CN110453604A - A kind of construction method of the rigid structure 0# block of high pier stud continuous beam - Google Patents
A kind of construction method of the rigid structure 0# block of high pier stud continuous beam Download PDFInfo
- Publication number
- CN110453604A CN110453604A CN201910700619.6A CN201910700619A CN110453604A CN 110453604 A CN110453604 A CN 110453604A CN 201910700619 A CN201910700619 A CN 201910700619A CN 110453604 A CN110453604 A CN 110453604A
- Authority
- CN
- China
- Prior art keywords
- bracket
- block
- construction method
- installation
- rigid structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of construction method of high rigid structure 0# block of pier stud continuous beam, after the completion of including the following steps: formwork installation bracket key box → casting concrete → concreting → installation attached wall, mounting platform and protective net → installation bracket → correction mounting bracket → precompressed → formwork installation Hanging Basket embedded part casting concrete → concreting after the completion of → form removal, bracket and bracket.
Description
Technical field
The present invention relates to technical field of bridge construction more particularly to a kind of construction parties of the rigid structure 0# block of high pier stud continuous beam
Method.
Background technique
Increasingly update with bridge construction technology be constantly progressive, long-span bridge construction of the cross a river across paddy is being built and is being raised
It is increasing to build engineering;The construction height of pier stud is more than hundred meters, and many places are in the environment of complicated topographical conditions, traditional pier stud
0# block construction method such as sets up the requirement that external scaffolding has been unable to meet high pier construction under complicated construction environment.
Summary of the invention
The purpose of the present invention is to solve problems of the prior art, and a kind of high pier stud continuous beam proposed is rigid
The construction method of structure 0# block, adopts the technical scheme that
A kind of construction method of the rigid structure 0# block of high pier stud continuous beam includes the following steps: formwork installation bracket key box → pour
After the completion of building concrete → concreting → installation attached wall, mounting platform and protective net → installation bracket → correction mounting bracket
After the completion of → precompressed → formwork installation Hanging Basket embedded part casting concrete → concreting → form removal, bracket and bracket.
Preferably, when pre-buried bracket key box, guarantee that each pre-buried bracket key box in same level height, is inserted into build-in consolidation,
Reinforced mesh circular bar must be increased at built-in fitting hole and make reinforcement processing;
Preferably, when installing wall-attaching equipment, wall-attaching equipment is required must be horizontal by baseline of bracket key box, and same seat in the plane is each
Wall-attaching equipment needs on the same axis.
Preferably, when attached wall, mounting platform and protective net are installed, attached wall is installed first, after wall-attaching equipment installs, then
Mounting platform and protective net, last mounting bracket.
Preferably, when bracket is installed, corresponding two brackets need to be installed, according to the center of gravity Reasonable Arrangement suspension centre of bracket,
Auxiliary rope is hung on bracket, and pier top descendant is lifted by loop wheel machine and draws auxiliary rope auxiliary in place, after bracket penetrates bracket key box
Bracket is slowly pulled in bracket key box, measures bracket elevation and levelness, plug ensures that bracket is met the requirements under upper pad.
Preferably, corresponding two brackets wear fining twisted steel to drawing after the installation is completed, fining twisted steel band double nut,
It is tight with torque wrench, after bracket installation qualification, lateral is carried out with No. 10 channel steels.
Preferably, the bracket is using 2 PSB830 grades of 32 fining twisted steels of φ as anchoring rod, single finish rolling screw thread
Steel can bear 600KN pulling force.
Preferably, template, bracket remove bracket after the completion of removing, in the pre-buried lifting hole(eyelet) of 0# block bottom plate bracket corresponding position, 0#
After block mount holder is removed, wirerope is penetrated to hoist engine out of lifting hole(eyelet) and lifts wirerope, removed to wearing fining twisted steel, with drawing
Rope pulls out the slow unloading of bracket to cushion cap.
Compared with prior art, the present invention provides a kind of construction method of high rigid structure 0# block of pier stud continuous beam, have with
It is lower the utility model has the advantages that
High pier, which lives the rational design based on 0# block frame system system in climbing formwork for construction, makes three-dimensional construction in high-altitude be changed into two-dimentional put down
Surface construction reduces the security risk coefficient of high-rise working;Calf support platform passes through structural concrete built-in fitting, bracket three's shape
At works-operation platform one stress system, the bearing capacity of structural concrete itself is made full use of;In the construction process without
The allocation and transportation of hoisting machinery are needed, construction equipment is reduced, accelerates construction progress, obtain good economic benefit.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation
Example is only a part of the embodiment of the present invention, instead of all the embodiments.
Embodiment one
A kind of construction method of the rigid structure 0# block of high pier stud continuous beam includes the following steps: formwork installation bracket key box → pour
After the completion of building concrete → concreting → installation attached wall, mounting platform and protective net → installation bracket → correction mounting bracket
After the completion of → precompressed → formwork installation Hanging Basket embedded part casting concrete → concreting → form removal, bracket and bracket.
