CN110439592A - Shield tunnel two serves as a contrast concrete structure and construction method - Google Patents

Shield tunnel two serves as a contrast concrete structure and construction method Download PDF

Info

Publication number
CN110439592A
CN110439592A CN201910729720.4A CN201910729720A CN110439592A CN 110439592 A CN110439592 A CN 110439592A CN 201910729720 A CN201910729720 A CN 201910729720A CN 110439592 A CN110439592 A CN 110439592A
Authority
CN
China
Prior art keywords
arch
concrete
antiarch
concrete layer
following
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910729720.4A
Other languages
Chinese (zh)
Inventor
丁仕辉
汪永剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hydropower Second Bureau Group Co ltd
Guangdong Construction Engineering Group Co Ltd
Original Assignee
Guangdong No 2 Hydropower Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong No 2 Hydropower Engineering Co Ltd filed Critical Guangdong No 2 Hydropower Engineering Co Ltd
Priority to CN201910729720.4A priority Critical patent/CN110439592A/en
Publication of CN110439592A publication Critical patent/CN110439592A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses shield tunnels two to serve as a contrast concrete structure and construction method, including the following antiarch position concrete layer in arch and arch concrete layer, the following antiarch position concrete layer in arch is in antiarch shape, arch concrete layer is domed, after the following antiarch position concrete layer in arch is fixedly connected with arch concrete layer, form the pour mass that section is circular ring shape, the following antiarch position in arch because concrete warehousing, pave, vibrate it is more convenient, construction quality is controllable, uses relatively inexpensive normal concrete;Arch because of concrete warehousing, pave, difficulty of vibrating, using can Self-leveling, without vibration self-compacting concrete.Meanwhile difficulty is poured to reduce envelope arch pump concrete, vault reserves action gap, is prompted by pre-buried Grouting Pipe pulp, stops pumping self-compacting concrete in time, and envelope arch pump concrete is avoided to cause the excessive damage telescoping steel form of pressure and quick-fried mould in storehouse.

