muti-piece baffle, and the space that 4 inner wall of baffle ring surrounds forms flowing hole 300.
Embedded water stop structure includes housing 2 and sealing piece 1;Housing 2 is placed on the outer wall of baffle ring 4, and housing 2 is ring Shape structure, the preferred copper seal of sealing piece 1, sealing piece 1 are cyclic structure, and sealing piece 1 includes fixed section 11 and sealing section 12, only Water section 12 protrudes into after passing through housing 2 close to the center of cyclic structure, center of the fixed section 11 far from cyclic structure, fixed section 11 In one phase lining cutting casting space 7, it is placed in housing 2 after 12 bending of sealing section;And filler 5 is equipped in housing 2, this is filled out Fill the preferred coarse sand of object 5.Sealing section 12 can restore original shape and protrude into flowing hole 300 to be formed for close after the removal of baffle ring 4 Seal the sealing element in gap between flowing hole 300 and plug 400.
In other embodiments, embedded water stop structure also can be set multiple, week of multiple embedded water stop structures along baffle ring 4 To arrangement, sealing section is restored original shape after baffle ring removal and is protruded into flowing hole, multiple sealing sections for restoring original shape It is enclosed the sealing element for sealing gap between flowing hole and plug.The two sides of housing 2 are arranged with connecting plate 3, connection Plate 3 and the outer wall of baffle ring 4 are fixed;The more dowels 6 connecting with the bar construction of vertical shaft one phase lining cutting are fixed on connecting plate 3.
Specific step is as follows for Construction of Silo:
1) dowel 6 is welded on connecting plate 3, dowel 6 is arranged at a certain distance, and dowel unilateral side length meets anchorage length It is required that;
2) when binding a phase lining concrete reinforcing bar, dowel 6 and a phase lining concrete reinforcement welding are fixed;
3) baffle ring 4 and connecting plate 3 are welded, guarantees that baffle ring 4 pours surface with fist stage concrete and flushes, to meet the overcurrent period Play the role of protecting Copper water stop;
4) nose of sealing piece 1 and the bending of sealing section 12 are placed in housing 2, fixed section 11 is located at phase lining cutting casting space In 7;Housing 2 is fixed on 4 outer wall of baffle ring after filling coarse sand in housing 2.
5) casting concrete in phase lining cutting casting space 7 forms a phase lining concrete layer;
6) 500 overcurrent of diversion tunnel is completed to check and accept;
7) after the completion of overcurrent, baffle ring 4 and connecting plate 3 is removed, the coarse sand in housing 2 is cleaned out, straight copper seal 1 is broken, Pour second stage concrete and plug 400.
The above is only the preferred embodiment of the application, not does any type of limitation to the application, although the application with Preferred embodiment discloses as above, however not to limit the application, any person skilled in the art is not departing from this In the range of applying for technical solution, a little variation or modification are made using the technology contents of the disclosure above and is equal to equivalent reality Case is applied, is belonged in technical proposal scope.

Claims (8)