Embodiment two
On the basis of example 1, when pre-buried bracket key box, guarantee that each pre-buried bracket key box in same level height, is inserted
Enter build-in consolidation, reinforced mesh circular bar must be increased at built-in fitting hole and make reinforcement processing;
Embodiment three
On the basis of example 2, when installing wall-attaching equipment, wall-attaching equipment is required must water by baseline of bracket key box
Flat, the same each wall-attaching equipment in seat in the plane needs on the same axis.
Example IV
On the basis of embodiment three, when attached wall, mounting platform and protective net are installed, attached wall, wall-attaching equipment are installed first
After installing, then mounting platform and protective net, last mounting bracket.
Embodiment five
On the basis of example IV, when bracket is installed, corresponding two brackets need to be installed, closed according to the center of gravity of bracket
Removing the work sets suspension centre, and auxiliary rope is hung on bracket, is lifted into pier top descendant by loop wheel machine and draws auxiliary rope auxiliary in place, bracket penetrates
Bracket is slowly pulled in bracket key box after bracket key box, measures bracket elevation and levelness, plug ensures that bracket satisfaction is wanted under upper pad
It asks.
Embodiment six
On the basis of embodiment five, corresponding two brackets wear fining twisted steel to drawing, finish rolling spiral shell after the installation is completed
Line steel band double nut, it is tight with torque wrench, after bracket installation qualification, lateral is carried out with No. 10 channel steels.
Embodiment seven
On the basis of embodiment six, the bracket using 2 PSB830 grades of 32 fining twisted steels of φ as anchoring rod,
Single fining twisted steel can bear 600KN pulling force.
Embodiment eight
On the basis of embodiment seven, template, bracket remove bracket after the completion of removing, and correspond to position in 0# block bottom plate bracket
It sets pre-buried lifting hole(eyelet), after 0# block mount holder is removed, wirerope is penetrated to hoist engine out of lifting hole(eyelet) and lifts wirerope, remove to wearing essence
Screw-thread steel is rolled, pulls out the slow unloading of bracket to cushion cap with messenger.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto,
Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its
Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.
Claims (8)
1. a kind of construction method of the rigid structure 0# block of high pier stud continuous beam, which comprises the steps of: formwork installs bracket
After the completion of key box → casting concrete → concreting → installation attached wall, mounting platform and protective net → installation bracket → correction
After the completion of the installation Hanging Basket embedded part casting concrete → concreting of mounting bracket → precompressed → formwork → form removal, bracket and
Bracket.
2. a kind of construction method of high rigid structure 0# block of pier stud continuous beam according to claim 1, it is characterised in that: pre-buried ox
When leg key box, guarantee that each pre-buried bracket key box in same level height, is inserted into build-in consolidation, must increase steel mesh at built-in fitting hole
Piece circular bar makees reinforcement processing.
3. a kind of construction method of high rigid structure 0# block of pier stud continuous beam according to claim 1, which is characterized in that installation is attached
When wall device, wall-attaching equipment is required must be horizontal by baseline of bracket key box, and the same each wall-attaching equipment in seat in the plane need to be in same axis
On.
4. a kind of construction method of high rigid structure 0# block of pier stud continuous beam according to claim 1, which is characterized in that installation is attached
When wall, mounting platform and protective net, installation attached wall first, after wall-attaching equipment installs, then mounting platform and protective net, finally
Mounting bracket.
5. a kind of construction method of high rigid structure 0# block of pier stud continuous beam according to claim 1, which is characterized in that bracket peace
When dress, corresponding two brackets need to be installed, according to the center of gravity Reasonable Arrangement suspension centre of bracket, auxiliary rope is hung on bracket, led to
It crosses loop wheel machine and is lifted into pier top descendant and draw auxiliary rope auxiliary in place, bracket is slowly pulled bracket key after penetrating bracket key box by bracket
Box measures bracket elevation and levelness, and plug ensures that bracket is met the requirements under upper pad.
6. a kind of construction method of high rigid structure 0# block of pier stud continuous beam according to claim 5, which is characterized in that corresponding
Two brackets wear fining twisted steel after the installation is completed to drawing, fining twisted steel band double nut, bracket installation tight with torque wrench
After qualification, lateral is carried out with No. 10 channel steels.
7. a kind of construction method of high rigid structure 0# block of pier stud continuous beam according to claim 1, which is characterized in that the support
For frame using 2 PSB830 grades of 32 fining twisted steels of φ as anchoring rod, single fining twisted steel can bear 600KN pulling force.