Description

Shield tunnel two serves as a contrast concrete structure and construction method
Technical field
The present invention relates to shield tunnels two to serve as a contrast in Construction Study field, serves as a contrast concrete more particularly to a kind of shield tunnel two Structure further relates to a kind of lining of shield tunnel two concrete structure construction method.
Background technique
Two lining concrete of shield tunnel, are that the operating condition after being built up according to the purposes and tunnel in tunnel designs, It is the primary load bearing structure in tunnel.Therefore, shield tunnel two serves as a contrast quality the having steadily in the long term very greatly to tunnel of concrete quality Influence.
The concrete lining of shield tunnel mainly uses Integral Steel mould trolley, concrete pump delivering concrete to put in storage Implement concrete pouring construction.However, carrying out concrete lining in tunnel, the especially concrete lining of vault is put in storage The influence of feeding difficulty, vault concrete speading is difficult, difficulty of vibrating.So that easily occurring the concrete of lining cutting after concreting Voids and pits, intensity is insufficient, and lining thickness is insufficient, bad in conjunction with construction joint sealing material, and vault lining cutting forms hole behind And other issues.
The existing means for solving above-mentioned quality problems are mostly to increase vault to put in storage spout, use big slump concrete; Vault concreting real-time dynamic monitoring system is added, whether full monitored concrete pours.Above-mentioned measure is in work progress In certain effect is played to the raising of vault concrete lining quality, but in the vault concrete lining of some intensive cloth muscles When, construction quality also fails to achieve the effect that satisfied.
Summary of the invention
The purpose of the present invention is to provide a kind of shield tunnel two and serves as a contrast concrete structure, and structure is simple, and intensity is high, pours It is convenient.
It further relates to a kind of shield tunnel two and serves as a contrast concrete structure construction method, easy to operate, it is low to pour difficulty, construction quality Controllably.
The solution that the present invention solves its technical problem is: a kind of lining of shield tunnel two concrete structure, including arch Following antiarch position concrete layer and with arch concrete layer made of the following antiarch position concrete layer formed by integrally casting in arch, arch The following antiarch position concrete layer in portion be in antiarch shape, arch concrete layer is domed, the following antiarch position concrete layer in arch and After arch concrete layer is fixedly connected, the pour mass that section is circular ring shape, the following antiarch position concrete layer in arch are formed For normal concrete layer, arch concrete layer is self-compacting concrete layer.
As a further improvement of the above technical scheme, the top of the arch concrete layer is equipped with the first plane, described Injecting paste material layer has been poured in first plane, in section, the outer surface of the injecting paste material layer and arch concrete layer it is outer Surface is on the circumference of same diameter circle.
As a further improvement of the above technical scheme, more Grouting Pipes are equipped in the top of the arch concrete layer, The Grouting Pipe and injecting paste material layer are in T-shaped.
As a further improvement of the above technical scheme, the Grouting Pipe be pierced by arch concrete layer top inner surface and First plane.
A kind of lining of shield tunnel two concrete structure construction method, includes the following steps,
1) it lays and completes to reinforcing bar and construction joint sealing material, carry out formwork using telescoping steel form;
2) after the completion of formwork, the template at telescoping steel form vault installs Grouting Pipe;
3) concrete pump and grouting pump are laid;
4) the concreting window opened up by telescoping steel form, pumping normal concrete carry out the following antiarch position in arch It pours, antiarch arch keeps balance feeding to pour with lower portion two sides when construction, and the Grouting Pipe at top rises in this casting process Scavenging action;
5) after the completion following antiarch position normal concrete in arch pours, pumping self-compacting concrete pours arch It builds, arch two sides keep balance feeding to pour when construction, and the Grouting Pipe at top plays scavenging action in this casting process;
6) when the Grouting Pipe of vault installation has slurries outflow, stop self-compacting concrete and pour, pass through Grouting Pipe tube pump Injecting paste material is sent to carry out closely knit slip casting.
As a further improvement of the above technical scheme, in step 2), the mounting means of Grouting Pipe is the one of Grouting Pipe End bounces back 2-5 centimetres behind top to section of jurisdiction inner sidewall, and the other end of Grouting Pipe is fixed in template.