1. a kind of flowing hole forms device, which is characterized in that the flowing hole forms device and is set to vertical shaft (100) and tunnel (200) intersection;It includes baffle ring (4) and embedded water stop structure that the flowing hole, which forms device,;
The space that baffle ring (4) inner wall surrounds forms flowing hole (300), and the outer wall of the baffle ring (4) is used for and flowing hole (300) the bar construction connection of the vertical shaft one phase lining cutting of periphery;
The embedded water stop structure includes housing (2) and sealing piece (1);The housing (2) is set to the outer wall of baffle ring (4) On, the sealing piece (1) includes fixed section (11) and sealing section (12), and the fixed section (11) is protruded into after passing through housing (2) In one phase lining cutting casting space (7), it is placed in the housing (2) after sealing section (12) bending;
The sealing section (12) can restore original shape after baffle ring (4) remove and protrude into flowing hole (300) to be formed for close Seal the sealing element in gap between flowing hole (300) and plug (400).
2. flowing hole according to claim 1 forms device, which is characterized in that the embedded water stop structure be equipped with it is multiple, Circumferentially along the baffle ring (4), multiple sealing sections (12) are enclosed multiple embedded water stop structures after restoring original shape For sealing the sealing element in gap between flowing hole (300) and plug (400).
3. flowing hole according to claim 1 or 2 forms device, which is characterized in that set up separately the two sides of the housing (2) Have connecting plate (3), the connecting plate (3) and the outer wall of baffle ring (4) are fixed.
4. flowing hole according to claim 3 forms device, which is characterized in that be fixed with more on the connecting plate (3) The dowel (6) being connect with the bar construction of vertical shaft one phase lining cutting.
5. flowing hole according to claim 1,2 or 4 forms device, which is characterized in that be equipped with and fill out in the housing (2) Fill object (5).
6. flowing hole according to claim 1,2 or 4 forms device, which is characterized in that the baffle ring (4) is by muti-piece baffle It encloses.
7. a kind of method for forming device progress Construction of Silo using flowing hole as claimed in any one of claims 1 to 6, including Following steps:
S1: the outer wall of the baffle ring (4) is connect with the bar construction of the vertical shaft one phase lining cutting of flowing hole (300) periphery, one Casting concrete in phase lining cutting casting space (7) forms a phase lining concrete layer;
S2: it completes diversion tunnel (500) overcurrent and checks and accepts;
S3: removing baffle ring (4), and the sealing section (12) is restored to the original state, and pours for blocking the stifled of the flowing hole (300) Head (400) makes the plug (400) and sealing element be connected.
8. the method for Construction of Silo according to claim 7, spy are, further comprising the steps of:
S4: pouring the second stage of lining concrete layer, completes Construction of Silo.
CN201910830416.9A 2019-09-04 2019-09-04 A kind of flowing hole forms device and shaft construction method Pending CN110513112A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910830416.9A CN110513112A (en) 2019-09-04 2019-09-04 A kind of flowing hole forms device and shaft construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910830416.9A CN110513112A (en) 2019-09-04 2019-09-04 A kind of flowing hole forms device and shaft construction method

Publications (1)

Publication Number Publication Date
CN110513112A true CN110513112A (en) 2019-11-29

Family

ID=68629707

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910830416.9A Pending CN110513112A (en) 2019-09-04 2019-09-04 A kind of flowing hole forms device and shaft construction method

Country Status (1)

Country Link
CN (1) CN110513112A (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101649746A (en) * 2009-08-25 2010-02-17 中国水电顾问集团华东勘测设计研究院 Method for arranging drain plug peripheral water stopping sheet of tunnel plug
CN101949293A (en) * 2010-10-09 2011-01-19 中国水电顾问集团成都勘测设计研究院 Periphery water stop structure of tunnel plug and setting method thereof
CN204266165U (en) * 2014-11-10 2015-04-15 南京市第二基础工程公司 The vertical water-stopping structure of a kind of concrete work deformation joint
CN206189365U (en) * 2016-11-18 2017-05-24 中国电建集团成都勘测设计研究院有限公司 A water conservancy diversion block structure that is used for diversion tunnel shutoff body to pour
CN106930778A (en) * 2017-03-17 2017-07-07 浙江省水利水电勘测设计院 A kind of water-conveyance tunnel concrete lining induces crack structure and method to set up
CN206800323U (en) * 2017-04-23 2017-12-26 南安市精立捷机械科技有限公司 One kind is used for the vertical sealing swaging die of concrete works movement joint
CN107605511A (en) * 2017-08-31 2018-01-19 中国电建集团北京勘测设计研究院有限公司 Cavern's plug peripheral water stopping structure and its construction method
CN206928255U (en) * 2017-05-16 2018-01-26 中国电建集团成都勘测设计研究院有限公司 The maintenance arrangement of the permanent plug of induced joint diversion tunnel
CN207567738U (en) * 2017-10-16 2018-07-03 三峡集团西藏能源投资有限公司 Diversion tunnel plugging structure
CN208685572U (en) * 2018-08-23 2019-04-02 中国电建集团成都勘测设计研究院有限公司 High outer water vertical shaft depressurizes discharge structure
CN210660088U (en) * 2019-09-04 2020-06-02 中国电建集团中南勘测设计研究院有限公司 Overflowing hole forming device