8. a kind of construction method of high rigid structure 0# block of pier stud continuous beam according to claim 1, which is characterized in that template,
Bracket removes bracket after the completion of removing, in the pre-buried lifting hole(eyelet) of 0# block bottom plate bracket corresponding position, after 0# block mount holder is removed, by steel
Cord penetrates hoist engine out of lifting hole(eyelet) and lifts wirerope, removes to fining twisted steel is worn, pulls out the slow unloading of bracket extremely with messenger
Cushion cap.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910700619.6A CN110453604A (en) | 2019-07-31 | 2019-07-31 | A kind of construction method of the rigid structure 0# block of high pier stud continuous beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910700619.6A CN110453604A (en) | 2019-07-31 | 2019-07-31 | A kind of construction method of the rigid structure 0# block of high pier stud continuous beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110453604A true CN110453604A (en) | 2019-11-15 |
Family
ID=68484173
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910700619.6A Pending CN110453604A (en) | 2019-07-31 | 2019-07-31 | A kind of construction method of the rigid structure 0# block of high pier stud continuous beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110453604A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004092078A (en) * | 2002-08-29 | 2004-03-25 | Nippon Ps:Kk | Structure and construction method for bridge |
CN102505636A (en) * | 2011-10-28 | 2012-06-20 | 中铁十六局集团有限公司 | Construction method of No.0 block of continuous rigid frame bridge of double-thin-wall pier |
CN202730635U (en) * | 2012-08-08 | 2013-02-13 | 中铁四局集团第二工程有限公司 | Hinged corbel bracket for No. 0 block of high-pier continuous beam |
CN109235275A (en) * | 2018-10-30 | 2019-01-18 | 中铁四局集团有限公司 | Frock suitable for continuous rigid frame overweight 0# piece bracket pre-compaction of high mound large-span |
-
2019
- 2019-07-31 CN CN201910700619.6A patent/CN110453604A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004092078A (en) * | 2002-08-29 | 2004-03-25 | Nippon Ps:Kk | Structure and construction method for bridge |
CN102505636A (en) * | 2011-10-28 | 2012-06-20 | 中铁十六局集团有限公司 | Construction method of No.0 block of continuous rigid frame bridge of double-thin-wall pier |
CN202730635U (en) * | 2012-08-08 | 2013-02-13 | 中铁四局集团第二工程有限公司 | Hinged corbel bracket for No. 0 block of high-pier continuous beam |
CN109235275A (en) * | 2018-10-30 | 2019-01-18 | 中铁四局集团有限公司 | Frock suitable for continuous rigid frame overweight 0# piece bracket pre-compaction of high mound large-span |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106812328B (en) | The whole two step lifting construction methods of string prestressed steel structure rack with hanging layer | |
CN103523683B (en) | Construction method for dismantling tower crane by use of small hoisting equipment | |
CN106012852B (en) | Support integrally falls frame construction method | |
CN207160585U (en) | Superelevation outer wall of basement Bailey bracket single side formwork architecture | |
CN205934747U (en) | A hang basket that is used for cantilever to pour bridge construction operation with pre -compaction structure | |
CN105908761A (en) | Construction technology of hanging basket moving platform for high slope | |
CN109138452A (en) | Heavy construction bolt sphere steel pipe rack entirety fast lifting construction technology | |
CN106400691A (en) | Integrated construction process for anti-collision wall formwork | |
CN204876547U (en) | Big template system of APC shell structure | |
CN102926332A (en) | Derrick arrangement of tools for replacing steel arch bridge suspender and replacing method thereof | |
CN204080650U (en) | A kind of end bay for road and bridge construction closes up suspension bracket | |
CN206110635U (en) | Automatic convertible integrally lift up elevator shaft operating platform of landing leg | |
CN207160615U (en) | A kind of safety protection device for formwork construction of high-rise building | |
CN101109028A (en) | Method of upside-down mounting hydraulic pressure lifting of converter shell | |
CN205442393U (en) | Posture that falls suspension system | |
CN102979297A (en) | Hanging type stairwell operating platform mechanism and construction method thereof | |
CN105951599B (en) | High column mould bases integrated construction technique | |
CN110453604A (en) | A kind of construction method of the rigid structure 0# block of high pier stud continuous beam | |
CN107587711A (en) | A kind of regularization assembled overhanging protection canopy and its assembly method | |
CN109555257A (en) | Combined support derrick type furred ceiling and construction method | |
CN106351125A (en) | Method for integrally overturning steel rope tower | |
CN205663175U (en) | Adjustable reinforcing pull rod formula scaffold frame of encorbelmenting | |
CN203755173U (en) | Formwork device used for hydraulic climbing of bridge high pier | |
CN105888269A (en) | Suspended cable type safety protection device for building construction overhead operation, and construction method of suspended cable type safety protection device | |
CN107299713A (en) | A kind of circular cone roofing integrally-lifting steel truss and its construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191115 |
|
RJ01 | Rejection of invention patent application after publication |