As a further improvement of the above technical scheme, after step 6), design pressure is kept to terminate after twenty minutes closely knit Slip casting recycles Grouting Pipe after concrete final set.
The beneficial effects of the present invention are: the present invention press shield tunnel concrete lining different parts, i.e., arch and arch with Lower antiarch position carries out lining cutting using the concrete for the different shape for meeting design requirement.The following antiarch position in arch is because of coagulation Soil puts in storage, paves, it is more convenient to vibrate, and construction quality is controllable, uses relatively inexpensive normal concrete;Arch enters because of concrete Storehouse paves, difficulty of vibrating, using can Self-leveling, without vibration self-compacting concrete.Meanwhile arch pump concrete is sealed to reduce Difficulty is poured, vault reserves the gap of certain action, prompts by pre-buried Grouting Pipe pulp, and it is mixed to stop pumping self-compaction in time Solidifying soil avoids envelope arch pump concrete from causing the excessive damage telescoping steel form of pressure and quick-fried mould in storehouse.The gap of arch crown is stopping pumping After self-compacting concrete, implements closely knit slip casting using slip casting machine and backfill.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment Attached drawing is briefly described.Obviously, described attached drawing is a part of the embodiments of the present invention, rather than is all implemented Example, those skilled in the art without creative efforts, can also be obtained according to these attached drawings other designs Scheme and attached drawing.
Fig. 1 is the partial vertical sectional schematic diagram of the embodiment of the present invention;
Fig. 2 is that A-A to section cuts open structural schematic diagram in Fig. 1;
Fig. 3 is that B-B direction Grouting Pipe position section cuts open structural representation in Fig. 1.
Specific embodiment
This part will be described in specific embodiments of the present invention, and the preferred embodiments of the invention is shown in the accompanying drawings, attached The effect of figure be with figure remark additionally book word segment description, enable a person to intuitively, visually understand of the invention Each technical characteristic and overall technical architecture, but it should not be understood as limiting the scope of the invention.
In the description of the present invention, it is to be understood that, be related to orientation description, for example, above and below, front, rear, left and right etc. The orientation or positional relationship of instruction is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of the description present invention and letter Change description, rather than the device or element of indication or suggestion meaning must have a particular orientation, with specific orientation construct and Operation, therefore be not considered as limiting the invention.
In the description of the present invention, several to be meant that one or more, it is multiple to be meant that two or more, be greater than, Be less than, more than etc. be interpreted as not including this number, it is above, following, within etc. be interpreted as including this number.If there is being described to first, Second is only intended to for the purpose of distinguishing technical characteristic, is not understood to indicate or imply relative importance or implicitly indicates institute The quantity of the technical characteristic of instruction or the precedence relationship for implicitly indicating indicated technical characteristic.
In description of the invention, unless otherwise restricted clearly, the words such as setting, installation, connection be shall be understood in a broad sense, institute Above-mentioned word in the present invention specific can rationally be determined with the particular content of combination technology scheme by belonging to technical field technical staff Meaning.
Referring to Fig.1~Fig. 3, a kind of lining of shield tunnel two concrete structure, including the following antiarch position concrete layer in arch 10 and with arch concrete layer 11 made of following 10 formed by integrally casting of antiarch position concrete layer in arch, the following antiarch position in arch Concrete layer 10 is in antiarch shape, and arch concrete layer 11 is domed, the following antiarch position concrete layer 10 in arch and arch coagulation After soil layer 11 is fixedly connected, the pour mass that section is circular ring shape is formed, the following antiarch position concrete layer 10 in arch is normal State concrete layer, arch concrete layer 11 are self-compacting concrete layer.The following antiarch position concrete layer 10 in arch and arch are mixed Solidifying soil layer 11 is connected and fixed integrally by coagulation soil characteristics.