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101649746A (en) * 2009-08-25 2010-02-17 中国水电顾问集团华东勘测设计研究院 Method for arranging drain plug peripheral water stopping sheet of tunnel plug
CN101949293A (en) * 2010-10-09 2011-01-19 中国水电顾问集团成都勘测设计研究院 Periphery water stop structure of tunnel plug and setting method thereof
CN204266165U (en) * 2014-11-10 2015-04-15 南京市第二基础工程公司 The vertical water-stopping structure of a kind of concrete work deformation joint
CN206189365U (en) * 2016-11-18 2017-05-24 中国电建集团成都勘测设计研究院有限公司 A water conservancy diversion block structure that is used for diversion tunnel shutoff body to pour
CN106930778A (en) * 2017-03-17 2017-07-07 浙江省水利水电勘测设计院 A kind of water-conveyance tunnel concrete lining induces crack structure and method to set up
CN206800323U (en) * 2017-04-23 2017-12-26 南安市精立捷机械科技有限公司 One kind is used for the vertical sealing swaging die of concrete works movement joint
CN206928255U (en) * 2017-05-16 2018-01-26 中国电建集团成都勘测设计研究院有限公司 The maintenance arrangement of the permanent plug of induced joint diversion tunnel
CN107605511A (en) * 2017-08-31 2018-01-19 中国电建集团北京勘测设计研究院有限公司 Cavern's plug peripheral water stopping structure and its construction method
CN207567738U (en) * 2017-10-16 2018-07-03 三峡集团西藏能源投资有限公司 Diversion tunnel plugging structure
CN208685572U (en) * 2018-08-23 2019-04-02 中国电建集团成都勘测设计研究院有限公司 High outer water vertical shaft depressurizes discharge structure
CN210660088U (en) * 2019-09-04 2020-06-02 中国电建集团中南勘测设计研究院有限公司 Overflowing hole forming device

Similar Documents

Publication Publication Date Title
CN102061710B (en) Underground continuous wall joint and manufacturing method thereof
CN206319886U (en) Tunnel lining structure
CN110453607A (en) Prefabricated pier steel bar connection mode and construction method thereof
CN106894449A (en) A kind of structure type of immersed tube tunnel final joint
CN108035337B (en) The construction method of a kind of diaphram wall and applied to the connector in this method
CN211547357U (en) Prefabricated structure grout sleeve joint construction of assembling
CN106930277A (en) A kind of construction of manual-excavation cast-in-place pile method
CN106284335A (en) Piling quality defect handling method
CN107605511A (en) Cavern's plug peripheral water stopping structure and its construction method
CN105239607B (en) Diaphram wall and concrete structure bottom plate whole anti-uplift structure and its construction method
CN105971022B (en) The construction method of the vertical sealing swaging die of concrete works movement joint with projection
CN207567738U (en) Diversion tunnel plugging structure
CN105625449B (en) The connecting structure method of concrete open caisson and steel open caisson
CN110513112A (en) A kind of flowing hole forms device and shaft construction method
CN107975152A (en) The ductility connecting structure and construction method of first floor vertical member and basement roof
CN106592532B (en) The construction method of concrete works deformation joint sealing swaging die with reinforcing fiber
CN207686288U (en) The manufacture of the horizontal hole to be provided of wall and plugging device
CN210660088U (en) Overflowing hole forming device
CN208763663U (en) A kind of tunnel and tunnel closure plug blocking plug foundation structure with tunnel
CN108193706A (en) A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure
CN208379644U (en) A kind of post-cast strip built for basement
CN109706932A (en) Karst cave plug structure and construction method
CN205976914U (en) Assembled windowsill structure of bearing down on one
CN214089952U (en) Bridge reinforcing foundation
CN109356124B (en) Chamber level crossing fork structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191129

RJ01 Rejection of invention patent application after publication