By the different parts of shield tunnel concrete lining, the i.e. following antiarch position in arch and arch, wanted using design is met The concrete for the different shape asked carries out lining cutting.Below arch because of concrete warehousing, pave, more convenient, construction quality of vibrating Controllably, using relatively inexpensive normal concrete;Arch because of concrete warehousing, pave, difficulty of vibrating, using can Self-leveling, exempt from The self-compacting concrete to vibrate.Meanwhile difficulty is poured to reduce envelope arch pump concrete, vault reserves action gap, by pre- The Grouting Pipe pulp prompt buried, stops pumping self-compacting concrete in time, and envelope arch pump concrete is avoided to cause pressure mistake in storehouse Big damage telescoping steel form and quick-fried mould.The gap of arch crown, after stopping pumping self-compacting concrete, the closely knit slip casting of slip casting machine backfills
Preferably, the top of the arch concrete layer 11 is equipped with the first plane, has poured slip casting in first plane Material layer 12, in section, the outer surface of the injecting paste material layer 12 and the outer surface of arch concrete layer 11 are in the same as always On the circumference of diameter circle.
Preferably, self-compacting concrete is without vibrating, can Self-leveling, self-compaction.Normal concrete can be by paving, shaking Puddling is real.
Preferably, more Grouting Pipes, the Grouting Pipe and injecting paste material are equipped in the top of the arch concrete layer 11 Layer 12 is in T-shaped.
Preferably, the Grouting Pipe is pierced by the top inner surface and the first plane of arch concrete layer 11.
A kind of lining of shield tunnel two concrete structure construction method, includes the following steps,
1) it lays and completes to reinforcing bar and construction joint sealing material, carry out formwork using telescoping steel form;
2) after the completion of formwork, the template 13 at telescoping steel form vault installs Grouting Pipe 15, and the lower end of Grouting Pipe 15 is exposed The lower end surface of template 13 at vault;
3) concrete pump and grouting pump are laid;
4) the concreting window 14 opened up by telescoping steel form, pumping normal concrete to the following antiarch position in arch into Row pours, and arch following antiarch position two sides keep balance feeding to pour when construction, forms the following antiarch position concrete in arch Layer 10, the Grouting Pipe at top plays scavenging action in this casting process;
5) after the completion following antiarch position normal concrete in arch pours, pumping self-compacting concrete pours arch It builds, arch two sides keep balance feeding to pour when construction, form arch concrete layer 11, the Grouting Pipe at top is in this casting process In play scavenging action;
6) when the Grouting Pipe 15 of vault installation there are slurries to flow out from the lower end of Grouting Pipe 15, stop self-compacting concrete and pour It builds, reserves action gap in vault, slip casting machine pumps injecting paste material by Grouting Pipe 15 from the bottom up and carries out closely knit slip casting, formed Injecting paste material layer 12.
Preferably, in step 2), the mounting means of Grouting Pipe 15 is that 15 inner end of Grouting Pipe is returned after pushing up to section of jurisdiction inner sidewall It 2-5 centimetres of contracting, fixes over the pattern 13.When concreting, the Grouting Pipe 15 to vault installation has slurries from Grouting Pipe 15 When lower end is flowed out, the action gap that reserved 2-5 centimetres of vault, slip casting machine by Grouting Pipe 15 pump from the bottom up injecting paste material into The closely knit slip casting of row, forms injecting paste material layer 12.
Preferably, it after step 6), keeps design pressure to terminate closely knit slip casting after twenty minutes, is recycled after concrete final set Grouting Pipe 15, the through-hole after the recycling exhaust pipe 15 that arch concrete layer 11 leaves can be used as subsequent touch seam slip casting and use.
The present invention presses the different parts of shield tunnel concrete lining, the i.e. following antiarch position in arch and arch, uses satisfaction The concrete of the different shape of design requirement carries out lining cutting.The following antiarch position in arch because of concrete warehousing, pave, vibrate more Convenient, construction quality is controllable, uses relatively inexpensive normal concrete;Arch because of concrete warehousing, pave, difficulty of vibrating, make With can Self-leveling, without vibration self-compacting concrete.Meanwhile difficulty is poured to reduce envelope arch pump concrete, vault reserves string High-voidage is prompted by pre-buried 15 pulp of Grouting Pipe, stops pumping self-compacting concrete in time, avoids envelope arch pump concrete Cause the excessive damage telescoping steel form of pressure and quick-fried mould in storehouse.The gap of arch crown, after stopping pumping self-compacting concrete, slip casting secret Real slip casting backfill.
It is to be illustrated to better embodiment of the invention, but the invention is not limited to the reality above Example is applied, those skilled in the art can also make various equivalent modifications on the premise of without prejudice to spirit of the invention or replace It changes, these equivalent variation or replacement are all included in the scope defined by the claims of the present application.

Claims (7)

1. a kind of shield tunnel two serves as a contrast concrete structure, it is characterised in that: including the following antiarch position concrete layer in arch and with Arch concrete layer made of the following antiarch position concrete layer formed by integrally casting in arch, the following antiarch position concrete layer in arch are in Antiarch shape, arch concrete layer is domed, after the following antiarch position concrete layer in arch is fixedly connected with arch concrete layer, shape It is the pour mass of circular ring shape at section, the following antiarch position concrete layer in arch is normal concrete layer, arch concrete Layer is self-compacting concrete layer.
2. shield tunnel two according to claim 1 serves as a contrast concrete structure, it is characterised in that: the arch concrete layer Top is equipped with the first plane, has poured injecting paste material layer in first plane, in section, the appearance of the injecting paste material layer The outer surface of face and arch concrete layer is on the circumference of same diameter circle.
3. shield tunnel two according to claim 2 serves as a contrast concrete structure, it is characterised in that: the arch concrete layer More Grouting Pipes are equipped in top, the Grouting Pipe and injecting paste material layer are in T-shaped.
4. shield tunnel two according to claim 3 serves as a contrast concrete structure, it is characterised in that: the Grouting Pipe is pierced by arch The top inner surface of concrete layer and the first plane.
5. a kind of shield tunnel two serves as a contrast concrete structure construction method, it is characterised in that: include the following steps,
1) it lays and completes to reinforcing bar and construction joint sealing material, carry out formwork using telescoping steel form;
2) after the completion of formwork, the template at telescoping steel form vault installs Grouting Pipe;
3) concrete pump and grouting pump are laid;
4) the concreting window opened up by telescoping steel form, pumping normal concrete carry out coagulation to the following antiarch position in arch Soil pours, and arch following antiarch position two sides keep balance feeding to pour when construction, and the Grouting Pipe at top is in this casting process Play scavenging action;
5) after the completion following antiarch position normal concrete in arch pours, pumping self-compacting concrete pours arch, applies Working hour arch two sides keep balance feeding to pour, and the Grouting Pipe at top plays scavenging action in this casting process;
6) when the Grouting Pipe of vault installation has slurries outflow, stop self-compacting concrete and pour, slip casting is injected by Grouting Pipe Material carries out closely knit slip casting.
6. shield tunnel two according to claim 5 serves as a contrast concrete structure construction method, it is characterised in that: in step 2) In, the mounting means of Grouting Pipe is that one end of Grouting Pipe bounces back 2-5 centimetres after pushing up to section of jurisdiction inner sidewall, the other end of Grouting Pipe It is fixed in template.
7. shield tunnel two according to claim 5 serves as a contrast concrete structure construction method, it is characterised in that: in step 6) Afterwards, it keeps design pressure to terminate closely knit slip casting after twenty minutes, recycles Grouting Pipe after concrete final set.
CN201910729720.4A 2019-08-08 2019-08-08 Shield tunnel two serves as a contrast concrete structure and construction method Pending CN110439592A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910729720.4A CN110439592A (en) 2019-08-08 2019-08-08 Shield tunnel two serves as a contrast concrete structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910729720.4A CN110439592A (en) 2019-08-08 2019-08-08 Shield tunnel two serves as a contrast concrete structure and construction method

Publications (1)

Publication Number Publication Date
CN110439592A true CN110439592A (en) 2019-11-12

Family

ID=68433989

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910729720.4A Pending CN110439592A (en) 2019-08-08 2019-08-08 Shield tunnel two serves as a contrast concrete structure and construction method

Country Status (1)

Country Link
CN (1) CN110439592A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939463A (en) * 2019-11-21 2020-03-31 中铁隧道局集团有限公司 Movable full-section integral steel mould lining trolley and application thereof in pumping and pouring of secondary lining concrete
CN113833480A (en) * 2021-09-29 2021-12-24 成都建工第九建筑工程有限公司 Shield initial tunneling and arrival construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104295305A (en) * 2014-02-12 2015-01-21 齐洪军 Process for achieving synchronous implementation of lining vault filling grouting and tunnel lining and equipment
CN107762532A (en) * 2016-08-23 2018-03-06 中铁十局集团第工程有限公司 Tunnel vault band mould grouting construction method
CN210686009U (en) * 2019-08-08 2020-06-05 广东水电二局股份有限公司 Shield tunnel two-lining concrete structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104295305A (en) * 2014-02-12 2015-01-21 齐洪军 Process for achieving synchronous implementation of lining vault filling grouting and tunnel lining and equipment
CN107762532A (en) * 2016-08-23 2018-03-06 中铁十局集团第工程有限公司 Tunnel vault band mould grouting construction method
CN210686009U (en) * 2019-08-08 2020-06-05 广东水电二局股份有限公司 Shield tunnel two-lining concrete structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王利民等: "洞桩法暗挖地铁车站关键节点防水施工技术", 《铁道建筑》, 31 May 2012 (2012-05-31), pages 70 - 73 *
耿新胜: "隧洞二衬混凝土施工工艺", 《黑龙江水利科技》, 30 April 2013 (2013-04-30), pages 17 - 19 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939463A (en) * 2019-11-21 2020-03-31 中铁隧道局集团有限公司 Movable full-section integral steel mould lining trolley and application thereof in pumping and pouring of secondary lining concrete
CN113833480A (en) * 2021-09-29 2021-12-24 成都建工第九建筑工程有限公司 Shield initial tunneling and arrival construction method
CN113833480B (en) * 2021-09-29 2024-05-24 成都建工第九建筑工程有限公司 Construction method for initial tunneling and arrival of shield

Similar Documents

Publication Publication Date Title
CN207739264U (en) A kind of Grouting Pipe
CN207177303U (en) Rail type vibrating rod
CN110439592A (en) Shield tunnel two serves as a contrast concrete structure and construction method
CN108385986A (en) A kind of device and method ensureing constructional column reinforcement location
CN104652371B (en) The glue of crossing set up based on old dam coagulates rock-fill dams and construction method thereof
CN107012861B (en) A kind of discrete material core expansive concrete stake and its construction method
CN107489432A (en) Tunnel support grouting equipment and its grouting method
CN208472708U (en) A kind of grouting behind shaft or drift lining filling pile structure
CN206495331U (en) A kind of easy reassembling type built-in fitting of builder's jack
CN105937221A (en) Manufacturing method for drilled grouting piles
CN209429263U (en) A kind of prefabricated column connected node fixing templates
CN109989395A (en) A kind of large-scale storage tank bored concrete pile assembled pile cover and its construction method
CN109750832A (en) A kind of construction method of constructional column concrete self-compaction
CN206971247U (en) Concrete toe board foundation reinforcing structure arranged on unloading rock mass
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN205714221U (en) A kind of Tunnel Second Lining vault is owed to dig place's teeming building structure
CN205475206U (en) Drainage formula cast in situ concrete thin wall tubular pile
CN205577430U (en) Concrete placement structure is managed to big scale of construction composite steel concrete column body swift current ball formula pipe cluster in ground
CN207813015U (en) Floor slab preformed hole tool-typed formwork support construction
CN205976503U (en) Vertical concrete structure's template lacing device
CN108193706A (en) A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure
CN212003113U (en) Broken rock mass slip casting is with only thick liquid device
CN211008658U (en) Construction structure for preventing two lining vault from being hollow at railway tunnel vault
CN210686009U (en) Shield tunnel two-lining concrete structure
CN106761823A (en) Exempt from wall for grouting segmentation cleaning bottom of hole retrusive controlling grouting method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Country or region after: China

Address after: 511340 20 / F, A-1 business center, Shuidian Plaza, building 1, Guangshen Avenue West, Xintang Town, Zengcheng District, Guangzhou City, Guangdong Province

Applicant after: Guangdong Construction Engineering Group Co.,Ltd.

Address before: 511340 20 / F, A-1 business center, Shuidian Plaza, building 1, Guangshen Avenue West, Xintang Town, Zengcheng District, Guangzhou City, Guangdong Province

Applicant before: GUANGDONG NO. 2 HYDROPOWER ENGINEERING Co.,Ltd.

Country or region before: China

CB02 Change of applicant information
TA01 Transfer of patent application right

Effective date of registration: 20240620

Address after: Room 1201-1208, Building 1, No. 1 Guangshen Avenue West, Xintang Town, Zengcheng District, Guangzhou City, Guangdong Province, 511340

Applicant after: Guangdong Hydropower Second Bureau Group Co.,Ltd.

Country or region after: China

Applicant after: Guangdong Construction Engineering Group Co.,Ltd.

Address before: 511340 20 / F, A-1 business center, Shuidian Plaza, building 1, Guangshen Avenue West, Xintang Town, Zengcheng District, Guangzhou City, Guangdong Province

Applicant before: Guangdong Construction Engineering Group Co.,Ltd.

Country or region before: China

TA01 Transfer of patent application right